PSM w ABS

download PSM w ABS

of 18

Transcript of PSM w ABS

  • ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014 521

    P A R T Section 14: Surveys Based on Preventative Maintenance Techniques

    7 A P P E N D I X

    S E C T I O N 14 Surveys Based on Preventative Maintenance

    Techniques (1 July 2012)

    1 General

    The intent of a Preventative Maintenance Program is for owners/operators to maintain their vessels with updated machinery maintenance practices, which may increase a vessels reliability and/or operational availability. While a Surveyor may allow a reduction in the amount of covered equipment being opened for crediting towards Special Continuous Survey of Machinery (CMS), provided it is enrolled in a Preventative Maintenance Program (PMP), operational testing may be increased.

    The following are procedures and conditions under which a properly conducted preventative maintenance plan may be credited as satisfying the requirements of Special Continuous Survey of Machinery. No preventative maintenance program supersedes the judgment of an ABS Surveyor, nor does it waive an ABS Surveyor(s) attendance for damage, overhaul of main engines, generator engines, steering gears, general insulation condition and resistance tests, electrical devices functional tests, reduction gear teeth examinations, hydrostatic tests of pressure vessels, tests and verification of safety devices such as relief valves, overspeed trips, emergency shut-offs, low-oil pressure trips, etc., as required by the ABS Rules for Building and Classing Steel Vessels, including the ABS Rules for Survey After Construction (Part 7). The reference to an ABS Recognized Condition Monitoring Company refers to those companies whom ABS has identified as an External Specialist. For additional requirements, refer to 7-A-14/19 of this Appendix.

    1.1 Survey and Maintenance Intervals

    Maintenance is to be carried out on the basis of intervals between overhauls recommended by manufacturers, documented operators experience and/or a condition monitoring system, where fitted. In general, the intervals for the Preventative Maintenance Program are not to exceed those specified for Special Continuous Survey of Machinery (CMS). However, for components where the maintenance is based on running hours or number of cycles, longer intervals may be accepted as long as the intervals are based on the manufacturers recommendations. In addition, if an approved PMP is in effect, the opening of individual items of equipment may not be required during the CMS cycle, based on satisfactory results within the program.

    1.2 Definitions

    i) Special Continuous Survey of Machinery (CMS) A program in which the total number of survey items is arranged in order to provide for survey of approximately 20% of the machinery each year during a five-year period.

    ii) Preventative Maintenance Program (PMP) A program that consists of Planned Maintenance and/or Condition Monitoring plans.

    a) Planned Maintenance (PM) A maintenance plan which uses time-based inspection, part replacement and/or overhauls in an effort to prevent equipment failures. Timing can be based on calendar days, cycles counter or equipment running hours. Such schedules are generally established by the machinery manufacturer and include lubrication servicing; filter, bearing and seal replacements; as well as major overhaul.

    b) Condition Monitoring (CM) The use of various technologies to determine the condition of equipment, at a specific moment in time, using minimal or non-invasive means. Common tools used in condition monitoring are vibration analysis, oil analysis, ferrography, thermography, electric current wave form analysis and boroscopic examination. Supplemental technologies, such as demodulation, ultrasonic analysis, shock-pulse, spike-energy, HFD, etc., for roller bearing element condition monitoring, may be used in addition to vibration analysis.

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    522 ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014

    iii) Condition Based Maintenance (CBM) A maintenance plan, conducted on a frequent or real-time

    basis, which is based on the use of Condition Monitoring to determine when part replacement or

    other corrective action is required. This process involves establishing a baseline and operating

    parameters, then frequently monitoring the machine and comparing any changes in operating

    conditions to the baseline. Repairs or replacement of parts are carried out before the machinery

    fails based upon the use of the tools prescribed for CM.

    iv) Reliability Centered Maintenance (RCM) RCM is a process that is used to determine the most

    effective approach to maintenance. It involves identifying actions that when taken will reduce the

    probability of failure and which actions are most cost effective. ABS has developed a maintenance

    program which uses RCM analysis of installed equipment to develop a Preventative Maintenance

    Program (PMP), a spare parts holdings list and includes a sustainment plan.

    a) Reactive Maintenance A RCM maintenance strategy in which equipment is run until

    failure before corrective action is taken. This is useful for items which are low-cost and

    have no impact on operational, environmental or safety concerns as a result of failure.

    b) One-Time Change A RCM maintenance strategy in which equipment or systems, that have

    been determined to present an unacceptable level of risk and have no potential mitigations,

    are replaced or significantly altered in order to provide an acceptable level of risk.

    1.3 Optional Notation (2014)

    An optional notation can be added to the Record indicating compliance with the Preventative Maintenance

    Program on one or more pieces of equipment. The PMP notation indicates less than 50%, and the PMP+ notation indicates 50% or greater of all classed equipment is enrolled into this program.

    3 Program Requirements

    For a Preventative Maintenance Program to be accepted in lieu of a conventional Special Continuous Survey

    of Machinery, the following conditions must be met:

    3.1 Age of Vessel

    There is no limit on the age of a vessel when entered into the program. However, an existing vessel

    applying for entrance into the program will be subject to a review of the vessels Survey Status records to

    ascertain the historical performance of the machinery which could affect the Preventative Maintenance

    Program. Provided there are no historical problems related to the maintenance of the machinery, the vessel

    will be considered eligible.

    3.3 Surveys (2014)

    Surveys related to the vessel are to be up-to-date, without outstanding recommendations which would

    affect the Preventative Maintenance Program. The machinery in the program is to be on a Special Continuous

    Survey of Machinery (CMS) cycle.

    If the vessel is not on CMS, the Owner is to be advised that the vessel is to be entered in CMS. For machinery

    for which an outstanding recommendation exists, confirmation is to be made that repairs have been performed,

    or if repairs have not been performed, the Owner is to be notified that an outstanding recommendation exists.

    The PMP notation can be applied to a vessel without an AMS notation with permanently installed machinery enrolled in either an approved PM, CM, or RCM plan. Vessels without an AMS notation will not be required to have the subject machinery on CMS, instead machinery will be credited in conjunction with the vessels

    Special Periodical Survey of Hull (SSH). However, all other requirements of the PMP notation are to be complied with, including but not limited to the submission of an annual report to the attending Surveyor, as

    detailed in 7-A-14/9.3 and maintenance of the required onboard documentation, as detailed in 7-A-14/11.

