Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The...
Transcript of Project Report for the proposed Mwachabo Market and Pry ...documents.worldbank.org/curated/en/...The...
The Rural Electrification Authority-REA
Report prepared and submitted by
Repcon associates
The Repcon Center
Sigona 410 off KEFRI/KARI Rd-Muguga
P.O. Box 79605-00200, Nairobi
Telefax: 254-20-2248119; Mobile- 0721-274358/0736499399
E-mail:[email protected] April 2013
Project Report for the proposed Mwachabo Market and Pry/Manoa
Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate
Constituency) 33 kV power distribution line
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
ii
DISCLOSURE PAGE
This Project Report is hereby disclosed for public review as follows:-
Proponent: The Rural Electrification Authority-REA
Assignment: Project Report for the proposed Mwachabo Market, Pry/Manoa Disp/ Chunga
Unga Market/Dighai Market/ Kamtonga Market/Mkuki Market 33 kV power
distribution line
Firm of Experts: Repcon Associates- NEMA Registration No. 0002,
Contact address: The Repcon Center,
Sigona 410, off KEFRI/KARI Rd Muguga,
P.O. Box 79605-00200, Nairobi.
Telefax: 254-20-2248119; Mobile- 0721-274358/0736499399
E-mail:[email protected]
Signed: ...................................... Date..........................
Michael M. Wairagu
Lead Expert (0177)/ Team Leader
Proponent: The Rural Electrification Authority-REA
Contact address: The Chancery, 6th
Flr, Valley Rd;
P.O. Box 34585-00100, Nairobi; Telephone: +254-20-4953000;
Fascimile: +254-20-2710944; Email: [email protected]
Attention of: Mr. Zackary O. Ayieko-CEO
Signed.......................................... Date....................
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
iii
EXECUTIVE SUMMARY
A. Introduction:
The subject of this Project Report is the proposed 35.3 km- Mwachabo Market, Pry/Manoa Disp/ Chunga
Unga Market/Dighai Market/ Kamtonga Market/Mkuki Market 33 kV power distribution line being
developed by the Rural Electrification Authority-REA on behalf of the Kenya Government. The Report
has been prepared for REA (Proponent) by Repcon Associates (The Environmental Firm of Experts) in
compliance with the Environmental Management and Coordination Act, 1999 and in line with Legal
Notice No. 101 of June 2003.
B. Scope of the Project Report:
The main objective of this Project Report is identify environmental and social impacts associated with
development and operation of the proposed power distribution line and recommend appropriate
mitigation measures for integration in all phases of project development.
Framework and depth of the Project Report has been dictated by requirements of EMCA 1999 and Legal
Notice 101 of June 2003 which has defined parameters for conduct of Environmental and Social Impact
Assessment studies in Kenya. Regulation 7(1) of Legal Notice 101 of EMCA dictates the following basic
content of Project Reports:-
a) The nature of the project;
b) The Division of the project including the physical area that may be affected by the project’s
activities;
c) The activities that shall be undertaken during the project construction, operation and
decommissioning phases;
d) The design of the project;
e) The materials to be used, products, by-products, including waste to be generated by the project
and the methods of disposal;
f) The potential environmental impacts of the project and the mitigation measures to be taken
during and after implementation;
g) An action plan for the prevention and management of possible accidents during the project
cycle;
h) A plan to ensure the health and safety of the workers and neighboring communities;
i) The economic and socio-cultural impacts to the local community and the nation in general;
j) The project budget;
k) Any other information that the Authority may require
C: Study Methodology pursued
The systematic investigative and reporting methodology specified for conduct Project Reports by Legal
Notice 101 of EMCA was adopted in this Study. Baseline data on project design was generated through
discussion with the client and review of project documentation. Opinions formed were revalidated
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
iv
through field work entailing site investigations and interviews with potentially affected people and
secondary stakeholders.
To identify, predict, analyze and evaluate potential impacts that may emanate from the project, diverse
study methods and tools including use of checklists, matrices, expert opinions and observations were
employed. An Environmental and Social Management Plan comprising an impact mitigation plan and
modalities for monitoring and evaluation were then developed to guide environmental management
during all phases of project development.
D: The Project Report Team
This Project Report study was undertaken by a team of 2 consultants namely:-
• Mr. Michael M. Wairagu-EIA Lead Expert
• Ms. Nancy Kanyi-Sociologist
E: Policy, legal and regulatory framework:
This Project Report has been developed to ensure that the proposed development of power distribution
lines is in conformity with national policy aspirations towards securing sustainable development.
Specifically, this report has been developed to ensure compliance with requirements of the
Environmental Management and Coordination Act (EMCA) 1999-Kenya’s supreme environmental law,
the National Constitution and World Bank’s safeguard requirements. Section 58 of EMCA requires that
all development proposed in Kenya to be subjected to environmental assessment to be conducted in
line with the Second Schedule and The Environmental (Impact Assessment and Audit) Regulations, 2003.
As well, Op 4.01 of the World Bank demands environmental assessment for Category A and B hence
occasioning the need for the study report disclosed here-in.
F. Project description:
The Proponent in respect of the proposed Mwachabo Market, Pry/Manoa Disp/ Chunga Unga
Market/Dighai Market/ Kamtonga Market/Mkuki Market 33 kV power distribution line is the Rural
Electrification Authority (REA) - a State Corporation established under Section 66 of the Energy Act No
12 of 2006 for purposes of accelerating the pace of rural electrification in Kenya.
Development of the Mwachabo power distribution line will be financed under auspices of the KEEP (REA
component) whose overall aim is to increase access to electricity in rural areas and is justifiable in that it
will electrify rural villages and institutions and thus unlock the opportunities associated with cost
effective access to convertible energy sources. The project will entail development of 35.3 kilometers of
Three Phase power distribution line which will comprise 3 lengths of parallel conductors (each 35.3 Km
long) mounted on a total of 133 wooden poles of 10-14 m height. The 33 kV power will be stepped
down to 0.433 through 2 differently located transformers and then supplied to consumers through new
low voltage lines to be constructed.
Mwacho market can be accessed by rough road from Mwatate though the Teita Estate from the
Mwatate-Taveta (A23 road) branching off just before Bura.
G: The proposed route of traverse
The Mwachabo power distribution line trading centers and institutions situated within the Mwachabo
location of Mwatate District. Mwachabo location is situated in the Taita lowlands which is part of the
expansive lowland area extending from the Yatta Plateau in the East to beyond the Tanzanian boundary
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
v
in the west and which contains the Tsavo East and West National Parks. Altitude generally averages 700
m above sea level.
On account of low altitude and absence of relief barriers, rainfall in the Mwatate lowlands averages
665mm delivered in two seasons; - March to May and November to December. The latter peak is more
pronounced. Further, the prevailing high temperatures exert a huge evaporative demand of 2189mm
annually which far exceeds moisture inputs from rainfall with a consequent huge moisture deficit
throughout the year. Long-term climate for the area is therefore semiarid which gives rise to savannah
woodlands dominated by Acacia-Commiphora formations.
As at the 2009 National Population Census, Mwachabo location had a population of 12,263 people
comprised of 3,065 households of which, the local Taita form the greater majority. The location hosts
the large-scale Teita Estate specialising in sisal growing but small settlements of Mwachabo, Manoa,
Kamtonga, Mkuki, etc are building up in the un-adjudicated area to the west of the sisal farm. These are
the settlements targeted for power supply.
H: Findings from the Study
(i) Overview of impacts:
The scope of adverse impacts associated with construction of 10 kilometres of 33 kV power distribution
line in an otherwise low density agricultural settlement is inherently low. Thus, for the proposed
Mwachabo power line, this study has only identified a total of 34 impacts, 17 of which are positive.
Other trends in impacts are as follows:-
• The other half of potential impacts are likely to be adverse.
• Ten of the 17 positive impacts are likely to be long-term in prevalence while 7 out of 8 adverse
impacts have a long-term effect with 2 of them being potentially irreversible.
• Nine out of sixteen adverse impacts have potential to cause secondary impacts while 6 of them
have cumulative tendency ie, they have potential to aggravate an already existing problem.
• The project has a marginal net positive impact pre mitigation which will require to be enhanced
through adoption of an effective impact mitigation strategy.
(ii) The Potential positive impacts anticipated
Positive implications of the project emanate from its potential to create short-term business and
employment opportunities to both professional staff and workers during the design phase while, at
construction phase, traders will benefit from opportunities to supply construction material while locals
will be employed in works. Upon commissioning, the project could supply electric power to 3 schools
and 5 rural trading centers where the potential to unlock business potential is real. Through adoption of
electricity and cutting down on use of fossil fuels, the project has potential to favor cutting down on
Green House Gas emissions to the benefit of the global climate.
(iii) The Potential adverse impacts/concerns
Core adverse impacts could include the following:-
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
vi
• Displacement of trees and property: By design, 33 kV distribution lines do not require land
acquisition to create way leaves and are also sited to avoid any standing structures. However,
such power lines do occasionally require that trees be removed and this present the main
adverse impact of the proposed power line. Along the proposed 35.3 kilometer long power line,
some indigenous tree could be removed and this could contribute to loss of floral biodiversity
through deforestation.
• Hazards to road users: Construction activity including transport of materials to the site and
erection of the power distribution line poses occupational health and safety hazard to both
construction crew and third parties.
• Conflict over use of road reserves: Unless properly coordinated, construction of power lines has
recently been observed to occasion conflicts over the use of road reserves and the same can
recur in regard of proposed power line.
• Hazards posed by presence of powered lines: Further, presence of the line changes the local
landscaper and skyline and such intrusion into space is a kind of pollution, not mentioning the
perpetual hazards introduced by presence of a powered line.
I: The Environmental and Social Management and Monitoring Plan
The proposed project is quite small in scale and given the passage in an medium density agricultural
settlement, the scope of anticipated impacts is quite low,. Further, the bulk of impacts is associated with
construction activity and will thus cease once construction ends. Intervention at mitigation has been
identified as follows:-
Mitigation of potential loss of trees: Project design will primarily aim at reducing tree casualties
through rerouting of the power line. Where tree removal is inevitable, such removal will be cleared
upfront with the County Agricultural Officers in line with the Agriculture (Farm Forestry) Rules 2009
upon which, REA will pay just and prompt compensation for all trees removed or lopped. Further,
towards rebuilding lost vegetation cover, REA will identify and support a local group to raise and plant
tree seedlings in the route of traverse. REA will follow and monitor progress of said trees to ensure
achievement of highest survival possible.
Compliance to requirements of OSHA 2007: The Contractor will be bound in contract to implement the
Code of Safety as outlined in 8.4 above. The core mitigation strategy is to optimize on construction time
so as to reduce the time taken to complete all civil works. The Contractor will deploy sober competent
staff working under competent supervisors. In addition to provision of protective gear, all workers will
be covered under the Workman Compensation Scheme.
REA to engage road sector stakeholders on use of road reserves: At the design stage, REA will engage
all road sector stakeholders to agree on mutually acceptable sharing of the target road reserves but in
the long run, this matter will require legal resolution.
REA to undertake public sensitization on hazards posed by live power lines: Towards curbing vandalism
of the power distribution line and associated hazards, the REA will mount public sensitization campaigns
in the affected area and will ensure that the property is promptly handed over to the community. As
well, the contractor should be held liable for all vandalism during the defect liability period.
The Monitoring Strategy: The responsibility for ensuring total environmental worth of the proposed
project vests with REA in the capacity of proponent. Towards this, the proponent will retain and deploy
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
vii
a team of highly motivated environmental and social scientists to monitor and report on all stages of the
project. Other action has been recommended as follows:-
i) The ESMMP as outlined above will be integrated into the Design Report with appropriate
allocation of funds in the Bills of Quantities.
ii) REA will therefore allocate the budget of Ksh 7 million be required to offset the social and
environmental impacts associated with the project.
iii) The Contractor will prepare routine reports which will be ascertained by the Supervising
Consulting Engineer before Payment Certificate can be issued.
iv) The contract for construction should bear clauses binding the contractor to implement impact
mitigation as part of the civil works. Environmental stabilization works will be covered under the
defect liability period.
v) REA will mount own internal monitoring to ensure that impact mitigation has been
implemented and will file annual audit reports with NEMA.
vi) The proposed project will adhere to all other laws of the land and will seek and obtain all
requisite statutory permits.
J: Recommendations of this Project Report
The proposed development of a power distribution project is largely aligned to reigning GOK Policies for
national development. The project enjoys a highly positive benefits profile as it will strongly support
initiatives towards poverty alleviation and reversal of environmental-degradation both of which are
critically important policy aspirations of the Kenya Government. This Study recommends that project
development should proceed but factor in the mitigation measures recommended herein. REA in the
capacity of proponent will require to closely monitor activities especially at construction stage and
simultaneously avail funds for environmental and social restoration.
Our recommendation is for the project to be licensed to proceed to the next level of development.
