FINAL REPORT Report Submitted to the World Bank, Colombo Amal S. Kumarage University of Moratuwa Sri Lanka [email protected] 20th May 2009
i
Contents
1 Provincial Profile ................................................................................................................. 1-1
1.1 Geographic and Demographic ....................................................................................... 1-1
1.1.1 Western Province ................................................................................................... 1-1
1.1.2 Uva Province .......................................................................................................... 1-2
1.2 Socio-economic ............................................................................................................. 1-3
1.2.1 Western Province ................................................................................................... 1-3
1.2.2 Uva Province .......................................................................................................... 1-4
1.3 Road Sector Classification & Institutional Arrangement .............................................. 1-5
1.3.1 National Roads ....................................................................................................... 1-6
1.3.2 Provincial Roads .................................................................................................... 1-6
1.3.3 Local Authority Roads: .......................................................................................... 1-7
1.3.4 Roads maintained by other Institutions: ................................................................ 1-7
1.3.5 Roads not maintained by any Institution: .............................................................. 1-7
1.4 Provincial Road Network .............................................................................................. 1-8
1.4.1 Western Province ................................................................................................... 1-8
1.4.2 Uva Province ........................................................................................................ 1-12
1.5 Vehicle Fleet & Traffic Levels.................................................................................... 1-16
1.5.1 Western Province ................................................................................................. 1-16
1.5.2 Uva Province ........................................................................................................ 1-17
1.6 Road Transport Regulation and Industry .................................................................... 1-18
1.6.1 Western Province ................................................................................................. 1-18
1.6.2 Uva Province ........................................................................................................ 1-19
2 Organizational Structure of Road Sector Agencies ............................................................. 2-1
2.1 Road Development Authority ....................................................................................... 2-1
2.1.1 Structure and Execution Procedures ...................................................................... 2-1
2.1.2 Capacity ................................................................................................................. 2-6
2.2 Provincial Road Development Authority-Western Province ........................................ 2-6
2.2.1 Structure and Execution Procedures ...................................................................... 2-6
2.2.2 Capacity ................................................................................................................. 2-8
2.3 Provincial Road Development Department-Uva Province ........................................... 2-8
2.3.1 Structure and Execution Procedures ...................................................................... 2-8
ii
2.3.2 Capacity ............................................................................................................... 2-11
2.4 Local Governments ..................................................................................................... 2-12
2.4.1 Structure and Execution Procedures .................................................................... 2-12
2.4.2 Capacity ............................................................................................................... 2-13
3 Sources and Procedures of Funding Roads .......................................................................... 2-1
3.1 National Roads .............................................................................................................. 3-3
3.2 Provincial Roads ........................................................................................................... 3-6
3.2.1 Sources & Procedures of Maintenance Funding .................................................... 3-6
3.2.2 Sources & Procedures of Capital Funding ............................................................. 3-7
3.3 Local Authority Roads ................................................................................................ 3-10
3.3.1 Sources and Procedures of Capital Funding ........................................................ 3-10
3.3.2 Sources and Procedures of Maintenance Funding ............................................... 3-13
4 Capital Expenditure for Roads (2004-2007) ........................................................................ 4-1
4.1 National Roads .............................................................................................................. 4-1
4.1.1 Western Province ................................................................................................... 4-1
4.1.2 Uva Province .......................................................................................................... 4-3
4.2 Provincial Roads ........................................................................................................... 4-4
4.2.1 Western Province ................................................................................................... 4-5
4.2.2 Uva Province .......................................................................................................... 4-7
4.3 Local Authority Roads .................................................................................................. 4-8
4.3.1 Western Province ................................................................................................... 4-8
4.3.2 Uva Province ........................................................................................................ 4-12
5 Maintenance Expenditure for Roads (2004-2007) ............................................................... 5-1
5.1 National Roads .............................................................................................................. 5-1
5.1.1 Western Province ................................................................................................... 5-1
5.1.2 Uva Province .......................................................................................................... 5-2
5.2 Provincial Roads ........................................................................................................... 5-2
5.2.1 Western Province ................................................................................................... 5-3
5.2.2 Uva Province .......................................................................................................... 5-4
5.3 Local Authority Roads .................................................................................................. 5-5
5.3.1 Western Province ................................................................................................... 5-5
5.3.2 Uva Province .......................................................................................................... 5-9
6 Analysis of Expenditure ....................................................................................................... 6-1
6.1 Trends (2004-2007) ....................................................................................................... 6-1
iii
6.2 Analysis of Maintenance Expenditure .......................................................................... 6-3
6.2.1 National Roads ....................................................................................................... 6-3
6.2.2 Provincial Roads .................................................................................................... 6-4
6.2.3 Local Authority Roads ........................................................................................... 6-5
6.3 Analysis of Capital Expenditure ................................................................................... 6-6
6.3.1 National Roads ....................................................................................................... 6-6
6.3.2 Provincial Roads .................................................................................................... 6-6
6.3.3 Local Authority Road ............................................................................................ 6-7
iv
List of Tables
Table 1-1: Geographic and Demographic Details of Western Province___________________ 1-2
Table 1-2: Geographic and Demographic Details of Uva Province ______________________ 1-3
Table 1-3: Socio-economic Details of Western Province ______________________________ 1-4
Table 1-4: Socio-economic Details of Uva Province _________________________________ 1-5
Table 1-5: Road Length (kms) 2001 ______________________________________________ 1-6
Table 1-5: Road Network in Western Province _____________________________________ 1-8
Table 1-6: Extent of National Road Network in Western Province ______________________ 1-8
Table 1-7: Extent and Type of Roads in Western Province ___________________________ 1-11
Table 1-8: Extent and Type of Local Authority in Western Province ___________________ 1-12
Table 1-9: Road Network in Uva Province________________________________________ 1-12
Table 1-10: Extent of National Road Network in Uva Province _______________________ 1-13
Table 1-11: Condition of Roads in Uva Province ___________________________________ 1-15
Table 1-12: Extent, Type and Condition of Urban Roads in Uva Province _______________ 1-16
Table 1-13: Vehicle Fleet in Western Province (2007) ______________________________ 1-16
Table 1-14: Vehicle Fleet in Uva Province (2007) __________________________________ 1-17
Table 2-1: Road Sector Agencies in Sri Lanka ______________________________________ 2-1
Table 2-2: Institutional Capacity of Road Development Authority, Western Province _______ 2-8
Table 2-3: Institutional Capacity of Provincial Road Development Department of UP _____ 2-11
Table 3-1: Head of Ministry of Highways & Road Development, 2008 Budget (SLR mn) ___ 3-3
Table 4-1: Financing of Improvement & Widening of National Roads and Bridges _________ 4-1
Table 4-2: Financing of Expressway Development Program-WP _______________________ 4-2
Table 4-3: Financing of National Roads under Highway Development Program-WP _______ 4-2
Table 4-4: STAART funding of National Roads in Western Province ___________________ 4-3
Table 4-5: Financing of the Improvement & Widening of National Roads and Bridges ______ 4-3
Table 4-6: Financing of National Roads under Highway Development Program ___________ 4-4
Table 4-7: Utilization of PSDG-Provincial Roads, Western Province ____________________ 4-5
Table 4-8: Utilization of Other Central Government Capital Funds, Western Province ______ 4-5
Table 4-9: Utilization of Provincial Council Capital Funds, Western Province_____________ 4-6
Table 4-10: Utilization of Tsunami Affected Road Rehabilitation Funds, Western Province __ 4-6
Table 4-11: Utilization of Funds under RSDP, Western Province ______________________ 4-7
Table 4-12: Utilization of PSDG-Provincial Road, Uva Province _______________________ 4-8
Table 4-13: Utilization of PSDG-Local Government Roads, Western Province ____________ 4-9
Table 4-14: Maga Neguma Investment for Rural Roads in Western Province ____________ 4-10
Table 4-15: Financing under Maga Neguma for the Rural Road in Gampaha District, 2007 _ 4-11
Table 4-16: Gama Neguma Investment for Western Province, 2008 ____________________ 4-12
Table 4-17: Utilization of PSDG-Local Government Roads, Uva Province ______________ 4-12
Table 4-18: PSDG Investment in Local Governments, Uva Province ___________________ 4-13
Table 4-19: Local Road Financing through DCB for Badulla District, 2008 ______________ 4-14
Table 4-20: Local Road Financing through DCB for Badulla District, 2008 ______________ 4-14
Table 4-21: Local Road Financing through DCB for Uva Province, 2008 _______________ 4-15
Table 4-22: Maga Neguma Investment for Rural Roads in Uva Province ________________ 4-16
Table 4-23: Financing under Maga Neguma for the Rural Road in Badulla District, 2007 __ 4-17
Table 4-24: Gama Neguma Investment for Uva Province, 2008 _______________________ 4-18
v
Table 4-25: Investment under RSAP for Pilot Projects in Uva Province, 2008 ____________ 4-18
Table 4-26: Capital Expenditure on National Roads vs GDP in WP ____________________ 4-19
Table 4-27: Capital Expenditure on Provincial Roads vs GDP in WP ___________________ 4-19
Table 4-28: Capital Expenditure on National Roads vs GDP in UP ____________________ 4-20
Table 4-29: Capital Expenditure on Provincial Roads vs GDP in UP ___________________ 4-20
Table 5-1: Periodic and Routine Maintenance of National Roads (RMTF), WP ____________ 5-1
Table 5-2: Maintenance of roads rehabilitated under ADB assistance ____________________ 5-1
Table 5-3: Maintenance of Bridges on National Roads (RMTF), WP ____________________ 5-2
Table 5-4: Periodic and Routine Maintenance of National Roads (RMTF), UP ____________ 5-2
Table 5-5: Maintenance of Bridges on National Roads (RMTF), UP ____________________ 5-2
Table 5-6: Utilization of Road Sector Maintenance Funds, Western Province _____________ 5-3
Table 5-7: Recurrent Expenditure of PRDD, Uva Province, 2007 _______________________ 5-4
Table 5-8: Utilization of Road Sector Maintenance Funds, Uva Province_________________ 5-4
Table 5-9: Type and Condition of Roads in CMC ___________________________________ 5-5
Table 5-10: Colombo Municipal Council Road Sector allocation _______________________ 5-6
Table 5-11 : Road Maintenance Cost, Dehiwala-Mt. Lavinia Municipal Council ___________ 5-7
Table 5-12: Road Maintenance Cost, Horana Urban Council __________________________ 5-7
Table 5-14: Road Maintenance Cost, Minuwangoda Urban Council _____________________ 5-8
Table 5-15: Road Maintenance Cost, Bulathsinghala Pradeshiya Sabha __________________ 5-8
Table 5-16: Head of Roads of Badulla Municipal Council Budget ______________________ 5-9
Table 5-17: Road Maintenance Cost, Haputale Urban Council ________________________ 5-10
Table 5-18: Road Maintenance Cost, Bandarawela Urban Council _____________________ 5-10
Table 5-19: Road Maintenance Cost, Passara Pradeshiya Sabha _______________________ 5-10
vi
List of Figures
Figure 1-1: National Road Network in Western Province ____________________________ 1-10
Figure 1-2: Provincial Road Network Condition-Western Province, 2007 _______________ 1-11
Figure 1-3: National Road Network in Uva Province _______________________________ 1-14
Figure 2-1: Organization chart of the RDA ________________________________________ 2-3
Figure 2-2: Organization chart of PRDA –Western Province __________________________ 2-7
Figure 2-3: Organizational Chart- Uva Provincial Road Development Department ________ 2-10
Figure 2-4: Organization Chart of Badulla Municipal Council ________________________ 2-15
Figure 2-5: Organization Chart of Colombo Municipal Council _______________________ 2-16
Figure 2-6: Organization Chart of Minuwangoda Urban Council ______________________ 2-17
Figure 2-7: Organization Chart of Divulapitiya Pradeshiya Sabha _____________________ 2-18
Figure 3-1: Procedure of Provincial Road Financing, 2008 ____________________________ 3-9
1-1
1 Provincial Profile
1.1 Geographic and Demographic
1.1.1 Western Province
The Western Province (WP), along the western seaboard of Sri Lanka is bordered by the
Sothern, North Western and Sabaragamuwa provinces. It has three administrative districts i.e.
Colombo, Gampaha and Kalutara and 33 divisional secretariats. Out of Sri Lankan’s urban
population, 54.6% reside in Colombo district, while Gampaha and Kalutara accounts for 14.6%
and 10.6% urban population. Colombo district is considered to be the most urbanized district in
Sri Lanka, while the other two districts carry higher percentage of rural population. Colombo city
is considered to be the centre of the economy and hence the busiest city in Sri Lanka.
Government offices, private offices, factories, hospitals, hotels, schools and the harbor located
within the Colombo city generates higher travel demand towards the city core.
Since the province is located in the low-country wet
zone, it experiences between 1,500 to 2,000 mm of
annual rainfall, most of which can be expected to occur
during the north-west monsoon period from May to
September. Generally a flat terrain prevails across most
parts of the province. The province is considered an
agricultural based rural area though it resides higher
urban population.
The Western Province extends over 3,684 sq km
(5.62% of the land surface of Sri Lanka) with a
population of 5,381,197 (28.67% of the country) thus
becoming the smallest in terms of the area and the
highest in terms of the population leading to the highest
population density of 1460.7 persons/sq km among Sri
Lanka's nine provinces. Provincial ethnic composition
is made up of 84.2% Sinhalese, 7.2% Tamils, 7.0% Moor and others. Its religious profile makes
it predominantly 73.3% Buddhist, 5.1% Hindu with 8.2% Islam and others. Table 1.1
summarizes the geographic and demographic profile of the province.
1-2
Table 1-1: Geographic and Demographic Details of Western Province1
Feature Western Island-wide
or % of Island
Area (sq km) 3,684 65,610
Road Density(km/sq km) 4.01 1.5
Population,2001 (mn) 5.381 18.750
Population Density,2001 (inhab./sq km) 1460.7 296
Ethnic
Composition, 2001
(%)
Sinhalese 84.2 82.0
Tamils 7.2 9.4
Moors 7.0 7.9
Others 1.6 0.7
Religious
Composition, 2001
(%)
Buddhists 73.3 76.7
Hindu 5.1 7.8
Islam 8.2 8.5
Other 3.4 7.0
1.1.2 Uva Province
The Uva Province (UP), one of the country’s land-locked provinces is bordered by the Eastern,
Southern, Sabaragamuwa and Central provinces. The province is divided into two districts and
26 Divisional Secretariat Divisions for administrative purposes. The two districts namely Badulla
and Monaragala have generally different geographical
features especially with respect to terrain and
livelihood. Rolling or mountainous terrain conditions
are visible in most parts of Badulla district while flat
or rolling terrain prevails within Monaragala District.
Covering the south eastern parts of the central
mountains and surrounding plains, the Uva province
offer a variety of diverse attractions to a visitor.
Dunhinda waterfalls, Diyaluma Falls, Rawana Falls,
the Yala National Park (lying partly in the Southern
and Eastern Provinces) and Gal Oya National Park
(lying partly in the Eastern Province). Two of the
country’s major waterways namely the Mahaweli and
Menik Ganga (rivers) and the huge Senanayake
Samudraya and Maduru Oya Reservoirs both used for
agricultural irrigation are also located within the
province.
1 Source: Department of Census & Statistics, 2001 census
1-3
Two different weather conditions are observable in the two districts. Monaragala district is in the
dry zone and Badulla district in the wet zone.
The Uva Province extends over 8,488 sq km (12.92% of the land surface of Sri Lanka) with a
population of 1,177,358 (6.3% of the country) thus becoming the 4th largest in terms of the area
but the 2nd lowest in terms of the population among Sri Lanka's nine provinces. The province
has a comparatively lower population density at 138.7 persons/sq km. Given its central and land
locked nature, its dependence on land transport is extremely high and road density is about 0.9
km/sq km. Provincial ethnic composition is made up of 79.9% Sinhalese, 15.8% Tamils, 4.0%
Moor and others. Its religious profile makes it predominantly 79.6% Buddhist, 14.4% Hindu
with 4.2% Islam and others. Table 1-2 summarizes the geographic and demographic profile of
the province.
Table 1-2: Geographic and Demographic Details of Uva Province2
Feature Uva Island-wide
or % of Island
Area (sq km) 8,488 65,610
Road Density(km/sq km) 0.89 1.5
Population,2001 (mn) 1.177 18.750
Population Density,2001 (inhab./sq km) 138 296
Ethnic
Composition, 2001
(%)
Sinhalese 79.9 82.0
Tamils 15.8 9.4
Moors 4.0 7.9
Others 0.3 0.7
Religious
Composition, 2001
(%)
Buddhists 79.6 76.7
Hindu 14.4 7.8
Islam 4.2 8.5
Other 1.8 7.0
1.2 Socio-economic
1.2.1 Western Province
The Western Province is considered to be the most developed province in the country.
Comparisons of provincial and national level basic socio economic parameters in Table 1-3
clearly illustrate the issue. In this respect the lowest poverty head count index, highest per capita
incomes and lower unemployment rate should be noted as being among the relevant indicators.
2 Source: Department of Census & Statistics, 2001 census
1-4
Table 1-3: Socio-economic Details of Western Province3
Feature Western Island-wide
or % of Island
GDP (Rs Mn), 2007 1,732,279 48.4% (% national)
GDP Growth % 17.7 21.7
Per capita income (SLR/year) ,2007 303,536 178,783
Poverty Head Count Index,2007 8.2% 15.2%
Unemployment Rate, 2006 8.1% 8.9%
Primary Industries Manufacturing,
Agriculture
(Rubber, rice and
food crops),
Livestock
Manufacturing,
Plantation( Tea, rubber,
coconut), tourism
Western province records the Lowest Poverty Head Count Index in Sri Lanka (statistics for
Northern Province is not available). Even though it is reported as 8.2 %, which is approximately
half of the national average of 15.2%, it still translates to around 441,000 people falling below
the poverty line which in fact exceeds the actual number of poor in Uva province even though
Uva has a much higher index. Western provincial share of the national GDP is around 48.4% and
has recorded the highest per capita income of Rs 303,536 (approx USD 2,500) in 2007. But the
rate of unemployment and hence the unemployed population is still higher when compared to
other provinces. This indicates that though Western province has reached a certain level of
economic development, it is still to be developed in social aspects.
1.2.2 Uva Province
The Uva Province is one of the least developed provinces in the country. This is well illustrated
in Table 1-4 where some of the basic socio economic parameters are given and compared to
national levels. In this respect the higher poverty head count index, lower per capita incomes and
higher unemployment rate should be noted as being among the relevant indicators.
3 Source: Central Bank, Sri Lanka
1-5
Table 1-4: Socio-economic Details of Uva Province4
Feature Uva Island-wide
or % of Island
GDP (Rs Mn), 2007 160,747 4.5% (% national)
GDP Growth % 28.2 21.7
Per capita income (SLR/year) ,2007 126,076 178,783
Poverty Head Count Index,2007 27% 15.2%
Unemployment Rate, 2006 8.1% 8.9%
Primary Industries Agriculture (Tea,
forests, rice and
food crops),
Livestock
Manufacturing,
Plantation( Tea, rubber,
coconut), tourism
Uva province records the highest Poverty Head Count Index in Sri Lanka (statistics for Northern
Province is not available). It is reported as 27.0% and even though lower than previous years it is
still approximately double the national average of 15.2%, which translates to around 346,000
people still below the poverty line. Uva provincial share of the national GDP is around 4.5% and
has recorded a per capita income of Rs 126,076 (approx USD 1,200) in 2007. Uva Province has
reached the 4th position with respect to per capita income which is an improvement from
previous years. It also has however recorded the 2nd highest GDP growth rate in Sri Lanka.GDP.5
This shows that the province is in the upward trend of economic development though it is
presently below average.
1.3 Road Sector Classification & Institutional Arrangement
The road network in Sri Lanka is made up of several types of roads classified according to their
functionality and management. There is no formally accepted classification system for Sri Lanka.
The following classification and notation will be followed in this report:
• National Roads
• Provincial Roads
• Urban Roads
• Rural Roads
This classification is based on the different tiers of government in Sri Lanka i.e; national,
provincial and local. The local governments are further identified as urban and rural local
authorities.
Table 1-5 gives the inventoried road length in the Road Sector Masterplan. However, there are
quite a significant number of rural roads which have not been inventoried. Moreover, this does
4 Source: Central Bank, Sri Lanka 5 Central Bank of Sri Lanka, Provincial GDP-2007
1-6
not include all the roads managed by other government institutes such as Irrigation Department,
Wild Life Department, Forest Department and so on, which are also used as thoroughfares, but
are not listed under a road agency. Moreover these lengths have changed since 2001. For
example, the road length given for WP as 14,783 km is presently reported as 15,409 km, while in
UP, the road length of 7,433 km has changed to 7,339 possibly from remeasuring.
Table 1-5: Road Length (kms) 20016
1.3.1 National Roads
These are roads that are presently managed by the Road Development Authority (RDA) and
constitute the roads classified as A & B Class. Such roads are generally those that are considered
as part of the national road network or those that provide access to places of national importance
etc. Roads that belong to the provincial authorities as well as agencies such as the Mahaweli
Authority, Municipal Councils are periodically gazetted and added to the national network. The
national roads in the Uva Province are maintained by the RDA through its 5 Executive
Engineering divisions namely the Badulla, Bandarawela, Mahiyangana, Monaragala and Bibile
divisions.
