Project Risk Management

46
Chapter 9: Project Risk Management Stevbros Training & Consultancy www.stevbros.edu.vn Copyright@STEVBROS Project Mamagement Fundamentals 1 PMI, PMP and PMBOK are registered marks of the Project Management Ins9tute, Inc.

Transcript of Project Risk Management

Page 1: Project Risk Management

Chapter  9:    Project  Risk  Management  

Stevbros  Training  &  Consultancy  www.stevbros.edu.vn  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   1  

PMI,  PMP  and  PMBOK  are  registered  marks  of  the  Project  Management  Ins9tute,  Inc.  

Page 2: Project Risk Management

Overview  

    Ini%a%ng  process  group  

Planning  process  group   Execu%ng  process  group  

Monitoring  &  controlling  process  group  

Closing  process  group  

Project  risk  management  

    •  Plan  Risk  Management  

•  IdenJfy  Risks  •  Perform  QualitaJve  

Risk  Analysis  •  Perform  QuanJtaJve  

Risk  Analysis  •  Plan  Risk  Responses  

    •  Control  Risks  

   

Copyright@STEVBROS   Project  Mamagement  Fundamentals   2  

Page 3: Project Risk Management

What  is  Risk?  

•  Risk  is  an  uncertain  event  or  condiJon  that,  if  it  occurs,  has  a  posiJve  or  negaJve  effect  on  a  project’s  objecJves  

•  Example  of  posiJve  events  –  You  ordered  new  soVware  which  is  cheaper  than  your  old  soVware  because  of  budget  constraints.  However,  the  new  soVware  turns  out  to  be  more  efficient.  

•  Example  of  negaJve  events  –  The  government  mandates  a  compulsory  holiday  due  to  an  outbreak  of  swine  flu.  The  project  gets  delayed  

Copyright@STEVBROS   STEVBROS  -­‐  Global  PMI  R.E.P   3  

Page 4: Project Risk Management

Concepts  •  Risk  appe9te,  which  is  the  degree  of  uncertainty  an  enJty  is  willing  to  take  on,  in  anJcipaJon  of  a  reward.  

•  Risk  averse,  one  who  does  not  take  risks.  •   Risk  tolerance,  which  is  the  degree,  amount,  or  volume  of  risk  that  an  organizaJon  or  individual  will  withstand.    

•  Risk  threshold,  which  refers  to  measures  along  the  level  of  uncertainty  or  the  level  of  impact  at  which  a  stakeholder  may  have  a  specific  interest.  Below  that  risk  threshold,  the  organizaJon  will  accept  the  risk.  Above  that  risk  threshold,  the  organizaJon  will  not  tolerate  the  risk.    Copyright@STEVBROS   STEVBROS  -­‐  Global  PMI  R.E.P   4  

Page 5: Project Risk Management

Risk  categorizaJon    examples  

•  Example  1:    –  External:  regulatory,  governmental,  subcontractors,  suppliers,  and  

environmental    –  Internal:  funding,  resource,  and  prioriJzaJon  –  Technical:  requirements,  technology,  and  quality  –  Project  Management:  esJmaJng,  planning,  schedule,  and  communicaJon  

•  Example  2:  –  Schedule  risk:?  –  Cost  Risk?  –  Quality  Risk?  –  Scope  Risk:  Looks  like  you  have  not  understood  the  work  properly  and  you  

might  have  to  redo  the  whole  thing!    –  Resource  Risk:  CEO  has  asked  the  technical  architect  to  work  on  another  

project.  In  such  cases,  who  would  make  design  decisions  on  the  projects?  

Copyright@STEVBROS   STEVBROS  -­‐  Global  PMI  R.E.P   5  

Page 6: Project Risk Management

Plan  risk    management  

•  The   process   of   defining   how   to   conduct   risk   management  acJviJes   for   a   project.   The   key   benefit   of   this   process   is   it  ensures   that   the   degree,   type,   and   visibility   of   risk  management  are  commensurate  with  both   the  risks  and  the  importance  of  the  project  to  the  organizaJon.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   6  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiEh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  11-­‐2  Page  313.  

