PTT_ Hydro Static Pressure Testing of Piping

download PTT_ Hydro Static Pressure Testing of Piping

of 23

Transcript of PTT_ Hydro Static Pressure Testing of Piping

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    1/23

    PREPAREDBY

    NAPTT PUBLIC COMPANY LIMITED

    CHECKED

    BY ONSHORE COMPRESSOR STATION 4

    PROJECT

    APPROVED

    BY

    CERTIFIED

    (PTT)NA

    REV.

    NO.

    DATE REVISED

    BY

    APPROVED

    BY

    DESCRIPTION

    D1 18-Feb-08 ISSUED FOR ITB

    D2 11-Jun-08 ISSUED FOR ITB

    SPECIFICATION FOR

    HYDROSTATIC PRESSURE TESTING OF PIPING

    SPC-0804.02-96.58 REV.D2

    TOTAL 23 PAGES

    AREA CODE OF SITE LOCATION

    GENERAL AREA: 010

    .

    PTT PLC. CONTRACT NO. PTT PLC. PROJECT NO.

    0804.02

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    2/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 2 OF 23

    REV: D2

    CONTENTS

    SECTION

    1. GENERAL ............................................................................................... 3

    2. PRESSURE TEST SYSTEM........................................................................ 4

    3. TEST WATER CRITERIA........................................................................... 6

    4. TESTING ................................................................................................ 7

    5. BLINDS FOR PRESSURE TEST .................................................................. 8

    6. TEST PACK PREPARATION ...................................................................... 8

    7. FIELD PIPE TESTING PROCEDURES..........................................................10

    8. TESTING PREPARATIONS .......................................................................12

    9. HYDROSTATIC TEST PROCEDURE...........................................................14

    10. SAFETY ................................................................................................15

    11. SENSITIVE LEAK TEST ...........................................................................16

    12. ALTERNATIVE TESTS .............................................................................16

    13. VESSELS AND EQUIPMENT.....................................................................17

    14. INSTRUMENTS ......................................................................................17

    15. CLEANING .............................................................................................18

    16. REPORTS AND RECORDS .......................................................................18

    17. TEST RECORDS .....................................................................................18

    APPENDIX I MINIMUM THICKNESS OF BLANK FOR PRESSURE TEST.............20

    APPENDIX II. DETAILS OF TEST FACILITIES ....................................................22

    APPENDIX III. TEST LIMITS SYMBOL..............................................................23

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    3/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 3 OF 23

    REV: D2

    1.0 GENERAL

    1.1 Purpose

    This Specification specifies pressure and leak test procedure and acceptance

    criteria of piping works to perform minimum quality level.

    1.2 Scope of Application

    This specification covers all the projects which to be done by CONTRACTOR

    (here in after refer to CONTRACTOR) in piping construction works.

    1.3 Definitions

    1.3.1 Category D Fluid Service (per ASME B31.3) - A fluid service in which all the

    following apply:

    (1) The fluid handled is nonflammable, nontoxic, and not damaging to

    human tissues

    (2) The design gauge pressure does not exceed 10.35 bar

    (3) The design temperature is between -29 C and 186 C.

    1.3.2 Category M Fluid Service (per ASME B31.3) - A toxic fluid service in whichexposure to very small quantities of the fluid in the environment can produce

    serious irreversible harm to persons on breathing or bodily contact, even when

    prompt restorative measures are taken.

    1.3.3 Damaging to Human Tissues (per ASME B31.3) - A fluid which, under

    expected operating conditions, can harm skin, eyes, or exposed mucous

    membranes so that irreversible damage may be done unless prompt restorative

    measures are taken. (Restorative measures may include flushing with water,

    administration of antidotes, medication, etc.)

    1.3.4 Calculated Test Pressure:- The test pressure determined in accordance with

    paragraph 4.0

    1.3.5 Minimum Test Pressure - The lowest allowable test pressure gauge reading.

    (the calculated test pressure plus the additional pressure resulting from the

    static head of the test fluid)

    1.3.6 Maximum Test Pressure - The highest allowable test pressure gauge reading.

    (the pressure test rating of the "weakest" component in the test system)

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    4/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 4 OF 23

    REV: D2

    1.4 References

    1.4.1 Related Code and Standards

    Piping construction works shall be performed in accordance with ASME B31.3

    and ASME section IX.

