Property Maintenance & Operations Manual Training
Transcript of Property Maintenance & Operations Manual Training
Property Maintenance & Operations Manual Training
Capital Project Management Contract Administration
November 29, 2010
2November 29, 2010
• November 8, 2010Workplace Health and SafetyHousekeepingSuite Turnover & Annual InspectionsAfternoon: Landscape Maintenance & Project Management / Contract
Administration
• November 29, 2010Landscape MaintenanceCapital Project Management Contract Administration
• Further Training & Education– Colleges, Universities & Property/Facility Management Associations – On-line, classroom settings, correspondence
Property Maintenance & Operations Manual Training
3
This chapter is in place in order to ensure a consistent and a logical process when managing individual capital projects or ongoing recurring service contracts.
A project must be carefully planned
• Projects must be completed within a predetermined time frame
• An estimate of value has been completed and a budget established that must be adhered to
• A defined scope of work has been established along with quality expectations
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
4
The Laws of Capital Project ManagementSteps that need to be followed:
• Identification of project
inspection process
identification of deficiencies
reason for deficiency existing
corrective action required
• Initiation
• Planning
• Control
• Change management
• Closeout
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
5
The Inspection Process
Building Components/Elements:• Components expected to last the life of the building
• Elements subject to extensive wear due to mechanical and human traffic or exposure to the elements
• Elements who’s useful life can be prolonged through Planned Preventative Maintenance (PPM)
• Elements that would be obsolete due to technical advances, fashions or lifestyles
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
6
The Inspection Process
DeficienciesOnce the deficiency has been identified & inspected:
• Corrective action may be immediate repair or replacement
• Corrective action may be planned and budgeted for future action
• It should be noted the reason for the deficiency
• Is it due to abuse, neglect, poor maintenance, inferior product etc.
• Use the most current products and building practices to correct the deficiency
• Pay me now or pay me later
• PPM program or immediate corrective action will prolong the expected life of the component and reduce capital expenditures
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
7
The Inspection Process
Deficiencies• Sound procedures are to be implemented on tendering
• Tendering is the process of securing competitive bid prices
• Obtain the best possible price from qualified contractors
• Define the work to be done (scope)
• Specification should be clear, concise, comprehensive and coordinated
• Include general requirements, product information and execution
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
8
Specification Content
• Type and quality of materials, products, equipment and fixtures
• Dimensions
• Method of fabrication and execution of the work
• Level of workmanship
• Testing requirements
• Drawing Content:
Quantities of materials, Products, Equipment, Dimensions, Layouts, Location of components, Schedule or lists of finishes, windows & doors
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
9
Tendering• Outline Specification - identifies the scope of work only. Not often used in construction
• Prescription Specification - directs the contractor in carrying out the task through a list of procedures
• Proprietary Specification (or base bid) - particular products or products are listed. Often qualified with a statement “approved alternate”
• Performance Specification - Specifies the end result or performance of a particular component or system
• Cost Plus Contracts – used when the extent of the work is unknown. Must be carefully supervised and monitored.
…
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
10
Tendering• Stipulated Price Contracts
Cost of the work as defined in the specification at a fixed dollar price.
• Unit Price Contract
Based on detailed listing of materials & estimated quantities required for the work
Tendering• Invitational:
You decide in which contractors will be permitted to bid…past performance
• Public:
This process is done by placing an add in the local newspaper/trade paper
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
11
Tendering
When tendering a project consider the following:
• Time to prepare the package
• Client/unit requirements
• Pre-tender meeting with contractors
• Method of securing bids
• The contractors will bid on the information provided
• Same information must be provided to each contractor
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
12
TenderingInstructions to Bidders
• Closing date
• Location of work
• Owners name and address
• Requirements for reference
• Bid security and bonding requirements
• Substitution information
• Liability insurance and WSIB requirements
• Requirements for certification of trades
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
13
Tendering
Construction Specifications Canada - 16 Division Master formatMaster format published by the Construction Specifications Institute and Construction Specifications Canada. Used by designers, suppliers and trades.
General requirements Finishes
Site-work Specialties
Concrete Equipment
Masonry Furnishings
Metal Special construction
Woods and plastics Conveying systems
Thermal and moisture protection Mechanical
Doors and windows Electrical
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
14
Tendering
Problems in SpecifyingAn analysis of nearly 200 projects showed the following breakdown problems in specifications that resulted in disputes:
“Or equal to clause” 35%
“Site construction problems” 18%
“Ambiguities” 17%
“Conflicts between drawings & specs 15%
“Inaccurate technical data” 15%
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
15
Pre- Tender Meeting• Intent of the meeting is to clarify the scope of work and answer any questions from the contractors.
• Disclose all relevant information
• This is an opportunity to identify anything that was in the specifications and an opportunity to include anything that was missed
Addendum• Change in the contract prior to closing – clarifies revisions, deletions and inclusions
• All contractors must receive this information in writing
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
16
Tender opening• Date stamp and record time of receipt
• Documents received after the closing time should not be opened
• Contractors may not amend their bid after they have been opened
• Not recommended to accept faxed bids. Confidentiality
• Public - tender opening on same day of closing
• Private - tender opening on a later day that has been specified
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
17
Review of BidsReject bids…
• Improper format, missing security deposit, contain escalator clauses or conditional letters
• Rejected bids should be returned to bidder with a letter explaining why the bid was rejected.