Page 7: Project Risk Management

Inputs  1.  Project  Management  Plan    

–  all   approved   subsidiary   management   plans   and   baselines   should   be  taken   into  consideraJon   in  order   to  make  the  risk  management  plan  consistent  with  them  

2.  Project  Charter    –  can  provide   various   inputs   such  as  high-­‐level   risks,   high-­‐level   project  

descripJons,  and  high-­‐level  requirements.    3.  Stakeholder  Register    4.  Enterprise  Environmental  Factors    

–  contain   risk   aetudes,   thresholds,   and   tolerances   that   describe   the  degree  of  risk  that  an  organizaJon  will  withstand.    

5.  OrganizaJonal  Process  Assets    –  contain   risk   categories,   common   definiJons   of   concepts   and   terms,  

risk  statement  formats,  standard  templates,  roles  and  responsibiliJes,  authority  levels  for  decision  making,  and  lessons  learned.    

 Copyright@STEVBROS   Project  Mamagement  Fundamentals   7  

Page 8: Project Risk Management

Tools  and  techniques  

1.  AnalyJcal  Techniques  –  for   example,   a   stakeholder   risk   profile   analysis  may   be   performed   to   grade   and   qualify   the  project   stakeholder   risk   appeJte   and   tolerance.  Other  techniques,  such  as  the  use  of  strategic  risk  scoring   sheets,   are   used   to   provide   a   high-­‐level  assessment   of   the   risk   exposure   of   the   project  based  on  the  overall  project  context.    

2.  Expert  Judgment  3.  MeeJngs    

Copyright@STEVBROS   Project  Mamagement  Fundamentals   8  

Page 9: Project Risk Management

Outputs  1.  Risk  Management  Plan    

–  Methodology:   approaches,   tools,   and   data   sources   that   will   be  used  to  perform  risk  management  on  the  project.    

–  Roles  and  responsibiliJes  –  BudgeJng  –  Timing  –  Risk  categories  –  DefiniJons  of  risk  probability  and  impact  –  Probability  and  impact  matrix  (details  at  next  slide).    –  Revised  stakeholders’  tolerances.  –  ReporJng  formats  –  Tracking:  documents  how  risk  acJviJes  will  be   recorded   for   the  benefit   of   the   current   project   and   how   risk   management  processes  will  be  audited.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   9  

Page 10: Project Risk Management

Probability  &  impact  matrix  

•  Risk  Probability:  High:  50  percent  or  higher  (likely);  Medium:  Between  10  and  50  percent  (unlikely);  Low:  10  percent  or  lower  (very  unlikely).  

•  Risk  Impact:  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   10  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiEh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.      All  Rights  Reserved.    Table  11-­‐1  Page  318.  

Page 11: Project Risk Management

IdenJfy  risks  •  The   process   of   determining   which   risks   may   affect   the   project   and  

documenJng   their   characterisJcs.   The   key   benefit   of   this   process   is   the  documentaJon  of  exisJng  risks  and  the  knowledge  and  ability  it  provides  to  the  project  team  to  anJcipate  events.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   11  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiEh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  11-­‐5  Page  319.  

Page 12: Project Risk Management

Inputs(1/3)  1.  Risk  Management  Plan  

–  are  the  assignments  of  roles  and  responsibiliJes,  provision  for  risk  management  acJviJes  in  the  budget  and  schedule,  and  categories  of   risk,   which   are   someJmes   expressed   as   a   risk   breakdown  structure    

2.  Cost  Management  Plan  –  provides  processes  and  controls   that   can  be  used   to  help   idenJfy  risks  across  the  project.  

3.  Schedule  Management  Plan  –  provides   insight   to   project   Jme/schedule   objecJves   and  expectaJons   which   may   be   impacted   by   risks   (known   and  unknown).  