    (1) ASME B31.3 Process Piping

    (2) ASME SECTION.IX "Welding and Brazing Qualifications"

    1.4.2 Related Specifications

    Following specification shall be used as a supplementary of this specification.

    (1) Piping Construction (SPC-0804.02-96.51)

    (2) Internal Cleaning of Piping (SES-PR. Q2- 99-0204.10-3500-013)

    1.5 Units

    Unless otherwise specified, metric, Celsius and Kilogram units sell be applied

    as the measurement system for the drawings and document to be submitted.

    However, nominal sizes of piping component shall be in accordance with inch

    system, which abbreviation in (B)

    2.0 PRESSURE TEST SYSTEM

    2.1 As large a piping system as practicable including its associated equipment

    shall be hydro tested together as a unit, unless the difference among their

    design pressures exceeds 15 percents of the lowest design pressure of the

    system components.

    The test pressure in the system shall be equal to the test pressure applied to

    the system component of which the design pressure is the lowest among the

    system as mentioned in the following paragraph.

    Where piping systems of different design pressures are fully welded together,

    then "cascade" pressure testing will be required, (i.e. complete the pressure

    test on the higher pressure system prior to system closure welding and then

    repeat full Pressure Test Procedure for the test of the combined systems at

    the lowest pressure).

    2.2 Heat exchangers, pressure vessels and fired heaters may be included in a testsystem, providing the system test pressure does not exceed the shop test

    pressure of any of the included items.

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    5/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 5 OF 23

    REV: D2

    2.3 The following equipment and components shall not be included in the system.

    The equipment shall be isolated from the system.

    2.3.1 Rotary equipment such as pumps, compressors and turbines.

    2.3.2 Safety valves rupture discs, flame arrest's, and steam traps.

    2.3.3 Pressure vessels with sophisticated internals.

    2.3.4 Equipment and piping lined with refractoriness.

    2.3.5 Storage tanks.

    2.3.6 Filters, if filter element(s) is not dismantled.

    2.3.7 Heat exchangers of which tube sheets and internals have been designed for

    differential pressure between tube side and shell side.

    2.3.8 Instruments such as control valves, pressure gages, level gages, and

    flowmeter. (excluding thermocouples)

    2.4 Exclusions

    The followings are excluded from the requirements of this specification:

    2.4.1 Any package unit previously tested by the manufacturer in accordance with

    the applicable codes.

    2.4.2 Plumbing systems, which are tested in accordance with the applicable

    plumbing codes.

    2.4.3 Lines and systems which are open to the atmosphere such as drain, vents,

    open discharge of relief valve, and atmospheric sewers.

    2.4.4 Instrument impulse lines between the block valve at the process or utility line

    and the connected instrument.

    2.5 Although instruments shall normally be excluded from the system, process

    lead lines shall be tested to the first block valve together with the piping

    system.

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    6/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 6 OF 23

    REV: D2

    Any vents or bypasses downstream of the instrument's first block valves shall

    be opened or the instrument shall be disconnected during the test to insurefull protection of that instrument.

    2.6 The test shall be hydrostatic using water, except if there is a possibility of

    damage due to freezing, or if the operating fluid or piping material would be

    adversely affected by water.

    Any other suitable liquid shall be used with CONTRACTOR'S approval.

    2.6.1 Testing on site with Kerosene or other inflammable fluids or compressed airshall be avoided as far as possible (except where specifically called for) and

    shall be carried out only with the approval of CONTRACTOR.

    2.6.2 If a flammable liquid is used, its flash point shall be not less than 50C and

    consideration shall be given to the test environment.

    2.7 Pneumatic testing shall be considered for the following;

    2.7.1 Gas, steam, or vapor lines when the weight of the hydro test liquid would

    overstress supporting structures or pipe wall.

