Numerical Study on Drying Shrinkage of Concrete Affected ...
PROVISIONS AGAINST THERMAL AND DRYING ...concrack5/PPT-PDF/General Presentation...DRYING SHRINKAGE...
-
Upload
nguyenngoc -
Category
Documents
-
view
223 -
download
1
Transcript of PROVISIONS AGAINST THERMAL AND DRYING ...concrack5/PPT-PDF/General Presentation...DRYING SHRINKAGE...
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 1
PROVISIONS AGAINST THERMAL AND DRYING SHRINKAGE CRACKING IN CONSTRUCTION OF PRESTRESSED
CONCRETE BRIDGE
K. Koroyasu
N. Kiyotaka
S. Nojima
Shimizu Corporation, JAPAN
Shimizu Corporation, JAPAN
Central Nippon Expressway, JAPAN
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 2
AGENDA
1.Introduction & Summary of Construction
2.Provisions for Thermal Cracking
3. ( Provisions for Drying Shrinkage Cracking )
4.Conclusions
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 3
Prestressed concrete bridge
In winter, the lowest temperature < 0°C
During the in-service period, the de-icing agent is planed to be used.
If the concrete structure has some cracks, the accelerated concrete deterioration becomes an issue.
Technical challenges was to control the early age cracking.
Introduction & Summary of Construction
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 4
Construction Outline
[Unit: m]
Type: 5 and 9 span of continuous PC box-girder bridgesErection method: Cantilever, Fixed falsework
Introduction & Summary of Construction
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 5
Side Closure
6.473
Cantilever
35.000
Column Carital
12.000
Cantilever
35.000
Closure
2.962
3.500
Cantilever Erection
Typical longitudinal section
Typical cross sections2.0252.325 3.0502.850
5.500
10.250 10.250
2.2252.325 2.8502.850In the Spans
Introduction & Summary of Construction
Column Capital
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 6
Introduction & Summary of Construction
This report explains the controlling methodsof the early age cracking that had beenadopted for the bridge construction of thecantilever erection.
Contents of this report
The early age cracking: Thermal cracking ( and Drying shrinkage cracking )
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 7
Requirements and Constraints
Targets of Thermal Crack Control(Minimum Limit Values of Thermal Cracking Index)
3D-FE Analysis for Initial Construction
Verification(Satisfy the Limit Values?)
Yes
Consideration of Additional Provisions
No
Standard Construction Methods and Material
Construction
First
Provisions for Thermal CrackingObjective
Flow diagram of verification (Ordinary)
Additional verification
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 8
Verification(Satisfy the Limit Values?)
Yes
Consideration of Additional Provisions
Confirmation of Each Matter Value for Property
No
First Construction
Thermal Fitting Analysis
3D-FE Analysis for the Following Constructions
Verification(Satisfy the Limit Values?)
