Property Maintenance & Operations Manual Training

37
Property Maintenance & Operations Manual Training Capital Project Management Contract Administration November 29, 2010

Transcript of Property Maintenance & Operations Manual Training

Property Maintenance & Operations Manual Training

Capital Project Management Contract Administration

November 29, 2010

2November 29, 2010

• November 8, 2010Workplace Health and SafetyHousekeepingSuite Turnover & Annual InspectionsAfternoon: Landscape Maintenance & Project Management / Contract

Administration

• November 29, 2010Landscape MaintenanceCapital Project Management Contract Administration

• Further Training & Education– Colleges, Universities & Property/Facility Management Associations – On-line, classroom settings, correspondence

Property Maintenance & Operations Manual Training

3

This chapter is in place in order to ensure a consistent and a logical process when managing individual capital projects or ongoing recurring service contracts.

A project must be carefully planned

• Projects must be completed within a predetermined time frame

• An estimate of value has been completed and a budget established that must be adhered to

• A defined scope of work has been established along with quality expectations

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

4

The Laws of Capital Project ManagementSteps that need to be followed:

• Identification of project

inspection process

identification of deficiencies

reason for deficiency existing

corrective action required

• Initiation

• Planning

• Control

• Change management

• Closeout

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

5

The Inspection Process

Building Components/Elements:• Components expected to last the life of the building

• Elements subject to extensive wear due to mechanical and human traffic or exposure to the elements

• Elements who’s useful life can be prolonged through Planned Preventative Maintenance (PPM)

• Elements that would be obsolete due to technical advances, fashions or lifestyles

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

6

The Inspection Process

DeficienciesOnce the deficiency has been identified & inspected:

• Corrective action may be immediate repair or replacement

• Corrective action may be planned and budgeted for future action

• It should be noted the reason for the deficiency

• Is it due to abuse, neglect, poor maintenance, inferior product etc.

• Use the most current products and building practices to correct the deficiency

• Pay me now or pay me later

• PPM program or immediate corrective action will prolong the expected life of the component and reduce capital expenditures

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

7

The Inspection Process

Deficiencies• Sound procedures are to be implemented on tendering

• Tendering is the process of securing competitive bid prices

• Obtain the best possible price from qualified contractors

• Define the work to be done (scope)

• Specification should be clear, concise, comprehensive and coordinated

• Include general requirements, product information and execution

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

8

Specification Content

• Type and quality of materials, products, equipment and fixtures

• Dimensions

• Method of fabrication and execution of the work

• Level of workmanship

• Testing requirements

• Drawing Content:

Quantities of materials, Products, Equipment, Dimensions, Layouts, Location of components, Schedule or lists of finishes, windows & doors

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

9

Tendering• Outline Specification - identifies the scope of work only. Not often used in construction

• Prescription Specification - directs the contractor in carrying out the task through a list of procedures

• Proprietary Specification (or base bid) - particular products or products are listed. Often qualified with a statement “approved alternate”

• Performance Specification - Specifies the end result or performance of a particular component or system

• Cost Plus Contracts – used when the extent of the work is unknown. Must be carefully supervised and monitored.

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

10

Tendering• Stipulated Price Contracts

Cost of the work as defined in the specification at a fixed dollar price.

• Unit Price Contract

Based on detailed listing of materials & estimated quantities required for the work

Tendering• Invitational:

You decide in which contractors will be permitted to bid…past performance

• Public:

This process is done by placing an add in the local newspaper/trade paper

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

11

Tendering

When tendering a project consider the following:

• Time to prepare the package

• Client/unit requirements

• Pre-tender meeting with contractors

• Method of securing bids

• The contractors will bid on the information provided

• Same information must be provided to each contractor

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

12

TenderingInstructions to Bidders

• Closing date

• Location of work

• Owners name and address

• Requirements for reference

• Bid security and bonding requirements

• Substitution information

• Liability insurance and WSIB requirements

• Requirements for certification of trades

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

13

Tendering

Construction Specifications Canada - 16 Division Master formatMaster format published by the Construction Specifications Institute and Construction Specifications Canada. Used by designers, suppliers and trades.

General requirements Finishes

Site-work Specialties

Concrete Equipment

Masonry Furnishings

Metal Special construction

Woods and plastics Conveying systems

Thermal and moisture protection Mechanical

Doors and windows Electrical

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

14

Tendering

Problems in SpecifyingAn analysis of nearly 200 projects showed the following breakdown problems in specifications that resulted in disputes:

“Or equal to clause” 35%

“Site construction problems” 18%

“Ambiguities” 17%

“Conflicts between drawings & specs 15%

“Inaccurate technical data” 15%

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

15

Pre- Tender Meeting• Intent of the meeting is to clarify the scope of work and answer any questions from the contractors.

• Disclose all relevant information

• This is an opportunity to identify anything that was in the specifications and an opportunity to include anything that was missed

Addendum• Change in the contract prior to closing – clarifies revisions, deletions and inclusions

• All contractors must receive this information in writing

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

16

Tender opening• Date stamp and record time of receipt

• Documents received after the closing time should not be opened

• Contractors may not amend their bid after they have been opened

• Not recommended to accept faxed bids. Confidentiality

• Public - tender opening on same day of closing

• Private - tender opening on a later day that has been specified

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

17

Review of BidsReject bids…

• Improper format, missing security deposit, contain escalator clauses or conditional letters

• Rejected bids should be returned to bidder with a letter explaining why the bid was rejected.