    2.7.2 Piping with linings subject to damage by the hydro test liquid.

    2.7.3 The instrument air headers shall be tested with dry-oil free air. The commodity

    test may be used if the systems are completed and the instrument air

    compressor is operational.

    3.0 TEST WATER CRITERIA

    3.1 Care shall be taken to insure the use of clean water for hydrostatic tests. Andthe sea water is prohibited to be used.

    A suitable filter should be provided in the filling line to the systems in order to

    remove foreign matter such as sand, rust or other particles in the proposed

    test water.

    3.2 Hydrostatic testing shall be performed using clam potable water with a

    chloride content of max 50 PPM for austenitic steels. In case this requirement

    can't be fulfilled the pipeline shall be reamed completely and flushed with

    water fulfilling the above requirement of 50 PPM max of chlorides.

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    7/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 7 OF 23

    REV: D2

    4.0 TESTING

    4.1 Hydrostatic testing of piping designed for internal pressure

    The minimum hydrostatic test pressure at any point in the system shall be as

    follows.

    (1) Not less than 1-1/2 times of the design pressure.

    (2) For a design temperature above the test temperature, the

    minimum test pressure shall be as calculated by the following

    equation.

    Where:

    Pt = minimum calculated hydrostatic test pressure (kg/cm2)

    P = internal design pressure (kg/cm2)

    St = allowable stress at test temperature (kg/ cm2)

    S = allowable stress at design temperature (kg/ cm2)

    See Table I, Appendix A, IASME 831.3 1

    When St and S are equal, test pressure is 1.5 x P.

    Where the test pressure as defined above would produce a stress in excess of

    the specified minimum yield strength at test temperature, the test pressure

    shall be reduced to a pressure at which the stress will not exceed the

    specified minimum yield strength at the test temperature.

    The maximum test pressure at which the stress produced will not exceed the

    specified minimum yield strength may be calculated by the following equation:

    Where:

    Pm = maximum test pressure (kg/ cm2)

    S = specified minimum yield strength at test temperature (kg/

    cm2)

    t = specified pipe wall thickness minus mill tolerance (cm)

    D = outside diameter (cm)

    E = quality factor (see ASME B31.3 table A-1 B)

    4.2 Hydrostatic testing of Piping Designed for External Pressure. (Jacked limes)

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    8/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 8 OF 23

    REV: D2

    4.2.1 Lines in external pressure service shall be subjected to an internal test

    pressure of 1-1/2 times the external differential design pressure but not lessthan a gauge pressure of 1.055kg/m2 (15 psi).

    4.2.2 Jacketed lines, the internal line shall be pressure tested on the basis of the

    internal or external design pressure, whichever is critical.

    This test shall be preformed prior to completion of the jacket.

    4.2.3 The jacket shall be pressure tested of the basis to the jacket design

    conditions.

    4.2.4 Where systems require hydrostatic testing through static equipment, the test

    pressure shall be selected so as not to exceed vessel test pressure.

    5.0 BLINDS FOR PRESSURE TEST

    5.1 Plain test blanks shall be used with 1/16 inch flat asbestos gaskets for

    blanking flat face, and raised face.

    Provide full face blanks and gaskets for CL 125 connections.

    However, where permanent operational blinds are installed, they may be used

    for pressure testing.

    5.2 Plate material, extra length bolts and gaskets, which are made at the Job Sitecould be used for testing. Maximum allowable hydrostatic testing pressure for

    test blinds refer to appendix I.

    5.3 Temporary spades and blanks installed for testing purposes shall be designed

    to withstand the test pressure without distortion. Temporary test spades and

    blanks shall be readily identifiable by painting a red color on the handle.

    5.4 For ring joint flanges, spare ring joints shall be required as they are to be used

    only once.

    6.0 TEST PACK PREPARATION

    6.1 General

    6.1.1 CONTRACTOR will prepare a marked up of P & ID indicating the test limits.

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    9/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 9 OF 23

    REV: D2

    6.1.2 From the marked up PID, Subcontractor will divide the piping into suitable

    Test Packs. The size of the packs may be revised by Subcontractor providedthat the specification for limits in Clause 6.2 below is complied with.

