Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

17
Proposed Generation Expansion Process For Review and Discussion March 1, 2011

Transcript of Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

Page 1: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

Proposed Generation Expansion Process

For Review and Discussion

March 1, 2011

Page 2: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

2

Agenda

• Goal of Generation Expansion Process• Overview of Process• Details of Iterative Process• Next Steps

March 1, 2011

Page 3: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

3

Goal

• To create a market-like expansion plan through 2030

• When evaluating transmission needs through 2030, we will need additional generation to serve forecasted loads

• Intent is to select generation technologies consistent with what the market would be likely to develop, given specific conditions in each scenario

March 1, 2011

Page 4: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

4

Overview of Process

March 1, 2011

Base Case Generation

• Add increment of renewable

capacity • Run Promod

• Evaluate Promod Results

• Run MP• Insert MP

expansion into Promod

• Insert Adjusted load shape into

MarketPower (MP)• Run MP

• Re-run Promod

• Add/Subtract increment renewable capacity

• Finalize Promod

Expansion PlanTransmission

Evaluation

Generation Siting

Pass

Fail

After Year +20 run and Pass

Fail

Repeated Every 3 Years

Page 5: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

5

Starting Case Information

• Latest load forecast developed by the load forecasting group

• Existing generation as listed in the 2010 CDR Winter Update– For discussion: Two potential options for future units that

currently have signed Interconnection Agreements• Include all units with signed Interconnection Agreements as of

March 1, 2011

• Do not include any units with signed Interconnection Agreements – let expansion process evaluate all future units

March 1, 2011

Page 6: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

6

Iterative Process

• Using Promod and MarketPower together– Use strengths of both software packages to develop a

generation expansion plan for each scenario– MarketPower is fast and evaluates multiple dispatchable

technologies at the same time. MarketPower does not evaluate hours in chonological order.

– Promod evaluates system commitment and dispatch across all hours - it maintains chronology of hourly patterns and provides unit-specific output data

• Promod will be run without transmission topology to see market-wide opportunities

March 1, 2011

Page 7: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

7

How Does MarketPower Work?

• Compares existing (base case generation) resources to peak load on an annual basis

• Evaluates technologies on a financial basis to determine its viability in the market– The equations for this calculation is listed in the appendix

• MarketPower will build a unit if the unit will operate at or above its calculated minimum capacity requirement when compared to an Advanced Combustion Turbine unit. Unit operations are based on estimates of market prices.

March 1, 2011

Page 8: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

8

What Information Does the Model Use?

• Created generic categories for each technology

• Generic operating and financial characteristics– Heat rate– Min up and down times– O&M costs– Capital costs– Capacity– Etc.

• The financial characteristics may change by scenario

March 1, 2011

Page 9: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

9

Promod Run to Evaluate Renewables with Diurnal Pattern

• Begin with Year + 3 (2014)– Insert an initial increment of renewable capacity into Promod

• Evaluate all potential renewable technologies

– Run Promod for Year + 3• Evaluate model results using financial criteria

– Marginal generator revenue » Also review avg. system production cost savings per MWh

– Others

• If units are profitable (i.e., revenue stream supports adequate IRR), add a second increment of capacity

• If units are not profitable, decrease initial increment of capacity and re-run Promod

• Continue the Promod runs at Year + 3 until a final capacity for each renewable technology has been determined

March 1, 2011

Page 10: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

10

Using Promod Results in MarketPower

• Adjust forecasted load shape to reflect net load with the renewable expansion units from Promod runs– Insert new load shape into MarketPower– Run MarketPower for Year + 3 through Year + 20 – Take MarketPower expansion plan from Year + 3 to Year + 6

and insert into Promod

March 1, 2011

Page 11: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

11

Iterative Process Contd.

• Run Promod at Year + 6 – Includes Promod renewable expansion plan from Year + 3 and

MarketPower thermal expansion plan from Year + 3 through Year +6

– Evaluate existing and expansion plan units using financial criteria

• Candidacy for mothball status will be assessed using operating hours, capacity factor, number of starts, etc.