LIST OF ABBREVIATIONS
AOJ = Area of Jurisdiction
BOQs = Bill of Quantities
CAP= Chapter of the Laws of Kenya
CITES = Convention on International Trade in Endangered Species
EA = Environmental Assessment
EHS = Environment Health and Safety
EMCA 1999 = Environment Management and Coordination Act 1999
EMP = Environmental Management Plan
ERC = Electricity Regulatory Commission
ESIA = Environmental and Social Impact Assessment
ESMMP = Environmental and Social Management and Monitoring Plan
GDP = Gross Domestic Product
GHG = Green House Gases
GoK = Government of Kenya
HV = High Voltage
IMP = Impact Mitigation Plan
IPPs = Independent Power Producers
KENGEN = Kenya Electricity Generating Company
KFS = Kenya Forestry Service
KLPC = Kenya Power and Lighting Company Limited
kV= Kilo volts
KWS = Kenya Wildlife Service
M&E= Monitoring & Evaluation
MDGs = Millennium Development Goals
MoE = Ministry of Energy
MW = Mega Watts
MWI = Ministry of Water and Irrigation
NEMA = National Environment Management Authority
O&M = Operation and Maintenance
PAC = Program Audit Consultant
PAPs = Project Affected Persons
PMs = Project Managers
RE= Resident Engineer
RETs = Renewable Energy Technologies
RAP = Resettlement Action Plan
SHS= Solar Home Systems
SMEs = Small and Micro- Enterprises
TL= Distribution Line
TORs = Terms of Reference
US$ = United States Dollar
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
ix
Table of Contents
DISCLOSURE PAGE .............................................................................................................. ii
EXECUTIVE SUMMARY ..................................................................................................... iii
1 CHAPTER ONE: INTRODUCTION .................................................................................................................................................................................................................................................................................................................... 1111
1.1 Background to this report ................................................................................................ 1
1.2 Scope and objectives of the Environmental and Social Impact Assessment ................... 1
1.2.1 Study scope ............................................................................................................. 1
1.2.2 Study Objectives ..................................................................................................... 1
1.2.3 The Environmental and Social Impact Assessment Team ...................................... 1
1.3 Approach and methodology to the Environmental and Social Impact Assessment........ 2
1.3.1 Discussions with the Project Design Consultant ..................................................... 2
1.3.2 Data collection ........................................................................................................ 2
1.3.3 Field work and public consultations ....................................................................... 2
1.3.4 Data analysis and impact prediction ....................................................................... 3
1.3.5 Formulation of an Environmental and Social Management Plan ........................... 3
1.3.6 Reporting procedure ............................................................................................... 3
1.4 Presentation of this Report .............................................................................................. 4
2 CHAPTER TWO: PROJECT DESCRIPTION /DISCLOSSURE ................................................................................................................................................................................ 5555
2.1 Overview .......................................................................................................................... 5
2.2 About the Proponent ....................................................................................................... 5
2.3 Objectives of the proposed Project ................................................................................. 5
2.4 Project Justification .......................................................................................................... 5
2.5 The proposed route of traverse ....................................................................................... 5
2.6 Design features of the distribution lines .......................................................................... 7
2.6.1 Nature of power distribution lines ......................................................................... 7
2.6.2 Scope of the project ................................................................................................ 8
2.6.3 Other specifications ................................................................................................ 8
2.6.4 Land requirement by the distribution lines ............................................................ 9
2.6.5 Project activities ...................................................................................................... 9
2.6.6 Land ownership within route of traverse ............................................................... 9
2.7 Total Cost of the Project................................................................................................... 9
3 CHAPTER THREE: POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ................................................................................ 11111111
3.1 Policy Frameworks ......................................................................................................... 11
3.1.1 Constitutional provisions ...................................................................................... 11
3.1.2 Other GOK Policies relevant to environmental conservation .............................. 12
3.1.3 World Bank’s Safeguard Policies (WBSGPs) .......................................................... 14
3.2 The Legal Framework for Environmental Management in Kenya ................................. 17
3.2.1 Provision of an Institutional Framework .............................................................. 17
3.2.2 EMCA requires Environmental Impact Assessment for new projects .................. 18
3.2.3 EMCA provides for gazzettment of Environmental Regulations .......................... 18
3.2.4 EMCA requires inter-sectoral coordination .......................................................... 20
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
x
3.2.5 EMCA requires conformity to International Conventions, Treaties and
Agreements ....................................................................................................................... 28
3.3 The Regulatory Framework ............................................................................................ 30
3.3.1 The Rural Electrification Authority-REA ................................................................ 30
3.3.2 The Energy Regulatory Commission-ERC .............................................................. 30
3.3.3 The National Environmental Management Authority-NEMA .............................. 30
4 CHAPTER FOUR: THE BASELINE ENVIRONMENT ................................................................................................................................................................................................................ 31313131
4.1 The Bio-physical baseline ............................................................................................... 31
4.1.1 Location and administrative set-up ...................................................................... 31
4.1.2 Relief and physiographic profile ........................................................................... 31
4.1.3 Climatic regime ..................................................................................................... 31
4.1.4 Cover vegetation ................................................................................................... 33
4.1.5 The socio-economic profile ................................................................................... 34
4.1.6 The inhabitants ..................................................................................................... 34
4.1.7 Population dynamics ............................................................................................. 34
4.1.8 Land use and livelihoods ....................................................................................... 34
4.2 Ecologically sensitive resources ..................................................................................... 34
5555 CHAPTER FIVE: STAKEHOLDER CONSULTATIONSCHAPTER FIVE: STAKEHOLDER CONSULTATIONSCHAPTER FIVE: STAKEHOLDER CONSULTATIONSCHAPTER FIVE: STAKEHOLDER CONSULTATIONS ................................................................................................................................................ 35353535
5.1 Need for stakeholder consultations ................................................................................ 35
5.2 Approach to stakeholder consultation ............................................................................ 35
5.2.1 Identification of stakeholders ................................................................................ 35
5.2.2 Levels in stakeholder consultations ...................................................................... 35
5.2.3 Methodologies in stakeholder consultation: ......................................................... 36
5.2.4 Progress in consultation ........................................................................................ 36
5.2.5 Comments from local stakeholders ....................................................................... 39
5.2.6 Comments from local Institutions ......................................................................... 40
5.3 Salient observation from stakeholders’ consultation ..................................................... 40
5.4 Modalities for conflict resolution ................................................................................... 40
6666 CHAPTER SIX: ANALYSIS OF ALTERNATIVESCHAPTER SIX: ANALYSIS OF ALTERNATIVESCHAPTER SIX: ANALYSIS OF ALTERNATIVESCHAPTER SIX: ANALYSIS OF ALTERNATIVES ........................................................................................................................................................................ 41414141
6.1 Overview ........................................................................................................................ 41
6.2 Levels in evaluating project alternatives ........................................................................ 41
6.2.1 Evaluation of the No Project option ..................................................................... 41
6.2.2 Options in the selection of the routes of traverse ............................................... 41
6.3 Choice between diverse distribution technologies........................................................ 41
6.4 Choice of Tower structures ............................................................................................ 42
6.5 The preferred option ...................................................................................................... 43
7 CHAPTER SEVEN: POTENTIAL IMPACTS FROM THE PROJECT ............................................................................................................................................ 45454545
7.1 Generic Social and Environmental Impacts ................................................................... 45
7.1.1 Outcome of impact prediction .............................................................................. 45
7.1.2 Analysis of impact severity ................................................................................... 45
7.2 Description of potential impacts .................................................................................... 45
7.2.1 Overview of impacts ............................................................................................. 45
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
xi
7.2.2 Impacts at Design Stage ........................................................................................ 46
7.2.3 Positive Impacts at Construction Stage ................................................................. 46
7.2.4 Negative impacts at Construction Stage ............................................................... 49
7.2.5 Impacts at the Operation Phase ........................................................................... 50
7.2.6 Adverse impacts from powering and operating the distribution line .................. 52
7.2.7 Core concerns about the project .......................................................................... 53
8 CHAPTER EIGHT: THE ENVIRONMENTAL MANAGEMENT PLAN ............................................................................................................................ 54545454
8.1 Overview ........................................................................................................................ 54
8.2 The Impact Mitigation Plan ............................................................................................ 54
8.3 Mitigation at design stage .............................................................................................. 54
8.4 Mitigation at construction stage .................................................................................... 54
8.4.1 Mitigation of impacts associated with tree removal ............................................ 54
8.4.2 Mitigation of potential conflict in the use of road reserves ................................. 57
8.4.3 Management of Occupational Health and Safety Hazards................................... 57
8.4.4: Management of Health and Safety Hazards within institutions and market centers
59
8.4.5 : Modalities for conflict resolution .......................................................................... 59
8.5 Mitigation of Impacts at Operation Stage ...................................................................... 59
8.6 Effectiveness of the Mitigation programme .................................................................. 59
8.6.1 Viability of Mitigation ........................................................................................... 59
8.6.2 Prevalence of residue impacts .............................................................................. 60
8.6.3 Management of decommissioning ....................................................................... 60
8.7 Monitoring requirements ............................................................................................... 60
8.7.1 The concepts ......................................................................................................... 60
8.8 Roles and Responsibilities in implementing the EMP .................................................... 64
8.9 Budget for Environmental and Social Mitigation ........................................................... 65
9 CHAPTER NINE: CONCLUSION AND RECOMMENDATIONS ........................................................................................................................................................ 66666666
9.1 The Project ..................................................................................................................... 66
9.2 Study Methodology pursued .......................................................................................... 66
9.3 Findings from the Study ................................................................................................. 66
9.3.1 Overview of impacts ............................................................................................. 66
9.3.2 Nature of the potential positive impacts anticipated .......................................... 66
9.3.3 Nature of the Potential adverse impacts/concerns.............................................. 67
9.4 The Environmental and Social Management and Monitoring Plan ............................... 67
9.4.1 The Impact Mitigation Plan: .................................................................................. 67
9.4.2 Effectiveness of the Mitigation Plan ..................................................................... 68
9.4.3 Total Cost in Environmental and Social Mitigation .............................................. 68
9.5 The Monitoring Strategy ................................................................................................ 68
9.6 Recommendations of this Project Report ...................................................................... 68
APPENDICES: ............................................................................................................................................................................................................................................................................................................................................................................................................................................................ 70707070
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
xii
List of Tables
Table 2.1: Summary features of the scheme ................................................................................................ 8
Table 3.1: Analysis of potential triggers to World Bank safeguards policies ............................................. 15
Table 3.3: Screening of the proposed power distribution line project against international treaties on
protection of nature ................................................................................................................................... 29
Table 3.4: Screening of the proposed power distribution line project against international treaties on
protection of the atmosphere .................................................................................................................... 29
Table 4.1: Climate data for the Mwatate area based on the Voi Meteorological station .......................... 31
Table 4.2: Population statistics for Mwatate District ................................................................................. 34
Table 5.1: Summary table of stakeholders consulted ................................................................................ 38
Table 6.1: Analysis of alternatives .............................................................................................................. 44
Table 7.1: Matrix for impact prediction and interpretation ...................................................................... 47
Table 8.1: Matrix for impact mitigation ..................................................................................................... 55
Table 8.3: Analysis of impacts scenario before and after mitigation ......................................................... 60
Table 8.4: Matrix for Environmental and Social Management and Monitoring (ESmmP) ......................... 62
List of Figures
Figure 2.1: Schematic presentation of the Mwachabo power distribution line project .............................. 7
Figure 2.2: Three phase power distribution ................................................................................................ 8
Figure 4.1: Seasonal moisture balance for Mwatate area .......................................................................... 33
List of Plates
Plate 2.1: Potential beneficiaries of the power distribution (i): Manoa dispensary (ii) Kamtonga Market
and (iii)the Manoa market ............................................................................................................................ 6
Plate 4.1: An inselberg in the Mwatate Plains ............................................................................................ 31
Plate 4.2: Remnant semi arid vegetation in the Mwachabo Location ...................................................... 33
Plate 5.1 : Stakeholder consultation at Kamtonga Trading Centre ............................................................ 37
Plate 7.1: Birds nesting on a tree at Kamtonga market removal of such trees implies loss of nesting
grounds for birds ......................................................................................................................................... 49
Plate 7.2: Transportation of construction materials has potential to undermine safety of other road users
.................................................................................................................................................................... 50
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
1
1 CHAPTER ONE: INTRODUCTION
1.1 Background to this report
The Rural Electrification Authority–REA is the Utility mandated by the Government of Kenya to design
and construct rural electrification schemes in Kenya. With support from the GoK and the World Bank,
REA is currently developing 150 rural electrification schemes under the Kenya Electricity Expansion
Project (KEEP). Under KEEP, REA will develop 33 kV power lines in 23 Counties among them Taita Taveta
County where the proposed Mwachabo Market, Pry/Manoa Disp/ Chunga Unga Market/Dighai Market/
Kamtonga Market/Mkuki Market 33 kV power distribution line (here after referred to as the
Mwachabo 33 kV power distribution line project) will be constructed. The latter line will supply electric
power to designated institutions and market centers within Mwatate Constituency.