    CONTRACTOR shall be notified of such revisions and will authorize

    Subcontractor to proceed if said revisions meet the specification.

    6.2 Test Pack Limits

    6.2.1 Subcontractor shall not test through equipment without CONTRACTORs

    written approval.

    6.3 Test Pack Format

    (1) Pressure test report for Piping

    (2) Marked-up PID

    (3) Blind check list

    (4) Welding History Report and Welding Joint Marked ISO Drawing

    (5) NDE Report.

    (6) PWHT and Hardness test Report

    (7) Post Test Punch List (CONTRACTOR + Client)

    (8) Copies of reinforcing pad pressure test certificates.(If necessary)

    6.3.1 Test packs will include the latest available revision of each isometric covering

    the scope of the test.

    (1) Test limits, and highlight line to be tested.

    (2) Size (thickness') and location of all test blinds and including those

    required at instrument connections e.g. orifice flanges.

    (3) Identify location for the connection of the fill and drainage points for

    the system.

    (4) Vent points

    (5) Drain points

    (6) Location and range of pressure gauges to be used. Minimum (2)

    Calibrate gauges enquired, one located at an accessible low point of

    the test and one gauge located at the highest points on the test

    manifold.

    (7) Any otherspecial requirements such as chloride content if applicable.

    (8) If required, temporary supports shall also be indicated in the test pack

    (9) Any control valve, check valve, safety valves or other piping

    accessories requiring removal,turning, or some other action should be

    highlighted.6.3.2 Test packs shall also contain copies of PID's marked-up to show at least the

    following information:

    (1) Piping Field Test Pack Number

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    10/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 10 OF 23

    REV: D2

    (2) Specific Limits of that Test Pack Only.

    (3) Testing Medium i.e. water, dematerialized / condensate water,or visual.

    (4) Hydrostatic Test Pressure.

    (5) Location of Test Blinds, Isolation valve, and Temporary piping

    6.4 Test Pack Approvals and Distribution

    6.4.1 After compilation of the test pack, the "Original" shall be submitted for

    approval by Subcontractor under cover of a transmittal memorandum to

    attention of CONTRACTOR's Engineer.

    6.4.2 CONTRACTOR's Engineer will review packs and sign them as "Approved", if

    acceptable.

    6.4.3 The "Original" pack will be returned to Subcontractor who will then distribute

    one (1) copy to CONTRACTOR's Engineer and (1) copy to CONTRACTOR Q/C.

    6.5 Field Change Sheet (FS for piping)

    6.5.1 CONTRACTOR's Engineer shall check the status of the affected test pack and

    advise subcontractor as follows:

    (1) For test packs not yet hydro tested

    Subcontractor shall amend the original of the test pack referencing the

    FS and Re-distribute including the FS.

    (2) For test packs where hydrostatic test completed

    CONTRACTOR will over-stamp the original test pack with "RETEST"

    The re-stamp original will then be returned to subcontractor under

    memorandum with an instruction to carry out the retesting.

    Redistribution will then proceed per 6.4.3 (above).

    7.0 FIELD PIPE TESTING PROCEDURES

    7.1 Piping Installation Completion

    7.1.1 Upon completion of the piping system component installation and seven (7)

    days prior to testing, Subcontractor shall submit original test pack toCONTRACTOR that Piping Test Pack Number is ready for mechanical

    clearance..

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    11/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 11 OF 23

    REV: D2

    7.1.2 Prior to submitting said memorandum Subcontractor shall have inspected the

    Piping Test Pack for its completeness of installation and have organized /reviewed all required documentation for Welding History, Post Weld Heat

    Treatment and Non-Destructive Testing.

