PROPHO
Transcript of PROPHO
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
Salient Feature of the Project
Location Sg. Mulau I Sg. Mantaranau Sg. Mulau II
HydrologyCatchment Area Design discharge
140km2
6.25m3/s50 km2
3.45m3/s160 km2
6.25m3/s
River Intake Gravity Weir Gravity Weir Gravity Weir
Settling BasinReinforced Concrete basin
Reinforced Concrete basin
Reinforced Concrete basin
Low Pressure PipeSizeLength
2.0m diameter1700m
1.7m diameter2600m
2.0m diameter1500m
Surge TankSizeHeight
8m diameter10.5m
7m diameter10.0m
6m diameter8.0m
PenstockSizeLength
1.7m diameter500m
1.4m diameter600m
1.7m diameter300m
PowerhouseReinforced Conrete Frame
Reinforced Conrete Frame
Reinforced Conrete Frame
TailraceReinforced concrete canal
Reinforced concrete canal
Reinforced concrete canal
Turbine Type Francis Francis Francis
Generator Type Synchronous Synchronous Synchronous
Transmission Line 11kV to common 33kV system
11kV to common 33kV system
11kV to common 33kV system
Switching Station Reinforced Concrete Frame
Reinforced Concrete Frame
Reinforced Concrete Frame
Installed Power Energy Generation
5000kW30,500 MWh
2500kW14,200MWh
2000kW12,500MWh
Page 1
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
EXECUTIVE SUMMARY
Afie Power Sdn Bhd (APSB) is proposing the development of an integrated
mini hydropower scheme at the Tuaran River basin in the district of
Tuaran, Sabah. This scheme would involved the setting up of three (3)
mini hydropower plants at the tributaries of the Tuaran River Basin with a
total installed capacity of 9.5 MW and an export capacity of 9.12 MW.
The development of this integrated mini hydropower scheme, on a build,
own and operate concept, will follow the guidelines outlined in the Small
Renewable Energy Program (SREP).
APSB, a joint venture company between a local Bumiputra
contractor, Afie Enterprise Sdn Bhd and H2RM Engineering Sdn Bhd,
the technical service provider, is confident for a smooth and fast
development of the Tuaran River basin mini hydropower plant as APSB
is backed by experienced and established parent companies.
APSB has, for the past one year, done a preliminary feasibility studies on
the proposed development through site visits, desk study and discussions
with SESB. A detail feasibility studies shall be carried out once APSB
obtained permission and support from the Ministry of Energy, Water and
Communication.
Page 2
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
1.0 INTRODUCTION
APSB is a joint venture between Sabah contractor, Afie Enterprise Sdn
Bhd (Afie) and H2RM Engineering Sdn Bhd (H2RM), a company
rendering engineering and project management services in the
development of mini hydro power plants. APSB is formed upon the
discovery of the potential of Tuaran River Basin for the
development of a mini hydro power scheme which lies in the district
of Tuaran. The proposed power plants are located at Sg. Mulau and
Sg. Mantaranau. These rivers are major tributaries of Tuaran River.
The potential of Sg. Mulau and Sg. Mantaranau were discovered
during a river scouting exercise carried out by H2RM in identifying
viable site locations for the development of mini hydropower plants.
After a preliminary feasibility study was carried out by H2RM, it is
found that by combining Sg. Mulau and Sg. Mantaranau
development, it is possible to harness the mini hydropower
capacity leading to an installed capacity of 9.5MW and export
capacity of 9.12MW.
For the past one year, APSB has done a preliminary feasibility
studies on the potential and viability of Tuaran River basin for the
development of mini hydro power plants. APSB has visited the site in
the process of determining the location of the intake, pipeline route,
power house and the interconnection point. APSB has also studied
the topography of the site and a preliminary calculation of energy
was performed based on calculated assumptions of certain data.
Page 3
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
APSB will conduct a detail and thorough study once the development
approval has been obtained from the Ministry of Energy, Water and
Communication.
APSB has also attended meetings and discussions with the District
Office of Tuaran and Economic Planning Unit of Sabah of which
clearance and support for the development was given on 4 th
December 2006 via a letter referenced PDTRN(S)400-9/2 Klt7/(93)
and 16 January 2008 via letter referenced UPEN 600-26/1/2 Vol.3/2
(attached).
