Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The...

129
The Rural Electrification Authority-REA Report prepared and submitted by Repcon associates The Repcon Center Sigona 410 off KEFRI/KARI Rd-Muguga P.O. Box 79605-00200, Nairobi Telefax: 254-20-2248119; Mobile- 0721-274358/0736499399 E-mail:[email protected] April 2013 Project Report for the proposed Mwachabo Market and Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The...

Page 1: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority-REA

Report prepared and submitted by

Repcon associates

The Repcon Center

Sigona 410 off KEFRI/KARI Rd-Muguga

P.O. Box 79605-00200, Nairobi

Telefax: 254-20-2248119; Mobile- 0721-274358/0736499399

E-mail:[email protected] April 2013

Project Report for the proposed Mwachabo Market and Pry/Manoa

Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate

Constituency) 33 kV power distribution line

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb371432
Typewritten Text
E2337 V15
Page 2: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

ii

DISCLOSURE PAGE

This Project Report is hereby disclosed for public review as follows:-

Proponent: The Rural Electrification Authority-REA

Assignment: Project Report for the proposed Mwachabo Market, Pry/Manoa Disp/ Chunga

Unga Market/Dighai Market/ Kamtonga Market/Mkuki Market 33 kV power

distribution line

Firm of Experts: Repcon Associates- NEMA Registration No. 0002,

Contact address: The Repcon Center,

Sigona 410, off KEFRI/KARI Rd Muguga,

P.O. Box 79605-00200, Nairobi.

Telefax: 254-20-2248119; Mobile- 0721-274358/0736499399

E-mail:[email protected]

Signed: ...................................... Date..........................

Michael M. Wairagu

Lead Expert (0177)/ Team Leader

Proponent: The Rural Electrification Authority-REA

Contact address: The Chancery, 6th

Flr, Valley Rd;

P.O. Box 34585-00100, Nairobi; Telephone: +254-20-4953000;

Fascimile: +254-20-2710944; Email: [email protected]

Attention of: Mr. Zackary O. Ayieko-CEO

Signed.......................................... Date....................

Page 3: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

iii

EXECUTIVE SUMMARY

A. Introduction:

The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa Disp/ Chunga

Unga Market/Dighai Market/ Kamtonga Market/Mkuki Market 33 kV power distribution line being

developed by the Rural Electrification Authority-REA on behalf of the Kenya Government. The Report

has been prepared for REA (Proponent) by Repcon Associates (The Environmental Firm of Experts) in

compliance with the Environmental Management and Coordination Act, 1999 and in line with Legal

Notice No. 101 of June 2003.

B. Scope of the Project Report:

The main objective of this Project Report is identify environmental and social impacts associated with

development and operation of the proposed power distribution line and recommend appropriate

mitigation measures for integration in all phases of project development.

Framework and depth of the Project Report has been dictated by requirements of EMCA 1999 and Legal

Notice 101 of June 2003 which has defined parameters for conduct of Environmental and Social Impact

Assessment studies in Kenya. Regulation 7(1) of Legal Notice 101 of EMCA dictates the following basic

content of Project Reports:-

a) The nature of the project;

b) The Division of the project including the physical area that may be affected by the project’s

activities;

c) The activities that shall be undertaken during the project construction, operation and

decommissioning phases;

d) The design of the project;

e) The materials to be used, products, by-products, including waste to be generated by the project

and the methods of disposal;

f) The potential environmental impacts of the project and the mitigation measures to be taken

during and after implementation;

g) An action plan for the prevention and management of possible accidents during the project

cycle;

h) A plan to ensure the health and safety of the workers and neighboring communities;

i) The economic and socio-cultural impacts to the local community and the nation in general;

j) The project budget;

k) Any other information that the Authority may require

C: Study Methodology pursued

The systematic investigative and reporting methodology specified for conduct Project Reports by Legal

Notice 101 of EMCA was adopted in this Study. Baseline data on project design was generated through

discussion with the client and review of project documentation. Opinions formed were revalidated

Page 4: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

iv

through field work entailing site investigations and interviews with potentially affected people and

secondary stakeholders.

To identify, predict, analyze and evaluate potential impacts that may emanate from the project, diverse

study methods and tools including use of checklists, matrices, expert opinions and observations were

employed. An Environmental and Social Management Plan comprising an impact mitigation plan and

modalities for monitoring and evaluation were then developed to guide environmental management

during all phases of project development.

D: The Project Report Team

This Project Report study was undertaken by a team of 2 consultants namely:-

• Mr. Michael M. Wairagu-EIA Lead Expert

• Ms. Nancy Kanyi-Sociologist

E: Policy, legal and regulatory framework:

This Project Report has been developed to ensure that the proposed development of power distribution

lines is in conformity with national policy aspirations towards securing sustainable development.

Specifically, this report has been developed to ensure compliance with requirements of the

Environmental Management and Coordination Act (EMCA) 1999-Kenya’s supreme environmental law,

the National Constitution and World Bank’s safeguard requirements. Section 58 of EMCA requires that

all development proposed in Kenya to be subjected to environmental assessment to be conducted in

line with the Second Schedule and The Environmental (Impact Assessment and Audit) Regulations, 2003.

As well, Op 4.01 of the World Bank demands environmental assessment for Category A and B hence

occasioning the need for the study report disclosed here-in.

F. Project description:

The Proponent in respect of the proposed Mwachabo Market, Pry/Manoa Disp/ Chunga Unga

Market/Dighai Market/ Kamtonga Market/Mkuki Market 33 kV power distribution line is the Rural

Electrification Authority (REA) - a State Corporation established under Section 66 of the Energy Act No

12 of 2006 for purposes of accelerating the pace of rural electrification in Kenya.

Development of the Mwachabo power distribution line will be financed under auspices of the KEEP (REA

component) whose overall aim is to increase access to electricity in rural areas and is justifiable in that it

will electrify rural villages and institutions and thus unlock the opportunities associated with cost

effective access to convertible energy sources. The project will entail development of 35.3 kilometers of

Three Phase power distribution line which will comprise 3 lengths of parallel conductors (each 35.3 Km

long) mounted on a total of 133 wooden poles of 10-14 m height. The 33 kV power will be stepped

down to 0.433 through 2 differently located transformers and then supplied to consumers through new

low voltage lines to be constructed.

Mwacho market can be accessed by rough road from Mwatate though the Teita Estate from the

Mwatate-Taveta (A23 road) branching off just before Bura.

G: The proposed route of traverse

The Mwachabo power distribution line trading centers and institutions situated within the Mwachabo

location of Mwatate District. Mwachabo location is situated in the Taita lowlands which is part of the

expansive lowland area extending from the Yatta Plateau in the East to beyond the Tanzanian boundary

Page 5: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

v

in the west and which contains the Tsavo East and West National Parks. Altitude generally averages 700

m above sea level.

On account of low altitude and absence of relief barriers, rainfall in the Mwatate lowlands averages

665mm delivered in two seasons; - March to May and November to December. The latter peak is more

pronounced. Further, the prevailing high temperatures exert a huge evaporative demand of 2189mm

annually which far exceeds moisture inputs from rainfall with a consequent huge moisture deficit

throughout the year. Long-term climate for the area is therefore semiarid which gives rise to savannah

woodlands dominated by Acacia-Commiphora formations.

As at the 2009 National Population Census, Mwachabo location had a population of 12,263 people

comprised of 3,065 households of which, the local Taita form the greater majority. The location hosts

the large-scale Teita Estate specialising in sisal growing but small settlements of Mwachabo, Manoa,

Kamtonga, Mkuki, etc are building up in the un-adjudicated area to the west of the sisal farm. These are

the settlements targeted for power supply.

H: Findings from the Study

(i) Overview of impacts:

The scope of adverse impacts associated with construction of 10 kilometres of 33 kV power distribution

line in an otherwise low density agricultural settlement is inherently low. Thus, for the proposed

Mwachabo power line, this study has only identified a total of 34 impacts, 17 of which are positive.

Other trends in impacts are as follows:-

• The other half of potential impacts are likely to be adverse.

• Ten of the 17 positive impacts are likely to be long-term in prevalence while 7 out of 8 adverse

impacts have a long-term effect with 2 of them being potentially irreversible.

• Nine out of sixteen adverse impacts have potential to cause secondary impacts while 6 of them

have cumulative tendency ie, they have potential to aggravate an already existing problem.

• The project has a marginal net positive impact pre mitigation which will require to be enhanced

through adoption of an effective impact mitigation strategy.

(ii) The Potential positive impacts anticipated

Positive implications of the project emanate from its potential to create short-term business and

employment opportunities to both professional staff and workers during the design phase while, at

construction phase, traders will benefit from opportunities to supply construction material while locals

will be employed in works. Upon commissioning, the project could supply electric power to 3 schools

and 5 rural trading centers where the potential to unlock business potential is real. Through adoption of

electricity and cutting down on use of fossil fuels, the project has potential to favor cutting down on

Green House Gas emissions to the benefit of the global climate.

(iii) The Potential adverse impacts/concerns

Core adverse impacts could include the following:-

Page 6: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

vi

• Displacement of trees and property: By design, 33 kV distribution lines do not require land

acquisition to create way leaves and are also sited to avoid any standing structures. However,

such power lines do occasionally require that trees be removed and this present the main

adverse impact of the proposed power line. Along the proposed 35.3 kilometer long power line,

some indigenous tree could be removed and this could contribute to loss of floral biodiversity

through deforestation.

• Hazards to road users: Construction activity including transport of materials to the site and

erection of the power distribution line poses occupational health and safety hazard to both

construction crew and third parties.

• Conflict over use of road reserves: Unless properly coordinated, construction of power lines has

recently been observed to occasion conflicts over the use of road reserves and the same can

recur in regard of proposed power line.

• Hazards posed by presence of powered lines: Further, presence of the line changes the local

landscaper and skyline and such intrusion into space is a kind of pollution, not mentioning the

perpetual hazards introduced by presence of a powered line.

I: The Environmental and Social Management and Monitoring Plan

The proposed project is quite small in scale and given the passage in an medium density agricultural

settlement, the scope of anticipated impacts is quite low,. Further, the bulk of impacts is associated with

construction activity and will thus cease once construction ends. Intervention at mitigation has been

identified as follows:-

Mitigation of potential loss of trees: Project design will primarily aim at reducing tree casualties

through rerouting of the power line. Where tree removal is inevitable, such removal will be cleared

upfront with the County Agricultural Officers in line with the Agriculture (Farm Forestry) Rules 2009

upon which, REA will pay just and prompt compensation for all trees removed or lopped. Further,

towards rebuilding lost vegetation cover, REA will identify and support a local group to raise and plant

tree seedlings in the route of traverse. REA will follow and monitor progress of said trees to ensure

achievement of highest survival possible.

Compliance to requirements of OSHA 2007: The Contractor will be bound in contract to implement the

Code of Safety as outlined in 8.4 above. The core mitigation strategy is to optimize on construction time

so as to reduce the time taken to complete all civil works. The Contractor will deploy sober competent

staff working under competent supervisors. In addition to provision of protective gear, all workers will

be covered under the Workman Compensation Scheme.

REA to engage road sector stakeholders on use of road reserves: At the design stage, REA will engage

all road sector stakeholders to agree on mutually acceptable sharing of the target road reserves but in

the long run, this matter will require legal resolution.

REA to undertake public sensitization on hazards posed by live power lines: Towards curbing vandalism

of the power distribution line and associated hazards, the REA will mount public sensitization campaigns

in the affected area and will ensure that the property is promptly handed over to the community. As

well, the contractor should be held liable for all vandalism during the defect liability period.

The Monitoring Strategy: The responsibility for ensuring total environmental worth of the proposed

project vests with REA in the capacity of proponent. Towards this, the proponent will retain and deploy

Page 7: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

vii

a team of highly motivated environmental and social scientists to monitor and report on all stages of the

project. Other action has been recommended as follows:-

i) The ESMMP as outlined above will be integrated into the Design Report with appropriate

allocation of funds in the Bills of Quantities.

ii) REA will therefore allocate the budget of Ksh 7 million be required to offset the social and

environmental impacts associated with the project.

iii) The Contractor will prepare routine reports which will be ascertained by the Supervising

Consulting Engineer before Payment Certificate can be issued.

iv) The contract for construction should bear clauses binding the contractor to implement impact

mitigation as part of the civil works. Environmental stabilization works will be covered under the

defect liability period.

v) REA will mount own internal monitoring to ensure that impact mitigation has been

implemented and will file annual audit reports with NEMA.

vi) The proposed project will adhere to all other laws of the land and will seek and obtain all

requisite statutory permits.

J: Recommendations of this Project Report

The proposed development of a power distribution project is largely aligned to reigning GOK Policies for

national development. The project enjoys a highly positive benefits profile as it will strongly support

initiatives towards poverty alleviation and reversal of environmental-degradation both of which are

critically important policy aspirations of the Kenya Government. This Study recommends that project

development should proceed but factor in the mitigation measures recommended herein. REA in the

capacity of proponent will require to closely monitor activities especially at construction stage and

simultaneously avail funds for environmental and social restoration.

Our recommendation is for the project to be licensed to proceed to the next level of development.

Page 8: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

LIST OF ABBREVIATIONS

AOJ = Area of Jurisdiction

BOQs = Bill of Quantities

CAP= Chapter of the Laws of Kenya

CITES = Convention on International Trade in Endangered Species

EA = Environmental Assessment

EHS = Environment Health and Safety

EMCA 1999 = Environment Management and Coordination Act 1999

EMP = Environmental Management Plan

ERC = Electricity Regulatory Commission

ESIA = Environmental and Social Impact Assessment

ESMMP = Environmental and Social Management and Monitoring Plan

GDP = Gross Domestic Product

GHG = Green House Gases

GoK = Government of Kenya

HV = High Voltage

IMP = Impact Mitigation Plan

IPPs = Independent Power Producers

KENGEN = Kenya Electricity Generating Company

KFS = Kenya Forestry Service

KLPC = Kenya Power and Lighting Company Limited

kV= Kilo volts

KWS = Kenya Wildlife Service

M&E= Monitoring & Evaluation

MDGs = Millennium Development Goals

MoE = Ministry of Energy

MW = Mega Watts

MWI = Ministry of Water and Irrigation

NEMA = National Environment Management Authority

O&M = Operation and Maintenance

PAC = Program Audit Consultant

PAPs = Project Affected Persons

PMs = Project Managers

RE= Resident Engineer

RETs = Renewable Energy Technologies

RAP = Resettlement Action Plan

SHS= Solar Home Systems

SMEs = Small and Micro- Enterprises

TL= Distribution Line

TORs = Terms of Reference

US$ = United States Dollar

Page 9: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

ix

Table of Contents

DISCLOSURE PAGE .............................................................................................................. ii

EXECUTIVE SUMMARY ..................................................................................................... iii

1 CHAPTER ONE: INTRODUCTION .................................................................................................................................................................................................................................................................................................................... 1111

1.1 Background to this report ................................................................................................ 1

1.2 Scope and objectives of the Environmental and Social Impact Assessment ................... 1

1.2.1 Study scope ............................................................................................................. 1

1.2.2 Study Objectives ..................................................................................................... 1

1.2.3 The Environmental and Social Impact Assessment Team ...................................... 1

1.3 Approach and methodology to the Environmental and Social Impact Assessment........ 2

1.3.1 Discussions with the Project Design Consultant ..................................................... 2

1.3.2 Data collection ........................................................................................................ 2

1.3.3 Field work and public consultations ....................................................................... 2

1.3.4 Data analysis and impact prediction ....................................................................... 3

1.3.5 Formulation of an Environmental and Social Management Plan ........................... 3

1.3.6 Reporting procedure ............................................................................................... 3

1.4 Presentation of this Report .............................................................................................. 4

2 CHAPTER TWO: PROJECT DESCRIPTION /DISCLOSSURE ................................................................................................................................................................................ 5555

2.1 Overview .......................................................................................................................... 5

2.2 About the Proponent ....................................................................................................... 5

2.3 Objectives of the proposed Project ................................................................................. 5

2.4 Project Justification .......................................................................................................... 5

2.5 The proposed route of traverse ....................................................................................... 5

2.6 Design features of the distribution lines .......................................................................... 7

2.6.1 Nature of power distribution lines ......................................................................... 7

2.6.2 Scope of the project ................................................................................................ 8

2.6.3 Other specifications ................................................................................................ 8

2.6.4 Land requirement by the distribution lines ............................................................ 9

2.6.5 Project activities ...................................................................................................... 9

2.6.6 Land ownership within route of traverse ............................................................... 9

2.7 Total Cost of the Project................................................................................................... 9

3 CHAPTER THREE: POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ................................................................................ 11111111

3.1 Policy Frameworks ......................................................................................................... 11

3.1.1 Constitutional provisions ...................................................................................... 11

3.1.2 Other GOK Policies relevant to environmental conservation .............................. 12

3.1.3 World Bank’s Safeguard Policies (WBSGPs) .......................................................... 14

3.2 The Legal Framework for Environmental Management in Kenya ................................. 17

3.2.1 Provision of an Institutional Framework .............................................................. 17

3.2.2 EMCA requires Environmental Impact Assessment for new projects .................. 18

3.2.3 EMCA provides for gazzettment of Environmental Regulations .......................... 18

3.2.4 EMCA requires inter-sectoral coordination .......................................................... 20

Page 10: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

x

3.2.5 EMCA requires conformity to International Conventions, Treaties and

Agreements ....................................................................................................................... 28

3.3 The Regulatory Framework ............................................................................................ 30

3.3.1 The Rural Electrification Authority-REA ................................................................ 30

3.3.2 The Energy Regulatory Commission-ERC .............................................................. 30

3.3.3 The National Environmental Management Authority-NEMA .............................. 30

4 CHAPTER FOUR: THE BASELINE ENVIRONMENT ................................................................................................................................................................................................................ 31313131

4.1 The Bio-physical baseline ............................................................................................... 31

4.1.1 Location and administrative set-up ...................................................................... 31

4.1.2 Relief and physiographic profile ........................................................................... 31

4.1.3 Climatic regime ..................................................................................................... 31

4.1.4 Cover vegetation ................................................................................................... 33

4.1.5 The socio-economic profile ................................................................................... 34

4.1.6 The inhabitants ..................................................................................................... 34

4.1.7 Population dynamics ............................................................................................. 34

4.1.8 Land use and livelihoods ....................................................................................... 34

4.2 Ecologically sensitive resources ..................................................................................... 34

5555 CHAPTER FIVE: STAKEHOLDER CONSULTATIONSCHAPTER FIVE: STAKEHOLDER CONSULTATIONSCHAPTER FIVE: STAKEHOLDER CONSULTATIONSCHAPTER FIVE: STAKEHOLDER CONSULTATIONS ................................................................................................................................................ 35353535

5.1 Need for stakeholder consultations ................................................................................ 35

5.2 Approach to stakeholder consultation ............................................................................ 35

5.2.1 Identification of stakeholders ................................................................................ 35

5.2.2 Levels in stakeholder consultations ...................................................................... 35

5.2.3 Methodologies in stakeholder consultation: ......................................................... 36

5.2.4 Progress in consultation ........................................................................................ 36

5.2.5 Comments from local stakeholders ....................................................................... 39

5.2.6 Comments from local Institutions ......................................................................... 40

5.3 Salient observation from stakeholders’ consultation ..................................................... 40

5.4 Modalities for conflict resolution ................................................................................... 40

6666 CHAPTER SIX: ANALYSIS OF ALTERNATIVESCHAPTER SIX: ANALYSIS OF ALTERNATIVESCHAPTER SIX: ANALYSIS OF ALTERNATIVESCHAPTER SIX: ANALYSIS OF ALTERNATIVES ........................................................................................................................................................................ 41414141

6.1 Overview ........................................................................................................................ 41

6.2 Levels in evaluating project alternatives ........................................................................ 41

6.2.1 Evaluation of the No Project option ..................................................................... 41

6.2.2 Options in the selection of the routes of traverse ............................................... 41

6.3 Choice between diverse distribution technologies........................................................ 41

6.4 Choice of Tower structures ............................................................................................ 42

6.5 The preferred option ...................................................................................................... 43

7 CHAPTER SEVEN: POTENTIAL IMPACTS FROM THE PROJECT ............................................................................................................................................ 45454545

7.1 Generic Social and Environmental Impacts ................................................................... 45

7.1.1 Outcome of impact prediction .............................................................................. 45

7.1.2 Analysis of impact severity ................................................................................... 45

7.2 Description of potential impacts .................................................................................... 45

7.2.1 Overview of impacts ............................................................................................. 45

Page 11: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

xi

7.2.2 Impacts at Design Stage ........................................................................................ 46

7.2.3 Positive Impacts at Construction Stage ................................................................. 46

7.2.4 Negative impacts at Construction Stage ............................................................... 49

7.2.5 Impacts at the Operation Phase ........................................................................... 50

7.2.6 Adverse impacts from powering and operating the distribution line .................. 52

7.2.7 Core concerns about the project .......................................................................... 53

8 CHAPTER EIGHT: THE ENVIRONMENTAL MANAGEMENT PLAN ............................................................................................................................ 54545454

8.1 Overview ........................................................................................................................ 54

8.2 The Impact Mitigation Plan ............................................................................................ 54

8.3 Mitigation at design stage .............................................................................................. 54

8.4 Mitigation at construction stage .................................................................................... 54

8.4.1 Mitigation of impacts associated with tree removal ............................................ 54

8.4.2 Mitigation of potential conflict in the use of road reserves ................................. 57

8.4.3 Management of Occupational Health and Safety Hazards................................... 57

8.4.4: Management of Health and Safety Hazards within institutions and market centers

59

8.4.5 : Modalities for conflict resolution .......................................................................... 59

8.5 Mitigation of Impacts at Operation Stage ...................................................................... 59

8.6 Effectiveness of the Mitigation programme .................................................................. 59

8.6.1 Viability of Mitigation ........................................................................................... 59

8.6.2 Prevalence of residue impacts .............................................................................. 60

8.6.3 Management of decommissioning ....................................................................... 60

8.7 Monitoring requirements ............................................................................................... 60

8.7.1 The concepts ......................................................................................................... 60

8.8 Roles and Responsibilities in implementing the EMP .................................................... 64

8.9 Budget for Environmental and Social Mitigation ........................................................... 65

9 CHAPTER NINE: CONCLUSION AND RECOMMENDATIONS ........................................................................................................................................................ 66666666

9.1 The Project ..................................................................................................................... 66

9.2 Study Methodology pursued .......................................................................................... 66

9.3 Findings from the Study ................................................................................................. 66

9.3.1 Overview of impacts ............................................................................................. 66

9.3.2 Nature of the potential positive impacts anticipated .......................................... 66

9.3.3 Nature of the Potential adverse impacts/concerns.............................................. 67

9.4 The Environmental and Social Management and Monitoring Plan ............................... 67

9.4.1 The Impact Mitigation Plan: .................................................................................. 67

9.4.2 Effectiveness of the Mitigation Plan ..................................................................... 68

9.4.3 Total Cost in Environmental and Social Mitigation .............................................. 68

9.5 The Monitoring Strategy ................................................................................................ 68

9.6 Recommendations of this Project Report ...................................................................... 68

APPENDICES: ............................................................................................................................................................................................................................................................................................................................................................................................................................................................ 70707070

Page 12: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

xii

List of Tables

Table 2.1: Summary features of the scheme ................................................................................................ 8

Table 3.1: Analysis of potential triggers to World Bank safeguards policies ............................................. 15

Table 3.3: Screening of the proposed power distribution line project against international treaties on

protection of nature ................................................................................................................................... 29

Table 3.4: Screening of the proposed power distribution line project against international treaties on

protection of the atmosphere .................................................................................................................... 29

Table 4.1: Climate data for the Mwatate area based on the Voi Meteorological station .......................... 31

Table 4.2: Population statistics for Mwatate District ................................................................................. 34

Table 5.1: Summary table of stakeholders consulted ................................................................................ 38

Table 6.1: Analysis of alternatives .............................................................................................................. 44

Table 7.1: Matrix for impact prediction and interpretation ...................................................................... 47

Table 8.1: Matrix for impact mitigation ..................................................................................................... 55

Table 8.3: Analysis of impacts scenario before and after mitigation ......................................................... 60

Table 8.4: Matrix for Environmental and Social Management and Monitoring (ESmmP) ......................... 62

List of Figures

Figure 2.1: Schematic presentation of the Mwachabo power distribution line project .............................. 7

Figure 2.2: Three phase power distribution ................................................................................................ 8

Figure 4.1: Seasonal moisture balance for Mwatate area .......................................................................... 33

List of Plates

Plate 2.1: Potential beneficiaries of the power distribution (i): Manoa dispensary (ii) Kamtonga Market

and (iii)the Manoa market ............................................................................................................................ 6

Plate 4.1: An inselberg in the Mwatate Plains ............................................................................................ 31

Plate 4.2: Remnant semi arid vegetation in the Mwachabo Location ...................................................... 33

Plate 5.1 : Stakeholder consultation at Kamtonga Trading Centre ............................................................ 37

Plate 7.1: Birds nesting on a tree at Kamtonga market removal of such trees implies loss of nesting

grounds for birds ......................................................................................................................................... 49

Plate 7.2: Transportation of construction materials has potential to undermine safety of other road users

.................................................................................................................................................................... 50

Page 13: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

1

1 CHAPTER ONE: INTRODUCTION

1.1 Background to this report

The Rural Electrification Authority–REA is the Utility mandated by the Government of Kenya to design

and construct rural electrification schemes in Kenya. With support from the GoK and the World Bank,

REA is currently developing 150 rural electrification schemes under the Kenya Electricity Expansion

Project (KEEP). Under KEEP, REA will develop 33 kV power lines in 23 Counties among them Taita Taveta

County where the proposed Mwachabo Market, Pry/Manoa Disp/ Chunga Unga Market/Dighai Market/

Kamtonga Market/Mkuki Market 33 kV power distribution line (here after referred to as the

Mwachabo 33 kV power distribution line project) will be constructed. The latter line will supply electric

power to designated institutions and market centers within Mwatate Constituency.