    Any machinery items not covered by the Preventative Maintenance Program are to be surveyed and credited

    in the usual way.

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014 523

    3.5 Damages

    There is to be no record of unrepaired damage to the vessel or its machinery which would affect the vessels

    ability to participate in the Preventative Maintenance Program.

    3.7 Computerized Maintenance Management Systems

    The activities of the Preventative Maintenance Program are to be programmed into the Computerized

    Maintenance Management System (CMMS) and the history of all maintenance tasks are to be recorded and

    stored in the CMMS by the operators/owners. These systems must include back-up devices, such as removable

    hard drives, thumb drives, CD-ROMs or remote on-line back-up systems and are updated at regular intervals.

    Details of the system are to be reviewed by the attending Surveyor during the implementation survey.

    5 Program Description

    5.1 General

    To enroll equipment items into Planned Maintenance (PM) [See 7-A-14/13.5.1(a)], a comprehensive plan

    is to be submitted to the attending ABS Survey Office for review prior to conducting an implementation survey.

    To enroll equipment items into Condition Monitoring (CM), the documentation required by 7-A-14/15.5.1(a) is

    to be submitted to the responsible ABS Engineering Office for approval prior to conducting an implementation

    survey. Only machinery subject to Special Continuous Survey of Machinery (CMS) is to be included in the

    program (unless review of any non-essential machinery is specifically requested by the Owner).

    5.3 Implementation Surveys

    Once a plan has been reviewed/approved, an implementation survey is to be carried out by the attending

    Surveyor prior to program commencement. The requirements for the implementation survey are provided

    in 7-A-14/13.3 (for PM plans) or 7-A-14/15.3 (for CM plans).

    Once this survey is carried out and the implementation found to be in order, a report confirming the

    implementation of the Planned Maintenance and/or Condition Monitoring plan(s) is to be submitted by the

    attending ABS Surveyor, and the plan(s) may be put into service.

    5.5 Machinery Status Indicators

    Once the Implementation Survey has been satisfactorily completed, the attending Surveyor shall advise

    Classification Documentation Center (CDC) that the items covered by a Planned Maintenance plan as per

    7-A-14/13.5.1(a)i) are to be shown by a PM indicator, and for the items covered by a Condition Monitoring

    plan as per 7-A-14/15.5.1(a)i) are to be shown by a CM indicator. When equipment is covered by both PM

    and CM plans, items covered are to be shown by a PM/CM indicator. The owner is to communicate with

    the attending Surveyor to ensure that the Survey Manager for a vessel shows the correct indicators for all

    listed equipment.

    5.7 Cancellation of Program

    The survey arrangement for machinery under the Preventative Maintenance Program may be cancelled by

    ABS if the program is not being satisfactorily carried out, as a result of insufficient maintenance records,

    lack of knowledge by the crew of the vessels program, the general condition of the machinery, or agreed

    intervals between overhauls are exceeded resulting in the annual survey not being completed within the

    survey window as required.

    Sale, change of vessel management, change of Recognized Condition Monitoring Specialists, or transfer of

    class is to be cause for reconsideration of the approval. If more than one occurs, the current plan will be

    cancelled and a new plan will be required to be submitted for approval.

    The Owner may cancel the survey arrangement for machinery under the Preventative Maintenance Program

    by informing ABS in writing. For this case, items which have been inspected under the program since the

    last Annual Survey may be credited for class at the discretion of the Surveyor.

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    524 ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014

    7 Overhauls and Damage Repairs

    7.1 Overhauls

    For equipment enrolled in the Condition Monitoring plan, following an overhaul, new baseline data is to be

    recorded in the presence of an ABS Recognized Condition Monitoring Company as soon as possible, but

    not to exceed the next vibration signature period or six months and is to be included in the Annual Report.

    Documentation on overhauls of items covered by the Preventative Maintenance Program is to be reported

    and signed by the chief engineer.

    7.3 Damage Repairs

    All damage to components/machinery is to be reported to ABS. Repairs of damaged components/ machinery

    are to be carried out to the satisfaction of the attending Surveyor in accordance with 7-1-1/7.1 and 7-1-1/7.3.

    Any repair and corrective action regarding machinery under the Preventative Maintenance Program is to be

    recorded and the repair verified by the attending Surveyor at the Annual Confirmation Survey. In the case of

    overdue outstanding recommendations or a record of unrepaired damage which would affect the Preventative

    Maintenance Program, the relevant items are to be removed from the program until the recommendation is

    fulfilled or the repair is carried out.

    9 Annual Surveys and Reporting

    9.1 Annual Confirmation Surveys

    Simultaneously with each Annual Survey of Machinery, for vessels enrolled in a Preventative Maintenance

    Program, an Annual Confirmation Survey is to be performed by the attending Surveyor. The purpose of

    this survey is to verify that the program is being correctly operated and that the machinery has been

    functioning satisfactorily since the previous survey. The survey is to include the following:

    i) A general examination of the items concerned is to be carried out.

    ii) The Surveyor is to review the Owners annual report, as detailed in 7-A-14/9.3, and the required

    onboard documentation as detailed in 7-A-14/11.

    iii) The performance and maintenance records are to be examined to verify that the machinery has

    functioned satisfactorily since the previous survey or action has been taken in response to machinery

    operating parameters which are outside acceptable tolerances and the overhaul intervals have been

    maintained.

    iv) Written details of breakdowns or malfunctions of equipment are to be made available.

    v) The description of repairs carried out is to be reviewed. Any machinery part, which has been replaced

    with a spare due to damage is to be retained onboard, where possible, until examined by the attending

    Surveyor.

    vi) At the discretion of the Surveyor, operational function tests, testing of safety devices and/or trips,

    confirmatory surveys and random check readings, are to be carried out as far as practicable and

    reasonable.

    Upon satisfactory completion of the above requirements, the Preventative Maintenance Program will be

    accepted by ABS for its continued use. The Surveyor may credit to the current CMS cycle any of the listed

    items that were overhauled and tested in the presence of and to the satisfaction of the attending Surveyor.

    Additionally, any of the listed equipment items that have been overhauled in accordance with the Planned

    Maintenance schedule may be credited to the CMS by the attending Surveyor after a satisfactory operational

    test. Any machinery that has acceptable operating conditions as per the approved Condition Monitoring plan

    may be credited to the current CMS cycle by the attending Surveyor after a satisfactory operational test.

