Project: WT Montgomery Road Phase I

23
PUBLIC WORKS DEPARTMENT Project: WT Montgomery Road Phase I Location / Limits: IH 90 West to Lucas Creek bridge. Scope: The main purpose of the project is to provide much needed drainage improvements and road reconstruction on WT Montgomery Road. Status: Complete Precinct: 1 Additional Information: Consultant: IDC, Inc. Advertise Date: June 26, 2015 Contractor: Curran Contracting Construction Start Date: 3 Q 2015 Construction Cost: $ 6,215,386.97 Construction End Date: 1 Q 2017 Joint Bid: SAWS

Transcript of Project: WT Montgomery Road Phase I

Page 1: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: WT Montgomery Road Phase I

Location / Limits:IH 90 West to Lucas Creekbridge.

Scope:The main purpose of the projectis to provide much neededdrainage improvements and roadreconstruction onWT Montgomery Road.

Status: Complete

Precinct: 1

Additional Information:Consultant: IDC, Inc. Advertise Date: June 26, 2015

Contractor: Curran Contracting Construction Start Date: 3 Q 2015

Construction Cost: $ 6,215,386.97 Construction End Date: 1 Q 2017

Joint Bid: SAWS

Page 2: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Talley Rd @ Culebra Rd Traffic Signal

Location / Limits:Talley Rd at Culebra Rd

Scope:The project contemplates thesignalization of the intersectionof Culebra Rd at Talley Rd.

Status: Complete

Precinct: 1

Additional Information:

Consultants:  Dannenbaum                         Bid Opening:   August 25, 2017  

Contractor:   EZ Bel                                       Construction Start:  January 9, 2018   

Construction Cost:  $ 173,809                     Construction End Date:  1 Q 2019

Page 3: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Alamo Ranch Parkway at Westwood Loop Traffic Signal

Location / Limits:Intersection of Alamo RanchPkwy and Westwood Loop.

Scope:Project for the construction of athru acceleration lane alongAlamo Ranch with an adjustedtraffic signal and supplementalsignage and stripping.

Status: Complete

Precinct: 1

Additional Information:

Consultants:  RPS                                                Bid Opening:   March 2, 2018  

Contractor:   EZ Bel       Construction Start:   3 Q 2018                        

Construction Cost:  $ 327,903                          Construction End Date:   1 Q  2019

Page 4: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: FM 1957 (Potranco Rd)

Location / Limits:Just west of SH 211 to Loop 1604

Scope:Construction will provide forenhanced connection betweentwo western relief routes of SH211 and Loop 1604. Theproposed improvements willexpand the existing two-lane ruralroadway section to an urbanroadway section consisting of two11-foot lanes, and two 14-footshared use lanes, continuous leftturn lane or 10-foot raised centermedian within an 80’ ROW(Minimum).

Status: Complete

Precinct: 1

Additional Information:Consultant: Pape-Dawson Advertise Date: November 20, 2015

Contractor: Texas Sterling Construction Construction Start Date: May 9, 2016

Construction Cost: $ 46,825,265 Construction End Date: July 19, 2019

Joint Bid: CPS , SAWS Pass Thru Project (TX DOT)

Page 5: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Marbach Rd & Bear Springs Traffic Signal

Location / Limits:Intersection of Marbach Rd &Bear Springs Dr

Scope:Signalize the intersection onMarbach Rd & Bear Springs Dr

Status: Complete

Precinct: 1

Additional Information:Consultants: Pape Dawson Engineers Bid Opening: July 20, 2018

Contractor: SAECO Construction Start: December 3, 2018

Construction Cost: $ 243,498 Construction End Date: June, 2019

Page 6: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Fischer Rd Phase I

Location / Limits:From Quintana Rd to IH 35 S

Scope:Project will expand the existingtwo-lane rural roadway section toan urban roadway section withreinforced concrete pavementconsisting of 16-foot travel lanesin each direction with 6 ft.shoulders with, curbs andsidewalks within an 86’ ROW(typical).

Status: Complete

Precinct: 1

Additional Information:Consultant: Garza EMC Advertise Date: June 7, 2019

Contractor: J3 Company Construction Start: October 28, 2019

Construction Cost: $ 2,108,824.38 Construction End Date: 3 Q 2020

Joint Bid: SAWS

Page 7: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: FM 471 (Culebra Rd)

Location / Limits:From Old FM 471 to FM 1560

Scope:The construction will completethe capacity gap that currentlyexists on FM 471 from FM1560 to Old FM 471. Theproposed improvements willwiden Culebra Road from itsexisting two-lane configurationto a four-lane divided roadwaywith anticipated bicycle andpedestrian amenities.

Status: Complete

Precinct: 1 & 2

Additional Information:Consultant : CP&Y Advertise Date: March 11, 2016

Contractor: Curran Contracting Construction Start Date: August 15, 2016

Construction Cost: $ 14,542,27324 Construction End Date: August 9, 2018

Joint Bid: SAWS, CPS Gas. Pass Thru Project (TX DOT)

Page 8: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Bridgewood Subdivision

Location / Limits:15 Various Streets inBridgewood Subdivision.

