ProtoDUNE Side Penetration Introduction · B110069_ V 10_ SIL-R eport_ Pruss AG_ Han nover_ PPA...
Transcript of ProtoDUNE Side Penetration Introduction · B110069_ V 10_ SIL-R eport_ Pruss AG_ Han nover_ PPA...
-
Long-Baseline Neutrino FacilityLBNF
ProtoDUNE Side Penetration
Introduction
David Montanari
LBNF/SBN Cryo Panels Meeting
7-8 December 2016
-
LBNF
Outline
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting2
• Introduction
• Views of cryostat with inline safety valve
• Inline safety valve 2D Drawing
• Actuator SIL rating
• Draft of risk mitigation strategies
• Summary
-
LBNF
Introduction
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting3
• LBNF plans to use below the liquid level side penetrations in its cryostats with
inline safety isolation valves and secondary shut-off valves.
• As engineering and physics prototype, ProtoDUNE plans to prototype as many
features as possible of the future LBNF/DUNE project.
• ProtoDUNE Single Phase (SP or NP-04) and Dual Phase (DP or NP-02) each
has one below liquid level side penetration for LAr circulation with the same
inline safety isolation valve that is planned for LBNF.
• From this point of view the cryostats are identical. Only ProtoDUNE SP is
presented. ProtoDUNE DP uses an identical configuration.
• LBNF identified a cryogenic safety valve where the actual valve seal is inside
the tank/cryostat. This type of safety valve is used on flammable liquids (LNG)
and other cryogenic installations (e.g. ASUs), but also petrochem plants.
• The layout has been developed with GTT and CERN to meet their
requirements (e.g. minimize the load transferred to the GTT membrane and
Triplex). It is expected to be the same for LBNF.
• The current design has been approved by GTT.
-
LBNF
Protego inline safety valve specs
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting4
• Fail safe close.
• Pneumatic actuator (SIL 2 rated) to keep it open under normal
conditions.
• T_des = 77 K
• P_des = 2.1 bara (compatible with the LBNF installation)
• Design code: AD2000.
• PED certification.
• LOx cleaning.
• Leak check on Pressure and Vacuum retaining components.
• Dielectric breaks on the feet per ProtoDUNE specs (< 10 pF).
• Dielectric break on the discharge pipe inside LAr pump valve box.
-
LBNF
3D view of NP-04 cryostat with inline safety valve
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting5
-
LBNF
3D view of NP-04 cryostat with inline safety valve – Detail
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting6
-
LBNF
Section view of inline safety valve in NP-04 cryostat
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting7
Steel Support Structure
Insulation
Primary Membrane
Protego Inline Safety Valve
Valve Actuator Valve Body
Detector
Internal Piping
LAr
Protego Inline Safety Valve
Steel Support Structure
Insulation Detector
Valve Actuator Valve Body
Primary Membrane
Internal Piping
-
LBNF
3D view of inline safety valve in NP-04 cryostat with valve box
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting8
Secondary isolation valve
Protego Inline Safety Valve
-
LBNF12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting9
10 mm SS plateTriplex1.2 mm membrane
LAr
Dielectric breaks
-
LBNF
Actuator SIL rating certification
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting10
B110069_V10_SIL-Report_Pruss AG_Hannover_PPA Seite 8 von 16
INGENIEURBÜRO URBAN – Dipl.-Ing. J. Urban Öffentl. Bestellung u. Vereidigung Zeichen für Sachverstand Unabhängigkeit Unparteilichkeit
Publicly certified The mark of quality in the expert profession Independence Impartiality Certificatión pública Señal de competencia Independencia Imparcialidad
© Ingenieurbüro Urban
Set of Components/Component Safety Data (acc. IEC 61508 and IEC 61511)
Set of Components/Component Pneumatic Diaphragm Actuator
Type PPA - N & U
Manufacturer Waldemar Pruss Armaturenfabrik GmbH
Component Type Type A Ref. IEC 61508-2
Mode of Operation Low demand operation
Safety Function Drive closing/opening in specified time
Safe State Drive in end position, fixed with defined force
Failure Rates [failure/109 hrs = FIT]
Failure Rate Distribution total safe dangerous detected dangerous undetected don’t care SFF [%]
SUM PPA - N & U
(with 6x Springs, no Diagnosis) 1,517 1,465 0 51 7 97
SUM PPA - N & U
(with 18x Springs, no Diagnosis) 8,288 8,081 0 207 7 98
Specification of component Architecture
Architecture 1oo1 1oo1 is the architecture of a single set of components/component of the analysed type.