This proposed power distribution line is the subject of this Project Report which has been motivated by
the need to ensure that supply of electric power to the target villages will be in conformity with
requirements for technically sustainable, socially acceptable and economically viable development
which is the essence of environmental impact assessment. Further, this report has been prepared under
contract by Repcon Associates- a Nairobi-based consultancy (See Appendix 1.1 for statutory registration
details) in conformity with Legal Notice 101 of EMCA.
1.2 Scope and objectives of the Environmental and Social Impact Assessment
1.2.1 Study scope
Essentially, the framework and depth of this Project Report was dictated by reining legislation namely
EMCA 1999 and its Legal Notice 101 of June 2003 which has defined parameters for conduct of
Environmental and Social Impact Assessment studies in Kenya. The Second Schedule of EMCA-1999
identified power distribution among projects that require to be subjected to environmental impact
assessment and this informed the need to design and execute the Project Report Study for the proposed
Mwachabo Project. As well, given the limited scale and scope of investment required in developing 33
kV power distribution lines, a decision was made to mount a study process culminating in development
of a Project Report in line with Legal Notice 101 of EMCA.
1.2.2 Study Objectives
Objectives for this Project Report Study were identified as follows;-
• To identify and assess potential environmental and social impacts of the proposed project.
• To identify all potential significant adverse environmental and social impacts of the proposed
project and recommend measures for mitigation measures.
• To verify compliance with the environmental regulations and industry’s standards
• To recommend cost effective measures to be implemented to mitigate the expected impact.
• To prepare a Project Report compliant to the Environmental Management and Coordination Act
[1999] and it’s Legal Notice 101.
1.2.3 The Environmental and Social Impact Assessment Team
This Environmental and Social Impact Assessment study was undertaken by a multidisciplinary team
bringing together skills as follows:-
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
2
• Mr. Michael M. Wairagu- EIA Lead Expert and Team Leader
• Ms. Nancy Kanyi-Sociologist
Details of NEMA registration status in respect of both team members are provided in Appendix 1.2.
1.3 Approach and methodology to the Environmental and Social Impact Assessment
A Project Report is primarily a tool aimed at facilitating identification and mitigation of adverse impacts
of an activity before its implementation commences while creating an opportunity for enhancing
positive impacts and thus improving on the entire net worth of the project. For the purposes of this
Project Report, systematic data correction took place through activities as follows:-
1.3.1 Discussions with the Project Design Consultant
Core discussions were held between the Study Team Leader (from Repcon) and Project Managers from
both SWECO and Aberdare Engineering Ltd from which, finer details of the assignment were negotiated
and harmonized. Consultative meetings also took place with staff of the REA in pursuit of better
understanding of the environmental mandate and capacity of the Authority. From such discussions, the
consultant obtained maps and project design data which helped better clarify the project scope.
1.3.2 Data collection
The Project Report Process also employed review of available reports towards familiarizing with the
focus and objectives of the entire programme. Core reports reviewed here included the Environmental
and Social Management Framework (ESMF) and the Resettlement Policy Framework (RPF) prepared for
KEEP. Secondary data for the route of traverse was obtained from diverse sources such as GOK planning
documents and policy blue prints, professional reports and releases, etc all of which provided an insight
into the socio-economic and biophysical baseline for the target area. A list of documents and data
sources consulted as part of this study is provided in Appendix 1.3. Preliminary opinions formed from
review of such documentation were re-validated during fieldwork undertaken within the traverse area.
1.3.3 Field work and public consultations
Fieldwork largely entailed onsite investigations so as to familiarize with the baseline environment of the
area potentially affected by the project. Analysis of potential impacts was based on investigations
undertaken along the entire route of traverse where data on physiographic, pedology, hydrology and
drainage, ecology and cover vegetation, settlement and land-use patterns, ecologically and economically
sensitive resources were collected. Accruing information formed the basis for impact prediction.
Further, and in line with requirements of Legal Notice 101 of EMCA and its Schedules, the proposed
project was subjected to public participation through conduct of public hearing along the traverse and
through one to one interviews with other stakeholders.
Chapter six below provides a record of the public participation process as pursued in this study. Views
/comments accruing not only served to inform the design process but also formed a basis for discussion
between the community and study team towards improving the overall quality of the proposed
interventions. Stakeholders in government including the provincial administration, land-based sectors,
etc were also consulted to clarify diverse issues and to ensure that proposed development was in
harmony with sectoral policies.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
3
1.3.4 Data analysis and impact prediction
Upon data analysis, potential environmental impacts (both positive and adverse) were predicted based
on available tools. The magnitude, significance, and acceptability of predicted impacts were evaluated
with a view to determining whether observed adverse impacts are significant enough to warrant
mitigation. The potential environmental impacts were described in both quantitative and qualitative
terms through application of existing body of knowledge, checklists and input from diverse stakeholders.
In particular, impact prediction in this study drew heavily on three tools namely:-
i) The Third Schedule to Legal Notice 101 of EMCA
ii) The Sectoral checklists for the Power Sector developed for the Asian Development Bank;
iii) The Checklist of Environmental Characteristics developed by the Department of Environmental
Affairs of the Republic of South Africa and,
iv) The Reference Guidelines for Environmental Assessments (which incorporates the Leopold
Matrix) developed by USAID / REDSO / WCA–Abidjan.
Impacts were further screened for occurrence and significance of residual (those which cannot be
mitigated satisfactorily) and cumulative impacts with a view to providing a basis of making
recommendations on the way forward for the project.
1.3.5 Formulation of an Environmental and Social Management Plan
Measures or interventions necessary to minimize, reduce, avoid or offset identified adverse impacts
were evaluated and presented in form of an Impact Mitigation Plan for the proposed development. Such
evaluation also included an assessment of Project Alternatives as reported in Chapter Six below. The
ESMP also identified modalities for monitoring and evaluation to ensure compliance in implementation
of proposed mitigation measures. This involved development of monitoring indicators and procedures
for continuous generation of project monitoring data and information.
1.3.6 Reporting procedure
The Study methodology as described above culminated with production of this Project Report
formulated in line with Regulation 7(1) of Legal Notice 101 of EMCA which requires that a proponent
shall prepare a project report stating: -
a) The nature of the project;
b) The Division of the project including the physical area that may be affected by the project’s
activities;
c) The activities that shall be undertaken during the project construction, operation and
decommissioning phases;
d) The design of the project;
e) The materials to be used, products, by-products, including waste to be generated by the project
and the methods of disposal;
f) The potential environmental impacts of the project and the mitigation measures to be taken
during and after implementation;
g) An action plan for the prevention and management of possible accidents during the project
cycle;
h) A plan to ensure the health and safety of the workers and neighboring communities;
i) The economic and socio-cultural impacts to the local community and the nation in general;
j) The project budget;
k) Any other information that the Authority may require
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
4
A draft version of this Project Report has been reviewed by REA and SWECO whereby emergent
comments have been input towards development of this Final Project Report which will be submitted to
NEMA in line with Regulation 8 of Legal Notice 101.
1.4 Presentation of this Report
This report is presented in nine chapters which integrate the content for Project Reports as stipulated in
Regulation 7 of LN 101 thus:-
• Chapter One (this chapter) outlines the background and procedure in developing this Project Report;
• Chapter Two provides a description of the project as proposed by REA;
• Chapter Three reviews relevant policies, legal, regulatory and administrative frameworks governing
conduct of environmental assessment in Kenya;
• Chapter Four provides the pre-project baseline environment;
• Chapter Five provides an analysis of alternatives to the project;
• Chapter Six reports on the outcome of stakeholder consultations;
• Chapter Seven analyses potential impacts of the project;
• Chapter Eight outlines the Environmental and Social Management and Monitoring Plan (ESMP)
developed for the project;
• Chapter Nine provides the conclusion and recommendation
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
5
2 CHAPTER TWO: PROJECT DESCRIPTION /DISCLOSSURE
2.1 Overview
This chapter provides an overview of the proposed distribution line as currently designed. The
description borrows largely from documentation availed by the Rural Electrification Authority-REA.
2.2 About the Proponent
The Proponent in respect of the proposed Mwachabo 33 kV power distribution line project is the Rural
Electrification Authority (REA)- a State Corporation established under Section 66 of the Energy Act, 2006
(No 12 of 2006) for purposes of accelerating the pace of rural electrification in Kenya. The Energy Act,
2006 sets out the functions of REA as follows:-
• To Manage the Rural Electrification Programme Fund
• To Develop and update the rural electrification master plan
• To Promote the use of renewable energy sources including small hydros, wind, solar, biomass,
geothermal, hybrid systems and oil fired components taking into account specific needs of
certain areas including the potential for using electricity for irrigation and in support of off-farm
income generating activities.
• Implementation and sourcing of additional funds for the rural electrification programme
• Management of the delineation, tendering and award of contracts for licences and permits for
rural electrification
2.3 Objectives of the proposed Project
The proposed Mwachabo 33 kV power distribution line project is being developed under auspices of
project KEEP whose REA component is designed to increase access to electricity in rural areas through
pursuit of three objectives namely;-
• Increasing access to electricity by accelerating connection rates and introducing a customer-
friendly connection policy;
• Promotion of the use of renewable energy sources like solar;
• Providing quality and affordable electricity to all in rural areas.
2.4 Project Justification
The project is justifiable in that, it will electrify rural villages and institutions and thus unlock the
opportunities associated with cost effective access to convertible energy sources. Plate 2.1 below
presents a pictorial summary of some intended beneficiaries of the project.
2.5 The proposed route of traverse
Though the proposed line targets villages in the Mwachabo Location of Mwatate District, the bulk of the
proposed distribution line will traverse the vast Teita Estate. Access is via the dirt road traversing the
Teita Estate which exits at Mwachabo Market, then forks to Manoa and Kamtonga and Mkuki and
Chunga Mali villages. The target villages can also be accessed from the Mwatate-Taveta (A23 road)
branching off just before the junction to Taita Salt Licks.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
6
Plate 2.1: Potential beneficiaries of the power distribution (i): Manoa dispensary (ii) Kamtonga
Market and (iii)the Manoa market
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
7
Figure 2.1: Schematic presentation of the Mwachabo power distribution line project
2.6 Design features of the distribution lines
2.6.1 Nature of power distribution lines
By design, there are 5 categories of power distribution lines depending on the voltage as follows:-
• Low voltage – less than 1000 volts, used for connection between a residential or small commercial
customer and the utility.
• Medium Voltage (Distribution) – between 1000 volts (1 kV) and to about 33 kV, used for distribution
in urban and rural areas.
• High Voltage (sub-distribution less than 100 kV); sub-distribution or distribution at voltage such as
115 kV and 138 kV), used for sub-distribution and distribution of bulk quantities of electric power
and connection to very large consumers.
• Extra High Voltage (distribution) – over 230 kV, up to about 800 kV, used for long distance, very high
power transmission.
• Ultra High Voltage – higher than 800 kV.
The proposed Mwachabo Power distribution line is a medium voltage line.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
8
2.6.2 Scope of the project
Distribution lines essentially comprise of an assembly of poles and cross bars on which conductors are
mounted. Detailed specifications inclusive of Bills of Quantities for the proposed Mwachabo Power
distribution line are provided in Appendix 2.1, a brief summary of which is provided in Table 2.1 below.
A 35.3 kilometer 33 kV power distribution line is proposed which implies that, the scheme will comprise
3 lengths of parallel conductors (each 35.3 Km long) mounted on a total of 133 wooden poles of 12-14
m height. The 33 kV power will be stepped down to 0.433 kV through 2 different located transformers
and supplied to consumers through new low voltage distribution lines to be constructed.
Table 2.1: Summary features of the scheme
Scheme/ Proposed alignment Project area Length
(km)
Total No of
poles
Total No of
transformers
Mwachabo Market, Pry/Manoa Disp/
Chunga Unga Market/Dighai Market/
Kamtonga Market/Mkuki Market
Mwatate Constituency-
Taita Taveta County
35.3 133 2
Diverse assembly of pole structures will be used in construction of the target distribution line as
follows:-
• Suspension structures to support the conductor vertically using suspension insulators.
• Strain structures to resist net tension in the conductors and the conductors attach to the
structure through strain insulators.
• Dead-end structures to support the full weight of the conductor and also all the tension in it by
use of strain insulators.
Figure 2.2: Three phase power distribution
2.6.3 Other specifications
Specifications: Conductors comprise the core media through which, power distribution takes place. In
the design of the proposed TL, the Wolf Conductor is preferred on account of higher efficiency of
distribution, thus resulting in lower losses of energy and cumulative un-served energy. The conductors
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
9
recommended for the various sub-project options are Aluminum Conductor Steel Reinforced (ACSR)
“Wolf” and “Lynx” conductors which are in accordance with Kenya’s Standards. The technical particulars
of conductors are as specified in Appendix 2.1 below.
Conductor configuration: The current practice in constructing power distribution lines in Kenya is to use
flat configuration conductors which results in shorter poles with a modest cost saving compared to the
typical triangular configuration with the three phases on three levels. For distribution lines longer than
100 kilometres, a full transposition (three sections) of the three phases is recommended due to the
impedance asymmetry resulting in a corresponding voltage and current imbalance at the end of the
distribution line.
