Project Project Status
Street Reconstruction & Repairs Working on SW 67th Street South of LeeWater Distribution,Storage & SCADA Gore Blvd. Waterline: Archeololgical Issues; Evaluating Other Alternatives
SEWTP, Tower & Dist. Lines Bidding Abandoned WWTP Demolition ProjectLandfill Subtitle "D" Cells Landfill Cells Complete; Performing Landfill Gas to Energy Feasibility Study
Phase II Sewer Rehab Program Under Construction (66% Complete)
Accounting Hardware & Software Project Complete
WWTP Ultraviolet System Project Complete
NW 38th (Cache to Gore) Right-Of-Way Acquisition OngoingNW 67th (Rogers Lane to Cache) Project Complete
SE 45th (Gore to Lee) Design Ongoing; Awaiting ODOT Funding
Meter Replacement Program Project Complete Numu Creek Drainage Project Complete
Lake Dam Improvements (if funds available) Pending Funding
Santa Fe Bridge (if funds available) Final Design Ongoing/Construction Pending Funding
Project Project Status
Phase II Sewer Rehab Program Under Construction (66% Complete)
Cameron University Building (CETES) Project CompleteDowntown Historic Preservation Project Project Complete
CITY OF LAWTON 2005 CIP SCHEDULE SALES TAX PROJECTS
CITY OF LAWTON AD VALOREM TAX PROJECTS
1
Project Description Project Status
STREETS
Ward One 09/10 Overlay Projects Complete; Reconstruction Projects On-going
Ward Two 09/10 Overlay Projects Complete
Ward Three 09/10 Overlay Projects Complete; Reconstruction Projects On-going
Ward Four 09/10 Overlay Projects Complete
Ward Five 10/11 Overlay Projects On Hold
Ward Six 10/11 Overlay Projects On Hold
Ward Seven 10/11 Overlay Projects Ongoing
Ward Eight 10/11 Overlay Projects On Hold
Purchase Asphalt Paving Machine Project Complete
BRAC & Existing CIP Projects NW 67th (Cache to Rogers Ln) Complete
NW 2nd (Gore to Columbia) Under Construction
Residential Street Designs Phases 1 & 2 Design Complete; Phase 3 Design Substantially Complete
Rogers Lane (I-44 to Flower Mound) Final Design Ongoing
WATERLINE IMPROVEMENTS
Low Flow Hydrant Project #1 Under Construction (21% Complete)
Low Flow Hydrant Project #2 Under Construction (50% Complete)
Low Flow Hydrant Project #3 Under Construction (36% Complete)
Low Flow Hydrant Project #4 11/12 Waterline Projects Scheduled, If Funding Available
Enterprise Car Rental F.H. Project Complete
Western Hills Christian Church F.H. Project Complete
Lawton Country Club Waterline Project Complete
SEWERLINE IMPROVEMENTS
Nine Mile Creek Sewer Line Final Design Ongoing/ROW Plans Ongoing
SEWER REHAB PROGRAM
Phase II Sewer Rehab Projects Under Construction (66% Complete)
CITY OF LAWTON 2008 CIP SCHEDULE
2