Hardware Fault Tolerance
HFT 0
Due to HFT=0, one failure has impact on the safety function. The influence of HFT on SIL
capability is respected in (2) below.
MTTR [h] 32 MTTR is the time required for repair of the set of components/component in case of failure.
MTTR has marginal influence on the pfd-value.
Diagnostic Coverage DC [%] 0%
In case of missing automatic diagnosis (e.g. partial stroke test): DC = 0 %. In case of
implemented partial stroke test: DC > 0% (value depends on efficiency of partial stroke test). Safe
Failure Fraction SFF increased by higher DC. Influence of DC on SIL capability of the set of
components/component is respected in (2) below (via SFF).
PPA –N with 6x Springs - Verification of SIL Capability (examples) (see comments on next page/backside of this page)
Proof Test Intervall 6 months 1 year 2 years 3 years 5 years
PFD (avg.) (IEC 61508-6, B3.2.2; λdu from FMEDA) 1.13 E-04 2.25 E-04 4.48 E-04 6.72 E-04 1.19 E-03
(1) quantitative achievable SIL (IEC 61508-1, Tab. 2) SIL 3 SIL 3 SIL 3 SIL 3 SIL 2
(2) qualitative achievable SIL (IEC 61508-2, Tab. 2) SIL 3 (for HFT 0; Typ A;90% SFF 0% (value depends on efficiency of partial stroke test). Safe
Failure Fraction SFF increased by higher DC. Influence of DC on SIL capability of the set of
components/component is respected in (2) below (via SFF).
PPA –N with 6x Springs - Verification of SIL Capability (examples) (see comments on next page/backside of this page)
Proof Test Intervall 6 months 1 year 2 years 3 years 5 years
PFD (avg.) (IEC 61508-6, B3.2.2; λdu from FMEDA) 8.49 E-05 1.68 E-04 3.35 E-04 5.01 E-04 8.34 E-04
(1) quantitative achievable SIL (IEC 61508-1, Tab. 2) SIL 4 SIL 3 SIL 3 SIL 3 SIL 3
(2) qualitative achievable SIL (IEC 61508-2, Tab. 2) SIL 3 (for HFT 0; Typ A;90% SFF
-
LBNF
Protego references 2008-2014 – 1/3
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting11
CONFIDENTIAL
-
LBNF
Protego references 2008-2014 – 2/3
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting12
CONFIDENTIAL
-
LBNF
Protego references 2008-2014 – 3/3
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting13
CONFIDENTIAL
- Mainly LNG tanks, but also ASUs and petrochem.
- Sizes up to 10,000 m3 and 150,000 m3/hr.
- 71 NB/AP (Bottom drain).- 9 SI/DP (Side penetration).
-
LBNF
Draft Mitigation Strategies
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting14
• Isolation valve (Protego, inline safety valve, seal inside the cryostat).
• Secondary Isolation Valve (inline shutoff valve downstream of the Protego).
• Engineering of integrated cryostat-inline valve system. See talk “Side penetration integrated
design (Protego, GTT, CERN)”.
• Risk analysis of integrated cryostat-inline valve system.
• Protection from accidental hits (bracing/etc. around sensitive parts, crane restriction).
• SIL 2 rated actuator connected to SIL 3 rated safety PLC.
• Early detection of equipment failure (with vacuum gauges in vacuum jackets of transfer lines).
• Restricted access to the pit(s) or cryostat floor level (controlled access with work permits).
• Oxygen sensors (in the pits) and ODH alarms (in the pits and in the hall).
• Information signs and training of personnel.
• Emergency ventilation (suction points nearby the side penetration. Fans sized for the most
credible leak scenario).
• Evacuation plan (in case of ODH alarm).
• Two means of egress.
Details in the contribution “Overall ProtoDUNE Risk Mitigation Plan” from Olga B.
-
LBNF
Summary
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting15
• The construction of the ProtoDUNEs cryostats is in progress.