1.3.2 Provincial Roads
These are roads that were classified as C, D and E class when the Provincial Councils were
established in 1989 under the 13th amendment to the Constitution. Usually, these are roads on
which a bus service operates and where such road is situated entirely within the province. These
roads are managed by the Provincial Council which has a statutory body referred to as the
Provincial Road Development Department (PRDD) through which it manages the road network.
At present, the PRDD is functioning through its 6 divisional offices located in Badulla,
Diyatalawa, Welimada, Mahiyangana, Monaragala and Wellawaya.
6 Source: Road Sector Master Plan, ADB, 2002
Province National Roads Provincial Roads Local Roads Total
Western 1,543 1,945 11,295 14,783 Southern 1,321 1,643 8,201 11,165
Sabaragamuwa 1,103 1,130 7,254 9,487
North Western 1,275 2,118 13,384 16,777
Central 1,707 2,433 8,283 12,423
North Central 1,160 1,771 5,485 8,416
Uva 1,147 1,839 4,447 7,433
North East 2,415 2,653 6,310 11,378
Total 11,671 15,532 64,659 91,862
1-7
1.3.3 Local Authority Roads:
These roads are classified under two categories of urban and local roads depending on the type of
local authority to which they belong.
Urban Roads: Roads that are not classified as national roads or provincial roads but are within
Municipal or Urban Council areas (MCs and UCs respectively) are identified in this report as
urban roads. At present there are only three Urban or Municipal councils in Uva, namely Badulla
MC, Haputale UC and Bandarawela UC.
Rural Roads: These are roads in rural areas maintained by the respective local authorities called
Pradeshiya Sabhas (Village Councils earlier). There are 22 Pradeshiya Sabhas in the province
namely Hali-ela, Mahiyangana, Meegahakivula, Passara, Sornathota, Bibile, Medagama, Buttala,
Monaragala, Wellawaya, Kandeketiya, Rideemaliadda, Madulla, Badalkumbura, Minipe,
Badulla, Haputale, Uva-Paranagama, Welimada, Ella, Haldummulla and Bandarawela. Unlike
the other roads described earlier, most of these roads are earth or gravel roads.
1.3.4 Roads maintained by other Institutions:
There are yet other roads which do not belong to or are maintained by any of the agencies which
are specifically charged with road maintenance such as those referred to above. These agencies
include the Mahaweli Development Authority, Irrigation Department, Forest Department, Wild
Life Conservation Department, Agrarian Services Department and Plantation Companies. The
length of these roads has also never been properly assessed, but is estimated at 4,500 km island
wide by the Road Sector Master Plan. Though these roads have not been gazetted as public
roads, public funds are used for their maintenance as these roads in most cases are used as public
thoroughfares and accessed by the rural population.
1.3.5 Roads not maintained by any Institution:
There is also an unspecified length of road in each province, which has not been included in the
road inventory of any government institution. These are usually roads serving a collection of
houses or very small villages, which have usually been constructed through self help schemes
(Shramadana) or funded by the decentralized votes of parliamentarians or provincial councilors,
but have not been officially handed over to the respective Pradeshiya Sabha. The extent of such
road length is not known.
1-8
1.4 Provincial Road Network
Road Network details are maintained by the agencies that are responsible for managing
respective road network hierarchy. But details of road type and road length, and condition of
roads at local government level, (i.e. of class E and unclassified roads) especially in the Uva
Province do not exist in general. Even when they do, they cannot be accepted as being accurate.
There is however now an initiative under a program to be implemented by the Provincial
Commissioner of Local Government in Uva to develop a road inventory for each local
government institution with the assistance of the World Bank. Most of Western Province Local
Governments maintains record of their network though accuracy of condition data is suspect.
Section 1.4.1 and 1.4.2 illustrate the extent, type and condition of each provincial road categories
in both these provinces separately.
1.4.1 Western Province
The total road network in WP is comparatively larger when compared to other provinces. Table
1-5 summarizes certain important details pertaining to the road network in the Western Province.
Table 1-6: Road Network in Western Province
Feature
National
Roads
Provincial
Roads
Local
Authority
Roads
Total
Roads
Length (km)
Western 1,511 1,975 11,923 15,409
Island wide 11,671 15,532 64,659 91,862
% 12.9 12.7 18.4 16.8
Road Density(km/km2) Western 0.41 0.54 3.24 4.18
Island wide 0.18 0.24 0.99 1.40
Road Length per Capita
(km/1000pop)
Western 0.28 0.37 2.22 2.86
Island wide 0.65 0.86 3.60 5.11
1.4.1.1 National Road
The length of National Roads maintained by the RDA in the Western Province is estimated as
1,510.8 km of which 254.59 km are A Class roads and 1256.2 km of B Class Roads. Table 1-6
and Figure 1-1 provide the details of the National Road Network in Western Province. Some
roads at the top of the hierarchy of B class roads in terms of traffic levels have now been called
AB Class in a new classification adopted by the RDA, which also refers to A class roads as AA
Class.
Table 1-7: Extent of National Road Network in Western Province
Road Division Total
1-9
Class
Colo
mb
o
Avissa
wella
Gam
pah
a
Neg
om
bo
Nitta
mb
uw
a
Kalu
tara
Agala
watta
AA 19.58 51.49 41.05 41.83 22.05 55.91 22.68 254.59
AB 29.37 9.83 0.69 3.99 19.31 1.9 0 65.09
B 127.87 127.68 205.32 200.37 189.11 62.43 278.33 1191.11
Total 176.82 189 247.06 246.19 230.47 120.24 301.01 1510.79
Of the National Roads, around 73% of the length of roads in the province is less than standard 2
lanes, while 6% is 4-lane width or wider. The balance 21% of the road length falls within 2 to 4
lanes. The condition of these roads as measured by the International Road Roughness Index (IRI)
shows that less than 2% of the length of the network is in very good condition with an IRI of 2 or
less and 92% of the length is in poor condition with an IRI of 4 or more.7
7 Source: TransPlan Database, University of Moratuwa
1-10
Figure 1-1: National Road Network in Western Province
1-11
1.4.1.2 Provincial Roads
Length of the provincial road network in Western Province is 1,975 km, of which there are 227.8
km of recently surfaced Double Bitumen Surface Treated DBST roads.
Table 1-8: Extent and Type of Roads in Western Province8
Type of Road
Total Kms
Metalled and Tarred (single Lane 2 to 4 m) – “D” 1,126
Metalled and Tarred (intermediate lane 4 to 6 m) “C” 849
Total 1,975
As shown in Figure 1-2, at present around 31% of the provincial road network is termed to be in
poor condition. Only 15% of the network is in very good condition. However in general the
network is considered to be comparatively in satisfactory motorable condition.
Figure 1-2: Provincial Road Network Condition-Western Province, 2007
8 Source: Planning Division of Uva Provincial Council,2008
1-12
1.4.1.3 Local Authority Roads
It is estimated that there are 11,923 km administered by the different local governments (MC,
UCs and PS) in Western Province9. But the local authorities especially the Pradeshiya Sabhas, do
not maintain records of the condition of their road network. Hence an assessment of the
condition of the roads is not possible. Visual observation indicates that other than the larger
municipal councils such as Colombo all other municipal councils as well as urban councils are
not maintaining their roads on a regular basis. It is most likely that over 50% of the road length
may be considered to be in poor condition. In the case of Pradeshiya Sabhas this may be even
more with over 2/3rd or 3/4th of the road lengths being considered to be in poor condition.
Table 1-9: Extent and Type of Local Authority in Western Province10
Road Category Type Total
Mettaled/Tar Gravel
Municipal Council 1,407.57 286.00 1,693.57
Urban Council 852.87 289.20 1,142.07
Pradeshiya Sabha 2,909.97 6,177.34 9,086.90
Total 5,170.41 6,752.54 11,922.54
Table 1.8 shows the length of road under each level of local authority in the WP. It is seen that
most roads are managed by PSs and that over 2/3rd of such roads are gravel roads. Since these
statistics have been compiled, is is estimated that between 5-10% of these gravel roads now have
been concreted under the governments Gama Neguma village upliftment program.
1.4.2 Uva Province
The total road network in UP is comparatively smaller compared to other provinces of the
country. Table 1-9 summarize important details of the road network in the Uva Province.
Table 1-10: Road Network in Uva Province
Feature
National
Roads
Provincial
Roads
Local
Authority
Roads
Total
Roads
Length(km)
Uva 1,151 1,741 4,447 7,339
Island wide 11,671 15,532 64,659 91,862
% 9.9 11.2 6.9 8.0
Road Density(km/km2) Uva 0.14 0.21 0.53 0.88
Island wide 0.18 0.24 0.99 1.40
Road Length per Capita
(km/1000pop)
Uva 0.98 1.49 3.80 6.28
Island wide 0.65 0.86 3.60 5.11
9 Commissioner of Local Government, Western Province 10 Source: Commissioner of Local Government, Western Province,2005
1-13
It can be seen that Uva Province compared to the national statistics, has a lower road density
when measured in terms of road length per sq km while it has a higher road density when
measured in terms of road length per capita.
1.4.2.1 National Roads
The length of National Roads maintained by the RDA in the Uva Province is estimated as 1,151
km of which 443.57 km are AA Class roads and 25.31 km AB Class roads and 682.58 km B
Class Roads. Table 1-10 and Figure 1-3 provide the details of the National Road Network in Uva
Province.
Table 1-11: Extent of National Road Network in Uva Province
Road Class Division
Total Bandarawela Badulla Mahiyangana Monaragala Bibile
AA 154.81 16.24 69.38 102.1 101.04 443.57
AB 0.36 NA 23.8 1.15 NA 25.31
B 206.23 138.33 77.29 104.29 156.44 682.58
Total 361.4 154.57 170.47 207.54 257.48 1151.46
Of the National Roads, around 192 km of roads in the province are two lane or below, while 277
kms are 4 lane or above. The condition of these roads as measured by the International Road
Roughness Index (IRI) shows that 21 km of the network is of good standard with an IRI of 3 or
less and 1,153 km is in poor condition with an IRI of 4 or more.11
11 Source: TransPlan Database, University of Moratuwa
1-14
Figure 1-3: National Road Network in Uva Province
1-15
1.4.2.2 Provincial Roads
The provincially administered road network in UP is 1,741 km, of which there are 192 km of
recently surfaced DBST roads. The rest is made of metalled and tarred roads of which there are
179.8 km of 2 to 4 meter wide single lane roads and 1,369.2 km of metalled intermediate lane
roads that are 4 to 6 meter wide. Additionally the PC also intends to gazette another 50 km of
rural roads as provincial roads in the near future.
Unlike for national roads, there are no roughness measurements available for most provincial
roads. Only approximate estimates based on visual observations made by the engineers are
available for provincial roads. As shown in Table 1-11, at present, around 45% of the provincial
road network is termed to be in poor condition, which is higher than in WP. The only roads
which are still in good condition are the 192 km of DBST surfaced roads completed over the last
5 years under the ADB funded Road Sector Development Project (RSDP). Of the rest, only
around 175 km are termed as being in good condition.
Table 1-12: Condition of Roads in Uva Province12
Type of Road
Total Kms
% of Length by Present
Road Condition
Good Fair Poor
Metalled and Tarred (single Lane 2 to 4 m) – “D” 179.76 20% 30% 50%
Metalled and Tarred (intermediate lane 4 to 6 m) “C” 1,369.20 10% 30% 40%
DBST Surface (Single lane 4 to 6m) 192.00 100% - -
The ADB funded RSDP project also included the construction of 7 new bridges, 11 bridges that
were re-decked and the repair of 50 bridge & causeways. Thus only around 362 km or
approximately 20% of the road network is in maintainable standard or within the design life
period. At present there are no on-going projects on provincial roads for the re-construction or
major improvements to provincial roads within the province.
1.4.2.3 Local Authority Roads
It is estimated that there are 4,447 km administered by the different local governments (MC, UCs
and PS) in Uva Province13. As mentioned earlier, local authorities in rural areas, specifically the
PSs at present do not maintain records of the details of their respective road network. However in
the case of the urban road network the respective urban local authorities do keep records since
their networks are located within a relatively small geographic area.
12 Source: Planning Division of Uva Provincial Council,2008 13 Road Sector Master Plan, RDA, 2005
1-16
Table 1-13: Extent, Type and Condition of Urban Roads in Uva Province14
Local
Government
Length by type (km) % in
good
condition
Mettalled
& Tarred
Concrete Gravel
/Earth
Stairs Foot
paths
Total
Badulla MC 47.54 N/A 37.53 N/A 0.57 83.71 75%
Bandarawela UC 15.60 1.00 4.00 2.85 3.00 26.45 85%
Haputale UC 5.00 0.96 0.60 0.30 N/A 6.86 60%
Total 68.14 1.96 42.13 3.15 3.57 117.02
Since UP is predominantly a rural province, only around 117 km of roads maintained by urban
local authorities. The type of roads under each of the councils is given in Table 1-12. There are
no details or condition reports of the rural local authorities. Visual observations reveal that at
least 3/4th of such road length is gravel and that overall 2/3rd of the road lengths appear to be in
poor condition.
1.5 Vehicle Fleet & Traffic Levels
1.5.1 Western Province
WP has the highest number of registered motor vehicles in Sri Lanka. Of a total estimated
operational fleet of 2.2 million vehicles in 2007, it is noted that 967,097 or around 43.5 % of
vehicles are registered in WP. It is noted that approximately half of the fleet of vehicles in WP
are two-wheelers and three-wheelers. The motor cycle is becoming a popular mode of transport
due to its low cost and maneuverability even on roads with poor surface condition.
Table 1-14: Vehicle Fleet in Western Province (2007)15
Vehicle Type Fleet
WP % of National Fleet
Omnibuses 7,124 45.0
Private Coaches 12,096 48.2
Dual Purpose Vehicles 106,571 58.9
Private Cars 182,421 72.4
Land Vehicles 16,793 18.2
Goods Transport Vehicles 83,891 46.1
Motor Cycles 414,770 36.8
Three-wheelers 141,559 41.4
14 Source: Respective Municipal and Urban Councils 15 Source: Central Bank of Sri Lanka,2007
1-17
Others 1,872 32.6
Total 967,097 43.5
The truck roads of the national network such as A1, A2, A3, A4 close to the boundary of the
Colombo city carries traffic volumes of between 60,000 to 80,000 vehicles per day16. But the
volumes of traffic on these same roads are in the range of 15,000 to 20, 000 at the provincial
boundary. On provincial roads the traffic volumes are generally in the range 3,000 to 10,000 vpd
and for local authority roads it was found to be in most instances between 100 to 1,000 vpd. The
typical vehicle composition on national roads within the province is that around 65-70 % of
vehicles are four wheeled or larger. The typical average speeds on the national roads are between
15 km/hr within the city, to 40 km/hr away from the city while that of the provincial network are
in the range of 15 to 40 km/hr depending on the terrain and condition of road.
1.5.2 Uva Province
UP has the 2nd lowest number of registered motor vehicles in Sri Lanka. Of a total estimated
operational fleet of 2.2 million vehicles in 2007, it is noted that only 74,376 or around 3.3 % of
vehicles are registered in UP even though 6.5% of the population live here. Of these also only
around 24,000 vehicles are four wheeled vehicles or larger.
Table 1-15: Vehicle Fleet in Uva Province (2007)17
Vehicle Type
Fleet
UP % of
National
Fleet
Omnibuses 553 3.5
Private Coaches 1,014 4.0
Dual Purpose Vehicles 4,952 2.7
Private Cars 3,830 1.5
Land Vehicles 6,395 6.9
Goods Transport Vehicles 7,873 4.3
Motor Cycles 36,304 3.2
Three-wheelers 13,299 3.9
Others 156 2.7
Total 74,376 3.3
The roads in the national network within the UP carries traffic volumes of between 1,500 to
2,500 vehicles per day18. On provincial roads the traffic volumes are generally in the range of 16 TransPlan Traffic Estimation Model, University of Moratuwa, 2008 17 Source: Central Bank of Sri Lanka,2007
1-18
500 to 1,000 vpd and for local authority roads it was found to be in most instances between 100
to 200 vpd. The typical vehicle composition on national roads is that around 60 % of vehicles are
four wheeled or larger. The typical average speeds on the national roads are between 15 to 40
km/hr while that of the provincial network are in the range of 15 to 30 km/hr mostly depending
on terrain and condition of road.
1.6 Road Transport Regulation and Industry
The Provincial Councils were established in 1989 under the 13th Amendment to the Constitution.
Subsequent to the Council becoming operative, each province has set up two different agencies
to manage functions relating to road transport. In the both Provinces a Road Passenger Transport
Authority (RPTA) has been set up by statute to regularize the provision of omnibus transport
together with a Department of Motor Traffic to collect revenue licenses of the motor vehicles
registered within the province.
Trucking is deregulated and there are independent small scale operators most of whom have
other businesses. They usually provide different capacity vehicles ranging from 2 tonnes to multi
axle container flat beds. Rates are competitive.
The issue of annual revenue licenses for motor vehicles registered to addresses within the
province and the collection of such revenues is carried out by the Provincial Motor Traffic
Department. The department does not have legal authority to perform new registrations or
transfer of ownership of vehicles which is handled by the Commissioner of Motor Vehicles
under the Central Government.
1.6.1 Western Province
The RPTA of the Western Province is authorized to issue route permits for intra-provincial buses
and for regularizing bus transport within the province. Currently there are around 6.540 private
omnibuses operating with permits issued by the RPTA of the WP. In addition there are around
1,413 state owned buses belonging to the Sri Lanka Transport Board, which comes under the
Ministry of Transport of the Central Government which are not issued route permits but are also
operating within the province. Besides this there are another 865 buses issued with permits by
National Transport Commission for inter-provincial (long-distance) services starting from within
the province.
18 TransPlan Traffic Estimation Model, University of Moratuwa, 2008
1-19
The National Transport Commission provides financial reimbursements to 190 dedicated school
bus trips within the WP under the ‘Sisu Saeriya’ program. There are also a further 67 dedicated
rural bus services under the ‘Gami Saeriya’ program. Both programs are delivered through
certification of delivery and attainment of standards monitored by a local user committee. These
provide important connections between rural and town centres within a province. These services
are expected to be significantly increased this year.
Other vehicles operating within the province for fee or reward such as school vans, office vans,
and three wheelers or taxis are regulated in the WP, by Act No 3 of 2006 and by Gazette No
1518 of 2007. Three Wheelers of which there are nearly 141,559 vehicles registered within the
province, provides passenger services within town areas and in rural areas, especially where
regular public transport does not operate or after such services cease to operate in the evenings.
These are mostly unregulated except for insurance and annual licensing as motor vehicles.
The railway network also covers much of the WP. Similar to the road network which has nodal
centre in Colombo, all railway lines radiate from Colombo, this covering over 200 km within the
province. The railway carries around 210,000 passengers across the city boundary every day
which translates to around 13% of all passenger movements. Its contribution to freight transport
is much less at around 3%.
1.6.2 Uva Province
The UP RPTA has issued around 1,086 route permits for private omnibuses to operate within the
province. Sri Lanka Transport Board also has deployed approximately 584 buses for intra-
provincial passenger transportation purposes. In addition there are another 173 buses issued with
permits by National Transport Commission for inter-provincial (long-distance) services starting
from within the province.
The National Transport Commission provides financial reimbursements to 30 dedicated school
bus trips and 57 dedicated rural bus services in UP under the ‘Sisu Saeriya’ and Gami Saeriya
programs. Operational and supervision aspects of these services are same as in the Western
Province. Especially the Gami Saeriya service is expected to play a significant role in provinces
such as Uva in which higher percentage of rural and agricultural based population resides.
Other vehicles operating within the province for fee or reward such as school vans, office vans,
and three wheelers or taxis are regulated in the UP, by Act No 3 of 2006 and by Gazette No 1518
of 2007. Three Wheelers of which there are nearly 13,000 vehicles registered within the
province, provide passengers services within town areas and in rural areas, especially where
regular public transport does not operate or after such services cease to operate in the evenings.
These are mostly unregulated except for insurance and annual licensing as motor vehicles.
1-20
In the UP the railway operates only within the Badulla district. Railway is not a popular travel
medium among local passengers due to the difficulty of access and its small extent within the
province. But it is popular among travelers coming from Colombo since it passes scenic
surroundings along its journey. The railway currently operates four passenger trains between
Badulla and Colombo and two goods trains. In addition there are a few local passenger cum
goods trains operating.
2-1
2 Organizational Structure of Road Sector Agencies
The aim of this chapter is to discuss organizational structures & capacity issues related to the
agencies that are responsible for each category of roads within the province which were
introduced in Chapter 1. The following table provides a summary.
Table 2-1: Road Sector Agencies in Sri Lanka
Road Category Responsible Agency
National Roads Road Development Authority
Provincial Roads Provincial Road Development Authority (Western)
Provincial Road Development Department (Uva)
Local Authority Roads Respective Municipal Council, Urban Councils & Pradeshiya Sabhas
Other Roads Ministry of Nation Building & Estate Infrastructure
2.1 Road Development Authority
National Roads are presently managed by the Road Development Authority (RDA) which is a
statutory body under the Ministry of Highways and Road Development incorporated under the
RDA Act No.73 of 1981. The functions of the RDA were expanded in 1986 when it became the
successor to the then Department of Highways.