This proposed power distribution line is the subject of this Project Report which has been motivated by

the need to ensure that supply of electric power to the target villages will be in conformity with

requirements for technically sustainable, socially acceptable and economically viable development

which is the essence of environmental impact assessment. Further, this report has been prepared under

contract by Repcon Associates- a Nairobi-based consultancy (See Appendix 1.1 for statutory registration

details) in conformity with Legal Notice 101 of EMCA.

1.2 Scope and objectives of the Environmental and Social Impact Assessment

1.2.1 Study scope

Essentially, the framework and depth of this Project Report was dictated by reining legislation namely

EMCA 1999 and its Legal Notice 101 of June 2003 which has defined parameters for conduct of

Environmental and Social Impact Assessment studies in Kenya. The Second Schedule of EMCA-1999

identified power distribution among projects that require to be subjected to environmental impact

assessment and this informed the need to design and execute the Project Report Study for the proposed

Mwachabo Project. As well, given the limited scale and scope of investment required in developing 33

kV power distribution lines, a decision was made to mount a study process culminating in development

of a Project Report in line with Legal Notice 101 of EMCA.

1.2.2 Study Objectives

Objectives for this Project Report Study were identified as follows;-

• To identify and assess potential environmental and social impacts of the proposed project.

• To identify all potential significant adverse environmental and social impacts of the proposed

project and recommend measures for mitigation measures.

• To verify compliance with the environmental regulations and industry’s standards

• To recommend cost effective measures to be implemented to mitigate the expected impact.

• To prepare a Project Report compliant to the Environmental Management and Coordination Act

[1999] and it’s Legal Notice 101.

1.2.3 The Environmental and Social Impact Assessment Team

This Environmental and Social Impact Assessment study was undertaken by a multidisciplinary team

bringing together skills as follows:-

Page 14: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

2

• Mr. Michael M. Wairagu- EIA Lead Expert and Team Leader

• Ms. Nancy Kanyi-Sociologist

Details of NEMA registration status in respect of both team members are provided in Appendix 1.2.

1.3 Approach and methodology to the Environmental and Social Impact Assessment

A Project Report is primarily a tool aimed at facilitating identification and mitigation of adverse impacts

of an activity before its implementation commences while creating an opportunity for enhancing

positive impacts and thus improving on the entire net worth of the project. For the purposes of this

Project Report, systematic data correction took place through activities as follows:-

1.3.1 Discussions with the Project Design Consultant

Core discussions were held between the Study Team Leader (from Repcon) and Project Managers from

both SWECO and Aberdare Engineering Ltd from which, finer details of the assignment were negotiated

and harmonized. Consultative meetings also took place with staff of the REA in pursuit of better

understanding of the environmental mandate and capacity of the Authority. From such discussions, the

consultant obtained maps and project design data which helped better clarify the project scope.

1.3.2 Data collection

The Project Report Process also employed review of available reports towards familiarizing with the

focus and objectives of the entire programme. Core reports reviewed here included the Environmental

and Social Management Framework (ESMF) and the Resettlement Policy Framework (RPF) prepared for

KEEP. Secondary data for the route of traverse was obtained from diverse sources such as GOK planning

documents and policy blue prints, professional reports and releases, etc all of which provided an insight

into the socio-economic and biophysical baseline for the target area. A list of documents and data

sources consulted as part of this study is provided in Appendix 1.3. Preliminary opinions formed from

review of such documentation were re-validated during fieldwork undertaken within the traverse area.

1.3.3 Field work and public consultations

Fieldwork largely entailed onsite investigations so as to familiarize with the baseline environment of the

area potentially affected by the project. Analysis of potential impacts was based on investigations

undertaken along the entire route of traverse where data on physiographic, pedology, hydrology and

drainage, ecology and cover vegetation, settlement and land-use patterns, ecologically and economically

sensitive resources were collected. Accruing information formed the basis for impact prediction.

Further, and in line with requirements of Legal Notice 101 of EMCA and its Schedules, the proposed

project was subjected to public participation through conduct of public hearing along the traverse and

through one to one interviews with other stakeholders.

Chapter six below provides a record of the public participation process as pursued in this study. Views

/comments accruing not only served to inform the design process but also formed a basis for discussion

between the community and study team towards improving the overall quality of the proposed

interventions. Stakeholders in government including the provincial administration, land-based sectors,

etc were also consulted to clarify diverse issues and to ensure that proposed development was in

harmony with sectoral policies.

Page 15: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

3

1.3.4 Data analysis and impact prediction

Upon data analysis, potential environmental impacts (both positive and adverse) were predicted based

on available tools. The magnitude, significance, and acceptability of predicted impacts were evaluated

with a view to determining whether observed adverse impacts are significant enough to warrant

mitigation. The potential environmental impacts were described in both quantitative and qualitative

terms through application of existing body of knowledge, checklists and input from diverse stakeholders.

In particular, impact prediction in this study drew heavily on three tools namely:-

i) The Third Schedule to Legal Notice 101 of EMCA

ii) The Sectoral checklists for the Power Sector developed for the Asian Development Bank;

iii) The Checklist of Environmental Characteristics developed by the Department of Environmental

Affairs of the Republic of South Africa and,

iv) The Reference Guidelines for Environmental Assessments (which incorporates the Leopold

Matrix) developed by USAID / REDSO / WCA–Abidjan.

Impacts were further screened for occurrence and significance of residual (those which cannot be

mitigated satisfactorily) and cumulative impacts with a view to providing a basis of making

recommendations on the way forward for the project.

1.3.5 Formulation of an Environmental and Social Management Plan

Measures or interventions necessary to minimize, reduce, avoid or offset identified adverse impacts

were evaluated and presented in form of an Impact Mitigation Plan for the proposed development. Such

evaluation also included an assessment of Project Alternatives as reported in Chapter Six below. The

ESMP also identified modalities for monitoring and evaluation to ensure compliance in implementation

of proposed mitigation measures. This involved development of monitoring indicators and procedures

for continuous generation of project monitoring data and information.

1.3.6 Reporting procedure

The Study methodology as described above culminated with production of this Project Report

formulated in line with Regulation 7(1) of Legal Notice 101 of EMCA which requires that a proponent

shall prepare a project report stating: -

a) The nature of the project;

b) The Division of the project including the physical area that may be affected by the project’s

activities;

c) The activities that shall be undertaken during the project construction, operation and

decommissioning phases;

d) The design of the project;

e) The materials to be used, products, by-products, including waste to be generated by the project

and the methods of disposal;

f) The potential environmental impacts of the project and the mitigation measures to be taken

during and after implementation;

g) An action plan for the prevention and management of possible accidents during the project

cycle;

h) A plan to ensure the health and safety of the workers and neighboring communities;

i) The economic and socio-cultural impacts to the local community and the nation in general;

j) The project budget;

k) Any other information that the Authority may require

Page 16: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

4

A draft version of this Project Report has been reviewed by REA and SWECO whereby emergent

comments have been input towards development of this Final Project Report which will be submitted to

NEMA in line with Regulation 8 of Legal Notice 101.

1.4 Presentation of this Report

This report is presented in nine chapters which integrate the content for Project Reports as stipulated in

Regulation 7 of LN 101 thus:-

• Chapter One (this chapter) outlines the background and procedure in developing this Project Report;

• Chapter Two provides a description of the project as proposed by REA;

• Chapter Three reviews relevant policies, legal, regulatory and administrative frameworks governing

conduct of environmental assessment in Kenya;

• Chapter Four provides the pre-project baseline environment;

• Chapter Five provides an analysis of alternatives to the project;

• Chapter Six reports on the outcome of stakeholder consultations;

• Chapter Seven analyses potential impacts of the project;

• Chapter Eight outlines the Environmental and Social Management and Monitoring Plan (ESMP)

developed for the project;

• Chapter Nine provides the conclusion and recommendation

Page 17: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

5

2 CHAPTER TWO: PROJECT DESCRIPTION /DISCLOSSURE

2.1 Overview

This chapter provides an overview of the proposed distribution line as currently designed. The

description borrows largely from documentation availed by the Rural Electrification Authority-REA.

2.2 About the Proponent

The Proponent in respect of the proposed Mwachabo 33 kV power distribution line project is the Rural

Electrification Authority (REA)- a State Corporation established under Section 66 of the Energy Act, 2006

(No 12 of 2006) for purposes of accelerating the pace of rural electrification in Kenya. The Energy Act,

2006 sets out the functions of REA as follows:-

• To Manage the Rural Electrification Programme Fund

• To Develop and update the rural electrification master plan

• To Promote the use of renewable energy sources including small hydros, wind, solar, biomass,

geothermal, hybrid systems and oil fired components taking into account specific needs of

certain areas including the potential for using electricity for irrigation and in support of off-farm

income generating activities.

• Implementation and sourcing of additional funds for the rural electrification programme

• Management of the delineation, tendering and award of contracts for licences and permits for

rural electrification

2.3 Objectives of the proposed Project

The proposed Mwachabo 33 kV power distribution line project is being developed under auspices of

project KEEP whose REA component is designed to increase access to electricity in rural areas through

pursuit of three objectives namely;-

• Increasing access to electricity by accelerating connection rates and introducing a customer-

friendly connection policy;

• Promotion of the use of renewable energy sources like solar;

• Providing quality and affordable electricity to all in rural areas.

2.4 Project Justification

The project is justifiable in that, it will electrify rural villages and institutions and thus unlock the

opportunities associated with cost effective access to convertible energy sources. Plate 2.1 below

presents a pictorial summary of some intended beneficiaries of the project.

2.5 The proposed route of traverse

Though the proposed line targets villages in the Mwachabo Location of Mwatate District, the bulk of the

proposed distribution line will traverse the vast Teita Estate. Access is via the dirt road traversing the

Teita Estate which exits at Mwachabo Market, then forks to Manoa and Kamtonga and Mkuki and

Chunga Mali villages. The target villages can also be accessed from the Mwatate-Taveta (A23 road)

branching off just before the junction to Taita Salt Licks.

Page 18: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

6

Plate 2.1: Potential beneficiaries of the power distribution (i): Manoa dispensary (ii) Kamtonga

Market and (iii)the Manoa market

Page 19: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

7

Figure 2.1: Schematic presentation of the Mwachabo power distribution line project

2.6 Design features of the distribution lines

2.6.1 Nature of power distribution lines

By design, there are 5 categories of power distribution lines depending on the voltage as follows:-

• Low voltage – less than 1000 volts, used for connection between a residential or small commercial

customer and the utility.

• Medium Voltage (Distribution) – between 1000 volts (1 kV) and to about 33 kV, used for distribution

in urban and rural areas.

• High Voltage (sub-distribution less than 100 kV); sub-distribution or distribution at voltage such as

115 kV and 138 kV), used for sub-distribution and distribution of bulk quantities of electric power

and connection to very large consumers.

• Extra High Voltage (distribution) – over 230 kV, up to about 800 kV, used for long distance, very high

power transmission.

• Ultra High Voltage – higher than 800 kV.

The proposed Mwachabo Power distribution line is a medium voltage line.

Page 20: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

8

2.6.2 Scope of the project

Distribution lines essentially comprise of an assembly of poles and cross bars on which conductors are

mounted. Detailed specifications inclusive of Bills of Quantities for the proposed Mwachabo Power

distribution line are provided in Appendix 2.1, a brief summary of which is provided in Table 2.1 below.

A 35.3 kilometer 33 kV power distribution line is proposed which implies that, the scheme will comprise

3 lengths of parallel conductors (each 35.3 Km long) mounted on a total of 133 wooden poles of 12-14

m height. The 33 kV power will be stepped down to 0.433 kV through 2 different located transformers

and supplied to consumers through new low voltage distribution lines to be constructed.

Table 2.1: Summary features of the scheme

Scheme/ Proposed alignment Project area Length

(km)

Total No of

poles

Total No of

transformers

Mwachabo Market, Pry/Manoa Disp/

Chunga Unga Market/Dighai Market/

Kamtonga Market/Mkuki Market

Mwatate Constituency-

Taita Taveta County

35.3 133 2

Diverse assembly of pole structures will be used in construction of the target distribution line as

follows:-

• Suspension structures to support the conductor vertically using suspension insulators.

• Strain structures to resist net tension in the conductors and the conductors attach to the

structure through strain insulators.

• Dead-end structures to support the full weight of the conductor and also all the tension in it by

use of strain insulators.

Figure 2.2: Three phase power distribution

2.6.3 Other specifications

Specifications: Conductors comprise the core media through which, power distribution takes place. In

the design of the proposed TL, the Wolf Conductor is preferred on account of higher efficiency of

distribution, thus resulting in lower losses of energy and cumulative un-served energy. The conductors

Page 21: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

9

recommended for the various sub-project options are Aluminum Conductor Steel Reinforced (ACSR)

“Wolf” and “Lynx” conductors which are in accordance with Kenya’s Standards. The technical particulars

of conductors are as specified in Appendix 2.1 below.

Conductor configuration: The current practice in constructing power distribution lines in Kenya is to use

flat configuration conductors which results in shorter poles with a modest cost saving compared to the

typical triangular configuration with the three phases on three levels. For distribution lines longer than

100 kilometres, a full transposition (three sections) of the three phases is recommended due to the

impedance asymmetry resulting in a corresponding voltage and current imbalance at the end of the

distribution line.

2.6.4 Land requirement by the distribution lines

The practice of the REA is to require a way leave corridor of equivalent to 10m width on either side of

the center line for 33 kV power distribution lines. Along the 20m wide corridor, an appropriate clearance

between conductors and vegetation and structures needs be maintained which requires that houses and

trees in excess of 7.5 metres are removed for the entire life of the distribution line. However, farming

and grazing within the corridor is generally permitted.

2.6.5 Project activities

Towards development of the distribution lines, activities are anticipated as follows:-

Design works: A technical design package for the proposed power distribution line has already been

prepared by REA.

Construction activity: Site preparation will involve manual clearing in holing areas and lopping of tall

vegetation to allow laying of conductors. Construction will involve delivery of poles, conductors,

insulators and other components of the distribution line. This will be followed by excavation following

which the poles will be erected. The major task will entail mounting of conductors and transformers

following which the project will be commissioned.

Operation phase: Upon powering, the project will then be operated by the Kenya Power Company

alongside other investments in Taita Taveta County. Routine maintenance will also involve securing of

pole foundations against erosion to insure against weakening and collapse of power lines.

2.6.6 Land ownership within route of traverse

As currently aligned, the traverse falls within privately owned lands, road reserves, and urban centers-

the latter of which are controlled by local authorities.

2.7 Total Cost of the Project

A summary of the Project Bills of Quantities is provided in Table 2.2 below. In total, construction of the

power distribution line is expected to cost the sum of Ksh 41,145,666.48. For a 35.3 Km long power

distribution line, this translates to a unit construction cost of Ksh 1.66 million per kilometre.

Page 22: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

10

Table 2.2: Estimated cost of constructing the power distribution line

SN Bill Item Cost (Ksh)

1 Project Survey works 1,207,070.00

2 Provision for Wayleave 0

3 6X50KVA,1X100KVA 33/0.433 KV TX 1,674,782.96

4 S/S Works 1,146,898.83

5 35.3Km of 33kv in 75 sqmm bare ACSR 26,751,351.22

6 720m of Lv 3ph in 100 sqmm bare aa

1045m of Lv Sph in 100 sqmm bare aa

695,437.14

7 6 No. S/L in 25 sqmm 4/c ug cable

6 No. S/L in 25 sqmm 4/c ug cable

309,716.33

8 Per diem, shutdown and press advert 255,000,00

9 Labour & Transport Costs 9,105,410.00

Total Planned Project Cost 41,145,666.48

Page 23: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

11

3 CHAPTER THREE: POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

The proposed Mwachabo Power distribution line project will comply with all Kenyan legal requirements

and the World Bank’s environmental and social safeguards. A brief outline of the operating policy, legal

and administrative framework is provided below.

3.1 Policy Frameworks

3.1.1 Constitutional provisions

Kenya now has a new Supreme law in form of the New Constitution which was promulgated on 27th

August 2010 to take supremacy over all aspects of life and activity in the New Republic. With regard to

environment, Section 42 of the Constitution states as follows:-

In Sections 69 and 70, the Constitution has inter alia identified national obligations in respect of the

environment and enforcement of environmental rights respectively as follows:-

Section 69 (1): The State shall—

(a) Ensure sustainable exploitation, utilization, management and conservation of the

environment and natural resources, and ensure the equitable sharing of the accruing benefits;

(b) Work to achieve and maintain a tree cover of at least ten per cent of the land area of Kenya;

(c) Protect and enhance intellectual property in, and indigenous knowledge of, biodiversity and

the genetic resources of the communities;

(d) Encourage public participation in the management, protection and conservation of the

environment;

(e) Protect genetic resources and biological diversity;

(f) Establish systems of environmental impact assessment, environmental audit and monitoring

of the environment;

(g) Eliminate processes and activities that are likely to endanger the environment; and

(h) Utilize the environment and natural resources for the benefit of the people of Kenya.

(2) Every person has a duty to cooperate with State organs and other persons to protect and conserve

the environment and ensure ecologically sustainable development and use of natural resources.

Section 70 provides for enforcement of environmental rights thus:-

(1) If a person alleges that a right to a clean and healthy environment recognized and protected under

Article 42 has been, is being or is likely to be, denied, violated, infringed or threatened, the person may

Page 24: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

12

apply to a court for redress in addition to any other legal remedies that are available in respect to the

same matter.

(2) On application under clause (1), the court may make any order, or give any directions, it considers

appropriate:-

(a) To prevent, stop or discontinue any act or omission that is harmful to the environment;

(b) To compel any public officer to take measures to prevent or discontinue any act or omission

that is harmful to the environment; or

(c) To provide compensation for any victim of a violation of the right to a clean and healthy

environment.

Essentially, the new constitution has embraced and provided further anchorage to the spirit and letter

of EMCA 1999 whose requirements for environmental protection and management have largely

informed Sections 69 through to 71 of the Document. In Section 72 however, the new constitution

allows for enactment of laws towards enforcement of any new provisions of the Supreme Law.

3.1.2 Other GOK Policies relevant to environmental conservation

(i) Kenya Vision 2030

Kenya Vision 2030 is the current national development blueprint for the period 2008 to 2030 and was

developed following on the successful implementation of the Economic Recovery Strategy for Wealth

and Employment Creation which saw the country’s economy back on the path to rapid growth since

2002. The objective of the Vision 2030 is to transform Kenya into a middle income country with a

consistent annual growth of 10 % by the year 2030. The 2030 goal for equity and poverty elimination is

to reduce the number of people living in absolute poverty to the tiniest proportion of the total

population. Kenya will aim at a society that guarantees equality of opportunity in accessing public

services and providing income-generating activities as widely as possible.

The level and intensity of commercial energy use in a country is a key indicator of the degree of

economic growth and development and Vision 2030 identifies energy as one of the infrastructural

enablers of the three “pillars” of the Vision. Kenya is therefore expected to use more energy in the

commercial sector on the road to 2030 since, as incomes increase and urbanization intensifies,

household demand for energy will also rise. Preparations have been made to meet this growth in

demand for energy under the Vision.

At the national level, wood fuel and other biomass account for about 68% of the total primary energy

consumption, followed by petroleum at 22%, electricity at 9% and others including coal at about less

than 1%. Solar energy is also extensively used for drying and, to some extent, for heating and lighting.

Electricity remains the most sought after energy source by Kenya society and access to electricity is

normally associated with rising or high quality of life. However, its consumption in Kenya is extremely

low at 121 kilowatt hours (khw) per capita (compared to 503khw in Vietnam or 4,595khw for South

Africa) and national access rate at about 15%. The access rate in the rural areas is estimated at 4%.

Page 25: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

13

Towards reversing this scenario, more resources are being invested towards power generation in

tandem with concerted efforts in policy and institutional reforms to bring in new service providers.

With regard to environmental quality, Vision 2030 anticipates a Kenyan nation characterised by a clean,

secure and sustainable environment by 2030 and sets the goals for 2012 as ;-(i) to increase forest cover

from less than 3% at present to 4%; and (ii) to lessen by half all environment-related diseases. Specific

strategies will involve promoting environmental conservation in order to provide better support to the

economic pillar flagship projects and for the purposes of achieving the Millennium Development Goals

(MDGs); improving pollution and waste management through the design and application of economic

incentives; and the commissioning of public-private partnerships (PPPs) for improved efficiency in water

and sanitation delivery. Kenya will also enhance disaster preparedness in all disaster-prone areas and

improve the capacity for adaptation to global climatic change. In addition, the country will harmonise

environment-related laws for better environmental planning and governance.

(ii) Sessional Paper No. 3 of 2009 on National Land Policy

The National Land Policy was formulated with the aim of securing rights over land and provide for

sustainable growth, investment and reduction of poverty in line with Government overall development

objectives. The policy will offer a framework of policies and laws designed to ensure the maintenance of

a system of land administration and management that will provide:

(a) All citizens with opportunity to access and beneficially occupy and use land;

(b) Economically viable, socially equitable and environmentally sustainable allocation and use of

land;

(c) Efficient, effective and economical operation of land markets;

(d) Efficient and effective utilization of land and land-based resources; and

(e) Efficient and transparent land dispute resolution mechanisms.

(iii) Sessional Paper No 1 of 1996 on Environment and Development:

Sessional Paper No 1 of 1996 is the official statement on national policy on environment and was

released in 1996 following on recommendations of the National Environment Action Plan (NEAP) of

1994. The NEAP Process had been launched earlier on in 1992 following the Country’s participation in

the United Nations Conference on Environment and Development (UNCED) in Rio de Geneiro during

which Kenya alongside other nations became signatory to Agenda 21 which called on all nations to pay

closer attention to environmental management at national level.