Yes
Consideration of Additional Provisions
No
Remaining Constructions to Follow
Measurement of Concrete Temperature
Provisions for Thermal CrackingObjective
Flow diagram of verification (This Construction)
Additional verification
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 9
Objective
Provisions for Thermal Cracking
PartMinimum
limit values ofcracking index
Rough indication ofcracking index in [1]
Upper slab,Bridge end 1.75
When thermal cracking is required to be prevented
(Thermal cracking probability: 5%)
Under slab,Web 1.45
When thermal cracking is required to be limited as much as possible
(Thermal cracking probability: 25%)
Target values of thermal cracking index
[1]: Standard Specification for Concrete Structures -2007
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 10
Part Change of cement type
Expansive additive
Insulated curing
Concrete cooling
Column capital
1st lift ○ ○ ○
2nd lift ○ ○
Cantilever ○ ○
Closure ○ ○ ○
Side closure
1st lift ○ ○
2nd lift ○ ○ ○
List of provisions against thermal cracking
Provisions for Thermal CrackingObjective
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 11
Provisions for Thermal Cracking
Part Original cement type ModificationColumn capital HPC*1 MPC*2
Cantilever HPC*1 OPC*3
Closure HPC*1 OPC*3+EX*4
Side closure
1st lift HPC*1 OPC*3
2nd lift HPC*1 OPC*3+EX*4
*1: High-early-strength Portland Cement (HPC)*2: Moderate-heat Portland Cement (MPC)*3: Ordinary Portland Cement (OPC)*4: Expansive Additive (EX)
Different types of binders for each part
Cement type and Expansive additive
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 12
Provisions for Thermal Cracking
Part Method of curing Period
Bridge face(In the spans)
Wet mat and Insulated mat
From casting to the assuranceage of strength
Bridge face(On the piers)
Wet mat and Insulated mat
From casting to the assuranceage of strength(The time when the insulatedmat was installed after thetemperature inside theconcrete reached the peak)
Types of insulated curing
Insulated curing
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 13
Provisions for Thermal CrackingCooling concrete< Cooling concrete with liquid nitrogen >
Agitator–bodyTruck
Tank lorry withliquid nitrogen
Jet nozzle Scaffolding for jet
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 14
Provisions for Thermal Cracking
Part Maximum limit concrete temperature at the casting
Management temperature after injection
1st lift 30°C 29°C
2nd lift 26°C 25°C
Management temperature of cooling< Cooling concrete with liquid nitrogen >Cooling concrete
Quantity of LN2 necessary to reduce concrete of1m3 by 1 °C was 14.9 kg/m3°C
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 15
Fan
Duct
Deflection tube Branched duct
Provisions for Thermal Cracking
< Air-cooling with the use of deflection tube >Cooling concrete
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 16
Case Conditions of analysis model
1 Standard construction only with OPC
2 Case 1 with MPC
3 Case 2 with insulated curing
4 Case 3 with cooling with LN2 and air-cooling
Provisions for Thermal CrackingEffect of provisions
Cases of 3D-FE analysis in advancefor the column capital part
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 17
Provisions for Thermal CrackingEffect of provisions< Case 1 > < Case 2 >
Standard constructiononly with OPC
Case 1 with MPC
Target values2nd lift : 1.751st lift : 1.45
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 18
Provisions for Thermal CrackingEffect of provisions< Case 3 > < Case 4 >
Case 2 with insulated curing Case 3 with LN2-coolingand air-cooling
Target values2nd lift : 1.751st lift : 1.45
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 19
Provisions for Thermal CrackingEffect of provisions
Result of thermal analysis (Case 4)
YesFirst Construction
Thermal Fitting Analysis
Yes
No
Remaining Constructions to Follow
Confirmation of EachMatter Value for Property
Measurement of Concrete Temperature
No
3D-FE Analysis for Initial Construction
Verification(Satisfy the Limit Values?)
Consideration ofAdditional Provisions
Consideration ofAdditional Provisions
Verification(Satisfy the Limit Values?)
3D-FE Analysis for the RemainingConstructions to Follow
: Measurement point
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 20
0
10
20
30
40
50
60
70
0 1 2 3 4Tempreature inside concrete(℃
)
(Day)
Prior analysis
Measured value
Fitting analysis0
10
20
30
40
50
60
70
0 1 2 3 4Tempreature inside concrete(℃
)(Day)
Prior analysis
Measured value
Fitting analysis
Provisions for Thermal CrackingEffect of provisions
< Effect of cooling with LN2 > < Effect of air-cooling >
JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan 21
Conclusions
It was confirmed that the provisions against the thermalcracking were effective.
It was confirmed that the provision to the cement type withless total heat generation due to the hydration reactionswas effective especially in the 1st lift.And reducing temperature of concrete such as cooling waseffective in the 2nd lift for controlling the thermal crack atthe column capital.The values of thermal properties calculated after the fittinganalysis were almost similar to one of the prior verifications.