4.  Quality  Management  Plan  –  provides   a   baseline   of   quality   measures   and   metrics   for   use   in  idenJfying  risks.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   12  

Page 13: Project Risk Management

Inputs(2/3)  5.  Human  Resource  Management  Plan    

–  provides   guidance   on   how   project   human   resources   should   be  defined,  staffed,  managed,  and  eventually  released.  

6.   Scope  Baseline    –  uncertainty   in   project   assumpJons   should   be   evaluated   as  potenJal  causes  of  project  risk.  

–  the  WBS   is   a   criJcal   input   to   idenJfying   risks   as   it   facilitates   an  understanding  of  the  potenJal  risks  at  both  the  micro  and  macro  levels.   Risks   can   be   idenJfied   and   subsequently   tracked   at  summary,  control  account,  and/or  work  package  levels.    

7.  AcJvity  Cost  EsJmates    –  acJvity  cost  esJmate  reviews  are  useful  in  idenJfying  risks    

8.  AcJvity  DuraJon  EsJmates    –  acJvity  duraJon  esJmate  reviews  are  useful  in  idenJfying  risks    

Copyright@STEVBROS   Project  Mamagement  Fundamentals   13  

Page 14: Project Risk Management

Inputs(3/3)  9.  Stakeholder  Register    

–  ensure   that   key   stakeholders,   especially   the   stakeholder,   sponsor,   and  customer   are   interviewed   or   otherwise   parJcipate   during   the   IdenJfy   Risks  process  

10.  Project  Documents    –  include   project   charter,   project   schedule,   schedule   network   diagrams,   issue  

log,   quality   checklist,   and   other   informaJon   proven   to   be   valuable   in  idenJfying  risks.    

11.  Procurement  Documents    –  the  complexity  and  the  level  of  detail  of  the  procurement  documents  should  be  

consistent  with  the  value  of,  and  risks  associated  with,  planned  procurement.  12.  Enterprise  Environmental  Factors  

–  include   published   informaJon,   including   commercial   databases,   academic  studies,   published   checklists,   benchmarking,   industry   studies,   and   risk  aetudes.  

13.  OrganizaJonal  Process  Assets    –  include  project  files,   including  actual  data,  organizaJonal  and  project  process  

controls,  risk  statement  formats  or  templates,  and  lessons  learned.    

Copyright@STEVBROS   Project  Mamagement  Fundamentals   14  

Page 15: Project Risk Management

Tools  and  techniques(1/2)  

1.  DocumentaJon  Reviews    –  The  quality  of   the  plans,  as  well  as  consistency  between   those  plans  and  

the  project  requirements  and  assumpJons,  may  be  indicators  of  risk  in  the  project.    

2.  InformaJon  Gathering  Techniques    –  Include  brainstorming,  Delphi  technique,  Interviewing,  Root  cause  analysis.    

3.  Checklist  Analysis    –  are   developed   based   on   historical   informaJon   and   knowledge   that   has  

been  accumulated   from  previous  similar  projects  and   from  other  sources  of   informaJon.   The   lowest   level   of   the   RBS   can   also   be   used   as   a   risk  checklist.  

4.  AssumpJons  Analysis  –  Every   project   and   its   plan   is   conceived   and  developed  based  on   a   set   of  

hypotheses,  scenarios,  or  assumpJons.  AssumpJons  analysis  explores  the  validity  of  assumpJons  as  they  apply  to  the  project.  It  idenJfies  risks  to  the  project   from   inaccuracy,   instability,   inconsistency,   or   incompleteness   of  assumpJons.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   15  

Page 16: Project Risk Management

Tools  and  techniques(2/2)  

5.  Diagramming  Techniques  –  Include  Cause  and  effect  diagrams,  System  or  process  flow  charts,  Influence  diagrams.  (details  at  next  slides)  

6.  SWOT  Analysis    –  examines   the   project   from   each   of   the   strengths,  weaknesses,  opportuniJes,  and  threats  (SWOT)    perspecJves  to  increase  the  breadth  of  idenJfied  risks  by  including  internally  generated  risks  

7.  Expert  Judgment    –  Risks   may   be   idenJfied   directly   by   experts   with  relevant   experience  with   similar   projects   or   business  areas.    