Through Sessional Paper No. 1 of 1996, the Kenya Government guarantees every citizen the inalienable

right to a clean and healthy environment and commits to pursue a policy strategy of integrating

environmental sensitivity into national development planning process and sets broad policy objectives

as follows:-

• Optimal use of natural land and water resources in improving the quality of human

environment;

Page 26: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

14

• Sustainable use of natural resources to meet the needs of the present generations while

preserving their ability to meet the needs of future generations;

• Integration of environmental conservation and economic activities into the process of

sustainable development;

• Meeting of national goals and international obligations by conserving bio-diversity, arresting

desertification, mitigating effects of disasters, protecting the ozone layer and maintaining an

ecological balance on earth.

Among other provisions, Sessional Paper No. 1 of 1996 also sets out sectoral priorities for environmental

sustainability which in most cases have been operationalised through formulation of guidelines for

quality and environmental management in respective sectors. A National Environmental Law (EMCA,

1999) has since been enacted to secure implementation of the national policy on environment.

3.1.3 World Bank’s Safeguard Policies (WBSGPs)

By virtue of source of funding, the proposed development of TLs by REA is also subject to World Bank

requirements for impact assessment. As such, Project Report study has been formulated to address and

cater for both Kenyan and World Bank requirements for impact assessment. World Bank projects and

activities are governed by Operational Policies, which are clearly spelt out in the Bank's Operational

Manual ("Bank Procedures" and "Good Practices"). The World Bank’s safeguard policies are designed to

ensure that projects proposed for Bank financing are environmentally and socially sustainable. These

operational policies include:

• OP 4.01 Environmental Assessment;

• OP 4.04 Natural Habitats;

• OP 4.09 Pest Management;

• OP 4.33 Cultural Heritage;

• OP 4.12 Involuntary Resettlement;

• OP 4.10 Indigenous People;

• OP 4.36 Forests;

• OP 4.37 Safety of Dams;

• OP 7.50 Projects on International Waterways ;

• OP 7.60 Projects in Disputed Areas.

An analysis of possible triggers of the WB SGPs by the proposed Mwachabo power distribution line

(table 3.1 below) indicates that the project is likely to trigger 3 out of 10 policy safeguards out of which,

displacement of human settlements and clearing of biodiversity to give way for distribution lines is likely

to be the most severe. In sections below, a highlight of requirements of the 3 SGPs likely to be triggered

is briefly provided. For a full description of all WB safeguard policies, the reader is referred to

www.worldbank.org.

The Environmental and Social Impact Assessment process in respect of the proposed distribution line

has also taken cognizance of upcoming World Bank Policies namely;- (i) Interim Guidance Note on land

use planning recently unveiled by the Operations Policy and Country Services Quality Assurance and

Compliance Unit and the Legal Department Environmental and International Law Unit; and (ii), The

Environmental Health and Safety Guidelines (www.ifc.org/ifcext/sustainability.nsf/

Page 27: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

15

Content/Environmental Guidelines). None of these safeguards are however triggered by the proposed

power distribution line. In sections below, brief commentaries on both OP 4.10 and Op 4.12 are

provided.

Table 3.1: Analysis of potential triggers to World Bank safeguards policies

World Bank Safeguard

policy

Triggers Trigger mechanism

Environmental

Assessment

(OP 4.01)

Triggered Project is category B and has to undergo mandatory Environmental

and Social Impact Assessment in line with OP 4.01

Natural Habitats (OP 4.04) Triggered The project will not support or lead to the conversion of natural

habitats, and the ESMF forbids any project activities inducing

significant conversion or degradation of critical natural habitats.

Appropriate mitigation measures will be followed to limit the impact

on local fauna, avi-fauna and to protect indigenous plant and tree

species along the low voltage line.

Forestry (OP 4.36) No Trigger The construction of low voltage distribution lines will not lead to the

significant degradation and conversion of critical forest areas and

forest ecosystems.

Pest Management (OP

4.09)

No trigger Project does not entail Pest Management or any use of chemicals

Cultural Property

(OP11.03)

No trigger Although it is not expected that the project will affect resources of

physical, cultural, and/or historical importance, a chance finds

procedure will be inserted into construction contracts , and

Museums of Kenya authorities will be notified if chance finds are

made

Indigenous Peoples (OP

4.10)

No Trigger There are no known IPs in the route of traverse

Involuntary Resettlement

(OP 4.12)

Triggered Some trees will be removed to create the ROW. Compensation at

present replacement value based on market assessment will be

made for these trees.

Safety of Dams (OP 4.37) No Trigger Project will not involve construction of dams

Projects on International

Waters (OP 7.50)

No trigger No project activities are planned for in

International Waters

Projects in Disputed Areas

(OP.60)

No Trigger There are no sites classified as disputed in the project area.

Total triggers 3

(i) Environmental Assessment (OP 4.01)

OP 4.01 requires Environmental Assessment (EA) for projects proposed for Bank financing to ensure that

they are environmentally sound and sustainable, and as a basis for decision making. Under OP 4.01

projects are screened and assigned either of four categories each of which requires different levels of

environmental assessment as follows:-

• Category A: A proposed project is classified as Category A if it is likely to have significant adverse

environmental impacts that are sensitive, diverse, or unprecedented. These impacts may affect an

area broader than the sites or facilities subject to physical works.

Page 28: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

16

• Category B: A proposed project is classified as Category B if it’s potential adverse environmental

impacts on human populations or environmentally important areas—including wetlands, forests,

grasslands, and other natural habitats—are less adverse than those of Category A projects. These

impacts are site-specific; few if any of them are irreversible; and in most cases mitigation measures

can be designed more readily than for Category A projects.

• Category C: A proposed project is classified as Category C if it is likely to have minimal or no adverse

environmental impacts. Beyond screening, no further EA action is required for a Category C project.

• Category FI: A proposed project is classified as Category FI if it involves investment of Bank funds

through a financial intermediary in subprojects that may result in adverse environmental impacts.

Although the project will have a positive impact on the environment overall, by improving the supply of

energy in rural areas of Kenya, thereby reducing the use of fossil fuels for domestic consumption, and

the use of firewood, OP/BP 4.01 is triggered because the physical interventions resulting from the

implementation of investments could have low to moderate negative impacts on the environment. The

Project is classified as Category B- a project with environmental impacts that are easily identified and

mitigated-requiring a partial environmental assessment. As such, this Project Report prepared in line

with requirements of LN 101 of EMCA is deemed sufficient to meet all requirements for environmental

assessment for this project category.

(ii) Involuntary Resettlement (OP 4.12)

OP 4.12 requires that a Resettlement Action Plan (RAP) be prepared for all projects that

anticipate displacement of both settlements and livelihoods. The policy aims to avoid involuntary

resettlement to the extent feasible, or to minimize and mitigate its adverse social and economic

impacts.

(iii) Operational Policy 4.04 on Natural Habitats seeks to ensure that World Bank-supported

infrastructure and other development projects take into account the conservation of biodiversity, as

well as the numerous environmental services and products which natural habitats provide to human

society. The policy strictly limits the circumstances under which any Bank-supported project can damage

natural habitats (land and water areas where most of the native plant and animal species are still

present). Specifically, the policy prohibits Bank support for projects which would lead to the significant

loss or degradation of any Critical Natural Habitats, whose definition includes those natural habitats

which are legally protected, officially proposed for protection, or unprotected but of known high

conservation value.

Given that the proposed Mwachabo power distribution line will traverse areas through which wildlife

disperse to and from the Tsavo West National Park, this SGP remains relevant. The proposed project will

be screened critically against requirements of this policy.

Modalities for harmonizing requirements of both the WB SGPs and GOK legal framework

Experience has shown that both OP 4.01 of the World Bank and EMCA 1999 are generally aligned in

principle and objective in that:-

Page 29: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

17

• Both require Environmental Assessment before project implementation leading to development

of comprehensive Environmental and social Management plans to guide resolution of social and

environmental impacts as anticipated.

• Both require public disclosure of Environmental and Social Impact Assessment and stakeholder

consultation during preparation,

• While OP 4.01 of World Bank stipulates different scales of Environmental and Social Impact

Assessment for different category of projects, EMCA requires Environmental and Social Impact

Assessment for all sizes of projects, which are required to be scoped as relevant

• Where EMCA requires consultation of Lead Agencies comprising of relevant sectors with legal

mandate under GoK laws, the WB has equivalent safeguards for specific interests.

• The Bank requires that stakeholder consultations be undertaken during planning,

implementation and operation phases of the project which is equivalent to the statutory annual

environmental audits at the operation phase of projects in Kenya.

A major guiding principle in this study is that pursuit of an in-depth Project Report process as stipulated

by EMCA 1999 is adequate to address all World Bank requirements for environmental and social

assessment. I

3.2 The Legal Framework for Environmental Management in Kenya

The Environmental Management and Coordination Act (EMCA) No. 8 of 1999 is the supreme

environmental law which lays out the legal and institutional framework for environmental management

in Kenya. The statute was enacted in 2000 with a view to harmonizing environmental legislation

previously scattered in 77 national laws. Under EMCA, provisions and safeguards for environmental

management have been put in place as follows:-

3.2.1 Provision of an Institutional Framework

In 2001, the Government established the administrative structures to implement EMCA, 1999 as

follows:-

The National Environment Council: The National Environment Council (the Council) is responsible for

policy formulation and directions for the purposes of EMCA 1999. The Council also sets national goals

and objectives and determines policies and priorities for the protection of the environment.

The National Environmental Management Authority: EMCA 1999 allows for formation of the National

Environmental Management Authority (NEMA) as the body charged with overall responsibility of

exercising general supervision and co-ordination over all matters relating to the environment and to be

the principal instrument of government in the implementation of all policies relating to the

environment. Under the Act, NEMA was established in 2001 when the first Director General was

appointed by the President.

Activities of NEMA are rolled out through three core directorates in charge of Enforcement, Education

and Policy. This is the institutional framework under which this Project Report process will be regulated

and processed to conclusion.

Page 30: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

18

Public Complaints Committee: Under EMCA 1999, a Public Complaints Committee has been established

to provide an administrative mechanism for addressing environmental harm. The Committee whose

membership include representatives from the Law Society of Kenya, NGOs and the business community

has the mandate to investigate complaints relating to environmental damage and degradation.

3.2.2 EMCA requires Environmental Impact Assessment for new projects

Section 58 of EMCA requires that an Environmental Impact Assessment (EIA) Study precede all

development activities proposed to be implemented in Kenya. The Act further requires that EIA studies

so designed, be executed in accordance with the Guidelines for Conduct of EIAs and Environmental

Audits (Kenya Gazette Supplement No. 56 of 13th

June 2003) as published by the National Environmental

Management Authority (NEMA). The Second Schedule of EMCA specifies the nature of projects that

should undergo Environmental and Social Impact Assessment. Under EMCA however, all projects

irrespective of size are to be subjected to Environmental and Social Impact Assessment studies. Under

electricity infrastructure, the Second Schedule identifies the following candidate projects as meriting

Environmental and Social Impact Assessment Studies:-

• Electricity generation stations,

• Electrical distribution lines;

• Electrical substations;

• Pumped storage schemes; have been specified as projects to be subjected to EIA.

The Project Report for the proposed Mwachabo power distribution line project has thus been designed

and conducted in response to this legal requirement and has also taken cognizance of other legal

instruments under EMCA as outlined elsewhere below in this report.

3.2.3 EMCA provides for gazzettment of Environmental Regulations

Under EMCA 1999, guidelines for environmental management have been promulgated through diverse

regulations. We highlight a few of the said regulations against which the proposed development of a

132kV power distribution line will be screened and harmonized.

Environmental (Impact Assessment and Audit) Regulations, 2003 (Legal Notice 101- Kenya Gazette

Supplement No. 56 of 13th

June 2003): The Regulations, 2003, stipulate procedures for carrying out

Environmental Impact Assessments (EIAs) and Environmental Audits (EAs). Regulation 3 states that “the

Regulations should apply to all policies, plans, programmes, projects and activities specified in Part IV,

Part V and the Second Schedule of the Act. Regulation 4(1) further states that: ‘‘…no proponent should

implement a project………

i) Likely to have a negative environmental impact; or

ii) For which an environmental impact assessment is required under the Act or these Regulations;

unless an environmental impact assessment has been concluded and approved in accordance with

these Regulations…’’.

Page 31: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

19

Among other requirements, these guidelines also prescribe the format and content of Project Reports.

LN 101 further sets out the schedule of EIA Fees payable to NEMA by project proponents. 1

Environmental Management and Co-ordination Act (Waste Management) Regulations 2006: These are

described in Legal Notice No. 121 of the Kenya Gazette Supplement No. 69 of September 2006. These

Regulations apply to all categories of waste as provided in the Regulations. These include:

• Industrial wastes;

• Hazardous and toxic wastes;

• Pesticides and toxic substances;

• Biomedical wastes;

• Radio-active substances.

These regulations outline requirements for handling, storing, transporting, and treatment / disposal of

all waste categories as provided therein.

Environmental Management and Coordination Act (Water Quality) Regulations 2006: These are

described in Legal Notice No. 120 of the Kenya Gazette Supplement No. 68 of September 2006. These

Regulations apply to drinking water, water used for agricultural purposes, water used for recreational

purposes, water used for fisheries and wildlife and water used for any other purposes. This includes the

following: Protection of sources of water for domestic use; Water for industrial use and effluent

discharge; Water for agricultural use. These Regulations outline:

• Quality standards for sources of domestic water;

• Quality monitoring for sources of domestic water;

• Standards for effluent discharge into the environment;

• Monitoring guide for discharge into the environment;

• Standards for effluent discharge into public sewers;

• Monitoring for discharge of treated effluent into the environment.

Conservation of Biological Diversity (BD) Regulations 2006: Legal Notice No. 160 of the Kenya Gazette

Supplement No. 84 of December 2006 applies to conservation of biodiversity which includes

conservation of threatened species, Inventory and monitoring of BD and protection of environmentally

significant areas, access to genetic resources, benefit sharing and offences and penalties. The route of

traverse has not been mapped for biodiversity as required by these regulations. However, from

investigations undertaken as part of this study, it was observed that the proposed line will largely

traverse agricultural settlements where the original natural vegetation has been replaced by crops and

the likelihood of occurrence of indigenous biodiversity is quite low. This regulation is that not likely to be

triggered.

1 LEGAL NOTICE NO 30 of EMCA (dated 11th February, 2009) - THE ENVIRONMENTAL (IMPACT ASSESSMENT AND AUDIT)

(AMENDMENT) REGULATIONS, 2009 sets new EIA Fees schedules as follows:-

1. These Regulations may be cited as the Environmental (Impact Assessment and Audit) (Amendment) Regulations, 2009.

2. The Environmental (Impact Assessment and Audit) Regulations, 2003, are amended in the Fifth Schedule by deleting item 4 and

substituting therefore the following new item –

“4. Environmental Impact Assessment licence-0.05% of the total cost of the project, to the minimum of KSh. 10,000 and maximum of

KSh. 1,000,000 payable as follows:

(a) 50% of the 0.05% being Processing Fee Payable upon submission of a project report;

(b) 50% of the 0.05% being licence fee payable upon collection of the Environmental Impact Assessment Licence”.

Page 32: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

20

National Sand Harvesting Guidelines, 2007: These Guidelines apply to all sand harvesting activities in

Kenya to ensure sustainable utilization of the sand resource and proper management of the

environment. Among Key features, the guidelines empower respective DECs to regulate sand harvesting

within areas of jurisdiction implying that, sand should only be sources from approved sites and by

approved dealers.

Guidelines on Noise level: NEMA has recently issued draft guidelines on ambient noise levels. In

conformity to these guidelines, the Environmental and Social Impact Assessment will formulate

measures to ensure that; - the Contractor keeps noise level within acceptable limits and construction

activities shall, where possible, be confined to normal working hours in the residential areas; schools,

dispensaries and other noise sensitive areas shall be notified by the Contractor at least 5 days before

construction is due to commence in their vicinity. Under all conditions, the Contractor must adhere to

the Noise Prevention and Control Rules of April 2005.

3.2.4 EMCA requires inter-sectoral coordination

In recognition that EMCA is an umbrella law coordinating diverse sectoral statutes all of which are still in

force, Legal Notice 101 of EMCA identifies and designates all GOK Agencies with legal mandates over

specific sectors to be Lead Agencies for purposes of Environmental Impact Assessment. LN 101 of EMCA

further requires that the respective sectors be consulted as Lead Agencies in making decisions

pertaining to environmental assessment for projects in respective sectors. This is to ensure that NEMA

does not approve projects that contradict sector policies and legislation.

As part of this Project Report process, an analysis of Kenyan laws considered relevant to development

and operation of power distribution lines was undertaken following which, sectoral triggers were

identified as outlined below.

(i) The Environment and Land Court Act No.19 of 2011:

This law was assented to on 27th

August, 2012 and commenced on 30th August, 2033to give effect to

Article 162(2)(b) of the Constitution; to establish a superior court to hear and determine disputes

relating to the environment and the use and occupation of, and title to, land, and to make provision for

its jurisdiction functions and powers, and for connected purposes. Section 13 (1) of the Act gives the

Court original and appellate jurisdiction to hear and determine all disputes in accordance with Article

162(2)(b) of the Constitution and with the provisions of this Act or any other written law relating to

environment and land. In exercise of its jurisdiction under Article 162 (2) (b) of the Constitution, the

Court shall have power to hear and determine disputes relating to environment and land, including

disputes:-

(a) relating to environmental planning and protection, trade, climate issues, land use planning,

title, tenure, boundaries, rates, rents, valuations, mining, minerals and other natural resources;

(b) Relating to compulsory acquisition of land;

(c) Relating to land administration and management;

(d) relating to public, private and community land and contracts, choses in action or other

instruments granting any enforceable interests in land; and

(e) any other dispute relating to environment and land.

Page 33: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

21

This statute is deemed relevant to all development proposed for i9mplementatiopn in Kenya as it

provides for legal recourse for disputes relating to environment and land. This is a law that any

developer including the REA should familiarize with.

(ii) The Energy Act of 2006:

Section (4) of the Energy Act 2006 establishes the Energy Regulatory Commission with a mandate under

Section 6 of the Energy Act as follows:-

i) to formulate, enforce and review environmental, health, safety and quality standards for the

energy sector, in coordination with other statutory authorities; and,

ii) To enforce and review regulations, codes and standards for the energy sector.

Thus, under Section 6 of the Energy Act, the ERC has full mandate to ensure environmental protection

within the energy sector in the capacity of de jure Lead Agency. Further, Section 30(1) and (2) of the

Energy Act 2006 requires that ‘The Commission shall, in granting or rejecting an application for a licence

or permit, take into consideration;- (i) the impact of the undertaking on the social, cultural or

recreational life of the community; and (ii), the need to protect the environment and to conserve the

natural resources in accordance with the Environmental Management and Coordination Act of 1999.

This Project Report process has partly been undertaken in fulfillment of requirements of the Energy Act

and indeed, the final output will be reviewed by the ERC in the capacity of Lead Agency.

(iii) Roads Act 2007:

The core feature of the Kenya Roads Act 2007 which came into effect in September 2007 was the

creation of Three autonomous Authorities (KeNHA), KeRRA and KURA) to take care of National, Rural

and Urban Roads respectively. Sections 3(2) (b), 4(2) (b) and 10(2) (b) are quite relevant to development

and operation of power distribution lines as they place all road reserves under the respective

jurisdictions of KeNHA, KeRRA and KURA depending on the category of the road. In essence, any

infrastructure service provider intending to utilize a road reserve will require consent of the respective

road authority. Further, under Section 27, the respective road authority has power to cause relocation

of infrastructure from the road reserve thus:-

(2) Where any infrastructure utility is located within a road reserve, the provider or operator of such

infrastructure utility shall, upon written request by the responsible Authority, relocate such infrastructure

utility to a location or alignment approved by the Authority at no cost to the Authority.

(3) Where an Authority intends to exercise any power under subsection (2) it shall give reasonable notice

of its intention to do so to the person having control of such infrastructure utility, and such person shall

cause to be removed such infrastructure utility within sixty days.

(4) Where, under subsection (2) or (3), any person having control of an infrastructure utility fails to

remove such infrastructure utility within the time stated in the notice, the concerned Authority may

remove such infrastructure utility at the cost of the person who was unable to comply with the notice

under subsection (3).

Page 34: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

22

Given the provisions of the Roads Act 2007, it is important that all developers targeting to use road

reserves to liaise closely with the relevant road authorities. The same position was articulated during

consultations with KeNHA and KeRRA undertaken as part of this study.

(iv) The Agriculture Act, Cap 318:

This statute seeks to promote and maintain a stable agriculture, to provide for the conservation of the

soil and its fertility and to stimulate the development of agricultural land in accordance with the

accepted practices of good land management and good husbandry. This Act primarily guides and

regulates farming practices. The Agriculture Act is the principal land use statute covering, inter-alia, soil

conservation and agricultural land use in general.

In 2009, the Minister for Agriculture gazetted The Agriculture (Farm Forestry) Rules, 2009 with the

objective and purpose of promoting and maintaining farm forest cover of at least 10 per cent of every

agricultural land holding and to preserve and sustain the environment in combating climate change and

global warming.

Rule 5 (1) requires every person who owns or occupies agricultural land shall establish and maintain a

minimum of 10 percent of the land under farm forestry which may include trees on soil conservation

structures or rangeland and cropland in any suitable configurations; provided that the species of trees or

varieties planted shall not have adverse effects on water sources, crops, livestock, soil fertility and the

neighborhood and should not be of invasive nature.

Rule 6 allows an inspector to take action within area of jurisdiction to ensure that land owners and

occupiers comply with requirements of rule 5 above. Regulation 10 on harvesting of farm trees requires

the following:

(1) Every land owner or occupier shall ensure that harvesting of trees shall be done in such a

manner as to maintain a 10 per cent tree cover at all times, with large scale harvesting requiring

a harvesting plan as governed by the provisions of the Forest Act No. 7 of 2005.

(2) The District Agricultural Committee shall establish mechanisms to facilitate the process of

notification and approval for ease of harvesting by land owners or occupiers.

(3) A person shall not harvest trees from a farm forest without notification and approval as

provided for in paragraph (2).

(4) Harvesting, processing and movement of farm forest products for commercial purposes shall

be governed by the provisions of the Forest Act, No. 7 of 2005.

From this analysis, it is apparent that a new approach to treatment of on-farm trees has been

established. As such, contrary to past practices, contractors contemplating removal of farm trees to

create way leaves will require authority from the District Agricultural committees.

(v) The Lands Act No. 6 of 2012:

The Land Act was enacted by Parliament to give effect to Article 68 of the Constitution, to revise,

consolidate and rationalize land laws; to provide for the sustainable administration and management of

land and land based resources, and for connected purposes. The Act applies to all land declared as (a)

Page 35: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

23

public land under Article 62 of the Constitution; (b) private land under Article 64 of the Constitution; and

(c) community land under Article 63 of the Constitution and any other written law relating to community

land.

The Land Act guarantees security of tenure for land under (a) freehold; (b) leasehold; (c) such forms of

partial interest as may be defined under the Act and other law, including but not limited to easements;

and (d) customary land rights, where consistent with the Constitution and guarantees equal recognition

and enforcement of land rights arising under all tenure systems and non-discrimination in ownership of,

and access to land under all tenure systems.

Under the Lands Act 2012, The Way leaves Act, Cap 292 and The Land Acquisition Act, Cap. 295 have

been revoked but Sections 8 and 9 allow for Compulsory Acquisition as an option in acquiring land for

public utility.

(vi) The Land Registration Act, No. 3 of 2012:

The Land Registration Act (LRA), 2012was assented to on 27th April, 2012 and commenced on 2nd May,

2012 with the objective and purpose of revising, consolidating and rationalizing the registration of titles

to land to give effect to the principles and objects of devolved government.

Sections 18 to 21 of the LRA 2012 deal with establishment and maintenance of boundaries to land.

Section 21(1) is relevant to development of power distribution lines in it that it criminalizes interference

with boundaries thus;- Any person who defaces, removes, injures or otherwise impairs a boundary

feature or any part of it unless authorized to do so by the Registrar commits an offence and is liable on

conviction to imprisonment for a term not exceeding two years or to a fine not exceeding two hundred

thousand shillings or to both.