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014 525

    9.3 Owners Annual Preventative Maintenance Report

    The Annual Confirmation Survey of the Preventative Maintenance Program is to be carried out by the attending

    Surveyor. The vessels qualified representative is to present an Annual Preventative Maintenance Report

    via hard copy or approved alternative electronic formats (7-A-14/9.5) containing the information detailed

    in 7-A-14/13.5.2 (for PM plans), 7-A-14/15.5.2 (for CM plans) and if applicable 7-A-14/17.7.2 (for RCM

    programs) to the attending Surveyor for review and verification at the time of the Annual Confirmation

    Survey of the Preventative Maintenance Program. Any reports submitted without all of the required information

    will be returned without action to the submitter.

    If the machinery included in the Preventative Maintenance Program has changed, this is to be stated. Any

    machinery to be added to the program is subject to the requirements of 7-A-14/5, its respective section

    [7-A-14/13.5 (for PM plans) or 7-A-14/15.5 (for CM plans)] and approval by the attending Surveyor.

    When adding machinery to a Condition Monitoring plan, approval is required from the responsible ABS

    Engineering Office. When removing machinery from any Preventative Maintenance Program, CDC is to

    be advised and the machinery status updated accordingly.

    9.5 Alternative Electronic Formats

    Owners may opt to submit their annual reports to the attending Surveyor in a portable electronic format

    (e.g., thumb drive, CD-ROM, or e-mail attachment), for review prior to or at the time of attendance onboard,

    as required by 7-A-14/9. Acceptable file types are those which are compatible with MS Word, MS Excel,

    and/or PDF. These reports must contain all the required information. In addition, the Owners must submit,

    annually, in hard copy, the following to the attending Surveyor:

    i) A letter stating that the annual report is on an alternative electronic format and meets the requirements

    of format and file type as per 7-A-14/9.5.

    ii) A summation and results of the annual vibration signatures. (For machinery enrolled in a Condition

    Monitoring Plan)

    iii) A summation and analysis of all unscheduled maintenance and breakdowns of the machinery enrolled

    into the program.

    iv) Directions on how to retrieve the report from the alternative electronic format.

    11 Onboard Documentation

    The vessels Chief Engineer shall be the responsible person onboard the vessel in charge of the Preventative

    Maintenance Program. If a computerized system is used for updating the maintenance documentation and

    maintenance program, access is to be permitted only by the Chief Engineer or other authorized persons.

    Additional requirements are provided in 7-A-14/13.7 (for PM plans), 7-A-14/15.7 (for CM plans) or

    7-A-14/17.9 (for RCM plans).

    13 Planned Maintenance (PM)

    13.1 General (2014)

    Owners may conduct Planned Maintenance on any item(s) of equipment. However, the following equipment

    cannot be enrolled into a PM plan and credit will not be given towards periodic surveys: x System Piping (All) x Valves (All) x Sea Chests x Bilge Pumps x Electrical Generators and associated Safety Devices and Trips (This does not include the prime mover or its attachments) x All Operational Tests

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    526 ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014

    x Fire Pumps x Fire Fighting Equipment x Main Engine Crankpin and Crosshead bearings x Main Engine Turbochargers x Main Engine Safety Devices and Trips x Oily Water Separators x Air Receivers with associated Relief Valves and Safety Devices x Heat Exchangers and Unfired Pressure Vessels with design pressures over 6.9 bar (7kgf/cm2, 100 psi) and associated Relief Valves x Steering Gear Piping, Pumps and Control/Relief Valves x Steam Turbines x Anchor Windlass

    13.3 PM Implementation Surveys

    Owners are to submit a written request to enroll their vessel(s) in the Preventative Maintenance Program. Planned Maintenance plans are to be reviewed by the attending ABS Survey Office. Both the initial review and implementation survey can be conducted at the same time onboard the vessel(s). To complete the implementation survey, the following items need to be checked:

    i) The onboard personnel are familiar with the PM Program

    ii) The machinery identification method and record keeping procedures are to be described.

    iii) The Preventative Maintenance Program is to be capable of producing the documentation required for the Annual Confirmation Survey (refer to 7-A-14/9 and 7-A-14/13.5.2) and required onboard documentation is present (see 7-A-14/11 and 7-A-14/13.7).

    iv) The vessel is to comply with the requirements of surveys and testing for retention of class.

    v) Details and back-up capabilities of the computerized system are to be reviewed.

    vi) Owners will submit a comprehensive schedule of servicing and overhaul including a description of the work to be performed at each interval.

    a) The proposed maintenance schedules are to be based upon the manufacturer recommended service and overhaul schedules. The vessel operator will submit a statement to ABS or show documentation that verifies that the proposed maintenance schedules are in accordance with manufacture recommendations.

    b) If the proposed maintenance schedules are based on vessel operators previous experience due to lack of manufacturers information, then appropriate evidence supporting operators proposals are to be submitted for review.

    vii) The PM Program is implemented according to the reviewed documentation and is adapted to the type and complexity of the components/systems on board.

    viii) The Survey status for the vessel is to be reviewed by the attending Surveyor. The vessel is to be on Special Continuous Survey of Machinery (CMS). The Surveyor is to ascertain if there are any damages or open outstanding recommendations that would prevent the proposed equipment items from being allowed.

    ix) The attending Surveyor will confirm, during the review, that the plan complies with the submission requirements of 7-A-14/13.5, including verification that machinery parts listed under 7-A-14/13 are not included. In addition, fire fighting appliances including breathing apparatus, fire extinguishers, firemans outfits and the international shore connection cannot be included under PM.

    x) Where the Owners Preventative Maintenance Program includes both planned maintenance and condition monitoring, then the attending Surveyor will have to ensure that the condition monitoring details have been approved by the responsible ABS Engineering Office and comply with the requirements of 7-A-14/15.3.

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014 527

    13.5 Administrative Requirements

    13.5.1 PM Plan Submission

    13.5.1(a) For Items Covered by a Planned Maintenance Plan

    i) A list and description of the machinery.

    ii) Organization chart identifying areas of responsibility.

    iii) Schedule of servicing and overhaul. This schedule is to meet at least the servicing and

    overhaul intervals specified by the manufacturer and a statement to this effect is to accompany

    the plan.

    iv) Description of the work to be performed at each interval.

    v) Machinery identification method and record keeping procedures.

    vi) Planned maintenance sheet(s)/record(s) for each machine to be considered.

    vii) A reference list showing owners equipment item name and ABS equivalent equipment

    name as shown in ABS Survey Manager.