Scope:The main purpose of the projectis to reconstruct 15 residentialstreets in the BridgewoodSubdivision with curb & guttersection, 4-foot sidewalk includingADA compliant ramps anddriveway approaches.

Status: Complete

Precinct: 2

Additional Information:Consultant: LNV Bid opening Date: February 15, 2019

Contractor: Winters Construction, Inc. Construction Start Date: May 27, 2019

Construction Cost: $ 3,877,600 Construction End Date: 4 Q 2020

Joint Bid: SAWS

Page 9: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Bridgewood Subdivision

Location / Limits:15 Various Streets inBridgewood Subdivision.

Scope:The main purpose of theproject is to reconstruct 15residential streets in theBridgewood Subdivision withcurb & gutter section, 4-footsidewalk including ADAcompliant ramps and drivewayapproaches.

Status: Complete

Precinct: 2

Additional Information:Consultant: LNV Bid opening Date: February 15, 2019

Contractor: Winters Construction, Inc. Construction Start Date: June 2019

Construction Cost: $ 3,877,600 Construction End Date: 4 Q 2020

Joint Bid: SAWS

Page 10: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Shaenfield PlaceSubdivision

Location / Limits:Various streets withinShaenfield Place Subdivision.

Scope:The scope of this project is toprovide mill/overlay andreconstruction of multiple streets,update pedestrian ramps andnew sidewalks along missingareas within ShaenfieldSubdivision.

Status: Complete

Precinct: 2

Additional Information:Consultant: Gonzalez De la Garza Bid Opening: May 12, 2017

Contractor: Tropical Constructions Construction Start Date: 2 Q 2017

Construction Cost: $ 2,581,989 Construction End Date: 4 Q 2019

Joint Bid: SAWS

Page 11: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Steubing Rd

Location / Limits:FM 1560 to Shaenfield Rd.

Scope:This project will reconstruct theexisting two roadway rural lanesection to a mixed rural/urbanroadway section withcontinuously reinforced concretepavement, curb & sidewalks onthe west side of the roadway anddrainage improvements.

Status: Complete

Precinct: 2

Additional Information:Consultant: Gonzalez De La Garza Bid Opening: April 13, 2017

Contractor: EZ Bel Construction Start Date: 2 Q 2017

Construction Cost: $ 465,827 Construction End Date: 4 Q 2017

Page 12: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Pct 2 Pavement Restoration

Location / Limits:On Wildhorse Pkwy, Cavern Hill and the streets within Stanton Run Subdivision

Scope:Pavement Restoration(Mill & Overlay, Base ReplacementSubgrade Stabilization).

Status: Complete

Precinct: 2

Additional Information:Consultant: ATKINS Bid opening: August 7, 2019

Contractor: Alamo City Constructors Construction Start: Dec. 2019

Construction Cost: $ 2,697,138 Construction End: 2 Q 2020

Joint Bid: SAWS

Page 13: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Boerne Stage Rd @ Cross Mountain Traffic Signal

Location / Limits:Boerne Stage Rd at CrossMountain Trail.

Scope:The project contemplates thesignalization of the intersectionof Boerne Stage Rd at CrossMountain St.

Status: Complete

Precinct: 3

Additional Information:Consultants: Dannenbaum Bid Opening: July 14, 2017

Contractor: SAECO Construction Start: 1 Q 2018

Construction Cost: $ 125,763 Construction End Date: 2 Q 218

Page 14: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Bulverde Rd Traffic Signal

Location / Limits:Bulverde Rd & Bulverde Oaks

Scope:The project contemplates thesignalization of the intersectionof Bulverde Rd & BulverdeOaks.

Status: Complete

Precinct: 3

Additional Information:Consultants: Kimley Horn Bid Opening: September 4, 2018

Contractor: SAECO Construction Start: March 26. 2018

Construction Cost: $ 106,515 Construction End Date: Sep 4, 2018 2019

Page 15: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Borgfeld Dr Phase II

Location / Limits:From Timberline Dr to FM 2696(Blanco Rd) including OldBlanco Rd south of BorgfeldDrive.

Scope:The project consists of 2 miles ofroadway reconstruction to two-12ft. travel lanes in each directiondesignated turn lanes atintersections, two 4-footshoulders and necessarydrainage.

Status: Complete

Precinct: 3

Additional Information:Consultant: CDS Muery Services Advertise Date: January 6, 2017

Contractor: Texas Sterling Construction Start Date: March 20, 2017

Construction Cost: $ 10,309,219.44 Construction End Date: 3 Q 2019

Joint Bid: SAWS Water & CPS Gas

Page 16: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Borgfeld Dr Phase II

Location / Limits:From Timberline Dr to FM 2696(Blanco Rd) including OldBlanco Rd south of BorgfeldDrive.