Thus, in line with the launching of the Small Renewable Energy
Program by the Government of Malaysia, APSB is most happy to
support the program with a proposal for the development of an
integrated mini hydropower scheme at Tuaran River basin, in the
district of Tuaran, Sabah.
Page 4
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
2.0 DEVELOPER BACKGROUND
APSB , a Bumiputra company, is 51% owned by Afie Enterprise Sdn
Bhd (Afie) and 49% owned by H2RM Engineering Sdn Bhd (H2RM).
Afie, incorporated in August 1998, is a 100% Bumiputra Kelas A PKK
contractor involves in civil and structural engineering works. With a paid
up capital of RM 800,00.00, Afie has been awarded contracts mainly
from Government sectors worth RM 140 million of which contracts
worth RM 94 million are ongoing. Among the on going contracts are the
Design, Build and Commissioning of Water Treatment Plant at
Sipitang, Sabah worth RM 56.8 million and the Design, Build and
Commissioning of Water Treatment Plant at Kudat, Sabah worth RM
30 million.
H2RM is an engineering company, specially formed for the purpose of
the joint venture for the development of the Tuaran River basin mini
hydropower scheme. H2RM is wholly owned by SSM Associates Sdn
Bhd (SSM), an engineering consulting company, providing engineering
and management services in civil, structural, mechanical and electrical
in buildings, roads and bridges, substations, sewerage and water
treatment, renewable energy projects such as are solar hybrid, wind
electrical power, mini hydropower, and electrical transmission facilities.
SSM started off as a partnership concern in 1991 and incorporated as
a private limited company in 1996. At present, SSM is the consultant to
Page 5
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
three mini hydro power plants development of total 9 MW in Sabah,
2MW mini hydro power plant in Selangor and 2.8 MW mini hydro power
plant in Kelantan.
3.0 PROJECT LOCATION
The proposed site is located at 20 km south east of Tamparuli town.
Access to site is through an asphalt road from Tamparuli town to Kg.
Pukak and finally through a well maintained laterite roads.
The proposed project areas are located about upstream of the
confluence of Sg. Tuaran and Sg. Mulau. The project sites are all
located on Sg. Tuaran tributaries; Sg. Mulau and Sg. Mantaranau.
The total catchment area of these three rivers amounting to 230km2
afforded a very good potential for development of mini hydropower.
These sites are about 6km upstream of the above river confluence
and located where there are good water gradient along the river
alignments. Such features would lead relatively high water head and
economically viable mini hydropower schemes. The powerhouse
locations are situated reasonable close to each other which allow a
common 33kV distribution system. This system is then connected to
the nearby SESB distribution system.
The locations of the diversion weirs, pipelines and the proposed
power house areas are shown in the attached location map in
Appendix 1.
Page 6
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
4.0 HYDROLOGICAL STUDIES
4.1 BASIN CHARACTERSTICS
The proposed project is located at three (3) major tributaries of
Tuaran River. The total catchment area of upstream of the
proposed intake site is 230 km2. All the catchment area of Tuaran
basin lies below 1000 m. The project site is located in the Western
Sabah Region at latitude N06°05’028”-05°56’528” and longitudes
E116°17’308”-116°23’372”. Whole catchment area lies in the Tuaran
District. The basin is leaf shape and shown in Figure 4.1
The upper drainage basin of Tuaran lies within the Crocker range.
The maximum altitude of the basin is 1000m amsl. The total length
of the Tuaran main stream up to the sea confluence is about 60 km
and its catchment area is about 546 km2.
The intake and powerhouse sites are in Sg. Mulau and Sg.
Mantaranau. They are located about 6km upstream of their
respective confluence with Tuaran River.
4.2 CLIMATE STUDY
The basin experiences warm and humid climatic condition throughout
the year. The yearly maximum temperature of the project sites are
about 35°C and the minimum temperature about between 20° C.
Page 7
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
The relative humidity in percent is 90% and is quite consistent
throughout the year.
4.3 HYDROLOGY STUDY
The reference metrological stations are the Tamu Darat and
Tuaran river stations, which provide both the rainfall and daily flow
records. From the available data, it is noticed that most of the
rainfall occurs over the basin during beginning and middle of the
year. The low rainfall usually occurs in March and August. The
flows in the rivers correspond concurrently to the rainfall data.
