Project Status The project is progressing well with both grading aspects and building components....

8

Transcript of Project Status The project is progressing well with both grading aspects and building components....

Page 1: Project Status The project is progressing well with both grading aspects and building components. The mason has erected many walls to “scaffold high”
Page 2: Project Status The project is progressing well with both grading aspects and building components. The mason has erected many walls to “scaffold high”

Project Status• The project is progressing well with both grading aspects

and building components. • The mason has erected many walls to “scaffold high”

and starting to take the walls in Gym/Cafeteria wing to bearing height.

• The steel frame in 2-3 wing is 98% complete and began on the K-1 wing on 10/4/10.

• Part of Gym/Cafeteria wing steel frame has been started. • Slab On Grade in 4-5 wing has been poured and the

mason has the interior walls up to scaffold height. • The plumber has finished the underground rough-in in K-

1 wing and 2-3 wing; the kitchen is the next area for installation.

• The electrician has continued with rough-in.• Project is 26% completed.

Page 3: Project Status The project is progressing well with both grading aspects and building components. The mason has erected many walls to “scaffold high”

Aerial Photo taken from Northern Elevation---Picture taken on 9/13/10

Gym

Cafeteria

4-5 wing2-3 wing

K-1 wing

Page 4: Project Status The project is progressing well with both grading aspects and building components. The mason has erected many walls to “scaffold high”

K-1 Wing Masonry in Fore Ground; 2-3 Wing Steel Frame on Right

Page 5: Project Status The project is progressing well with both grading aspects and building components. The mason has erected many walls to “scaffold high”

Picture taken from Church Parking Lot viewing 2-3 wing Steel Frame

Page 6: Project Status The project is progressing well with both grading aspects and building components. The mason has erected many walls to “scaffold high”

Slab on Grade poured in 4-5 wing. Steel for 2-3 wing.

Page 7: Project Status The project is progressing well with both grading aspects and building components. The mason has erected many walls to “scaffold high”

Givens Street Extension Completed prior to Children returning to School on 8/25/10

Page 8: Project Status The project is progressing well with both grading aspects and building components. The mason has erected many walls to “scaffold high”

Project in relation to the existing school; Picture taken from North Elevation