2.6.4 Land requirement by the distribution lines
The practice of the REA is to require a way leave corridor of equivalent to 10m width on either side of
the center line for 33 kV power distribution lines. Along the 20m wide corridor, an appropriate clearance
between conductors and vegetation and structures needs be maintained which requires that houses and
trees in excess of 7.5 metres are removed for the entire life of the distribution line. However, farming
and grazing within the corridor is generally permitted.
2.6.5 Project activities
Towards development of the distribution lines, activities are anticipated as follows:-
Design works: A technical design package for the proposed power distribution line has already been
prepared by REA.
Construction activity: Site preparation will involve manual clearing in holing areas and lopping of tall
vegetation to allow laying of conductors. Construction will involve delivery of poles, conductors,
insulators and other components of the distribution line. This will be followed by excavation following
which the poles will be erected. The major task will entail mounting of conductors and transformers
following which the project will be commissioned.
Operation phase: Upon powering, the project will then be operated by the Kenya Power Company
alongside other investments in Taita Taveta County. Routine maintenance will also involve securing of
pole foundations against erosion to insure against weakening and collapse of power lines.
2.6.6 Land ownership within route of traverse
As currently aligned, the traverse falls within privately owned lands, road reserves, and urban centers-
the latter of which are controlled by local authorities.
2.7 Total Cost of the Project
A summary of the Project Bills of Quantities is provided in Table 2.2 below. In total, construction of the
power distribution line is expected to cost the sum of Ksh 41,145,666.48. For a 35.3 Km long power
distribution line, this translates to a unit construction cost of Ksh 1.66 million per kilometre.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
10
Table 2.2: Estimated cost of constructing the power distribution line
SN Bill Item Cost (Ksh)
1 Project Survey works 1,207,070.00
2 Provision for Wayleave 0
3 6X50KVA,1X100KVA 33/0.433 KV TX 1,674,782.96
4 S/S Works 1,146,898.83
5 35.3Km of 33kv in 75 sqmm bare ACSR 26,751,351.22
6 720m of Lv 3ph in 100 sqmm bare aa
1045m of Lv Sph in 100 sqmm bare aa
695,437.14
7 6 No. S/L in 25 sqmm 4/c ug cable
6 No. S/L in 25 sqmm 4/c ug cable
309,716.33
8 Per diem, shutdown and press advert 255,000,00
9 Labour & Transport Costs 9,105,410.00
Total Planned Project Cost 41,145,666.48
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
11
3 CHAPTER THREE: POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK
The proposed Mwachabo Power distribution line project will comply with all Kenyan legal requirements
and the World Bank’s environmental and social safeguards. A brief outline of the operating policy, legal
and administrative framework is provided below.
3.1 Policy Frameworks
3.1.1 Constitutional provisions
Kenya now has a new Supreme law in form of the New Constitution which was promulgated on 27th
August 2010 to take supremacy over all aspects of life and activity in the New Republic. With regard to
environment, Section 42 of the Constitution states as follows:-
In Sections 69 and 70, the Constitution has inter alia identified national obligations in respect of the
environment and enforcement of environmental rights respectively as follows:-
Section 69 (1): The State shall—
(a) Ensure sustainable exploitation, utilization, management and conservation of the
environment and natural resources, and ensure the equitable sharing of the accruing benefits;
(b) Work to achieve and maintain a tree cover of at least ten per cent of the land area of Kenya;
(c) Protect and enhance intellectual property in, and indigenous knowledge of, biodiversity and
the genetic resources of the communities;
(d) Encourage public participation in the management, protection and conservation of the
environment;
(e) Protect genetic resources and biological diversity;
(f) Establish systems of environmental impact assessment, environmental audit and monitoring
of the environment;
(g) Eliminate processes and activities that are likely to endanger the environment; and
(h) Utilize the environment and natural resources for the benefit of the people of Kenya.
(2) Every person has a duty to cooperate with State organs and other persons to protect and conserve
the environment and ensure ecologically sustainable development and use of natural resources.
Section 70 provides for enforcement of environmental rights thus:-
(1) If a person alleges that a right to a clean and healthy environment recognized and protected under
Article 42 has been, is being or is likely to be, denied, violated, infringed or threatened, the person may
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
12
apply to a court for redress in addition to any other legal remedies that are available in respect to the
same matter.
(2) On application under clause (1), the court may make any order, or give any directions, it considers
appropriate:-
(a) To prevent, stop or discontinue any act or omission that is harmful to the environment;
(b) To compel any public officer to take measures to prevent or discontinue any act or omission
that is harmful to the environment; or
(c) To provide compensation for any victim of a violation of the right to a clean and healthy
environment.
Essentially, the new constitution has embraced and provided further anchorage to the spirit and letter
of EMCA 1999 whose requirements for environmental protection and management have largely
informed Sections 69 through to 71 of the Document. In Section 72 however, the new constitution
allows for enactment of laws towards enforcement of any new provisions of the Supreme Law.
3.1.2 Other GOK Policies relevant to environmental conservation
(i) Kenya Vision 2030
Kenya Vision 2030 is the current national development blueprint for the period 2008 to 2030 and was
developed following on the successful implementation of the Economic Recovery Strategy for Wealth
and Employment Creation which saw the country’s economy back on the path to rapid growth since
2002. The objective of the Vision 2030 is to transform Kenya into a middle income country with a
consistent annual growth of 10 % by the year 2030. The 2030 goal for equity and poverty elimination is
to reduce the number of people living in absolute poverty to the tiniest proportion of the total
population. Kenya will aim at a society that guarantees equality of opportunity in accessing public
services and providing income-generating activities as widely as possible.
The level and intensity of commercial energy use in a country is a key indicator of the degree of
economic growth and development and Vision 2030 identifies energy as one of the infrastructural
enablers of the three “pillars” of the Vision. Kenya is therefore expected to use more energy in the
commercial sector on the road to 2030 since, as incomes increase and urbanization intensifies,
household demand for energy will also rise. Preparations have been made to meet this growth in
demand for energy under the Vision.
At the national level, wood fuel and other biomass account for about 68% of the total primary energy
consumption, followed by petroleum at 22%, electricity at 9% and others including coal at about less
than 1%. Solar energy is also extensively used for drying and, to some extent, for heating and lighting.
Electricity remains the most sought after energy source by Kenya society and access to electricity is
normally associated with rising or high quality of life. However, its consumption in Kenya is extremely
low at 121 kilowatt hours (khw) per capita (compared to 503khw in Vietnam or 4,595khw for South
Africa) and national access rate at about 15%. The access rate in the rural areas is estimated at 4%.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
13
Towards reversing this scenario, more resources are being invested towards power generation in
tandem with concerted efforts in policy and institutional reforms to bring in new service providers.
With regard to environmental quality, Vision 2030 anticipates a Kenyan nation characterised by a clean,
secure and sustainable environment by 2030 and sets the goals for 2012 as ;-(i) to increase forest cover
from less than 3% at present to 4%; and (ii) to lessen by half all environment-related diseases. Specific
strategies will involve promoting environmental conservation in order to provide better support to the
economic pillar flagship projects and for the purposes of achieving the Millennium Development Goals
(MDGs); improving pollution and waste management through the design and application of economic
incentives; and the commissioning of public-private partnerships (PPPs) for improved efficiency in water
and sanitation delivery. Kenya will also enhance disaster preparedness in all disaster-prone areas and
improve the capacity for adaptation to global climatic change. In addition, the country will harmonise
environment-related laws for better environmental planning and governance.
(ii) Sessional Paper No. 3 of 2009 on National Land Policy
The National Land Policy was formulated with the aim of securing rights over land and provide for
sustainable growth, investment and reduction of poverty in line with Government overall development
objectives. The policy will offer a framework of policies and laws designed to ensure the maintenance of
a system of land administration and management that will provide:
(a) All citizens with opportunity to access and beneficially occupy and use land;
(b) Economically viable, socially equitable and environmentally sustainable allocation and use of
land;
(c) Efficient, effective and economical operation of land markets;
(d) Efficient and effective utilization of land and land-based resources; and
(e) Efficient and transparent land dispute resolution mechanisms.
(iii) Sessional Paper No 1 of 1996 on Environment and Development:
Sessional Paper No 1 of 1996 is the official statement on national policy on environment and was
released in 1996 following on recommendations of the National Environment Action Plan (NEAP) of
1994. The NEAP Process had been launched earlier on in 1992 following the Country’s participation in
the United Nations Conference on Environment and Development (UNCED) in Rio de Geneiro during
which Kenya alongside other nations became signatory to Agenda 21 which called on all nations to pay
closer attention to environmental management at national level.
Through Sessional Paper No. 1 of 1996, the Kenya Government guarantees every citizen the inalienable
right to a clean and healthy environment and commits to pursue a policy strategy of integrating
environmental sensitivity into national development planning process and sets broad policy objectives
as follows:-
• Optimal use of natural land and water resources in improving the quality of human
environment;
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
14
• Sustainable use of natural resources to meet the needs of the present generations while
preserving their ability to meet the needs of future generations;
• Integration of environmental conservation and economic activities into the process of
sustainable development;
• Meeting of national goals and international obligations by conserving bio-diversity, arresting
desertification, mitigating effects of disasters, protecting the ozone layer and maintaining an
ecological balance on earth.
Among other provisions, Sessional Paper No. 1 of 1996 also sets out sectoral priorities for environmental
sustainability which in most cases have been operationalised through formulation of guidelines for
quality and environmental management in respective sectors. A National Environmental Law (EMCA,
1999) has since been enacted to secure implementation of the national policy on environment.
3.1.3 World Bank’s Safeguard Policies (WBSGPs)
By virtue of source of funding, the proposed development of TLs by REA is also subject to World Bank
requirements for impact assessment. As such, Project Report study has been formulated to address and
cater for both Kenyan and World Bank requirements for impact assessment. World Bank projects and
activities are governed by Operational Policies, which are clearly spelt out in the Bank's Operational
Manual ("Bank Procedures" and "Good Practices"). The World Bank’s safeguard policies are designed to
ensure that projects proposed for Bank financing are environmentally and socially sustainable. These
operational policies include:
• OP 4.01 Environmental Assessment;
• OP 4.04 Natural Habitats;
• OP 4.09 Pest Management;
• OP 4.33 Cultural Heritage;
• OP 4.12 Involuntary Resettlement;
• OP 4.10 Indigenous People;
• OP 4.36 Forests;
• OP 4.37 Safety of Dams;
• OP 7.50 Projects on International Waterways ;
• OP 7.60 Projects in Disputed Areas.
An analysis of possible triggers of the WB SGPs by the proposed Mwachabo power distribution line
(table 3.1 below) indicates that the project is likely to trigger 3 out of 10 policy safeguards out of which,
displacement of human settlements and clearing of biodiversity to give way for distribution lines is likely
to be the most severe. In sections below, a highlight of requirements of the 3 SGPs likely to be triggered
is briefly provided. For a full description of all WB safeguard policies, the reader is referred to
www.worldbank.org.
The Environmental and Social Impact Assessment process in respect of the proposed distribution line
has also taken cognizance of upcoming World Bank Policies namely;- (i) Interim Guidance Note on land
use planning recently unveiled by the Operations Policy and Country Services Quality Assurance and
Compliance Unit and the Legal Department Environmental and International Law Unit; and (ii), The
Environmental Health and Safety Guidelines (www.ifc.org/ifcext/sustainability.nsf/
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
15
Content/Environmental Guidelines). None of these safeguards are however triggered by the proposed
power distribution line. In sections below, brief commentaries on both OP 4.10 and Op 4.12 are
provided.
Table 3.1: Analysis of potential triggers to World Bank safeguards policies
World Bank Safeguard
policy
Triggers Trigger mechanism
Environmental
Assessment
(OP 4.01)
Triggered Project is category B and has to undergo mandatory Environmental
and Social Impact Assessment in line with OP 4.01
Natural Habitats (OP 4.04) Triggered The project will not support or lead to the conversion of natural
habitats, and the ESMF forbids any project activities inducing
significant conversion or degradation of critical natural habitats.
Appropriate mitigation measures will be followed to limit the impact
on local fauna, avi-fauna and to protect indigenous plant and tree
species along the low voltage line.
Forestry (OP 4.36) No Trigger The construction of low voltage distribution lines will not lead to the
significant degradation and conversion of critical forest areas and
forest ecosystems.
Pest Management (OP
4.09)
No trigger Project does not entail Pest Management or any use of chemicals
Cultural Property
(OP11.03)
No trigger Although it is not expected that the project will affect resources of
physical, cultural, and/or historical importance, a chance finds
procedure will be inserted into construction contracts , and
Museums of Kenya authorities will be notified if chance finds are
made
Indigenous Peoples (OP
4.10)
No Trigger There are no known IPs in the route of traverse
Involuntary Resettlement
(OP 4.12)
Triggered Some trees will be removed to create the ROW. Compensation at
present replacement value based on market assessment will be
made for these trees.