Under the LRA 2012, Statutes previously related to land property namely;- The Indian Transfer of

Property Act 1882, The Government Lands Act, (Cap 280), The Registration of Titles Act, (Cap 281), The

Land Titles Act, (Chapter 282) and The Registered Land Act, (Cap. 300) now stand repealed.

(vii) The Physical Planning Act (Cap 286):

This Act provides for the preparation and implementation of physical development plans for connected

purposes. It establishes the responsibility for the physical planning at various levels of government

mainly the District Level. The Act provides for a hierarchy of plans in which guidelines are laid down for

the future physical development of areas referred to in the specific plan. The intention is that the three-

tier order plans, the national development plan, regional development plan, and the local physical

development plan should concentrate on broad policy issues. The Act also advocates for public

participation in the preparation of plans and requires that proper consideration be given to the potential

for economic and social development.

This Project Report study has confirmed that planning of the RE Projects under KEEP has taken account

of regional development plans and will specifically seek to utilize existing way leaves. Public

consultations have been undertaken as part of this study to ensure that sectoral policies and strategies

are adhered to in course of developing the power lines.

(viii) Local Government act Cap 265:

Page 36: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

24

A principal target of the REA component of KEEP is to electrify market centres which are created and

governed under Cap 265. Specifically, under Cap 265, LA have planning jurisdiction and control for all

land under the Authorities area. As such, any development targeting use of any land under LAs will

require consent as appropriate. The same should apply to use of any way leaves under the jurisdiction of

a county council.

Cap 265 also empowers LAs to act in the protection of the environment. This Act empowers the

Municipal Authority to provide and maintain sanitation and sewerage services and to take measures to

control or prohibit factories and industries from emitting smoke, fumes, chemicals, gases, dust, smell,

noise, vibrations or any danger, discomfort or annoyance to the neighbourhood and to control

disinfections particularly using cyanide. They are empowered to punish those disrupting sanitation or

sewerage lines and can compel owners to construct sewage line into the systems and drainages.

(ix) The Occupation Health and Safety Act 2007:

This is an Act of Parliament to provide for the safety, health and welfare of workers and all persons

lawfully present at workplaces, to provide for the establishment of the National Council for

Occupational Safety and Health and for connected purposes. The Act has the following functions among

others:-

• Part VI of the Act gives the requirements for occupational health provisions which include

cleanliness, ventilation, overcrowding, etc.

• Part VII of the Act contains provisions for the safe operation of machinery and includes all prime

movers and distribution equipment. Additionally this part includes the safe operation of cranes,

chains, ropes, lifting tackles, pressure vessels and their statutory examination by DOHSS

Approved Persons.

• Part VIII of the Act contains provisions for general safety of a workplace especially fire safety.

This part of the Act will apply to the proposed project during the design, construction and

operational phases respectively of the project.

• Part IX of the Act deals with Chemical Safety. This will not be applicable to the proposed project

as it will not handle and transport hazardous materials.

• Part X of the Act deals with the General Welfare conditions that must be present during the

operational phase of the project. Such conditions include first aid facilities, supply of drinking

water, etc.

• Part XI of the Act contains Special Provisions on the management of health, safety and welfare.

These include work permit systems, PPE requirements and medical surveillance. All sections of

this part of the Act will be applicable to the proposed project during the operational phase.

Section 8.2 of this Project Report has outlined clear modalities to be followed by contractors towards

mitigating/minimizing/avoiding occupational health and safety hazards.

(x) The Wildlife (Conservation and Management) Act (Cap 376):

This principal Act regulates wildlife conservation and management in Kenya. The Act establishes Kenya

Wildlife Service (KWS) as the implementing agency. Under section 9 and subsection 3A, the functions of

KWS are stated among others as: to provide advice to the government and local authorities and

landowners on the best methods of wildlife conservation and management and authority to ensure

viability of conservation areas. Furthermore, the Minister responsible for wildlife has discretionary

Page 37: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

25

powers to promulgate such regulations to enhance the management of such conservation areas, so long

as the regulations so promulgated are reasonable and not ultra vires to the parent Act.

Investigations conducted within the route of traverse revealed that, there are per se, no areas

controlled by the KWS under Cap 376. However, Mwachabo location comprises an import ant dispersal

area for wildlife moving from the Shimba Hills National Park in the South to the Tsavo West National

Park efforts will be made to minimize damage to wildlife habitat especially trees which are crucial for

maintaining minimum viable populations.

(xi) The Forests Act 2005:

The Forests Act 2005 repealed Cap 385 of the Laws of Kenya and provides for the establishment, control

and regulation of forests. The Act confers powers on the Minister responsible of Forests to set aside

specific areas for the conservation of fauna and flora, for the management of water catchments,

prevention of soil erosion or for the protection and management of indigenous forests on alienated

Government land. Such forest land includes those formerly gazetted under Cap 385, thus essentially

putting the control of all Kenyan forests under a single statute.

The Forests Act 2005 makes illegal, any alienation of gazetted forest land for any purposes considered

contradictory to the dictum of conservation, requiring that, such proposals to be debated and approved

by Parliament, after completion of a comprehensive Environmental and Social Impact Assessment Study.

Further, towards operationalizing the Forests Act 2005, the KFS has gazetted forest rules namely:- The

Forest (Harvesting)Rules, 2009; The Forest (Charcoal making) Rules, 2009; and, The Forest (Participation

in sustainable management) Rules, 2007 but in our view, nothing in the proposed power distribution

line occasions triggers to either the parent law or its subsidiary legislation. However, as observed

elsewhere above in this report, the main trigger is likely to be in the Farm Forestry Rules gazetted under

Cap 318.

(xii) Occupiers Liability Act (Cap. 34) revised 2009

Rules of Common Law regulates the duty which an occupier of premises owes to his visitors in respect of

danger and risk due to the state of the premises or to things omitted or attributes an affliction on

his/her health to a toxic materials in the premises. In additional to creation of a way leave, the REA

working with local leadership will mount a public sensitization programme to ensure that people are

aware of the hazards posed by presence of powered distribution lines.

(xiii) Penal Code (Cap.63)

The Act makes it criminal for anybody to pollute common resources such as air, public water supply,

acoustic quality, etc and stipulates fines for diverse offences.

The EMP prepared as part of this Project Report has identified nuisances as potential adverse impacts of

the project and has recommended activities towards mitigation/ minimization/ avoidance of nuisances

arising from the project activities.

(xiv) The Standards Act Cap 496

The Act is meant to promote the standardization of the specification of commodities, and to provide for

the standardization of commodities and codes of practice; to establish a Kenya Bureau of Standards, to

define its functions and provide for its management and control. Code of practice is interpreted in the

Act as a set of rules relating to the methods to be applied or the procedure to be adopted in connection

Page 38: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

26

with the construction, installation, testing, sampling, operation or use of any article, apparatus,

instrument, device or process.

The Act contains various specifications touching on electrical products and the Proponent shall ensure

that commodities and codes of practice utilized in the project adhere to the provisions of this Act.

(xv) Public Roads and Roads of Access Act (Cap. 399)

Sections 8 and 9 of the Act provides for the dedication, conversion or alignment of public travel lines

including construction of access roads adjacent lands from the nearest part of a public road. Sections 10

and 33 allow for notices to be served on the adjacent land owners seeking permission to construct the

respective roads. The proponent has confirmed to this study that no new access roads will be opened up

and the project will rely on existing roads.

(xvi) The Coast Development Authority Act No 6 of 1989 (Cap 444):

The Coast Development Authority Act was enacted in 1989 and commenced on January 18th

, 1999

expressly to provide for the establishment of the Coast Development Authority (CDA) to plan and co-

ordinate the implementation of development projects in whole of the Coast Province and the exclusive

economic zone and for connected purposes. Under Section 8, the CDA Act outliners function of the CDA

as follows:-

a) to plan for the development of the Area and initiate project activities identified from such planning

in the development and through the Government generally;

b) to develop an up-to-date long range development plan for the Area;

c) to initiate such studies, and carry out such surveys of the Area as may be considered necessary by

the Government or the Authority, and to assess alternative demands within the Area on the natural

resources thereof, and initiate, operate, or implement such projects as may be necessary to exploit

those natural resources including agriculture (both irrigated and rain fed), forestry, wildlife and

tourism industries, electric power generation, mining, and fishing, and to recommend economic

priorities;

d) to co-ordinate the various studies of schemes within the Area such that human, water, animal, land

and other resources are utilized to the best advantage and to monitor the design and execution of

planned projects within the Area;

e) to effect a programme of both monitoring and evaluating the performance of projects within the

Area so as to improve such performance and establish responsibility thereof, and to improve future

planning;

f) to co-ordinate the present abstraction and use of natural resources, especially water, within the

Area and to set up effective monitoring of abstraction and usage;

g) to cause and effect the construction of any works deemed necessary for the protection and

utilization, of the water and soils of the Area including hydro-power development for multipurpose

utilization of water resources;

h) to ensure that landowners in the Area undertake all the measures specified by the Authority to

protect the water and soils of the Area;

i) to identify, collect, collate and correlate all such data related to the use of water and other

resources and also economic and related activities within the Area as may be necessary for the

efficient forward planning of the Area;

Page 39: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

27

j) to maintain a liaison between the Government, the private sector and other interested agencies in

the matter of the development of the Area with a view limiting he duplication of effort and ensuring

the best use of the available technical resources;

k) to examine the hydrological effects and the subsequent ecological changes on the development

programmes and evaluate how they affect the economic activities of the persons dependent on

river environment;

l) to implement development projects and programmes whose primary objective is to promote socio-

economic development of the Coast Province in particular and Kenya in general;

m) to plan and liaise with the relevant authorities as necessary in the exploration and development of

the extensive fishing and marine activities an Kenya especially the exclusive economic zone.

The areas targeted for electrification under the current project fall within the planning jurisdiction of the

CDA. Caution therefore has been taken to link the proposed development to the CDA in course of

Stakeholder consultations.

(xvii) The Limitations of Actions Act (Cap. 22)

This Act provides for recognition of squatters and the conditions under which they would have rights for

compensation for loss of land. If squatters have been in occupation of private land for over twelve (12)

years, then they would have acquired rights as adverse possessors of that land as provided under the

Limitation of Actions Act, section 7. Investigations undertaken for this Project Report did not identify any

land users who merited classification as squatters in which case, no further action in respect of this

statute is recommended.

(xviii) The Civil Aviation Act, Cap 394

Under this Act, the Kenya Civil Aviation Authority (KCAA) has to authorize and approve the height of all

proposed masts for purposes of ensuring the safety of flying aircraft over the proposed project area.

However, investigations conducted under this study did not come across any airstrip that would warrant

triggers to Cap 394.

(xix) The Water Act 2002

In March 2003, the Water Act 2002 came into effect to provide a legal framework for management and

conservation of the national water resource base in line with policy changes in the sector. New

institutions with separate functions have now been established, and decentralized decision making is

reflected in autonomous regional bodies. Henceforth, these are the institutions with which all works

touching on water resources have to coordinate with. They include:

Ministry of Water and Irrigation: The MWI is the trustee of all water resources in the country. The

present key roles and functions of the MWI have been defined in the National Water and Sanitation

Services as: water policy formulation; water resources management policy; apportionment of water

resources and abstraction licensing; appointment of water undertakers; regulation, setting and approval

of standards; approval of water tariffs, levies, rates and charges; development and operation and

maintenance of urban and rural water supply systems; wastewater treatment and control; water quality

and pollution control; catchment area conservation; water conservation (by National Water

Conservation and Pipeline Corporation); irrigation and dam construction schemes; flood control and

land reclamation (MWRMD, 2003).

Page 40: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

28

The Water Resource Management Authority: This is a body corporate charged (under Section 8(1) of

the Water Act 2002) with the overall responsibility of overseeing sustainable development of the

national water resource base. The functions of the WRMA as provided in Section 8 of the Water Act

2002 is to manage, protect and conserve the water resources with regional offices at catchment levels

for decentralized decision-making, quick response to water resources management problems and for

speedy water allocation process.

In order to coordinate activities in water resource management, WRMA has issued Guidelines for Water

Resource Management (LN 171), Part IX of which specifies code of conduct with regard to activities in

riparian areas. In the impression of this study, there are no triggers to the Water Act and its LN 171.

This National Museums and Heritage Act, 2006:

The National Museums and Heritage Act was enacted and commenced on 8th September 2006 for the

following purposes:- (i) to consolidate the law relating to national museums and heritage; (ii) to provide

for the establishment control, management and development of national museums and the

identification, protection, conservation and distribution of the cultural and natural heritage of Kenya;

(iii) to repeal the Antiquities and Monuments Act and the National Museums Act; (iv) and for connected

purposes.

Under Section 25, Cap 216 allows for declaration of National Heritage sites which then remain protected

from any annihilation or alteration under the law. This Project Report process has taken precaution to

ascertain that none of the areas traversed by the proposed Mwachabo Power distribution line harbours

assets gazetted under Cap 216.

3.2.5 EMCA requires conformity to International Conventions, Treaties and Agreements

Kenya is a signatory as well as a party to various international conventions, treaties and protocols

relating to the environment and aimed at achieving sustainable development. According to the Registrar

of International Treaties and other Agreements in Environment (UNEP 1999), there are 216 such

treaties, 29 of which are of interest to Kenya. The country is a signatory to 16 such agreements, which

range from use of oil, protection of natural resources and, protection of the atmosphere. The

agreements are both regional and international and became legally binding on Kenya upon ratification

thereof by the rightfully designated Kenyan Authority.

Protocols towards protection of the natural environment: There are 16 agreements of significance to

Kenya especially due to its high dependence on fuel wood and hydropower. At international level, Kenya

has signed and ratified the following tools:-

� Convention on Biological Diversity, 1992;

� United Nations Convention to Combat Desertification 1994;

� the International Plant Protection Convention 1951;

� the Convention on Wetlands of International Importance (Ramsar 1971);

� Convention on International Trade in Endangered Species (CITES) of Wild Fauna and Flora, 1990,

which protects forests as habitat for endangered species; and also ,

� Convention concerning the Protection of World Cultural and Natural Heritage, 1972, which also

protects threatened plants.

Page 41: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

29

For purposes of this study, the proposed power distribution line was screened for possible against all the

10 conventions for possible triggers. Though none were explicitly identified, it is worth noting that tree

removal towards creating way leaves is a precursor to the desertification process.

Table 3.3: Screening of the proposed power distribution line project against international treaties on protection of

nature

No Convention Status in

project area

Remarks

International Plant Protection Convention 1951 No trigger

Convention on Wetlands of International Importance

(Ramsar 1971)

No trigger

Convention concerning the Protection of World

Cultural and Natural Heritage, 1972

No trigger

Convention on International Trade in Endangered

Species (CITES) of Wild Fauna and Flora, 1990

No Trigger

Convention on Biological Diversity, 1992 No trigger

Agenda 21 of the United Nations Conference on

Environment and Development-UNICED (The Rio

Conference)

Legally non-binding

United Nations Convention to Combat Desertification

1994

No trigger Tree removal is a precursor to

desertification

Protection of the Atmosphere: Most of the greenhouse and ozone depleting emissions emanate from

man’s activities in sourcing energy and as such, the conventions in this area mainly aim at protecting the

atmosphere from harmful emissions. Kenya is party to the Vienna Convention of 1985 on Protection of

the Ozone Layer together with its three Protocols of 1990, 1992 and 1994. Kenya is also a signatory to

the United Nations Framework Convention on Climate Change (UNFCCC) 1992, and its Kyoto Protocol of

1997) which principally aims at cutting down on emission of greenhouse gases. Both conventions are

deemed quite relevant to projects targeting substitution of biomass energy with cleaner energy sources

such as the proposed rural electrification. The observation here is that though removal of trees to create

way leaves directly impacts on the carbon sink, the shift from kerosene and biomass to use of electricity

has a more significant impact of emission of greenhouse gases. Removal of trees is thus seen as a

necessary cost towards adoption of cleaner energy.

Table 3.4: Screening of the proposed power distribution line project against international treaties on protection of

the atmosphere

No Convention Status in

project area

Remarks

The 1985 Vienna Convention on Protection of the

Ozone Layer

The 1987 United Nations Montreal Protocol on

substances that deplete the ozone layer

No trigger

The 1992 United Nations Framework Convention

on Climate Change (UNFCCC) which led to the

Kyoto Protocol of 1997

Trigger Tree removal impacts on the

carbon sink but use of electricity

for lighting cuts down on GHG.

The 1997 Kyoto Protocol on Climate Change Trigger

Page 42: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

30

3.3 The Regulatory Framework

This Project Report Process is subject to control by three administrative frameworks namely:-

3.3.1 The Rural Electrification Authority-REA

The Rural Electrification Authority (REA) is a State Corporation established under Section 66 of the

Energy Act, 2006 (No 12 of 2006) to manage the Rural Electrification Programme including the

formulation of a rolling Rural Electrification Programme Master Plan which would present least-cost

electrification options for target areas. In the capacity of Employer in this Study, REA has defined the

scope and coverage of the Project which to a large extent determines the depth of the study to be

undertaken. Towards this, the Employer has stipulated Study tasks to be executed towards ensuring a

comprehensive, legally proficient study output. The REA thus wields the administrative framework

towards supervision and quality control of the study.

3.3.2 The Energy Regulatory Commission-ERC

The Energy Sector in Kenya is regulated by the ERC which was established under the Energy Act of 2006.

Section 6 of the Energy Act 2006 confers on the ERC a mandate to ensure environmental protection

within the energy sector in the capacity of de jure Lead Agency. Section 6 of the Energy Act empowers

the ERC to formulate, enforce and review environmental, health, safety and quality standards for the

energy sector, in coordination with other statutory authorities; and, to enforce and review regulations,

codes and standards for the energy sector. Further, Section 30(1) and (2) of the Energy Act 2006

requires that ‘The Commission shall, in granting or rejecting an application for a licence or permit, take

into consideration; - (i) the impact of the undertaking on the social, cultural or recreational life of the

community; and (ii), the need to protect the environment and to conserve the natural resources in

accordance with the Environmental Management and Coordination Act of 1999.

This Project Report has partly been prepared in fulfillment of requirements of the Energy Act 2006 and

indeed, the final output will be reviewed by the ERC in the capacity of Lead Agency.

3.3.3 The National Environmental Management Authority-NEMA

EMCA 1999 allows for formation of the National Environmental Management Authority (NEMA) as the

body charged with overall coordination of environmental protection in Kenya. A Director General (DG)

appointed by the President heads the Authority established in 2001. Several Directors in charge of

Enforcement, Education, Policy, who are assisted by Assistant Directors and Senior Officers under them,

assist the DG. To facilitate coordination of environmental matters at District level, EMCA 1999 allows for

creation of District Environmental Committees (DEC) traditionally chaired by respective District

Commissioners. However, in order to align to requirements of Kenya Constitution 2010, NEMA has

devolved functions to Counties. Under the New arrangement, EIA licensing for projects will take place at

either the County or National level depending on the perceived environmental risk category as per the

NEMA advert of 9th

July 2012.

Thus this Project Report recognizes NEMA as the sole regulator of EIA processes in Kenya. Indeed, the

second objective of the Project Report is to facilitate Environmental Licensing of the 33 kV Distribution

line by NEMA; in which case, the Report has to ensure compliance with all standards as set out by NEMA

in capacity of Environmental Regulator in Kenya. The Project Report Process has thus been tied up to the

NEMA institutional framework at Head Office and County levels.

Page 43: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

31

4 CHAPTER FOUR: THE BASELINE ENVIRONMENT

4.1 The Bio-physical baseline

4.1.1 Location and administrative set-up

The entire Mwachabo power distribution line project falls within the Mwatate District of Taita Taveta

County. Specifically, the Mwachabo location targeted for power supply lies to the south of the Mwatate-

Taveta (A23) road to the west of the Teita Sisal Estate.

4.1.2 Relief and physiographic profile

Mwatate District comprises the lowland belt of the Taita Taveta Highland-Lowland Continuum.

Mwachabo location is situated in the Taita lowlands which is part of the expansive lowland area

extending from the Yatta Plateau in the East to beyond the Tanzanian boundary in the west and which

contains the Tsavo East and West National Parks. Relief is dominated by a generally flat, monotonous

plain which is only interrupted by minor local depressions and occasional inselbergers. Altitude generally

averages 700 m above sea level.

Plate 4.1: An inselberg in the Mwatate Plains

4.1.3 Climatic regime

Rainfall data for the Voi Meteorological station which is considered nearest to the Project area is

presented in Table 4.1. On account of low altitude and absence of relieve barriers, annual rainfall in the

Mwatate lowlands in a low of 555mm. Annual rainfall is delivered in 2 distinct wet seasons lasting

March to April and November to December with the bulk of rainfall occurring in the second season.

June to September marks a severe dry season with mean monthly rainfall generally below 20mm.

Table 4.1: Climate data for the Mwatate area based on the Voi Meteorological station

Page 44: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

32

Month Daily

maximum

Temp (oC)

Daily

minimum

Temp (oC)

Daily

Sunshine

hours

Daily

wind

run

Monthly

evaporation

Monthly

mean rainfall

(Voi)

Monthly

mean rainfall

(Taveta)

Jan 31.6 20.1 8.1 92.5 191 34 57

Feb 32.9 20.2 7.4 95.1 195 29 42

Mar 33.3 20.8 7.7 100 211 79 95

Apr 31.8 20.4 7 116.9 174 100 143

May 29.9 20 7 149.6 169 30 64

Jun 29 18.3 6.9 161.4 173 6 19

Jul 28.1 17.5 6.1 168.3 174 3 12

Aug 28 17.2 5.7 179.3 167 8 12

Sep 29.2 17.6 6.7 156.8 178 15 12

Oct 31.1 18.9 8.4 137.5 206 26 21

Nov 31.4 20.1 7.7 103.2 181 106 120

Dec 30.6 20.4 7.8 87 170 119 76

Total 2189 555 673

Max 33.3 20.8 8.4 179.3 211 119 143

Min 28 17.2 5.7 87 167 3 12

Ave 30.6 19.3 7.2 129 182 46 56

For purposes of this study, climate of the proposed traverse has been calibrated against standard

parameters namely the climatic index as determined by the ratio of rainfall (r) to potential evapo-

transpiration (Eo) based on the method of Sombroek et. al, 1982.2 With a mean annual rainfall of

555mm and an equivalent potential evapotranspiration of 2189mm, Mwatate area has a climatic index

(r/Eo ratio) of 0.25 which translates to a Climatic Zone V which is semi-arid, fairly hot to very hot.

Monthly rainfall does not exceed potential evapotranspiration demand in any month (Fig 4.2) implying

that moisture scarcity poses the most severe limitation to ecological productivity in the area. Past

studies on local rainfall patterns (Ogallo, 1979) suggest that long-term rainfall patterns in Taita include

cyclical droughts, such as those experienced in 1887, 1921, 1970-71, 1974-75. In the last 30 years (1969-

1999), the major droughts were experienced in 1984, 1988 and in 1998.

2

Page 45: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

33

0

50

100

150

200

250

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Mo

nth

ly r

ain

fall/

PE

T(m

m) Moisture balance for the Mwatate area

Mean monthly PET(mm) Monthly mean rainfall (mm)

Figure 4.1: Seasonal moisture balance for Mwatate area

4.1.4 Cover vegetation

Mwatate area is semi-arid characterized by Savannah bush land comprised of Acacia-Commiphora

Dryland Forest, where the dominant species include; Acacia tortilis, Acacia nilotica, Acacia bussei, Acacia

hockii, Commiphora africana, Commiphora campestris, Commiphora confusa. The average canopy

height is between 5-7m with the maximum height being approximately 10m. There are occasional taller

hardwood species such as Terminalia spinosa, Melia volkensii, Boscia coriacea, Cassia abbreviata,

Newtonia hildebrantii. On account of human incursion, the original vegetation has been removed either

in total as in the case of the Teita Sisal Estate or partially to provide wood for building and charcoal

making. Remaining bushlands are subsequently dominated by low growing shrubs comprised of

Commiphora spp, Balanites, Accacia spp, Terminalias, among others (Plate 4.2).