The RDA is the premier highway authority in the country and is responsible for the maintenance
and development of the National Highway Network, comprising of Trunk Roads (A Class- sub
categorized as AA and AB) and Main roads (B Class) It is also responsible for the planning,
designing and construction of new highways, bridges and expressways to augment the existing
network. The National Highway Network consists of 11,67119 km of roads and 4,429 bridges
(span of more than 3 m) as at the end of 2007.
2.1.1 Structure and Execution Procedures
The organizational structure of the RDA is designed to carry out its assigned functions in order
to achieve its goals and objectives. The management of the RDA is effected by a Board of
Management appointed by the Minister of Highways and Road Development. One of the members
is appointed as the Chairman of the Authority. The Board of Management is responsible to the
19 Road Sector Master Plan, 2005
2-2
Minister for the implementation of Government Policy regarding the development of the National
Highway Network in the country.
The organization under the Board of Management has the General Manager as the Chief
Executive Officer. The General Manager is assisted by 6 Additional General Managers & 14
Directors to carry out the various functions. In addition there are 10 Project Directors in charge
of various Project Management Units – mostly for foreign funded programs under the Ministry
of Highways & Road Development and are appended to the RDA through the Chairman.
2-3
Figure 2-1: Organization chart of the RDA
2-4
The organization has 14 functional divisions, namely for Maintenance Management &
Construction, Road Works, Engineering Service, Highway Design, Planning, Research &
Development, Mechanical, Training, Property Management & Revenue, Land Acquisition &
Resettlement, Legal, Finance, Administration and Internal Audit each headed by a Director.
Since August 2007 the management of the RDA appoints 4 Additional General Managers to
supervise the 11 Engineering sector divisions (excluding Finance, Administration and Internal
Audit) and another AGM for all the Project Management Units(PMUs).
Most of the foreign funded projects are handled by their respective PMUs under the Ministry of
Highways & Road Development. They maintain independent accounting units, and are directly
responsible to the Ministry of Highways & Road Development. The Annual Reports of these 10
PMU’s are prepared separately. These PMUs are identified as:
1. PMU of Asian Development Bank Projects
2. PMU of Japanese Aided Projects
3. PMU of Miscellaneous Foreign Aided Projects
4. PMU of the Southern Transport Development Project
5. PMU of the Outer Circular Highway Project
6. PMU of the Road Sector Development Project
7. PMU of the World Bank Funded Road Sector Assistance Project
8. PMU of the Road Project Preparatory Facility.
9. PMU of the Colombo-Katunayake Expressway
10. PMU of the Colombo-Kandy Alternative Highway project
In the execution of road maintenance and capital work of the national roads, the functionality of
the Maintenance Management & Construction and Work Divisions is considered to be the most
important. Moreover the provincial and regional offices of the RDA function under this division.
2.1.1.1 Maintenance Management and Construction Division
The Additional General Manager (AGM) & the Director (Maintenance Management &
Construction) directs and co-ordinates the work of the Provincial Directors with the assistance of
a Deputy Director. There are 10 Provincial Directors and each of them have two or three Chief
Engineers who are in charge of each administrative district. Each Chief Engineer is assisted by
two or three Executive Engineers depending on the kilometerage of roads in the Region.
2.1.1.2 Works Division
The works division handles the following items of work:
2-5
• Widening & Improvement of roads – this includes continuation work of the Small
Scale Infrastructure Rehabilitation and Upgrading Projects (SIRUP) in the year 2007.
The Projects in Ampara, Monaragala, Badulla and Hambantota districts which are
funded by Japan Bank for International Corporation (JBIC) under PPRD Projects
from April 2007 and the projects in all other Districts coming under Government of
Sri Lanka (GoSL) funding.
• Sri Lanka Tsunami Affected Area Recovery and Takeoff (STAART) Projects funded
by JBIC.
• Construction of Pedestrian Subways at Kurunegala, Maharagama & Kottawa, funded
by GoSL
• National Roads Improvement for Greater Dambulla Development Plan, funded by
GoSL
• Access Road Improvement - International Airport at Weeravila, funded by GoSL
• Construction of Flyovers in the City of Colombo and Suburbs, funded by GoSL
In addition its functions include:
• Co-coordinate all tendering and awarding of contracts of value more than Rs. 10.0
million based on tender documents prepared by Provincial Directors / Director
(Works)
• Formation of the formal contract documents for the above works.
• Providing advice / support & training to Provincial Directors on contract management
/ claim evaluation, time extension respectively.
• Provide support to General Manager in Contract Management.
2.1.1.3 Executive Engineers Offices
Periodic and Routine maintenance of the National Road network is carried out by Executive
Engineering (EE) offices established in each district under Maintenance Management and
Construction Division of the RDA.
In the UP there are 5 divisional Executive Engineer’s (EE) Offices located in Bandarawela,
Badulla, Mahiyangana, Bibile and Monaragala. In the WP, the RDA has set up EE divisions of
Colombo, Avissawella, Gampaha, Negombo, Nittambuwa, Kalutara and Agalawatta.
The primary functions of the divisional offices are the (a) maintenance of National Highways,
(b) maintenance of bridges on the National Highways, (c) light rehabilitation and minor
improvement of National Highways using domestic funds, (d) improvements to weak bridges
with local funds (e) rehabilitation and improvement of minor roads and bridges on request.
2-6
These EEs offices employ their own labour force and machinery for both routine and urgent
maintenance work. But for periodic maintenance work, contractors are selected for work in
package basis following government tender procedure.
2.1.2 Capacity
The RDA has in recent years obtained foreign assistance in strengthening its planning functions.
Some software such as the Road Maintenance Expenditure Control (RMEC) and HDM IV are
now available for costing and prioritizing of maintenance work carried out by the RDA. The
RDA is also acquiring detailed road inventory and road condition data. The RDA has the
technical human resources to carry out the road works but would need capacity enhancement in
several key areas including new techniques, project management, planning, road safety, traffic
management etc. Another short coming is that presently a significant portion of its human
resource is utilized in attending to emergency work on non-RDA roads (mostly rural roads).
Other than for maintenance, all project work is carried out through contractors.
2.2 Provincial Road Development Authority-Western Province
2.2.1 Structure and Execution Procedures
The Provincial Road Development Authority (PRDA) is headed by a Board of Directors, one of
whom is appointed as the Chairman. The Board is virtually an advisory body with the Chairman
assuming the role of the Chief Executive for the conduct of the affairs of the Authority.
The next in line is the General Manager (Super Grade) who is responsible for the execution of
the PRDA’s work program and for executing administrative control over the PRDA. Director-
Internal Auditor is responsible to the Chairman. There are 2 Additional General Managers for
Engineering and Finance under the General Manager (Super Grade) in addition to the 3 Directors
for Human Resource Management, Legal and Lands. The Additional General Manager
(Engineering) deals with operational functions of road works with the assistance of the 5
Engineering Directors positioned under him. Two of them handle operations in the South and
North regional works respectively, with a senior Executive Engineer and 5 Executive Engineers
placed under each of them. These Executive Engineers are placed in divisional offices in the
North and South regions and they are responsible for the execution of works at divisional level.
Director Engineering (Mechanical), Director Engineering (Planning Programming, Research &
Development) and Director Engineering (Designing & Special Projects) are the 3 other
Engineering Directors responsible to the Additional General Manager (Engineering). Each of
them is supported by engineering staff positioned under them. The Organization Chart of the
PRDD in WP is shown in Figure 2-2.
2-7
Figure 2-2: Organization chart of PRDA –Western Province
BOARD OF DIRECTORS
CHAIRMAN
GENERAL MANAGER (SUPPER GRADE)
ADDITIONAL GENERAL MANAGER
ENGINEERING (SPECIAL GRADE) ADDITIONAL GENERAL MANAGER
FINANCE (SPECIAL GRADE )
Director Engineering (Mechanical)
Mechanical Engineer
Mechanical Engineer
Mechanical Engineer
Director Engineering
Operation (North)
Director Engineering
Operation (South)
Senior Executive Engineer (Operation)
(North)
Executive Engineer (05 Nos)
Senior Executive Engineer (Operation)
(South)
Executive Engineer (05 Nos)
Director Engineering (Planning Programming & Research & Development)
Director Engineering (Designing & Special
Projects)
Planning , Programming &
Monitoring Engineer
Material Quality Control
Engineer
Contract Engineers
(As required)
Director Finance
Accountant 02 (Nos)
Director Human Resource
Management
Administration Officer
Director Legal
Director Lands
Director Internal Auditor
Support Technical Clerical Staff
Support Technical Clerical Staff
Support Technical and
Clerical Staff
Design and Document Engineer
Laboratory Manager
Material Technicians
Clerical Staff
Technical Officer,
Drafts Person Clerk, Typist
Technical Officer, Drafts
Persons,
Support Staff
Staff Assistant Accountant 2 Book Keeper Management
Assistant Clarical Staff
Staff Assistant Management
Assistant Clarical Staff
Audit Assistant
2-8
2.2.2 Capacity
Table 2-2 gives a summary of the institutional capacity which is available within the PRDA in WP.
Table 2-2: Institutional Capacity of Road Development Authority, Western Province
Availability/Requirement Present Issues
Personnel No direct labour force
Employees Cadre Available
Engineers 12 12
Technical Officers 70 70 Draughtsman 1 0 Clerical 71 70 Quantity Surveyor 0 0
-Presently, there are no vacancies available in technical grades. This is a significant issue compared to other provincial road agencies since they are failing to complete their technical cadre. Being an Authority, PRDA can offer a good salary for their staff. This would be the probable reason for keeping their cadre intact.
Plants & Equipments
• Maintain a Machinery Unit under a Director
• Several surveying and quality assurance equipment such as Thedolites, Levels, and other material testing laboratory equipment are available in adequate amounts.
- At present, machineries are hired when needed. But several small construction equipment, surveying instruments and laboratory equipment are available at the PRDA head office and its regional offices. Most of these were donated by the ADB at the end of the RSDP project.
Supporting Assets
• There are 40 Nos of personal computers
• Several design and planning software are being used.(RMMS, GIS etc)
• Office furniture and space are inadequate.
• Number of supporting assets such as photocopy machines, printers, roneo machines, type writersinadequate.
. -RSDP project furniture and computers were donated to the PRDA at the end of the project. - PRDA doesn’t possess a separate building for a head office with adequate space - Office vehicles for head office and regional offices are inadequate.
Contractor & Material Availability
- Local contractor availability and their capabilities are satisfactory.
- Transport and material cost are comparatively low compared to the other provinces of the country.
2.3 Provincial Road Development Department-Uva Province
The Provincial Road Development Department (PRDD) in the UP is responsible for the
construction, maintenance and administration of the provincial road network. It is under the
Ministry of Electricity, Provincial Roads and Co-operative Development.
2.3.1 Structure and Execution Procedures
Presently, the Road Development Department (RDD) of the Uva Province is headed by a
Director (Roads) who functions under the Deputy Chief Secretary (Engineering Services). Three
Chief Engineers, an Accountant and an Administrative Officer are placed under the Director with
2 Chief Engineers assigned for executing work in each of the districts, namely Badulla and
2-9
Monaragala and the other one assigned for budgeting, planning and designing of road works.
There are 6 Divisional Engineers attached to the Divisional Offices in Badulla, Diyatalawa,
Welimada, Mahiyangana, Monaragala and Wellawaya working under the respective District
Chief Engineers. The Organization Chart of the PRDD in UP is shown in Figure 2-3.
Routine Maintenance: is conducted by means of 3 km packages contracted to laborers who live
in close proximity to those locations. The contracts are for mostly manual work including
weeding, clearing of drains etc. Equipments such as mammotties and knives, axes required for
such maintenance activities are provided by the PRDD. They also inform the Executive Engineer
if there are minor repairs such as pot-hole corrections. In such a case the PRDD carries out such
work using its own staff. Emergency maintenance activities which are of a magnitude beyond the
individual contractor to deal with, are carried out by the PRDD itself.
Procedures followed in executing periodic maintenance, routine maintenance and road
rehabilitation in Uva province is different to other provinces.
Periodic Maintenance: Since specific funds are not available for periodic maintenance, there is
no such activity at present. But the PRDD has initiated a program called the “Premix Program”
to fund their periodic maintenance functions using province Specific Development Grant
(PSDG) which is intended for capital works. Manual Premix plants are established in every
regional office with the necessary funds for the program allocated through the PSDG. It should
be noted that with the very poor condition of roads in UP, the Premix Program is a measure
whereby the roads are kept in a basic level of motorability. However since most of these roads
have exceeded their design life such programs cannot be treated as periodic interventions.
Road Surface Overlaying & Purchasing Machinery: In addition to the Premix Program, the
PRDD uses the balance funds in PSDG for overlaying around 10 km of road surface per year.
This work can be considered an improvement and is in fact the only capital work carried out by
the PRDD. Moreover, 10% of PSDG (capital expenditure) is set apart for purchasing vehicles
and machinery needed for road works. The PRDD hands over the machinery it procures to the
Provincial Mechanical Engineering Division and hires them back when necessary at
comparatively low rates for their needs for which they get priority.
2-10
Figure 2-3: Organizational Chart- Uva Provincial Road Development Department
Director (Roads)
Accountant Administrative Officer CE-Monaragala CE-Budgeting, Planning & Design CE- Badulla
DE- Badulla Division
DE- Mahiyangana Division
DE- Welimada Division
DE- Diyatalawa Division
DE- Monaragala Division
DE- Wellawaya Division
CE- Chief Engineer
DE- Divisional Engineer
2-11
2.3.2 Capacity
Table 2-3 gives a summary of the institutional capacity available within the PRDD in UP.
Table 2-3: Institutional Capacity of Provincial Road Development Department of UP
Availability/Requirement Present Issues
Personnel
Employees Cadre Available
Engineers 11 9
Technical Officers 33 28
Draughtsman 10 10
Clerical 38 35
Quantity Surveyor - -
Computer Operator - -
-It can be seen that there are vacancies in most of the
technical grades. It is also noted that there are no
Quantity Surveyors or Computer Operators assigned
for the department. It is typical that they are unable
to fill these vacancies due to one of the following
reasons:
• Procedural constraints in recruiting applicable
personnel especially in the case of technical staff
recruitments.
• Inability to find suitably qualified staff
particularly since staff salaries are lower than
other government institutions such as RDA.
Plants &
Equipments
• Seven Premix Plants are available (one for
each division)
• No machinery in possession of the PRDD
-10% of PSDG (Capital Expenditure) is allocated for
vehicles/machinery needed for the road works.
PRDD hands over these machineries to the
Provincial Mechanical Engineering Division and
they hire these machinery at comparatively low rates
on PRDD requisitions.
-Department maintains premix plants which are
financially supported by the Finance Commission
under the premix program. These plants are
established in all six divisions and each plant is
producing 5 cubes of premix per week.
Supporting
Assets
• 20 Nos of personal computers are available
but there are no design nor planning software.
• Office furniture and space is inadequate.
• There are several vehicles for office use.
-Since there is no design office established yet, there
are no trained personnel to run design software.
-RSDP project furniture and computers were donated
to the PRDD at the end of the project.
- There are several departments in the building where
the PRDD head office is located.
Contractor &
Material
Availability
- Due to lack of continuity of work and stated
tendering problems, there is a shortage of
contractors graded above M2 (ICTAD)
- Government restrictions do not allow use of
locally available material
-Available contractor’s capacity (technical &
machinery) is not adequate for carrying out large
rehabilitation works.
-There are shortages of construction material,
especially the metal that is required. The government
has restricted the operation of quarries in the region
due to environmental issues, though these rocks
would have well suited the metals needed for the
construction (higher AIV)
-Higher rates are being paid for the material transport
compared to the other two provinces as metal in
particular is transported from WP.
2-12
2.4 Local Governments
All Municipal Councils, Urban Councils and Pradeshiya Sabhas generally execute road
maintenance through their own civil works divisions. As there is no standard mode of operation
across all Local Authorities, this report includes the observation of selected Local Government
Authorities in each province as listed below:
Western Province
Colombo Municipal Council, Minuwangoda Urban Council, Horana Urban Council,
Divulapitiya Pradeshiya Sabha and Bulathsinhala Pradeshiya Sabha.
Uva Province
Badulla Municipal Council, Bandarawela Urban Council, Haputale Urban Council, Passara
Pradeshiya Sabha and Monaragala Pradeshiya Sabha.
In general, even though the structure and execution procedures are more or less similar in both
provinces; there is generally a higher capacity in terms of staff and equipment in local authorities
in the WP when compared to those in UP.
2.4.1 Structure and Execution Procedures
The head of the Badulla Municipal Council is an elected Mayor. The Municipal Commissioner,
who is the head of the staff, is responsible to the Mayor. According to the organizational chart in
Figure 2-4, the key functions of the municipality are performed by its 4 sections namely; the
Secretarial Department, Accounts Department, Health Department, and the Engineering
Department. Sectional heads of these 4 departments are answerable to the Municipal
Commissioner.
There is a Works Department under the Municipal Engineer that is responsible for all the
construction and maintenance activities including the road sector. These activities are carried out
by Technical Officers and with work gangs under a supervisor.
The Organizational Structure of the Colombo Municipal Council (CMC) is slightly different to
Badulla Municipal Council. The CMC has a Deputy Municipal Commissioner (Engineering)
under whom all the engineering functions are carried out. The Deputy Municipal Commissioner
(Engineering) is assisted by several directors including Director (Works) who is responsible for
road works. This position is supported by an Engineering Staff as indicated in Figure 2-5
The UCs are headed by a Chairperson elected through the local government elections. The next
in line is the Secretary to the Council who is responsible for the execution of the council’s work
program and its administration. The Civil Works division which includes road maintenance is
2-13
generally headed by the Superintendant of Works who reports directly to the Secretary.
Technical Officers and the direct labor force attached to the division supports him in executing
road maintenance and other civil works. Figure 2-6 shows the organization chart of
Minuwangoda Urban Council as a typical UC.
Similar to the UCs the head of the PS= the Chairman, is elected through an election. The next in
line is the Secretary who is responsible for the execution of the work program and administration
of the Pradeshiya Sabhas. The Civil Works program of the PS is generally headed by a Technical
Officer who is directly under the Secretary. The Technical Officer executes the required road
maintenance and other civil work programs with the assistance of the direct labour assigned
under him. Figure 2-7 shows the Organization Chart of Divulapitiya Pradeshiya Sabha as a
typical illustration.
Generally local governments carry out only road maintenance work as they usually do not have
the required funds for new work or rehabilitation work. There is no regular annual work plan for
road maintenance either. Weeding, clearing of drains and pot-hole patching etc. is the usual
maintenance work performed using direct labor force of the local authorities. But the more
expensive capital work programs that require tarring and metalling or more expensive repairs
are classified under periodic maintenance. Such improvement and rehabilitation work is
contracted to contractors chosen through a process of competitive tendering.
Local governments especially the PSs also function as the implementation agency of rural road
projects handled by District Divisional Secretaries. Funds from the Decentralized Capital Budget
(DCB), ‘Maga Neguma’ and ‘Gama Neguma’ programs (each of which will be described later)
come under this category.
2.4.2 Capacity
The existing technical and labor capacity for most of the Pradeshiya Sabhas appear to be
inadequate considering the condition and the extent of the road network. Most of the Ps employs
a Technical Officer and a labour team of about 5-10. Municipal and Urban Councils employ
comparatively better qualified technical staff including Engineers, Superintendent of Works and
Technical Officers even though their road network is in much better condition and its extent is
less.
There are also other reasons for the better condition of roads in MC and UC areas. In the first
instance MCs and UCs have more earned incomes and secondly it is difficult to find competent
staff in rural areas. Moreover there is greater visibility of the condition of roads in urban areas
and political representatives and others exert pressure for the speedy repair of any road in poor
2-14
condition. Since Pradeshiya Sabhas cannot afford to have technical officers who have specialized
competencies in road works, each technical officer has to be responsible for all the civil works in
the area and is not specialized in road works.
The Municipal and Urban Councils usually have some equipment belonging to them which
would include at least one Roller. However most Pradeshiya Sabhas do not have and mechanized
equipment for road repairs.
