Provide and support mission ready Arctic Warriors from America’s premier Joint Base community 673d Air Base Wing Leadership Update JBER-Richardson Housing Privatization

Transcript of Provide and support mission ready Arctic Warriors from America’s premier Joint Base community 673d...

Provide and support mission ready Arctic Warriors from America’s premier Joint Base community

673d Air Base Wing

Leadership Update

JBER-Richardson Housing Privatization

673d Air Base Wing – Home of America’s Arctic Warriors

Project Status

• Schedule slipped with target award now 1 July 11• Possible early start of construction 1 Jun 11• No further relocations occurring in calendar year 2011• Pre-construction activity is occurring throughout JBER- Richardson housing community and Moose Crossing neighborhood

673d Air Base Wing – Home of America’s Arctic Warriors

Construction Schedule

2011

Cottonwood East (48)

Cottonwood South 390, 391,&393 (22)

Cottonwood East (88)

DEMOLITION

CONSTRUCTION & RENOVATION

Moose Crossing (156)

Moose Haven (36)

Cottonwood South (66) South Road

Moose Haven Reno (83) – No moves req

RELOCATIONS

Cottonwood East (48)

Cottonwood South 390, 391,&393 (22)

Kodiak (16)

• Target early start 1 Jun 11 or at award 1 Jul 11• No additional moves scheduled for CY11• Sites cleared in Moose Haven and Cottonwood• Demolition in Cottonwood East and South

Note: 1,142 units available at all times during construction

New construction Renovations in other neighborhoods

673d Air Base Wing – Home of America’s Arctic Warriors

Construction Schedule

2012

Cottonwood South “Y” road (78)

Raven Ridge (124)Birch Hill (16) Fireweed (16)

Independence East (60)

Independence East (24)

Cottonwood South (66) South Road

Cottonwood South (60) “Y” Road

Raven Ridge (80)

Birch Hill (17)

Fireweed (16)

Moose Haven Reno (83) – No moves

Cottonwood East (88)

Moose Crossing (156)

DEMOLITION

Note: 1,142 units available at all times during construction

• New construction completed in Kodiak, Moose Haven, Cottonwood and Moose Crossing• Relocation into newly constructed homes will be phased as they come online• Relocation coordination will be well in advance

Kodiak (16)

Moose Haven (36)

Cottonwood North (51)

RELOCATIONS

New construction New construction completed Renovations in other neighborhoods

673d Air Base Wing – Home of America’s Arctic Warriors

Construction Schedule

2013

Cottonwood North (40) Cottonwood North (64)

Independence West (94)

Independence West (18)

Cottonwood South (60) “Y” Road

Fireweed Reno (140)

Puffin Park Reno (52)

Independence Reno (24)

Raven Ridge Reno (36)

Birch Hill (17)

Raven Ridge (80)

Fireweed (16)

Note: 1,142 units available at all times during construction

DEMOLITION

Cottonwood North (51)

• New construction completed in Birch Hill, Cottonwood, Raven Ridge, and Fireweed• Relocation into newly constructed homes will be phased as they come online• Relocation coordination will be well in advance

RELOCATIONS

New construction New construction completed Renovations in other neighborhoods

673d Air Base Wing – Home of America’s Arctic Warriors

Construction Schedule

2014

Final Landscape Establishment Period

Independence West (94)

Independence West (18)

Completion of demolition activityFinal landscape period

DEMOLITION

List of unknown timelinesRelocation/transition scheduleCommunity PlazaCommunity recreation areas/facilities

673d Air Base Wing – Home of America’s Arctic Warriors

Construction Activity

673d Air Base Wing – Home of America’s Arctic Warriors

Construction Activity 2011

New Home Construction• Early start (1 Jun) in Kodiak, Moose Haven, and Moose Crossing• Cottonwood South and East• New homes – construction start to beneficial occupancy estimated 7 to 10 months

673d Air Base Wing – Home of America’s Arctic Warriors

Construction Activity2012

Birch Hill Families relocate to Kodiak (16)

Raven Ridge (124) Families

Cottonwood South(78) Families

Fireweed (16) and Independence (84) Families

• Phased movements occurring in CY12 as new units come online• 1,142 homes available at all times during construction

Note: Families relocating will move into new or more modern units

673d Air Base Wing – Home of America’s Arctic Warriors

Construction Activity 2013

Cottonwood North (104) and Independence West (112)

• Phased movements occurring in CY13 as new units come online• 1,142 homes available at all times during construction

Note: Families relocating will move into new or more modern units

673d Air Base Wing – Home of America’s Arctic Warriors

New Home Construction

End State

673d Air Base Wing – Home of America’s Arctic Warriors

Project End State

End State Units

Construct New 602

Major Renovations

335

As-Is 303

Demolish 604

End State 1,240

Building 337 1