Safety of Dams (OP 4.37) No Trigger Project will not involve construction of dams
Projects on International
Waters (OP 7.50)
No trigger No project activities are planned for in
International Waters
Projects in Disputed Areas
(OP.60)
No Trigger There are no sites classified as disputed in the project area.
Total triggers 3
(i) Environmental Assessment (OP 4.01)
OP 4.01 requires Environmental Assessment (EA) for projects proposed for Bank financing to ensure that
they are environmentally sound and sustainable, and as a basis for decision making. Under OP 4.01
projects are screened and assigned either of four categories each of which requires different levels of
environmental assessment as follows:-
• Category A: A proposed project is classified as Category A if it is likely to have significant adverse
environmental impacts that are sensitive, diverse, or unprecedented. These impacts may affect an
area broader than the sites or facilities subject to physical works.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
16
• Category B: A proposed project is classified as Category B if it’s potential adverse environmental
impacts on human populations or environmentally important areas—including wetlands, forests,
grasslands, and other natural habitats—are less adverse than those of Category A projects. These
impacts are site-specific; few if any of them are irreversible; and in most cases mitigation measures
can be designed more readily than for Category A projects.
• Category C: A proposed project is classified as Category C if it is likely to have minimal or no adverse
environmental impacts. Beyond screening, no further EA action is required for a Category C project.
• Category FI: A proposed project is classified as Category FI if it involves investment of Bank funds
through a financial intermediary in subprojects that may result in adverse environmental impacts.
Although the project will have a positive impact on the environment overall, by improving the supply of
energy in rural areas of Kenya, thereby reducing the use of fossil fuels for domestic consumption, and
the use of firewood, OP/BP 4.01 is triggered because the physical interventions resulting from the
implementation of investments could have low to moderate negative impacts on the environment. The
Project is classified as Category B- a project with environmental impacts that are easily identified and
mitigated-requiring a partial environmental assessment. As such, this Project Report prepared in line
with requirements of LN 101 of EMCA is deemed sufficient to meet all requirements for environmental
assessment for this project category.
(ii) Involuntary Resettlement (OP 4.12)
OP 4.12 requires that a Resettlement Action Plan (RAP) be prepared for all projects that
anticipate displacement of both settlements and livelihoods. The policy aims to avoid involuntary
resettlement to the extent feasible, or to minimize and mitigate its adverse social and economic
impacts.
(iii) Operational Policy 4.04 on Natural Habitats seeks to ensure that World Bank-supported
infrastructure and other development projects take into account the conservation of biodiversity, as
well as the numerous environmental services and products which natural habitats provide to human
society. The policy strictly limits the circumstances under which any Bank-supported project can damage
natural habitats (land and water areas where most of the native plant and animal species are still
present). Specifically, the policy prohibits Bank support for projects which would lead to the significant
loss or degradation of any Critical Natural Habitats, whose definition includes those natural habitats
which are legally protected, officially proposed for protection, or unprotected but of known high
conservation value.
Given that the proposed Mwachabo power distribution line will traverse areas through which wildlife
disperse to and from the Tsavo West National Park, this SGP remains relevant. The proposed project will
be screened critically against requirements of this policy.
Modalities for harmonizing requirements of both the WB SGPs and GOK legal framework
Experience has shown that both OP 4.01 of the World Bank and EMCA 1999 are generally aligned in
principle and objective in that:-
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
17
• Both require Environmental Assessment before project implementation leading to development
of comprehensive Environmental and social Management plans to guide resolution of social and
environmental impacts as anticipated.
• Both require public disclosure of Environmental and Social Impact Assessment and stakeholder
consultation during preparation,
• While OP 4.01 of World Bank stipulates different scales of Environmental and Social Impact
Assessment for different category of projects, EMCA requires Environmental and Social Impact
Assessment for all sizes of projects, which are required to be scoped as relevant
• Where EMCA requires consultation of Lead Agencies comprising of relevant sectors with legal
mandate under GoK laws, the WB has equivalent safeguards for specific interests.
• The Bank requires that stakeholder consultations be undertaken during planning,
implementation and operation phases of the project which is equivalent to the statutory annual
environmental audits at the operation phase of projects in Kenya.
A major guiding principle in this study is that pursuit of an in-depth Project Report process as stipulated
by EMCA 1999 is adequate to address all World Bank requirements for environmental and social
assessment. I
3.2 The Legal Framework for Environmental Management in Kenya
The Environmental Management and Coordination Act (EMCA) No. 8 of 1999 is the supreme
environmental law which lays out the legal and institutional framework for environmental management
in Kenya. The statute was enacted in 2000 with a view to harmonizing environmental legislation
previously scattered in 77 national laws. Under EMCA, provisions and safeguards for environmental
management have been put in place as follows:-
3.2.1 Provision of an Institutional Framework
In 2001, the Government established the administrative structures to implement EMCA, 1999 as
follows:-
The National Environment Council: The National Environment Council (the Council) is responsible for
policy formulation and directions for the purposes of EMCA 1999. The Council also sets national goals
and objectives and determines policies and priorities for the protection of the environment.
The National Environmental Management Authority: EMCA 1999 allows for formation of the National
Environmental Management Authority (NEMA) as the body charged with overall responsibility of
exercising general supervision and co-ordination over all matters relating to the environment and to be
the principal instrument of government in the implementation of all policies relating to the
environment. Under the Act, NEMA was established in 2001 when the first Director General was
appointed by the President.
Activities of NEMA are rolled out through three core directorates in charge of Enforcement, Education
and Policy. This is the institutional framework under which this Project Report process will be regulated
and processed to conclusion.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
18
Public Complaints Committee: Under EMCA 1999, a Public Complaints Committee has been established
to provide an administrative mechanism for addressing environmental harm. The Committee whose
membership include representatives from the Law Society of Kenya, NGOs and the business community
has the mandate to investigate complaints relating to environmental damage and degradation.
3.2.2 EMCA requires Environmental Impact Assessment for new projects
Section 58 of EMCA requires that an Environmental Impact Assessment (EIA) Study precede all
development activities proposed to be implemented in Kenya. The Act further requires that EIA studies
so designed, be executed in accordance with the Guidelines for Conduct of EIAs and Environmental
Audits (Kenya Gazette Supplement No. 56 of 13th
June 2003) as published by the National Environmental
Management Authority (NEMA). The Second Schedule of EMCA specifies the nature of projects that
should undergo Environmental and Social Impact Assessment. Under EMCA however, all projects
irrespective of size are to be subjected to Environmental and Social Impact Assessment studies. Under
electricity infrastructure, the Second Schedule identifies the following candidate projects as meriting
Environmental and Social Impact Assessment Studies:-
• Electricity generation stations,
• Electrical distribution lines;
• Electrical substations;
• Pumped storage schemes; have been specified as projects to be subjected to EIA.
The Project Report for the proposed Mwachabo power distribution line project has thus been designed
and conducted in response to this legal requirement and has also taken cognizance of other legal
instruments under EMCA as outlined elsewhere below in this report.
3.2.3 EMCA provides for gazzettment of Environmental Regulations
Under EMCA 1999, guidelines for environmental management have been promulgated through diverse
regulations. We highlight a few of the said regulations against which the proposed development of a
132kV power distribution line will be screened and harmonized.
Environmental (Impact Assessment and Audit) Regulations, 2003 (Legal Notice 101- Kenya Gazette
Supplement No. 56 of 13th
June 2003): The Regulations, 2003, stipulate procedures for carrying out
Environmental Impact Assessments (EIAs) and Environmental Audits (EAs). Regulation 3 states that “the
Regulations should apply to all policies, plans, programmes, projects and activities specified in Part IV,
Part V and the Second Schedule of the Act. Regulation 4(1) further states that: ‘‘…no proponent should
implement a project………
i) Likely to have a negative environmental impact; or
ii) For which an environmental impact assessment is required under the Act or these Regulations;
unless an environmental impact assessment has been concluded and approved in accordance with
these Regulations…’’.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
19
Among other requirements, these guidelines also prescribe the format and content of Project Reports.
LN 101 further sets out the schedule of EIA Fees payable to NEMA by project proponents. 1
Environmental Management and Co-ordination Act (Waste Management) Regulations 2006: These are
described in Legal Notice No. 121 of the Kenya Gazette Supplement No. 69 of September 2006. These
Regulations apply to all categories of waste as provided in the Regulations. These include:
• Industrial wastes;
• Hazardous and toxic wastes;
• Pesticides and toxic substances;
• Biomedical wastes;
• Radio-active substances.
These regulations outline requirements for handling, storing, transporting, and treatment / disposal of
all waste categories as provided therein.
Environmental Management and Coordination Act (Water Quality) Regulations 2006: These are
described in Legal Notice No. 120 of the Kenya Gazette Supplement No. 68 of September 2006. These
Regulations apply to drinking water, water used for agricultural purposes, water used for recreational
purposes, water used for fisheries and wildlife and water used for any other purposes. This includes the
following: Protection of sources of water for domestic use; Water for industrial use and effluent
discharge; Water for agricultural use. These Regulations outline:
• Quality standards for sources of domestic water;
• Quality monitoring for sources of domestic water;
• Standards for effluent discharge into the environment;
• Monitoring guide for discharge into the environment;
• Standards for effluent discharge into public sewers;
• Monitoring for discharge of treated effluent into the environment.
Conservation of Biological Diversity (BD) Regulations 2006: Legal Notice No. 160 of the Kenya Gazette
Supplement No. 84 of December 2006 applies to conservation of biodiversity which includes
conservation of threatened species, Inventory and monitoring of BD and protection of environmentally
significant areas, access to genetic resources, benefit sharing and offences and penalties. The route of
traverse has not been mapped for biodiversity as required by these regulations. However, from
investigations undertaken as part of this study, it was observed that the proposed line will largely
traverse agricultural settlements where the original natural vegetation has been replaced by crops and
the likelihood of occurrence of indigenous biodiversity is quite low. This regulation is that not likely to be
triggered.
1 LEGAL NOTICE NO 30 of EMCA (dated 11th February, 2009) - THE ENVIRONMENTAL (IMPACT ASSESSMENT AND AUDIT)
(AMENDMENT) REGULATIONS, 2009 sets new EIA Fees schedules as follows:-
1. These Regulations may be cited as the Environmental (Impact Assessment and Audit) (Amendment) Regulations, 2009.
2. The Environmental (Impact Assessment and Audit) Regulations, 2003, are amended in the Fifth Schedule by deleting item 4 and
substituting therefore the following new item –
“4. Environmental Impact Assessment licence-0.05% of the total cost of the project, to the minimum of KSh. 10,000 and maximum of
KSh. 1,000,000 payable as follows:
(a) 50% of the 0.05% being Processing Fee Payable upon submission of a project report;
(b) 50% of the 0.05% being licence fee payable upon collection of the Environmental Impact Assessment Licence”.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
20
National Sand Harvesting Guidelines, 2007: These Guidelines apply to all sand harvesting activities in
Kenya to ensure sustainable utilization of the sand resource and proper management of the
environment. Among Key features, the guidelines empower respective DECs to regulate sand harvesting
within areas of jurisdiction implying that, sand should only be sources from approved sites and by
approved dealers.
Guidelines on Noise level: NEMA has recently issued draft guidelines on ambient noise levels. In
conformity to these guidelines, the Environmental and Social Impact Assessment will formulate
measures to ensure that; - the Contractor keeps noise level within acceptable limits and construction
activities shall, where possible, be confined to normal working hours in the residential areas; schools,
dispensaries and other noise sensitive areas shall be notified by the Contractor at least 5 days before
construction is due to commence in their vicinity. Under all conditions, the Contractor must adhere to
the Noise Prevention and Control Rules of April 2005.
3.2.4 EMCA requires inter-sectoral coordination
In recognition that EMCA is an umbrella law coordinating diverse sectoral statutes all of which are still in
force, Legal Notice 101 of EMCA identifies and designates all GOK Agencies with legal mandates over
specific sectors to be Lead Agencies for purposes of Environmental Impact Assessment. LN 101 of EMCA
further requires that the respective sectors be consulted as Lead Agencies in making decisions
pertaining to environmental assessment for projects in respective sectors. This is to ensure that NEMA
does not approve projects that contradict sector policies and legislation.
As part of this Project Report process, an analysis of Kenyan laws considered relevant to development
and operation of power distribution lines was undertaken following which, sectoral triggers were
identified as outlined below.