    7.1.3 CONTRACTOR will inspect the Piping System with prepare punch list.

    7.1.4 Only after CONTRACTOR have verified and endorsed welding QC clearance

    on the test pack and cleared all "A" Punch List items from the CONTRACTOR

    punch list, will PTT/Consultant be notified by formal transmittal of the

    CONTRACTOR endorsed Test Pack. On receipt of the Test Pack,

    PTT/Consultant will review and inspect the QC documentation and punch

    piping pressure test system".

    7.1.5 PTT/Consultant will review and verify welding QC clearance and punch the

    piping system tested. Only after PTT/Consultant have endorsed the welding

    QC as acceptable and punch list items have been cleared, will the Test Pack

    be formally returned to CONTRACTOR endorsed "Released for Testing"

    7.1.6 If PTT/Consultant identify deficiencies in the Test Pack documentation,

    welding QC documentation and or outstanding class A punch list items, theTest Pack will be formally returned to CONTRACTOR complete with attached

    punch lists to be corrected and signed prior to resubmittal.

    7.2 QC Clearance

    During the time the Punch List is being prepared, the CONTRACTOR's QC

    Section and Subcontractor QC Section shall proceed as follows:

    7.2.1 Alloy Verification (For stainless steel material)(1) Where applicable, Subcontractor QC Inspector shall confirm that all alloy

    verification data is complete.

    (2) After checking alloy verification documentation, the Subcontractor QC

    Inspector shall notify CONTRACTOR's QC Engineer that the

    documentation is complete for checking/ verification by CONTRACTOR,

    which may be reviewed by Owner.

    7.2.2 Post Weld Heat Treatment (PWHT) and Hardness Testing

    When applicable, submission of data for PWHT and Hardness Testing shall

    Review with test data.

    7.2.3 Non Destructive Testing (NDT)

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    12/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 12 OF 23

    REV: D2

    (1) After checking NDT records the Subcontractor's Inspection Group shall

    notify CONTRACTOR's QC Engineer that documentation is "Complete"for checking/verification by CONTRACTOR, which may be reviewed by

    Owner.

    (2) In addition, a visual check shall be carried out in the field by

    Subcontractor and CONTRACTOR/Owner Inspection to ensure all

    welding has been correctly performed and that no remedial work is

    required. If there is remedial work required it should be recorded on the

    Punch List.

    7.2.4 CONTRACTOR's QC Clearance

    If CONTRACTOR's QC Engineer and/or Owner's Area Welding Inspectors find

    outstanding items during this review/inspection he shall add these welding

    items to a separate

    "Welding Punch List" maintained with the welding / tractability isometrics for

    the Piping Field Test Report. When all items are completed to the satisfaction

    of CONTRACTOR and Owner's Welding Inspectors he will then sign the

    "Original" Piping Field Test Report as ready to test.

    8.0 TESTING PREPARATIONS

    8.1 All joints, including welds, shall be accessible and left uninstalled, unpainted

    and exposed for examination during the test. Joints previously tested in

    accordance with this specification may be insulated or covered.

    8.2 Piping designed for vapor or gas shall be provided with additional temporary

    supports, if necessary, to support the weight of the test liquid. Where

    required, temporary supports shall be specified in the pressure test

    documents.

    8.3 Lines which are counterweight supported shall be temporarily blocked during

    testing in order to sustain the weight of the test fluid. Spring hangers which

    have been provided with stops for carrying the test load normally do not

    require additional temporary supports:

    If this is not the case, temporary support must be provided before filling the

    system.

    8.4 Before Testing

    8.4.1 Piping systems shall have been completely checked for correctness.

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    13/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 13 OF 23

    REV: D2

    8.4.2 All lines, vessels and equipment shall be checked to insure the entire system

    can be completely drained after testing.

    8.4.3 Vents or other high point connections shall be opened to eliminate air from

    lines which are to receive a hydrostatic test.

    8.4.4 Temporary gaskets may be used, which are not the same as permanent

    gaskets, provided.

    (1) Such use will not lead to damage of the flange faces.

    (2) Temporary gaskets are removed immediately after completion of tests.

    8.5 Vessels that are to be tested through shall be-reviewed in order to determine

    the best method to prevent air entrapment when filling and to prevent a

    vacuum when draining.