Flow duration curves each project intake sites are derived from the
above two stations. This is depicted in Table 4.1
Table 4.1: Flow Duration Curve Data – Integrated Tuaran River Scheme
PercentageExceedance
Sg Mulau Flow(m3/s)
Sg. Mataranau Flow(m3/s)
Sg. Mengkaladom Flow(m3/s)
0%5%10%15%20%25%30%35%40%45%50%55%60%65%70%75%
47.135.927.022.018.716.114.112.310.99.608.407.506.605.805.104.30
16.8012.809.607.906.705.805.004.403.903.403.002.702.302.101.801.50
13.5010.307.706.305.304.604.003.503.102.702.402.101.901.701.401.20
Page 8
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
80%85%90%95%
100%
3.602.902.201.600.30
1.301.000.800.600.10
1.000.800.600.400.10
Page 9
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
5.0 GEOLOGICAL STUDIES
Generally the project site is under laid by the Kulapis Formation. The
lithology of the site comprises of limestone, shale, siltstone and
sandstone.
The regional geology of the project area is given in the
fig.5.1.
The project area is covered with limestone, shale, and siltstone
and sandstone material. It is expected the geological conditions at site
would pose little problem for construction of the mini hydropower
project.
Figure 5.1 Figure 5.1 Geological condition at site
Page 10
Kulapis Formation
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
6.0 MINI HYDRO POWER PLANT DESCRIPTION
Mini hydro is a form of renewable energy adopted by the
government as the fifth fuel resource. The fuel used in this system
is water, which is the main force to run the turbine consequently
generate electricity. This technology is proven on the reliability of
continuous supply of electricity.
Run-of- river concept will be employed in the proposed scheme.
It refers to the mode of operation in which the hydro plant uses
only the water that is available in the natural flow of the river.
Run-of-river implies that no water storage or flooding and that
power fluctuate with the stream flow. This concept requires low
diversion weir and the environment impact are less significant.
In adopting this concept, certain hydraulic features have to be
incorporated in the design and are described below:
6.1 DESCRIPTION OF PHYSICAL FACILITIES
6.1.1 CIVIL WORKS
6.1.1.1 Intake Structures
A water intake is a structure to divert water into a pipelines or
waterway. An intake must be able to divert the required
Page 11
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
amount into the penstock without producing a negative
impact on the local environment and with minimum head loss.
Its design, based on geological, hydraulic, structural and
economic considerations requires special care to avoid
unnecessary maintenance and operational problems that
cannot be easily remedied and would have to be tolerated for
the life of the project.
The water intake will consist of concrete gravity structure with
an overflow spillway section with two gated undersluice.
Attached to the side, shall be the settling basin structure. The
basin will allow suspended sand particle to be settled and
flushed away. The basin is connected to the pipeline system.
The typical drawings of the intake system are attached in the
Appendix 1. The dimensions of intake structures for the three
project locations are summarized in Table 6.1.
Sg. Mulau ISg.
MantaranauSg. Mulau II
Intake type
Intake length
Intake height
Gravity
30m
4m
Gravity
25m
4m
Gravity
25m
4m
Table 6.2 Dimensions for the settling basins.
Sg. Mulau ISg.
MantaranauSg. Mulau II
Type
Basin length
Reinforced Concrete
Reinforced Concrete
Reinforced Concrete
Page 12
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
Basin height30m
4m
25m
4m
25m
4m
6.1.1.2 Pipeline
Mild steel pipeline or open channel will be adopted to convey
water from the intake to the turbine in the power house. For steel
pipelines, it may be installed over or under the ground,
depending on factors such as the nature of the ground itself, the
penstock material, the ambient temperatures and the
environmental requirements. Thrust blocks will be constructed at
all vertical and horizontal bends. Pipes that are installed above
ground will be supported by reinforced concrete pipe supports.
It is expected that the pipeline system be divided into two main
portions; the low pressure pile and the penstock. These portions
are divided by the surge tank which is required to allow proper
operation of the turbine system. The penstock connects the
surge tank to the power house and is usually faced with high
water pressure and will require higher thickness. The
dimensions and details of the pipeline and surge tank are stated
in Table 6.3.
Sg. Mulau ISg.