(i) The Environment and Land Court Act No.19 of 2011:
This law was assented to on 27th
August, 2012 and commenced on 30th August, 2033to give effect to
Article 162(2)(b) of the Constitution; to establish a superior court to hear and determine disputes
relating to the environment and the use and occupation of, and title to, land, and to make provision for
its jurisdiction functions and powers, and for connected purposes. Section 13 (1) of the Act gives the
Court original and appellate jurisdiction to hear and determine all disputes in accordance with Article
162(2)(b) of the Constitution and with the provisions of this Act or any other written law relating to
environment and land. In exercise of its jurisdiction under Article 162 (2) (b) of the Constitution, the
Court shall have power to hear and determine disputes relating to environment and land, including
disputes:-
(a) relating to environmental planning and protection, trade, climate issues, land use planning,
title, tenure, boundaries, rates, rents, valuations, mining, minerals and other natural resources;
(b) Relating to compulsory acquisition of land;
(c) Relating to land administration and management;
(d) relating to public, private and community land and contracts, choses in action or other
instruments granting any enforceable interests in land; and
(e) any other dispute relating to environment and land.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
21
This statute is deemed relevant to all development proposed for i9mplementatiopn in Kenya as it
provides for legal recourse for disputes relating to environment and land. This is a law that any
developer including the REA should familiarize with.
(ii) The Energy Act of 2006:
Section (4) of the Energy Act 2006 establishes the Energy Regulatory Commission with a mandate under
Section 6 of the Energy Act as follows:-
i) to formulate, enforce and review environmental, health, safety and quality standards for the
energy sector, in coordination with other statutory authorities; and,
ii) To enforce and review regulations, codes and standards for the energy sector.
Thus, under Section 6 of the Energy Act, the ERC has full mandate to ensure environmental protection
within the energy sector in the capacity of de jure Lead Agency. Further, Section 30(1) and (2) of the
Energy Act 2006 requires that ‘The Commission shall, in granting or rejecting an application for a licence
or permit, take into consideration;- (i) the impact of the undertaking on the social, cultural or
recreational life of the community; and (ii), the need to protect the environment and to conserve the
natural resources in accordance with the Environmental Management and Coordination Act of 1999.
This Project Report process has partly been undertaken in fulfillment of requirements of the Energy Act
and indeed, the final output will be reviewed by the ERC in the capacity of Lead Agency.
(iii) Roads Act 2007:
The core feature of the Kenya Roads Act 2007 which came into effect in September 2007 was the
creation of Three autonomous Authorities (KeNHA), KeRRA and KURA) to take care of National, Rural
and Urban Roads respectively. Sections 3(2) (b), 4(2) (b) and 10(2) (b) are quite relevant to development
and operation of power distribution lines as they place all road reserves under the respective
jurisdictions of KeNHA, KeRRA and KURA depending on the category of the road. In essence, any
infrastructure service provider intending to utilize a road reserve will require consent of the respective
road authority. Further, under Section 27, the respective road authority has power to cause relocation
of infrastructure from the road reserve thus:-
(2) Where any infrastructure utility is located within a road reserve, the provider or operator of such
infrastructure utility shall, upon written request by the responsible Authority, relocate such infrastructure
utility to a location or alignment approved by the Authority at no cost to the Authority.
(3) Where an Authority intends to exercise any power under subsection (2) it shall give reasonable notice
of its intention to do so to the person having control of such infrastructure utility, and such person shall
cause to be removed such infrastructure utility within sixty days.
(4) Where, under subsection (2) or (3), any person having control of an infrastructure utility fails to
remove such infrastructure utility within the time stated in the notice, the concerned Authority may
remove such infrastructure utility at the cost of the person who was unable to comply with the notice
under subsection (3).
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
22
Given the provisions of the Roads Act 2007, it is important that all developers targeting to use road
reserves to liaise closely with the relevant road authorities. The same position was articulated during
consultations with KeNHA and KeRRA undertaken as part of this study.
(iv) The Agriculture Act, Cap 318:
This statute seeks to promote and maintain a stable agriculture, to provide for the conservation of the
soil and its fertility and to stimulate the development of agricultural land in accordance with the
accepted practices of good land management and good husbandry. This Act primarily guides and
regulates farming practices. The Agriculture Act is the principal land use statute covering, inter-alia, soil
conservation and agricultural land use in general.
In 2009, the Minister for Agriculture gazetted The Agriculture (Farm Forestry) Rules, 2009 with the
objective and purpose of promoting and maintaining farm forest cover of at least 10 per cent of every
agricultural land holding and to preserve and sustain the environment in combating climate change and
global warming.
Rule 5 (1) requires every person who owns or occupies agricultural land shall establish and maintain a
minimum of 10 percent of the land under farm forestry which may include trees on soil conservation
structures or rangeland and cropland in any suitable configurations; provided that the species of trees or
varieties planted shall not have adverse effects on water sources, crops, livestock, soil fertility and the
neighborhood and should not be of invasive nature.
Rule 6 allows an inspector to take action within area of jurisdiction to ensure that land owners and
occupiers comply with requirements of rule 5 above. Regulation 10 on harvesting of farm trees requires
the following:
(1) Every land owner or occupier shall ensure that harvesting of trees shall be done in such a
manner as to maintain a 10 per cent tree cover at all times, with large scale harvesting requiring
a harvesting plan as governed by the provisions of the Forest Act No. 7 of 2005.
(2) The District Agricultural Committee shall establish mechanisms to facilitate the process of
notification and approval for ease of harvesting by land owners or occupiers.
(3) A person shall not harvest trees from a farm forest without notification and approval as
provided for in paragraph (2).
(4) Harvesting, processing and movement of farm forest products for commercial purposes shall
be governed by the provisions of the Forest Act, No. 7 of 2005.
From this analysis, it is apparent that a new approach to treatment of on-farm trees has been
established. As such, contrary to past practices, contractors contemplating removal of farm trees to
create way leaves will require authority from the District Agricultural committees.
(v) The Lands Act No. 6 of 2012:
The Land Act was enacted by Parliament to give effect to Article 68 of the Constitution, to revise,
consolidate and rationalize land laws; to provide for the sustainable administration and management of
land and land based resources, and for connected purposes. The Act applies to all land declared as (a)
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
23
public land under Article 62 of the Constitution; (b) private land under Article 64 of the Constitution; and
(c) community land under Article 63 of the Constitution and any other written law relating to community
land.
The Land Act guarantees security of tenure for land under (a) freehold; (b) leasehold; (c) such forms of
partial interest as may be defined under the Act and other law, including but not limited to easements;
and (d) customary land rights, where consistent with the Constitution and guarantees equal recognition
and enforcement of land rights arising under all tenure systems and non-discrimination in ownership of,
and access to land under all tenure systems.
Under the Lands Act 2012, The Way leaves Act, Cap 292 and The Land Acquisition Act, Cap. 295 have
been revoked but Sections 8 and 9 allow for Compulsory Acquisition as an option in acquiring land for
public utility.
(vi) The Land Registration Act, No. 3 of 2012:
The Land Registration Act (LRA), 2012was assented to on 27th April, 2012 and commenced on 2nd May,
2012 with the objective and purpose of revising, consolidating and rationalizing the registration of titles
to land to give effect to the principles and objects of devolved government.
Sections 18 to 21 of the LRA 2012 deal with establishment and maintenance of boundaries to land.
Section 21(1) is relevant to development of power distribution lines in it that it criminalizes interference
with boundaries thus;- Any person who defaces, removes, injures or otherwise impairs a boundary
feature or any part of it unless authorized to do so by the Registrar commits an offence and is liable on
conviction to imprisonment for a term not exceeding two years or to a fine not exceeding two hundred
thousand shillings or to both.
Under the LRA 2012, Statutes previously related to land property namely;- The Indian Transfer of
Property Act 1882, The Government Lands Act, (Cap 280), The Registration of Titles Act, (Cap 281), The
Land Titles Act, (Chapter 282) and The Registered Land Act, (Cap. 300) now stand repealed.
(vii) The Physical Planning Act (Cap 286):
This Act provides for the preparation and implementation of physical development plans for connected
purposes. It establishes the responsibility for the physical planning at various levels of government
mainly the District Level. The Act provides for a hierarchy of plans in which guidelines are laid down for
the future physical development of areas referred to in the specific plan. The intention is that the three-
tier order plans, the national development plan, regional development plan, and the local physical
development plan should concentrate on broad policy issues. The Act also advocates for public
participation in the preparation of plans and requires that proper consideration be given to the potential
for economic and social development.
This Project Report study has confirmed that planning of the RE Projects under KEEP has taken account
of regional development plans and will specifically seek to utilize existing way leaves. Public
consultations have been undertaken as part of this study to ensure that sectoral policies and strategies
are adhered to in course of developing the power lines.
(viii) Local Government act Cap 265:
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
24
A principal target of the REA component of KEEP is to electrify market centres which are created and
governed under Cap 265. Specifically, under Cap 265, LA have planning jurisdiction and control for all
land under the Authorities area. As such, any development targeting use of any land under LAs will
require consent as appropriate. The same should apply to use of any way leaves under the jurisdiction of
a county council.
Cap 265 also empowers LAs to act in the protection of the environment. This Act empowers the
Municipal Authority to provide and maintain sanitation and sewerage services and to take measures to
control or prohibit factories and industries from emitting smoke, fumes, chemicals, gases, dust, smell,
noise, vibrations or any danger, discomfort or annoyance to the neighbourhood and to control
disinfections particularly using cyanide. They are empowered to punish those disrupting sanitation or
sewerage lines and can compel owners to construct sewage line into the systems and drainages.
(ix) The Occupation Health and Safety Act 2007:
This is an Act of Parliament to provide for the safety, health and welfare of workers and all persons
lawfully present at workplaces, to provide for the establishment of the National Council for
Occupational Safety and Health and for connected purposes. The Act has the following functions among
others:-
• Part VI of the Act gives the requirements for occupational health provisions which include
cleanliness, ventilation, overcrowding, etc.
• Part VII of the Act contains provisions for the safe operation of machinery and includes all prime
movers and distribution equipment. Additionally this part includes the safe operation of cranes,
chains, ropes, lifting tackles, pressure vessels and their statutory examination by DOHSS
Approved Persons.
• Part VIII of the Act contains provisions for general safety of a workplace especially fire safety.
This part of the Act will apply to the proposed project during the design, construction and
operational phases respectively of the project.
• Part IX of the Act deals with Chemical Safety. This will not be applicable to the proposed project
as it will not handle and transport hazardous materials.
• Part X of the Act deals with the General Welfare conditions that must be present during the
operational phase of the project. Such conditions include first aid facilities, supply of drinking
water, etc.
• Part XI of the Act contains Special Provisions on the management of health, safety and welfare.
These include work permit systems, PPE requirements and medical surveillance. All sections of
this part of the Act will be applicable to the proposed project during the operational phase.
Section 8.2 of this Project Report has outlined clear modalities to be followed by contractors towards
mitigating/minimizing/avoiding occupational health and safety hazards.
(x) The Wildlife (Conservation and Management) Act (Cap 376):
This principal Act regulates wildlife conservation and management in Kenya. The Act establishes Kenya
Wildlife Service (KWS) as the implementing agency. Under section 9 and subsection 3A, the functions of
KWS are stated among others as: to provide advice to the government and local authorities and
landowners on the best methods of wildlife conservation and management and authority to ensure
viability of conservation areas. Furthermore, the Minister responsible for wildlife has discretionary
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
25
powers to promulgate such regulations to enhance the management of such conservation areas, so long
as the regulations so promulgated are reasonable and not ultra vires to the parent Act.
Investigations conducted within the route of traverse revealed that, there are per se, no areas
controlled by the KWS under Cap 376. However, Mwachabo location comprises an import ant dispersal
area for wildlife moving from the Shimba Hills National Park in the South to the Tsavo West National
Park efforts will be made to minimize damage to wildlife habitat especially trees which are crucial for
maintaining minimum viable populations.
(xi) The Forests Act 2005:
The Forests Act 2005 repealed Cap 385 of the Laws of Kenya and provides for the establishment, control
and regulation of forests. The Act confers powers on the Minister responsible of Forests to set aside
specific areas for the conservation of fauna and flora, for the management of water catchments,
prevention of soil erosion or for the protection and management of indigenous forests on alienated
Government land. Such forest land includes those formerly gazetted under Cap 385, thus essentially
putting the control of all Kenyan forests under a single statute.
The Forests Act 2005 makes illegal, any alienation of gazetted forest land for any purposes considered
contradictory to the dictum of conservation, requiring that, such proposals to be debated and approved
by Parliament, after completion of a comprehensive Environmental and Social Impact Assessment Study.
Further, towards operationalizing the Forests Act 2005, the KFS has gazetted forest rules namely:- The
Forest (Harvesting)Rules, 2009; The Forest (Charcoal making) Rules, 2009; and, The Forest (Participation
in sustainable management) Rules, 2007 but in our view, nothing in the proposed power distribution
line occasions triggers to either the parent law or its subsidiary legislation. However, as observed
elsewhere above in this report, the main trigger is likely to be in the Farm Forestry Rules gazetted under
Cap 318.
(xii) Occupiers Liability Act (Cap. 34) revised 2009
Rules of Common Law regulates the duty which an occupier of premises owes to his visitors in respect of
danger and risk due to the state of the premises or to things omitted or attributes an affliction on
his/her health to a toxic materials in the premises. In additional to creation of a way leave, the REA
working with local leadership will mount a public sensitization programme to ensure that people are
aware of the hazards posed by presence of powered distribution lines.
(xiii) Penal Code (Cap.63)
The Act makes it criminal for anybody to pollute common resources such as air, public water supply,
acoustic quality, etc and stipulates fines for diverse offences.