    13.5.2 Owners Annual Preventative Maintenance Report Requirements

    13.5.2(a) PM Plan Report Annual

    i) A summary list of all machinery covered under the Planned Maintenance Program, including

    a complete description of work completed on each machine since the last submitted

    report. The Owner may add or delete equipment subject to the approval of the attending

    ABS Surveyor, who is also to notify the ABS Classification and Documentation Center

    (CDC) of any machinery additions or deletions, as necessary.

    ii) Planned maintenance sheet(s)/record(s) for each machine.

    iii) Exceptions, notes and comments noted during work.

    iv) Modifications and justifications to the schedule, such as might be recommended by a

    machinery manufacturers technical bulletin.

    v) List of machines that failed prior to scheduled maintenance or servicing, and related record

    of corrective actions taken.

    If the machinery included in the Planned Maintenance plan has changed, this is to be stated. Any machinery

    to be added to the plan is subject to the requirements of 7-A-14/13.5.1 and approval by the attending Surveyor.

    The Owner is to advise the attending Surveyor of all machinery for which periodic maintenance is not

    indicated or is incomplete as per the initial planned maintenance report. In the meantime, the condition of

    the machinery is to be to the satisfaction of the attending Surveyor.

    13.7 Onboard Documentation

    13.7.1 PM Plan

    i) The latest up-to-date information required in 7-A-14/13.5.1(a)

    ii) A copy of the manufacturers service manuals and/or shipyards maintenance instructions

    iii) Reference documentation (trend investigation procedures, etc.)

    iv) All records showing compliance with the program (including repairs and renewals carried

    out) are to be made available for review by the attending Surveyor at the Annual Survey

    of Machinery.

    v) A copy of the reviewed PM Plan

    vi) A users manual for the Computerized Maintenance Management System

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    528 ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014

    15 Condition Monitoring (CM)

    A Condition Monitoring plan, which uses quarterly, semi-annual or annual measurements, is intended to be

    supplemented with some Planned Maintenance activities. The benefit of using condition monitoring is that

    it may extend the intervals on certain Planned Maintenance activities (e.g., replacement of parts which are

    in good working order) based on the condition of the equipment at these periodic measurements. With

    regards to vibration measurements, ABS principally allows two methods to be used towards the crediting

    of the CMS cycle as discussed in 7-A-14/9.1. A summary of the first method involves the Chief Engineer

    or other trained crewmember(s) collecting overall vibration data on a quarterly basis and a representative

    specialist of an ABS Recognized Condition Monitoring Company collecting one set of complete vibration

    signatures annually. A summary of the second method, discussed in 7-A-14/15.11, involves complete vibration

    signatures being collected semi-annually by a representative specialist of an ABS Recognized Condition

    Monitoring Company, with no requirement for data collection by the Chief Engineer or crewmembers. For

    both methods, one set of complete vibration signatures is required to be taken during the three months prior

    to the date that the Annual Preventative Maintenance Report is provided to the attending Surveyor.

    When equipment is covered by both PM and CM plans (substantiated by a PM/CM indicator), the results

    of the CM analysis may affect the requirements of the vessels PM plan. When the CM analysis demonstrates

    that the equipment is operating satisfactorily, consideration will be given for deferring appropriate PM tasks.

    15.1 General (2014)

    Owners may conduct Condition Monitoring on any item(s) of equipment. However, the following equipment

    cannot be enrolled into a CM plan and credit will not be given towards periodic surveys: x System Piping (All) x Valves (All) x Sea Chests x Bilge Pumps x Electrical Generators and associated Safety Devices and Trips (This does not include the prime mover or its attachments) x All Operational Tests x Fire Pumps x Fire Fighting Equipment x Main Engine Safety Devices and Trips x Oily Water Separators x Air Receivers with associated Relief Valves and Safety Devices x Heat Exchangers and Unfired Pressure Vessels with design pressures over 6.9 bar (7 kgf/cm2, 100 psi) and associated Relief Valves x Steering Gear Piping, Pumps and Control/Relief Valves x Anchor Windlass

    15.3 CM Implementation Surveys

    Owners are to submit a written request to enroll their vessel(s) in the Preventative Maintenance Program.

    Condition Monitoring plans are to be approved by the responsible ABS Engineering Office. The plan must

    be approved before an implementation survey can be conducted. To complete the implementation survey,

    the following items need to be checked:

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014 529

    i) The CM Program is implemented according to the approved documentation and is adapted to the

    type and complexity of the components/systems on board

    ii) The onboard personnel are familiar with the CM Program

    iii) The machinery identification method and record keeping procedures are to be described.

    iv) The Preventative Maintenance Program must be capable of producing the documentation required

    for the Annual Confirmation Survey (refer to 7-A-14/9 and 7-A-14/15.5.2) and required onboard

    documentation is present (7-A-14/11 and 7-A-14/15.7).

    v) Details and back-up capabilities of the computerized system are to be reviewed.

    vi) The vessel is able to comply with the requirements of surveys and testing for retention of class.

    vii) The Survey status for the vessel is to be reviewed by the attending Surveyor. The vessel is to be

    on Special Continuous Survey of Machinery (CMS). The Surveyor is to ascertain if there are any

    damages or open outstanding recommendations that would prevent the proposed equipment items

    from being allowed.

    viii) The attending Surveyor will confirm, during the review, that the plan complies with the submission

    requirements of 7-A-14/15.5, including verification that machinery parts listed under 7-A-14/15

    are not included. In addition, fire fighting appliances including breathing apparatus, fire extinguishers,

    firemans outfits and the international shore connection cannot be included under CM.

