Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact...
-
Upload
clark-rivett -
Category
Documents
-
view
249 -
download
8
Transcript of Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact...
![Page 1: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/1.jpg)
Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP)Environmental and Social Impact Assessment (ESIA)
Report by Panel of Experts*Almaty May 2011
Torkil Jønch Clausen (Chair)Erik Helland-Hansen
* Desk review by Richard Fuggle and Frederic Giovannetti
1
![Page 2: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/2.jpg)
PANEL OF EXPERTSPURPOSE OF FIRST VISIT
Inception visit: Review of consultants’ Inception Report
( - detailed comments to consultants) Site visit Initial discussions with Government of Tajikistan and World Bank and consultants
First impressions Questions and identification of some key issues/challenges
2
![Page 3: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/3.jpg)
ROLE OF ESIA
Independent comprehensive assessment: All environmental and social impacts
- positive and negative- all stages: construction through operation- all affected areas, from reservoir to Aral Sea
Based on good international practice
Sound basis for national and regional assessment
3
![Page 4: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/4.jpg)
ESIA and TEAS
Two studies - two consultants - two POEs ONE Rogun HPP
Need for close coordination, on e.g. Hydrology Geology Economics Dam optimization, cost and operations
4
![Page 5: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/5.jpg)
THE BASIN CONTEXT
Rogun HPP in Vakhsh-Amu Darya context: Vakhsh River contributing some 20-30% of Amu Darya flow Upstream of Nurek Dam (300 m, initial reservoir 10.5 cu.km.) Upstream in Vakhsh cascade
Potential incremental impacts to be seen in basin context, and extent of project impacts defined
5
![Page 6: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/6.jpg)
THE NUREK DAM
Nurek HPP: Similar size as Rogun HPP Operation for hydropower (3000 MW) with irrigation off-takes Effective sediment trap
Almost 40 years of operational and impact experience
Need to draw on Nurek lessons learned 6
![Page 7: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/7.jpg)
CATCHMENT AND RESERVOIR
Some key biophysical issues: Highly naturally erosive upstream catchment Loss of fertile agricultural land Deep stratified reservoir
Marginal human influence on upper catchment Particular focus on future reservoir behavior/conditions
7
![Page 8: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/8.jpg)
RESETTLEMENT
Resettlement in progress – a promising start: Formation of Directorate Resettlement of several households in progress Concern about former Soviet resettlement legacy
Compensation or enhancement? Start Public Consultation and Disclosure Plan early
8
![Page 9: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/9.jpg)
DAM SITE ISSUES
Some site visit impressions: Deficiencies in occupational health conditions Site preparation, waste and land management challenging
Accident records/analyses as basis for improvement
Immediate focus on site conditions
9
![Page 10: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/10.jpg)
DOWNSTREAM ISSUES- THE SETTING -
Rogun HPP downstream impacts: On the Nurek HHP From Nurek to Vakhsh/Pyanj confluence Downstream Amu Darya from confluence Vakhsh/Pyanj
Need for factual information Dialogue among riparians (Nukus Declaration spirit)
10
![Page 11: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/11.jpg)
DOWNSTREAM ISSUES- KEY ANALYSES -
Rogun HPP downstream impact assessment calls for: Strong focus on hydrology: entire Basin, agreed datasets (TEAS- ESIA cooperation) Nurek history/experience Impacts in Vakhsh cascade context
Assessment now: Stage 1, alternatives/SEA, Stage 2
Hydrometry stations on both Vakhsh and Pyanj
11
![Page 12: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/12.jpg)
PARTICULAR COORDINATION ISSUES
Rogun HPP alternatives: Study of power supply options of Tajikistan- including Strategic Environmental Assessment (SEA)- including analysis of alternatives
Optimization of dam height
Scheduling and coordination challenge12
![Page 13: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/13.jpg)
CLIMATE CHANGE
Climate change analysis included in TOR, but adequately? Hydrologic stationarity problem => uncertain flow estimates Downstream impacts from entire basin
Need for up-to -date, state-of-art analysis of entire basin Need for risk management approaches
13
![Page 14: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/14.jpg)
SUMMARY OF KEY DRIVERS AND RECOMMENDATIONS
KEY DRIVERS FOR THE ANALYSIS1. Basin hydrology2. Dam height3. Reservoir operations
KEY RECOMMENDATIONS FOR ESIA PROCES1. Coordinate TEAS and ESIA closely2. Assess Rogun HPP in the wider basin context3. Give immediate attention to site conditions and occupational
health4. Promote dialogue and information sharing among riparians5. More attention to climate change6. Incorporate lessons learned from Nurek HPP
14
![Page 15: Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP) Environmental and Social Impact Assessment (ESIA) Report by Panel of Experts* Almaty.](https://reader036.fdocuments.in/reader036/viewer/2022081505/551a4403550346a4248b5c11/html5/thumbnails/15.jpg)
THANK YOU
15