The EMP prepared as part of this Project Report has identified nuisances as potential adverse impacts of
the project and has recommended activities towards mitigation/ minimization/ avoidance of nuisances
arising from the project activities.
(xiv) The Standards Act Cap 496
The Act is meant to promote the standardization of the specification of commodities, and to provide for
the standardization of commodities and codes of practice; to establish a Kenya Bureau of Standards, to
define its functions and provide for its management and control. Code of practice is interpreted in the
Act as a set of rules relating to the methods to be applied or the procedure to be adopted in connection
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
26
with the construction, installation, testing, sampling, operation or use of any article, apparatus,
instrument, device or process.
The Act contains various specifications touching on electrical products and the Proponent shall ensure
that commodities and codes of practice utilized in the project adhere to the provisions of this Act.
(xv) Public Roads and Roads of Access Act (Cap. 399)
Sections 8 and 9 of the Act provides for the dedication, conversion or alignment of public travel lines
including construction of access roads adjacent lands from the nearest part of a public road. Sections 10
and 33 allow for notices to be served on the adjacent land owners seeking permission to construct the
respective roads. The proponent has confirmed to this study that no new access roads will be opened up
and the project will rely on existing roads.
(xvi) The Coast Development Authority Act No 6 of 1989 (Cap 444):
The Coast Development Authority Act was enacted in 1989 and commenced on January 18th
, 1999
expressly to provide for the establishment of the Coast Development Authority (CDA) to plan and co-
ordinate the implementation of development projects in whole of the Coast Province and the exclusive
economic zone and for connected purposes. Under Section 8, the CDA Act outliners function of the CDA
as follows:-
a) to plan for the development of the Area and initiate project activities identified from such planning
in the development and through the Government generally;
b) to develop an up-to-date long range development plan for the Area;
c) to initiate such studies, and carry out such surveys of the Area as may be considered necessary by
the Government or the Authority, and to assess alternative demands within the Area on the natural
resources thereof, and initiate, operate, or implement such projects as may be necessary to exploit
those natural resources including agriculture (both irrigated and rain fed), forestry, wildlife and
tourism industries, electric power generation, mining, and fishing, and to recommend economic
priorities;
d) to co-ordinate the various studies of schemes within the Area such that human, water, animal, land
and other resources are utilized to the best advantage and to monitor the design and execution of
planned projects within the Area;
e) to effect a programme of both monitoring and evaluating the performance of projects within the
Area so as to improve such performance and establish responsibility thereof, and to improve future
planning;
f) to co-ordinate the present abstraction and use of natural resources, especially water, within the
Area and to set up effective monitoring of abstraction and usage;
g) to cause and effect the construction of any works deemed necessary for the protection and
utilization, of the water and soils of the Area including hydro-power development for multipurpose
utilization of water resources;
h) to ensure that landowners in the Area undertake all the measures specified by the Authority to
protect the water and soils of the Area;
i) to identify, collect, collate and correlate all such data related to the use of water and other
resources and also economic and related activities within the Area as may be necessary for the
efficient forward planning of the Area;
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
27
j) to maintain a liaison between the Government, the private sector and other interested agencies in
the matter of the development of the Area with a view limiting he duplication of effort and ensuring
the best use of the available technical resources;
k) to examine the hydrological effects and the subsequent ecological changes on the development
programmes and evaluate how they affect the economic activities of the persons dependent on
river environment;
l) to implement development projects and programmes whose primary objective is to promote socio-
economic development of the Coast Province in particular and Kenya in general;
m) to plan and liaise with the relevant authorities as necessary in the exploration and development of
the extensive fishing and marine activities an Kenya especially the exclusive economic zone.
The areas targeted for electrification under the current project fall within the planning jurisdiction of the
CDA. Caution therefore has been taken to link the proposed development to the CDA in course of
Stakeholder consultations.
(xvii) The Limitations of Actions Act (Cap. 22)
This Act provides for recognition of squatters and the conditions under which they would have rights for
compensation for loss of land. If squatters have been in occupation of private land for over twelve (12)
years, then they would have acquired rights as adverse possessors of that land as provided under the
Limitation of Actions Act, section 7. Investigations undertaken for this Project Report did not identify any
land users who merited classification as squatters in which case, no further action in respect of this
statute is recommended.
(xviii) The Civil Aviation Act, Cap 394
Under this Act, the Kenya Civil Aviation Authority (KCAA) has to authorize and approve the height of all
proposed masts for purposes of ensuring the safety of flying aircraft over the proposed project area.
However, investigations conducted under this study did not come across any airstrip that would warrant
triggers to Cap 394.
(xix) The Water Act 2002
In March 2003, the Water Act 2002 came into effect to provide a legal framework for management and
conservation of the national water resource base in line with policy changes in the sector. New
institutions with separate functions have now been established, and decentralized decision making is
reflected in autonomous regional bodies. Henceforth, these are the institutions with which all works
touching on water resources have to coordinate with. They include:
Ministry of Water and Irrigation: The MWI is the trustee of all water resources in the country. The
present key roles and functions of the MWI have been defined in the National Water and Sanitation
Services as: water policy formulation; water resources management policy; apportionment of water
resources and abstraction licensing; appointment of water undertakers; regulation, setting and approval
of standards; approval of water tariffs, levies, rates and charges; development and operation and
maintenance of urban and rural water supply systems; wastewater treatment and control; water quality
and pollution control; catchment area conservation; water conservation (by National Water
Conservation and Pipeline Corporation); irrigation and dam construction schemes; flood control and
land reclamation (MWRMD, 2003).
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
28
The Water Resource Management Authority: This is a body corporate charged (under Section 8(1) of
the Water Act 2002) with the overall responsibility of overseeing sustainable development of the
national water resource base. The functions of the WRMA as provided in Section 8 of the Water Act
2002 is to manage, protect and conserve the water resources with regional offices at catchment levels
for decentralized decision-making, quick response to water resources management problems and for
speedy water allocation process.
In order to coordinate activities in water resource management, WRMA has issued Guidelines for Water
Resource Management (LN 171), Part IX of which specifies code of conduct with regard to activities in
riparian areas. In the impression of this study, there are no triggers to the Water Act and its LN 171.
This National Museums and Heritage Act, 2006:
The National Museums and Heritage Act was enacted and commenced on 8th September 2006 for the
following purposes:- (i) to consolidate the law relating to national museums and heritage; (ii) to provide
for the establishment control, management and development of national museums and the
identification, protection, conservation and distribution of the cultural and natural heritage of Kenya;
(iii) to repeal the Antiquities and Monuments Act and the National Museums Act; (iv) and for connected
purposes.
Under Section 25, Cap 216 allows for declaration of National Heritage sites which then remain protected
from any annihilation or alteration under the law. This Project Report process has taken precaution to
ascertain that none of the areas traversed by the proposed Mwachabo Power distribution line harbours
assets gazetted under Cap 216.
3.2.5 EMCA requires conformity to International Conventions, Treaties and Agreements
Kenya is a signatory as well as a party to various international conventions, treaties and protocols
relating to the environment and aimed at achieving sustainable development. According to the Registrar
of International Treaties and other Agreements in Environment (UNEP 1999), there are 216 such
treaties, 29 of which are of interest to Kenya. The country is a signatory to 16 such agreements, which
range from use of oil, protection of natural resources and, protection of the atmosphere. The
agreements are both regional and international and became legally binding on Kenya upon ratification
thereof by the rightfully designated Kenyan Authority.
Protocols towards protection of the natural environment: There are 16 agreements of significance to
Kenya especially due to its high dependence on fuel wood and hydropower. At international level, Kenya
has signed and ratified the following tools:-
� Convention on Biological Diversity, 1992;
� United Nations Convention to Combat Desertification 1994;
� the International Plant Protection Convention 1951;
� the Convention on Wetlands of International Importance (Ramsar 1971);
� Convention on International Trade in Endangered Species (CITES) of Wild Fauna and Flora, 1990,
which protects forests as habitat for endangered species; and also ,
� Convention concerning the Protection of World Cultural and Natural Heritage, 1972, which also
protects threatened plants.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
29
For purposes of this study, the proposed power distribution line was screened for possible against all the
10 conventions for possible triggers. Though none were explicitly identified, it is worth noting that tree
removal towards creating way leaves is a precursor to the desertification process.
Table 3.3: Screening of the proposed power distribution line project against international treaties on protection of
nature
No Convention Status in
project area
Remarks
International Plant Protection Convention 1951 No trigger
Convention on Wetlands of International Importance
(Ramsar 1971)
No trigger
Convention concerning the Protection of World
Cultural and Natural Heritage, 1972
No trigger
Convention on International Trade in Endangered
Species (CITES) of Wild Fauna and Flora, 1990
No Trigger
Convention on Biological Diversity, 1992 No trigger
Agenda 21 of the United Nations Conference on
Environment and Development-UNICED (The Rio
Conference)
Legally non-binding
United Nations Convention to Combat Desertification
1994
No trigger Tree removal is a precursor to
desertification
Protection of the Atmosphere: Most of the greenhouse and ozone depleting emissions emanate from
man’s activities in sourcing energy and as such, the conventions in this area mainly aim at protecting the
atmosphere from harmful emissions. Kenya is party to the Vienna Convention of 1985 on Protection of
the Ozone Layer together with its three Protocols of 1990, 1992 and 1994. Kenya is also a signatory to
the United Nations Framework Convention on Climate Change (UNFCCC) 1992, and its Kyoto Protocol of
1997) which principally aims at cutting down on emission of greenhouse gases. Both conventions are
deemed quite relevant to projects targeting substitution of biomass energy with cleaner energy sources
such as the proposed rural electrification. The observation here is that though removal of trees to create
way leaves directly impacts on the carbon sink, the shift from kerosene and biomass to use of electricity
has a more significant impact of emission of greenhouse gases. Removal of trees is thus seen as a
necessary cost towards adoption of cleaner energy.
Table 3.4: Screening of the proposed power distribution line project against international treaties on protection of
the atmosphere
No Convention Status in
project area
Remarks
The 1985 Vienna Convention on Protection of the
Ozone Layer
The 1987 United Nations Montreal Protocol on
substances that deplete the ozone layer
No trigger
The 1992 United Nations Framework Convention
on Climate Change (UNFCCC) which led to the
Kyoto Protocol of 1997
Trigger Tree removal impacts on the
carbon sink but use of electricity
for lighting cuts down on GHG.
The 1997 Kyoto Protocol on Climate Change Trigger
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
30
3.3 The Regulatory Framework
This Project Report Process is subject to control by three administrative frameworks namely:-
3.3.1 The Rural Electrification Authority-REA
The Rural Electrification Authority (REA) is a State Corporation established under Section 66 of the
Energy Act, 2006 (No 12 of 2006) to manage the Rural Electrification Programme including the
formulation of a rolling Rural Electrification Programme Master Plan which would present least-cost
electrification options for target areas. In the capacity of Employer in this Study, REA has defined the
scope and coverage of the Project which to a large extent determines the depth of the study to be
undertaken. Towards this, the Employer has stipulated Study tasks to be executed towards ensuring a
comprehensive, legally proficient study output. The REA thus wields the administrative framework
towards supervision and quality control of the study.
3.3.2 The Energy Regulatory Commission-ERC
The Energy Sector in Kenya is regulated by the ERC which was established under the Energy Act of 2006.
Section 6 of the Energy Act 2006 confers on the ERC a mandate to ensure environmental protection
within the energy sector in the capacity of de jure Lead Agency. Section 6 of the Energy Act empowers
the ERC to formulate, enforce and review environmental, health, safety and quality standards for the
energy sector, in coordination with other statutory authorities; and, to enforce and review regulations,
codes and standards for the energy sector. Further, Section 30(1) and (2) of the Energy Act 2006
requires that ‘The Commission shall, in granting or rejecting an application for a licence or permit, take
into consideration; - (i) the impact of the undertaking on the social, cultural or recreational life of the
community; and (ii), the need to protect the environment and to conserve the natural resources in
accordance with the Environmental Management and Coordination Act of 1999.
This Project Report has partly been prepared in fulfillment of requirements of the Energy Act 2006 and
indeed, the final output will be reviewed by the ERC in the capacity of Lead Agency.
3.3.3 The National Environmental Management Authority-NEMA
EMCA 1999 allows for formation of the National Environmental Management Authority (NEMA) as the
body charged with overall coordination of environmental protection in Kenya. A Director General (DG)
appointed by the President heads the Authority established in 2001. Several Directors in charge of
Enforcement, Education, Policy, who are assisted by Assistant Directors and Senior Officers under them,
assist the DG. To facilitate coordination of environmental matters at District level, EMCA 1999 allows for
creation of District Environmental Committees (DEC) traditionally chaired by respective District
Commissioners. However, in order to align to requirements of Kenya Constitution 2010, NEMA has
devolved functions to Counties. Under the New arrangement, EIA licensing for projects will take place at
either the County or National level depending on the perceived environmental risk category as per the
NEMA advert of 9th
July 2012.
