ProtoDUNE Side Penetration Introduction · B110069_ V 10_ SIL-R eport_ Pruss AG_ Han nover_ PPA...

24
Long-Baseline Neutrino Facility LBNF ProtoDUNE Side Penetration Introduction David Montanari LBNF/SBN Cryo Panels Meeting 7-8 December 2016

Transcript of ProtoDUNE Side Penetration Introduction · B110069_ V 10_ SIL-R eport_ Pruss AG_ Han nover_ PPA...

  • Long-Baseline Neutrino FacilityLBNF

    ProtoDUNE Side Penetration

    Introduction

    David Montanari

    LBNF/SBN Cryo Panels Meeting

    7-8 December 2016

  • LBNF

    Outline

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting2

    • Introduction

    • Views of cryostat with inline safety valve

    • Inline safety valve 2D Drawing

    • Actuator SIL rating

    • Draft of risk mitigation strategies

    • Summary

  • LBNF

    Introduction

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting3

    • LBNF plans to use below the liquid level side penetrations in its cryostats with

    inline safety isolation valves and secondary shut-off valves.

    • As engineering and physics prototype, ProtoDUNE plans to prototype as many

    features as possible of the future LBNF/DUNE project.

    • ProtoDUNE Single Phase (SP or NP-04) and Dual Phase (DP or NP-02) each

    has one below liquid level side penetration for LAr circulation with the same

    inline safety isolation valve that is planned for LBNF.

    • From this point of view the cryostats are identical. Only ProtoDUNE SP is

    presented. ProtoDUNE DP uses an identical configuration.

    • LBNF identified a cryogenic safety valve where the actual valve seal is inside

    the tank/cryostat. This type of safety valve is used on flammable liquids (LNG)

    and other cryogenic installations (e.g. ASUs), but also petrochem plants.

    • The layout has been developed with GTT and CERN to meet their

    requirements (e.g. minimize the load transferred to the GTT membrane and

    Triplex). It is expected to be the same for LBNF.

    • The current design has been approved by GTT.

  • LBNF

    Protego inline safety valve specs

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting4

    • Fail safe close.

    • Pneumatic actuator (SIL 2 rated) to keep it open under normal

    conditions.

    • T_des = 77 K

    • P_des = 2.1 bara (compatible with the LBNF installation)

    • Design code: AD2000.

    • PED certification.

    • LOx cleaning.

    • Leak check on Pressure and Vacuum retaining components.

    • Dielectric breaks on the feet per ProtoDUNE specs (< 10 pF).

    • Dielectric break on the discharge pipe inside LAr pump valve box.

  • LBNF

    3D view of NP-04 cryostat with inline safety valve

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting5

  • LBNF

    3D view of NP-04 cryostat with inline safety valve – Detail

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting6

  • LBNF

    Section view of inline safety valve in NP-04 cryostat

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting7

    Steel Support Structure

    Insulation

    Primary Membrane

    Protego Inline Safety Valve

    Valve Actuator Valve Body

    Detector

    Internal Piping

    LAr

    Protego Inline Safety Valve

    Steel Support Structure

    Insulation Detector

    Valve Actuator Valve Body

    Primary Membrane

    Internal Piping

  • LBNF

    3D view of inline safety valve in NP-04 cryostat with valve box

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting8

    Secondary isolation valve

    Protego Inline Safety Valve

  • LBNF12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting9

    10 mm SS plateTriplex1.2 mm membrane

    LAr

    Dielectric breaks

  • LBNF

    Actuator SIL rating certification

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting10

    B110069_V10_SIL-Report_Pruss AG_Hannover_PPA Seite 8 von 16

    INGENIEURBÜRO URBAN – Dipl.-Ing. J. Urban Öffentl. Bestellung u. Vereidigung Zeichen für Sachverstand Unabhängigkeit Unparteilichkeit

    Publicly certified The mark of quality in the expert profession Independence Impartiality Certificatión pública Señal de competencia Independencia Imparcialidad

    © Ingenieurbüro Urban

    Set of Components/Component Safety Data (acc. IEC 61508 and IEC 61511)

    Set of Components/Component Pneumatic Diaphragm Actuator

    Type PPA - N & U

    Manufacturer Waldemar Pruss Armaturenfabrik GmbH

    Component Type Type A Ref. IEC 61508-2

    Mode of Operation Low demand operation

    Safety Function Drive closing/opening in specified time

    Safe State Drive in end position, fixed with defined force

    Failure Rates [failure/109 hrs = FIT]

    Failure Rate Distribution total safe dangerous detected dangerous undetected don’t care SFF [%]

    SUM PPA - N & U

    (with 6x Springs, no Diagnosis) 1,517 1,465 0 51 7 97

    SUM PPA - N & U

    (with 18x Springs, no Diagnosis) 8,288 8,081 0 207 7 98

    Specification of component Architecture

    Architecture 1oo1 1oo1 is the architecture of a single set of components/component of the analysed type.