Copyright@STEVBROS   Project  Mamagement  Fundamentals   16  

Page 17: Project Risk Management

Root-­‐cause  analysis  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   17  

Page 18: Project Risk Management

Influence  diagram  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   18  

Page 19: Project Risk Management

Outputs  

1.  Risk  Register  – List  of  idenJfied  risks:      •  A   structure   for   describing   risks   using   risk   statements  may  be  applied,  for  example,  EVENT  may  occur  causing  IMPACT,  or  If  CAUSE  exists,  EVENT  may  occur  leading  to  EFFECT.    •  In  addiJon  to  the  list  of  idenJfied  risks,  the  root  causes  of  those  risks  may  become  more  evident.  

– List  of  potenJal  responses  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   19  

Page 20: Project Risk Management

Perform  qualitaJve  risk  analysis  

•  The  process  of  prioriJzing  risks  for  further  analysis  or  acJon  by  assessing  and  combining  their  probability  of  occurrence  and  impact.  The  key  benefit  of   this  process   is   that   it  enables  project  managers   to   reduce  the   level  of  uncertainty  and  to  focus  on  high-­‐priority  risks.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   20  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiEh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  11-­‐8  Page  328.  

Page 21: Project Risk Management

Inputs  1.  Risk  Management  Plan  

–  Analysis   process   include   roles   and   responsibiliJes   for   conducJng   risk  management,   budgets,   schedule   acJviJes   for   risk   management,   risk  categories,   definiJons   of   probability   and   impact,   the   probability   and  impact  matrix,  and  revised  stakeholders’  risk  tolerances  

2.  Scope  Baseline  –  E.g.   Projects   of   a   common   or   recurrent   type   tend   to   have   more   well-­‐

understood   risks.   Projects   using   state-­‐of-­‐the-­‐art   or   first-­‐of-­‐its-­‐kind  technology,  and  highly  complex  projects,  tend  to  have  more  uncertainty.  

3.  Risk  Register    –  contains  the  informaJon  that  will  be  used  to  assess  and  prioriJze  risks.    

4.  Enterprise  Environmental  Factors    –  include   industry   studies   of   similar   projects   by   risk   specialists,   and   risk  

databases  that  may  be  available  from  industry  or  proprietary  sources.    5.  OrganizaJonal  Process  Assets    

–  include  informaJon  on  prior,  similar  completed  projects  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   21  

Page 22: Project Risk Management

Tools  and  techniques  

1.  Risk  Probability  and  Impact  Assessment  (next  slides)  2.  Probability  and  Impact  Matrix  (next  slides)  3.  Risk  Data  Quality  Assessment    

–  assessment  is  a  technique  to  evaluate  the  degree  to  which  the  data  about  risks  is  useful  for  risk  management.  It  involves  examining  the  degree  to  which  the  risk  is  understood  and  the  accuracy,  quality,  reliability,  and   integrity  of  the  data  about  the  risk.  

4.  Risk  CategorizaJon    –  risks  to  the  project  can  be  categorized  by  sources  of  risk  (e.g.,  using  the  RBS),  the  

area  of  the  project  affected  (e.g.,  using  the  WBS),  or  other  useful  categories  (e.g.,  project  phase)  to  determine  the  areas  of  the  project  most  exposed  to  the  effects  of  uncertainty.  Risks  can  also  be  categorized  by  common  root  causes.    

5.  Risk  Urgency  Assessment    –  risks  requiring  near-­‐term  responses  may  be  considered  more  urgent  to  address.  

Indicators  of  priority  may  include  probability  of  detecJng  the  risk,  Jme  to  affect  a  risk  response,  symptoms  and  warning  signs,  and  the  risk  raJng.  

6.  Expert  Judgment    

Copyright@STEVBROS   Project  Mamagement  Fundamentals   22  

Page 23: Project Risk Management

Probability  &  impact  matrix  

•  Risk  Probability:  High:  50  percent  or  higher  (likely);  Medium:  Between  10  and  50  percent  (unlikely);  Low:  10  percent  or  lower  (very  unlikely).  

