    Schedule for Final Year Project Semester 1CE00901-3 Project: Research and Planning

    DATE (WeekBeginning)

    EVENT Student Activity Reference

    1/8/13 Session 1: ProjectCommencement

    Prepare Project File Read description and requirements of project specialism.

    Commence research on suitable topic for project.

    Discuss with lecturer and/or R&D staff to obtain inputs on specific topic

    and/or research interest.

    Project

    Handbook

    1/8/13 Session 2: Idea Generation

    7/8/13Draft Proposal Hard CopySubmission

    Complete Draft Proposal (subject to further revision)

    12/8/13-16/8/13Session 3: Preparing ProjectProposal

    Finalise research topic

    Note of your supervisors name, email and phone extension

    Notice board at

    Level 323/8/13

    Publication of FYP supervisorlist

    26/8/13-30/8/13 Supervisor Clinic Emphasise on a clear problem statement and objectives and refrain from

    indulging on functionalities of system at this stage

    Finalise PPF

    PAGOL

    6/9/13 PPF final online submission

    3/9/13-6/9/13Session 4: Specification

    Writing

    Read thoroughly components of PSF

    Proceed with academic, secondary and primary research

    11/9/13PPF online approval by

    Supervisor

    Arrange meeting with supervisor for mandatory

    supervisory meeting 1

    PAGOL

    9/9/13-13/9/13Session 5: Research &Ethics

    Submit ethics form (signed by supervisor)

    Maintain a separate document to list extracts taken from sources together

    with complete reference using Harvard referencing

    9/9/13-13/9/13

    Session 6: PreparingResearch Design

  • 7/27/2019 Project Timelines

    2/3

    9/9/13-13/9/13Mandatory Supervisory

    Meeting - 1

    Meet supervisor having booked an appointment

    via consultation hour.

    Submission ofEthics Form after obtaining supervisors signature.

    Bring along project file & project log sheet

    Continue with academic, secondary and primary research

    Log Sheet

    20/9/13 PSF Online Submission Continue with academic, secondary and primary research PAGOL

    27/9/13 PSF Online Approval Supervisor/Advisor

    Continue with academic, secondary and primary research PAGOL

    23/9/13-27/9/13Session 7: Data GatheringMethods

    Finalise appropriate data gathering methods based on research topic,

    research design and project proposal

    Prepare to show supervisor: research topic, project proposal and

    research design

    Meet lecturer if extensive corrections were made during supervisor clinic

    before submitting PPF online

    23/9/13-27/9/13 Session 8: Data Analysis Continue with academic, secondary and primary research

    7/10/13-11/10/13Session 9: DocumentationPreparation

    Create contents page of documentation

    Arrange meeting with supervisor for mandatory supervisory meeting 2

    14/10/13-18/10/13Session 10: PlagiarismAvoidance

    14/10/13-18/10/13Mandatory SupervisoryMeeting - 2

    Finalise documentation of academic, secondary and primary research

    with citation and references attached show and discuss it with yoursupervisor for approval

    Meet supervisor having booked an appointment via consultation hour.

    Bring along project file & project log sheet

    Log Sheet

    21/10/13-25/10/13Session 11: How to do yourFYP presentation

    Compile findings of academic, secondary and primary research

    09/11/13 onwards Viva*

    Rehearse for presentation

    Thoroughly scrutinize documentation

  • 7/27/2019 Project Timelines

    3/3

    Schedule for Final Year Project Semester 2CE00902-3 Project: Analysis and Design | CE00903-3 Implementation, Testing & Evaluation

    WeekBeginning

    ACTIVITY Student Activity Reference

    21/1/14-30/1/14

    Mandatory Supervisory Meeting - 3

    Meet supervisor having booked an appointment via consultation hour.

    Bring along project file & project log sheet Arrange meeting with supervisor for mandatory supervisory meeting

    4

    Log Sheet

    11/2/14-20/2/14

    Mandatory Supervisory Meeting - 4

    Meet supervisor having booked an appointment via consultation hour.

    Bring along project file & project log sheet

    Arrange meeting with supervisor for mandatory supervisory meeting

    5

    Log Sheet

    3/3/14-7/3/14

    Mandatory Supervisory Meeting - 5

    Meet supervisor having booked an appointment via consultation hour.

    Bring along project file & project log sheet

    Show supervisor progress of final system and documentation

    Discuss with supervisor revised contents page of documentation.

    Log Sheet

    10/3/14-14/3/14

    Submission Briefing

    Arrange meeting with supervisor for mandatory supervisory meeting

    6

    17/3/14-21/3/14

    Mandatory Supervisory Meeting - 6

    Meet supervisor having booked an appointment via consultation hour.

    Bring along project file & project log sheet

    Show supervisor final system and documentation Log Sheet

    28/3/14Report Submission( CD)

    Review submission guidelines

    31/3/14-7/4/14

    Supervisor View/MarksDocumentation

    Prepare for final presentation

    17/4/14Report Submission (Combbound &Hardbound)

    Print and bind project (hard cover binding and soft bound) including CD

    18/4/14-22/4/14

    Advisor Views/Marks Documentation Prepare for final presentation

    23/4/14onwards

    FYP Presentation** Rehearse for presentation

    Thoroughly scrutinize documentation and system