Public Meeting November 9, 2016 SRQ Media Room
Transcript of Public Meeting November 9, 2016 SRQ Media Room
Public Meeting November 9, 2016 SRQ Media Room
Agenda
• Call Meeting to Order • Approval of Minutes • Program Schedule Review • Phase 1 MOT Plan Update • LS 87 Landscape Plan • Phase 1 Schedule Review • Outstanding Business • New Business • Public Input • Adjournment
Program Overview
PHASE 3 LS 87 Gravity
Mains
PHASE 1 LS 87 Microtunneling
PHASE 2 LS 87 Structure
PHASE 3 LS 7 Demo and
Restoration
ALTA VISTA STREET
US 41
POMELO AVE O
SPR
EY
AVE
POM
ELO
PL
ACE
Construction Sequencing – 3 Phases
Program Overview
Phase Start Finish
2015 2016 2017 2018 2019 2020
Q 1/2
Q 3/4
Q 1/2
Q 3/4
Q 1/2
Q 3/4
Q 1/2
Q 3/4
Q 1/2
Q 3/4
Q 1/2
Q 3/4
Con
stru
ctio
n
Phase 1 May 2016
July 2017
Phase 2 May 2017
Oct. 2019
Phase 3 Aug. 2019
Dec. 2020
Projected Construction Timelines
Phase 1 – Lift Station 87 Microtunneling Maintenance of Traffic Plan Update
To maintain safe traffic flow during construction by:
• Directing traffic to Mound Street/US 41 to avoid neighborhoods
• Addressing pedestrian detours and sidewalk closures
• Identifying access to businesses on Osprey Avenue
Lift Station 87 Landscape Plan
Public Participation Overview
• Series of Public Meetings Hover Arcade
Brick Façade
• Public Meeting – July 26, 2016
Red Brick Option
Sarasota High School
Landscape Architectural Renderings
• Site Plan Application
December 2014
Input from Urban Design Studio
• Landscape Architect – David W. Johnston Associates, Inc.
Phillip J. Smith, ASLA
Phase 1 Schedule Review
• Jacking Shaft MH17 (Between Lincoln and Bridge)
October/November 2016
• Receiving Shaft MH21 (Osprey/US 41 Intersection) December 2016/January 2017
• Jacking Shaft MH24 (Luke Wood Park) December 2016/January 2017
Phase 1 Schedule Review
• MT Drive 1 (Osprey Avenue)
December/January 2017
• MT Drive 2 (Luke Wood Park) February 2017
• Demobilization July 2017
• Outstanding Business
• New Business
Public Input