Scope:The project consists of 2 miles ofroadway reconstruction to two-12ft. travel lanes in each directiondesignated turn lanes atintersections, two 4-footshoulders and necessarydrainage.

Status: Complete

Precinct: 3

Additional Information:Consultant: CDS Muery Services Advertise Date: January 6, 2017

Contractor: Texas Sterling Construction Start Date: March 20, 2017

Construction Cost: $ 9,056,127 Construction End Date: 3 Q 2019

Joint Bid: SAWS Water & CPS Gas

Page 17: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Candlewood Streets Phase I

Location / Limits:Candlebrook, Candlecreek,Candlewind, Candlestone,Candlebluff, Candlecrest,Candlecrown, Candleglade,Candleknoll, Woodglow,Candleridge, Candlerock,Candlefire, Candlewick,Candleview.

Scope:Project will reconstruct 15residential streets in Candlewoodsubdivision with curb & guttersection, 4-foot sidewalk includingADA complaint ramps anddriveway approaches.

Status: Complete

Precinct: 4

Additional Information:Consultant: LNV Engineering Bid Opening: August 22, 2014

Contractor: San Antonio Cons. Construction Start Date: Nov. 17, 2014

Construction Cost: $ 5,068,761 Construction End Date: September 9, 2018

Joint Bid: SAWS

Page 18: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Glen Mont Drive

Location / Limits:From Crestway Rd to OldWalzem Rd

Scope:Proposed improvements willrehabilitate the existing GlenMont Drive two lane urbanconfiguration by incorporatinga new pavement section, buspads, necessary drainage, andpedestrian amenities within a50’ ROW .

Status: Complete

Precinct: 4

Additional Information:Consultants: Halff & Assoc. Bid Opening: July 22, 2014

Contractor: Sterling Delaware Holding Inc. Construction Start Date: 4 Q 2014

Construction Cost: $ 12,332,423 Construction End Date: 1 Q 2017

Joint Bid: SAWS, SARA, CPS-Gas MPO Project

Page 19: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Palm Park Subdivision

Location / Limits:Ideal Ave, Parkett Drive, andPalm Park Blvd.

Scope:Construction to reestablish barditches and add pipe culvertsunder existing driveways andintersections.

Status: Complete

Precinct: 4

Additional Information:

Consultant: Young Professional           Bid Opening:   December 15, 2017   

Contractor:  EZ Bel    Construction Start Date: February  14, 2018

Construction Cost:  $  1,199,318        Construction End Date:   2 Q 2019

Joint Bid:   CPS‐Gas   

Page 20: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Candlewood Phase II

Location / Limits:On next streets: CandleheadLn, Cameron Spgs, AshleySpgs, Candlehill, Candletree,Candleglenn and Lyndell Spgs.

Scope:Project will be reconstruct 7streets (7,147 L.F.) in theCandlewood Subdivision withcurbs & gutter section, 4 footsidewalk including ADAcompliant ramps and drivewayapproaches.

Status: Complete

Precinct: 4

Additional Information:Consultant: Halff Bid opening: July 27, 2018

Contractor: EZ Bel Construction, LLC Construction Start Date: January , 2019

Construction Cost: $ 4,077,203.10 Construction End Date: 2 Q 2020

Joint Bid: SAWS

Page 21: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Binz-Engleman Rd Sidewalk and Traffic Signals

Location / Limits:From N Foster Rd to Woodlake Parkway.

Scope:Signalize the intersection onBinz-Engleman Rd and Woodlake Pky.

Status: Complete

Precinct: 4

Additional Information:Consultant: Dannenbaum Advertise Date: June 2, 2017

Contractor: The Levy Co Construction Start Date: October 2019

Construction Cost: $ 327,948 Construction End Date: January 2020

Joint Bid: N/A

Page 22: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Binz-Engleman Rd Sidewalk and Traffic Signals

Location / Limits:From N Foster Rd to Woodlake Parkway.

Scope:Signalize the intersection onBinz-Engleman Rd and Woodlake Pky.

Status: Complete

Precinct: 4

Additional Information:Consultant: Dannenbaum Advertise Date: June 2, 2017

Contractor: The Levy Co Construction Start Date: October 2019

Construction Cost: $ 327,948 Construction End Date: January 2020

Joint Bid: N/A

Page 23: Project: WT Montgomery Road Phase I

PUBLIC WORKS DEPARTMENT

Project: Pedestrian Crossing Improvements

Location / Limits:

County Wide, 25 locations.

Scope:

The project consists of 49different sites across BexarCounty that include additionalsignage, additional pavementmarking, 16 rectangular rapidflash beacons (RRFB), upgradedhandicap ramps, and pedestrianrefuge islands. .

Status: Complete

Precinct: CW

Additional Information:

Consultant:  Dannenbaum Bid opening: August 18, 2017 

Contractor:  EZ Bel Construction             Construction Start Date:   January , 2018

Construction Cost:  $ 1,573,692              Construction End Date:    2 Q 2019