Project Status for the James Webb Space Telescope Partner’s Workshop
Phil SabelhausJWST Program Manager
May 19, 2009
JWST-PRES-012897
Organization Mission Lead: Goddard Space Flight Center International collaboration with ESA & CSA Prime Contractor: Northrop Grumman Space Technology Instruments:
― Near Infrared Camera (NIRCam) – Univ. of Arizona― Near Infrared Spectrograph (NIRSpec) – ESA― Mid-Infrared Instrument (MIRI) – JPL/ESA― Fine Guidance Sensor (FGS) – CSA
Operations: Space Telescope Science Institute
Description
Deployable infrared telescope with 6.5 meter diameter segmented adjustable primary mirror
Cryogenic temperature telescope and instruments for infrared performance
Launch June 2014 on an ESA-supplied Ariane 5 rocket to Sun-Earth L2
5-year science mission (10-year goal)
James Webb Space Telescope (JWST)
www.JWST.nasa.gov
JWST Science Themes
End of the dark ages: First light and reionization
The assembly of galaxies
Birth of stars and proto-planetary systems
Planetary systems and the origin of life
Optical Telescope Element (OTE)
Integrated Science Instrument Module (ISIM)
Sunshield
Spacecraft Bus
Warm Sun-facing Side
Cold Space-facing Side
Optical Telescope Element (OTE)
Integrated Science Instrument Module (ISIM)
Sunshield
Spacecraft Bus
Warm Sun-facing Side
Cold Space-facing Side
3
2006 2007 2008 2009 2010 2011 2012 2013 2014
FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JWST Master Schedule
Major Mission Milestones
Integration & Test
OTE
JSC Activity
SSDIF Activity
Pathfinder Structure (PF) Flight Structure (PMBSS)
Pr imary Mirrors (PMSA)
Flight Sunshield
Spacecraft (SC)
SC & IES Simulators
Observatory FSW/EMTB
Build 1 & 2/V&V
ISIM
Integration & Test
NIRSpec
MIRI
NIRCam
FGS
Cooling System
Ground Segment
1
SDR
1
T-NAR
3
PDR/NAR
6
KDP-II
12
CDR
9
SIR
12
KDP-III
12
MOR
6
TRR
2
PSR
5
FRR/KDP-IV
6
LRD
12
ORR
11
Design & Drawings for 1/3 Scale Sunshield Test
9
IDR
12
Fab
2
Integ
3
TRR
5
Test
TRR
6
Depreps 8
Test
9
Depreps
7
SC Panel Integ
9
SCE In teg
11 12
Subsys Deploy
1
Vib
2
TV
4
SubsysDeploy
6 6
CST 2/ EMC
8
Acoustic, Vib ,
Shock
10
Deploy/ CST 3
2 2
Ship Prep
5 6
Launch Prep
11
OTE PDR
10
OTE CDR
9
OTIS TRR
2
ACFRA
1
ITT GSESRR
4
GSEPDA
3
GSECDA
11
JSC InstallReady GSE
1
Bakeout
2
Install PAF w/o AOS
3 4
GSE Comm
6
InstallPAF w/AOS
7 8
PFCryoTest
1 2
Ambient
6
OTE/F lt ISIM Cryo
12
OAS RA
1
GSESRR
4
GSEPDA
3
GSECDA
5
SESReady
SSDIF Ready
5
GSE Installation
12
PF OpticsInteg
3
F lt Optics In teg
7
F inal Mir ro r
F lt ISIMInteg
10 11 1
Acous, Vibe CoCi Test
3
Start PF Struct. PF Structure Design/Fab /Assy
8
CDA 12
PF Stru tsPF PMBSS
5
Cry Cyc TRR 7
PF SMSS
8
9
11
Test 11
PF Str Integ
2
Assy
3
MMS ISIM Test Cpt.