2-15
Figure 2-4: Organization Chart of Badulla Municipal Council
Mayor
Deputy Mayor & Members
Municipal Commissioner
Accountant Secretary Engineer Medical Officer
Clerical Staff Clerical Staff
Water Works Department
Superintendent of Work
Technical Officers
Supervisors
Labourers
Works Department
Labourers
Superintendent of Work
Technical Officers
Supervisors
Chief Public Health Inspector
Public Health Inspectors
Supervisors
Labourers
2-16
Figure 2-5: Organization Chart of Colombo Municipal Council
The Mayor
Deputy Municipal Commissioner ( Development )
Deputy Municipal Commissioner ( Engineering )
Deputy Municipal Commissioner ( Administration )
Director (Workshop )
Director (Traffic Design & Road Safety) )
Director ( Planning )
Director ( Works )
Director ( Projects )
Director ( Drainage )
Director ( Solid Waste
Management )
Superintending Engineer ( South
Superintending
Engineer ( North ) SE
(CRMU)
District Engineers
– 1,2A,2B
District Engineer s
Supervisors Drivers
Labourers
Technical Inspector
Road Engineers
Technical Inspector
Supervisors Drivers
Labourers
Technical Offices
Supervisors Drivers
Labourers
SE (studies)
Chief Architect
SE
(traffic)
Road Engineers
Architects Road Engineers
Technical Offices
Draughts men
Technical Offices
2-17
Figure 2-6: Organization Chart of Minuwangoda Urban Council
Chairman
Internal Auditor
Secretary
General Administration
Accountant
Clerical Staff
Chief Clerck
Physical Planning
Labourers
Clerical Staff
Revenue & Environment &
Public Health Inspector
Labourers
Chief Public Health Inspector
Public Welfare
Chief Development
Librarian
Supporting Staff
Chief Development
Technical Officers
Office Clerk
Superintendent of Work
2-18
Figure 2-7: Organization Chart of Divulapitiya Pradeshiya Sabha
Chairman
Secretary
Development
Clerical
Chief Clark
Labourers Librarian
Librarian
Primary School Head
Medical Officer
Supporting Staff
Community Development Officer
Technical Officer
2-1
2.5 Private Sector Involvement
The GoSL has made several attempts to attract private sector involvement in road funding, design, construction and maintenance over the last 3 decades.
2.5.1 Funding
Private sector funding has not been hitherto successful for road financing in Sri Lanka. Several
new highways and expressways that have been planned in recent years have been offered for
Foreign Direct Investment to private parties. GoSL has actively promoted projects such as the
Colombo-Katunayake Expressway, Colombo-Kandy Alternative Highway on BOO, BOT basis
but without success since traffic levels on these proposed highways are considered still to be quite
moderate and the per capita incomes of road users is still relatively low. As a result such investors
have demanded large guarantees from GoSL. The CKE project has now been recommissioned on
basis of a commercial loan from China where a Chinese contractor will bring the required foreign
investment to be paid back over a period of time. This is planned as a toll road, but tolls are only
expected to bring less than 1/3rd of the required payments. There has been no interest from private
investors for provincial or rural roads.
2.5.2 Design
The RDA and the PRDAs have design offices that attend to the design requirements of locally
funded new roads and road rehabilitation projects. However almost all foreign funded projects at
all three levels of the road network, have their design work carried out through the engagement of
private design consultants.
2.5.3 Construction
Almost all new road construction is now out sourced to the private sector at all three levels of road
administration. There are a couple of long-standing foreign road construction firms and several
local firms of repute. While these are mostly engaged in the road projects of the national road
network, and very rarely do they engage in projects on the provincial network. This too would be
for foreign funded projects. The lack of regularity of work and problems of tendering are
reportedly reasons why they are not found to work on the provincial road network. Contractors of
lower rating only are generally found to undertake work in the provinces.
2.5.4 Maintenance
Road maintenance is shared between the road agencies and private sector. The RDA undertakes
its routine maintenance through its internal staff, but also uses private sector contractors for larger
2-2
works. Different provinces have different procedures with some provinces out sourcing all its road
maintenance to private sector while their own work gangs attend to emergency works. At the local
government level also there are internal labour gangs that attend to routine works while specific
rehabilitation projects are out sourced through competitive tender.
3-3
3 Sources and Procedures of Funding Roads
The Government strategy pertaining to the manner of funding the road sector has not been
explicitly stated. The implicit strategy it has followed can be gathered from the funding
arrangements in past years and particularly the manner in which funding has been allocated for the
different road networks. This section investigates the funding for the road sector as contained in
the budgetary provisions of the Government. The actual expenditures based on the data collected
from the provinces will be discussed in following chapters.
Before the creation of Provincial Councils the practice was that all funding for roads was allocated
to two ministries. The Ministry of Highways was given funds for all roads A, B, C, D and E while
each local authority was given an allocation through the Ministry in charge of Local Authorities
for its own road network within their areas. However, with the advent of the Provincial Councils,
this situation changed with the Finance Commission made responsible for determining
distributional criterion for the allocations made by the Government to the Ministry of Local
Government and Provincial Councils under the requirements as per 13th constitutional
amendment, together with the Provincial Council Act No. 42 of 1987 and the Provincial Council
(Consequential Provisions) Act No. 12 of 1989 which established legislative and executive
powers at the provincial level.
3.1 National Roads
The National Budget allocates funds for the RDA through the Ministry of Highways and Road
Development in two different expenditure categories labeled Recurrent and Capital. The Treasury
allocates funds for national roads through domestic and foreign funding sources. Domestically
funded recurrent expenditure basically provides for personal emoluments, travelling expenses, and
for the service & maintenance of capital assets. Though Road Maintenance is a Recurrent
Expenditure it is categorized under Capital Expenditure along with expenditure for road
construction, rehabilitation and improvement. Table 3-1 gives typical breakdown of fund
allocation, as per the National Budget for the period 2006 to 2008, for the execution of different
road programs for the national road network.
Table 3-1: Head of Ministry of Highways & Road Development, 2008 Budget (SLR mn)20
Description 2006
Actual
2007
Approved
2007
Revised
2008
Estimate
Recurrent Expenditure 177 186 193 114
Personal Emoluments 28 32 32 40
Other Recurrent 148 154 161 74
20 Source: National Budget-2008
3-4
Capital Expenditure 25,870 45,684 47,487 51,904
Expressway Development 7,665 12,884 11,338 12,798
Southern Transport Development Project 7,130 7,256 6,845 6,488
Colombo Katunayake Expressway 246 2650 2650 1700
Outer Circular Highways 187 2885 1750 4580
Highways Development 8,917 12,672 14,440 14,030
Maintenance of Roads & Bridges(RMTF) 2,933 3,410 3,410 2,950
Road Network Improvement Project 3,603 3,008 3,776 1,045
Road Sector Assistant Project 935 3,464 3,889 4,361
National Highway Sector project 1 1,572 1,572 4,056
Widening & improvement of Roads 3,001 3,427 4,102 4,880
Construction of Bridges & Flyovers 1,180 2,543 2,583 4,734
Tsunami Affected Road Rehabilitation 1,443 8,049 8,937 7,552
Institutional Support 1,923 3,015 2,965 3,901
Maga Neguma 1,800 3,082 3,082 4,000
Other Capital Expenditure 41 12 40 16
Grand Total 26,047 45,870 47,681 52,018
Financing 26,047 45,870 47,681 52,018
Domestic 11,781 21,252 22,262 24,535
Foreign 14,265 24,619 25,419 27,483
The recurrent funds are based on staffing levels and other operational costs.
As outlined earlier, the spending on national roads comes from more than a single sources. These
are identified as:
a) Central Government Allocations for both capital and recurrent expenditures made to the
Ministry of Highways for work carried out through the RDA.
b) Projects funded through foreign loans channeled to the RDA through the Ministry of
Highways.
c) Projects funded through foreign loans channeled to the RDA through other central
government ministries and agencies without being allocated to and going through the
Ministry of Highways.
It has been noted that ‘the review of the records of both the RDA and the NBD reveals that even
though the spending on national roads is mostly carried out through the RDA, there are other
ministries such as the Ministry of Nation Building & Development and the Ministry of Local
Government & Provincial Councils that handle budget allocations spent on national roads. The
spending by the Ministry of Mahaweli on major roads which will eventually become part of the
national road network has also been considered’21.
21 Source: Kumarage A.S., Roads Public Expenditure Review n Sri Lanka, World bank, 2006
3-5
3.1.1.1 Sources & Procedure of Maintenance Funding
Until year 2006 the budgetary allocation for road maintenance was made directly to the Ministry
of Highway through the domestic fund. Since January 2007, once the Road Maintenance Trust
Fund (RMTF) was set up, the government budget made its road maintenance allocation to the
RMTF. The fund commenced with $ 30 million for the year 2007 and was expected to be
increased by $ 4 million annually until year 2010. It was expected that the fund would then be
transformed in to a dedicated second generation road fund. But presently the RMTF is only a
supplementary account. Moreover it is confined only for national roads.
The RDA carries out its periodic and routine maintenance by allocating funds to their divisional
offices established within the provinces. Allocation for routine maintenance is released according
to the road condition assessment made by the Executive Engineers of the divisional offices, based
on the RMBEC road maintenance estimation software programme. Road improvement work items
are selected on priority basis, taking into consideration the assessed needs for each district.
However the RDA always complains that the full allocation cannot be used since the Treasury
does not release the agreed Imprest on time.
3.1.1.2 Sources & Procedure of Capital Funding
As indicated in Table3-1; new construction, improvement and rehabilitation work of national
roads are funded by the National Budget through the Ministry’s Capital Expenditure allocation..
These Capital allocations are based on project proposals that are submitted to the Treasury and are
included in the budget. These include projects that are funded entirely through domestic funds as
well as projects which are funded by foreign donors with counterpart domestic funding. Most
foreign funded projects are identified by consultants provided by the donor agencies.
In the case of domestically funded projects, there is no particular pipeline for projects. Projects are
chosen based on prevailing political expediencies. Large scale, domestically funded projects
however are usually mentioned in the budget speech thus officially declaring such projects as
policy decisions. Allocations coming under the Maga Neguma Program are currently confined to
upgrading of rural roads and even though such allocations come under the Ministry of Highways,
the RDA is not the implementing agency of such work programs.
Some funds making up around Rs 100 to 200 mn which are allocated to the Ministry of Highways
are transferred on a regular basis to the RDA on completion of specific work programs.
3-6
3.2 Provincial Roads
The Central Government allocates more than 90% of all budgetary needs of the Provincial
Councils (PCs) with provincial revenue accounting for only about 10% of their total financial
needs for both recurrent and capital expenditure. In year 2007, the total expenditure of all PCs was
Rs. 105, 850 mn but only Rs.13,900 mn was collected by the PCs from devolved revenues.22 Each
year the Central Government in consultation with the Finance Commission allocates domestic &
foreign funds in the form of grants for provincial development through the MLGPC to each
province. Treasury transfers funds directly to the PCs by notifying at the same time both the
Finance Commission and the MLGPC.
There are 5 major sources/channels23 of Treasury funding for provincial road development:
• Domestic Funds
• Foreign aid loans
• Foreign aid related grants
• Reimbursable Foreign aid loans
• Foreign aid related domestic funds
3.2.1 Sources & Procedures of Maintenance Funding
Central Government provides a Block Grant to all PCs for their recurrent expenditures on account
of road work. The Block Grant is provided from domestic funds of the Central Government. Other
than the Western Province most provinces get the majority of their recurrent budget from Block
Grants received from the Central Government. For the road sector this includes salaries,
overheads and an allocation for recurrent maintenance which in addition to other assets includes a
significant portion for expenditure of road maintenance.
PCs prepare their annual recurrent expenditure needs in consultation with the Finance
Commission (FC) by requesting Block Grants through the National Budget. PCs get their
budgetary allocation of Block Grant made under the National Budget released through the
Ministry of Local Government & Provincial Councils (MLGPC) and the FC. Basically PCs have
to involve both these institutions in order to get their allocations released.
Though the amount of the allocation is specified under the Head of each PC in the National
Budget, it is distributed among the PCs considering their generated revenues and cash flows and
usually after informal discussion in this regard with the FC & the MLGPC. This Block Grant is
usually released as a monthly Imprest. However, the MLCPG has no power to regulate the
utilizations of these funds after releasing to the PCs.
22 National Budget of Sri Lanka, 2007 23 Ibid
3-7
But in the case of the Western Provincial RDA, they maintain a special fund which is financed
through their own revenue. In the case of a shortfall in government capital or recurrent funds, the
PRDA uses these funds to continue with the work program.
3.2.2 Sources & Procedures of Capital Funding
Central Government provides domestically funded Criteria Based Grants and Matching Grants
(which were provided only till 2006) for capital expenses of PCs. But PCs have not allocated
funds from these grants for road sector development over the last five years. Provincial Specific
Development Grant (PSDG) which identifies sectoral expenditure is the only domestic funding
source which has been utilized by the PCs for capital works in the road sector.
Similar to the procedure for providing Block Grant, the PCs have to negotiate with the FC and
MPCLG to request the release of funds from the Treasury. PCs have to finalize the development
priorities in consultation with the FC. Once the program is finalized the FC recommends to the
Treasury to allocate the funds required under PSDG for the next financial year. Once the
allocation is made under the National Budget, PCs can request the Treasury for their allocations
with the approval of the MLGPC and the FC. Treasury releases the PSDG to the PCs through
MLGPCs with a notification to FC based on pre-identified and agreed development priorities in
the province. The FC has authority to supervise the progress of the performance of the PCs in
these projects prior to releasing these grants. PCs do not have provision to deviate from the grant
utilization guidelines provided by the FC.
Until 2006, the PCs had to channel their requests for funds through the MLGPC. Since this
process was found to experience delays in funds reaching the PCs, the Treasury authorized the
release of funds directly to the Chief Secretary of the respective PC with a notification to the
Ministry and to the FC.
In addition to road rehabilitation using domestically funded PSDG funds, there was an ADB
funded Road Sector Development Project (RSDP) (2003-2008) which was executed by the
MLGPC for rehabilitating the provincial road network in both Uva and Western provinces. Since
these projects are executed under MLGCP, the ministry has to forward the budgetary
requirements of each project to the Treasury in their annual budget proposals. Component of
foreign aid related domestic funds are mainly utilized for the local operational cost of the projects.
The project implementing agency of RSDP can request their financial requirements directly from
the Treasury. Thereafter the Treasury inquires from the MLGPC for a certification from the
Project Director for the payment requested by the implementing agency before funds are released.
The WP RDA receives capital grants through the Provincial Council Fund, Parliamentarians
Decentralized Capital Budget and their own funds for the execution of capital work. But such
funds are usually not available for the Uva Province. Present funds allocating and procedure for
release of funds for the provincial road sector is graphically represented in Figure 3-1.
3-8
3-9
Figure 3-1: Procedure of Provincial Road Financing, 2008
Eg: PSDG, Criteria & Block Grant based works
Ministry of PCs & LG
Fund Requesting Criteria (No specific criterion for foreign funds)
Fund Releasing Criteria
Periodic & Routine Maintenance
Rehabilitation & Improvements Eg: RSDP Eg: CAARP
STAART
Notification of fund releasing
Notification of
fund releasing
Next year Road Work Program
Finalized Next year Road Work Program
Funding recommendations for approved Road Program
Central Government
(Treasury)
Domestic Financing Foreign Financing
Finance Commission
• Domestic Funds
• Foreign aid related domestic funds
Domestic Financing Sources
Ministry of PCs & LG • Devolved Revenue
• Foreign aid loans
• Foreign aid grants
• Reimbursable Foreign aid loans
Provincial Councils
Provincial Road Agency
Foreign Financing Sources
3-10
3.3 Local Authority Roads
3.3.1 Sources and Procedures of Capital Funding
Local Governments, especially Pradeshiya Sabhas rarely allocate finance for the capital work of
road sector. Therefore rural roads are mainly rehabilitated and improved through the external
domestic funding sources of the PSDG, Decentralised Capital Budget (DCB), Maga Neguma,
Gama Neguma and Uva-Wellassa projects. In addition, there is the World Bank funded Road
Assistant Project now in progress for rehabilitating rural roads in Uva Province.
Public Expenditure on Urban Roads
Urban roads have fewer sources of funding when compared to provincial roads. The primary
source of funding is through their own funds. These funds are used primarily to pay the shortfall
in salaries after the payment of 60% of salaries provided by the Central Government through the
Ministry of Local Government & Provincial Councils and disbursed direct to the respective
Provincial Council based on the recommendation of the Finance Commission. Except for a few
councils which have reasonably good revenue bases, others claim that they do not have adequate
funds for maintenance and rehabilitation work on the urban road system.
From 2006, the Finance Commission has agreed to release part of the funding under the PSDG for
local authority roads to urban and municipal councils as well. In addition, several councils have to
pay back loans taken for the UDLIHP program funded by the ADB during 2000 to 2004. This is
for roads and bridges constructed under this project. Presently, urban roads do not receive any
significant foreign funds. Neither do they have any source of road user charges as opposed to
Central Government collections of import duties, fuel taxes etc and provincial revenues from fuel
taxes as well as vehicle licensing fees, which is reality is collected on their behalf too.
Public Expenditure on Rural Roads
The spending on rural roads cannot be estimated to any degree of reliability or accuracy. This is
because there are numerous sources, most of them executing the work through different
arrangements that vary from place to place. The primary source of funding is the annual PSDG
grant from the Central Government channeled through the Ministry of Local Government &
Provincial Councils and distributed through the Finance Commission with instructions to the
relevant Provincial Councils on the allocations to each Pradeshiya Sabha. There are also PSDG
funds under a numerous other headings such as Backward Areas Roads, Development of Scenic
Resources, Mahaweli Roads, Estate Infrastructure, Rural Infrastructure and 5 year Development
Plan, which are found to incur varying percentages of the allocated funds to each such vote on
rural roads.
3-11
3.3.1.1 Provincial Specific Development Grant-Local Authority Roads
Similar criterion in allocating and releasing PSDG funds for provincial roads is followed for local
authority roads as well. Budgetary requirements of each of the local authorities for their road
rehabilitation programs are prepared by the Provincial Commissioner in consultation with the FC
and the respective Local Authority. The Provincial Commissioner sends the finalized and agreed
financial requirements to the National Budget Department through the MPCLG to be included in
national budget allocation.
Once the budgetary allocations are made, the Treasury releases the requested PSDG to the
Commissioner upon the recommendation of the FC. The Provincial Commissioner thereafter
distributes the grants among the respective Local Authorities in accordance to the FC’s directions
which are based upon a pre-agreed schedule of investment.
However in the budget for the year 2007, allocations were made for Infrastructure Development
of Local Authorities including a road sector component. There was no specific dedicated PSDG
allocation for Local Authority roads as in previous years.
In parallel to the PSDG road program, there were two other projects functioning under the
Provincial Commissioner during the years 2005 and 2006. In year 2005 there was a Local
Government Road Upgrading Project which was intended to enhance the motorability of roads
that are served by public transport services. Similarly in the year 2006, Local Authority Road
Rehabilitation Project was conducted under the Five Year Development Plan. Funding procedures
for both these projects was the same as for the PSDG since the FC was also involved in the
process.
3.3.1.2 Decentralized Capital Budget (DCB)
The Annual National Budget allocates as a Decentralised Capital Budget (DCB), an amount of Rs.
5 million for each Member of Parliament, totalling Rs 1,125 mn annually. These funds are mainly
utilized for regional infrastructure development such as for road, electricity, drinking water and
irrigation projects. As decided by the respective Member of Parliament. Until the year 2006 DCB
allocation came under the head of Ministry of Rural Livelihood Development and after which it
was transferred to the Ministry of Nation Building & Estate Infrastructure Development
(MNBEID).
In the case of Local Authority road improvement and rehabilitation, Parliamentarians select
projects in consultation with the local authorities and submit their final schedule of DCB Program
to the District Secretary. District Secretary is responsible to obtain approval for the program from
the MNBEID. Once the program is approved the District Divisional Secretary calls for tenders for
road projects through the respective District Divisional Secretariat or alternatively projects are
3-12
handed over to relevant Pradeshiya Sabha for execution of the work program. Depending on the
physical progress of the work, payments are made by the Ministry to the contractors or the
Pradeshiya Sabha with the approval of the District Divisional Secretary.
3.3.1.3 Maga Neguma
Maga Naguma was started in year 2004 under the Ministry of Road Development and later it was
transferred to the Ministry of Highways and Road Development in year 2008. The District
Secretary executed the project with the assistance of the divisional secretariat in DS division level
when project was carried out under the Ministry of Road Development during the period of 2004
to 2007.
The National Budget allocates fund for the project to the Head of Road Development Ministry
based on the budget proposals handed over by the Ministry itself. The project executing agency,
the District Secretariat, called for tenders through the respective divisional secretariat as
accordance to a pre-identified road rehabilitation schedule. Some Local Authority road projects
are handed over to the relevant Pradeshiya Sabha for execution of work. Depending on the
physical progress of the work, payments are made by the Ministry to the contractors or to the
Pradeshiya Sabha with the approval of District Secretary.
3.3.1.4 Gama Neguma
The Gama Neguma programme was initiated in year 2006 under the Ministry of Rural Livelihood
Development with a budgetary allocation of Rs. 400 mn. But the project started to function
effectively only after year 2007 under the same ministry. However in year 2008 it was transferred
to the Ministry of Nation Building & Estate Infrastructure Development. This project functions on
the basis that 20% of project cost is to be contributed by the community. Therefore most of the
projects are executed by locally established community and welfare organizations under the
supervision of the District Secretary.
Until year 2007, the National Budget allocated funds for the project to the Head of Rural
Livelihood Development Ministry based on the budget proposals handed over by the Ministry
itself. The District Secretariat and the Divisional Secretariat executes pre-identified projects with
the participation of local community groups and local governments. Depending on the physical
progress of the work, payments are made by the Ministry to the relevant project implementing
agencies or to the Pradeshiya Sabhas upon the certification of the District Secretary.
