Proton Driver / Project X

31
Proton Driver / Project X Keith Gollwitzer Fermilab August 30, 2012

description

Proton Driver / Project X. Keith Gollwitzer Fermilab August 30, 2012. Outline. Proton Driver Requirements Project X as part of Proton Driver Reference Design Upgrade Path Formatting Rings Accumulator Compressor Delivery to Target Plans. Proton Driver Requirements. - PowerPoint PPT Presentation

Transcript of Proton Driver / Project X

Page 1: Proton Driver / Project X

Proton Driver / Project X

Keith Gollwitzer

Fermilab

August 30, 2012

Page 2: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 2

Outline

• Proton Driver Requirements• Project X as part of Proton Driver

– Reference Design– Upgrade Path

• Formatting Rings– Accumulator– Compressor

• Delivery to Target• Plans

August 30, 2012

Page 3: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 3

Proton Driver Requirements

• Start from IDS-NF

• Muon Collider is similar except– 1 Bunch per train at 12-15 Hz

August 30, 2012

Parameter Value

Kinetic Energy 5-15 GeV

Average Beam Power 4MW (3.125 x 1015 protons/s)

Repetition Rate 50 Hz

Bunches per train 3

Total Time for bunches 240 μs

Bunch Length (rms) 1-3 ns

Beam Radius (rms) 1.2 mm

Geometric Emittance (rms) < 5 μm

β* at target > 30 cm

Note that 1 bunch is acceptable

Page 4: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 4

Project X Mission Goals

• Provide a neutrino beam for long baseline neutrino oscillation experiments based on a capability of targeting at least 2 MW on proton beam power at any energy between 60-120 GeV.

• Provide MW-class, multi-GeV, proton beams supporting multiple kaon, muon and neutrino based precision experiments. Simultaneous operations of the rare processes and neutrino programs are required.

• Provide a path toward a muon source for possible future Neutrino Factory and/or Muon Collider.

• Provide Options for implementing a program of Standard Model tests with nuclei and/or nuclear energy applications.

August 30, 2012

Project X

: Accelerator O

verview June 2011

Page 5: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 5

Project X Reference Design

• CW Linac will support average beam current of 1 mA to 3 GeV

• Pulsed Linac (3-8 GeV) will have a ~5% duty factor

• Possible 8 GeV beam power of 320 kW

• Programmable Chopper System (part of H- source) will provide appropriate bunch structure for the linac experiments as well as fill the appropriate part of the RF buckets in the accumulating Recycler Ring

August 30, 2012

Pulsed Linac chosen over RCS in FY11 as a better upgrade path for MAP

Page 6: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 6

ChoppersOne gross chopper prior to RFQ

Programmable chopper after RFQ (162.5MHz) which is capable of

single bunch selection; limits beam current in CW linac

Project X Choppers & Splitters

August 30, 2012

SplittersPulsed Dipole: switch from 3GeV experiment area and Pulsed Linac

Transverse RF beam splitter synchronized with programmable

chopper

Page 7: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 7

Gross Chopping & Splitting

August 30, 2012

Page 8: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 8

Fine Chopping

August 30, 2012

Page 9: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 9

Project X – MAP Task Force

• Members of Project X and MAP teams have outlined how to – Upgrade Project X to achieve 4MW at 8GeV

• Increase particles– Doubling per linac bunch & average beam current to 5 mA

• Increase pulsed linac duty factor– Increase to 10%

– Beam Reformatting• Accumulation Ring• Bunch Compression

August 30, 2012

Met April 2011- December 2011 Working on report

Page 10: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 10

Proton Driver Layout

August 30, 2012

Accumulator Ring

Compressor Ring

4MW Target

Page 11: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 11

Project X Upgrade Path - 1

August 30, 2012

Front End (warm)H- ion source, RFQ, MEBT, Programmable Chopper System

Initially 5mARun at 10mA (Ion source is capable)

Programmable Chopper

Capable of bunch by bunch 162.5MHz

Will suppress beam to limit beam current down stream to

5mA 1mA average

Entire front end is being

designed for 10mA

Page 12: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 12

Front End Collimation

• Systems designed to intercept beam will have to be able to handle the increased number of particles – Factor of two prior to chopper system– Factor of five downstream of chopper

• Project X team is designing an absorber associated with the programmable chopper capable of 25kW from 5kW

• Will also need to be able to handle increase in beam size– Larger emittance for larger RFQ output current

August 30, 2012

Page 13: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 13

Project X Upgrade Path - 2

August 30, 2012

3 GeV CW SRF LinacAverage beam current 1mA 5mA

325 and 650MHz

Retuning of couplers to be efficient –may set initially for higher current

Page 14: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 14

Project X Upgrade Path - 3

August 30, 2012

Pulsed Linac

1.3 GHz SRF3-8 GeV

10% 5% duty factor at 10Hz 15Hz

More RF powerUpgrade of couplersMore cryo capacity

Page 15: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 15

Project X Pulsed Linac

August 30, 2012

Page 16: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 16

Project X Upgrade Path - 4

August 30, 2012

• Conventional facilities– More water cooling– Building space

• More cryo capacity• More Klystrons

• An upgrade re-uses >75% of RDR cost

Project X RDR cost distribution (FY11)