• Each one will have a below liquid level side penetration equipped with an inline
safety valve (with the seal inside the cryostat), which is fail safe close, and an inline
shut-off valve (before the connection to the LAr circulation pumps).
• The inline safety valve is a standard device from Protego (SI/DP 150). The
connection to the cryostat is tank-specific and it has no impact on the functionality
of the valve. The design has been done according to GTT requirements and
approved by GTT.
• A draft of the risk mitigation strategies has been presented and will be detailed in
Olga’s contribution. It addresses the following topics: engineering of the device,
risk analysis of the integrated system (membrane cryostat-in line safety valve-steel
support structure), physical protection of the device, early detection of equipment
failures, access restriction to pit level, Oxygen sensors and ODH alarms,
emergency ventilation, evacuation and egress.
• We believe that the system as designed and the proposed risk mitigation strategies
provide an adequate level of safety and we look forward to your feedback.
-
LBNF
Thanks
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting16
-
LBNF
Backup slides
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting17
-
LBNF
NP-02 Cryogenics
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting18
Steel Support Structure
Insulation
Primary Membrane
Protego Inline Safety Valve
Valve Actuator Valve Body
Detector
Internal Piping
LAr
LAr Filters
LAr circulation pumps
Condenser
LAr Phase separator
LN2 Phase separator
LAr storage tank(NP-02/NP-04)
LN2 storage tank(NP-02/NP-04)
LAr Filters Regeneration(NP-02/NP-04)
-
LBNF
NP-04 Cryogenics
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting19
Steel Support Structure
Insulation
Primary Membrane
Protego Inline Safety Valve
Valve Actuator Valve Body
Detector
Internal Piping
LAr
LAr Filters
LAr circulation pumps
Condenser
LAr Phase separator
LN2 Phase separator
-
LBNF
NP-02 and NP-04 Cryogenics
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting20
Steel Support Structure
Insulation
Primary Membrane
Protego Inline Safety Valve
Valve Actuator Valve Body
Detector
Internal Piping
LAr
-
LBNF
LBNF Mezzanine
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting21
-
LBNF
LBNF LAr circulation pumps
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting22
-
LBNF
LBNF LAr/GAr Filtration systems (in Central Utility Cavern)
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting23
LAr/GAr Filters
LAr/GAr Filters
Particulate filters
Regen blowers
Particulate filters
H2 generators
H2 generators
PLC racks in situ
LN2 Cold Boxes
Detectors #1, 2
Detectors #3, 4
-
LBNF
Brief Description of the LAr Purification System
12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting24
• We use LAr filters filled with Mol Sieve and Copper pellets to purify the LAr from Water and Oxygen.
The Mol Sieve adsorbs Water and the Copper pellets adsorb Oxygen. Inline particulate filters
upstream of the LAr filters prevent particles that might be present in the LAr to enter the LAr filters.
• After being exposed to air, the Mol Sieve and Copper pellets inside the LAr filters are saturated and
need to be activated with high Temperature (~220-240 C) and H2 prior to being put in service.
• With the high temperature the Mol Sieve releases the trapped Water. The Oxygen trapped inside the
Copper reacts with the H2 (at high T) and creates Water, which is then released. A simplified
activation/regeneration procedure follows:
- The LAr filters are pre-heated with Argon at ~180 C.
- An Ar-H2 mix (2.5% H2 or less) is heated up to 180 C and sent through the LAr filters.
- As the H2 reacts with the Copper, a heat wave is observed through the bed. The temperature locally increases to
~220-240 C. The process continues until the heat wave passes through and the dew point observed at the outlet is
about -40 C. The water content at the outlet is also measured and should be in a trend going down.
- Hot Argon gas is flow into the system to remove all H2, followed by cool Argon to lower the Temperature.
- The cool down process can be accelerated by pumping down the LAr filters.
• The same process needs to be repeated after several months of service (how many depends on the
initial purity of the LAr) to remove the Water and Oxygen that the LAr filters adsorbed from the LAr.
The process in this case is called regeneration, because the Mol Sieve and Copper only contain the
Water and Oxygen removed from the LAr, they are not saturated with air as at the beginning.
• To be able to continuously purify the LAr, there are two set of LAr filters, one in operation and one in
standby/regeneration.