PROJECT STATUS UPDATE JUNE 16, 2015
Transcript of PROJECT STATUS UPDATE JUNE 16, 2015 - Blair Hills NATURE CENTER BLAIR...ORGANIZATIONAL THEMATIC...
PROJECT STATUS UPDATE
JUNE 16, 2015
• PRESENTATION: MATTHEW FELDHAUS,LA COUNTY DEPARTMENT OF PUBLICWORKS
• CITY OF CULVER CITY: CHARLESHERBERTSON, DIRECTOR OF PUBLICWORKS
• BLAIR HILLS HOA AND COMMUNITY
• MITIGATED NEGATIVE DECLARATIONCOMPLETE AND BEING IMPLEMENTED
• DESIGN-BUILDER SELECTION COMPLETE
• DEMOLITION AND SITE CLEARANCECOMPLETE
• 90% CONSTRUCTION DOCUMENTSCOMPLETED JUNE 15, 2015
• AUGUST 2015: PLAN CHECK/PERMITCOMPLETE
• SEPTEMBER 2015: MOBILIZATION ANDCONSTRUCTION START
• APRIL 2016: SUBSTANTIAL COMPLETION
• JULY 2016: NATURE CENTER OPEN TOTHE PUBLIC