    8.6 Short pieces of piping which must be removed to permit installation of a blind

    or blank shall be tested separately.

    8.7 Lines containing check valves shall have the source of pressure located in the

    piping upstream of the-check valve so that the pressure is applied under the

    seat.

    If this is not possible, remove or jack open the check valve closure mechanism

    or remove check valve completely and provide necessary spool piece or

    blinds.

    A notation shall be included on the Punch List that check valve flapper has

    been removed. A new gasket shall be installed by Subcontractor wherever the

    check valve bonnet has been disturbed. Where flappers have been removed,

    valves shall be marked by tagging.

    8.8 Systems that include expansion joints:

    8.8.1 Expansion joints shall be excluded from pressure testing if the piping test

    pressure is greater than the allowable test pressure of the expansion joint.

    8.8.2 When a pressure test is required to be maintained for a period of time during

    which the testing medium in the system would be subject to thermal

    expansion, provision shall be made for relief of any pressure greater than the

    maximum pressure.

    8.8.3 Holding pins/spring stops shall not be removed from spring supports or

    hangers until testing is completed and permission to remove is obtained from

    the CONTRACTOR.

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    14/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 14 OF 23

    REV: D2

    8.8.4 Test equipment to be used during testing shall have suitable capacity for the

    range of test pressures required. The range of pressure gauge(s) shall not beless than 11/2 nor more than four times that pressure.

    8.8.5 All pressure gauges and chart recorders are to be calibrated specifically for

    OCS#4 Project prior to use. If gauges have been used previously on other

    projects or for other purposes, they shall be recalibrated. Validation of gauges

    and chart recorders shall be for a maximum of 90days, however, recalibration

    shall be required if the calibrated gauge/recorder is damaged or strained.

    8.8.6 If the specified test, duration exceeds 8 hours, then a chart recorder shall be

    used to record test pressure.

    8.8.7 Prior approval must be obtained from the CONTRACTOR and Owner to include

    vessels or inline equipment in the pressure test circuit.

    8.8.8 (1) All necessary precautions shall be taken to ensure that, where

    applicable, nitrogen purges in vessels or equipment are maintained and

    ingress of moisture prevented.

    (2) Purges shall not be released without CONTRACTOR approval, and shall

    be reinstated upon completion of required work, unless otherwisedirected by the CONTRACTOR.

    8.8.9 No equipment/instrument that is part of permanent works shall be used as

    part of pressure testing equipment (i.e. pressure gauges, chart recorders,

    valves, safety valves etc)

    9.0 HYDROSTATIC TEST PROCEDURE

    9.1 A systems test shall be employed. So as to hydrostatically test as much

    piping as possible at one time. This test shall include one or more lines but

    should not be connected to vessels and equipments.

    9.2 The minimum test pressure for a system test shall be such that each line in

    the system is subjected to a minimum test pressure in accordance with

    paragraphs 4.1 or 4.2

    9.3 The maximum system test pressure shall not exceed the pressure test rating

    of any piping component.

    9.4 Systems or sections of systems to be tested may be isolated by closed valves

    provided the alive seat is suitable for the test pressure.

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    15/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 15 OF 23

    REV: D2

    9.5 Where a valve is not suitable, vessels, equipment or other piping not included

    in the system to be pressure tested shall be disconnected from the system orisolated by blinds or other means during the test.

    9.6 The normal location for the pressure test gauge is at grade near the pressure

    test pump and at the highest point of the piping system. Readings may be

    made at higher points providing the gauge pressure reading plus the static

    head (0.97 kg/cm2/M) between grade and the point of measurement does not

    exceed the maximum test pressure.

    9.7 Hydrostatic test pressure shall be maintained for a sufficient length of time to

    visually determine if there are any leaks, but not less than ten (10) minutes.

    Test pressure shall not be required to be maintained in excess of two hours

    after notification to CONTRACTOR.

    9.8 After completion of the test, pressure shall be released by opening the valve

    gradually so as not to endanger personnel or damage equipment.