Plate 4.2: Remnant semi-arid vegetation in the Mwachabo Location

Page 46: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

34

Of special mention are the local isolated hills within the project area where vegetation is fairly intact and

is reputed to be teeming with wildlife species such as lions, leopards, among others. Given the close

vicinity to the Tsavo West National Park, the southern parts of Mwatate District are home to a diversity

of over 50 species of large mammal, more than 20 species of bats, over 300 species of birds and

important populations of IUCN Red List species such as Grevys zebra (Equus grevyi), Cheetah (Acinonyx

jubatus), Lion (Panthera leo), African wild dog (Lycaon pictus) as well as the African elephant (Loxidonta

africana). Such wildlife occasionally disperses into the Mwachabo location.

4.1.5 The socio-economic profile

4.1.6 The inhabitants

Mwatate District is primarily inhabited by the Taita who are native to this area. However, the

employment and trade opportunities presented by large-scale sisal farming, tourism, mining and cross-

border trade at Taveta have attracted people from other communities who have formed cosmopolitan

settlements in Mwatate Town and other trading centers.

4.1.7 Population dynamics

As at the 2009 National Population Census, the then Mwatate Division (now a District) had a total

population of 60,698 people comprised of 15,839 Households. Mwachabo location had a population of

12,263 people comprised of 3,065 households. Being a new settlement and on account of presence of

the Teita Sisal Estate, the population density is low, at 31 persons per square kilometer.

Table 4.2: Population statistics for Mwatate District

Administrative

Unit

Pop statistics (2009 Census)

Men Women Total Households Density (Pers/km2)

Mwakitau Loc 3,426 3,500 6,926 1,859 10

Bura Loc 4,813 5,146 9,959 2,707 38

Mwachabo Loc 6,355 5,908 12,263 3,065 31

Mwatate Loc 7,444 7,064 14,508 4,050 42

Mwatate Div 30,420 30,278 60,698 15,839 35

4.1.8 Land use and livelihoods

Large-scale sisal farming comprises the main land use within Mwachabo location. Outside of the large-

scale farms, livelihoods are based on subsistence mixed agriculture in which crop farming is combined

with keeping of local animals while others rely on trade. On account of aridity, crop farming is a risky

business on which account, this location frequently relies on food relief.

4.2 Ecologically sensitive resources

Mwachabo location shares common boundaries with the Tsavo West National Park on which account, it

is an important habitat and dispersal area for wildlife. This ecological function is however threatened by

increased bush clearing for agricultural settlements.

Page 47: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

35

5 CHAPTER FIVE: STAKEHOLDER CONSULTATIONS

5.1 Need for stakeholder consultations

Legal Notice of 101 of June 2003 requires that all environmental assessment process in Kenya to

incorporate Public Consultation - a requirement informed by awareness that stakeholders are largely in

the constituency likely to be impacted by proposed developments and it is imperative that they be

informed of the project following which they can make informed comments and reactions to the

proposed development. It is also important to ensure that all stakeholder interests are identified and

incorporated in project development, implementation and operation and, against such background,

consultation was undertaken with a cross section of stakeholders both within and outside the project

area of influence with the following objectives:-

i) To disclose the project to both primary, secondary and other stakeholders;

ii) To obtain the reaction/comments/concerns of all stakeholders which is integral to the impact

prediction and interpretation process

iii) To obtain on the ground information of the pre project baseline. Thus, fieldwork combined both

stakeholder consultation and documentation of the baseline environment.

5.2 Approach to stakeholder consultation

5.2.1 Identification of stakeholders

The proposed distribution lines comprise a unique project in that, right from onset, project design

entails acquisition of land for construction of permanent overhead structures traversing close to 35.3

kilometers of land. Of necessity, numerous people are likely to be affected by the project and are

therefore bona-fide stakeholders demarcated by the decision to follow the proposed route of traverse.

The same were identified and consulted through diverse for a as outlined elsewhere below.

This study also identified other categories of stakeholders comprised of GoK offices, parastatals etc

within sectors deemed likely to be impacted by the project. This category was also consulted as key

informants on sectoral policy and to advise this EIA study on mitigation measures to be put in place so as

to minimize adverse impacts in respective sectors. In this category were also included local policy

makers and opinion leaders, local administration, local authorities, civic leaders among others.

5.2.2 Levels in stakeholder consultations

Of necessity, stakeholder consultations should take place alongside project design and implementation

to ensure that the project puts in place measures to cater for stakeholder concerns in all project phases.

In case of the proposed development of power distribution lines, stakeholder consultation was

approached at four levels namely;-

i) Briefing by Project Engineers: Briefing commenced after negotiating the contract and consisted

of discussions between the Consultant and the SWECO/Aberdare Engineers team. During such

discussion, the Engineers clarified the scope and expectations; mode of contract administration

and deliverables on the contract, and also provided information on project design to the

consultant. Notably, the consultant obtained design reports and maps from the feasibility study

phases of the project and also obtained contacts for supervision team on the ground.

Page 48: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

36

ii) National Level consultation: This entailed consultation with the project design team, Client and

Lead agencies (KFS and KeRRA) deemed relevant to the project. Such consultations applied to

the entire 8 schemes that were the subject of the contract for EIA.

iii) County and District Level consultations: These were mounted at respective counties and

districts with discussion focusing on project falling within such jurisdiction. However as

expected, the reaction especially from government sectoral Agencies (Education, KFS,

Agriculture, Public Health etc) are cross-cutting and hence applicable to all the 8 projects

irrespective of the administrative jurisdiction. Thus views of the KFS, KeRRA, Public Health,

Agriculture etc have been applied in developing the project report and by extension the EMP for

the entire 8 projects.

iv) Project level consultations: Consultations have targeted residents of Mwachabo location who

essentially are the primary stakeholders to the project. While discussions at district level mainly

targeted line ministries those at county level mainly targeted county and regional offices such

as, county commissioners, county councils, KeRRA regional officers, County Forest Coordinators

etc where the target was to obtain sectoral position on potential impact of rural electrification

to that sector.

5.2.3 Methodologies in stakeholder consultation:

All consultations for this Study were undertaken by the Team Leader. Consultations generally employed

diverse methodologies depending on the target audience. Methodologies included;

• Key informant interviews:-

• Focus Group Discussions (FGD):-

• One to one consultations: These were held with local residents or traders when it was not

possible to cause for a quorum for a focus group discussion. At the end of an interview each

informant was requested to sign the comments as registered by the Team Leader.

• Indirect consultations: Numerous individuals and institutions previously played diverse roles in

the formulation and design of the power distribution lines project and though it was not

possible to make direct contacts with them, the same was achieved through study and review of

outputs left behind in form of reports. Thus, considerable time input was devoted to review of

project documents towards preparation of this Project Report. Appendix 5.1 provides a list of

documents reviewed as part of this study.

5.2.4 Progress in consultation

A summary and tally of the entire stakeholders consulted for this project is provided in table 5.1 below.

Essentially a total of 27 people were consulted and this includes the national level stakeholders (the

Project Design Engineers, the Rural Electrification Authority (REA), Kenya Forest Service (KFS), the Kenya

Rural Roads Authority-KeRRA, etc) and some county based GOK stakeholders whose inputs are deemed

relevant to all the 8 rural electrification schemes contracted for environmental impact assessment.

A record of Nairobi based consultations is provided in Appendix 5.2 below while Appendix 5.3 provides a

record of project specific consultations conducted in Taita Taveta County, Mwatate District and the

Mwachabo location (Plate 5.1).

Page 49: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

37

Plate 5.1 : Stakeholder consultation at Kamtonga Trading Centre

County/ Provincial administration: In the capacity of coordinator of GOK business at grassroots level,

this sector was contacted in all the 8 counties targeted for REP scheme development with outcome as

follows:-

i) The sector is not aware of any adverse environmental and social impacts associated with rural

electrification.

ii) At locational and divisional level, this sector required that project contractor to establish contact

and linkage so as to ensure incident free construction of the power lines.

iii) Chiefs contacted also requested to be involved during construction and commissioning of the

power lines so as to ensure community mobilization towards securing of the investment

(Transformers) from theft and vandalism.

The Kenya Forest Service: Concerns of the KFS at the County (CFC) and zonal levels resonated with

those of their counterparts at NEMA.KFS is concerned that;

i) None of REP schemes pass through gazetted forests.

ii) From past experience trees are either excessively lopped or removed to give way for REPs

iii) In most cases trees are removed by REP contractors without consulting the KFS offices on the

ground in complete bleach of the requirements of the forest act.

iv) The KFS requires that all EIA project reports proposed in respect of REP be shared with CFCs for

review and possible comments on impacts on tree resources.

v) The KFS also required to be involved at construction stage to ensure that trees are protected

and to advise on modalities for replacement of trees so lost.

Ministry of public health: At county level, the ministry of public health was only contacted at Wundanyi

under auspices of the District Medical Officer of Health (DMOH) who appreciated the great impact of

rural electrification towards facilitating service delivery by dispensaries. The DMOH however expressed

concern over ability of dispensaries to pay for connection to grid power supply given their very low

budgetary allocation.

Page 50: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

38

Table 5.1: Summary table of stakeholders consulted

Part Level of

consultation

Stakeholder category No Nature of meeting No of

people

met

Part

one

National Level

(General)

KFS 2 Met Deputy Director forest

conservation and Management and

the officer in the legal services

department.

2

KeRRA 1 Met an officer in the survey

department.

1

KeNHA 1 Met with the Manager- Surveyor

Services

1

REA 1 Held several discussions with the

Project Manager and Way leave officer

2

Aberdare/SWECO 1 Held several consultative meetings

with both Project managers and a

supervisor

3

Part

Two

County Level

(General)

County Commissioner 1 County Commissioner visited but was

out of office

0

County Council of Taita

Taveta

Chief Officers of this Council were in a

meeting whole day

Kenya Rural Roads

Authority

1 Held telephone discussion with the

Head of the KERRA sub-office at

Mwatate

1

Kenya Forest Service 3 Met with the County forest

coordinator in Taita Taveta

3

NEMA 1 CDE and CEO were out of office. Held

discussion with the CEO on the phone.

1

Part

Three

District Level

(Scheme

Specific)

Provincial Administration 1 Assistant chief-Mruru/Mwanganga sub

location

1

Ministry Of Agriculture 1 District Agriculture Officer 1

Ministry of Health 1 District Medical Officer of Health 1

Part

Four

Project level

(Specific)

Local residents and

traders

2 1 Baraza at Kamtonga market and 1

semi baraza at Manoa market.

29

Local Dispensary 1 Met the Kenya Certified Nurse Manoa

dispensary

1

Total 18 46

The Kenya Rural Roads Authority: KeRRA was not consulted only at sub regional level at Taita County.

Comments here are borrowed from consultations held with KeRRA officers in Makueni, Kitui and

Machakos under the same contract who made comments as follows:-

i) KeRRA is concerned that contractors for REP do not take time to familiarize with the extent and

alignment of rural roads leading to some power distribution poles being erected in the middle of

the road reserve and thus creating conflicts with either road users or future road development.

ii) KeRRA requires to be consulted during the process of design and construction of power lines

within areas of jurisdiction.

Page 51: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

39

Local Authorities-County and Town Councils: During the visit to Wundanyi, Chief Officers of the Taita

Taveta County Council were locked in a meeting the whole day and were thus not available for

consultation. Views expressed here are based on consultations made with the Kilifi County Council,

Makueni County Council, Wote and Tala Town Councils and the Masaku County Council. Local

authorities raised concerns as follows:-

i) REP should be designed and constructed to utilize existing and anticipated road reserves, taking

care to reserve the 9 m required for road construction. As such REPs should be restricted to

within one metre boundary of road reserves.

ii) Where power poles are cited in private property, they should exploit boundary areas to avoid

conflict with future development.

iii) County Councils are concerned about indiscriminate tree removal to give way to power lines in

market centers. In spite of money having been spent to establish and tend such scenarios, local

authorities should be consulted during the design and construction of power lines within areas

of jurisdiction.

iv) Local authorities stated that contractors doing business within respective areas of jurisdiction

should pay rates as appropriate in line with Cap 265.

Ministry of Agriculture: Concerns were raised as follows:-

• Excessive lopping of fruit trees interferes with food security and the farm based livelihoods.

• Electric poles and way leaves fix the land out of certain uses and can interfere with the farm

economy.

• Supply of electricity was potential to undermine adoption of either renewable energy

technologies such as solar pv biogas, wind etc.

• These comments were found to apply to all schemes.

Ministry of Education: This is one sector that was observed to potentially benefit from electrification of

rural schools.

• Power supply to schools will facilitate replacement of diesel engines in boarding schools and

hence cut down the school operating costs.

• Power supply to schools will improve academic performance through increased time for prep,

reduced generator noise introduction of IT and allied courses.

• Electrical faults and malfunction however have potential to cause fire outbreak and associated

safety hazards.

• Power failure especially in the evening has been known to cause unrest and instability in

schools.

5.2.5 Comments from local stakeholders

Comments from the Public:

The comments are informed by 2 consultative meetings at Manoa market and an FGD held at Kamtonga

market with residents and traders. Their views are as follows:

(i) The public is in favour of the project as it will open up the area and they will benefit from various

investments which will therewith be facilitated by electricity.

(ii) Compensation: For the property that will be affected, the residents wanted to know whether they

will be compensated. More so, they also wanted to know if there will be compensation for poles

erected on private land.

Page 52: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

40

(iii) Beneficiaries: The residents wanted to know whether people who live at a radius of 3km will benefit

from the project.

(iv) Opportunities: Residents wanted to know if the local youth will be employed during the

construction phase.

(v) Route of traverse: residents wanted to know why the line follows corners instead of shortcuts.

(vi) The residents were wondering whether this is another of the political gimmicks.

5.2.6 Comments from local Institutions

The Manoa dispensary

They are in favour of the power distribution to the area as they will be able to offer services that were

previously not offered eg maternity care and laboratory services.

Local schools: It was not possible to get comments from local schools which were already closed at the

time of fieldwork. However, going by interviews with schools from other counties, power supply is

welcome as it will facilitate adoption of IT and computer based learning and school management.

5.3 Salient observation from stakeholders’ consultation

From the foregoing analysis and documentation, salient observation can be deduced as follows.

i. Public support and demand for rural electrification: The public is in support of this project and some

of the benefits they anticipate include:

• Lighting up of villages and village institutions.

• Opportunities will be created through such investments as welding, salons, cybercafés etc which

will not have been possible without electricity.

• Education will be more enhanced and diversified through E-learning and other computer based

academic programmes.

ii. Public apprehension over trees removals: Overwhelmingly indiscriminate and excessive removals of

trees to give way to power lines emerged as the most severe and commonly identified adverse

impact of rural electrification. The same area identified by both local owners and government sector

stakeholders. Removal of trees also sets in questions of compensation to respective owners.

iii. Potential conflict on use of roads reserves owing to misplacement of power distribution.

iv. Conflict over allocation of jobs in the building of power lines.

v. Concerns on the safety and security of power distribution equipment before and after

commissioning

5.4 Modalities for conflict resolution

Some recommendations on approaches to conflict and dispute resolution during project development

are outlined in section 8.45 below.

Page 53: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

41

6 CHAPTER SIX: ANALYSIS OF ALTERNATIVES

6.1 Overview

In sections below, we provide some background to the process that informed formulation of the project

in its current design. Notably, the project was subjected to detailed feasibility studies where diverse

options were considered leading to identification of the project and choice of technological options as

currently proposed. Project alternatives were considered at diverse levels namely; technological

options, route of coverage etc out of which, an overhead distribution line mounted on wooden poles

delivering power to markets within Mwachabo location was selected. Some of the options considered

are briefly reviewed in sections below.

6.2 Levels in evaluating project alternatives

6.2.1 Evaluation of the No Project option

Access to electricity remains low in Kenya and the country has one of the lowest percentage coverage by

electricity among African countries. In Uganda, only 9 percent of the population has access to electricity;

in Kenya, 14 percent; in Congo, 6 percent. In oil-rich Nigeria, the energy demands are nearly twice

national power output and this lack of industrial energy is continents biggest obstacles to development

and a big turnoff for foreign investors. Further, firms operating in Kenya persistently report erratic

power supply as a critical impediment to competitiveness. Expansion of electric power distribution

networks has great potential to redress this matter thereby catalyzing badly needed investment

especially in rural areas.

The proposed Mwachabo power distribution line is being developed as part of a wider national initiative

aimed at supplying power to rural markets and institutions. The no-project scenario would imply

continuation of inadequate power supply and is clearly not desirable for an economy that is struggling to

recover from impacts of political violence and drought. As such, any initiative with potential to increase

the percentage of Kenyan population covered by electricity is economically strategic in line with current

government emphasis on increasing percentage national coverage by electricity particularly in rural

areas.

Provision of additional power supply has been identified as crucial to achievement of the national

development aspirations as elaborated in the national development blue print–the Vision 2030 in which

case, the focus is on modalities for supply rather than the justification of what is clearly a move towards

implementation of government policy.

6.2.2 Options in the selection of the routes of traverse

The first six kilometres of the Mwachabo power distribution line will traverse the Teita Sisal estate

where the core consideration is the need to keep clear of sisal plantations to the extent possible.

Subsequent to this need, the route of traverse was aligned to the reserve of an existing road with the

result that the power distribution line will be longer and possibly more expensive compared to a straight

traverse.

6.3 Choice between diverse distribution technologies

Distribution vs local generation: Grid electric power is available at the Taita Sisal Estate within 6

kilometers of the first load center namely Mwachabo market which makes it much cheaper to tap and

distribute as opposed to local generation. Local generation would also require multiple investment in

Page 54: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

42

generating stations backed up by distribution lines to the points of consumption and would eventually

end up being more expensive.

In spite of grid electricity being readily available, the high rate of solar radiation averaging 7.2 hrs daily

provide excellent opportunities for tapping and utilizing solar power which should be taken advantage

of.

Overhead versus underground distribution lines: The choice between overhead versus underground

distribution lines was also considered. Indeed, electric power can be distributed by underground power

lines which facilitate distribution across: (i) densely populated urban areas, (ii) areas where land is

unavailable or planning consent is difficult, (iii) rivers and other natural obstacles, (iv) and with

outstanding natural or environmental heritage, (v) areas of significant or prestigious infrastructural

development and land whose value must be maintained for future urban expansion and rural

development, etc. Additionally, underground power lines are;-

• Less subject to damage from extreme weather conditions (mainly lightning, wind and freezing)

• Greatly reduced emission, into the surrounding area, of electromagnetic fields (EMF). All electric

currents generate EMF, but the shielding provided by the earth surrounding underground power

distribution lines restricts their range and power.

• Underground power distribution lines need a narrower surrounding strip of about 1–10 meters

to install, whereas an overhead line requires a surrounding strip of about 20 meters wide to be

kept permanently clear for safety, maintenance and repair.

• Underground power distribution lines pose no hazard to low flying aircraft or to wildlife, and are

significantly safer as they pose no shock hazard (except to the unwary digger).

Some disadvantages of underground power cables:

• Undergrounding is more expensive, since the cost of burying cables is several times greater than

overhead power distribution lines, and the life-cycle cost of an underground power cable is two

to four times the cost of an overhead power distribution line.

• Whereas finding and repairing overhead cable breaks can be accomplished in hours,

underground repairs can take days or weeks, and for this reason redundant lines are run.

• Underground power cables, due to their proximity to earth, cannot be maintained live, whereas

overhead power cables can be.

• Operations are more difficult since the high reactive power of underground cables produces

large charging currents and so makes voltage control more difficult.

Given all these considerations, construction of overhead distribution lines is the option favored by REA.

6.4 Choice of Tower structures

Steel poles: Tubular steel poles are typically used in urban areas, but are more vulnerable to vandalism

especially in isolated areas.

Wood: In Kenya, use of single wood utility pole structures is common in the construction of 33 kV power

distribution lines as proposed for Mwachabo. Construction entails placing a pole in the ground upon

which, one cross arm is fixed at the top end for purpose of supporting insulators and conductors. Wood

Page 55: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

43

is considered cheaper that other materials and has an overall cost saving of 20-30%. Wood is preferred

for such construction for, in addition to being relatively cheaper, wood has surge voltage insulating

properties which is not found in steel, aluminum or reinforced concrete structures.

Concrete: Use of concrete pylons worldwide is limited by their excessive weight which makes handling

and installation complex.

Aluminum: Where towers must be placed in inaccessible terrain by helicopters, the extra material cost

of aluminum towers will be offset by lower installation cost. Design of aluminum lattice towers is similar

to that for steel, but must take into account lower stress properties inherent to aluminum.

6.5 The preferred option

A comparison of all the options is summarized in table 6.1 below. From the analysis, the proposal to

investment in a medium voltage overhead distribution line based on wooden poles as currently

designed seems to be the preferred option given cost and technical considerations. Any adverse

impacts will be mitigated as per the Environmental and Social Management Plan (ESMP) unveiled in

Chapter Eight Below.

Page 56: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets

(Mwatate Constituency) 33 kV power distribution line

Table 6.1: Analysis of alternatives

Level of

evaluation

Option evaluated Advantages Disadvantages Preferred option Mitigation of

adverse impacts

Project No project scenario Savings to the national

economy, will avoid

environmental and social

costs

Economic losses due to

power outages, slowed

economic growth.

Develop project As per ESMP

Alternatives

in the route

of traverse

Winding as

opposed to straight

course

Less encroachment on sisal

plantations.

Route is longer and more

costly

Longer alignment

along existing road

reserve

Budget for

construction

Choice of

technology

Local generation

vis Distribution

Cut down on distribution

costs, will avoid displacement

and environmental costs

Requires multiple

investments in generating

stations and distribution to

market.

Distribution option As per ESMP

Overhead vs

underground

cables

It is cheaper to develop and

maintain.

High displacement costs and

exposure to accidents and

EMR in OHDLs

Use OHDL As per ESMP

Wooden poles vs

steel and concrete

poles

Wood is cheaper, readily

available and has inherent

surge protect properties.

Sourcing of wood impacts on

natural carbon sink.

Use of wooden

poles.

As per ESMP

Page 57: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

7 CHAPTER SEVEN: POTENTIAL IMPACTS FROM THE PROJECT

7.1 Generic Social and Environmental Impacts

7.1.1 Outcome of impact prediction

The Mwachabo power distribution line as proposed will require space in terms of both vertical and

horizontal projection and depending on the current physical and social characteristics of this space,

some impacts are likely to be triggered whose analysis is the subject of this chapter.

Impact prediction for this ESIA Study basically relied on four tools namely;-

• The generic checklist for impact prediction issued by NEMA as the Third Schedule to Legal

Notice 101. Appendix 7.1 presents a matrix based on this Schedule.

• The Checklist for Environmental Characteristics developed by the Department of Environmental

Affairs of the Republic of South Africa (Appendix 7.2).

7.1.2 Analysis of impact severity

Predicted impacts were analyzed for severity through screening for diverse attributes/ features

including magnitude, persistence, potential for reversibility, cumulative and tendencies, potential to

occasion secondary and cyclic impacts etc. Potential impacts were subsequently ranked on a scale of 2P,

P, O, N and 2N reflecting Highly Positive, Positive, Neutral, Adverse and Highly Adverse category of

impacts respectively. Table 7.1 below provides a summarized outcome of impact prediction and

interpretation based on application of the four checklists to the design, construction, and operation

phases of the proposed power distribution line and substation.

7.2 Description of potential impacts

7.2.1 Overview of impacts

Scale of impacts: The tally of potential impacts and their trends as identified in respect of the proposed

Mwachabo power distribution line are summarised as follows:-

Impact category Total Long-term

effect

Irreversible

effect

Cumulative

effect

Potential for

secondary impact

Total impacts areas 34 17 3

Positive impacts 17 10

Negative impacts 17 7 2 6 9

Net impact pre

mitigation

0

It must be pointed out that the scope of adverse impacts associated with construction of 35.3

kilometers of a medium voltage power distribution line in an otherwise low density agricultural

settlement is inherently low. Thus, for the proposed Mwachabo power distribution line, a total of 34

impacts out of which 17 are positive were identified. Other trends can be summarized as follows:-

• Only 17 negative impacts are likely to be occasioned by the proposed construction and

operation of the 10 kilometres of power distribution line as proposed and, all are observed to be

of low severity.