    15.5 Administrative Requirements

    15.5.1 CM Plan Submission

    15.5.1(a) For Items Covered by a Condition Monitoring Plan

    i) A list and description of the machinery covered including:

    a) Method of data collection and analysis tools

    b) Nominal rpm

    c) Horsepower

    d) Location and orientation of sensor attachments, which are to be permanently marked

    and/or affixed by a Recognized Condition Monitoring Specialist on covered

    machinery

    e) Sampling procedures for oil analysis

    ii) Organization chart identifying areas of responsibility.

    iii) Schedule of data collection.

    iv) Type and model of data collection instrument, including sensor and attachment method

    and calibration schedule.

    v) Acceptance criteria of data.

    vi) Baseline data. Initial or baseline data are to be recorded in the presence of the Surveyor

    and/or a representative specialist of an ABS Recognized Condition Monitoring Company

    and are to be compared to the acceptable vibration levels shown in SNAMEs T&R Bulletin

    3-42 Guidelines for the Use of Vibration Monitoring for Preventative Maintenance or

    other equivalent national or international standards. The Owner is to be notified of all

    machinery that does not meet acceptance criteria (i.e., machinery with high vibration levels).

    vii) A reference list showing owners equipment item name and ABS equivalent equipment

    name as shown in ABS Survey Manager.

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    530 ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014

    15.5.2 Owners Annual Preventative Maintenance Report Requirements

    15.5.2(a) CM Plan Report Annual

    i) A summary report listing all machinery covered under the Condition Monitoring plan, clearly

    stating the overall condition of the machinery based on the most recent vibration measurement

    data (i.e., Satisfactory, Marginal, or Unacceptable). Data for the report must have been

    collected within three months of the submission date of the report by an ABS Recognized

    Condition Monitoring Company. This report is to be provided to the attending Surveyor.

    ii) Where the crew is taking vibration measurements, then training records for the designated

    crew members and description of training is to be included. Also, the type of recording

    device, method of data collection and calibration of the data collector must be provided. See

    also. The attending Surveyor may request a trained crewmember to demonstrate proficiency

    in vibration reading and related management of the obtained data.

    iii) Summary and analysis of machines that failed prior to a vibration reading or servicing.

    iv) Records of any maintenance conducted on equipment enrolled in the CM Plan.

    v) Records of any equipment that has been replaced, including information required by

    7-A-14/15.5.1(a).

    If the machinery included in the Condition Monitoring plan has changed, this is to be stated. Any machinery

    to be added to the plan is subject to the requirements of 7-A-14/15.5.1 approval by the responsible ABS

    Engineering Office and the attending Surveyor. Any machinery to be deleted from the Condition Monitoring

    plan is to be brought to the attention of the attending Surveyor and written documentation sent to the

    responsible ABS Engineering Office and CDC.

    Vibration readings are to be compared to the baseline readings in the implementation report. The Owner is

    to advise the attending Surveyor of required maintenance or additional monitoring which is needed for

    machinery with vibration readings above those in the approved baseline. Machinery unavailable for

    measurements are to be noted and the Owner advised that readings are to be submitted for review. In the

    meantime, the condition of the machinery is to be to the satisfaction of the attending Surveyor.

    15.7 Onboard Documentation

    15.7.1 CM Plan

    i) The latest up-to-date information required in 7-A-14/15.5.1(a).

    ii) For vessels with onboard vibration meters or FFT vibration analyzers, manuals supplied

    by manufacturers for use of data collectors and computer programs, as well as guidance

    for machine operating and diagnosis of machine faults.

    iii) Condition monitoring data, including all data since last opening of the machine and the

    original baseline data.

    a) Complete vibration data (including vibration signatures), as specified in

    7-A-14/15.5.1(a), are to be taken and reviewed by a representative of an ABS

    Recognized Condition Monitoring Company on an annual basis or more frequently

    when warranted by abnormal conditions or operational parameters, and retained

    onboard for review by the attending Surveyor.

    b) Full trend analysis (including spectral analysis for vibration) of machinery displaying

    operating parameters exceeding acceptable tolerances. Also, alarm criteria.

    c) Relevant operational data during data recording, such as sea state, machine

    temperature, other equipment affecting the data, etc. are to be included.

    d) Quarterly overall broadband vibration meter readings recorded by vessel personnel

    (or documentation showing alternative techniques are approved) and retained

    onboard for review by the attending Surveyor.

    iv) Reference documentation (trend investigation procedures, etc.).

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014 531

    v) Records of lube oil analysis, rotor positioning readings, and interstage bleed system pressures

    are to be recorded by the vessels personnel at least on a quarterly basis and retained onboard

    for review annually by the attending Surveyor.

    vi) If the vessel includes internal combustion engines in the program, the data outlined in

    7-A-14/15.9.2 must be retained onboard for review annually by the attending Surveyor.

    vii) Calibration date of equipment. Calibration is to be in accordance with the manufacturers

    recommendations or annually, if not otherwise specified.

    viii) Crew training records of the designated members, where crew is taking periodic vibration

    readings.

    ix) Any repairs or changes to any machines must be reported, and a summation and analysis

    of all unscheduled maintenance and/or breakdowns of monitored equipment.

    x) All records showing compliance with the program, including a copy of the most recent

    Owners annual report are to be made available for review by the Surveyor at the Annual

    Survey of Machinery.

    xi) A copy of the approved CM Plan and ABS approval letter

    xii) A users manual for the Computerized Maintenance Management System

    15.9 Special Conditions

    15.9.1 Steam Turbine

    Condition monitoring of turbines must provide information as per 7-A-14/11.

    The main propulsion turbine rotor journal bearings, thrust bearings, and flexible couplings are to

    be opened up for examination. The low pressure exhaust trunk is to be opened for examination of the

    last row of low pressure and astern wheels. Providing vibration readings, lubrication oil analysis and

    axial rotor position checks and turbine operating records are reviewed and all considered satisfactory

    by the Surveyor, the lifting of the main propulsion turbine casings (HP and LP) may be waived at

    alternate, subsequent Special Periodical Surveys, as outlined in 7-6-2/3.1.4.

    On turbines where variable or abnormal readings are noted, readings are to be recorded by the

    vessels personnel more frequently, as appropriate to properly monitor the performance range or

    establish the trend.