6
TRL 6 Vib ro -Acoustic
7
Delta-2CDA
12
Start FltCryo Test #1
6
Start F lt Cryo Test #2
12
PF PMSA
3
#1
4
#2
5
#3,
6
#4#5 #6 (Last PM Batch )
7
4
1
SRS Membrane Development
12
Sheldahl Pilot Production
1
SRS PDR
NGST Membrane Qual Testing
12
F lt Membrane Mat'l Fab Cpt
1
TV Membrane Del
5
SRS CDR 12
Qual Test Cpt
1 6
F lt Membrane Fab
1
Preliminary Design
Evolu tionary Path finder (EPF) Development & Testing
12
Structure T IM
2
PDR 3 4
IVA Design
12
2
MMS PDA 4
Fab
6
Shell MRR 7
Integ & Test
9
SSCDR
11
Tooling MFG & Un it Testing
4
Integ & Test
9
Sh ip to I&T
12
StructurePDA 7
PDR
12
Prem Structure CDA 2
Structure CDA
8
CDR
12
Test
3
SC Structure Del
3
Prop I&T
9
Sh ip Propulsion System to I&T
10
ISIM SDL
1
ISIM SDL &ICDH Lab
3
ETU ISIM I&T(Type 1A)
5
10
IESSDL
6
IES EMTB
7
F lt ISIM (Type 2A)
11
IES OTB
2
Bld 1 PDR
6
Bld 1 CDR/ Bld 2 PDR
3
Bld 1 TRR
3
Bld 2 CDR
1
Bld 2 TRR
5
FSW Del to SC
12
FSW Del to Obs
2
B 1.1
6
B 1.2
4
B 1.3
9
B 1 Update
10
B1 Verif
1
B 2 Verif 3
B 1 Val Cpt
5
B 2.1 Verif 11
B 2.1 Val Cpt
11
B 2.2 Verif 5
B 2.2 Val Cpt
7
Obs Ver if 10
Obs Val
10
ISIM PDR
3
ISIM CDR
4
Rec Structure (from ATK)
6
Structure Acceptance Testing
3
Start I&T
5
OSIM
10
PER
10
Del F lt ISIMto OTE
11
10
CDR
7
ETU Del
7
F lt Del
12
CDR
8
STM Del
6
F lt Del
5
CDR
8
ETU Del
9
F lt Del
3
Guider CDR
3
TFI/Systems CDR
10
ETU Del
6
F lt Del
10
SRR
2
PDR
4
CDR
6
6
EM CHARegion 1
9
EM CTA
1
CCES/CELS
3
F ltCTA
4
F ltCHA
5
CCAMock-up
12
F lt CCA/CCE
3
F ltCCA/CCE
(spare)
12
CCTS B 1.2
4
CCTS B 2.0
9
CCTS B2.1
5
CCTS B2.2
4
CCTS B2.3
4
S&OC PDR
10
CCTS B 2.4
7
S&OC Rel 0.0
10
S&OC CDR
12
S&OC Rel 1.0
12
OTB Del
7
S&OC Rel 2.0
1
S&OC Rel 2.x
12
Start "on call" Support
Rev. G Inc ludes NGAS Master Sc hedule - December 2008 Baseline& ISIM Master Sc hedule - Rev. G
Sunshield (SS)
Evolutionary Pathfinder (EPF)
Mate OTE/F lt ISIM
Membranes
3
CST 1,Modal
Mgm'tReserve
Cryo Pr f Load
SC Bus Fab & Assembly
Cryo Cycle BP Cpt
JWST Overview ScheduleJWST Overview Schedule Needs to be updated for the June 2014 LRDNeeds to be updated for the June 2014 LRD
JWST_ISIM.May.QSR/3
4
Associate DirectorP. Sabelhaus
Deputy Associate DirectorJ. Decker
Deputy Associate Director / TechnicalJ. Durning
Business ManagerR. King
Deputy Business ManagerC. Steeley
Senior Project ScientistJ. Mather (665)
Deputy Sr Project ScientistJ. Gardner (665)
Chief Safety and Mission Assurance Officer (CSO)J. Radich (324)
Mission Systems EngineerM. Menzel (599)