    Hardware Fault Tolerance

    HFT 0

    Due to HFT=0, one failure has impact on the safety function. The influence of HFT on SIL

    capability is respected in (2) below.

    MTTR [h] 32 MTTR is the time required for repair of the set of components/component in case of failure.

    MTTR has marginal influence on the pfd-value.

    Diagnostic Coverage DC [%] 0%

    In case of missing automatic diagnosis (e.g. partial stroke test): DC = 0 %. In case of

    implemented partial stroke test: DC > 0% (value depends on efficiency of partial stroke test). Safe

    Failure Fraction SFF increased by higher DC. Influence of DC on SIL capability of the set of

    components/component is respected in (2) below (via SFF).

    PPA –N with 6x Springs - Verification of SIL Capability (examples) (see comments on next page/backside of this page)

    Proof Test Intervall 6 months 1 year 2 years 3 years 5 years

    PFD (avg.) (IEC 61508-6, B3.2.2; λdu from FMEDA) 1.13 E-04 2.25 E-04 4.48 E-04 6.72 E-04 1.19 E-03

    (1) quantitative achievable SIL (IEC 61508-1, Tab. 2) SIL 3 SIL 3 SIL 3 SIL 3 SIL 2

    (2) qualitative achievable SIL (IEC 61508-2, Tab. 2) SIL 3 (for HFT 0; Typ A;90% SFF 0% (value depends on efficiency of partial stroke test). Safe

    Failure Fraction SFF increased by higher DC. Influence of DC on SIL capability of the set of

    components/component is respected in (2) below (via SFF).

    PPA –N with 6x Springs - Verification of SIL Capability (examples) (see comments on next page/backside of this page)

    Proof Test Intervall 6 months 1 year 2 years 3 years 5 years

    PFD (avg.) (IEC 61508-6, B3.2.2; λdu from FMEDA) 8.49 E-05 1.68 E-04 3.35 E-04 5.01 E-04 8.34 E-04

    (1) quantitative achievable SIL (IEC 61508-1, Tab. 2) SIL 4 SIL 3 SIL 3 SIL 3 SIL 3

    (2) qualitative achievable SIL (IEC 61508-2, Tab. 2) SIL 3 (for HFT 0; Typ A;90% SFF

  • LBNF

    Protego references 2008-2014 – 1/3

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting11

    CONFIDENTIAL

  • LBNF

    Protego references 2008-2014 – 2/3

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting12

    CONFIDENTIAL

  • LBNF

    Protego references 2008-2014 – 3/3

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting13

    CONFIDENTIAL

    - Mainly LNG tanks, but also ASUs and petrochem.

    - Sizes up to 10,000 m3 and 150,000 m3/hr.

    - 71 NB/AP (Bottom drain).- 9 SI/DP (Side penetration).

  • LBNF

    Draft Mitigation Strategies

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting14

    • Isolation valve (Protego, inline safety valve, seal inside the cryostat).

    • Secondary Isolation Valve (inline shutoff valve downstream of the Protego).

    • Engineering of integrated cryostat-inline valve system. See talk “Side penetration integrated

    design (Protego, GTT, CERN)”.

    • Risk analysis of integrated cryostat-inline valve system.

    • Protection from accidental hits (bracing/etc. around sensitive parts, crane restriction).

    • SIL 2 rated actuator connected to SIL 3 rated safety PLC.

    • Early detection of equipment failure (with vacuum gauges in vacuum jackets of transfer lines).

    • Restricted access to the pit(s) or cryostat floor level (controlled access with work permits).

    • Oxygen sensors (in the pits) and ODH alarms (in the pits and in the hall).

    • Information signs and training of personnel.

    • Emergency ventilation (suction points nearby the side penetration. Fans sized for the most

    credible leak scenario).

    • Evacuation plan (in case of ODH alarm).

    • Two means of egress.

    Details in the contribution “Overall ProtoDUNE Risk Mitigation Plan” from Olga B.

  • LBNF

    Summary

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting15

    • The construction of the ProtoDUNEs cryostats is in progress.