    15.9.2 Internal Combustion Engines

    Machine condition monitoring of internal combustion engines must provide a detailed engine analysis,

    as well as information provided in 7-A-14/5.1. The following data must be recorded at least monthly,

    unless indicated otherwise.

    i) Operating time (running hours)

    ii) Power output (MCR)

    iii) RPM

    iv) Cylinder pressure as function of crank angle

    v) Injection pressure as function of crank angle

    vi) Cylinder liner and piston ring wear (on basis of compression/firing pressures or proximity

    readings)

    vii) Scavenging air pressures and temperatures

    viii) Lubricating oil and cylinder oil consumption

    ix) Bearing temperatures (main, crank pin, crosshead and internal thrust, as fitted)

    x) Cylinder exhaust temperatures

    xi) Turbocharger vibration and T/C RPM

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    532 ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014

    xii) Lubricating oil analysis (quarterly)

    xiii) Crankshaft deflection readings for medium/slow speed diesel engines, as defined in 4-2-1/1.3

    of the ABS Rules for Building and Classing Steel Vessels (quarterly).

    For machines for which variable or abnormal readings are noted, readings are to be recorded by the

    vessels personnel more frequently, as appropriate to properly monitor the performance range or

    establish the trend.

    15.9.3 Electrical Switch Gear and Power Distribution Panels

    Condition monitoring plans for electrical equipment are to include examination of panels,

    switchboards, transformers and other essential electrical apparatus by infrared photographic

    thermography during each five-year survey cycle while the circuit is energized and under normal

    workloads. A report describing the results of the survey, as well as periodic insulation resistance

    records must be retained onboard for review by the attending ABS Surveyor.

    15.9.4 Diesel Engine Bearing Wear Monitoring Systems (2014)

    Condition Monitoring plans for bearing wear monitoring systems apply to main, crosshead and

    crank pin bearings. The bearing wear monitoring system may be credited towards CMS under the

    Condition Monitoring plan, in lieu of the required bearing open out method. In order for ABS to

    accept this alternative to main diesel engine bearing open out inspections, the following minimum

    requirements have been established for implementing a bearing wear monitoring system:

    i) The Owner is to submit a written request to the responsible ABS Engineering Office to

    review details of the system to be installed and vessel(s) on which the system is to be fitted.

    ii) The bearing wear monitoring system is to be ABS Type Approved.

    iii) Owner is to provide a letter from the engine manufacturer confirming, for the engine model

    installed, that the specified bearing monitoring system eliminates the need for normal

    opening of the bearings for inspections and listing the specific bearings that are covered.

    iv) Engine bearings are placed under Condition Monitoring status and an implementation survey

    is required.

    v) Vessel's Chief Engineer is responsible for maintaining records of trend measurements

    from established initial base line value. Therefore, appropriate records are to be available

    for examination by the attending Surveyor during surveys.

    vi) The attending Surveyor will retain the option to require (partial or full) opening of a bearing

    where the bearing condition analysis suggests abnormalities, based on external examination,

    feeler gauge readings, bearing edge condition, oil analysis results, or crank shaft deflections,

    etc.

    For crosshead bearings enrolled in this plan, one crosshead bearing is to be opened out for

    inspection during each Special Survey cycle. If problems are found, then further openings

    may be required. Owners are encouraged to open these bearings during drydocking periods

    whenever possible.

    15.9.5 Permanently Installed Monitoring Equipment

    Permanently installed electronic analyzing equipment used for the Condition Monitoring Program is to

    comply with the requirements of 4-9-3/17 of the ABS Rules for Building and Classing Steel Vessels,

    regarding testing and certification of automatic and remote control systems for use onboard ship.

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014 533

    15.11 Alternative Techniques

    Application of techniques of condition monitoring other than those mentioned above will be specially

    considered.

    15.11.1 Semi-Annual Alternative (2014)

    Condition monitoring based on semi-annual signatures is acceptable as an alternative technique for

    rotating machinery in lieu of quarterly overall vibration meter readings supplemented by an annual

    signature, as required in 7-A-14/15.7.1iii). The semi-annual signatures are to be taken and reviewed

    by a representative of an ABS Recognized Condition Monitoring Company. External checks, such

    as lube oil analysis, shaft position indicating and bearing temperatures are not affected and are to

    continue to be monitored by the crew at least on a quarterly basis.

    The annual Owners report is to clearly indicate that this alternative is being utilized and must include

    both semi-annual signatures for all of the monitored equipment. In addition, a summation and

    analysis of all unscheduled maintenance and/or breakdowns of the monitored equipment which were

    not identified by the semi-annual signatures must be included. Any reports submitted without the

    required statement of maintenance and/or summation will be returned without action to the submitter.

    17 Reliability Centered Maintenance (RCM)

    17.1 Application

    The following are procedures and conditions under which a properly conducted Reliability Centered

    Maintenance (RCM) analysis and the resulting Preventative Maintenance Program may be credited as

    satisfying the requirements of Special Continuous Survey of Machinery.

    No preventative maintenance plan supersedes the judgment of an ABS Surveyor, nor does it waive an ABS

    Surveyor(s) attendance for damage, overhaul of main engines, generator engines, steering gears, general

    insulation condition and resistance tests, electrical devices functional tests, reduction gear teeth examinations,

    hydrostatic tests of pressure vessels, tests and verification of safety devices such as relief valves, overspeed

    trips, emergency shut-offs, low-oil pressure trips, etc., as required by the ABS Rules for Building and

    Classing Steel Vessels, including the ABS Rules for Survey After Construction (Part 7).It is a prerequisite

    that the machinery in this program be on a Special Continuous Survey of Machinery (CMS) cycle.

    17.3 General

    By using RCM principles, maintenance is evaluated and applied in a rational manner. Functional failures

    with the highest risk are identified and then focused on. Equipment items and their failure modes that will

    cause high-risk functional failures are identified for further analyses. Maintenance tasks and maintenance

    strategies that will reduce risk to acceptable levels are determined. Spare parts inventories are determined based

    on the maintenance tasks developed and a risk assessment. An RCM sustainment procedure is instituted to

    continually monitor and optimize maintenance. Accordingly, improved equipment and system reliability

    can be expected.

    Additional information and explanations on how to develop a RCM program can be found in the ABS

    Guide for Survey Based on Reliability Centered Maintenance (RCM Survey Guide), and the ABS Guidance

    Notes on Reliability Centered Maintenance (RCM Guidance Notes).