•  Risk  Impact:  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   23  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiEh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Table  11-­‐1  Page  318.  

Page 24: Project Risk Management

Probability  &  impact  matrix  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   24  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiEh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  11-­‐10  Page  331.  

Page 25: Project Risk Management

Outputs  1.  Project  Documents  Updates    –  Risk  register  updates.    

•  As   new   informaJon   becomes   available   through   the  qualitaJve  risk  assessment,  the  risk  register  is  updated.    

•  Updates   to   the   risk   register   may   include   assessments   of  probability   and   impacts   for   each   risk,   risk   ranking   or   scores,  risk   urgency   informaJon   or   risk   categorizaJon,   and   a  watch  list  for  low  probability  risks  or  risks  requiring  further  analysis.    

– AssumpJons  log  updates.    •  As   new   informaJon   becomes   available   through   the  qualitaJve  risk  assessment,  assumpJons  could  change.    

•  The   assumpJons   log   needs   to   be   revisited   to   accommodate  this  new  informaJon.  AssumpJons  may  be  incorporated  into  the  project  scope  statement  or  in  a  separate  assumpJons  log.    

Copyright@STEVBROS   Project  Mamagement  Fundamentals   25  

Page 26: Project Risk Management

Perform  quanJtaJve  risk  analysis  

•  The   process   of   numerically   analyzing   the   effect   of   idenJfied   risks   on  overall   project   objecJves.   The   key   benefit   of   this   process   is   that   it  produces  quanJtaJve  risk  informaJon  to  support  decision  making  in  order  to   reduce  project  uncertainty.  This  process   isn’t  applied   for  projects  with  low  complexity,  low  dollar  value.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   26  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiEh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  11-­‐11  Page  334.  

Page 27: Project Risk Management

Inputs  1.  Risk  Management  Plan  

–  provides   guidelines,  methods,   and   tools   to   be   used   in   quanJtaJve   risk  analysis.    

2.  Cost  Management  Plan  –  provides  guidelines  on  establishing  and  managing  risk  reserves.    

3.  Schedule  Management  Plan  –  plan  provides  guidelines  on  establishing  and  managing  risk  reserves.    

4.  Risk  Register    –  register  is  used  as  a  reference  point  for  performing  quanJtaJve  risk    

analysis.    5.  Enterprise  Environmental  Factors    

–  include   industry   studies   of   similar   projects   by   risk   specialists,   and   risk  databases  that  may  be  available  from  industry  or  proprietary  sources.    

6.  OrganizaJonal  Process  Assets    –  include  informaJon  from  prior,  similar  completed  projects.    

Copyright@STEVBROS   Project  Mamagement  Fundamentals   27  

Page 28: Project Risk Management

Tools  and  techniques  

1.  Data  Gathering  and  RepresentaJon  Techniques    –  Such  as  interviewing,  probability  distribuJons  (PERT)  

2.  QuanJtaJve  Risk  Analysis  and  Modeling  Techniques    –  Such   as   sensiJvity   analysis,   expected   monetary   value  analysis,  modeling  and  simulaJon  (next  slides)  

3.  Expert  Judgment    –  Expert   judgment  also   comes   into  play   in   the   interpretaJon  of   the   data.   Experts   should   be   able   to   idenJfy   the  weaknesses   of   the   tools   as  well   as   their   strengths.   Experts  may   determine   when   a   specific   tool   may   or   may   not   be  more   appropriate   given   the   organizaJon’s   capabiliJes   and  culture.    