3-13
3.3.1.5 Uva Wellassa Project
The Uva-Wellassa Development Project was commenced in year 2005, under the Ministry of
Health, Nutrition & Uva Wellassa Development. Infrastructure development and up-lifting of
welfare facilities in UP are the major objectives of this project. Rural road rehabilitation was one
of the project components for which 17% of the total allocation in the year 2005 was provided.
After reshuffling ministries in year 2006, this project was shifted to the Ministry of Regional
Development. However the project was not operational after year 2007. Since the year 2008 the
remaining work in the project is carried out under the Ministry of Nation Building and Estate
Infrastructure Development.
This project was entirely funded domestically. The National Budget made the allocation during
the period for years 2005 to 2007 under the relevant ministry. The Ministry had established a
Project Implementation Unit in the Badulla District Secretariats for executing this project.
Respective ministries released funds to this unit according to the work that was executed.
3.3.1.6 Road Sector Assistant Project-Rural Roads
This project commenced in year 2008 as a pilot project for investigating a suitable road surfacing
for Local Authority roads in Uva Province. The pilot project invested on roads in
Siyabalanduwa, Meegahakivula and Rideemaliadda Pradeshiya Sabhas. Under this project 33.32
km were rehabilitated in year 2008 with different surface types such as mettalling & tar,
concreting and gravel. Funding was arranged through the Ministry of Highways and Road
Development. A separate project office was established in the office of the Provincial
Commissioner and financing of the project is carried out under the supervision of Provincial
Commissioner.
3.3.2 Sources and Procedures of Maintenance Funding
Road maintenance, especially routine maintenance, is generally neglected by the local
governments due to the unavailability of funds. However periodic maintenance is carried out from
time to time with the capital funds provided by PCs and its members though it is identified as road
development activity by the Local Authorities. Even though MCs and UCs road sector are also
under-funded they are able to keep the road network in satisfactory condition since the extent of
the network is small.
Funds for road maintenance are allocated in the respective Local Authority budget through their
recurrent revenue which is funded with revenues collected by the authority and the grants received
from the government. Around 30-40% of estimated annual recurrent revenue of local authorities is
made up of government grants received via the respective PC.
4-1
4 Capital Expenditure for Roads (2004-2007)
4.1 National Roads
In the past few years the Capital Allocation for the RDA was made under the program headings of
Expressway Development, Highway Development, Improvement & widening of roads and
Construction of Bridges & flyovers etc. The national roads in both Western and Uva provinces
included several projects under these programs of Highway Development, Improvement &
widening of roads and Construction of Bridges & flyovers during the period of 2004-2007. This
chapter assesses the Capital Allocation and Expenditure for the two provinces performed with
respect to each afore-mentioned program during the period of 2004 to 2007.
4.1.1 Western Province
A number of road rehabilitation projects in the WP have been completed under different foreign funded projects. These are discussed in the following sections:
4.1.1.1 Improvement & Widening of National Roads (SIRUP)
Financial investment for executing national road improvement and widening is mainly made
through the Small Infrastructure Road Upgrading Project (SIRUP) which is funded by
reimbursable foreign aid loans. This project is implemented throughout the island by the RDA for
the improvement of the national road network. WP received the largest amount of SIRUP funding
during the past few years equaling provincial allocation to 15-20% of total allocation. Table 4-1
illustrates the financing made through SIRUP for the national road network in Western Province.
Table 4-1: Financing of Improvement & Widening of National Roads and Bridges24
Rs. Million
2004 2005 2006 2007
Budgetary Allocation N/A 1060.0 1010.0 630.0
Actual Expenditure 480.6 961.8 600.1 925.2
4.1.1.2 Expressway Development
The importance of Outer Circular Highway (OCH) for Colombo city was in discussion for many
years and it was started with the detailed design carried out in year 2004. Not limiting to OCH,
several expressway development projects were also started in the recent past extending from OCH
to Katunayake, Kandy and Southern part of the country. Though Alternate Colombo-Kandy
Highway (ACKH) & Southern Highway extends beyond the provincial boundaries, its potential
24 Source: Road Development Authority-Planning Division
4-2
developmental impact on is significant. Table 4-2 shows the expenditure incurred on these
expressways during the period of 2004 to 2007. Expenditure of ACKH & OCH in year 2004
includes detailed design in addition to construction cost.
Table 4-2: Financing of Expressway Development Program-WP
Project Name Rs. Million
2004 2005 2006 2007
STDP-Kottawa to Kurundugaha-hetekma(JBIC) 361.1 321.7 3200.6 4146.4
Colombo-Katunayake (Domestic) 50.0 385.8 245.8 497.9
Outer Circular Highway (JBIC) 7.8 23.4 187.0 894.2
Alternate Colombo-Kandy Highway-(SIDA) 43.1 8.6 2.2 32.7
Construction of the Colombo-Katunayake Expressway is executed through domestic funding
sources. JBIC funds for OCH and Southern Highway (section from Kottawa-Kurundugaha-
hetekma).
4.1.1.3 Highway Development
ADB & JBIC funded Road Network Improvement Project (RNIP) and JBIC funded Baseline
Road-Phase III are executed under this program during the period of 2004 to 2007. Island-wide
Road Network Improvement Project includes rehabilitation of several flood affected roads and
also Panadura-Ingiriya, road in the WP. Table 4-3 illustrates the expenditures incurred during
2004 to 2007 for both these projects. It should be noted however, that the amounts relate to RNIP
expenditure are for the total package and not limited to the projects in Western Province only.
Table 4-3: Financing of National Roads under Highway Development Program-WP25
Project Name Rs. Million
2004 2005 2006 2007
Road Network Improvement Project-ADB,JBIC 2934.1 1844.6 3,060 3171.5
Baseline Road Phase III-JBIC 222.0 92.7 0.4 49.8
Expenditure of Baseline Road in year 2004 includes detailed design and construction cost as well.
4.1.1.4 Tsunami Affected Road Rehabilitation
Since 2005 JBIC has funded the STAART project invested for the rehabilitation of Tsunami
affected areas in Western, Southern and North Eastern. Estimated cost component of STAART for
rehabilitating national roads in Western Province is Rs. 116.6 mn. Table 4-4 shows the investment
made under the above cost component during the period of 2006 to 2008.
25 Source: Road Development Authority-Planning Division
4-3
Table 4-4: STAART funding of National Roads in Western Province
Rs. Millions
2004 2005 2006 2007 2008
Allocation N/A N/A 18.9 17.0 21.0
Expenditure N/A N/A 30.9 53.0 10.0
4.1.1.5 Construction of Bridges & Flyovers
There is also an Overseas Development Assistance loan under which steel bridges and flyovers
are being constructed mostly in the Western Province. No cost figures have been published in this
regard as yet. The first tranche of five bridges is presently under construction, all of which are to
be located within WP.
4.1.2 Uva Province
A number of road rehabilitation projects in the UP have been completed under different foreign funded projects. These are discussed in the following sections:
4.1.2.1 Improvement & Widening of National Roads (SIRUP)
Financial investment for executing national road improvement and widening is mainly made
through the Small Infrastructure Road Upgrading Project (SIRUP) which is funded by
reimbursable foreign aid loans. This project is implemented island wide through the RDA for the
improvement of the national road network. But UP received the least amount of SIRUP funding
during the past few years. Table 4-5 illustrates the financing made through SIRUP for the national
road network in Uva Province.
Table 4-5: Financing of the Improvement & Widening of National Roads and Bridges26
SL Rs. million
2004 2005 2006 2007
Budgetary Allocation N/A 33.0 309.0 180.0
Actual Expenditure 28.7 25.7 36.1 21.9
4.1.2.2 Highway Development
Under this program, several road rehabilitation and improvement work have been executed
during the period of 2004-2007. Among them, the construction of the new Badulla-Kandy
26 Source: Road Development Authority-Planning Division
4-4
alternate road is the only new road project in UP. This was carried out with domestic funds while
all other projects were funded thorough foreign grants or loans. Projects such as Ratnapura-
Beragala-Bandarawela road are not limited to the province but they directly contribute to the
regional development of several provinces. Additionally road rehabilitation of World Bank funded
Road Sector Assistance Project (RSAP) which included the Wellawaya-Siyabalanduwa roads
and ADB funded National Highway Sector Project (NHSP) included Kandy –Mahiyangana road
which fall through Uva Province. Table 4-6 illustrates the expenditure incurred during the period
2004 to 2007 under the Highway Development program. However it should be noted that
expenditure figures of NHSP and RSAP are for the whole package implemented island-wide and
are not limited to the expenditure within the province.
Table 4-6: Financing of National Roads under Highway Development Program27
Project Name Rs. Million
2004 2005 2006 2007
Ratnapura-Beragala-Bandarawela Rd(EDCF) 311.4 411.9 365.9 103.3
Rehabilitation of Balangoda -Bandarawela
Rd(EDCF)
20.0 965.7 1,068.50 1,387.20
Road Sector Assistance Project-WB 2.0 137.2 934.7 3,794.90
National Highway Sector Project-ADB NA NA 1.3 126.2
Badulla-Kandy Alternate Rd(Domestic) NA NA 10.4 34.5
Also, the RDA received financial aid under Pro-poor Rural Road Development Programme for
certain rehabilitation work carried out in Badulla and Monaragala Districts. Rs 24 mn was spent
under this program in year 2007. Original values of the projects for Badulla and Monaragala
districts were estimated as Rs.254.5 mn and Rs 351.7 mn respectively.
4.2 Provincial Roads
During the period of 2004 to 2007, provincial roads in both provinces were rehabilitated by the
Road Sector Development Project implemented by the Ministry of Provincial Councils & Local
Governments with financial with funding and technical assistance from the ADB. Additionally the
UP-PRDD and WP-PRDA also executed a limited amount of general road improvement &
rehabilitation functions using Provincial Specific Development Grant received from the Central
Government.
27 Source: Road Development Authority-Planning Division
4-5
4.2.1 Western Province
4.2.1.1 Provincial Specific Development Grant
The Central Government has financed the PRDA through PSDG for carrying out road
rehabilitation and improvement of provincial roads. The WP is entitled to the highest allocation
of PSDG-Provincial roads. Though it is mentioned that these funds are allocated for road
rehabilitation and improvement, they are actually for periodic maintenance functions such as pot-
hole patching, sand/slurry sealing or surface treatments. Table 4-7 illustrates the PSDG utilization
in Western Province.
Table 4-7: Utilization of PSDG-Provincial Roads, Western Province28
Source Rs Million
2004 2005 2006 2007 2008
Provincial Specific
Development Grants
(PSDG)- Provincial Roads
Allocation 160.0 260.0 300.0 500.0 793.8
Expenditure 135.2 216.7 247.1 271.9 651.96
Utilization (%)
4.2.1.2 Other Central Government Funds
In addition to regular funding sources such as PSDG, provincial roads are funded in ad-hoc basis
by several domestic sources such as Decentralized Capital Budget (DCB), Maga Neguma
Programme, and State Infrastructure Development Program. During the period of 2004 to 2008,
road improvements were carried out for the provincial road network in WP using several sources
shown in Table 4-8.
Table 4-8: Utilization of Other Central Government Capital Funds, Western Province29
Source Rs Million
2004 2005 2006 2007 2008
DCB- Provincial Roads Expenditure 1.47 3.31 4.20 22.98 5.03
Maga Neguma Program Expenditure 16.14
State Infrastructure
Development Program
Expenditure 158.30
Total Expenditure 1.47 161.61 20.24 22.98 5.03
28 Source: Provincial Road Development Authority, Western Province 29 Source: Provincial Road Development Authority, Western Province
4-6
4.2.1.3 Provincial Council Capital Funds
Table 4-9: Utilization of Provincial Council Capital Funds, Western Province30
Source Rs Million
2004 2005 2006 2007 2008
DDC-Programme Expenditure 27.40 133.61 3.50 2.56 -
4.2.1.4 Tsunami Affected Road Rehabilitation
Projects such as the STAART, TAARP and ADB-road rehabilitation projects invested on
rehabilitation of Tsunami affected provincial roads in Western province during the period of 2005
to 2007. Investments made under these projects are illustrated in Table 4-10.
Table 4-10: Utilization of Tsunami Affected Road Rehabilitation Funds, Western Province 31
Source Rs Million
2004 2005 2006 2007 2008
STAART32
Project Expenditure 59.63
TAARP33
Expenditure 82.80
ADB –Road Rehabilitation Expenditure 135.45
Total Expenditure N/A 59.63 135.45 82.80 N/A
4.2.1.5 Road Sector Development Project-ADB
The ADB funded Road Sector Development Project rehabilitated 800 km of provincial roads and
53 bridges in the Western, North Western, North Central and Uva provinces at an estimated cost
of Rs. 10,350 mn. Since this project was implemented only for the upgrading of the existing road
network, the projects were chosen on the basis of least amount of land acquisition and road
widening requirements. As shown in Table 4-11, the RSDP was initiated in year 2003 with an
investment of US$ 21.40 mn for the rehabilitation of 227.87 kms including several small bridges
in Western province. Project was completed in mid 2008.
30 Source: Provincial Road Development Authority, Western Province 31 Source: Provincial Road Development Authority, Western Province 32 Sri Lanka Tsunami Affected Areas Recovery Take-off 33 Tsunami Affected Area Rebuilding Project
4-7
Table 4-11: Utilization of Funds under RSDP, Western Province
34
Source Rs Million
2004 2005 2006 2007 2008
ADB funded RSDP Expenditure 198.5 637.49 945.67 704.84 270.28
4.2.2 Uva Province
4.2.2.1 Provincial Specific Development Grant
Capital Expenditure of the PRDD is facilitated through the Provincial Specific Development
Grant (PSDG) that is allocated to PC by the Treasury. Since specific funds are not available for
periodic maintenance, there is no such activity at present. It should be noted that with the very
poor condition of roads in UP, the Premix Program is a measure whereby the roads are kept in a
basic level of motorability. However since most of these roads have exceeded their design life
such programs cannot be treated as periodic interventions.
The production cost of premix is about Rs. 40,000/- per cube. At present around 5 cubes of
premix are produced per week for each division. UP has 6 divisions and therefore approximately
Rs 60 million is required for this Premix Program per year. This program is carried out by direct
labour employed by the PRDD.
In addition to the Premix Program, the PRDD uses the balance funds in PSDG for overlaying
around 10 km of road surface per year which cost about Rs.6 million per km (at 4-5 m width and
90 mm overlay thickness). This work can be considered an improvement and thus in fact the only
capital work carried out by the PRDD. Moreover, 10% of PSDG (capital expenditure) is set apart
for purchasing vehicles and machinery needed for road work. The PRDD hands over the
machinery it procures to the Provincial Mechanical Engineering Division and hires them back
when necessary at comparatively low rates for their needs for which they get priority.
The PRDD uses PSDG for several periodic maintenance functions and the premix program as
discussed before.
34 Source: Provincial Road Development Authority, Western Province
4-8
Table 4-12: Utilization of PSDG-Provincial Road, Uva Province 35
Source Rs Million
2004 2005 2006 2007 2008 Oct.
Provincial Specific
Development Grants
(PSDG)- Provincial Roads
Allocation 462.0 227.8 270.0 315.0 315.0
Expenditure 123.0 200.0 173.4 106.3 105.6
Utilization (%) 26.6 87.8 64.2 33.7 33.5
In this case also, the utilization has been very poor. The reasons cited are the same as for recurrent
expenditure. In addition when payments are delayed at the beginning of the year insufficient time
remains to award contracts and to complete them within the year for which funds have been
allocated.
4.2.2.2 Road Sector Development Project-ADB
The RSDP, similar to the project in WP during 2003 to 2008, invested US$ 23.53 mn for the
rehabilitation of 193.3 km (30 roads) and 13 packages of road structure in UP from 2007 to 2008.
4.3 Local Authority Roads
During the period of 2004 to 2007, majority of the Local Authority roads in UP and WP were
rehabilitated by the domestically funded Maga Neguma and Gama Neguma programs. Moreover
the domestically funded Uva-Wellassa Development Project and the World Bank funded Road
Sector Assistance Project also rehabilitated the Local Authority road network in Uva province.
Parliamentarians in both provinces also invested on local authority roads through their
Decentralized Capital Budget allocation. In addition to those funding sources under different
Central Government ministries have been used for development of local authority roads.
4.3.1 Western Province
4.3.1.1 Provincial Specific Development Grant-Local Authority Roads
WP generally received the highest amount of allocation under PSDG funding. However since
2005 the Central Government has further increased the budgetary allocation of the PSDG for
Western Province. Even though the budgetary allocations are not fully released by Treasury, there
is general evidence that there has been a high utilization of the funds that have been released even
though Table 4-13 indicates lower utilization.
35 Source: Planning Division of Road Department, Uva Province
4-9
Table 4-13: Utilization of PSDG-Local Government Roads, Western Province36
Rs. Millions
2004 2005 2006 2007
Budgetary Allocation 40.0 50.0 436.5 360.037
Actual Expenditure N/A 17.9 158.9 138.0
4.3.1.2 Decentralized Capital Budget
There are 47 elected Members of Parliament for WP. Each of these members are entitled to an
annual allocation of Rs. 5 mn as their DCB. Analysis shows that 20-25% of DCB is invested for
Local Authority roads through District Secretariats. Thereby it is estimated that around Rs 50
million is spent annually on local authority roads in Western Province. However under the DCB
funding procedures, the allocation for a road is limited to Rs 100,000 and such expenditure is not
adequate for improving an entire road. Therefore most of this expenditure is for repair or
rehabilitation or concreting of short sections of road, repair of culverts etc.
4.3.1.3 Maga Neguma
The detailed investment of Maga Neguma for WP is illustrated in Table 4-14. Imprest released
and utilization of funding in Maga Neguma project shows continuous improvement during the
period of 2004 to 2007. Priority of investment has been given to Gampaha and Kalutara Districts
due to their less urbanised nature.
36 Source: Ministry of Provincial Councils and Local Government 37 In year 2007 PSDG allocation offered for Infrastructure Development of Local Authorities including road s
4-10
Table 4-14: Maga Neguma Investment for Rural Roads in Western Province38
District
2007 Nov. 2006 2005 2004 Colom
bo
Gam
paha
Kalu
tara
Island w
ide
Colo
mb
o
Gam
pa
ha
Kalu
tara
Islan
d w
ide
Colo
mb
o
Gam
pa
ha
Kalu
tara
Islan
d w
ide
Western
Islan
d w
ide
No of Projects 212 403 244 3889 213 401 371 4926 43 64 95 1345
Ph
ysical D
etails
Target Road Length (km) 62.8 73.5 49.9 1001.0 70.0 100.0 70.0 2000.0
Ach
ieved
(km
)
Metalling & Tarring (km) 17.0 23.3 9.7 209.2 53.2 76.9 74.0 909.8 15.0 24.6 32.0 381.3
Gravelling (km) 0.3 83.9 1.3 1012.9 1.0 0.2 329.0
Motor Grading (km) 0.0 0.2 4.1 0.9 84.0
Concreting (km) 14.9 41.9 18.2 485.8 5.3 9.0 20.7 277.3 0.7 21.1
Total (km) 32.0 65.5 27.9 778.8 58.7 91.2 95.5 2284.0 16.0 24.6 32.8 731.4 15.5 600.0
Physical Progress (%) 50.9 89.1 55.9 77.8 83.9 91.2 136.5 114.2
Stru
ctures
Con
structed
Side Drains (km) 0.1 0.5 27.1 2.2 2.1 9.1 250.9 0.7 0.1 217.0
Ret. Walls (m2) 28.0 184.1 0.0 39.0 78.0 1558.9 0.1 6.2
Rock blasting & Removal. (m3.) 10.0 191.2 325.8
Bridges (Nos.) 6 19
Culverts (Nos.) 3 4 337 2 4 5 340 218
Cause ways (Nos.) 50 1 1 58 25
Fin
ancial D
etails
Allocation (Rs.Mn) 167.0 242.0 147.0 3082.0 100.0 150.0 80.0 1800.0 15.6 25.7 33.2 500.0
Expenditure (Rs. Mn.) 68.1 114.8 73.1 1487.0 89.0 115.0 111.8 1800.0 15.7 25.0 35.3 500.0 18.2 213.0
Financial Progress (%) 40.8 47.5 49.8 48.2 89.0 76.7 139.8 100.0 100.6 97.3 106.6 100.0
Beneficiary Families 2,048 4,868 2,408 57,482 2605 4496 4320 71904 889 1386 1950 34615
38 Source: Ministry of Nation Building & Estate Infrastructure
4-11
Gampaha District DS division level investment of Maga Neguma Program in 2007 is illustrated
in Table 4-15.
Table 4-15: Financing under Maga Neguma for the Rural Road in Gampaha District, 2007 39
DS Division
Road Length (km) Constructed
Structures
(nos.)
Allocation(
Rs.)