    17.3.1 Definitions

    A RCM analysis as defined by the RCM Guidance Notes will generate additional types of maintenance

    tasks which are not previously defined by the Preventative Maintenance Program. In order to

    simplify the RCM Program plan approval process, implementation survey and annual surveys, the

    following groupings of these tasks will be used to determine the applicable requirements:

    i) Planned Maintenance type-tasks x Planned Maintenance Tasks x Failure Finding Tasks x Other Applicable and Effective Tasks

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    534 ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014

    ii) Condition Monitoring type-tasks x Condition Monitoring Tasks x Combinations of Planned Maintenance and Conditioning Monitoring Tasks 17.3.2 Optional Notations

    The RCM Program is to be approved by an ABS Engineering Office. Upon completion of a

    satisfactory Implementation Survey, a Certificate of Approval for Reliability Centered Maintenance

    Program is to be issued by the attending Surveyor. A notation, if appropriate, will be entered in

    the Record. The Owner may select desired systems or equipment items for which a RCM analysis

    will be conducted and will be used to develop a Preventative Maintenance Program. All machinery

    items covered by the RCM analysis will be surveyed and credited in accordance with the ABS

    Rules for Survey After Construction (Part 7) and the respective section(s) of the Preventative

    Maintenance Program.

    When the RCM Program is approved for the equipment related to:

    i) The propulsion system, including as applicable: prime mover(s), reduction gears, shafting,

    propeller or other thrusting device, all auxiliary systems providing, cooling, control, electrical

    power, exhaust, fuel, lubrication and equipment related to the steering or other directional

    control system, the RCM Program will be assigned and distinguished in the Record with

    the class notation RCM (PROP).

    ii) The cargo handling (cargo pumps, associated piping for internal and independent tanks)

    and safety equipment (i.e., inert gas system, vapor emission control) for a tanker, liquefied

    gas carrier or chemical carrier, the RCM Program will be assigned and distinguished in

    the Record with the class notation RCM (CARGO).

    iii) Systems used in connection with drilling, when the drilling system is in compliance with

    the ABS Guide for the Classification of Drilling Systems, will be distinguished in the

    Record with the class notation RCM (CDS).

    iv) (2014) When the RCM Program is approved for the Production or Facilities systems and

    equipment on an FPSO or FSO, the RCM Program will be distinguished in the Record

    with the class notation RCM (PFE).

    17.3.3 Survey Credit Towards the Current CMS Cycle.

    Owners may conduct a RCM analysis on any item(s) of equipment, but credit will only be given

    towards periodic surveys when the equipment and associated Preventative Maintenance tasks (as

    defined in 7-A-14/17.3.1) are in compliance with the applicable requirements stated in 7-A-14/13

    and/or 7-A-14/15.

    17.5 RCM Implementation Surveys

    Owners are to submit a written request to enroll their vessel(s) in the Reliability Centered Maintenance (RCM)

    Program. RCM plans are to be approved by the responsible ABS Engineering Office. The plan must be

    approved before an implementation survey can be conducted. To complete the implementation survey, the

    following items need to be checked:

    i) The RCM Program is implemented according to the approved documentation and is adapted to the

    type and complexity of the components/systems on board.

    ii) The onboard personnel are familiar with the RCM Program.

    iii) The machinery identification method and record keeping procedures are described and implemented.

    iv) The onboard RCM software must be capable of producing the documentation required for the Annual

    Confirmation Survey (refer to 7-A-14/9 and 7-A-14/17.7.2) and required onboard documentation

    is present (7-A-14/11 and 7-A-14/17.9).

    v) A Spare Parts list is readily available and the crew knows how to find parts using it.

    vi) A RCM sustainment process is in effect which supports the RCM analysis and future updates.

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014 535

    vii) Details and back-up capabilities of the computerized system are to be reviewed.

    viii) The vessel is able to comply with the requirements of surveys and testing for retention of class.

    ix) The Survey status for the vessel is to be reviewed by the attending Surveyor. The vessel is to be

    on Special Continuous Survey of Machinery (CMS). The Surveyor is to ascertain if there are any

    damages or open outstanding recommendations that would prevent the proposed equipment items

    from being allowed.

    x) The attending Surveyor will confirm, during the review, that the plan complies with the submission

    requirements of 7-A-14/17.7, including verification that machinery parts listed under 7-A-14/13

    (or 7-A-14/15 if applicable) are not included. In addition, fire fighting appliances including breathing

    apparatus, fire extinguishers, firemans outfits and the international shore connection cannot be

    included under RCM.

    xi) For vessels that are due to be placed in service or have recently been delivered so that little or no

    scheduled maintenance has been performed, the Surveyor is to verify items i), iii), iv), v), vi) are

    available and the onboard personnel have been trained to implement the RCM Program, item ii).

    17.7 Administrative Requirements

    17.7.1 Items Required for RCM Program Submission

    i) Define Systems

    ii) Identify Functions and functional failure

    iii) Conduct Failure Modes, Effects, and Criticality Analysis

    iv) Select a failure management strategy

    v) Develop a Preventative Maintenance Program plan

    vi) Develop a spare parts holding plan [refer to 7-A-14/17.7.1(a)]

    vii) Develop a RCM sustainment plan [refer to 7-A-14/17.7.1(b)]

    viii) Document and submit the analysis and plans.

    ix) A reference list showing owners equipment item name and ABS equivalent equipment

    name as shown in ABS Survey Manager.

    17.7.1(a) Spare Parts Holding Documentation. The spare parts holding documentation is to be a

    summary. The documentation is to provide the following information:

    i) There is to be identification between the maintenance task listed and the RCM analysis

    (e.g., Item Nos. in the RCM analysis).

    ii) The task type is to be listed (e.g., Condition Monitoring (CM), Planned Maintenance (PM),

    Combination of CM and PM (CM/PM), Failure Finding (FF), One-time Change (OTC),

    Run-to- Failure (RTF), Any Applicable and Effective Task (AAET).

    iii) The risk due to a spare being out of stock, along with the appropriate spare parts strategy

    (e.g., Order parts before demand, Hold parts in storage, Revise RCM maintenance tasks,

    Review RCM maintenance tasks, No spares holdings required).

    iv) The maintenance procedure is listed.

    An example of a Spare Parts Holding Determination summary is shown in Section 2, Table 10 of

    the RCM Survey Guide.