Page 58: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

46

• Ten of the 17 positive impacts are likely to be long-term in prevalence while 7 out of 8 adverse

impacts have a long-term effect with 2 of them being potentially irreversible.

• Nine out of sixteen adverse impacts have potential to cause secondary impacts while 6 of them

have cumulative tendency i.e., they have potential to aggravate an already existing problem.

• The project has a marginal net positive impact pre mitigation which will require to be enhanced

through adoption of an effective impact mitigation strategy.

Presentation of impacts: From this analysis, it is apparent that the bulk of adverse impacts (Ns) will

manifest at the construction stage while most benefits (Ps) will be realized during the operation phase.

In line with this trend, impact mitigation will be targeted more on the construction phase activities.

Without exception, all adverse impacts have potential to occasion secondary impacts and thus merit

mitigation. For purposes of this study, impact prediction has captured the three core phases of the

proposed development namely;-Design, Construction and Operation phases. Similarly, impacts analysis

as presented in Table 7.1 has captured and followed all the four phases of the project. Brief highlight of

impacts at each stage of the project are presented in sections below.

7.2.2 Impacts at Design Stage

Positive Impacts of design Stage:

Generally, the design phase is associated with positive impacts mainly manifested through creation of

business opportunities for professionals involved in the design work, support staff hired in the

enumeration survey, etc, while the country benefits from generation of additional planning data which

will influence policy decisions within long time frames. Certainly, the database compiled from design

report will find consumption far beyond the confines of this project.

Adverse impacts at Design Stage:

Adverse impacts would mainly be manifested through site disturbances and accidents associated with

field survey work.

7.2.3 Positive Impacts at Construction Stage

(i)Creation of business opportunities:

The proposed distribution lines will comprise of 35.3 Km of conductors and 5 transformers supported by

126 poles. Construction work wills therefore some modest entail investment estimated at Ksh 41.15

million, the bulk of which will go into procurement of construction material and hiring of the contractor.

Construction of the distribution line will thus open up extensive trade opportunities while other

economic benefits will accrue through creation of employment opportunities for both skilled and semi-

skilled labour engaged in construction. At local level, communities will benefit from short-term

employment opportunities in the construction activity.

(ii)Creation of opportunity for change:

Relocation of buildings and property from the right of way has destabilizing effects to PAPs. However,

the same process provides opportunity to occasion changes such as the need to regularize land and

property subdivisions and transfers, the need to settle boundary disputes, the need to formalize

inheritance etc which, in the long-run provides a stronger foundation for economic growth.

Page 59: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets

(Mwatate Constituency) 33 kV power distribution line

Table 7.1: Matrix for impact prediction and interpretation

Project

Phase

Source of

Impact

Potential Impact Severity

*

Persistence Trigger to

secondary

impacts

Triggers to

cumulative

impacts

Design Stage Design

Studies, field

surveys and

inventories

Creation of temporary opportunities for gainful

employment

P Short-term

Generation of additional site-specific data

/study reports

P Long-term

Capacity building and sensitization P Long-term

Minor accidents during survey work N Short-term Reversible Minor

Construction

Phase

Supply of

materials

Business opportunities in supply and transport

of construction materials

P Short term

Generation of GHG in the transportation of

construction materials

N Short-term Reversible Climate change

and impacts

GHG build-up

Road hazards in material transportation N Short-term Reversible

impacts

Irreversible

impacts

Traffic build up

Construction

work

Short-term opportunities for business and

employment in construction

P Short-term

Revenue to GoK and Local Authorities through

taxes

P Short-term

Opportunity for change P Long-term

Damage of property (tree crops) from ROW

corridor

N Long term Reversible Escalating

poverty

Can aggravate

poverty

Deforestation and loss of Carbon sink from

felling trees

N Long-term Reversible GHG build-up Aggravates a

global concern

Occupational health and safety concerns for

construction crew

N Short-term Reversible Impacts of

injuries and

occasional

death

None

Solid wastes from construction activity N Short-term Reversible Littering,

injuries, etc

Solid waste is a

growing problem

Loss of nesting grounds for avifauna, bees, and

dry season fodder from tree removal

N Long-term Reversible Risks to pop

stability

Increasing loss

due to human

encroachment

Impact on existing and future infrastructures 2N Long-term Reversible Higher costs in

service delivery

Least Concern

Operation Presence of Economic gains from improved and stabilized 2P Long-term

Page 60: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets

(Mwatate Constituency) 33 kV power distribution line

48

Project

Phase

Source of

Impact

Potential Impact Severity

*

Persistence Trigger to

secondary

impacts

Triggers to

cumulative

impacts

Phase powered lines

power supply

Enhanced delivery of services in medicare,

education, admin, telecommunication, etc

2P Long-term

Financial gains in oil to electricity substitution,

and elimination of maintenance costs for diesel

engines, etc

P Long-term

Employment creation, reduced cost of

investment

2P Long-term

Cutting down on GHG emissions due to

petroleum to electricity substitution

2P Long-term

Reduction in solid waste from lead acid

batteries, dry cells, candle residues, waste oil/

spares from gensets etc

P Long-term

Adverse

impacts from

charged high

voltage power

lines

Exposure to Electromagnetic fields (EMF) N Long-term Irreversible Hazards to

public health

Increasingly a

problem

worldwide

Impact on avifauna and other wildlife from

presence of charged wires

N Long term Reversible Risks to

population

stability

Cumulative

Permanent visual intrusion into space N Long-term Irreversible Rare Intrusion by

power lines a

growing problem

Hazards in attempted vandalism of

transformers

2N Long-term Reversible None This is a grave

concern

nationally.

Disincentive on use of other Renewable Energy

Sources e.g. RETs

2N Long-term Reversible A growing

problem

Net environmental worth of

the project pre-mitigation

17 (17 positive outputs, mainly long-term),

17(17 adverse outputs, 9 long-term, 3 irreversible),

Net score=0 (Net neutral impact before mitigation)

Some adverse impacts

irreversible

*N=low adverse impact; 2N=moderately severe impact; 0= no impact; P=positive impact, 2P= significantly positive impact.

Page 61: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

7.2.4 Negative impacts at Construction Stage

(i) Impacts associated with removal and lopping of trees in the right of way:

By design, 33 kV power lines require little in terms of way leave in which case, their construction does

not entail extensive removal of trees and structures. However, the requirement that all trees

underneath power lines be removed to avoid incidence of accidents from powered lines has impacts as

follows:-

Loss of livelihood: On farm trees are part of the family capital and productive resources which generate

cash income upon harvesting and sale or from harvesting of fruits. Thus premature felling as occasioned

by construction of power lines represents a major loss on the side of the farmer who has spent

resources to nature the trees. In some cases, some families have no hope of ever benefitting from the

proposed power supply in which case, removal of their trees without adequate compensation pushes

them further into poverty.

Degradation of habitat for fauna and flora biodiversity: Removal of tree cover in a marginal climatic

potential area interferes with the survival of dependent vegetation due to loss of shade, stemflow,

nutrient cycling and other ecological support functions performed by mature trees. Further, removal of

mature seeding trees undermines the self-perpetuating capacity of affected species which in addition to

loss of nesting grounds for insects and avifauna, fodder and forage for browsers, shade and shelter etc,

has critical implications to the health of wildlife populations (see plate 7.2).

Plate 7.1: Birds nesting on a tree at Kamtonga market

(iii Hazards associated with transport and delivery of construction materials: Construction of a 35.3

kilometer power distribution line with require about 133 poles and several rolls of concoctors all of

which will be transported by road whose transportation raises concerns in terms of impact on local

roads and safety of other road users (see plate 7.3).

Page 62: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

50

Plate 7.2: Transportation of construction materials has potential to undermine safety of other road users

(iv) Concerns in the storage of construction materials and components: Privatization of services in

construction of power distribution and distribution lines in Kenya have created a huge demand for

transformers, conductors etc which poses huge challenges in the management of such stores given the

increasing cases of theft of the same. Against such a background, the storage of power distribution

materials worth millions of shillings can easily escalate incidence of crime whereby resultant searches

and arrests serve only to antagonize the project from host communities.

(v) Occupational Health and Safety impacts on workers: Construction, testing and commissioning of a

power distribution line in an area reputed to be infested with wildlife will expose workers to multiple

occupational hazards such as injury and loss of life from accidental falling, motor accidents,

electrocution, mauling by animals, etc which are costly to both affected families in terms of loss of

income and the government through loss of productive labour and increased dependency. Though such

risks prevail only during the construction phase, their impacts can be long lasting depending on the

degree of injury sustained.

(vi) Generation of construction waste: Junk in form of scrap metal, plastics, pvc cords, etc will be

generated from construction activity. Such waste, estimated at 10% of all construction materials has

potential to pose environmental challenges unless appropriately disposed.

7.2.5 Impacts at the Operation Phase

Extension of the distribution lines is potentially very beneficial especially on economic and

environmental fronts. We highlight some of the benefits here below.

Creating opportunities to promote economic growth:

Energy is identified as one of the infrastructural enablers of the ‘’three pillars” of Vision 2030 and with

only 4% of the rural population having access to electricity; the rate of economic development must

remain understandably low. Kenya is therefore expected to use more energy in the commercial sector

on the road to Vision 2030 and as incomes increase and urbanization intensifies, household demand for

energy will also rise. The challenges facing the power sub-sector include a weak power distribution and

Page 63: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

51

distribution infrastructure, high cost of power, low per capita power consumption and low countrywide

electricity access. Preparations have been made to meet this growth in demand for energy under the

Vision as follows:-

• The government has continued to finance extension of electricity supply in the rural areas as

part of the basic infrastructure to stimulate economic growth and employment creation. This is

intended to increase electricity access in rural areas currently at 4% to 12% by the year 2012.

• The Kenya Electricity distribution Company (KETRACO) has been created with full mandate to

expand the electricity distribution grid and the government is also encouraging the Kenya Power

and Lighting Company to adopt affordable connection policies so as to boost the number of

customers in the rural areas.

• A Rural Electrification Authority (REA) charged with the mandate of implementing the Rural

Electrification Programme came into operation in July 2007. In addition, Ethiopia and Kenya

have undertaken a feasibility study and secured financing to facilitate the transfer of power to

Kenya from a number of large Ethiopian hydropower projects that provide power at lower costs

compared to that generated locally.

Against this background, construction of the proposed Mwachabo power distribution line is seen as a

positive intervention towards implementation of GOK strategies for economic growth especially in rural

areas. Positive benefits will manifest as follows:-

• Provision of electric power will open up market centres to investments such as engineering

services, welding, banking, computer services, etc that are difficult to provide in absence of grid

electricity.

• Electricity supply to rural centres will widen opportunities for gainful employment, human

resource development and rural commerce all of which are recipe for rural transformation.

• Once connected to power distribution networks, some institutions such as schools and water

supply projects currently relying on diesel generators and pump sets will now shift to a relatively

cheaper, cleaner and more reliable energy source and in the process, cut down on financial

strains imposed by purchase of diesel fuels. In the process, schools taking advantage of

continuous supply of electricity will light for longer hours and thus mount more aggressive

study/tuition programmes thus greatly improving on quality of delivery of education.

• Similarly, health institutions connecting to power distribution networks can henceforth adopt

power driven technologies and thus widen the array of services –imaging, immunization,

sterilization, theatre, etc, hitherto difficult to provide.

• Improved lighting in homes will motivate school / college going students to comfortably

undertake evening studies, and women and men will gain some precious time for themselves to

extend income generating work into the evening hours.

• Use of electricity for lighting and heating will also improve quality of indoor ambient conditions

thus improving the health of the people.

Cutting down on smoke and GHG emissions:

Within some urban households, supply of electric power could see a possible reduction in use of

biomass energy such as charcoal and firewood for cooking and heating through adoption of electric

stoves and other energy saving appliances thus improving domestic air quality with a possible impact on

family health. However, owing to economic and social considerations (type and quality of meals), most

rural folk connecting to electricity still opt for charcoal and firewood in cooking instead only preferring

to use electricity for lighting and watching television. Thus, substitution from petroleum fuels to

Page 64: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

52

electricity will immediately cut down smoke emitted from burning of fuels (in lighting, heating and

motion) and thus improve on air quality for local residents including those operating the gen-sets.

Cutting down on waste oils and spares:

Routine operation and maintenance of diesel-powered engines releases waste oils, spares etc, all of

which are environmentally hazardous especially when in contact with water. The phasing out of diesel

engines upon substitution to electricity will go some way towards eliminating environmental pollution

associated with operation of diesel powered engines.

7.2.6 Adverse impacts from powering and operating the distribution line

Operation of the power distribution line has numerous socio-environmental benefits as enumerated

above. However, for such benefits to be felt down to all intended beneficiaries there is need to insure

against trends and actions with potential to trigger adverse impacts that can erode accrued benefits.

Such potential adverse impacts and their causes are briefly highlighted here below.

Influence on land-use/ future development:

Like any other infrastructure, installation of power lines has a strong influence on any future

development. Thus, given that power lines normally follow existing way leaves, improper siting has

potential to complicate or compromise future development-especially road expansion. This has been

identified as a potential source of conflict with the roads sector. The Roads Act 2007 currently identifies

the Roads Sector as the custodian of all road reserves which requires their total consultation in any

proposed utilization of the road reserve.

Visual intrusion effects:

Construction of a distribution line with 10-14 m high poles supporting conductors where none existed

before will change entire landscapes and introduce visual obstacles where none existed before. This can

be frustrating to local residents who will have to get used to changed neighborhoods and possibly

trends.

Disincentive on use of other energy sources eg RETs:

It is the Policy of the Kenya Government to encourage use other RETs (Renewable Energy Technologies)

such as solar converters, wind-driven generators, etc to supplement supply of grid electricity whose

supply is inadequate to meet peak demand. However, the practice in Kenya is for such practice to be

abandoned once connection to grid electricity is assured. As such, in a country whose firm generation

capacity is inadequate to meet the demand, supply of grid electricity provides a strong dis-incentive

against exploration of other, equally viable options for lighting and heating in rural areas. This is a long-

term trend whose reversal requires intervention at policy level.

Impacts on avifauna:

The Taita Hills and vicinity (Sagalla, Kasigau, etc.) are recognised as Important Bird Areas (IBAs) famous

for the Southern Banded Snake Eagle, Taita Falcon and Abbott's Starling as well as the 3 globally-

endangered species Taita Thrush, Taita White-eye and Taita Apalis which are endemic to these hills.

Birds occasionally find the electrical wires a resting place and are ever in danger of death and injury

from electrocution and collision with bare conductors. The problem is however more pronounced on

transmission lines and towers of 25 m height and above. Thus whenever bare conductors are used in

power transmission, the spacing would be critical as this would affect the lives of birds and especially

those with a wide wingspan. The latter are usually fewer and run a higher risk of elimination due to

Page 65: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

53

either habitat destruction or other forms of killing and introduction of bare conductors thus increases

threats to survival.

7.2.7 Core concerns about the project

From analysis undertaken elsewhere above, potential adverse impacts from the proposed construction

of a power distribution line are quite modest and of low to moderate severity ranking. Towards

attempting mitigation, two adverse impacts however stand out as follows:-

• Project will displace trees and hence occasion some modest but fundamental economic and

ecological impacts.

• The project is likely to occasion conflict with the Roads Act 2007 over utilization of road

reserves.

Impacts however, have readily available means for mitigation and would therefore not stand in the way

for project implementation. An impact mitigation programme is outlined in sections below.

Page 66: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

54

8 CHAPTER EIGHT: THE ENVIRONMENTAL MANAGEMENT PLAN

8.1 Overview

This chapter outlines the environmental and social management strategy to be pursued in the

development and operation of proposed power distribution lines. The strategy comprises of both

an impact Mitigation Plan and an Environmental and Social Monitoring Plan

8.2 The Impact Mitigation Plan

Preparation of this Project Report has preceded project implementation in which case,

recommendations made here-in have a fair chance of being incorporated into and influence final

outcome of the project design process. This study recommends that findings be incorporated into

project design as a core mitigation strategy. Towards mitigation of specific impacts, action will be taken

as allowed for in Table 8.1 below.

8.3 Mitigation at design stage

The design stage is crucial to impact mitigation for any project. Firstly, at the design stage, projects enjoy

unlimited flexibility which makes alterations possible towards modifying components with potential to

occasion adverse impacts. As such, many potential impacts can easily be offset through modification of

the project design. In the case of proposed power lines, REA should take advantage of the design stage

to engage road sector stakeholders to mutually agree on modalities of using the road reserve. Such an

action will forestall conflict over use of the same space during construction and operation of the power

lines.

As well, the design stage allows for identification and commitment of resources towards impact

mitigation. It is thus hoped that, at this point, REA will identify and commit resources towards

compensating farmers for property to be displaced by the proposed power distribution line project.

8.4 Mitigation at construction stage

8.4.1 Mitigation of impacts associated with tree removal

Mitigation will principally aim at minimizing the number of trees to be removed which will require route

alignment to avoid areas of concentrated trees.

• Where tree removal is inevitable, proposed removalbe coordinated with the County Agricultural

Officer in line with the Agriculture (Farm Forestry) Rules 2009.

• REA will pay just compensation to affected farmers.

• As part of the Corporate Social Responsibility Programme, REA facilitate replacement of all lost

trees so as to rebuild cover vegetation, associated biodiversity and carbon sinks. The target here

is to support recreation of at least 10 ha of woodlots comprised of fruit trees, agroforestry trees

(casuarinas, grevillea and indigenous spp) as will be removed from the ROW. This may take the

form of funds set aside to purchase seedlings for issue to schools or institutions with land to

spare for reforestation.

Page 67: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets

(Mwatate Constituency) 33 kV power distribution line

Table 8.1: Matrix for impact mitigation

Project Phase Source of

Impact

Potential Impact Severity Mitigation Impact after

mitigation

Design Stage Design

Studies, field

surveys and

inventories

Creation of temporary opportunities for

gainful employment

P

Generation of additional site-specific data

/study reports

P

Capacity building and sensitization P

Minor accidents during survey work N Deploy competent staff 0

Construction

Phase

Supply of

materials

Business opportunities in supply and

transport of construction materials

P

Road hazards in material transportation N Contractor to observe the Highway Code 0

Construction

work

Short-term opportunities for business and

employment in construction

P

Revenue to GoK and Local Authorities

through taxes

P

Opportunity for change P

Damage of property (tree crops) from ROW

corridor

N Provide just compensation for any loss P

Generation of GHG in the transportation of

construction materials

N Reduce distances covered in material

sourcing

N

Occupational health and safety concerns for

construction crew

N Deploy sober, competent crew with

supervision. Provide PPEs.

N

Solid wastes from construction activity N Apply the 3 Rs concept. 0

Impact on existing and future infrastructures 2N REA to consult road sector stakeholders in

the design and construction of power lines

in road reserves

N

Operation

Phase

Presence of

power lines

Economic gains from improved and stabilized

power supply

2P

Enhanced delivery of services in medicare,

education, admin, telecommunication, etc

2P

Financial gains in oil to electricity substitution,

and elimination of maintenance costs for

diesel engines, etc

P

Employment creation, reduced cost of

investment

2P

Cutting down on GHG emissions due to 2P

Page 68: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets

(Mwatate Constituency) 33 kV power distribution line

56

Project Phase Source of

Impact

Potential Impact Severity Mitigation Impact after

mitigation

petroleum to electricity substitution

Reduction in solid waste from lead acid

batteries, dry cells, candle residues, waste

oil/ spares from gensets etc

P

Adverse

impacts from

charged high

voltage power

lines

Exposure to Electromagnetic Fields (EMF) N Threat not fully appreciated N

Impact on avifauna and other wildlife from

presence of charged wires

N Use of insulted conductors 0

Permanent visual intrusion into space N Adoption of insulated conductors which are

compatible with trees

N

Hazards in attempted vandalism of

transformers

2N Public sensitization campaign N

Disincentive on use of other Renewable

Energy Sources e.g. RETs

N REA to mount efforts to promote

alternatives to grid power

N

Net environmental worth of

the project pre-mitigation

17P (17 positive outputs, mainly long-term),

16 (16 adverse outputs, 9 long-term, 3 irreversible),

Net score=1P (Marginal positive impact before

mitigation)

18P (18 positive outputs, mainly long-term),

8N (8 adverse(irreversible) outcomes

Net score=10P (Major positive impact after mitigation)

Page 69: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

57

8.4.2 Mitigation of potential conflict in the use of road reserves

The Roads Act 2007 identifies the Roads Sector as bona fide custodian of road reserves in Kenya.

However, given that road reserves have traditionally also accommodated other public infrastructure,

there is need to formulated a mutually acceptable code of practice to facilitate coexistence between

roads and other infrastructure. The same will require to be sealed in law in the long run. In the interim,

all sectors targeting to use road reserve for infrastructure development should engage with relevant

road sector stakeholders (KeNHA, KeRRA, KURA) at the planning stage.

8.4.3 Management of Occupational Health and Safety Hazards

Though the scale of the proposed construction is small, it will involve climbing of poles to mount

electrical conductors and insulators which, coupled with activities associated with commissioning of

powered lines are wrought with high inherent risks of accidents. Mitigation will be undertaken as

follows:-

(i) Health and Safety requirements:

The Contractor shall do everything in his power to secure the safety of his crew, third parties and this

property. Towards this, the Contractor shall comply with all standard and legally required health and

safety regulations gazetted under the Occupational Health and Safety Act (OSHA) 2007 and the Factories

and Other Places of Work Regulations and shall submit Method Statements covering the procedures for

the main activities which could generate emergency situations through accidents or neglect of

responsibilities. These situations include, but are not limited to accidents at the work place including

wildlife invested areas, accidental fires; accidental leaks and spillages and vehicle and plant accidents.

Specific to accidents at work place:

• The Contractor shall also ensure that the necessary equipment for work in hazardous area –

protective boots, PPEs, helmets, etc are provided.

• The Contractor shall provide a standard first aid kit to field staff;

• The Contractor shall be responsible for the protection of the public and public property from

any dangers associated with construction activities, and for the safe and easy passage of

pedestrians and traffic in areas affected by the construction activities;

• All works which may pose a hazard to humans and domestic animals are to be protected,

fenced, demarcated or cordoned off as instructed by the RE. If appropriate, symbolic warning

signs must be erected;

• Speed limits appropriate to the vehicles driven are to be observed at all times on access and

haul roads. Operators and drivers are to ensure that they limit their potential to endanger

humans and animals at all times by observing strict safety precautions;

• No unauthorized firearms are permitted on site.

(ii) Fire Prevention and control:

The Contractor shall take all reasonable and precautionary steps to ensure that fires are not started as a

consequence of his activities on site. Activities are specified as follows:-

• The Contractor shall ensure that there is basic fire-fighting equipment available on site;

• Flammable materials should be stored under conditions that will limit the potential for ignition

and the spread of fires;

• Hot’ work activities shall be restricted to a site approved by the RE;

Page 70: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

58

• Smoking shall not be permitted in those areas where there is a fire hazard. These areas shall

include any areas (e.g. bushlands) where vegetation or other material can make liable the rapid

spread of an initial flame.

• The Contractor shall ensure that all site personnel are aware of the fire risks and how to deal

with any fires that occur. This shall include, but not be limited to regular fire prevention talks

and drills and, posting of regular reminders to staff.

• Any fires that occur shall be reported to the RE immediately and then to the relevant

authorities;

• In the event of a fire, the Contractor shall immediately employ such plant and personnel as is at

his disposal and take all necessary action to prevent the spread of the fire and bring the fire

under control;

• Costs incurred through fire damage will be the responsibility of the Contractor, should the

Contractor’s staff be proven responsible for such a fire.

