Project+management+basics

32
PROJECT MANAGEMENT BASICS ISOM 502

description

project management

Transcript of Project+management+basics

Page 1: Project+management+basics

PROJECT MANAGEMENT BASICS

ISOM 502

Page 2: Project+management+basics

2

Page 3: Project+management+basics

3

Page 4: Project+management+basics

4

Page 5: Project+management+basics

5

WBS

Page 6: Project+management+basics

6

Page 7: Project+management+basics

7

Function Point Analysis (FPA)

1000

Code of Lines 1.4 Estimate Time *

* Measured in person months

Page 8: Project+management+basics

8

PERT Time/Work Estimation

Estimates Days

Optimistic (To) 20

Likely (TL) 24

Pessimistic (TP) 34

20 4 24 34Time Estimate = 25 Days

6

6

4Estimate Time PLo TTT

Page 9: Project+management+basics

9

Page 10: Project+management+basics

10

Page 11: Project+management+basics

Gantt Chart

Task Duration

Task

SummaryTask

11

Page 12: Project+management+basics

Gantt Chart

Task Dependency

12

Page 13: Project+management+basics

13

Types of Dependencies

Page 14: Project+management+basics

Gantt ChartCritical Tasks

Non-Critical Tasks

14

Page 15: Project+management+basics

15

Network Diagram

Page 16: Project+management+basics

A1day

G6 days

I2 days

F4 days

C3 days

D4 days

B2 days

E5 days

H6 days

J3 days

Path Length

A-D-H-J 1+4+6+3 = 14 days

B-E-H-J 2+5+6+3 = 16 days

B-F-J 2+4+3 = 9 days

C-G-I 3+6+2+3 = 14 days

CRITICALPATH

16

Page 17: Project+management+basics

17

Critical Path Analysis (CPA)

Page 18: Project+management+basics

Example: Project Y

Task

Duration

Dependency

K 5 days

L 10 days

M 7 days K, L

K5 days

L10 days

M7 days

18

Page 19: Project+management+basics

K5 days

L10 days

M7 days

ES=0

ES=0

EF=5

EF=10

ES=10 EF=17

LF=17LS=10

LF=10

LF=10

LS=5

LS=0

19

Page 20: Project+management+basics

K5 days

0 5

105

Activity Total Slack

K 5 – 0 = 5

Total Slack is the amount of time that an activity can be delayed without delaying the project completion date

Total Slack = LS - ES

20

Page 21: Project+management+basics

K5 days

M7 days

0 5 10 17

1710105

Activity Free Slack

K 10 – 5 = 5

Free Slack is the amount of time that an activity can be delayed without delaying the next activity.

Free Slack = ESM - EFK

21

Page 22: Project+management+basics

Three Inter-related Concepts of Scheduling

22

Page 23: Project+management+basics

23

Day 1 Day 2 Day 3 Day 4

8 Hrs 8Hrs 8Hrs 8Hrs

Day 1

Day 2

Day 3

Day 4

Day 5

Day 6

2 Hrs 2 Hrs

4 Hrs 8Hrs 8 Hrs 8 Hrs

Day 1

Day 2

Day 3

Day 4

Day 5

Day 6

8 Hrs 8 Hrs

8 Hrs 4Hrs 2 Hrs 2 Hrs

Page 24: Project+management+basics

24

Page 25: Project+management+basics

Tracking Gantt Chart

100% complete

20% Complete

25

Page 26: Project+management+basics

Tracking Gantt Chart

Baseline(Initial Scheduleof task)

Actual Start Dateof Task

Scheduled Start Dateof Task is now delayed

26

AB

D

C

Page 27: Project+management+basics

27

Page 28: Project+management+basics

Task Y

Task Y

Planned Budget(BAC)

$10,000

Planned Time 10 days

10 Days

28

Illustrative Case

BAC: Budget at Completion

Page 29: Project+management+basics

Task Y

Progress at the end of 5 days

Actual Cost (AC) $6,000

% Work Completed

40%

5 Days

29

Illustrative Case

40%

Page 30: Project+management+basics

Task Y

5 Days

30

Illustrative Case

40%

Earned Value (EV)=

Planned Value (PV)=

000,4$000,10$100

40

000,5$000,10$10

5

Page 31: Project+management+basics

Progress at the end of 5 days

Actual Cost (AC) $6,000

Earned Value (EV)

$4,000

Planned Value (PV)

$5,000

31

Illustrative Case

$4,000Cost Performance Index (CPI)

$6,000

0.67

EV

AC

Cost Variance (CV) $4,000 $6,000

$2,000

EV AC

Page 32: Project+management+basics

Progress at the end of 5 days

Actual Cost (AC) $6,000

Earned Value (EV)

$4,000

Planned Value (PV)

$5,000

32

Illustrative Case

$4,000Scheduled Performance Index (SPI)

$5,000

0.80

EV

PV

Schedule Variance (SV) $4,000 $5,000

$1,000

EV PV