• Check for accuracy, bid security, names of sub-trades
• Confirm that errors of omissions have not taken place.
• Check for references prior to awarding
• Check for financial situation of contractor and their track record on paying their sub-trades
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
18
Awarding the ContractLetter of intent to award asking for the following documentation:
Performance bond, WSIB clearance, Labor & Material bond, Liability insurance, MSDS/WHMIS, H&S Checklist
Legal Implications• Implied as a contract once tender packages are out in circulation
• The court considers tender calls as an offer and the bid as acceptance
• A contract is deemed to exist if the bid is made in compliance of the conditions of the tender package
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
19
Typical Pitfalls• Hoping problems work themselves out
• Relying on second hand inputs rather than following up yourself
• Not asking for help
• Winning contractor is predetermined
• Strong bias against a particular contractor
• Bidders have not been advised to changes to the contract documents
• Not appointing knowledgeable person as the contract administrator
• Not provide all information to contractors in writing
• Not documenting all contacts with the contractors including items of discussion
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
20
Project Review• Monitoring the progress of the project begins on the first day
• Initial contract meeting
• Review contract documents
• Establish a schedule
• Establish the lines of communication
• Sample and Mock-Ups
Keep Everything Under Control• Before the project starts have an initial meeting with all involved to discuss the following:
Owner, Contractor, Client and/or tenant(s), Designer, Suppliers
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
21
Improving Procedures• Early communication
• Pre-construction meeting with the architect, project manager, contractor & sub-contractors
• Early sourcing of materials to ensure availability
• Shop drawings at an early stage
• Review at an early stage for building science validation
• Develop a bank of proven details
• Delete poor details
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
22
Role of the Contract Administrator• Monitor & control costs, are the conditions of the contract are being met?
• Confirm on site the methods of construction and quality of materials used
• Prevent unacceptable substitutions or poor assembly
• Interpret the intent of the drawings and specifications
• Foresee the possibility of error, omissions or misunderstandings
• Prevent unnecessary conflicts, disputes or costly delays
• Record events & decisions which could have an impact now or later in the project
• Plan the project sequence with the contractor –
ensures co-ordination of sub-trades, confirm the advance ordering of materials
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
23
Role of the Contract Administrator
• Provide prompt and periodic reporting of the progress of the work
• Use judgment & experience in permitting certain substitutions (equal or better)
•Provide consultation regarding optional ways of performing some portion of the work that will be acceptable to all
• Prevent unfair practices, procedures or any attempt to avoid obligations in the contract
•Give Health & Safety priority at the outset of planning and identify hazardous conditions during the construction phase.
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
24
Initial Site Meetings• Review contract documents
• Start and completion dates
• Temporary services, washroom facilities
• Building access, parking and storage
• Owner/contractor contacts during and after hours, communication
• Construction schedule
• Products and substitutions
• Change orders
• Progress payments
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
25
Site Review Meetings• At the end of each week conduct a project review meeting
• Prepare a well thought agenda that includes
Major accomplishments since the last review
Schedule status (actual vs. planned)
Major issues (problems)
Plans for the next review period
• Invite the essential people
• Clearly identify the objectives of the meeting
• Review the deliverables, where they met?
…
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
26
Site Review Meetings• Has quality control been established and is the standard being met?
• When milestones are not being met the Contract Administrator should be focusing on why they are not being met.
• When will they be met.
• The earliest date the project will be back on schedule
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
27
Capital Project Management & Contract Administration Chapter 12
Slippage• Slippage can cause disastrous delays and backlogs
• Identify the milestones that have not been met
• Create an action plan to meet these milestones while maintaining existing ones.
• Follow project schedules and stay on track
• Schedules should clearly identify:
- Who is doing what task
- When it is to be completed by.
November 29, 2010
28
Wrap-up Meetings
• Identify deficiencies and discuss the schedule to achieve completion
• Discuss outstanding defects
• Resolve warranty issues and the submissions required
• Identify any required reports and warranties
• Secure regulatory agency releases to permit occupancy
• Identify required As-Built drawings (changes recorded on original drawings)
• Identify required Record drawings ( permanent recorded changes on new transparency)
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
29
Construction Lien Act• A lien is a charge on the owners interest in his or her land and building.
• Everyone supplying construction materials & services to a project has lien rights except architects and their employees.
• Lien rights begin as soon as a person provides materials or services to an improvement
• A lien must be registered within 45 days of publication of substantial performance or within 45 days of completion of providing materials or services.
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
30
Holdbacks• 10% of the contract value must be held from all progress payments to the head contractor to cover potential lien claims.
• Anyone who receives payment is holding it in trust for those that actually supplied materials and or services.
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
31
Substantial Performance• If a construction project is substantially completed, that is, it is inhabitable or useable, then payment has to be made.
• The owner is permitted to make a reasonable deduction for the cost of achieving full performance.
3% of the first $500k of the contract price
2% of the next $500k
1% of the balance of the contract price
Capital Project Management & Contract Administration Chapter 12
November 29, 2010
Refer to Chapter 12 of the manual for more information relating to Capital Project Management and Contract Administration.