(iii) Control of Solid Waste:

All storage and construction sites are to be kept clean, neat and tidy at all times. No burying or dumping

of any waste materials, metallic waste, litter or refuse shall be permitted. The Contractor must adhere

to Environmental Management and Co-ordination (Waste Management) Regulations 2006. The

Contractor shall implement measures to minimize waste and develop a waste management plan to

include the following:-

• All personnel shall be instructed to dispose of all waste in a proper manner;

• At all places of work the contractor shall provide litter collection facilities;

• The final disposal of the site waste shall be done at the location that shall be approved by the

RE, after consultation with local administration and local leaders;

• The provision of sufficient bins (preferably vermin and weatherproof) at the camp and work

sites to store the solid waste produced on a daily basis;

• Wherever possible, materials used or generated by construction shall be recovered at the

conclusion of each task for safe disposal including recycling.

• Provision for responsible management of any hazardous waste generated during the

construction works.

(iv) General materials handling, use and storage:

All materials shall be stored within the Contractors camp unless otherwise approved by the RE;

• Stockpile areas shall be approved by the RE;

• All imported fill, soil and/or sand materials shall be free of weeds, litter and contaminants.

Sources of imported materials shall be listed and approved by the RE;

• The Contractor shall ensure that delivery drivers are informed of all procedures and restrictions

(including ‘No go’ areas) required;

• Any electrical or petrol driven pumps shall be equipped and positioned so as not to cause any

danger of ignition of the stored product;

• Collection containers (e.g. drip trays) shall be placed under all dispensing mechanisms for

hydrocarbons or hazardous liquid substances to ensure no contamination from any leaks is

reduced;

• Regular checks shall be conducted by the Contractor on the dispensing mechanisms for all above

ground storage tanks to ensure faulty equipment is identified and replaced in timely manner;

Page 71: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

59

• Only empty and externally clean tanks may be stored on bare ground. All empty and externally

dirty tanks shall be sealed and stored on an area where the ground has been protected.

8.4.4: Management of Health and Safety Hazards within institutions and market centers

All construction work within school compounds will be confined to non-school days including week

ends. At all times however, the Safety Code promoted by the KPLC will always be observed by the

Contractor.

8.4.5 : Modalities for conflict resolution

In every administrative location within the traversed, the contractor will seek to enlist 2 respected

village elders who will resolve all disputed associated with the power distribution line. This is the same

team who will mobilize the community towards a final handing over meeting where all outstanding

disputes will be addressed before the Contractor hands over the project. The Final payment will only be

released upon submission of minutes from the final handover meeting showing clear attendance and

signed by the said elders’ teams.

8.5 Mitigation of Impacts at Operation Stage

Proposed mitigation activities at this stage are focused on minimizing hazards associated with presence

of electricity. Hazards of electrocution, fire outbreak etc cannot be eliminated entirely. However,

professional design and implementation of electricity supply schemes coupled with implementation of a

public sensitization campaign will greatly reduce incidence of accidents.

Towards promoting use of RETs:

Towards ensuring that supply of grid electricity does not discourage use of other RETs, solutions can

only be sought at policy level. However, adoption of a pricing mechanism that provides electricity

consumers with incentives to conserve grid power through adoption of available conservation packages

including use of RETs is one option towards sustaining the search for alternatives. Indeed, the

disincentive towards search for other energy alternatives is the main drawback associated with supply of

electricity. It is a drawback that has no readily available means for mitigation currently.

Mitigating impacts of electrocution:

Accidental electrocution is mainly mitigated through reservation and maintenance of the wayleave. REA

will undertake routine maintenance of the ROW to clear all vegetation and settlements. . All power

poles will be girdles with spiked wire to discourage climbing and will be fitted with warning (Hatari) signs

to alert all to the danger posed by presence of charged power lines.

8.6 Effectiveness of the Mitigation programme

8.6.1 Viability of Mitigation

Effectiveness of the proposed mitigation programme has been assessed based on analysis of impact

prevalence before and after mitigation (Table 8.2) based on this analysis, this Environmental and Social

Impact Assessment Study observes that, there is a great potential to mitigate adverse impacts and

hence improve the net worth of the proposed distribution lines. From Table 8.2, it is apparent that

Page 72: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

60

application of mitigation measures as identified and recommended has potential to reduce tally of

adverse impacts (Ns) from 16 to 8 while simultaneously increasing the positive ones (Ps) from 17 to 18.

Thus, subtracting the Ns from the Ps gives an overall net tally of 10P implying a very positive net impact

after mitigation.

Table 8.3: Analysis of impacts scenario before and after mitigation

Nature of impact Pre-mitigation tally Post-mitigation tally

Positives 17P 18P

Negatives 16N 8N

Net 1P 10P

Residue impacts 8N

Irreversible adverse impacts 3 3

Overall, the proposed project enjoys a highly positive benefits profile as it will strongly support

initiatives towards poverty alleviation and reversal of environmental-degradation both of which are

critically important policy aspirations of the Kenya Government. This Study recommends that project

development should proceed but factor in the mitigation measures recommended herein.

Implementation of this EMP will however require close follow-up and scrutiny to ensure achievement

and substance of this esteemed net positive profile of the project. Requirements for monitoring are

explored below.

8.6.2 Prevalence of residue impacts

This study observes that 8 of the 16 adverse impacts associated with the project will persist even after

mitigation. These are the impacts whose probability can be reduced substantially through mitigation but

cannot be eliminated entirely. Their management requires implementation of a strict monitoring

programme as outlined elsewhere below.

8.6.3 Management of decommissioning

Design of power distribution lines assumes an economic life of 25-30 years for wooden poles and 40

years for distribution cables which imply that, at some point, the system will require to be

decommissioned either in whole or by components. Concerns associated with decommissioning would

include occupational health and safety hazards, accumulation of scrap metal waste, electrical

conductors, insulators and other components which apart from taking up productive space would also

pose diverse hazards (health and safety, harboring of vermin, etc) to local inhabitants and their

property. The ESMP unveiled below has explicit requirements for management of decommissioning

phase impacts.

8.7 Monitoring requirements

8.7.1 The concepts

Monitoring involves the collection and analysis of data about project activities. The data should be easy

to collect and easy to understand. The focus of monitoring is to use the knowledge gained to correct and

adjust project implementation and management in order to achieve project objectives. Monitoring

allows project participants to keep track of project activities, to determine whether project objectives

are being achieved, and to make whatever changes are necessary to improve project performance.

Page 73: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga

Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

61

To be successful, monitoring begins with clear project design followed by identification and elaboration

of appropriate criteria and indicators. This document provides guidance about incorporating monitoring

and evaluation elements in each stage of the project cycle.

Indicators and means of verification in M&E: Indicators form the key elements of any monitoring and

evaluation system. The advantage of identifying indicators is that it provides management and staff with

a clear set of targets at each level of performance and ensures that progress can be measured against

the targets. Indicators also make possible the comparison of inputs with the completion of outputs and

achievement of objectives and goals, thus providing the basis for performance evaluation. For purposes

of this Project Report, indicators have been formulated to facilitate monitoring of compliance in

implementing the project.

8.7.2 Procedure for M&E in project development

Table 8.3 below provides the matrix of Environmental and Social Management and Monitoring as

proposed for the development of a 33 kV distribution line. From this plan, it is clear that most mitigation

activity will take place at the construction stage having been allowed for at the design stage. This study

recommends this ESMP to be applied further as follows:-

(i) The ESMP will be integrated into the Design Report- as a standalone chapter and also to

moderate design decisions

(ii) Further, it will be integrated into the BOQs to ensure funding allocation of environmental and

social mitigation.

(iii) Ultimately, Contracts for Construction will bear clauses from the ESMP to ensure that the

contractor is legally bound to implement impact mitigation

The ESMP in table 8.2 provides a detailed framework of issues, indicators and responsibilities in

monitoring the project.

Page 74: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate

Constituency) 33 kV power distribution line

62

Table 8.4: Matrix for Environmental and Social Management and Monitoring (ESMP)

Project Phase Source of

Impact

Potential Impact Mitigation measures Budget

(Ksh 000)

Responsible

Cost Head

Objectively

Verifiable Indicators

Monitoring *

Authority

Design Stage Design

Studies, field

surveys and

inventories

Creation of temporary opportunities for

gainful employment

Generation of additional site-specific data

/study reports

Capacity building and sensitization

Minor accidents during survey work Deploy competent staff Exercise

already

completed

Construction

Phase

Supply of

materials

Business opportunities in supply and

transport of construction materials

Road hazards in material transportation Transporters to follow

highway code

Contract for

material

supply

Contractor Ditto REA BOM

Construction

work

Short-term opportunities for business and

employment in construction

Revenue to GoK and Local Authorities

through taxes

Damage of property (tree crops) from ROW

corridor

Just compensation for all

displaced assets

2,000 REA Negotiated

agreements with

PAPs

REA BOM

REA to support local

reforestation projects

2,000 REA No of seedlings

raised and planted

REA BOM

Occupational health and safety concerns for

construction crew

Deploy sober, competent

crew with supervision.

Provide PPEs.

Contract for

Construction

Contract for

Construction

Clause in contract for

construction

REA BOM

Solid wastes from construction activity Apply the 3 Rs concept. Contract for

construction

Contract for

Construction

Clause in contract for

construction

REA BOM

Mitigation of conflict over use of road

reserve

REA to consult road sector

stakeholders in the design and

construction of power lines in

road reserves

Internal

budget

REA Clause in the REA

code Service Charter

REA BOM

Law review to allow legally Internal REA Draft Bill or REA BOM

Page 75: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate

Constituency) 33 kV power distribution line

63

Project Phase Source of

Impact

Potential Impact Mitigation measures Budget

(Ksh 000)

Responsible

Cost Head

Objectively

Verifiable Indicators

Monitoring *

Authority

coordinated multiple use of

road reserves

budget Regulations

Operation

Phase

Presence of

powered lines

Economic gains from improved and

stabilized power supply

Enhanced delivery of services in medicare,

education, admin, telecommunication, etc

Financial gains in oil to electricity

substitution, and elimination of

maintenance costs for diesel engines, etc

Employment creation, reduced cost of

investment

Cutting down on GHG emissions due to

petroleum to electricity substitution

Reduction in solid waste from lead acid

batteries, dry cells, candle residues, waste

oil/ spares from gensets etc

Adverse

impacts from

charged high

voltage power

lines

Exposure to Electromagnetic Fields (EMF) Threat not fully appreciated

but small for low voltage lines

Impact on avifauna and other wildlife from

presence of charged wires

Use of insulted conductors Contract for

supervision

Contract for

supervision

Clauses in design

report and contract

REA BOM

Hazards in attempted vandalism of

transformers

REA to mount community

sensitization campaign

1,000 REA No of sensitisation

meetings held

Disincentive on use of other Renewable

Energy Sources e.g. RETs

Outreach programme to

promote alternatives to grid

power

2,000 REA Internal

budget

Ditto REA BOM

Page 76: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

64

8.7.3 Requirements for Compliance Monitoring

Compliance monitoring will be mainstreamed into the overall project monitoring system.

Compliance monitoring will be based on the ESMP (Table 8.3) and will mainly vest on three

institutions namely the REA in the capacity of Employer, ERC in the capacity of regulator in the

power sector and NEMA in the capacity of environmental regulator. The roles of all stakeholders in

facilitating achievement of project goals are enumerated in sections below. Tools will be used for

monitoring as follows:-

• Completion certificates issued by the Resident Engineer (Supervisor of Works) on behalf of

the REA

• REAs internal monitoring reports

• Monitoring reports submitted to NEMA annually

• Monitoring reports produced by the ERC in capacity of regulator in the power sector.

Overall, the responsibility for securing overall soundness and viability of the project vests with the

REA in the capacity of proponent and employer in this project.

8.8 Roles and Responsibilities in implementing the EMP

This Environmental and Social Impact Assessment identifies several crucial players in executing

impact mitigation measures for the proposed development of 33 kV distribution line. They include:-

The Design Engineer: The design stage of the project is crucial as the point when mitigation

measures are inbuilt into the project design and those with financial implications allowed for in the

BOQs. Given this consideration, the Design Engineer plays a very crucial role in incorporating findings

from the environmental assessment into the project design and ensuring compliance by contractors.

The Project Contractor(s): For purposes of this ESIA, the Project Contractor will play the crucial role

of offsetting impacts associated with construction activities including those along the material

supply chain. Employment of professionally competent contractors is therefore crucial to

achievement of the goals of this ESIA. Clauses binding the contractor to implement impact mitigation

in course of civil works will be inbuilt into the Contract for Works and subsequently supervised by

the Design Engineer.

REA: In its capacity as the Employer in the project the REA has overall responsibility of securing the

technical and economic viability of the REP in line with performance contract and national policy

aspirations. REA will also ensure that the proposed project complies with all statutory requirements.

The National Environment Management Authority-NEMA: EMCA 1999 allows for formation of the

National Environmental Management Authority NEMA as the body charged with overall

coordination of environmental protection in Kenya. To fully pursue this mandate, NEMA has gazette

Legal Notice 101 of June 2003 which among others require that Annual Audit reports be filed for any

project granted Environmental Licensing by the Authority. In line with this regulation, audit reports

in respect of this power distribution line will be filed by REA annually.

The Electricity Regulatory Commission (ERC): Among many functions, the ERC is mandated to

license and undertake technical audit of activities of all players in the Power Sector in Kenya and is

therefore a crucial stakeholder in the power sector. The Standards Act, Chapter 496 of the Laws of

Kenya empowers the ERC to enforce safety regulations and to ensure that electrical apparatus and

Page 77: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

65

works meet the standards set by the Kenya Bureau of Standards or, where no such standards exist,

with the relevant international standards approved by the Kenya Bureau of Standards.

8.9 Budget for Environmental and Social Mitigation

The sum of Ksh Seven million (7,000,000) will be required to finance both social and environmental

mitigation of the project.

Page 78: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

66

9 CHAPTER NINE: CONCLUSION AND RECOMMENDATIONS

9.1 The Project

The subject of this Project Report is the proposed 35.3 Km long Mwachabo power distribution line

project being developed by the Rural Electrification Authority-REA on behalf of the Kenya

Government. The Report has been prepared for REA by Repcon Associates in line with the

Environmental Management and Coordination Act, 1999 and Legal Notice No. 101 of June 2003. The

report examines the project in terms of the proposed development, possible adverse impacts at

both construction and operation phases and provides an Environmental and Social Plan.

9.2 Study Methodology pursued

The systematic investigative and reporting methodology specified for conduct Project Reports by

Legal Notice 101 of EMCA was adopted in this Study. Baseline data on project design was generated

through discussion with the client and review of project documentation. Opinions formed were

revalidated through field work entailing site investigations and interviews with potentially affected

people and secondary stakeholders.

To identify, predict, analyze and evaluate potential impacts that may emanate from the project,

diverse study methods and tools including use of checklists, matrices, expert opinions and

observations were employed. An Environmental and Social Management Plan comprising an impact

mitigation plan and modalities for monitoring and evaluation were then developed to guide

environmental management during all phases of project development.

9.3 Findings from the Study

9.3.1 Overview of impacts

It must be pointed out that the scope of adverse impacts associated with construction of 35.3

kilometers of a medium voltage power distribution line in an otherwise low density agricultural

settlement is inherently low. Thus for the proposed power line, this study has identified a total of 34

impacts, 17 of which are positive. Other trends in impacts are as follows:-

• Half of the 34 impacts likely to be occasioned by the proposed construction and operation of

the 35.3 kilometres of power distribution line are negative.

• Ten of the 17 positive impacts are likely to be long-term in prevalence while 7 out of 8

adverse impacts have a long-term effect with 2 of them being potentially irreversible.

• Nine out of sixteen adverse impacts have potential to cause secondary impacts while 6 of

them have cumulative tendency i.e., they have potential to aggravate an already existing

problem.

• The project has a net neutral impact pre mitigation which will require to be enhanced

through adoption of an effective impact mitigation strategy.

9.3.2 Nature of the potential positive impacts anticipated

Positive implications of the project emanate from its potential to create short-term business and

employment opportunities to both professional staff and workers during the design phase while, at

construction phase, traders will benefit from opportunities to supply construction material while

locals will be employed in works. Upon commissioning, the project could supply electric power to

one dispensary, several schools and 5 rural trading centers where the potential to unlock business

potential is real. Through adoption of electric power and cutting down on use of fossil fuels, the

Page 79: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

67

project has potential to favor cutting down on Green House Gas emissions to the benefit of the

global climate.

9.3.3 Nature of the Potential adverse impacts/concerns

Core adverse impacts could include the following:-

Displacement of trees and property: The proposed route of traverse is a semi arid rangeland

dominated by low growing acacia woodland formation whose height is well below the standard

height of power distribution lines in which case potential damage is likely to be minimal.

Hazards to road users: Construction activity including transport of materials to the site and actual

building of the power distribution line poses occupational health and safety hazards to both

construction crew and third parties.

Conflict over use of road reserves: Unless properly coordinated, construction of power lines has

recently been observed to occasion conflicts over the use of road reserves and the same can recur in

regard of proposed power line.

Hazards posed by powered lines: Further, presence of the line changes the local landscaper and

skyline and such intrusion into space is a kind of pollution, not mentioning the perpetual hazards

introduced by presence of a powered line.

9.4 The Environmental and Social Management and Monitoring Plan

An Environmental and Social Management and Monitoring Plan (ESMP) comprising both an Impact

Mitigation Plan (IMP) and Monitoring Plan (MP) has been developed for the project.

9.4.1 The Impact Mitigation Plan:

The bulk of impacts including nuisances, occupational health and safety issues, social impacts of

construction crew etc are associated with construction activity and will thus cease once construction

ends. Requisite intervention has been identified as follows:-

Mitigation of impacts of tree removal: All proposed tree removal will have to be coordinated with

County Agricultural Officers in Line with the Agriculture (Farm Forestry) Rules 2009. Further, REA will

pay just and prompt compensation for all trees removed or lopped. Further, towards rebuilding lost

vegetation cover, REA will identify and support a local group to raise and plant tree seedlings in the

route of traverse. REA will follow and monitor progress of said trees to ensure achievement of

highest survival possible.

Mitigation of Health and safety impact: The Contractor will be bound in contract to implement the

Code of Safety as outlined in 8.4 above. The core mitigation strategy is to optimize on construction

time so as to reduce the time taken to complete all civil works. The Contractor will deploy sober

competent staff working under competent supervisors. In addition to provision of protective gear, all

workers will be covered under the Workman Compensation Scheme.

Mitigation of potential for conflict in use of the road reserves: At the design stage, REA will engage

all road sector stakeholders to agree on mutually acceptable sharing of the target road reserves but

in the long run, this matter will require legal resolution.

Mitigation of hazards associated with presence of a powered line: Towards curbing vandalism of

the power distribution line and associated hazards, the REA will mount public sensitization

campaigns in the affected area and will ensure that the property is promptly handed over to the

Page 80: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

68

community. As well, the contractor should be held liable for all vandalism during the defect liability

period.

9.4.2 Effectiveness of the Mitigation Plan

Based on analysis of impact prevalence before and after mitigation it is evident that, application of

mitigation measures as identified and recommended has potential to totally eliminate most impacts

and greatly tone down others. However, 8 of the eighteen adverse impacts associated with the

project will persist even after mitigation. These are the impacts whose probability can be reduced

substantially through mitigation but cannot be eliminated entirely. Their management requires

implementation of a strict monitoring programme which has already been outlined within this

report.

9.4.3 Total Cost in Environmental and Social Mitigation

A total Ksh 7 million will be required to offset the social and environmental impacts associated with

the project.

9.5 The Monitoring Strategy

The Mitigation strategy proposed is largely focused on ensuring that mitigation action will be

implemented. Requirements for this are as follows:-

i) The responsibility for ensuring total environmental worth of the proposed project vests with

REA in the capacity of proponent. Towards this, the proponent will retain and deploy the

team of highly motivated environmental and social scientists to monitor and report on all

stages of the project.

ii) The ESMP as outlined above be integrated into the Design Report with appropriate

allocation of funds in the Bills of Quantities.

iii) The Contractor will prepare routine reports which will be ascertained by the Supervising

Consulting Engineer before Payment Certificate can be issued.

iv) The contract for construction should bear clauses binding the contractor to implement

impact mitigation as part of the civil works. Environmental stabilization works will be

covered under the defect liability period.

v) REA will mount own internal monitoring to ensure that impact mitigation has been

implemented and will file annual audit reports with NEMA.

vi) The proposed project will adhere to all other laws of the land and will seek and obtain all

requisite statutory permits.

9.6 Recommendations of this Project Report

The proposed development of a power distribution project is largely aligned to reigning GOK Policies

for national development. The project enjoys a highly positive benefits profile as it will strongly

support initiatives towards poverty alleviation and reversal of environmental-degradation both of

which are critically important policy aspirations of the Kenya Government. This Study recommends

that project development should proceed but factor in the mitigation measures recommended

herein. REA in the capacity of proponent will require to closely monitor activities especially at

construction stage and simultaneously avail funds for environmental and social restoration.

Our recommendation is for the project to be licensed to proceed to the next level of development.

REFERENCES

Page 81: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

69

1. Foliart D. E., Pollock B. H, G. Mezei, R Iriye, J M Silva, K L Ebi, L Kheifets, M P Link, and R Kavet,

2006:

Magnetic field exposure and long-term survival among children with leukemia. British

Journal of Cancer 16; 94(1): 161-164. Cancer Research UK. 2006

2. ERB (2005): Environmental, Health & Safety Policy Framework for the electric power sub-sector.

ERB Head Office, Nairobi.

3. OGALLO, L. (1979), Rainfall variability in Africa. Monthly Weather Revision, 107: pp. 1133-1139.

4. Republic of Kenya, Ministry of Energy, 2000: Study on Energy, Demand, Supply and Policy

Strategy for Households, Small Scale Industries and Services Establishments in Kenya. Ministry

of Energy, Nairobi.

5. UNEP & WMO, (1991): Greenhouse Gas Inventory Reporting Instructions Final Draft. IPCC Draft

Guidelines for National Greenhouse Gases Inventories Vol I. IPCC & OECD joint programme.

6. UNEP & WMO, 1991): Greenhouse Gas Inventory Reporting Instructions Final Draft. IPCC Draft

Guidelines for National Greenhouse Gases Inventories Vol I. IPCC & OECD joint programme.

Page 82: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

70

APPENDICES:

Appendix 1.1: Statutory registration for Repcon Associates

Appendix 1.2: NEMA registration for Study Team

Appendix 1.3: List of documents and data sources consulted

Appendix 2.1: Bills of Quantities for the power distribution line

Appendix 5.1: Nairobi based consultations

Appendix 5.2: Project specific consultations in Taita Taveta County

Appendix 7.1: Third Schedule to Legal Notice 101

Appendix 7.2: Leopold Matrix

Page 83: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

71

Appendix 1.1: Statutory registration for Repcon Associates

Page 84: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

72

Page 85: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

73

Appendix 1.2: NEMA registration for Study Team

Page 86: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

74

Page 87: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

75

Page 88: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

76

Page 89: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

77

Appendix 1.3: List of documents and data sources consulted

Page 90: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

78

REFERENCES

1. Foliart D. E., Pollock B. H, G. Mezei, R Iriye, J M Silva, K L Ebi, L Kheifets, M P Link, and R Kavet, 2006

:

Magnetic field exposure and long-term survival among children with leukemia. British Journal of Cancer

16; 94(1): 161-164. Cancer Research UK. 2006

2. ERB (2005): Environmental, Health & Safety Policy Framework for the electric power sub-sector. ERB Head

Office, Nairobi.

3. OGALLO, L. (1979), Rainfall variability in Africa. Monthly Weather Revision, 107: pp. 1133-1139.

4. Republic of Kenya, Ministry of Energy, 2000: Study on Energy, Demand, Supply and Policy Strategy for

Households, Small Scale Industries and Services Establishments in Kenya. Ministry of Energy, Nairobi.

5. UNEP & WMO, (1991): Greenhouse Gas Inventory Reporting Instructions Final Draft. IPCC Draft Guidelines

for National Greenhouse Gases Inventories Vol I. IPCC & OECD joint programme.