    17.7.1(b) RCM Sustainment Documentation. The sustainment documentation is to be maintained

    onboard by the vessel/rig/facility operators. The sustainment process is to be designed to allow

    verification by the attending Surveyor at the annual Survey. Sustainment documentation is to

    include the following items:

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    536 ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014

    i) Trend Analysis

    ii) Maintenance Requirement Document Reviews

    iii) Task-packaging Reviews

    iv) Age-exploration Tasks

    v) Failures

    vi) Relative Ranking Analysis

    vii) Other Activities

    17.7.2 Owners Annual RCM Program Report Requirements

    The Annual Confirmation of the Reliability Centered Maintenance Program will be carried out by

    the attending Surveyor, who will confirm the Program is being effectively implemented onboard.

    The vessels Owner or qualified representative is to present an Annual Reliability Centered

    Maintenance Report containing the following information to the attending Surveyor for review

    and verification at the time of the Annual Confirmation Survey. Any reports submitted without all

    of the required information will be returned without action to the submitter. The annual report is to

    be submitted in an electronic format in accordance with the requirements of 7-A-14/9.5. Information

    to be included with the annual report is detailed in the following:

    i) If equipment items included in the Reliability Centered Maintenance Program are to be

    changed, this is to be stated. Any machinery to be added to the system will require approval

    by the responsible ABS Engineering Office and the attending Surveyor with appropriate

    notification sent to CDC. Any machinery to be deleted from the RCM Program is to be

    brought to the attention of the attending Surveyor and written documentation sent to the

    responsible ABS Engineering Office and CDC.

    ii) If during the sustainment process it was determined that the time interval for any Planned

    Maintenance type-task needs to be altered, then changes will need to be submitted with

    documentation that supports the change in interval to the attending Surveyor for review

    and acknowledgement.

    iii) All Planned Maintenance type-tasks As per the requirements of 7-A-14/13.5.2(a)

    iv) All Condition Monitoring typetasks As per the requirements of 7-A-14/15.5.2(a)

    v) RCM Sustainment Activities Evidence of sustainment activities are to be included in the

    annual report. The results of relative ranking analyses, trend analyses, maintenance

    requirements document reviews, task packaging reviews, age exploration tasks and failure

    investigations of all unscheduled maintenance and/or breakdowns are to be provided.

    Sustainment activities can be conducted ashore as long as some shipboard personnel, who

    have been participating in the RCM program aboard the subject vessel, are involved in the

    sustainment activities. Appropriate documentation can also be produced ashore but will be

    required to be present in addition to normally required onboard documentation during the

    annual confirmation survey.

    vi) Report Exceptions The Owner is to advise the attending Surveyor of all machinery for

    which maintenance is not indicated or is incomplete as per the implementation report or

    when additional monitoring is needed for machinery with vibration readings above those in

    the approved baseline. If either of the above mentioned situations occurs, the condition of

    the machinery is to be to the satisfaction of the attending Surveyor.

    17.9 Onboard Documentation

    The vessels Chief Engineer shall be the responsible person onboard, and in charge of the Reliability Centered

    Maintenance Program. If a computerized system is used for updating the maintenance documentation and

    maintenance program, access is to be permitted only by the Chief Engineer or other authorized persons.

    The following information is to be available onboard.

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014 537

    i) The latest up-to-date information required in 7-A-14/15.5.1(a).

    ii) For vessels with onboard vibration meters or FFT vibration analyzers, manuals supplied by

    manufacturers for use of data collectors and computer programs, as well as guidance for machine

    operating and diagnosis of machine faults.

    iii) Condition monitoring data, including all data since last opening of the machine and the original

    baseline data.

    iv) Reference documentation (trend investigation procedures, etc.).

    v) Records of lube oil analysis, rotor positioning readings, and interstage bleed system pressures are

    to be recorded by the vessels personnel at least on a quarterly basis and retained onboard for

    review annually by the attending Surveyor.

    vi) Complete vibration data, as specified in 7-A-14/15.5.1(a), are to be taken at least quarterly, or

    more frequently when warranted by abnormal conditions and operational parameters, and to be

    reviewed by a representative specialist of an ABS Recognized Condition Monitoring Company

    and retained onboard for review annually by the attending Surveyor.

    vii) If the vessel includes internal combustion engines in the program, the data outlined in 7-A-14/15.9.2

    must be retained onboard for review annually by the attending Surveyor.

    viii) Calibration date of equipment. Calibration is to be in accordance with the manufacturers

    recommendations or annually, if not otherwise specified.

    ix) Any repairs or changes to any machines must be reported, and a summation and analysis of all

    unscheduled maintenance and/or breakdowns of monitored equipment.

    x) All records showing compliance with the program, including a copy of the most recent Owners

    annual report are to be made available for review by the Surveyor at the Annual Survey of Machinery.

    xi) Crew training records of the designated members, where crew is taking periodic vibration readings.

    xii) Records for required spare parts, inventory and ordering procedures to procure additional spare

    parts are to be readily available.

    xiii) Records of sustainment activities are to be readily available, refer to 7-A-14/17.7.1(b).

    xiv) A copy of the approved RCM Plan and ABS approval letter

    xv) A users manual for the Computerized Maintenance Management System

    19 Information

    For information on becoming an ABS External Specialist, please contact:

    American Bureau of Shipping

    16855 Northchase Drive

    Houston, TX 77060-6008

    Attn: External Specialist Coordinator

    Telephone: 281-877-5971

    Fax: 281-877-6012

    21 ABS Offices Responsible for PMP and RCM

    ABS Americas

    ABS Americas Division

    16855 Northchase Drive

    Houston, TX 77060-6008

    Attn: Manager, Houston SED Ship Machinery & Systems

  • Part 7 Rules for Survey After Construction Appendix Section 14 Surveys Based on Preventative Maintenance Techniques 7-A-14

    538 ABS RULES FOR SURVEY AFTER CONSTRUCTION . 2014

    ABS Europe

    ABS Europe Ltd.

    No. 1 Frying Pan Alley

    London, E1 7HR, United Kingdom

    Attn: Manager, Engineering

    ABS Pacific

    ABS Pacific Division

    Urban Square Yokohama

    4th/9th Floor

    1-1 Sakae-Cho

    Kanagawa-Ku

    Yokohama 221-0052, Japan

    Attn: Manager, Engineering Services, Machinery, Electrical & Control Systems

    ABS Greater China

    ABS Greater China Division

    5th Floor

    Silver Tower

    No. 85 Taoyuan Road

    Luwan District

    Shanghai, 200021 P.R. China

    Attn: Manager, Engineering Services