• A mothballed unit will have the ability to be restarted within succeeding MarketPower analysis

– Begin adding initial increment of renewable capacity at Year + 6– Repeat process

• 3 year increments

• Until final expansion plan through Year +20 has been developed

March 1, 2011

Page 12: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

12

Next Steps

• Generation Expansion plan will go through the generation siting process– Dispatchable siting will use geographic databases

• Develop lists of acceptable siting locations by fuel by county

• Rank these buses by LMP’s

• Site based on LMP rankings

– Renewable siting will evaluate both capacity factors and LMP’s• Proceed with transmission evaluation

– Existing and expansion units will be reassessed during the transmission evaluation process

• Financial criteria developed during generation expansion plan

• Candidacy for mothball status

• Re-evaluate expansion plan if unserved energy is not able to be solved with transmission projects

March 1, 2011

Page 13: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

13

Results

• This process will be repeated for each scenario• Plan is to provide expansion results for BAU scenario at April

LTSTF meeting– Capacity additions by prototype for each year – Reserve margin by year– Etc.

March 1, 2011

Page 14: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

14

QUESTIONS???

March 1, 2011

Page 15: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

15

Appendix: MarketPower Build Decision Calculations

March 1, 2011

Total Fixedt = Capitalt + Fixedt

Total Energyt = Fuelt + Variablet

Avg Fixedt = Total Fixedt / Generationt

Avg Variablet = Total Energyt / Generationt

(Avg Fixed1 – Avg Fixed2) / (Avg Var1 –Avg Var2) = %

Page 16: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

16

Generic Generating Resource Assumptions (2010$)

Operating characteristics for existing generating resources

March 1, 2011

Heat Rate

Min up time

Min down time

Variable O&M

Fixed O&M Start Cost

BTU/kWh HRs HRs $/MWh $/kW-yr $

Gas steam reheat 12,000 8 8 8.00 13.25 2,500 gas steam non-reheat 13,000 8 8 5.00 20.50 2,500 Supercritical Gas Steam 11,000 8 8 6.50 15.75 2,500 Combustion Turbines (LM6000) 9,500 1 1 8.00 8.25 2,000 Combustion Turbines ("E" class) 11,500 1 1 4.00 5.00 1,000 Nuclear 10,000 168 24 4.00 73.00 Coal 9,800 24 12 5.00 25.50 5,000 Combined Cycle (1995 and later) 7,200 6 4 2.65 13.25 15,000 Combined Cycle (LM6000) 8,000 4 8 5.00 12.00 5,000 Combined Cycle ("E" class) 8,500 4 4 3.00 13.50 3,000 Biomass 13,000 8 6 9.50 13.25 2,500

Technology

Page 17: Proposed Generation Expansion Process For Review and Discussion March 1, 2011.

17

Generic Generating Resource Assumptions (2010$)

Operating characteristics for new generating resources

March 1, 2011

Capacity Heat RateMin

CapacityMin up

time

Min down time

Variable O&M Start Cost

Estimated CF

MW BTU/kWh MW HRs HRs $/MWh $ %

Conventional CC (F type) 500 7,200 200 6 8 2.65 10,000 50%Advanced CC (H & G type) 400 6,700 250 6 8 2.90 15,000 50%Conventional CT (F type) 170 10,500 130 2 3 8.00 7,500 10%Advanced CT (LMS100) 100 9,200 70 2 3 13.00 10,000 10%Supercritical Coal 600 9,000 250 24 12 3.95 5,000 75%Supercritical Coal W/ CCS 625 11,950 250 24 12 7.35 7,000 80%IGCC 625 9,000 250 24 12 5.75 5,000 60%IGCC W/ CCS 539 10,700 250 24 12 7.00 7,000 60%Nuclear 1,100 10,300 600 168 48 4.00 - 90%On shore Wind 100 - - - - - - 35%Off Shore Wind 100 - - - - - - 40%Geothermal 40 11,000 20 8 8 10.00 - 80%Biomass - wood 40 13,000 15 8 8 9.50 2,500 75%Solar PV 10 - - - - - - 33%Solar Thermal 100 - - - - - - 38%

Technology