    As a rule, pressure releasing rate shall be 300 kg/ cm2/hr. For piping line for

    which pressure releasing rate is to be specified, refer to specific job

    requirements.

    9.9 After completion of the test, the piping and equipment shall be drained

    completely.

    9.10 Piping systems shall be filled from a low point and filtered with a 10 micron

    filter. During filling of the system all air or gaseous substance shall be vented

    from high point to the maximum extent possible.

    9.11 Hydrostatic test water will be discharged to the nearest storm water drains.

    10.0 SAFETY

    The safety related issues including but not limited to the following should be

    addressed in Job Hazard Analysis (JHA) to be made by CONTRACTOR for

    performance of Pressure Testing activities:

    10.1 Appointment of CONTRACTOR's Test Controller who is in attendance and

    responsible throughout the testing and inspects the welding during testing.

    10.2 Appointment of the subcontractor's test controller who will be responsible for

    ensuring safe testing in accordance to the specification.

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    16/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 16 OF 23

    REV: D2

    10.3 Display of safety warning signs to alert workers in the vicinity of the pressure

    testing with line, identification.

    10.4 Pressure test training and maintenance of a competency register as required

    by CONTRACTOR Safety Plan.

    10.5 Pressure rating for the test manifold and the test equipment and the required

    inspection/testing.

    11.0 SENSITIVE LEAK TEST

    Piping required to have a sensitive leak test shall be tested by the gas and

    bubble formation testing method specified in article 10, section V, of the

    ASME boiler and pressure vessel code. If an additional hydrostatic pressure

    test is required, it shall be done after the sensitive leak test.

    12.0 ALTERNATIVE TESTS

    This test shall be applied in accordance with ASME B31.3 Para 344.9 or

    ASME B31.4 Para 437.1.4(b), if required, subject to approval from

    PTT/Consultant

    12.1 Void

    12.2 Void

    12.3 Initial Service Leak test

    12.3.1 This test is applicable only to piping in Category Fluid service at the

    owner's option.

    12.3.2 A piping system used only for category ID fluid service may be tested at

    the normal operating conditions of the system during or prior to initial

    operation by examining for leaks at every joint not previously hydrostatic

    or pneumatic tested in accordance with this specification.

    12.3.3 Unless dictated otherwise by contractual provision, commodity testingshall be performed before mechanical completion.

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    17/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 17 OF 23

    REV: D2

    12.4 Non Pressure Piping shall be checked thoroughly by visual examination in due

    course after installation

    13. VESSELS AND EQUIPMENT

    13.1 Hydrostatic testing of the following items is not permitted. However, they

    may be pneumatically tested with adjoining piping system, if so designated in

    the Field Pressure Testing.

    13.1.1 Vessels or equipment supported by other vessels or equipment or by a

    support Structure or foundation not capable of supporting the hydro test

    load.

    13.1.2 Vessels or equipment not capable of sustaining the hydro test load.

    13.1.3 Vessels with internals or linings that would be damaged by the test fluid.

    13.2 The following shall be excluded from all pressure tests:13.2.1 Pumps, compressors and turbines. Associated lube and seal oil systems

    which could be impaired by the presence of water shall be tested with lube

    oil.

    13.2.2 Equipment and Seller furnished piping specifically recommended by the

    manufacturer not to be tested.

    13.2.3 Strainer and filter elements.

    13.2.4 Vessels which do not satisfy impact requirements at pressure test

    temperature

    14.0 INSTRUMENTS

    14.1 All instruments will be protected from damage when hydro testing process

    and utility piping systems. Paragraph 2.3 outlines the status of instruments

    during testing to insure protection.

    14.2 Control valves shall have their bodies shop tested and need not be retested in

    the field, but where valve does not restrict test pressure, valve may be

    included in a system test. Valves shall be jacked open during test.

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    18/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 18 OF 23

    REV: D2

    15.0 CLEANING

    15.1 Tested piping shall be internally cleaned to remove all remaining dust and

    foreign matter by water flushing or blowing with air.