• Check for accuracy, bid security, names of sub-trades

• Confirm that errors of omissions have not taken place.

• Check for references prior to awarding

• Check for financial situation of contractor and their track record on paying their sub-trades

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

18

Awarding the ContractLetter of intent to award asking for the following documentation:

Performance bond, WSIB clearance, Labor & Material bond, Liability insurance, MSDS/WHMIS, H&S Checklist

Legal Implications• Implied as a contract once tender packages are out in circulation

• The court considers tender calls as an offer and the bid as acceptance

• A contract is deemed to exist if the bid is made in compliance of the conditions of the tender package

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

19

Typical Pitfalls• Hoping problems work themselves out

• Relying on second hand inputs rather than following up yourself

• Not asking for help

• Winning contractor is predetermined

• Strong bias against a particular contractor

• Bidders have not been advised to changes to the contract documents

• Not appointing knowledgeable person as the contract administrator

• Not provide all information to contractors in writing

• Not documenting all contacts with the contractors including items of discussion

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

20

Project Review• Monitoring the progress of the project begins on the first day

• Initial contract meeting

• Review contract documents

• Establish a schedule

• Establish the lines of communication

• Sample and Mock-Ups

Keep Everything Under Control• Before the project starts have an initial meeting with all involved to discuss the following:

Owner, Contractor, Client and/or tenant(s), Designer, Suppliers

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

21

Improving Procedures• Early communication

• Pre-construction meeting with the architect, project manager, contractor & sub-contractors

• Early sourcing of materials to ensure availability

• Shop drawings at an early stage

• Review at an early stage for building science validation

• Develop a bank of proven details

• Delete poor details

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

22

Role of the Contract Administrator• Monitor & control costs, are the conditions of the contract are being met?

• Confirm on site the methods of construction and quality of materials used

• Prevent unacceptable substitutions or poor assembly

• Interpret the intent of the drawings and specifications

• Foresee the possibility of error, omissions or misunderstandings

• Prevent unnecessary conflicts, disputes or costly delays

• Record events & decisions which could have an impact now or later in the project

• Plan the project sequence with the contractor –

ensures co-ordination of sub-trades, confirm the advance ordering of materials

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

23

Role of the Contract Administrator

• Provide prompt and periodic reporting of the progress of the work

• Use judgment & experience in permitting certain substitutions (equal or better)

•Provide consultation regarding optional ways of performing some portion of the work that will be acceptable to all

• Prevent unfair practices, procedures or any attempt to avoid obligations in the contract

•Give Health & Safety priority at the outset of planning and identify hazardous conditions during the construction phase.

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

24

Initial Site Meetings• Review contract documents

• Start and completion dates

• Temporary services, washroom facilities

• Building access, parking and storage

• Owner/contractor contacts during and after hours, communication

• Construction schedule

• Products and substitutions

• Change orders

• Progress payments

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

25

Site Review Meetings• At the end of each week conduct a project review meeting

• Prepare a well thought agenda that includes

Major accomplishments since the last review

Schedule status (actual vs. planned)

Major issues (problems)

Plans for the next review period

• Invite the essential people

• Clearly identify the objectives of the meeting

• Review the deliverables, where they met?

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

26

Site Review Meetings• Has quality control been established and is the standard being met?

• When milestones are not being met the Contract Administrator should be focusing on why they are not being met.

• When will they be met.

• The earliest date the project will be back on schedule

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

27

Capital Project Management & Contract Administration Chapter 12

Slippage• Slippage can cause disastrous delays and backlogs

• Identify the milestones that have not been met

• Create an action plan to meet these milestones while maintaining existing ones.

• Follow project schedules and stay on track

• Schedules should clearly identify:

- Who is doing what task

- When it is to be completed by.

November 29, 2010

28

Wrap-up Meetings

• Identify deficiencies and discuss the schedule to achieve completion

• Discuss outstanding defects

• Resolve warranty issues and the submissions required

• Identify any required reports and warranties

• Secure regulatory agency releases to permit occupancy

• Identify required As-Built drawings (changes recorded on original drawings)

• Identify required Record drawings ( permanent recorded changes on new transparency)

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

29

Construction Lien Act• A lien is a charge on the owners interest in his or her land and building.

• Everyone supplying construction materials & services to a project has lien rights except architects and their employees.

• Lien rights begin as soon as a person provides materials or services to an improvement

• A lien must be registered within 45 days of publication of substantial performance or within 45 days of completion of providing materials or services.

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

30

Holdbacks• 10% of the contract value must be held from all progress payments to the head contractor to cover potential lien claims.

• Anyone who receives payment is holding it in trust for those that actually supplied materials and or services.

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

31

Substantial Performance• If a construction project is substantially completed, that is, it is inhabitable or useable, then payment has to be made.

• The owner is permitted to make a reasonable deduction for the cost of achieving full performance.

3% of the first $500k of the contract price

2% of the next $500k

1% of the balance of the contract price

Capital Project Management & Contract Administration Chapter 12

November 29, 2010

Refer to Chapter 12 of the manual for more information relating to Capital Project Management and Contract Administration.

32

Capital Replacements…

November 29, 2010

33

Capital Replacements…

November 29, 2010

34November 29, 2010

Some questionable methods…

35November 29, 2010

36November 29, 2010

37November 29, 2010