MantaranauSg. Mulau II
Low Pressure Pipe
2.0m diameter1700m length
1.7m diameter2600m length
2.0m diameter1500m length
Surge Tank8m diameter
7m diameter10.0m height
6m diameter8.0m height
Page 13
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
10.5m height
Penstock1.7m diameter
500m1.4m diameter
600m1.7m diameter
300m
Typical drawings of pipe and its ancillaries are attached in
Appendix 2.
6.1.1.3 Power house
The power house protects the electromechanical equipment
from incremental weather effects. The number, type and power of
the generators, their configuration, the scheme head of the site
controls the shape and size of the building. The building is usually
reinforced concrete frame with metal cladding for wall and roof. It
is divided into the turbine hall, control and switchgear room. Utility
room and toilet are also provided for storage and amenity
purposes. The outdoor transformers are installed on concrete
plinth, close to the switchgear room. Table 6.4 illustrates the
general dimension of the power house.
Table 6.4 General dimension of the power house.
Sg. Mulau ISg.
MantaranauSg. Mulau II
Power House Type
Reinforced concrete frame
Reinforced concrete frame
Reinforced concrete frame
Dimensions 30m x 15m 25m x 13m 25m x 13m
Page 14
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
The general layout of the power house is attached in the Appendix
3.
6.1.1.4 Tailrace
Water in the pipeline, passes through the turbine in the power
house, returns to the river through a tailrace. Since the water
have high exit velocities, the tailrace shall be designed to
ensure that the powerhouse would not be undermined. The
design shall also ensure that, during relatively high flows or
flooding condition, the water in the tailrace does not rise so high
that it interferes with the turbine operation. The tailrace is usually
constructed of reinforced concrete canal with stop logs to control
the water level. This is imperative to ensure proper functioning of
the Francis water turbines.
6.1.2 ELECTROMECHANICAL EQUIPMENT AND AUXILIARIES
6.1.2.1 Turbine equipment
The purpose of the turbine is to transform the water potential
energy to mechanical rotational energy i.e. the water pressure
and velocity of the water react with the runner of turbine to
produce torque on the shaft. The type, geometry and dimensions
of the turbine will be fundamentally conditioned by the following
criteria:
a. Water Head
Page 15
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
b. Design Flow
c. Rotational speed
d. Cavitations problems
Based on the data available and site conditions, the most appropriate
turbines would be of Francis type. This turbine type has been
employed successfully throughout the world for both large and small
hydro installation with moderately high water head. For ease in
maintenance and operation, it is envisaged that 2 turbines system be
adopted for each project location. Table 6.5 depicts the turbine
configuration based on optimizing of the derived hydrology data and
flow rates.
Table 6.5 Configuration of turbines
Sg. Mulau ISg.
MantaranauSg. Mulau II
Turbine Type Francis Francis Francis
No. and Rating
2 x 2500kW 2 x 1000kW 2 x 1250kW
Design FlowGross Head
6.25m3/s91m
3.45m3/s91m
2.55m3/s91m
6.1.2.2 Generators equipment
The proposed scheme will be installed with synchronous
generators which transform the mechanical energy into electrical
Page 16
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
energy. The generator shall be horizontal shaft type, each
complete with exciter, AVR, and the necessary auxiliary
equipment. Each of these generators would be coupled directly to
their associated turbines. The power would be generated at a
rated voltage of 3.3kV, rated frequency 50Hz and a rated power
factor 0.85. Each generator in the powerhouse shall be connected
to a 3.3kV group bus. The power outputs from all the three project
locations 3.3kV group buses are stepped up to 11kV by means of
three-phase 3.3/11 kV transformers and shall be fed into the
transmission system at 11kV through a single circuit overhead line
to a common 11/33kV substation near Kg. Pukak. Table 6.6
illustrates depicts the turbine configuration based on optimizing of the
derived hydrology data and flow rates.
Table 6.6 Generator details
Sg. Mulau ISg.
MantaranauSg. Mulau II
Generator Type
Francis Francis Francis
No. and Rating
2 x 3000kVA 2 x 2500kVA 2 x 2600kVA
Power factor 0.85 0.85 0.85
The two generators at each powerhouse will be synchronized at
the 3.3kV generation busbar. Three core type CT shall be
connected in the stator for protection purpose. Insulation materials
shall be of class F. 11kV indoor single bus configuration shall be
Page 17
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
adopted. SF6 circuit breakers are provided, on the transformer
secondary and line side. The transformer will be located at the
outdoor area. The surge arrestors are provided on the line side to
protect against over-voltages caused by lightning and switching
surges.
