Proposed Convention Center Hotel
GEORGE R. BROWN CONVENTION CENTER | HILTON AMERICAS - HOUSTON | JONES HALL FOR THE PERFORMING ARTS
MILLER OUTDOOR THEATRE | WORTHAM THEATER CENTER | THEATER DISTRICT PARKING | THEATER DISTRICT PARKS
![Page 2: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/2.jpg)
ÔGEORGE R. BROWNC O N V E N T I O N C E N T E R
2025M A S T E R P L A N
![Page 3: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/3.jpg)
�
GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler
COMPARATIVE ANALYSIS
HOTEL CAPACITY
1,000�additional hotel rooms are immediately needed to match the average number available to our competitor convention centers
2,000 2,000 �hotel rooms are needed to match the ratio of rooms per exhibition space compared to other cities
![Page 4: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/4.jpg)
GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler
KEY DRIVERS
CONVENTION
FACILITIES
HOTEL
PACKAGE
GRBCC PRIORITIES
1HOTEL
PACKAGE
TRANSPORTATION
DISTRICT
AMENITIES
SAFETY &
SECURITY
2
3
DISTRICT
AMENITIES
CONVENTION
FACILITIES
![Page 5: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/5.jpg)
GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler
KEY DRIVERS
HOTEL PACKAGE
MEETING PLANNERS:
• Consider availability andquality of hotels near the
convention center whenselecting a city to host their event
• Prefer dealing with fewer hotelsthat are located nearby to meettheir inventory needs
• Prefer to avoid the expense of
EXISTING NEARBY HOTELS
• Prefer to avoid the expense ofshuttle bussing from remote hotels
• Prefer ‘attached’ conventioncenter hotels with climate controlled connections
![Page 6: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/6.jpg)
GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler
KEY DRIVERS
HOTEL PACKAGE
Consider a second attached convention center hotel
Consider hotel development offering different products on GRBCC’s four corners
99
PROPOSED NEARBY HOTELS
![Page 7: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/7.jpg)
Date Process
Selection Committee • Selection Committee comprised of:
o Ric Campo (HFC Board Member)
o David Solomon (HFC Board Member)
o Katy Caldwell (HFC Board Member)
o Deon Warner (HFC Board Member)
o Andy Icken (Chief Development Officer, City of
Houston)
March 7, 2012 • Request for Qualifications issued
• Advertisement placed in Houston Chronicle from March 7 –• Advertisement placed in Houston Chronicle from March 7 –
March 13
• Advertisement placed in Houston Business Journal for March
9 and March 16
• Advertised and document made available online on Onvia
from March 7 – April 20
• RFQ published on HFC website
• Emailed notification to over 165 developer, architect, hotel
brand, investor, and construction contacts
March 27, 2012 • Pre-proposal meeting at the GRBCC; approximately 100
individuals attended
![Page 8: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/8.jpg)
April 20, 2012 • RFQ due
• 11 responses received from the following:
o Discovery Central
o Hines
o Houston Now
o Matthews Southwest
o Mortenson
o Parkway Service Group
o Product Marketing International
o RIDA Development Corporationo RIDA Development Corporation
o Trammell Crow
o TRT/Omni
o White Lodging
![Page 9: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/9.jpg)
May 4, 2012 • Six teams were shortlisted for interviews based on:
– Relevant experience,
– Financial strength with privately financed hotels,
and other commercial and residential projects,
– Designer’s relevant experience with similar
projects,
─ Developer’s and designer’s key personnel
experience,
– Approach to financing, and
– Responsiveness to the RFQ. – Responsiveness to the RFQ.
The six teams included:
o Discovery Central
o Hines
o Parkway Service Group
o RIDA Development Corporation
o TRT/Omni
o White Lodging
![Page 10: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/10.jpg)
May 30-31, 2012 • The Selection Committee conducted oral interviews with
the six development teams
• The Selection Committee shortlisted two development
teams – RIDA Development Corporation and TRT/Omni.
• The Selection Committee directed staff to enter into term
sheet negotiations with the short-listed firms.
September 10, 2012 • Final term sheets received from developers
September 24, 2012 • Final interviews
• Selection Committee directed HFC staff to enter into
exclusive negotiations with RIDA Development Corporation
![Page 11: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/11.jpg)
![Page 12: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/12.jpg)
Going Forward• Begin negotiations with RIDA Development Corporation
– Approximately $375 Million Investment: 825 Construction Jobs &
500 Permanent Jobs
– Privately owned and requires substantial private investment by RIDA
– Hotel Brand to be finalized
– Will include a MWBE clause
– Will include a labor neutrality clause
• Begin a process later this year regarding the proposed garage
• Work closely with PWE & METRO regarding mobility and impact of light rail around the proposed Hotel site and GRBCC.
![Page 13: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/13.jpg)
Future City Council Action
• Plan to return to Council later this year with a detailed description of the proposed agreements.
• No Direct General Funds from the City used. • As with other convention projects in Houston and across the Country,
tax rebates (HOT, etc.) and other incentives will likely be required.tax rebates (HOT, etc.) and other incentives will likely be required.
• Houston First may issue debt requiring Council approval.
– Could require Council approval to release the lien on Hilton Americas-Houston.
• No financial impact on the City or the City’s debt model.
![Page 14: Proposed Convention Center Hotel - houstontx.gov · GEORGE R. BROWN CONVENTION CENTER 2025 MASTER PLAN Gensler COMPARATIVE ANALYSIS HOTEL CAPACITY 1,000 additional hotel rooms are](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f0247807e708231d403798c/html5/thumbnails/14.jpg)