Project Update - Ohio Department of Transportation Side...PROJECT TIMELINE 2014 May 2016 April Sign...

2
Call 740-833-8068 Email [email protected] Facebook ODOTColumbusDistrict6 Twitter @ODOT_Columbus How to sign up for project updates Visit www.270-23.com Click the orange RECEIVE TRAFFIC ALERTS button Enter your name and email address What kinds of things will I receive? Project updates Upcoming impacts to traffic Photos and videos I have questions. How do I contact ODOT? STAY INFORMED - it’s easy! Construction at I-270/US 23/SR 315 Project Update 2013 September Construction starts at I-270/US 23 Construction starts on Ohio’s first trench that will carry two NB express lanes of US 23 2015 July Construction begins at I-270/US 23/SR 315 August September A section of the Olentangy Trail at I-270/SR 315 closes Ohio’s first trench opens Construction of additional SB lane on US 23 begins November Olentangy Trail opens 2017 TBD 60 day ramp closures: I-270 west to SR 315 north and SR 315 south to I-270 east Fall Open new ramps: SR 315 south to I-270 east, I-270 east to US 23, and US 23 to SR 315 PROJECT TIMELINE 2014 May 2016 April

Transcript of Project Update - Ohio Department of Transportation Side...PROJECT TIMELINE 2014 May 2016 April Sign...

Page 1: Project Update - Ohio Department of Transportation Side...PROJECT TIMELINE 2014 May 2016 April Sign up for updates at Facebook: ODOT Columbus District 6 Twitter/Instagram: @ODOT_Columbus

2013

Call 740-833-8068

Email [email protected]

Facebook ODOTColumbusDistrict6

Twitter @ODOT_Columbus

How to sign up for project updates• Visit www.270-23.com• Click the orange RECEIVE TRAFFIC ALERTS button• Enter your name and email address

What kinds of things will I receive? • Project updates• Upcoming impacts to traffic• Photos and videos

I have questions. How do I contact ODOT?

STAY INFORMED - it’s easy!

Construction at I-270/US 23/SR 315

Project Update

2013September Construction starts at I-270/US 23

Construction starts on Ohio’s first trench that will carry two NB express lanes of US 23

2015July Construction begins

at I-270/US 23/SR 315

August

September

A section of the Olentangy Trail at I-270/SR 315 closes

Ohio’s first trench opens

Construction of additional SB lane on US 23 begins

November Olentangy Trail opens

2017TBD 60 day ramp closures: I-270

west to SR 315 north and SR 315 south to I-270 east

Fall Open new ramps: SR 315 south to I-270 east, I-270 east to US 23, and US 23 to SR 315

PROJECT TIMELINE

2014May

2016April

Page 2: Project Update - Ohio Department of Transportation Side...PROJECT TIMELINE 2014 May 2016 April Sign up for updates at Facebook: ODOT Columbus District 6 Twitter/Instagram: @ODOT_Columbus

Sign up for updates at www.270-23.com

Facebook: ODOT Columbus District 6

Twitter/Instagram: @ODOT_Columbus