6.1.2.3 Control and Protection
The powerhouse will normally be attended. Full automatic control
of units will also be possible. Both manual and automatic control
will be provided.
The protection panels will accommodate the turbine-generator, the
main transformer, transmission line and auxiliary transformer
protection relays.
Turbine shall be provided for various protection schemes.
Different protection schemes will be adopted for generation
protection such as; differential protection, field loss protection,
reverse power protection, over-voltage and over-current protection
and ground-over protection.
6.1.2.4 Interconnection Facilities
The interconnection facilities would consist of the common
11/33kV substation facility and the outgoing 33kV transmission
line. The substation shall be located near Kg. Pukak. It shall be a
reinforced concrete frame structure with switchgear and control
Page 18
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
rooms to accommodate the associated equipment.
The incoming 11kV line from the three project sites shall be
connected to 11kV group busbar. These are then stepped up to
33kV by means of one three-phase 11/33kV transformer and shall
be fed at 33kV through a single circuit overhead transmission line
to the existing SESB Tambalugu, Tuaran substation. A new 33kV
bay comprising all necessary equipment shall have to be procured
and installed to allow the interconnection.
6.1.2.5 Interconnection Facilities
Apart from the above, auxiliary equipment are needed to ensure
proper and smooth running of the hydropower facilities. The
required equipment can be summarized as follows;
• Water shut off valve(s) for the turbine.
• Bypass gates and controls.
• Hydraulic control system for the turbine and valve
• Electrical protection and control system
• Electrical switchgears
• Auxiliary Transformers
• Telecommunication system
• DC battery systems
• Powerhouse crane
• Utility interconnection or transmission and distribution
system.
A single line diagram illustrating the all above installation is
Page 19
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
attached in the Appendix 4.
7.0 ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
The environmental impact arising from the development of mini
hydro scheme to this area is very minimal. The concept to be
adopted in the development of the mini hydro at this area is of a
run-off-river concept, which means that there is no submergence
of either flora or fauna.
As for the construction activities, the impact is minimal to the
surrounding as the activities of construction is similar to that of a
general civil engineering construction works.
8.0 PROJECT COST AND FINANCING
Until a detail feasibility study is carried out, it is estimated that the
total development cost shall be in the region of RM 96.9 million.
APSB will be responsible wholly in financing the development
costs.
Page 20
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
9.0 SELLING PRICE
APSB is proposing a selling price of 19.5 sen for the whole license
period of 21 years, on a willing seller willing buyer and take and pay
basis.
10.0 PROJECT VIABILITY
At a proposed selling price of 19.5 sen for a licensed period of 21
years, the project is found to be economically viable with a project
Internal Rate of Return of 10.2%, which is slightly higher than
APSB’s cost of capital.
The Tuaran Integrated River Basin mini hydro power plants, with an
installed capacity of 9.5 MW and generating capacity of 9.12 MW, is
expected to be developed within 24 months at an estimated cost of
RM 96.9 million, including Interest During Construction.
Page 21
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
11.0 CONCLUSION
The proposed development of Tuaran Integrated River Basin mini
hydro power plants is in line with the Government of Malaysia Fifth
Fuel Policy and the Small Renewable Energy Program in promoting
renewable energy as the fifth source of energy generation mix in
Malaysia.
APSB, backed by Afie Eterprise Sdn Bhd, a local Sabah company
with 9 years construction experience and H2RM Engineering Sdn
Bhd, a wholly owned subsidiary of SSM Associated Sdn Bhd, an
engineering consultant company with 16 years experience in project
management and consultancy, is confident to develop the proposed
project successfully as APSB has the technical and financial support
from its parent companies.
Hence, APSB is very hopeful that Ministry of Energy, Water and
Communication approve our proposal to develop the Tuaran
Page 22
Integrated Mini Hydropower Project - Sg Tuaran Afiepower Sdn Bhd
Integrated River Basin mini hydro power plants in supporting the
Government strategy to intensify the development of Renewable
Energy as the fifthr fuel resource.
Page 23