    15.2 Flushing shall be done with clean water using hydrostatic test water where

    possible. Water used for special flushing or cleaning of austenitic stainless

    steel shall not contain more than 50 PPM chlorides, i.e.

    15.3 Where special treatment is required, such as cleaning of compressor suction

    and lube oil piping, a separate procedure shall be prepared by

    CONTRACTOR'S Operations/Commissioning Group.

    16.0 REPORTS AND RECORDS

    16.1 As a minimum, the Subcontractor shall maintain records of all pressure tests,

    records of all welding operations, including welder numbers, weld numbers,

    and post weld heat treatment charts referenced to weld numbers, records of

    all hardness tests, records of all cleaning, pressure gauges calibration sheets,

    and when certification is required, all certification records.

    16.2 All records shall be submitted and approved by the CONTRACTOR and shall

    be submitted to the Owner.

    16.3 Piping Field Test Report shall be prepared for each line segment of non

    pressure piping.

    17.0 TEST RECORDS

    17.1 Records shall be made of each piping system test.

    These records, when completed, shall be submitted as part of the test and

    inspection certificates which are required for precommisioning.

    Records shall include:

    1) Date of test

    2) Identification of piping system and any vessels or equipment tested

    with the piping system.

    3) Test medium

    4) Test pressure and maintaining time

    5) Minimum ambient temperature

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    19/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 19 OF 23

    REV: D2

    17.2 All test records, and authorized CONTRACTOR certifications shall be retained

    in the Test Package records for turnover to the Owner. Test data base shall beestablished to monitor status and progress.

    17.3 Where complete drainage is impossible, the system shall be flushed free of all

    test water using boiler condensate or dematerialized water containing less

    than five(5) PPM chlorides, alcohol, petroleum distillate or another suitable

    flushing solution. Hot air drying is not acceptable in lieu of flushing, but water

    may be blown out of pockets using air.

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    20/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 20 OF 23

    REV: D2

    Appendix I Minimum Thickness of Blank for Pressure test

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    21/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 21 OF 23

    REV: D2

    1. In case where piping diameter is 1B or under.

    Test Pressure (kg / cm2) Thickness of Blind Plate (mm)

    7 or under 1.6

    8 14 2.3

    15 40 2.5

    41 60 3.2

    61 115 4.5

    116 210 6.0

    2. In case where piping diameter is 26B or over, following formula shall be

    applied to determine the thickness of blind plate.

    Thickness of blind plate tm = t + c

    dg : Inside diameter of gasket (mm) for raised face flanges, or the gasket

    pitch diameter for ring joint and fully retained gasket flanges(inches)

    P : design gauge pressure (psig)

    S : stress value for material from Table A-1 B (psig)

    E: quality factor from table A-1A or A-1 B

    C : corrosion / erosion, plus mill tolerance allowance(inches)

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    22/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 22 OF 23

    REV: D2

    Appendix II. Details of Test Facilities

    Schematic DWG for Supplying Source

    (1) For Pneumatic Test (Not applicable)

    (2) For Hydrostatic Test

    Equipment List for Piping Pressure Test.

    (1) Pump

    - Test Pump (Pressurizing Rump)

    - Water Supply Pump

    (2) Air Compressor (for blowing, if required)

    (3) Pressure Gauge (Two (2) or more)

    (4) Rubber Hose W/Steel Wire Reinforced

    (5) Temporary Piping with accessory

    (6) Chemical Inhibitor (If required)

    (7) Radios (Warlike Talkie)

    (8) Other materials

  • 8/6/2019 PTT_ Hydro Static Pressure Testing of Piping

    23/23

    HYDROSTATIC

    PRESSURE TESTING

    OF PIPING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-96.58

    PAGE: 23 OF 23

    REV: D2

    Appendix III. Test Limits Symbol

    (1) Pressure Gauge hall be used and having graduation of 1.5 or 2 times of

    test of more including gauge in pump discharge.

    (2) PG shall be installed two or more including gauge in pump discharge.

    (3) Calibrated gauge shall be used.

    (4) Gauge be installed at the highest and the lowest point.