Deputy Mission Sys EngM. Davis (Ball)
ISIM ManagerJ. Dunn
Deputy ISIM MgrM. Voyton
ISIM Financial MgrC. Doria-Warner
Ground Segment & Ops Manager
A. Johns
Observatory ManagerP. Geithner
Deputy Obs MgrK. Parrish (545)
ISIM Systems EngineerR. Lundquist (599)
ISIM Structure MgrE. Johnson (543)
ISIM I&T ManagerM. Drury (Sigma)
Instrument Systems Manager
S. Lambros
MIRI Instr MgrP. Driggers (SGT)
NIRSpec Instr MgrT. Johnson (556)
NIRCam Instr MgrD. Yun
FGS Instr MgrS. Lambros
J. Abell (SGT) - FGS ISE
ISIM FSW MgrB. Savadkin (582)
Science Operations Manager
B. Seaton (581)
Mission Engineering Manager
J. Gal-Edd (581)
OTE ManagerL. Feinberg (550)
Deputy OTE ManagerR. Keski-Kuha (551)
L. Markley (591) – ACSP. Maghami (OSC) – GNCC. Schiff (595) – Flt DynK. Mehalick (551) – Opt SysR. Sengupta (Sigma) – Risk CoordA. Sherman (SGT) – Chair, ERBC. Perrygo (SGT) – SunshieldM. Bussman (SGT) – Rqmts R. Ivancic (SGT) – S/C SysD. Muheim (592) – Integ Modeling
M. Greenhouse (665) - ISIM Scientist M. Clampin (667) – Observatory ScientistG. Sonneborn (665) – Operations ScientistC. Bowers (667) – Deputy Observatory ScientistB. Rauscher (665) - Deputy ISIM Scientist
P. Gibbons (321) – Project Safety MgJ. Radich (Acting) (324) – ISIM CSO
W. Hayden (592) – OTE SEJ. Howard (551) – Opt. Design LeadB. Dean (551) – OTE WFSC LeadL. Cohen (SAO) – Mech Sys LeadK. Thakore (544) – Electromech Lead
M. Smith (556) – NIRSpec ISER. Estep (556) – Microshutter SS Mgr
S. Manthripragada (556) – Detector SS Mgr
C. Aymergen (SGT) – MIRI ISE
R. Ohl (Acting) (551) – Optical LeadP. Davila (551) – Optical SysJ. McCloskey (565) – Elec SysS. Glazer (545) – Thermal SysR. Carter (SGT) – Mech SysJ. Johnston (542) – Str Sys & Int ModR. Ladbury (561) - RadiationS. Le (Ball) – MaterialsR. Perry (SGT) – Contam E. Greville (SGT) - FSW Sys R. Sharma (544) – Electromech SysS. Allen (565) – HarnessD. Ramey (SGT) – Ops Lead K. Barnes (581) - FSW Sys
IGSS Development Manager
J. Steck (583)
R. O’Mara – Financial MgrC. McKenzie (210.S) – Procurement MgrJ. King (210.S) – Contracting OfficerD. Miller – Project Support MgrL. Chandler (130) – Public Affairs
ICDH Hardware MgrQ. Nguyen (561)
Obs ScientistM. Clampin (667)
Deputy Obs Scientist C. Bowers (667)
OperationsScientist
G. Sonneborn (665)
ISIM ScientistM. Greenhouse (665)Deputy ISIM Scientist
B. Rauscher (665)
C. Adams (584) – FOS MgrB. Bruce (441) – PRD MgrR. Detter (594) FITSWriter MgrP. Johnson (583) – PPS MgrD. Matusow (581) – OSS Mgr