 Copyright@STEVBROS   Project  Mamagement  Fundamentals   28  

Page 29: Project Risk Management

Decision  Tree  and  EMV  

•  EVM used with Decision Tree to choose between many alternative which take into account the future events

•  Example:

[ ]∑ ×= (Impact) ty)(ProbabiliEVM

Example  Source:  Copyright@STEVBROS   Project  Mamagement  Fundamentals   29  

Page 30: Project Risk Management

SensiJvity  Analysis  

•  To determine which risks have the most potential impact to the project •  Changing one or more elements/variables and set other elements to its

baseline then see the impact. •  One typical display of sensitivity analysis is the tornado diagram

Copyright@STEVBROS   Project  Mamagement  Fundamentals   30  

Page 31: Project Risk Management

Modeling  and    simulaJon  

A   Guide   to  the   Project  Management  B o d y   o f  Knowledge,    FiEh   Edi9on  ( P M B O K ®  G u i d e )  © 2 0 1 3  P r o j e c t  Management  Ins9tute,   Inc.    A l l   R i g h t s  Reserved.    Figure   11-­‐17  Page  340.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   31  

Page 32: Project Risk Management

Outputs  1.  Project  Documents  Updates    –  ProbabilisJc   analysis   of   the   project:   EsJmates   are  made  of  potenJal  project  schedule  and  cost  outcomes  lisJng   the   possible   compleJon   dates   and   costs   with  their  associated  confidence  levels.  

–  Probability  of  achieving  cost  and  Jme  objecJves:  For  instance,   in   Figure   11-­‐17,   the   likelihood   of   achieving  the  cost  esJmate  of  US$41  million  is  about  12%  

–  PrioriJzed  list  of  quanJfied  risks  –  Trends   in   quanJtaJve   risk   analysis   results:   As   the  analysis   is   repeated,   a   trend   may   become   apparent  that  leads  to  conclusions  affecJng  risk  responses  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   32  

Page 33: Project Risk Management

Plan  risk  response  •  The   process   of   developing   opJons   and   acJons   to   enhance  

opportuniJes  and  to  reduce  threats  to  project  objecJves.  The  key   benefit   of   this   process   is   that   it   addresses   the   risks   by  their   priority,   inserJng   resources   and   acJviJes   into   the  budget,  schedule  and  project  management  plan  as  needed.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   33  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiEh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  11-­‐18  Page  342.  

Page 34: Project Risk Management

Inputs  1.  Risk  Management  Plan  

–  include   roles  and   responsibiliJes,   risk  analysis  definiJons,  Jming  for  reviews  (and  for  eliminaJng  risks  from  review),  and  risk  thresholds  for  low,  moderate,  and  high  risks.  Risk  thresholds   help   idenJfy   those   risks   for   which   specific  responses  are  needed.  

2.  Risk  Register  –  refers   to   idenJfied   risks,   root   causes   of   risks,   lists   of  potenJal   responses,   risk   owners,   symptoms   and  warning  signs,   the   relaJve   raJng   or   priority   list   of   project   risks,  risks   requiring   responses   in   the   near   term,   risks   for  addiJonal   analysis   and   response,   trends   in   qualitaJve  analysis  results,  and  a  watch  list,  which  is  a  list  of  low-­‐  priority  risks  within  the  risk  register.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   34  

Page 35: Project Risk Management

Tools  and  techniques  (1/3)  

1.  Strategies  for  NegaJve  Risk  or  Threats:  –  Avoid:   Eliminate   the   threat   enJrely,   isolate   project  objecJves  from  the  risk’s  impact.  

–  Transfer   (Deflect,  Allocate):   shiV  some  or  all   the  negaJve  impact  of  a  threat  to  a  third  party  

– MiJgate:   implies   a   reducJon   in   the   probability   and/or  impact   of   an   adverse   risk   event   to   be   within   acceptable  threshold  limits  

–  Accept:   deal   with   the   risks,   project   management   plan   is  not  changed  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   35  

Page 36: Project Risk Management

Tools  and  techniques  (2/3)  

2.  Strategies  for  PosiJve  Risks  or  OpportuniJes:  – Exploit:   seek   to  ensure   the  opportuniJes  definitely  happen  

– Share:  allocate  some  or  all  of  the  ownership  of  the  opportunity   to   a   third   party   who   is   best   able   to  capture  the  opportunity  for  the  project  benefit.  