Actual
Expenditure(Rs.) Targetted Achieved
Divulapitiya 6.4 5.96
None
22,785,250 13,388,861
Katana 7.92 7.62 33,627,125 21,166,962
Minuwangoda 10.99 10.63 29,805,625 20,253,096
Mirigama 5.82 5.52 12,943,000 10,013,066
Attanagalla 12.82 9.47 24,444,875 15,128,484
Gampaha 9.32 9.13 19,825,625 13,090,172
Ja-Ela 6.45 6.4 24,039,752 22,518,077
Wattala 0.13 0.13 550,000 392,141
Mahara 10.88 9.67 24,884,125 15,145,146
Dompe 12.64 11.36 25,084,125 13,738,297
Biyagama 5.2 4.19 12,944,125 9,071,446
Kelaniya 7.94 7.22 22,705,625 17,209,804
Total 96.51 87.3
253,639,252 171,115,552
4.3.1.4 Gama Neguma
The Gama Neguma Programme initiated in 2006, had an allocation that was limited to Rs.100,
000/- per DS division amounting to a total of Rs 1.3 million for Gampaha District. Gama Neguma
Program generally invests 80-90% of its allocation on rural road rehabilitation island-wide. This
is confirmed by the fact that actual expenditure for roads in Gampaha District was Rs. 502.4 mn
from a total of Rs. 546.3 mn during 2008.
Table 4-16 illustrates Gama Neguma investment made for rural infrastructure development in the
Western Province during 2008.
39 Source: District Secretariat-Gampaha, Work performed in 2008 as a ccontinuation of work remained in 2007 is also
considered.
4-12
Table 4-16: Gama Neguma Investment for Western Province, 2008
District
Rs. Millions
Estimated
cost
Allocation Imprest
released
Expenditure
Colombo 429.76 316.54 354.40 336.47
Gampaha 727.80 695.89 535.00 546.30
Kalutara 703.03 516.36 599.30 554.27
Total 1860.59 1528.79 1488.70 1437.04
4.3.2 Uva Province
4.3.2.1 Provincial Specific Development Grant-Local Authority Roads
Over the last 5 years the PSDG budgetary allocation for local roads in Uva has been continuously
increased Central Government by a slight margin, though the full amounts were never fully
released. Similar to previous years, the PC did not receive the full budgetary allocation in any of
these years, due to inadequate imprest released by the Treasury. In general, it was noted that the
released imprest has been fully utilized by most of the local governments in Uva Province during
the period of 2004-2007. However a considerable increase in the annual road sector expenditure
was also observed during this period.
Table 4-17: Utilization of PSDG-Local Government Roads, Uva Province40
Rs. Millions
2004 2005 2006 2007
Budgetary Allocation 35.00 40.00 45.00 150.0041
Actual Expenditure N/A 5.26 27.32 35.80
The breakdown of expenditure provided for each of the Local Authorities in UP by Local
Authority by the PSDG and the Up-grading and Five Year Development Plan funding is given in
Table 4-18. The Road Upgrading funding pipeline was in operation in 2005 which was further
developed as a 5 year plan in 2006 wherein provinces were required to request their capital
requirements on the basis of a planned investment. However this scheme has since then been
abandoned.
40 Source: Commissioner of Local Governments, Uva Province 41 In year 2007 PSDG allocation offered for Infrastructure Development of Local Authorities including road s
4-13
Table 4-18: PSDG Investment in Local Governments, Uva Province
42
Local Government
Road Sector Expenditure (Rs.)
2005 2006 2007
PSDG Up-Grading PSDG 5 Year Plan PSDG
Badulla District 3,346,455 3,284,668 17,584,078 5,348,779 23,596,081
Badulla MC 963,013
Bandarawela UC 1,962,281 458,231
Haputale UC 977,932 94,453 973,425
Bandarawela 675,000 844,742 580,092 949,317
Haldummulla 26,366 1,132,169 278,488 1,019,946
Haputale 142,150 942,868 191,715 2,657,103
Welimada 579,622 504,475 782,855 796,393
Rideemaliadda 471,332 902,826 140,955 1,294,855
Uva Paranagama 231,573 549,259 304,059
Ella 669,084 1,498,852 99,546 4,301,817
Passara 551,328 1,495,716 735,575 1,876,229
Diyatalawa 1,791,749 998,496
Badulla 966,025 309,599 1,317,347
Sornathota 969,004 275,635 2,610,738
Mahiyangana 988,444 610,084 1,315,790
Meegahakivula 1,314,804 231,244 475,493
Hali-Ela 882,400 308,831 2,170,496
Kandeketiya 1,303,024 237,597 1,427,619
Monaragala District 1,913,031 2,950,052 9,731,236 5,861,194 12,204,780
Monaragala 52,952 1,800,175 72,000 298,691 771,528
Buttala 75,000 853,889 223,033 1,941,123
Bibile 276,934 481,612 1,019,614 667,407
Medagama 954,089 586,947 2,099,572
Madulla 480,545 961,540 1,131,881 372,894
Thanamalwila 1,027,600 966,690 2,464,167 2,309,629
Badalkumbura 970,377 145,372 2,878,615
Siyabalanduwa 1,393,511 98,978 84,110
Wellawaya 668,265 1,204,526 244,718 1,407,766
Kataragama 1,335,000 339,543
Provincial Total 5,259,486 6,234,720 27,315,314 11,209,973 35,800,861
42 Source: Commissioner of Local Governments, Uva Province
4-14
4.3.2.2 Decentralized Capital Budget (DCB):
The total allocation of DCB funds for Badulla District in year 2008 was Rs 40.35 mn. Table 4-19
gives the DS division level breakdown of DCB funding in Badulla District.
Table 4-19: Local Road Financing through DCB for Badulla District, 200843
D.S. Divisions
Financial Investment (Rs.), 2008
Allocation
available for DSD
Road Sector
Allocation Expenditure
Mahiyangana 2,945,000 1,115,000 1,101,317
Rideemaliadda 3,072,000 760,000 749,459
Meegahakivula 972,200 135,000 119,726
Kandeketiya 1,270,000 315,000 296,212
Sornathota 1,405,000 335,000 330,904
Badulla 4,585,013 875,937 577,322
Passara 2,374,425 885,925 821,087
Lunugala 1,589,750 470,000 358,723
Hali-ela 3,573,538 890,087 587,519
Ella 1,580,000 250,000 245,499
Bandarawela 2,540,507 368,500 298,183
Haputale 2,691,749 635,000 615,353
Haldummulla 1,783,375 673,375 492,715
Welimada 3,727,672 1,540,000 1,479,638
Uva Paranagama 2,006,600 330,000 329,994
Total 36,116,829 9,578,824 8,403,651
The total allocation of DCB for Monaragala District in year 2008 was Rs 25.56 mn. Table 4-20
gives the DS division level breakdown of DCB funding in Monaragala District.
Table 4-20: Local Road Financing through DCB for Badulla District, 200844
D.S. Divisions
Financial Investment (Rs.), 2008
Allocation
available for DSD
Road Sector
Allocation Expenditure
Monaragala 4,003,378 337,500 124,200
Badalkumbura 2,732,313 590,000 131,584
Siyabalanduwa 1,480,000 335,000 100,000
Bibile 1,070,000 240,000 0
43 Source: District Secretariat, Badulla 44 Source: District Secretariat, Monaragala
4-15
Medagama 3,902,900 285,000 63,180
Madulla 1,635,000 200,000 0
Buttala 910,000 30,000 0
Wellawaya 850,000 200,000 110,420
Thanamalwila 745,000 100,000 100,000
Sewanagla 607,500 200,000 199,773
Kataragama 170,000 N/A N/A
Total 18,106,091 2,517,500 829,157
Investment of DCB can be summarized as follows at provincial level
Table 4-21: Local Road Financing through DCB for Uva Province, 2008
District
Financial Investment (Rs.), 2008
Allocation
available for DSD
Road Sector
Allocation Expenditure
Badulla 36,116,829 9,578,824 8,403,651
Monaragala 18,106,091 2,517,500 829,157
Provincial Total 54,222,920 12,096,324 9,232,808
Since the parliamentarians of these two districts have not changed since year 2004, the amount of
allocation is very consistent. It is also observed that in general, Badulla and Monaragala districts
have respectively invested about 20-25% and 3-5% of total DCB for rural road sector in past
years. Therefore Table 4-20 and Table 4-21 can be used as typical illustration of DCB funding for
road sector in the two districts during the period 2004 to 2007.
4.3.2.3 Maga Neguma
The detailed expenditure of the Maga Neguma Program for UP is depicted in Table 4-22. Imprest
released and utilization of funding in Maga Neguma project is significantly higher when
compared to the other road sector projects in UP.
4-16
Table 4-22: Maga Neguma Investment for Rural Roads in Uva Province45
2007 Nov. 2006 2005 2004
District
Ba
du
lla
Mo
na
rag
ala
Islan
d w
ide
Ba
du
lla
Mo
na
rag
ala
Islan
d w
ide
Ba
du
lla
Mo
na
rag
ala
Islan
d w
ide
Uv
a
Islan
d w
ide
No of Projects 126 142 3889 75 97 4926 32 38 1345
Ph
ysi
cal
Det
ails
Target Road Length
(Year 2007) (km) 36.64 62.7 1,001.00 45 70 2000
Ach
iev
ed (
km
)
Metalling & Tarring 3.28 0.52 209.16 8.31 8.26 909.84 13.28 4.48 381.29
Gravelling 0.2 10.1 83.87 27.06 62.06 1,012.93 1.13 21.55 329.04
Motor Grading
0 7.28 33.34 83.96
Concreting 14.29 21.99 485.77 7.31 3.29 277.25 0.05 0.09 21.05
Total 17.77 32.61 778.80 49.96 106.95 2,283.98 14.46 26.12 731.38 2.55 600.00
Physical Progress
(%) 48.5 52.0 77.8 111 153 114
Str
uct
ure
s
Co
nst
ruct
ed
Side Drains (k.m) 0.77 1.07 27.08 11.07 15.89 250.86 7.91 17.64 216.95
Ret. Walls (m2) 6 184.14 9.00 40.70 1,558.86 6.2
Rock blasting &
Removal (m3.) 4.5 10.00 30.00 191.22 56 325.75
Bridges (Nos.) 1 6 19
Culverts (Nos.) 9 72 337 29.00 25.00 340 6 14 218
Causeways (Nos.) 3 20 50 2.00 16.00 58 3 25
Fin
anci
al D
etai
ls
Allocation (Rs Mn.) 94.00 84.00 3,082.00 60.00 50.00 1,800.00 10.90 10.04 500.00
Expenditure (Rs
Mn.) 37.41 59.74 1,487.03 31.55 40.93 1,800.00 11.82 11.50 500.00 1.20 213.00
Financial Progress
(%) 39.8 71.1 48.2 53 82 100 108 115 100
Beneficiary Families 1,330 2,300 57,482 901 1591 71904 734 1788 34615
Badulla District DS division level investment of Maga Neguma Programme in year 2007 is
illustrated in Table 4-23.
45 Source: Ministry of Nation Building & Estate Infrastructure
4-17
Table 4-23: Financing under Maga Neguma for the Rural Road in Badulla District, 2007 46
DS Division
Road Length (km) Constructed
Structures
(nos.)
Allocation(
Rs.)
Actual
Expenditure(Rs.
)
Targetted Achieved
Mahiyangana 1.268 1.268 4,857,329 4,857,551
Rideemaliadda 0.800 0.250 3,785,703 1,196,436
Kandeketiya 1.615 1.615 5,004,155 4,510,491
Meegahakivula 7.500 6.100 4 5,613,426 3,669,286
Sornathota 1.765 1.765 5,089,042 4,594,823
Badulla 1.750 0.932 1 6,367,900 3,396,237
Passara 3.025 3.025 4,948,455 4,829,881
Lunugala 1.050 0.850 4,320,429 3,210,618
Hali-ela 1.950 1.000 5,449,291 2,462,885
Ella 2.334 2.300 2 4,740,083 4,630,637
Bandarawela 1.862 1.862 3,999,036 3,894,689
Haputale 2.060 2.060 4,680,276 4,554,394
Haldummulla 1.000 0.900 1 3,389,502 2,872,224
Welimada 9.000 7.750 4 5,390,329 1,800,158
Uva Paranagama 0.850 0.810 3,288,409 2,114,536
Administrative cost 374,085
Total 37.829 32.487 12 70,923,365 52,968,931
4.3.2.4 Gama Neguma
In 2007 Rs 214.5 mn was spent in Badulla District under the Gama Neguma Programme for
several rural infrastructure development projects, from which 56.76 km of rural road rehabilitation
work valued at Rs. 183.6 mn was implemented during the year. Estimated cost of the Gama
Neguma programme in Monaragala District in year 2007 was Rs 124.5 mn of which around Rs
100 million can be assumed to have been invested on the road sector. The total Gama Neguma
investment in year 2008 for Uva Province is given in Table 4-24. As indicted before around 80-
90% of this is dedicated for rural road development.
46 Source: District Secretariat-Badulla, Work performed in 2008 as a continuation of work from 2007 is also
considered.
4-18
Table 4-24: Gama Neguma Investment for Uva Province, 2008
District Rs. Millions
Estimated cost Allocation Imprest released Expenditure
Monaragala 836.37 676.72 547.70 536.70
Badulla 610.39 525.07 456.00 452.50
Total 1446.76 1201.79 1003.70 989.20
4.3.2.5 Road Sector Assistant Project (RSAP)-Rural Roads
For 2008, Rs 156.7 mn was spent out of an allocation of Rs 250 mn for the pilot projects that
were implemented in Siyabalanduwa, Meegahakivula and Rideemaliadda DS divisions. Table 4-
25 shows the investments made in year 2008 under this project for each Provincial Council.
Table 4-25: Investment under RSAP for Pilot Projects in Uva Province, 2008
Pradeshiya Sabha Length(km) Project Cost (Rs. mn.)
Meegahakivula PC 5.02 50.10
Siyabalanduwa PC 14.90 54.76
Rideemaliadda PC 14.50 51.43
Total 33.32 156.70
4.3.2.6 Uva Wellassa Development Project
In year 2005, a capital fund of Rs.500 mn was given to the Ministry of Health, Nutrition and Uva
Wellassa Development for carrying out this project. Road sector allocation was only Rs. 88 mn.
The actual expenditure of whole project was Rs 392 mn for the year of 2005. In 2006, the capital
allocation was increased to Rs.506 mn by including a rural road rehabilitation component of Rs
196.5 mn offered to the Ministry of Regional Development for executing development activities a
related to the Uva Wellassa project. But Rs 446 million had to be transferred back to the Health
Ministry for the remaining work of year 2005 leaving a balance of only Rs. 60 million to be
utilized by the project for the year 2006.
4.4 Capital Expenditure and GDP
The capital expenditure on roads with respect to the provincial GDP has been analysed in this section. In doing so, we have restricted to an analysis only of the spending on national and provincial roads, since there is no exact figure for spending on the local authority roads and only estimates are possible.
4-19
4.4.1 Western Province
\
Tables 4-26 and 4-27 give the capital expenditure in national and provincial roads in the WP. As
can be observed, the spending as a percentage of the provincial GDP varies between 0.34% to
0.56% percent for national roads and between 0.04% to 0.11% for provincial roads. This is much
less than the desired expenditure levels of around 2 to 3 percent.
Table 4-27: Capital Expenditure on Provincial Roads vs GDP in WP
4.4.2 Uva Province
Tables 4-28 and 4-29 give the capital expenditure in national and provincial roads in the UP. As
can be observed, the spending as a percentage of the provincial GDP has increased from 0.47% to
3.4% percent for national roads but decreased from 0.62% to 0.128% for provincial roads during
the period 2004 to 2007.
Table 4-26: Capital Expenditure on National Roads vs GDP in WP
Source/Program in WP Expenditure (Rs. Mn)
2004 2005 2006 2007
SIRUP 480.6 961.8 600.1 925.2
Expressway Development 462.0 739.5 3635.6 5571.2
Highway Development 3156.1 1937.3 3060.4 3221.3
Tsunami Affected Road Rehabilitation 30.9 53.0
Total Expenditure 4098.7 3638.6 7327.0 9770.7
% by Provincial GDP 0.44 0.34 0.50 0.56
% by National GDP 0.23 0.17 0.25 0.27
Source/Program Expenditure (Rs. Mn)
2004 2005 2006 2007
PSDG 135.2 216.7 247.1 271.9
Other Central Government Fund 1.5 161.6 20.2 23.0
Provincial Council Capital Fund 27.4 133.6 3.5 2.6
Tsunami Affected Road Rehabilitation 59.6 135.5 82.8
ADB funded RSDP 198.5 637.5 945.7 704.8
Total Expenditure 362.6 1209.0 1352.0 1085.1
% by Provincial GDP 0.04 0.11 0.09 0.06
% by National GDP 0.02 0.06 0.05 0.03
4-20
Table 4-28: Capital Expenditure on National Roads vs GDP in UP
Source/Program Expenditure (Rs. Mn)
2004 2005 2006 2007
SIRUP 28.7 25.7 36.1 21.9
Highway Development 333.4 1514.8 2380.8 5446.1
Total Expenditure 362.1 1540.5 2416.9 5468.0
% by Provincial GDP 0.47 1.66 1.93 3.40
% by National GDP 0.02 0.07 0.08 0.15
Table 4-29: Capital Expenditure on Provincial Roads vs GDP in UP
Source/Program Expenditure (Rs. Mn)
2004 2005 2006 2007
PSDG 123 200 173.4 106.3
ADB funded RSDP 349.0 349.0 349.0 349.0
Total Expenditure 472.0 549.0 522.4 455.3
% by Provincial GDP 0.62 0.59 0.42 0.28
% by National GDP 0.03 0.03 0.02 0.01
5-1
5 Maintenance Expenditure for Roads (2004-2007)
5.1 National Roads
All the maintenance functions are funded through Road Maintenance Trust Fund (RMTF) as
mentioned earlier. Based on a schedule prepared by assessing the network condition, a pre-defined
amount of allocation for each divisional office is released by RDA after assessing the value of
executed maintenance functions.
5.1.1 Western Province
Annual allocation and expenditure for road maintenance in WP during the period 2004 to 2007 is
given in Table 5-1.
Table 5-1: Periodic and Routine Maintenance of National Roads (RMTF), WP47
SL Rs. Millions
2004 2005 2006 2007
Allocation 95.0 282.0 317.5 342.8
Expenditure 128.0 290.1 291.9 317.0
When required, the RDA inter-changes funds between two separate works and hence original
allocation for those works are changed. Through this criterion, in year 2004 and 2005 the RDA
has allocated additional funds for Western Province road maintenance work. Thereby the actual
expenditure in both these years was increased compared to the original allocation.
In addition to the funds from the RMTF there was a separate program in place until the year 2006
for maintaining roads rehabilitated under ADB assistance.
Table 5-2: Maintenance of roads rehabilitated under ADB assistance
Rs. Millions
2004 2005 2006
Allocation 2.00 3.27 3.27
Expenditure 0.60 0.001 0.11
The RDA separately allocates funds for bridge maintenance on its national roads. Allocation and
Expenditure under bridge maintenance funding in WP is given in Table 5-3
47 Source: Road Development Authority- Planning Division
5-2
Table 5-3: Maintenance of Bridges on National Roads (RMTF), WP48
SL Rs. Millions
2004
All Island
2005
All Island
2006 2007
UP UP
Allocation 50.0 50.0 17.0 28.0
Expenditure 38.7 46.5 5.0 8.8
5.1.2 Uva Province
As in the case of Western province, the maintenance functions are funded through Road
Maintenance Trust Fund (RMTF). Annual allocation and expenditure for road maintenance in UP
during the period 2004 to 2007 is given in Table 5-4.
Table 5-4: Periodic and Routine Maintenance of National Roads (RMTF), UP49
SL Rs. Millions
2004 2005 2006 2007
Provincial Allocation 72.2 196.0 288.5 290.8
Provincial Expenditure 72.1 104.5 145.9 167.0
Allocation and Expenditure under bridge maintenance in UP is given in Table 5-5
Table 5-5: Maintenance of Bridges on National Roads (RMTF), UP50
SL Rs. Millions
2004
All Island
2005
All Island
2006 2007
UP UP
Allocation 50.0 50.0 18.0 16.0
Expenditure 38.7 46.5 7.2 12.5
5.2 Provincial Roads
Road maintenance of Western and Uva provincial road networks are executed by the Provincial
Road Development Authority (PRDA) and Road Development Department (PRDD) respectively.
These two agencies are assisted by their divisional offices in carrying out the maintenance
functions.
48 Source: Road Development Authority-Planning Division 49 Source: Road Development Authority- Planning Division 50 Source: Road Development Authority-Planning Division
5-3
5.2.1 Western Province
The PRDA has introduced a package based periodic maintenance scheme especially with the
intention of effective handling of the funds available to the Authority. In this program the PRDA
releases funds continuously to respective divisional offices under the number given to a specific
package until the work is completed. Selection and prioritizing of roads is done using the
software of Road Maintenance Management System (RMMS) which was introduced by ADB
funded RSDP. Execution of such work is done through local contractors selected following
government procurement guidelines.
Routine maintenance is executed by using direct labor force and machinery available with the
PRDA and its divisional offices. This work is performed under the supervision of divisional
heads.