6. UNEP & WMO, 1991): Greenhouse Gas Inventory Reporting Instructions Final Draft. IPCC Draft Guidelines

for National Greenhouse Gases Inventories Vol I. IPCC & OECD joint programme.

Page 91: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

79

Appendix 2.1: Bills of Quantities for the power distribution line

Page 92: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

80

Page 93: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

81

Page 94: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

82

Page 95: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

83

Page 96: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

84

Appendix 5.1 Nairobi based consultations

Page 97: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

85

Page 98: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

86

Page 99: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

87

Page 100: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

88

Page 101: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

89

Page 102: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

90

Appendix 5.2: Project specific consultations in Taita Taveta County

Page 103: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

91

Page 104: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

92

Page 105: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

93

Page 106: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

94

Page 107: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

95

Page 108: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

96

Page 109: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

97

Appendix 7.1: Third Schedule to Legal Notice 101

Page 110: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

98

THIRD SCHEDULE

GENERAL GUIDELINES FOR CARRYING OUT AN ENVIRONMENTAL

IMPACT ASSESSMENT STUDY

An environmental impact assessment study shall be conducted in accordance with the general

environmental impact assessment guidelines and administrative procedures issued by the

Authority. An environmental impact assessment study shall include the following:

1. Sources of Impact

2. Project Inputs

3. Project Activities

4. Areas of Impact on the Natural and Human Environments

5. Environmental Impacts (General Impacts on the Natural and human Environment)

6. Environmental Guidelines and Standards (National Legislation, International

guidelines. International Conventions and Treaties)

7. Mitigation Measures

8. Environmental Management Plan

9. Environmental Monitoring and Auditing.

Page 111: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

99

Appendix 7.2: Leopold Matrix

Page 112: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

100

Summary Matrix of Environmental Impact Assessment for proposed the Mwachabo Market

and Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate

Constituency) 33kV power distribution line

POTENTIAL IMPACTS OF PROJECT DECISION

1. Agricultural Lands

a) Are there cultivable lands in the area? Yes No Unk

b) Will project decision result in more or improved cultivable land? Yes No Unk

c) Will project decision result in less or damage cultivable land? Yes No Unk

ESTIMATE IMPACT ON AGRICULTURAL LAND:

ND HA MA LA LA O LB HB

2. Soil Erosion

a) Will project decision help to prevent soil loss or erosion Yes No Unk

b) Will project decision directly cause or worsen soil loss or

erosion?

Yes No Unk

c) Could project decision indirectly lead to practices that could

cause soil loss or erosion? Yes No Unk

d) Is it necessary to consult a soils scientist Yes No Unk

ESTIMATED IMPACT ON SOIL EROSION:

ND HA MA LA LA O LB HB

3. Slope Stability

a) Does project decision involve actual modification of slopes Yes No Unk

b) Will project decision affect stability of slopes indirectly Yes No Unk

c) Will project decision result in slope stability? Yes No Unk

d) Could project decision cause people livestock or property to be

located where existing unstable slopes could be a hazard?

Yes No Unk

e) Is it necessary to consult a geo-technical engineer? Yes No Unk

ESTIMATED IMPACT ON SLOPE STABILITY:

ND HA MA LA LA O LB HB

4. Energy - Mineral Resources

a) Do energy - mineral resources exist in project area? Yes No Unk

b) Will project decision help to develop, now or in the future,

important energy-mineral resources?

Yes No Unk

c) Will project decision cause significant consumption of additional Yes No Unk

Page 113: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

101

energy -mineral resources such as engine fuels?

d) Could project decision prevent or impede future development of

essential energy-mineral resources?

Yes No Unk

e) Is it necessary to consult with a minerals agency or mining

engineer?

Yes No Unk

ESTIMATED IMPACT ON ENERGY/ MINERAL RESOURCES:

ND HA MA LA LA O LB HB

5. Surface Water Quantity

a) Do surface water resources exist in project area? Yes No Unk

b) Is information available on present and future demands on water

resources as result of the project?

Yes No Unk

c) Will project decision help to increase or preserve available

surface water supplies by such things as improved drainage / run-

off conditions?

Yes No Unk

d) Will project decision increase demand or cause loss of available

surface water directly or indirectly?

Yes No Unk

e) Is it necessary to consult a hydrologist? Yes No Unk

ESTIMATED IMPACT ON SURFACE WATER QUANTITY:

ND HA MA LA LA O LB HB

6. Surface Water Quality

a) Is information available on present water quality? Yes No Unk

b) Will project decision lead to additional natural or man made

discharges into surface waters?

Yes No Unk

c) Will project decision help to improve or protect surface water

quality?

Yes No Unk

d) Could project decision cause deterioration of surface water

quality either directly or indirectly?

Yes No Unk

e) Is it necessary to consult a water quality engineer or agency? Yes No Unk

ESTIMATED IMPACT ON SURFACE WATER QUALITY:

ND HA MA LA LA O LB HB

7. Ground Water Quantity

a) Do ground water resources exist in project area? Yes No Unk

b) Is information available on present and future demands on water

resources as result of the project?

Yes No Unk

Page 114: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

102

c) Will project decision help to increase or preserve available ground

water supplies by such things as improving recharge conditions?

Yes No Unk

d) Will project decision increase demand or cause loss of available

ground water either directly or indirectly?

Yes No Unk

e) Is it necessary to consult a hydrogeologis? Yes No Unk

ESTIMATED IMPACT ON GROUNDWATER QUALITY:

ND HA MA LA LA O LB HB

8. Ground Water Quality

a) Is information available on present water quality? Yes No Unk

b) Will project decision cause any natural or man made discharges

into ground aquifers?

Yes No Unk

c) Could project decision cause deterioration of ground water quality? Yes No Unk

d) Could project decision cause deterioration of ground water quality

either directly or indirectly?

Yes No Unk

e) Is it necessary to consult a ground water quality specialist? Yes No Unk

ESTIMATED IMPACT ON GROUND WATER QUALITY.

ND HA MA LA LA O LB HB

9. Air Quality

a) Is information available on existing air quality? Yes No Unk

b) Will project decision produce any air emission directly? Yes No Unk

c) Will project decision help to reduce existing air pollution sources

such as open burning operations?

Yes No Unk

d) Could project decision lead to practices that worsen air quality such

as causing increased road traffic or industrialization?

Yes No Unk

e) Could project decision lead to a change in engine use or fuel

combination that could cause serious air problems?

Yes No Unk

ESTIMATED IMPACT ON AIR QUALITY:

ND HA MA LA LA O LB HB

10. Noise

a) Is noise now a problem in project area? Yes No Unk

b) Will project help in reducing undesirable noise conditions? Yes No Unk

c) Will project cause temporary or sustained increases in noise

generation conditions such as heavy machinery or road travel?

Yes No Unk

d) Could project cause movements of people to high noise level Yes No Unk

Page 115: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

103

locations?

e) Is it necessary to consult a noise specialist? Yes No Unk

ESTIMATED IMPACT ON AIR QUALITY:

ND HA MA LA LA O LB HB

11. Aquatic Ecosystems

a) Are there any aquatic ecosystems of which the types listed below

which, by nature of their size, abundance or type, can be considered

significant or unique?

River?

Streams?

Lakes?

Ponds?

Yes No Unk

b) Are these systems essentially:

Pristine?

Moderately degraded?

Severely degrade?

Ponds?

Yes

Yes

Yes

No

No

No

Unk

Unk

Unk

c) Are these systems used by the local people:

i) Consumptively

For drinking water?

For Irrigation?

For livestock?

ii) Non-consumptively

For washing and bathing?

For waste Disposal?

For Transportation?

For Harvest of non-domesticated

plants or animals as food, fiber

animals as food, fiber fur or other

useful products?

Yes

Yes

Yes

No

No

No

Unk

Unk

Unk

d) Will the project directly affect consumption use of water? Yes No Unk

e) Will the project directly or indirectly affect either non-consumptive

or consumptive uses of these ecosystems by:

Use or production of toxic material (both during

construction and / operation) which might enter these

systems?

Alteration of drainage?

Increasing erosion?

Causing increase in populations so as to place added stress

on their systems?

Yes

Yes

Yes

Yes

No

No

No

No

Unk

Unk

Unk

Unk

ESTIMATED IMPACT ON AQUATIC ECOSYSTEMS:

ND HA MA LA LA O LB HB

12. Wetland Ecosystems

b) Are these systems

Pristine?

Yes

No

Unk

Page 116: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

104

Moderately degraded?

Severely degraded?

Yes

Yes

No

No

Unk

Unk

c) Are these systems used by local people For:

Drinking water?

Livestock Water?

Washing and Bathing?

Waste Disposal?

Agriculture?

Harvest on non-domesticate plants or animals as food, fur, or

fiber?

Yes

Yes

Yes

Yes

Yes

Yes

No

No

No

No

No

No

Unk

Unk

Unk

Unk

Unk

Unk

e) Will the project either directly or indirectly affect wetlands by:

Changing population or land use practices so as to

increase Drainage of wetlands for use as agricultural, industrial

or urban land?

Use or production (either during construction and /

operation of toxic materials which might enter wetlands?

Use the water directly?

Alter drainage patterns so as to affect wetlands?

Increase erosion so as to affect wetlands?

Yes

Yes

Yes

Yes

Yes

No

No

No

No

No

Unk

Unk

Unk

Unk

Unk

ESTIMATED IMPACT ON WET LAND ECOSYSTEMS:

ND HA MA LA LA O LB HB

13. Terrestrial Ecosystems

a) Are there any aquatic ecosystems of which the types listed below

which, by nature of their size, abundance or type, can be

considered significant or unique?

Forest?

Savanna?

Grassland?

Desert?

Yes

Yes

Yes

Yes

No

No

No

No

Unk

Unk

Unk

Unk

Page 117: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

105

b) Are these ecosystem:

Pristine?

Moderately degraded?

Severely Degraded?

Yes

Yes

Yes

No

No

No

Unk

Unk

Unk

c) Are these present trends towards alteration of these ecosystems

through cutting, burning, etc. to produce agricultural, industrial, or

urban land?

Yes

No

Unk

d) Does the local population use these ecosystems to obtain non-

domesticated:

Food plants?

Medicinal Plants

Wood Products?

Fiber?

Fur?

Food Animals?

Yes

Yes

Yes

Yes

Yes

Yes

No

No

No

No

No

No

Unk

unk

Unk

Unk

Unk

Unk

e) Will the project require clearing or alteration of:

Small areas of land in these ecosystems?

Moderate areas of land in these ecosystems?

Large areas of land in these ecosystems?

Yes

Yes

Yes

No

No

No

Unk

Unk

Unk

f) Does the project rely on any raw materials (wood, fiber) from

these Ecosystems?

Yes

No

Unk

g) Will the project decrease use of products from these

ecosystems by producing or providing substitute

materials?

Yes

No

Unk

h) Will the project cause increased population growth in

the area, bringing about increased stress on these

ecosystem?

Yes

No

Unk

ESTIMATE IMPACT ON TERRESTRIAL ECOSYSTEMS:

ND HA MA LA LA O LB HB

Page 118: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

106

14. Endangered species

a) Is the existence of endangered species in the project

area:

Very unlikely

Probable

Highly probable

Documented fact

Yes

Yes

Yes

Yes

No

No

No

No

Unk

Unk

Unk

Unk

b) Are these species:

Of scientific interest only?

Of scientific interest and highly sought after by

local people for food, hides, sale to animal

dealers.

Yes

No

Unk

c) Will the project affect the habitat of these animals:

Directly by destruction of habitat?

Indirectly by altering habitat through changing

drainage, land use?

Yes

Yes

No

No

Unk

Unk

d) Will the project increase ease of access to these

habitats?

Yes No Unk

e) Will the project increase population in the project are,

thus placing increased pressure on these species and /

or on their habitat?

Yes No Unk

ESTIMATED IMPACT ON ENDANGERED SPECIES

ND HA MA LA O LB HB

15. Migratory Species

a) In the project area are there any:

Migratory fish

Migratory birds

Yes

Yes

No

No

Unk

Unk

Page 119: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

107

Migratory animals Yes No Unk

b) Are these species used by local people for food, fur, or

other products?

Yes

No.

Unk

c) Will the project require any dams, roads, pipelines or

other alignments which could interfere with these

migratory animals?

Yes

No

Unk

d) Will the project destroy any habitat (resting, feeding

reproductive) which are critical to these species?

Yes

No

Unk

e) Will increased population place additional stress on

these species?

Yes

No

Unk

ESTIMATED IMPACT ON MIGRATORY SPECIES

ND HA MA LA O LB HB

16. Beneficial Plants

a) Do non domesticated plants occur in the project area

which are used or sold by local peoples as:

Food?

Fiber?

Ornament?

Forage?

Building Materials

Yes

Yes

Yes

Yes

No

No

No

No

No

Unk

Unk

Unk

Unk

Unk

b) Do these plants occur in :

Undisturbed habitat?

Moderately disturbed habitat?

Severely disturbed habitat?

Yes

Yes

Yes

No

No

No

Unk

Unk

Unk

c) Are these plants:

Utilized heavily?

Utilized moderately?

Yes

Yes

No

No

Unk

Unk

Page 120: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

108

Utilized only occasionally? Yes No Unk

d) Is this use:

Peculiar to the local population?

Universal in the region / country?

Yes

Yes

No

No

Unk

Unk

e) Will the project:

Decrease habitat for these plants?

Increase access to these plants?

Provide substitute products or the necessary money

to replace the use of these plants through increased

population?

Yes

Yes

Yes

No

No

No

Unk

Unk

Unk

ESTIMATED IMPACT ON BENEFICIAL PLANTS

ND HA MA LA LA O LB HB

17. Beneficial Animals

a) Do non domesticated animals occur in the project area

which are used or sold by local people as:

Souvenir products?

Food?

Fur?

Pets?

Yes

Yes

Yes

Yes

No

No

No

No

Unk

Unk

Unk

Unk

b) Do these animals occur in:

Undisturbed habitats?

Moderately disturbed habitat?

Severely disturbed habitat?

Yes

Yes

Yes

No

No

No

Unk

Unk

Unk

Page 121: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

109

c) Are these animals:

Utilized heavily?

Utilized moderately?

Utilized only occasionally?

Yes

Yes

Yes

No

No

No

Unk

Unk

Unk

d) Is this use:

Peculiar to the local population?

Universal in the region/county?

Yes

Yes

No

No

Unk

Unk

e) Will the project:

Decrease habitat for these animals?

Increase habitat for these animals?

Increase access to these animals?

Provide substitute products or the necessary

money to replace the use of these animals?

Increase use of these animals through increased

population?

Yes

Yes

Yes

Yes

Yes

No

No

No

No

No

Unk

Unk

Unk

Unk

Unk

ESTIMATED IMPACT ON BENEFICIAL ANIMALS:

ND HA MA LA LA O LB HB

18. Pest Plants

a) Are there currently any pest plant problems in the

project area?

Yes

No

Unk

b) Are there any potential pest plant species known to

exist in the project area?

Yes

No

Unk

c) Are these pest plants associated with:

Severely disturbed land?

Agricultural land?

Stagnant or polluted water?

Yes

Yes

Yes

No

No

No

Unk

Unk

Unk

Page 122: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

110

d) Will the project:

Increased habitat for pest plants?

Decreased habitat for pest plants?

Provide opportunity for control of pest plants?

Increase the possibility of introduction of pest

plants through increased commerce?

Yes

Yes

Yes

Yes

No

No

No

No

Unk

Unk

Unk

Unk

ESTIMATED IMPACT ON PEST PLANTS:

ND HA MA LA O LB HB

19. Pest Animals

a) Are there currently any problems with pest animals in

the project area?

Yes

No

Unk

b) Are there any animals in the project area which, under

altered ecological conditions, have the potential for

becoming pest species

Yes

No

Unk

c) Are these species associated with:

Severely disturbed land?

Agricultural land?

Aquatic Habitats?

Yes

Yes

Yes

No

No

No

Unk

Unk

Unk

d) Will the project:

Increased habitat for pest animals?

Decreased habitat for pest animals?

Provide opportunity for control of pest animals?

Increase the possibility of introduction of pest

animals through increased commerce?

Provide the opportunity for control of pest

animals?

Yes

Yes

Yes

Yes

Yes

No

No

No

No

No

Unk

Unk

Unk

Unk

Unk

Page 123: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

111

ESTIMATED IMPACT ON PEST ANIMALS:

ND HA MA LA O LB HB

20. Disease Vectors

a) Are the known disease problems in the project area

transmitted through vector species such as mosquitoes,

flies, snails, etc?

Yes

No

Unk

b) Are these vector species associated with :

Aquatic habitats?

Forest habitats?

Agricultural habitats?

Degraded habitats?

Human settlements?

Yes

Yes

Yes

Yes

Yes

No

No

No

No

No

Unk

Unk

Unk

Unk

Unk

c) Will the project:

Increase vector habitat?

Decrease vector habitat?

Vector control?

Yes

Yes

Yes

No

No

No

Unk

Unk

Unk

d) Will the project work force be possible source of

introduction of disease vectors not currently found in

the project areas?

Yes

No

Unk

e) Will increased access to any commerce with the

project area be a possible source of disease vectors

not presently occurring in the project area?

Yes

No

Unk

f) Will the project provide opportunities for vector

control through improved standards of living?

Yes

No

Unk

ESTIMATED IMPACT ON DISEASE VECTORS:

ND HA MA LA LA O LB HB

21: Disease Vectors

a) Are vector-borne diseases an important part of the

Page 124: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

112

local public health situation? Yes No Unk

b) Are these clinics or other disease control programs in

operation or planned for the area?

Yes

No

Unk

c) Will the project decision result in an increase in

disease vector density or distribution?

Yes

No

Unk

d) Will the project decision result in workers of other

persons entering the area with contagious or vector

borne diseases?

Yes

No

Unk

e) Will the project decision result in clearing operations

that could expose workers to disease vectors?

Yes

No

Unk

g) Will the project decision increase the hazard of

accident to the local population to receive health

care?

Yes

No

Unk

h) Is it necessary to consult with a public health

specialist?

Yes

No

Unk

ESTIMATED IMPACT ON PUBLIC HEALTH:

ND HA MA LA O LB MB HB

22. Resource/Land-use

a) Are the natural resources of the area under intensive

use pressure?

Yes

No

Unk

b) Are lands in the project area intensively developed? Yes No Unk

c) Will the project decision increase pressure on land

resources?

Yes

No

Unk

d) Will the project decision result in workers or other

persons entering the area with contagious or vector

borne disease?

Yes

No

Unk

Page 125: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

113

e) Will the project decision result in clearing operations

that could expose workers to disease vectors?

Yes

No

Unk

f) Will the project decision increase the hazard of

accident to the local population?

Yes

No

Unk

g) Will the project decision improve opportunities for

the local population to receive health care?

Yes No Unk

h) Is it necessary to consult with a public health

specialist?

Yes No Unk

ESTIMATED IMPACT ON PUBLIC HEALTH

ND HA MA LA LA O LB HB

Conventional / Non-conventional Energy sources

a) Will the project increase the demand for conventional

energy sources (petroleum, hydropower)?

Yes

No

Unk

b) Will the project increase the demand for

nonconventional energy sources (fuelwood, dung,

agricultural wastes)?

Yes

No

Unk

c) Should an energy planner be consulted? Yes No Unk

ESTIMATED IMPACT ON ENERGY SOURCES:

ND HA MA LA O LB HB

23. Distribution Systems

a) Are the production / distribution networks for agricultural

and manufactured commodities fully understood?

Yes

No

Unk

b) Will the project decision enhance the equitable

distribution of these products?

Yes

No

Unk

c) Will the project decision increase the demand for certain

commodities within or outside the area?

Yes

No

Unk

Page 126: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

114

d) Will the project decision decrease the demand for

certain locally produced goods?

Yes

No

Unk

e) Will the project decision improve the ease with which

consumers in the area obtain commodities?

Yes

No

Unk

f) Will the project decision improve the ease with which

consumers in the area obtain commodities?

Yes

No

Unk

f) Is it necessary to consult a social anthropologist? Yes No Unk

ESTIMATED IMPACT ON DISTRIBUTION SYSTEMS

ND HA MA LA O LB HB

25. Employment

a) Is there potential work force in the area fully employed? Yes No Unk

b) Will the project decision substantially increase the rate

of employment?

Yes

No

Unk

c) Will the project decision remove job opportunities in the

area?

Yes

No

Unk

d) Will the project decision result in drawing workers from

other local employers?

Yes

No

Unk

e) Is it necessary to consult with a socioeconomist? Yes No Unk

ESTIMATED IMPACT ON EMPLOYMENT

ND HA MA LA LA O LB HB

26. At-Risk Population

a) Are the adverse impacts of the project unequally

distributed in the target population?

Yes

No

Unk

b) Have the at-risk groups been identified? Yes No Unk

Page 127: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

115

c) Have all possible actions been identified that would

lessen the impact on at-risk groups?

Yes

No

Unk

d) Is the assistance of a social anthropologist required to

adequately answer these questions?

Yes No Unk

ESTIMATED IMPACT ON AT-RISK POPULATION

ND HA MA LA LA O LB HB

27. Migrant population

a) Are there presently certain mobile groups in the target

population?

Yes

No

Unk

b) Will the project decision result in immigration of people

to the area?

Yes

No

Unk

c) Are local institutions and agencies adequately geared to

handle this influx?

Yes

No

Unk

d) Will the project decision result in the movement of

people out of the area?

Yes

No

Unk

e) Can their probable destinations be predicted? Yes No Unk

f) Are local institutions and agencies or receiving agencies

able to handle these migrant groups?

Yes

No

Unk

g) Is it necessary to consult a social anthropologist? Yes No Unk

ESTIMATE IMPACT ON MIGRANT POPULATION

ND HA MA LA O LB HB

28. Community Stability

a) Are the interrelationships of various social groups in the

project area understood?

Yes

No

Unk

Page 128: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

116

b) Will the project decision establish institutions that will

improve these interrelationships?

Yes

No

Unk

c) Will the project decision establish create competition

among social groups that would reduce community

cohesion?

Yes No Unk

d) Is it necessary to consult a social anthropologist? Yes No Unk

ESTIMATED IMPACT ON COMMUNITY STABILITY

ND HA MA LA O LB HB

29. Cultural and Religious Values

a) Have studies been conducted of the cultural values of

the project area?

Yes

No

Unk

b) Are the cultural characteristics unique to the project area

adequately known?

Yes

No

Unk

c) Will the project decision adversely affect the religious

attitudes of area residents?

Yes

No

Unk

d) Are there special superstitions or religious taboos that

will affect the acceptance of the project by the target

population?

Yes

No

Unk

e) Is it necessary to consult a social anthropologist? Yes No Unk

ESTIMATED IMPACT ON CULTURAL AND RELIGIOUS VALUES

ND HA MA LA O LB MB HB

30. Tourism and Recreation

a) Is there at present a significant degrees of tourism in the

area?

Yes

No

Unk

b) Is there un-exploited tourism or recreation potential in the

area?

Yes

No

Unk

c) Will the project decision result in more effective

Page 129: Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa

The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/

Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line

117

utilization of present or future tourism opportunities? Yes No Unk

d) If so, will this adversely affect an existing or potential

tourist or recreation attraction?

Yes

No

Unk

e) Will the project decision adversely affect an existing or

potential tourist or recreation attraction?

Yes

No

Unk

ESTIMATED IMPACT ON TOURISM AND RECREATION

ND HA MA LA O LB MB HB

31. Nutrition

a) Have adequate data been gathered on the nutritional

levels in the project area?

Yes

No

Unk

b) Do these data differentiate among various population

sub-groups, by age, sex or social level?

Yes

No

Unk

C) Will the project decision result in changed food habits

in the target population?

Yes

No

Unk

d) Will these changes result in improved nutritional

characteristics?

Yes

No

Unk

e) Are the services of a nutrition specialist required? Yes No Unk

ESTIMATED IMPACT ON NUTRITION

ND HA MA LA O LB MB HB