– Enhance:   increase   the   probability   and/or   the  posiJve  impacts  of  an  opportunity.  

– Accept:  not  acJvely  pursuing  an  opportunity  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   36  

Page 37: Project Risk Management

Tools  and  techniques(3/3)  

3.  ConJngent  Response  Strategies  –  contain  events  that  trigger  the  conJngency  response,  such  as   missing   intermediate   milestones   or   gaining   higher  priority   with   a   supplier,   should   be   defined   and   tracked.  Risk   responses   idenJfied   using   this   technique   are   oVen  called   conJngency   plans   or   fallback   plans   and   include  idenJfied  triggering  events  that  set  the  plans  in  effect.    

4.  Expert  Judgment    –  is   input   from   knowledgeable   parJes   pertaining   to   the  acJons  to  be  taken  on  a  specific  and  defined  risk.  ExperJse  may  be  provided  by  any  group  or  person  with  specialized  educaJon,   knowledge,   skill,   experience,   or   training   in  establishing  risk  responses.    

Copyright@STEVBROS   Project  Mamagement  Fundamentals   37  

Page 38: Project Risk Management

Outputs(1/2)  

•  Project  Management  Plan  Updates    Include   schedule   management   plan,   cost  management   plan,   quality   management   plan,  procurement   management   plan,   human  resource   management   plan,   scope   baseline,  schedule  baseline,  cost  baseline.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   38  

Page 39: Project Risk Management

Outputs  (2/2)  •  Project  Documents  Updates    

–  Update  to  risk  register  •  Risk  owners  and  assigned  responsibiliJes;    •  Agreed-­‐upon  response  strategies;    •  Specific  acJons  to  implement  the  chosen  response  strategy;    •  Trigger  condiJons,  symptoms,  and  warning  signs  of  a  risk  occurrence;    •  Budget  and  schedule  acJviJes  required  to  implement  the  chosen  responses;    •  ConJngency  plans  and  triggers  that  call  for  their  execuJon;    •  Fallback   plans   for   use   as   a   reacJon   to   a   risk   that   has   occurred   and   the   primary  

response  proves  to  be  inadequate;    •  Residual   risks   that   are   expected   to   remain   aVer   planned   responses   have   been  

taken,  as  well  as  those  that  have  been  deliberately  accepted;    •  Secondary  risks  that  arise  as  a  direct  outcome  of  implemenJng  a  risk  response;  and    •  ConJngency  reserves  that  are  calculated  based  on  the  quanJtaJve  risk  analysis  of  

the  project  and  the  organizaJon’s  risk  thresholds.    –  Other   updates:   assumpJons   log   updates,   technical   documentaJon  

updates,  change  requests  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   39  

Page 40: Project Risk Management

Control  risks  •  The  process  of  implemenJng  risk  response  plans,  tracking  idenJfied  risks,  

monitoring  residual  risks,  idenJfying  new  risks,  and  evaluaJng  risk  process  effecJveness   throughout   the   project.   The   key   benefit   of   this   process   is  that  it  improves  efficiency  of  the  risk  approach  throughout  the  project  life  cycle  to  conJnuously  opJmize  risk  responses.    

Copyright@STEVBROS   Project  Mamagement  Fundamentals   40  

A  Guide  to  the  Project  Management  Body  of  Knowledge,  FiEh  Edi9on  (PMBOK®  Guide)  ©2013  Project  Management  Ins9tute,  Inc.    All  Rights  Reserved.    Figure  10-­‐20  Page  349.  

Page 41: Project Risk Management

Inputs  1.  Project  Management  Plan    

–  includes  the  risk  management  plan,  provides  guidance  for  risk  monitoring  and  controlling.    