Though the PRDA maintains an Authority Fund which is financed through authority revenue,
recurrent expenses including road maintenance is mainly covered by the finance provided by the
Provincial Council Recurrent Grant (PCRG). The Central Government Block Grant and
Provincial revenue are the sources of Provincial Council Recurrent Grant. Around 50% of
recurrent expenses of the PRDA are allocated for the maintenance of capital assets which include
road maintenance expenditure. Table 5-6 illustrates the road maintenance allocations and
expenditures incurred during the period of 2004 to 2008.
Table 5-6: Utilization of Road Sector Maintenance Funds, Western Province51
Source Rs Million
2004 2005 2006 2007 2008
PCRG- Road Maintenance
Component
Allocation 80.00 120.00 120.00 200.00 520.00
Expenditure 92.62 131.09 212.95 200.00 560.00
Utilization (%) 115.8% 109.2% 176.7% 100% 107.7%
Though imprest released by the central government in terms of block grant is poor, it is observed
in Table 5-6 that in most years, the PRDA’s expenditure is higher than budgetary allocation
provided for road maintenance. This is because the PRDA unlike and other PC is capable of
providing additional funding requirements through their Authority Fund until the allocation is
received so that work program is uninterrupted and is completed even though all the required
funds have not been allocated by the Treasury. Once the following year’s allocation is received,
the portion of expenses advanced from the Authority Fund is compensated.
51 Source: Provincial Road Development Authority, Western Province
5-4
5.2.2 Uva Province
The PRDD’s recurrent expenses through which road maintenance is carried out are met through
the Block Grant provided by the Treasury. There are no funding sources available with PRDD
such as Authority Fund in Western Province. The recurrent expenditure of the PRDD includes
personal emoluments, traveling expenses, supplies, contractual services and maintenance
expenses etc. More than 50% of the block grant provided to the PRDD is used for maintenance
expenses through which routine allocations such as for contracted labourers are made.
Table 5-7: Recurrent Expenditure of PRDD, Uva Province, 200752
Rs.’000
Recurrent Expenditure 2006 Actual 2007 Estimate 2008 Estimate
Personal Emoluments 22,594.0 35,226.0 34,268.0
Traveling Expenses 1,661.0 2,000.0 3,000.0
Supplies 1,282.0 3,669.0 3,250.0
Maintenance Expenditure 26,456.0 62,065.0 53,725.0
Contractual Services 736.0 1,296.0 2,100.0
Transfers 341.0 600.0 1,000.0
Other Recurrent Expenditure - 60.0 80.0
Total 53,070.0 104,916.0 97,423.0
By comparing the allocations for maintenance with the values appearing in Table 5-7, it is
envisaged that more than 90% of the above maintenance expenses voted for the RDD are utilized
for routine road maintenance activities. Other maintenance such as vehicles and building gets
around 10%.
Table 5-8: Utilization of Road Sector Maintenance Funds, Uva Province53
Source Rs Million
2004 2005 2006 2007 2008 Oct.
Block Grant- Road
Maintenance Component
Allocation 40.0 40.0 50.0 60.0 50.0
Expenditure 27.0 26.8 24.8 46.8 13.6
Utilization (%) 67.5 67.0 49.6 78.0 27.2
Table 5-8 shows the utilization of the PSDG by the PRDD of Uva Province. There are several
reasons attributed to the low utilization, the highest of which is recorded as 78% in 2007. These
reasons are:
(i) Since there are several programs undertaken by different provincial agencies under the
PSDG other than the roads program, the low utilization of those programs locks up funds
within the province and the Treasury does not release funds when what is already allocated
52 Source: Financial Statement 2008, Uva Provincial Council 53 Source: Planning Division of Road Department, Uva Province
5-5
to the entire province is not utilized. This problem has apparently been sorted out since
2007, as funds are now released by the Chief Secretary on the basis of bills in hand as
opposed to passing on the block allocations in their entirety.
(ii) Another reason attributed is that the Treasury does not release the imprest required to
award contracts. As such often programs cannot be awarded even though the tender is
ready. Sometimes the delay in receiving the imprest, delays the payment for work already
carried out. This leads to problems in retaining good contractors as well.
(iii)Furthermore it was pointed out that the allocations are not released for several months at
the beginning of the year. As a result, the period of time available for completion of work
is less. Delays also result in unattended damages increasing. This in turn increases the
maintenance burden.
(iv) Moreover the monsoonal rains that arrives in the months of May to September also
interferes with the work and progress in utilization is difficult when funds are not received
at the beginning of the year.
5.3 Local Authority Roads
Local governments do not follow a rational policy or methodology for allocating funds for road
maintenance as discussed in Chapter 3. The funding available for local road maintenance is
studied at the Municipal Council (MC), Urban Council (UC) and Pradeshiya Sabha (PS) levels.
For this purpose, respective officials and sources in selected local governments in both provinces
were interviewed and information was collected on personal basis.
5.3.1 Western Province
Colombo MC, Dehiwala-Mt. Lavinia MC, Horana UC, Minuwangoda UC, Divulapitiya PS and
Bulathsinghala PS were selected as samples representing the Local Authorities in WP. The
following are some of the important features and issues that were found during the
survey/interviews.
5.3.1.1 Colombo Municipal Council
• The Colombo Municipal Council maintains 370 km of asphalt/tarred roads. The type and
condition of the network is given in the following table.
Table 5-9: Type and Condition of Roads in CMC54
54 Source: Budget 2009, Badulla Municipal Council
5-6
Type of Road
Total
Kms
% of Length by
Present Road
Condition
Good Fair Poor
Metalled and Tarred (intermediate lane 4 to 6 metres) 126 30 70
Metalled and Tarred (two lanes over 6 metres) 66 40 60
Asphalt Surface (intermediate lane 4 to 6 m) 195 40 60
Asphalt Surface (two lanes over 6 m) 93 35 40 25
• Additionally, the council also maintains 2 bridges, 80 culverts, 45 signalized junctions as other
road related assets.
• Actual revenue of the council for the year 2007 was Rs 74.59 mn. It is estimated to increase
up to Rs 184 mn for the year 2009.
• Allocation for road sector periodic and routine maintenance is made through Council revenue.
Table 5-10 shows the earned revenue and its allocation for road maintenance. It should be noted that the road sector allocations for CMC exclude salaries to the employees in road sector of the Council.
Table 5-10: Colombo Municipal Council Road Sector allocation
Rs Million
2004 2005 2006 2007 2008
Revenue collected 2,619.2 3,246.4 3,988.6 3,500.4 4,063.5
Road Sector Allocation 450.6 422.6 456.4 433.2 543.4
• Road selection for periodic maintenance is mainly based on road condition measured in road
roughness and political influence.
5.3.1.1 Dehiwala-Mt. Lavinia Municipal Council
• The Dehiwala- Mt Lavinia Municipality which is in Colombo district maintains 180 km of
asphalt/tarred roads and 12 km of gravel roads. It is reported that 50% of the network in good
condition while 10% is reported to be in poor condition. Remaining 40% is in motorable
condition but not considered as being satisfactory.
• Additionally, the council also maintains 10 bridges and 150 culverts.
• Estimated recurrent revenues of the council for 2007 and 2008 are Rs. 618.6mn and Rs. 752.2
mn respectively.
• Allocation for road sector periodic and routine maintenance is made through Council revenue.
Table 5-11 shows allocation for road maintenance.
5-7
Table 5-11 : Road Maintenance Cost, Dehiwala-Mt. Lavinia Municipal Council55
Year 2004 2005 2006 2007 est.
Maintenance Cost (Rs.mn.) 21.66 17.70 30.13 30.00
5.3.1.2 Horana Urban Council
• Road network in the Horana UC in the Kalutara district consists of 17.54 km of tarred roads
and 4.60 km of concrete roads. Around 90% of the length of the total network is reported to be
in good condition. These roads are generally access roads for public and administrative places
in the city on which there are no public transport services at present.
• Additionally the council maintains 2 bridges and 10 culverts.
• Road maintenance is funded through the recurrent revenue of the council. Recurrent revenue
and its road maintenance cost component are illustrated in Table 5-11. Road maintenance
costs include maintenance of the machinery as well. However 75-80% of this maintenance
cost is spent directly on road maintenance items such as material, fuel and casual labour.
Table 5-12: Road Maintenance Cost, Horana Urban Council56
Year 2005 2006 2007 2008 est.
Recurrent Revenue (Rs.) 24,618,353 26,010,618 34,675995 60,620,832
Maintenance cost (Rs.) 4,705649 9,671146 2,384855 16,000,000
5.3.1.3 Minuwangoda Urban Council
• The road network in Minuwangoda UC in Gampaha District consists of 17.47 km of tarred
roads, 1.03 km of concrete roads and 0.5 km of gravel roads. About 65-70% of the network is
reported to be in good condition.
• Additionally, the council maintains 3 bridges and 30 culverts.
• Actual recurrent revenue of the council including Central Government grants was Rs.23.85
mn in 2006. This is estimated to increase to Rs 24.10 mn and Rs. 29.50 mn for year 2007 and
2008 respectively.
• Road maintenance expenditure during the period of 2004 to 2007 is as follows. These amounts
include material, fuel and casual labour costs only.
55 Source: Haputale Urban Council 56 Source: Horana Urban Council
5-8
Table 5-13: Road Maintenance Cost, Minuwangoda Urban Council57
Year 2004 2005 2006 2007 est. 2008 est.
Maintenance cost(Rs.) 563,151 1,443,421 158,010 295,000 305,000
• Decrease in road maintenance financing is observable due to road condition improvement.
5.3.1.4 Divulapitiya Pradeshiya Sabha
• The road network in the Divulapitiya PS in Gampaha district consists of 55.68 km of tarred
roads and 284.06 km of gravel roads according to records prepared before concreting of roads
in 2006. In recent years 10-15 km of the network has been concreted. Overall, about 55-60%
of the network is reported to be in good condition.
• Actual recurrent revenue of the council including grants received from Central Government
was Rs.62.67 mn in 2007. This is estimated to increase to Rs 77.95 mn in 2008 including a Rs.
10 mn domestic loan to purchase heavy machinery.
• Rs 2.39 mn was spent for road maintenance in 2007. This has increased to Rs. 6.75 mn in
2008. Additionally, the PS received a Rs. 4.1 mn allocation for pot hole patching in year 2008.
5.3.1.5 Bulathsinhala Pradeshiya Sabha
• Since Bulathsinhala Pradeshiya Sabha in Kalutara district has been established more recently,
the length of the road network is yet to be finalized. But it is estimated to be about 90 km in
which 70-75% of the length is gravel surfaced. Most of roads are in poor condition due to
regular flooding in the area.
• The actual revenue of the council including Central Government grants was Rs. 29.56 mn in
2007. This is estimated to increase up to Rs 70.20 mn for year 2009.
• Funding for road maintenance is allocated through the recurrent revenue of the Pradeshiya
Sabha.
• Road maintenance expenditure during the period 2005 to 2007 is as follows. These amounts
include material, fuel and casual labour costs only.
Table 5-14: Road Maintenance Cost, Bulathsinghala Pradeshiya Sabha58
Year 2005 2006 2007
Maintenance cost (Rs.) 176,879 98,028 500,000
57 Source: Horana Urban Council 58 Source: Bulathsinghala Urban Council
5-9
5.3.2 Uva Province
Badulla MC, Bandarawela UC, Haputale UC, Passara PS and Monaragala PS were selected as
samples for representing Uva Provincial Local Governments. Following are the important issues
raised in terms of local road sector financing.
5.3.2.1 Badulla Municipal Council
• Badulla Municipal Council maintains 47.54 km of asphalt/tarred roads, 21.53km of gravel
roads and 14.57 km of other roads. About 75% of the network is presently reported to be in
good condition.
• Additionally, the council also maintains 0.57 km of footways, 73.60 km of drains, 170 culverts
and 13 bridges.
• Actual revenue of the council was Rs 74.59 mn for the year 2007. It is estimated to increase to
Rs 184 mn in 2009.
• The Council Budget for 2009 for roads is as shown follows.
Table 5-15: Head of Roads of Badulla Municipal Council Budget59
Category 2007 Actual
(Rs.)
2008 Est.
(Rs.)
2009 Est.
(Rs.)
Recurrent Expenditure
(Personnel emoluments, Travel expenses
supply and equipments etc.)
14,329,984 20,711,000 30,851,000
Capital Expenditure - 11,200,000 16,795,000
(Material, equipment and road development)
Total 14,329,984 31,911,000 47,646,000
• Recurrent expenditure in year 2007 can be considered as routine maintenance expenditure
unless there are funds for capital work.
• In year 2008 and 2009 funding allocations were Rs 31.9mn and Rs 47.65 mn respectively.
These were available for periodic maintenance of roads by the Council.
5.3.2.2 Haputale Urban Council
• Road network of Haputale UC in Badulla district consists of 5 km of tarred roads, 1.26 km of
concrete roads and 0.6 km of gravel roads.
• Actual recurrent revenue of the council including grants from central Government was
Rs.13.26 mn in 2006. This is estimated to increase to Rs 15.64 mn and Rs. 16.59 mn for year
2007 and 2008 respectively.
59 Source: Budget 2009, Badulla Municipal Council
5-10
• Road maintenance expenditure during the period of 2004 to 2007 is as follows. These amounts
include material, fuel and casual labour costs only.
Table 5-16: Road Maintenance Cost, Haputale Urban Council60
Year 2004 2005 2006 2007 2008
Maintenance cost(Rs.) 10,140 51,263 16950 - 10,094
5.3.2.3 Bandarawela Urban Council
• The road network in the Bandarawela UC in Badulla district is made up of 15.6 km of
tarred roads, 1 km of concrete roads and 4 km of earth roads. About 80% of the network is
reported to be presently in good condition
• Road maintenance expenditure during the period of 2004 to 2007 is as follows. These
amounts include material, fuel and casual labour costs only.
Table 5-17: Road Maintenance Cost, Bandarawela Urban Council61
Year 2004 2005 2006 2007 2008
Maintenance cost(Rs. mn) 1.75 6.15 est. N/A 3.82 9.5 est
5.3.2.4 Passara Pradeshiya Sabha
• The road network in Passara PS in Badulla district consists of 90 km of tarred roads, 113
km of gravel roads, 2 km of concrete roads and 34.2 km of earth roads. Presently 60% of
the network is reported to be in good condition.
• Actual recurrent revenue of the Pradeshiya Sabha including grants from Central
Government was Rs 34.86 mn in 2007. The estimated revenue for year 2009 is Rs 44 mn.
• Road maintenance expenditure during the period of 2004 to 2007 is as follows. These
amounts include material, fuel and casual labour costs only.
Table 5-18: Road Maintenance Cost, Passara Pradeshiya Sabha62
Year 2004 2005 2006 2007 2008
Maintenance Cost (Rs. mn) 3.23 3.41 4.15 6.18 2.79
60 Source: Haputale Urban Council 61 Source: Bandarawela Urban Council 62 Source: Passara Pradeshiya Sabha
5-11
5.3.2.5 Monaragala Pradeshiya Sabha
• The road network in the Monaragala PS in Monaragala district consists of 56.2 km of
tarred roads, 362 km of gravel roads and 13.7 km of concrete roads. Approximately 40%
of the network in good condition.
• Actual revenue of the Pradeshiya Sabha was Rs 27.99 mn in 2007. This includes revenues
collected by the Pradeshiya Sabha and Grants received from the Central Government.
• Rs 2.31 mn and Rs 2.85 mn has been spent for road maintenance in 2007 and 2008
respectively.
6-1
6 Analysis of Expenditure
This chapter provides selected analysis of the expenditure patterns as stipulated in the Terms of Reference.
6.1 Trends (2004-2007)
The analysis of trends in expenditure for each of the two provinces for the period 2004 to 2007 is given in Tables 6-1 and 6-2. In calculating total revenues and expenditure of the Local Authorities, the per km costs for the sample councils and PSs have been used to estimate a total for the entire province. Moreover, the expenditure reported in these tables, do not include spending on RDA projects that span across more than one province.
Table 6-1: Total Expenditure on all Roads in Western Province (2004-2007)
Description Source of Funding
Rs. Million
2004 2005 2006 2007
Maintenance Expenditure 745.7 938.8 1027.4 1032.6
National Roads RMTF 132.3 295.3 291.9 317.0
Provincial Roads Block Grant 92.6 131.1 213.0 200.0
Local Authority Roads Colombo Municipal Council Revenue 135.2 126.8 136.9 130.0
Revenue of Municipal/Urban Councils 321.5 321.5 321.5 321.5
Pradeshiya Sabha Revenue 64.1 64.1 64.1 64.1
Capital Expenditure 921.4 2324.7 2489.5 2764.3
National Roads SIRUP 480.6 961.8 600.1 925.2
Provincial Roads PSDG-Provincial Roads 135.2 216.7 247.1 271.9
Other Central Government Fund 1.5 161.6 20.2 23.0
Provincial Council Fund 27.4 133.6 3.5 2.6
Tsunami road rehabilitation 59.6 135.5 82.8
RSDP 198.5 637.5 945.7 704.8 Local Authority Roads PSDG N/A 17.9 158.9 138.0
DCB 60.0 60.0 60.0 60.0
Maga Neguma 18.2 76.0 315.8 256.0
Gama Neguma 2.7 300.0
Total 1667.1 3263.6 3516.9 3796.9
In the case of the WP the following conclusions can be made:
1. Central Government funding of local roads is highly inconsistent.
2. There are constant changes to development programs and institutions handling
development and implementation of such development of rural roads.
3. The maintenance expenditure has increased at 8.5% p.a. from Rs 745 million in 2004 to Rs
1032.6 million in 2007. Since construction cost inflation during this period has been
around 15% p.a. it has been in effect a decrease in real terms.
6-2
4. The capital expenditure has increased at 31.6% p.a. from Rs 921.2 million in 2004 to Rs
2,764 million in 2007. There has been a real term increase in capital expenditure.
5. However the capital expenditure has been mostly in the foreign funded SIRUP program
and the ADB funded RSDP project as well as in the concreting of local authority roads
under the Maga Neguma program.
6. The value of capital work under the RDAs work programs for projects that are not
considered under the works project but under one of its PMUs such as Alternate Trunk
Roads, Expressway Projects as well as Flyovers and Bridges have not been included in this
analysis. The value of the work executed under these projects varies sharply from year to
year and does not demonstrate a trend. On average there is spending of between Rs 3 to 5
billion per year in the WP on such projects, all of which are foreign funded.
Table 6-2: Total Expenditure on all Roads in Uva Province (2004-2007)
Description Source
Rs. Million
2004 2005 2006 2007
Maintenance Expenditure 154.0 187.1 228.5 276.9
National Roads RMTF 76.4 109.7 153.1 179.5
Provincial Council
Roads Block Grant 27.0 26.8 24.8 46.8
Local Authority Roads Municipal Council Revenue 12.0 12.0 12.0 12.0
Urban Council Revenue 3.1 3.1 3.1 3.1
Pradeshiya Sabha Revenue 35.5 35.5 35.5 35.5
Capital Expenditure 540.3 641.7 786.8 1,285.4
National Roads SIRUP 28.7 25.7 36.1 21.9
Provincial Council
Roads PSDG 123.0 200.0 173.4 106.3
RSDP 376.3 376.3 376.3 376.3
Local Authority Roads PSDG N/A 5.3 27.3 35.8
DCB 11.1 11.1 11.1 11.1
Maga Neguma 1.2 23.3 72.5 97.2
Gama Neguma 2.0 283.6
RSAP 156.7
Uva Wellassa 88.0 196.5
Total 694.3 828.8 1,015.2 1,562.3
In the case of the UP the following conclusions can be made:
1. Central Government funding of local roads is highly inconsistent.
2. There are constant changes to development programs and institutions handling
development and implementation of such development of rural roads.
3. The maintenance expenditure has increased at 15.8% p.a. from Rs 154 million in 2004 to
Rs 276 million in 2007. Since construction cost inflation during this period has been
around 15% p.a. here has not been an increase in real terms.
6-3
4. The capital expenditure has increased at 22.5% p.a. from Rs 694 million in 2004 to Rs
1,562 million in 2007. There has been a real term increase in capital expenditure.
5. However the capital expenditure has been mostly in the concreting of local authority roads
under the Maga Neguma, Maga Neguma and other programs.
6. The value of capital work under the RDAs work programs for projects that are not
considered under the works project but under one of its PMUs such as improvements to
the truck roads have not been included in this analysis. The value of the work executed
under these projects varies sharply from year to year and does not demonstrate a trend. On
average there is spending of around Rs 500 per year in the UP on such projects, all of
which are foreign funded.
6.2 Analysis of Maintenance Expenditure
6.2.1 National Roads
The National Road network including its bridges is maintained through the RMTF allocation. The
following table shows trends in road maintenance expenditure during the period of 2004 to 2007.It
can be seen from Table 6-3 that the per km cost as well as the per capita cost on the network has
increased at around 35% p.a. well ahead of construction cost inflation for this period. However as
noted in the previous section also, the per km and the per capita cost for both WP and UP has
increased at lesser rates and below that required to indicate an increase in real economic terms.
In terms of maintenance funds spent per road km in the province irrespective of road category, as
well as spending per capita, both WP and UP fall significantly below the national average.