A. Bigel (583) – Dev/Test EngT. Pfarr (CSC) – IGSS Integ. Mgr
E. Woodward (583) - IGSS I&T Mgr.
J. Van Campen (SGT) –NIRCam ISE
R. Lynch (599) – Sys MgrR. Sabatino (581) – F&G SW SysG. Mosier (592) – Integ Modeling(Acting) K. Parrish (545) – Therm SysJ. Lawrence (543) – Mech SysG. Golnik (Schafer) – Opt SysS. Irish (542) – Structures(Acting) R. Meloy (Muniz) – Elec SysB. Jeffers (QSS) – PartsS. Le (Ball) – Materials E. Wooldridge (546) – Contam
Ground Segment I&T Manager
C. Fatig (SAIC)
G. Henegar (564) IRSU Mgr
R. Rashford (GEC) – IEC Mgr
James Webb Space Telescope (JWST) Project – Code 443
OSIM MgrT. Pham (556)
K. Banks (552) – Obs Cryocooler SE
ISIM CSOJ. Radich (Acting) (324)R. Lynch (599) – JSC Sys Eng
J. Allen (DSC) – S/C Electrical
Signature:
Observatory Sys EngM. Davis (Ball)
Observatory I&T MgrC. Diaz (Sigma)
Launch Vehicle LiaisonJ. Lawrence (543)
Sunshield ManagerK. Parrish (545)
Spacecraft ManagerR. Ivancic (SGT)
Software ManagerR. Sabatino (581)
Cryocooler ManagerM. Larson (JPL)
JWST-REF-000838Revision Y
Original signed by John E. Decker3/20/2009
JWST_ISIM.May.MPR/4
5
Personnel Changes since last WorkshopPersonnel Changes since last Workshop
Personnel update:– Richard Lynch has rejoined the team as the JSC Systems Engineer– Robby Estep has taken over as the MSS Manager– Ray Ohl is the ISIM optical lead– Hal Bremmer is the project’s scheduling lead– Claudia Krogel has joined the Mission Systems Team– Lisa Link is the point of contact in the CM Office
6
General: All observatory components, except for the spacecraft, have successfully completed their
preliminary design reviews ISIM CDR held in March
All science instruments have successfully completed their critical design reviews LRD moving to June 2014; Mission CDR moving to March 2010
Will have 7 months of critical path slack; so the ship date only slipped by 8 months Maintain ISIM deliveries Maintain near term OTE, Sunshield and Spacecraft milestones
Not sure about plans for the next Partner’s Workshop with the upcoming major reviews Observatory:
Lower level Spacecraft PDR’s underway JWST full scale core test is underway Completed the Sunshield Membrane Management System (MMS) delta PDR First spacecraft simulator delivered to the ISIM software lab at GSFC
Ground System: The Ka band upgrades required to support JWST L&EO and normal operations have been
completed at the DSN Canberra and Goldstone Sites NGAS hosted an open house to mark the grand opening of the “Webb Telescope Control Room” in
M8. The control room will be operated using CCTS hardware and software
Project StatusProject Status
7
Full Scale Core Test HardwareFull Scale Core Test HardwareCore Thermal Test
Focus AreaOptical Telescope Element
Sun ShieldSpacecraft Bus
Decagon Test Membrane
SS Support Frame
Top Weldment
Base Weldment
Bus Simulator
IEC
PTR Radiators
Lift Sling
Backplane Support Frame (BSF)
Membrane Tensioning System
Center Backplane
Stray Light Bib
Diagonal Shields
Deep Space Edge Radiator (DSER) Panels
Cable Radiator
Counterbalance Weights
FLIGHT Observatory
CORE TEST thermal facsimile
8
Core Test Article Integration Complete and Core Test Article Integration Complete and Testing is UnderwayTesting is Underway
Core Test integration complete– OTE/SC assemblies mated– GSFC radiometers received and installed– He shroud installed, leak checks completed– MLI closeouts complete– Instrumentation installation and checkout complete– Cool down started on April 17th
Core Test Article
Installation on Chamber Lid
He Shroud Installation
9
Observatory I&T control room at NGST
10
Telescope: ATK Operations:
Bonding of flight and pathfinder OTE Primary Mirror Backplane Support Structure (PMBSS) continues
Tinsley operations are continuing: Five PM segments have been shipped to Ball Secondary Mirror has been delivered to Ball TM1 (Tertiary Mirror 1) delivered to Ball The remaining flight primary, secondary and tertiary mirrors are in various stages of rough
polishing and smooth out grinding
Ball operations: Four Primary Mirror Segment Assembly (PMSA) have been built up to configuration 3 (the full
PMSA configuration) Received, inspected and cleaned Tertiary Mirror at Ball Received last 4 flight Delta Frames from Axsys; JWST work at Axsys is complete!