2.  Risk  Register    –  has  key  inputs  that  include  idenJfied  risks  and  risk  owners,  agreed-­‐upon  

risk  responses,  control  acJons  for  assessing  the  effecJveness  of  response  plans,   risk   responses,   specific   implementaJon   acJons,   symptoms   and  warning   signs   of   risk,   residual   and   secondary   risks,   a  watch   list   of   low-­‐priority  risks,  and  the  Jme  and  cost  conJngency  reserves  

3.  Work  Performance  Data    –  deliverable  status,  schedule  progress,  and  costs  incurred  

4.  Work  Performance  Reports    –  take   informaJon   from   performance   measurements   and   analyze   it   to  

provide   project   work   performance   informaJon   including   variance  analysis,  earned  value  data,  and  forecasJng  data.  These  data  points  could  be  impacsul  in  controlling  performance  related  risks.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   41  

Page 42: Project Risk Management

Tools  and  techniques  

1.  Risk  Reassessment  –  oVen   results   in   idenJficaJon   of   new   risks,   reassessment   of   current   risks,   and   the  

closing  of  risks  that  are  outdated.  Risk  reassessments  should  be  regularly  scheduled  2.  Risk  Audits  

–  examine  and  document   the  effecJveness  of   risk   responses   in  dealing  with   idenJfied  risks   and   their   root   causes,   as   well   as   the   effecJveness   of   the   risk   management  process.    

3.  Variance  and  Trend  Analysis    4.  Technical  Performance  Measurement    

–  compares   technical   accomplishments   during   project   execuJon   to   the   schedule   of  technical   achievement.   Such   technical   performance   measures   may   include   weight,  transacJon  Jmes,  number  of  delivered  defects,  storage  capacity,  etc.  DeviaJon,  such  as  demonstraJng  more  or  less  funcJonality  than  planned  at  a  milestone,  can  help  to  forecast  the  degree  of  success  in  achieving  the  project’s  scope.    

5.  Reserve  Analysis    –  compares   the   amount   of   the   conJngency   reserves   remaining   to   the   amount   of   risk  

remaining  at  any  Jme  in  the  project  in  order  to  determine  if  the  remaining  reserve  is  adequate.  

6.  MeeJngs    Copyright@STEVBROS   Project  Mamagement  Fundamentals   42  

Page 43: Project Risk Management

Outputs  1.  Work  Performance  InformaJon    2.  Change  Requests    

–  ImplemenJng  conJngency  plans  or  workarounds  someJmes  results   in  a  change   request.   It   includes   recommended   correcJve   acJons,  recommended  prevenJve  acJons  

3.  Project  Management  Plan  Updates  4.  Project  Documents  Updates  

–  outcomes  of  risk  reassessments,  risk  audits,  and  periodic  risk  reviews.  5.  Actual  outcomes  of  the  project’s  risks  and  of  the  risk  responses  6.  OrganizaJonal  Process  Assets  Updates    

–  include  templates  for  the  risk  management  plan,  including  the  probability  and   impact   matrix   and   risk   register;   risk   breakdown   structure;   and  lessons  learned  from  the  project  risk  management  acJviJes.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   43  

Page 44: Project Risk Management

Summary  

IdenJfy  Risk  

• Input:  uncertainJes  • Output:  risk  register  

QualitaJve/QuanJtaJve  Analysis  

• Input:  risk  register  • Output:  updated  risk  register,  watch-­‐list  

Plan  Risk  Response  

• Input:  risk  register  • Output:  conJngency  plan,  fallback  plan,  residual  risk,  secondary  risk  

Control  Risk  

• Input:  risk  register  • Output:  workaround,  correcJve  acJons,  prevenJve  acJons  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   44  

Page 45: Project Risk Management

Summary  

•  Watch   list,   residual   risk,   secondary   risk,  fallback   plan,   conJngency   plan,   conJngency  reserve,  workarounds.  

•  4  response  strategies  for  threads.  •  4  response  strategies  for  opportunity.  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   45  

Page 46: Project Risk Management

QuesJons  for  review  

Copyright@STEVBROS   Project  Mamagement  Fundamentals   46  

•  You  did  the  good  job  at  this  chapter.    Please  complete  quesJons  for  review  before  moving  to  next  chapter.