Page 17: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 17

Project X to Formatting Rings

• The outlined Project X upgrade will provide

4MW of H- beam at 8GeV – Pulsed linac repetition rate is appropriate for

NF/MC– Linac beam pulses are delivered at 162.5MHz with

only 50% occupancy

• Beam re-formatting– Accumulation/conversion to proton beam– Package in few bunches of appropriate length

August 30, 2012

Page 18: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 18

Possible Operational Schemes

• Upgraded Project X pulses at 15Hz– Programmable chopper allows half of beam to be sent

into RF bucket for 6.67ms pulse

• Accumulation Ring is used to convert to proton beam into 4 bunches

• Transfer beam to Compressor Ring– Neutrino Factory: 1 bunch at a time (effectively 60Hz)– Muon Collider: all bunches at once

• Compressor Ring bunch rotates beam and extracts– Muon Collider: each bunch takes different path to

arrive at target simultaneouslyAugust 30, 2012

Page 19: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 19

First passes at Rings’ Designs

• Several people have designed and investigated rings

August 30, 2012

Parameter Accumulator CompressorCircumference 300m 300mTransition γt 4.0 11.3Slip factor αp =1/γt2-1/γ2 0.051 -0.0032rf voltage Vrf 4.0kV 120kV bunches (h)  4  4

Parameter Symbol Value Unit

Circumference C 292 m

FODO cells L, NC, φ 11.2, 20, 90 m

Dipole params L, B 4.0, 1.25 m, T

Quad params L, B’ 0.8, 8.0 m, T/m

βmax,ηmax βmax,ηmax 18.0, 3.5 m

transitions αp, γt0.038, 4.52

tunes νx, νy 5.44, 5.30

rf voltage Vrf, frf 4kV, 4MHz

Parameter AR CRCircumference, m 308.23 308.23 Momentum compaction -0.052 0.001Slippage factor -0.063 -0.01RF frequency, MHz 3.87 3.87RF voltage, kV 10 240Synchrotron tune 2.110-4 4.210-4

Peak current, A 100 1040Final r.m.s. bunch length, ns 29.2 3.2Final r.m.s. energy spread 5.210-4 6.910-3

Threshold impedance, Ohm 20 3 53R.m.s. emittance, m 5 5Space charge tuneshift, h/v (Gaussian distribution) 0.02/0.02 0.14/0.16Betatron tunes, h/v 7.94/6.91 6.76/8.44

Will continue to develop and investigate lattices

Page 20: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 20

Accumulator Injection R&D

• Stripping 4MW at 8GeV – Foils versus laser

• Will interface with other groups also doing high-powered multi-GeV stripping

• Need to develop method to handle ~1% of beam not stripped

August 30, 2012

Page 21: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 21

Compressor Ring

• Accept single bunch, or all bunches, from Accumulator• Does a quick bunch rotation• Extracts beam

• Do not expect space charge problem due to quick process

• Investigate location– Can be away from Project X and Accumulator – Could be in same tunnel as Accumulator– Possibly be incorporated into Accumulator

• NF issue would be multiple bunch rotations may blow-up beam

August 30, 2012

Page 22: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 22

Neutrino Factory Beam Line

• Extracted beam from Compressor Ring is delivered to target

• Beam enters the target area with an angle to the solenoid axis and will have a path such that the center of the interaction region is on the solenoid’s axis

• Discussions with target station group about where last focusing element can be placed– Target Infrastructure

• Jet• Cooling

– Radiation ShieldingAugust 30, 2012

From Target and Absorbers talk by K. McDonald

Page 23: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 23

Muon Collider Beam Line - 1

• Extracted bunches from Compressor Ring are sent into different length beam lines

August 30, 2012

Page 24: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 24

Muon Collider Beam Line - 2

• Each beam line enters the target area with an angle to the solenoid axis and will have a path such that the center of the interaction region is on the solenoid’s axis

August 30, 2012

Simplified schematic with no solenoid field

Page 25: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 25

Muon Collider Beam Line - 3

• Once we understand the Neutrino Factory single beam line and target area interface:– Will determine which 4 beam paths into target

area can be used– Determine spacing of beams for last beam line

element which will have to do the following• Be part of the final focus for all beams• Be a 4-way dipole to hit the appropriate trajectories

August 30, 2012

Page 26: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 26

Plans

• FY 13-15– Design and investigate the Accumulator and Compressor

Rings– Contribute to IDS-NF with Project X Proton Driver

information– Single beam line interface with Target Area for Neutrino

factory– Develop multi-beam lines and final focus magnet concepts

for Muon Collider– Develop MAP staging options with Proton X

• FY 16-18– Evaluate MAP staging options with Proton X– Prepare performance and costing for Technical Feasibility

ReportAugust 30, 2012

Page 27: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 27

Back-up Slides

August 30, 2012

Page 28: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 28

Project X Ion Source

August 30, 2012

Page 29: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 29

Project X RFQ Studies

August 30, 2012

Page 30: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 30

Project X CW Linac: Worst Case

• 3 GeV physics program stay with average beam current of 1 mA.– 10% at 5 mA and 90% at 1 mA average current

August 30, 2012

Page 31: Proton Driver / Project X

K. Gollwitzer | DOE Review of MAP (FNAL, August 29-31, 2012) 31

Project X 650 MHz RF Power

August 30, 2012