6-4
Table 6-3: Maintenance Financing of National Roads through RMTF
Year 2004 2005 2006 2007
Na
tio
nal
Expenditure (Rs.) 1,034,050,000 1,789,119,000 2,932,665,000 3,409,850,000
Expenditure/km (Rs./km)
88,599.95 153,296.12 251,277.95 292,164.34
Expenditure/ Capita (Rs.) 55.15 95.42 156.41 181.86
Wes
tern
Expenditure(Rs.) 132,300,000 295,300,000 291,900,000 317,000,000
% by National 12.79 16.51 9.95 9.30
Expenditure/km (Rs./km) 87,557.91 195,433.49 193,183.32 209,794.84
Expenditure/Capita (Rs.) 24.59 54.88 54.25 58.91
Uva
Expenditure(Rs.) 76,400,000 109,700,000 153,100,000 179,500,000
% by National 7.39 6.13 5.22 5.26
Expenditure/km (Rs./km) 66,377.06 95,308.43 133,014.77 155,951.35
Expenditure/Capita(Rs.) 64.91 93.20 130.08 152.51
6.2.2 Provincial Roads
Provincial Roads are annually funded by block grants provided by the central government. Table
6-4 shows the trends in maintenance expenditure of both WP and UP when compared with North
Central and Eastern Provinces. It can be seen that WP and UP are two provinces that have seen an
increased in maintenance funding for provincial roads over the period 2004 to 2007 when
compared to NCP and EP, two provinces which have seen a reduction.
6-5
Table 6-4: Maintenance Financing of Provincial Roads through Block Grant
Year 2004 2005 2006 2007
No
rth
Cen
tral Expenditure 30,800,000 19,400,000 73,800,000 15,900,000
Expenditure/km 15,786.78 9,943.62 37,826.76 8,149.67
Expenditure/ Capita 26.92 16.96 64.51 13.90
Wes
tern
Expenditure 92,620,000 131,090,000 212,950,000 200,000,000
% by National
Expenditure/km 46,896.20 66,374.68 107,822.78 101,265.82
Expenditure/Capita 17.21 24.36 39.57 37.17
Uv
a
Expenditure 27,000,000 26,800,000 24,800,000 46,800,000
% by National
Expenditure/km 15,508.33 15,393.45 14,244.69 26,881.10
Expenditure/Capita 22.94 22.77 21.07 39.76
East
ern
Expenditure 31,700,000 15,900,000 40,900,000 19,800,000
% by National
Expenditure/km 28,870.67 14,480.87 37,249.54 18,032.79
Expenditure/Capita 21.13 10.60 27.27 13.20
6.2.3 Local Authority Roads
Local Authority roads are maintained using revenue of the respective local governments. Since
maintenance expenditure on roads differs drastically between MCs, UCs and PSs, the following
summary table of approximate averages has been prepared based on the samples collected.
Table 6-5: Road Maintenance of Local Authorities Financed through Revenue Collected
(averages)
Year Western Uva
Rs per year Rs per km Rs per year Rs per km
Colombo Municipal Council 132,200,000 275,417
Other MCs in WP 146,318,125 120,625
Badulla Municipal Council 12,000,000 143,472
Urban Councils 175,134,150 153,348 2,811,118 102,371
Pradeshiya Sabha 64,144,427 7,059 35,493,010 8,197
6-6
It can be observed that the maintenance spending across local authorities appear to be fairly
rational. The expenditure of heavier trafficked roads in CMC area is over Rs 275,000 per km,
while other MCs and UCs both in WP and in UP are in the range of between Rs 100,000 to Rs
150,000 per km. In the case of PSs, the expenditure on maintenance is much lower at between Rs
7,000 to 8,000 per km.
6.3 Analysis of Capital Expenditure
6.3.1 National Roads
Provincial level improvement and rehabilitation of the national road network is regularly carried
out under annual allocation made under SIRUP. Table6-6 shows that SIRUP funding has
increased significantly over the period 2004 to 2007 at around 38% p.a. which is well above
inflation rate. However this increase in WP has been much below the national average and just
above inflationary increases, while that of UP has been negative.
Table 6-6: Capital Expenditure on National Road under SIRUP
Year 2004 2005 2006 2007
Nati
on
al
Expenditure 1,107,619,000 2,507,048,000 3,001,253,000 4,581,821,000
Expenditure/km 94,903.52 214,810.04 257,154.74 392,581.70
Expenditure/ person 59.07 133.71 160.07 244.36
Wes
tern
Expenditure 480,600,000 961,800,000 600,100,000 925,200,000
% by National 43.39 38.36 19.99 20.19
Expenditure/km 318,067.50 636,532.10 397,154.20 612,309.73
Expenditure/Capita 89.31 178.74 111.52 171.94
Uv
a
Expenditure 28,700,000 25,700,000 36,100,000 21,900,000
% by National 2.59 1.03 1.20 0.48
Expenditure/km 24,934.84 22,328.41 31,364.03 19,026.93
Expenditure/Capita 24.38 21.84 30.67 18.61
6.3.2 Provincial Roads
The capital expenditure of the provincial road network is funded mostly through the PSDG-
provincial road component. Though there have been several other sources of capital funding such
as STAART, DCB, Maga Neguma projects providing financial assistance to provincial roads
during the last five years, they are not available on a regular basis. Therefore expenditure
assessment is carried out with respect to the regular funding source of PSDG. Table 6-7 shows
6-7
that the expenditure levels vary sharply between provinces. Comparing with NCP and EP, it is
seen that in 2007, WP has the highest allocation per km, while UP has the lowest even though UP
had the highest in 2004. In terms of per capita spending NCP, a province with low population
density has high expenditure per person, while WP becomes the lowest.
Table 6-7: Capital Expenditure on Provincial Road under PSDG
Year 2004 2005 2006 2007
No
rth
Cen
tral Expenditure 112,500,000 170,200,000 192,800,000 170,000,000
Expenditure/km 57,662.74 87,237.31 98,821.12 87,134.80
Expenditure/ Capita 98.34 148.78 168.53 148.60
Wes
tern
Expenditure 135,200,000 216,700,000 247,100,000 271,900,000
% by National
Expenditure/km 68,455.70 109,721.52 125,113.92 137,670.89
Expenditure/Capita 25.13 40.27 45.92 50.53
Uva
Expenditure 123,000,000 200,000,000 173,400,000 106,300,000
% by National
Expenditure/km 70,649.05 114,876.51 99,597.93 61,056.86
Expenditure/Capita 104.50 169.92 147.32 90.31
East
ern
Expenditure 40,000,000 75,300,000 56,200,000 85,400,000
% by National 7.39 6.13 5.22 5.26
Expenditure/km 36,429.87 68,579.23 51,183.97 77,777.78
Expenditure/Capita 26.67 50.20 37.47 56.93
6.3.3 Local Authority Road
Local Authority roads are also funded by PSDG-local authority road component on a regular
basis. This funding is analyzed in Table 6-8.
7-8
Table 6-8: Capital Expenditure on Local Road under PSDG
Year 2005 2006 2007
Na
tio
nal
Expenditure 193,600,000 488,246,000 401,974,000
Expenditure/km 2,994.17 7,551.09 6,216.83
Expenditure/ Capita 10.33 26.04 21.44 W
este
rn Expenditure 17,900,000 158,900,000 138,000,000
% by National 9.25 32.55 34.33
Expenditure/km 1,501.30 13,327.18 11,574.27
Expenditure/Capita 3.33 29.53 25.65
Uv
a
Expenditure 5,260,000 27,320,000 35,800,000
% by National 2.72 5.60 8.91
Expenditure/km 1,182.82 6,143.47 8,050.37
Expenditure/Capita 4.47 23.21 30.42
In addition local authority roads are now regularly funded by DCB, Maga Neguma and Gama
Neguma Programs. Maga Neguma and Gama Neguma investments continuously increased
significantly in following years. Since this funding is only starting it is difficult to show any trends
in the expenditure.
7 Conclusions & Recommendations The following summary conclusions and recommendations are made:
1. The period of review from 2004 to 2007 shows a sharp increase in capital expenditure in
both WP and UP for improvement and rehabilitation of roads at all three levels of the road
network.
2. Most of this increase has come from increased donor agency funding for the national and
provincial road sector as well as domestic and donor funding for rural roads.
3. Government has taken specific policy intervention to improve rural accessibility by
concreting sections of rural roads across the country. This expenditure has increased
several-fold since 2004. As a result capital expenditure on rural roads has increased per
capita and it has also become more equitable across the country.
4. Provincial roads continue to depend heavily on funding from Central Government. Only
the Western Province spends substantially on its provincial road network.
7-9
5. The WP has setup an Authority Specific Fund which is used as an advance account to
complete projects when Central Government Funds get delayed. In other provinces most
allocated funds do not get fully utilized due to delays in receiving imprest.
6. There is no evidence that capital expenditure on roads at any level of the network either
from donor or domestic funding is implicitly tied to specific developmental projects or
plans.
7. Overall maintenance spending though increased in current value, demonstrates a reduction
per km in real terms. Even the Road Maintenance Trust Fund, the contribution to which
has not been increased since its inception, has not been able to achieve this due to its
management intervention authority being limited to being only an account.
8. The maintenance of national roads are based on an assessment of condition and the RDA
is able to follow general routine maintenance schedules under the proper technical
applications and supervision.
9. The maintenance spending on roads in some provinces appear to have reduced sharply in
real terms. This demonstrates the absence of a minimum level of funding for roads which
should be ensured as in the case of other expenses such as salaries etc. Hence it is
recommended that maintenance of roads be included in budgets as a recurrent item.
10. The irregularity of maintenance funding results in even allocated funds been under
utilized. This does not lead to preventative maintenance. Hence all maintenance
interventions are made more expensive. Such inconsistent funding patterns leads to poor
efficiency of public expenditure as scientifically determined maintenance schedules cannot
be observed so that cost are kept low and serviceability at an optimum. Only the WP has
developed an assessment based maintenance expenditure plan.
11. The general capacity at provincial level to supervise new constructions or maintenance is
very low. A high proportion of cadre positions for technical staff remain vacant or are
filled by people with less than stipulated qualification or experience. There is also no
consistency across provinces on the equipment available for provincial road works.
7-10
12. The on going capital spending at all levels of the road network namely new expressways
and rehabilitation of national roads; rehabilitation of provincial roads and the concreting of
sections of rural roads would entail heavy maintenance. There does not seem to be
increased maintenance provision for the higher investments.
13. Funding of urban local authorities seems to be ignored by both donor as well as domestic
funding. This is likely due to the perception that urban areas are capable of raising their
own funds for maintenance. However analysis shows that even the bigger urban local
authorities can only raise 5 to 15% of the expenditure. Smaller UCs in Uva for example
are unable to raise even 1%. These urban local authority roads are very much dependent
on DCB funding.
7-11
Appendix I – Survey Forms
7-12
Public Expenditure Review on Road Sector-Local Authority Roads
Interviewee: Commissioner of Provincial Council (Steering agent of Gvnt. funds for Local
Authorities)
Objective: Identifying sources, level and trends in funding for local authority roads
1. Provincial Council:
2. Length of Road Network(if available)
3. Sources of funding available for Local Authority roads (Through Provincial Council for maintenance
and improvements-domestic, foreign, revenue etc.)
i. Municipal Councils
ii. Urban Councils
iii. Pradeshiya Sabhas
4. Funding for Road maintenance (2004-2008)
Source Rs Million
2004 2005 2006 2007 2008
a) Allocation
Expenditure
b) Allocation
Expenditure
c) Allocation
Expenditure
5. What is the Criterion of fund allocation for road maintenance for local authorities?
6. Funding for Road Construction/improvement (2004-2008)
Source Rs Million
2004 2005 2006 2007 2008
a) Allocation
Expenditure
b) Allocation
Expenditure
c) Allocation
Expenditure
Local Authority
Road Length (Kms)
Metal/Tar Gravel Concrete Total
Municipal Council
Urban Council
Local Authority
7-13
7. What is the Criterion of fund allocation for road construction/improvement for local authorities?
8. Is there a method for assessing the utilization of fund allocated through Provincial Budget?
9. Are there any local road improvement projects running directly under ministries other than M/PC &
LG? (Gama Neguma-Nation Building, Maga Neguma-Regional Development etc.). If so mention the
project, funding sources (domestic/Foreign) under each executing ministries. Also mention the role of
Authority in such projects
10. Documents to Collect
I. Provincial Budgets (2004-2008)
II. Any other sources of information relevant
7-14
Public Expenditure Review on Road Sector-Local Authority Roads
Interviewee: Local Authority (Executing agency of local road maintenance, construction &
improvement)
Objective:
Identifying the nature of the network,
Identifying sources, level and trends in funding for local authority roads
Identifying institutional arrangement, Personnel & Operational capacity
1. Provincial Council & Local Authority:
2. Road Length, Type and Condition
Type of Road
Total
Kms
% of Length by
Present Road
Condition
Good Fair Poor
Gravel/Earth Road (Single Lane – 2-4 metres)
Gravel/Earth Road (Intermediate Lane – 4-6 m)
Gravel/Earth Road (Two Lane – Over metres)
Metalled and Tarred (single Lane 2 to 4 m)
Metalled and Tarred (intermediate lane 4 to 6 lanes)
Metalled and Tarred (two lanes over 6 metres)
Asphalt Surface (intermediate lane 4 to 6 m)
Asphalt Surface (two lanes over 6 m)
DBST Surface (Single lange 4 to 6m)
3. What other road assets do you maintain?
a) Bridges (number) -
b) Culverts (approximate number) –
c) Traffic Signalized Junctions-
d) Other-
4. Funding handled by Authority for local road maintenance (channelled through PC and District
Secretariat)(2004-2008)
Source Rs Million
2004 2005 2006 2007 2008
a) Allocation
Expenditure
b) Allocation
Expenditure
7-15
c) Allocation
Expenditure
5. What is the road selection criterion maintenance?
6. Funding handled by Authority for local Road Construction/improvement (channelled through
PC and District Secretariat)(2004-2008)
Source Rs Million
2004 2005 2006 2007 2008
a) Allocation
Expenditure
b) Allocation
Expenditure
c)DCB Allocation
Expenditure
7. What is the road selection criterion for new construction/improvement?
8. Allocation for road sector through revenue of Local Authority.
Rs Million
2004 2005 2006 2007 2008
Revenue collected
Road Sector Allocation
9. Are there any local road improvement projects running directly under ministries other than
M/PC & LG? (Gama Neguma-Nation Building, Maga Neguma-Regional Development etc.).
If so mention the project, funding sources (domestic/Foreign) under each executing ministries.
Also mention the role of Authority in such projects
10. Capacity of the Local Authority
I. Personnel
7-16
Employees Cadre Available Remarks
Engineers
Technical Officers
Draughtsmen
Clerical
Quantity Surveyor
Computer Operator/Data Entry Assistants
II. Operational(Construction equipments and machineries)
III. Other Supporting Assets(Office equipment & machineries)
11. Method of construction and maintenance of roads(by direct labor or contracting)
12. Cost estimates per km
Per km
Metal/Ta
r
Gravel Concrete Total
New construction
Improvement/Rehabilitation
Periodic Maintenance
Routine Maintenance
13. Documents to Collect
I. Budgets of Local Authority (2004-2008)
II. Road list
III. Organizational Chart
IV. Any other sources of information relevant
7-17
Public Expenditure Review on Road Sector-Provincial Roads
Interviewee: Provincial Road Development Authority
1. Name of Province:
2. Total km of Provincial Roads:
3. Capital Expenditure Allocated for Provincial Roads (2004-2008):
Source Rs Million
2004 2005 2006 2007 2008
Through Finance Commission
a) Criteria Based Grants
b) Matching Grants
c) Project Specific Development
Grants (PSDG)
d) Other
Through Other Central Govt Sources
Provincial Council Funds
Direct Foreign Funding
7-18
4. Capital Expenditure Utilized for Provincial Road 2004-2008:
Source Rs Million
2004 2005 2006 2007 2008
Through Finance Commission
a) Criteria Based Grants
b) Matching Grants
c) Project Specific Development
Grants (PSDG)
d) Other
Through Other Central Govt Sources
Provincial Sources
Direct Foreign Funding
5. Funds for Maintenance Available
Source Rs Million
2004 2005 2006 2007 2008
a)
b)
c)
6. Funds for Maintenance Utilized
Source Rs Million
2004 2005 2006 2007 2008
a)
b)
c)
7. Road Type and Condition
7-19
Type of Road
Total
Kms
% of Length by
Present Road
Condition
Good Fair Poor
Gravel/Earth Road (Single Lane – 2-4 metres)
Gravel/Earth Road (Intermediate Lane – 4-6 m)
Gravel/Earth Road (Two Lane – Over metres)
Metalled and Tarred (single Lane 2 to 4 m)
Metalled and Tarred (intermediate lane 4 to 6 lanes)
Metalled and Tarred (two lanes over 6 metres)
Asphalt Surface (intermediate lane 4 to 6 m)
Asphalt Surface (two lanes over 6 m)
8. Capacity of the Road Development Authority/Department
Employees Cadre Available Remarks
Engineers
Technical Officers
Draughtsmen
Clerical
Quantity Surveyor
Computer Operator/Data Entry
Assistants
9. What was your salary bill for 2007?
10. What other highway assets do you maintain?
e) Bridges (number)
f) Culverts (approximate number)
g) Other
11. Do you have a Design Office.? Yes/No
12. Do you have an approved method for selecting roads for rehabilitation or repair? Yes/No
13. How many computers do you have in working condition?
14. What proportion of the maintenance work is done in house?
15. What proportion of capital works is done in house?
7-20
16. What is the regular labour strength?
17. Give typical expenditure % as breakdown for maintenance activities
• Material –
• Labour –
• Equipment –
• Other
• Taxes
18. Give the different sources of funding raised as revenue by the Provincial Council by source
which are based on the use of transport highway facilities.
Source Rs Million
2004 2005 2006 2007 2008
a)
b)
c)
19. Details of foreign funded projects running under M/PC & LG
20. Are there any provincial road improvement projects running directly under ministries other
than M/PC & LG? (Gama Neguma-Nation Building, Maga Neguma-Regional Development
etc.). If so mention the project, funding sources (domestic/Foreign) under each executing
ministries. Also mention the role of Authority in such projects
7-21
Public Expenditure Review on Road Sector-National Roads
Interviewee: Road Development Authority (Executing agency of national road maintenance,
construction, rehabilitation & improvement)
Objective:
Identifying the nature of the network,
Identifying sources, level and trends in funding for national roads
Identifying institutional arrangement, Personnel & Operational capacity
1. Province:
2. Road Length, Type and Condition
Type of Road
Total
Kms
% of Length by
Present Road
Condition
Good Fair Poor
Gravel/Earth Road (Single Lane – 2-4 metres)
Gravel/Earth Road (Intermediate Lane – 4-6 m)
Gravel/Earth Road (Two Lane – Over metres)
Metalled and Tarred (single Lane 2 to 4 m)
Metalled and Tarred (intermediate lane 4 to 6 lanes)
Metalled and Tarred (two lanes over 6 metres)
Asphalt Surface (intermediate lane 4 to 6 m)
Asphalt Surface (two lanes over 6 m)
DBST Surface (Single lange 4 to 6m)
3. What other road assets do you maintain in the province?
h) Bridges (number) -
i) Culverts (approximate number) –
j) Traffic signalized junctions-
k) Other-
4. Funding for routine maintenance of national roads (2004-2008)
Rs Million
2004 2005 2006 2007 2008
Allocation
Expenditure
5. Funding for periodic maintenance of national roads (2004-2008)
7-22
Rs Million
2004 2005 2006 2007 2008
Allocation
Expenditure
6. What is the road selection criterion periodic maintenance?
7. Funding for new road/road assets(bridges, culverts etc.) construction (2004-2008)
Project Funding
Source
Rs Million
2004 2005 2006 2007 2008
Allocation
Expenditure
Allocation
Expenditure
Allocation
Expenditure
8. Funding for road/road assets rehabilitation and improvement(2004-2008)
Project Funding
Source
Rs Million
2004 2005 2006 2007 2008
Allocation
Expenditure
Allocation
Expenditure
Allocation
Expenditure
9. Are there any national road improvement projects running under different ministries other
than MOH? (Gama Neguma-Nation Building, Maga Neguma-Regional Development etc.). If
so mention the project, funding sources (domestic/Foreign) under each executing ministries.
Also mention the role of Authority in such projects
10. What is the road selection criterion for rehabilitation and improvements?
11. Capacity of the Road Development Authority-Provincial Office
I. Personnel
Employees Cadre Available Remarks
7-23
Engineers
Technical Officers
Draughtsmen
Clerical
Quantity Surveyor
Computer Operator/Data Entry Assistants
II. Operational(Divisional offices ,Construction equipments and machineries)
III. Other Supporting Assets(Office equipment & machineries)
12. Method of construction and maintenance of roads(by direct labor or contracting)
13. Cost estimates per km
Per km
Metal/Ta
r
Gravel Concrete Total
New construction
Improvement/Rehabilitation
Periodic Maintenance
Routine Maintenance
14. Documents to Collect
I. Road list in each province
II. Organizational Chart-Provincial Office & Head office
III. Any other sources of information relevant
7-24
Appendix II – Geo Referenced Maps