    • Each one will have a below liquid level side penetration equipped with an inline

    safety valve (with the seal inside the cryostat), which is fail safe close, and an inline

    shut-off valve (before the connection to the LAr circulation pumps).

    • The inline safety valve is a standard device from Protego (SI/DP 150). The

    connection to the cryostat is tank-specific and it has no impact on the functionality

    of the valve. The design has been done according to GTT requirements and

    approved by GTT.

    • A draft of the risk mitigation strategies has been presented and will be detailed in

    Olga’s contribution. It addresses the following topics: engineering of the device,

    risk analysis of the integrated system (membrane cryostat-in line safety valve-steel

    support structure), physical protection of the device, early detection of equipment

    failures, access restriction to pit level, Oxygen sensors and ODH alarms,

    emergency ventilation, evacuation and egress.

    • We believe that the system as designed and the proposed risk mitigation strategies

    provide an adequate level of safety and we look forward to your feedback.

  • LBNF

    Thanks

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting16

  • LBNF

    Backup slides

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting17

  • LBNF

    NP-02 Cryogenics

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting18

    Steel Support Structure

    Insulation

    Primary Membrane

    Protego Inline Safety Valve

    Valve Actuator Valve Body

    Detector

    Internal Piping

    LAr

    LAr Filters

    LAr circulation pumps

    Condenser

    LAr Phase separator

    LN2 Phase separator

    LAr storage tank(NP-02/NP-04)

    LN2 storage tank(NP-02/NP-04)

    LAr Filters Regeneration(NP-02/NP-04)

  • LBNF

    NP-04 Cryogenics

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting19

    Steel Support Structure

    Insulation

    Primary Membrane

    Protego Inline Safety Valve

    Valve Actuator Valve Body

    Detector

    Internal Piping

    LAr

    LAr Filters

    LAr circulation pumps

    Condenser

    LAr Phase separator

    LN2 Phase separator

  • LBNF

    NP-02 and NP-04 Cryogenics

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting20

    Steel Support Structure

    Insulation

    Primary Membrane

    Protego Inline Safety Valve

    Valve Actuator Valve Body

    Detector

    Internal Piping

    LAr

  • LBNF

    LBNF Mezzanine

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting21

  • LBNF

    LBNF LAr circulation pumps

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting22

  • LBNF

    LBNF LAr/GAr Filtration systems (in Central Utility Cavern)

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting23

    LAr/GAr Filters

    LAr/GAr Filters

    Particulate filters

    Regen blowers

    Particulate filters

    H2 generators

    H2 generators

    PLC racks in situ

    LN2 Cold Boxes

    Detectors #1, 2

    Detectors #3, 4

  • LBNF

    Brief Description of the LAr Purification System

    12.07.16 David Montanari | LBNF/SBN Cryo Safety Panels Meeting24

    • We use LAr filters filled with Mol Sieve and Copper pellets to purify the LAr from Water and Oxygen.

    The Mol Sieve adsorbs Water and the Copper pellets adsorb Oxygen. Inline particulate filters

    upstream of the LAr filters prevent particles that might be present in the LAr to enter the LAr filters.

    • After being exposed to air, the Mol Sieve and Copper pellets inside the LAr filters are saturated and

    need to be activated with high Temperature (~220-240 C) and H2 prior to being put in service.

    • With the high temperature the Mol Sieve releases the trapped Water. The Oxygen trapped inside the

    Copper reacts with the H2 (at high T) and creates Water, which is then released. A simplified

    activation/regeneration procedure follows:

    - The LAr filters are pre-heated with Argon at ~180 C.

    - An Ar-H2 mix (2.5% H2 or less) is heated up to 180 C and sent through the LAr filters.

    - As the H2 reacts with the Copper, a heat wave is observed through the bed. The temperature locally increases to

    ~220-240 C. The process continues until the heat wave passes through and the dew point observed at the outlet is

    about -40 C. The water content at the outlet is also measured and should be in a trend going down.

    - Hot Argon gas is flow into the system to remove all H2, followed by cool Argon to lower the Temperature.

    - The cool down process can be accelerated by pumping down the LAr filters.

    • The same process needs to be repeated after several months of service (how many depends on the

    initial purity of the LAr) to remove the Water and Oxygen that the LAr filters adsorbed from the LAr.

    The process in this case is called regeneration, because the Mol Sieve and Copper only contain the

    Water and Oxygen removed from the LAr, they are not saturated with air as at the beginning.

    • To be able to continuously purify the LAr, there are two set of LAr filters, one in operation and one in

    standby/regeneration.