Project Factsheet – Kwun Tong Line Extension Contract 1002, Whampoa Station and Overrun Tunnel Page 1 of 2 Kwun Tong Line Extension Contract 1002, Whampoa Station and Overrun Tunnel Project: Kwun Tong Line Extension Contract 1002, Whampoa Station and Overrun Tunnel Original Contract Sum: HK$856 million Contract Start Date: May 2011 Contract Completion Date: May 2015 Client: MTR Corporation Limited

Transcript of Project Factsheet Tong Line...Kwun Tong Line Extension Contract 1002, Whampoa Station and Overrun...

  • Project Factsheet – Kwun Tong Line Extension Contract 1002, Whampoa Station and Overrun Tunnel

    Page 1 of 2 Kwun Tong Line Extension Contract 1002, Whampoa Station and Overrun Tunnel

    Project: Kwun Tong Line Extension Contract 1002, Whampoa Station and Overrun Tunnel

    Original Contract Sum: HK$856 million

    Contract Start Date: May 2011

    Contract Completion Date: May 2015

    Client: MTR Corporation Limited

  • Project Factsheet – Kwun Tong Line Extension Contract 1002, Whampoa Station and Overrun Tunnel

    Page 2 of 2 Kwun Tong Line Extension Contract 1002, Whampoa Station and Overrun Tunnel

    Description:

    Construction of new station, platform and overrun tunnels and associated vent shaft.