MSFC XRCF Operations: The A1 and EDU PMSA’s cryo vac test has been completed
Project Status (Continued)
11
Optical Telescope Element (OTE) Hardware ProgressOptical Telescope Element (OTE) Hardware Progress
Flight Center Section bonding with Pathfinder CS in foreground
Fine Steering Mirror
Mirrors in XRCF ChamberMirrors in XRCF Chamber
Tertiary Mirror
SMA Hexapod complete
Secondary MirrorSecondary Mirror
12
Integrated Science Instrument Module (ISIM)– Successfully completed ISIM Level CDR in March– Good progress on other ISIM components, ISIM Command and Data Handling (IC&DH) unit,
ISIM Remote Services Unit (IRSU), structure, etc Instruments:
– MIRI- MIRI Verification Model (VM) completed it’s second cryo test- Selected flight and spare detectors and built into Focal Plane Module’s (FPM’s)- Instrument shield (for cryo cooler) concept review held last week
– NIRSpec- Selection of flight detectors agreed to by NASA & ESA- Instrument CDR successfully held- Development Model (DM) cryo testing underway- Flight Model (FM) integration underway
– NIRCam- Selected flight detectors for NIRCam- Completed bonding and vibration testing of the NIRCam Engineering Test Unit (ETU)
Optical Bench– FGS
- 3 of 4 FGS flight detectors (including the spare) have been selected- Completed first ETU cryo pupil illumination test- All ETU hardware installed on optical bench or in formal testing
Program Status and Recent Progress (Continued)
1313
JWST Instrument Engineering, Verification and Development Models
FGS Engineering Model MIRI Verification Model
NIRSpec Development ModelNIRCam ETU OBA with Mass Simulators
14
ISIM Hardware
PDU ETU Side A and Side B
ISIM Structure Bonding
OSIM Primary Mirror
IC&DH ETU
15
SES Shroud in Bldg 10 for ISIM Testing
1616
Remaining Major 2009 events: ISIM flight structure delivery to the GSFC from ATK in August MIRI flight Focal Plane system delivery to RAL in August (TBR) Sunshield 1/3 Scale Test Readiness Review (TRR) in August at NGAS Spacecraft Bus PDR, July 28-30 at NGAS Cryo Cooler CDR in June at NGAS Flight NIRSpec Micro Shutter system delivery to ESA in September Modified Pathfinder NIRSpec Detector system delivery to ESA July Optical Telescope Element CDR scheduled for October at NGAS Sun Shield CDR scheduled for November at NGAS
Mission Critical Design Review in March 2010 at the GSFC
Project Status (continued)Project Status (continued)
17
Cost increases Late ISIM deliveries Low cost reserves Problematic use of the Space Cargo Transporter System (SCTS)
– The project has included costs for a JWST unique shipping container in this year’s budget– Working with NGAS and Arianespace on requirements
NIRCam Wave Front Error– Proceeding with the redesigned bonded lens mount design
- Review held on May 14th
– Developed a new alignment plan, which allows for greater accuracy both during build up and at the module level Meeting Cryo Cooler allocations with required margins
– Baselined MIRI shield– Concept review held last week
Microshutter shock survivability– Qualification unit over tested and failed– Established new testing approach and levels– Testing currently underway at Astrium
Rebuilt ASIC cost and schedule– New ASIC’s will be ready in the November 2009 to March 2010 timeframe
MIRI FPE noise issues Primary Mirror A1 actuator gear motor failure