Thus this Project Report recognizes NEMA as the sole regulator of EIA processes in Kenya. Indeed, the
second objective of the Project Report is to facilitate Environmental Licensing of the 33 kV Distribution
line by NEMA; in which case, the Report has to ensure compliance with all standards as set out by NEMA
in capacity of Environmental Regulator in Kenya. The Project Report Process has thus been tied up to the
NEMA institutional framework at Head Office and County levels.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
31
4 CHAPTER FOUR: THE BASELINE ENVIRONMENT
4.1 The Bio-physical baseline
4.1.1 Location and administrative set-up
The entire Mwachabo power distribution line project falls within the Mwatate District of Taita Taveta
County. Specifically, the Mwachabo location targeted for power supply lies to the south of the Mwatate-
Taveta (A23) road to the west of the Teita Sisal Estate.
4.1.2 Relief and physiographic profile
Mwatate District comprises the lowland belt of the Taita Taveta Highland-Lowland Continuum.
Mwachabo location is situated in the Taita lowlands which is part of the expansive lowland area
extending from the Yatta Plateau in the East to beyond the Tanzanian boundary in the west and which
contains the Tsavo East and West National Parks. Relief is dominated by a generally flat, monotonous
plain which is only interrupted by minor local depressions and occasional inselbergers. Altitude generally
averages 700 m above sea level.
Plate 4.1: An inselberg in the Mwatate Plains
4.1.3 Climatic regime
Rainfall data for the Voi Meteorological station which is considered nearest to the Project area is
presented in Table 4.1. On account of low altitude and absence of relieve barriers, annual rainfall in the
Mwatate lowlands in a low of 555mm. Annual rainfall is delivered in 2 distinct wet seasons lasting
March to April and November to December with the bulk of rainfall occurring in the second season.
June to September marks a severe dry season with mean monthly rainfall generally below 20mm.
Table 4.1: Climate data for the Mwatate area based on the Voi Meteorological station
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
32
Month Daily
maximum
Temp (oC)
Daily
minimum
Temp (oC)
Daily
Sunshine
hours
Daily
wind
run
Monthly
evaporation
Monthly
mean rainfall
(Voi)
Monthly
mean rainfall
(Taveta)
Jan 31.6 20.1 8.1 92.5 191 34 57
Feb 32.9 20.2 7.4 95.1 195 29 42
Mar 33.3 20.8 7.7 100 211 79 95
Apr 31.8 20.4 7 116.9 174 100 143
May 29.9 20 7 149.6 169 30 64
Jun 29 18.3 6.9 161.4 173 6 19
Jul 28.1 17.5 6.1 168.3 174 3 12
Aug 28 17.2 5.7 179.3 167 8 12
Sep 29.2 17.6 6.7 156.8 178 15 12
Oct 31.1 18.9 8.4 137.5 206 26 21
Nov 31.4 20.1 7.7 103.2 181 106 120
Dec 30.6 20.4 7.8 87 170 119 76
Total 2189 555 673
Max 33.3 20.8 8.4 179.3 211 119 143
Min 28 17.2 5.7 87 167 3 12
Ave 30.6 19.3 7.2 129 182 46 56
For purposes of this study, climate of the proposed traverse has been calibrated against standard
parameters namely the climatic index as determined by the ratio of rainfall (r) to potential evapo-
transpiration (Eo) based on the method of Sombroek et. al, 1982.2 With a mean annual rainfall of
555mm and an equivalent potential evapotranspiration of 2189mm, Mwatate area has a climatic index
(r/Eo ratio) of 0.25 which translates to a Climatic Zone V which is semi-arid, fairly hot to very hot.
Monthly rainfall does not exceed potential evapotranspiration demand in any month (Fig 4.2) implying
that moisture scarcity poses the most severe limitation to ecological productivity in the area. Past
studies on local rainfall patterns (Ogallo, 1979) suggest that long-term rainfall patterns in Taita include
cyclical droughts, such as those experienced in 1887, 1921, 1970-71, 1974-75. In the last 30 years (1969-
1999), the major droughts were experienced in 1984, 1988 and in 1998.
2
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
33
0
50
100
150
200
250
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Mo
nth
ly r
ain
fall/
PE
T(m
m) Moisture balance for the Mwatate area
Mean monthly PET(mm) Monthly mean rainfall (mm)
Figure 4.1: Seasonal moisture balance for Mwatate area
4.1.4 Cover vegetation
Mwatate area is semi-arid characterized by Savannah bush land comprised of Acacia-Commiphora
Dryland Forest, where the dominant species include; Acacia tortilis, Acacia nilotica, Acacia bussei, Acacia
hockii, Commiphora africana, Commiphora campestris, Commiphora confusa. The average canopy
height is between 5-7m with the maximum height being approximately 10m. There are occasional taller
hardwood species such as Terminalia spinosa, Melia volkensii, Boscia coriacea, Cassia abbreviata,
Newtonia hildebrantii. On account of human incursion, the original vegetation has been removed either
in total as in the case of the Teita Sisal Estate or partially to provide wood for building and charcoal
making. Remaining bushlands are subsequently dominated by low growing shrubs comprised of
Commiphora spp, Balanites, Accacia spp, Terminalias, among others (Plate 4.2).
Plate 4.2: Remnant semi-arid vegetation in the Mwachabo Location
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
34
Of special mention are the local isolated hills within the project area where vegetation is fairly intact and
is reputed to be teeming with wildlife species such as lions, leopards, among others. Given the close
vicinity to the Tsavo West National Park, the southern parts of Mwatate District are home to a diversity
of over 50 species of large mammal, more than 20 species of bats, over 300 species of birds and
important populations of IUCN Red List species such as Grevys zebra (Equus grevyi), Cheetah (Acinonyx
jubatus), Lion (Panthera leo), African wild dog (Lycaon pictus) as well as the African elephant (Loxidonta
africana). Such wildlife occasionally disperses into the Mwachabo location.
4.1.5 The socio-economic profile
4.1.6 The inhabitants
Mwatate District is primarily inhabited by the Taita who are native to this area. However, the
employment and trade opportunities presented by large-scale sisal farming, tourism, mining and cross-
border trade at Taveta have attracted people from other communities who have formed cosmopolitan
settlements in Mwatate Town and other trading centers.
4.1.7 Population dynamics
As at the 2009 National Population Census, the then Mwatate Division (now a District) had a total
population of 60,698 people comprised of 15,839 Households. Mwachabo location had a population of
12,263 people comprised of 3,065 households. Being a new settlement and on account of presence of
the Teita Sisal Estate, the population density is low, at 31 persons per square kilometer.
Table 4.2: Population statistics for Mwatate District
Administrative
Unit
Pop statistics (2009 Census)
Men Women Total Households Density (Pers/km2)
Mwakitau Loc 3,426 3,500 6,926 1,859 10
Bura Loc 4,813 5,146 9,959 2,707 38
Mwachabo Loc 6,355 5,908 12,263 3,065 31
Mwatate Loc 7,444 7,064 14,508 4,050 42
Mwatate Div 30,420 30,278 60,698 15,839 35
4.1.8 Land use and livelihoods
Large-scale sisal farming comprises the main land use within Mwachabo location. Outside of the large-
scale farms, livelihoods are based on subsistence mixed agriculture in which crop farming is combined
with keeping of local animals while others rely on trade. On account of aridity, crop farming is a risky
business on which account, this location frequently relies on food relief.
4.2 Ecologically sensitive resources
Mwachabo location shares common boundaries with the Tsavo West National Park on which account, it
is an important habitat and dispersal area for wildlife. This ecological function is however threatened by
increased bush clearing for agricultural settlements.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
35
5 CHAPTER FIVE: STAKEHOLDER CONSULTATIONS
5.1 Need for stakeholder consultations
Legal Notice of 101 of June 2003 requires that all environmental assessment process in Kenya to
incorporate Public Consultation - a requirement informed by awareness that stakeholders are largely in
the constituency likely to be impacted by proposed developments and it is imperative that they be
informed of the project following which they can make informed comments and reactions to the
proposed development. It is also important to ensure that all stakeholder interests are identified and
incorporated in project development, implementation and operation and, against such background,
consultation was undertaken with a cross section of stakeholders both within and outside the project
area of influence with the following objectives:-
i) To disclose the project to both primary, secondary and other stakeholders;
ii) To obtain the reaction/comments/concerns of all stakeholders which is integral to the impact
prediction and interpretation process
iii) To obtain on the ground information of the pre project baseline. Thus, fieldwork combined both
stakeholder consultation and documentation of the baseline environment.
5.2 Approach to stakeholder consultation
5.2.1 Identification of stakeholders
The proposed distribution lines comprise a unique project in that, right from onset, project design
entails acquisition of land for construction of permanent overhead structures traversing close to 35.3
kilometers of land. Of necessity, numerous people are likely to be affected by the project and are
therefore bona-fide stakeholders demarcated by the decision to follow the proposed route of traverse.
The same were identified and consulted through diverse for a as outlined elsewhere below.
This study also identified other categories of stakeholders comprised of GoK offices, parastatals etc
within sectors deemed likely to be impacted by the project. This category was also consulted as key
informants on sectoral policy and to advise this EIA study on mitigation measures to be put in place so as
to minimize adverse impacts in respective sectors. In this category were also included local policy
makers and opinion leaders, local administration, local authorities, civic leaders among others.
5.2.2 Levels in stakeholder consultations
Of necessity, stakeholder consultations should take place alongside project design and implementation
to ensure that the project puts in place measures to cater for stakeholder concerns in all project phases.
In case of the proposed development of power distribution lines, stakeholder consultation was
approached at four levels namely;-
i) Briefing by Project Engineers: Briefing commenced after negotiating the contract and consisted
of discussions between the Consultant and the SWECO/Aberdare Engineers team. During such
discussion, the Engineers clarified the scope and expectations; mode of contract administration
and deliverables on the contract, and also provided information on project design to the
consultant. Notably, the consultant obtained design reports and maps from the feasibility study
phases of the project and also obtained contacts for supervision team on the ground.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
36
ii) National Level consultation: This entailed consultation with the project design team, Client and
Lead agencies (KFS and KeRRA) deemed relevant to the project. Such consultations applied to
the entire 8 schemes that were the subject of the contract for EIA.
iii) County and District Level consultations: These were mounted at respective counties and
districts with discussion focusing on project falling within such jurisdiction. However as
expected, the reaction especially from government sectoral Agencies (Education, KFS,
Agriculture, Public Health etc) are cross-cutting and hence applicable to all the 8 projects
irrespective of the administrative jurisdiction. Thus views of the KFS, KeRRA, Public Health,
Agriculture etc have been applied in developing the project report and by extension the EMP for
the entire 8 projects.
iv) Project level consultations: Consultations have targeted residents of Mwachabo location who
essentially are the primary stakeholders to the project. While discussions at district level mainly
targeted line ministries those at county level mainly targeted county and regional offices such
as, county commissioners, county councils, KeRRA regional officers, County Forest Coordinators
etc where the target was to obtain sectoral position on potential impact of rural electrification
to that sector.
5.2.3 Methodologies in stakeholder consultation:
All consultations for this Study were undertaken by the Team Leader. Consultations generally employed
diverse methodologies depending on the target audience. Methodologies included;
• Key informant interviews:-
• Focus Group Discussions (FGD):-
• One to one consultations: These were held with local residents or traders when it was not
possible to cause for a quorum for a focus group discussion. At the end of an interview each
informant was requested to sign the comments as registered by the Team Leader.
• Indirect consultations: Numerous individuals and institutions previously played diverse roles in
the formulation and design of the power distribution lines project and though it was not
possible to make direct contacts with them, the same was achieved through study and review of
outputs left behind in form of reports. Thus, considerable time input was devoted to review of
project documents towards preparation of this Project Report. Appendix 5.1 provides a list of
documents reviewed as part of this study.
5.2.4 Progress in consultation
A summary and tally of the entire stakeholders consulted for this project is provided in table 5.1 below.
Essentially a total of 27 people were consulted and this includes the national level stakeholders (the
Project Design Engineers, the Rural Electrification Authority (REA), Kenya Forest Service (KFS), the Kenya
Rural Roads Authority-KeRRA, etc) and some county based GOK stakeholders whose inputs are deemed
relevant to all the 8 rural electrification schemes contracted for environmental impact assessment.
A record of Nairobi based consultations is provided in Appendix 5.2 below while Appendix 5.3 provides a
record of project specific consultations conducted in Taita Taveta County, Mwatate District and the
Mwachabo location (Plate 5.1).
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
37
Plate 5.1 : Stakeholder consultation at Kamtonga Trading Centre
County/ Provincial administration: In the capacity of coordinator of GOK business at grassroots level,
this sector was contacted in all the 8 counties targeted for REP scheme development with outcome as
follows:-
i) The sector is not aware of any adverse environmental and social impacts associated with rural
electrification.
ii) At locational and divisional level, this sector required that project contractor to establish contact
and linkage so as to ensure incident free construction of the power lines.
iii) Chiefs contacted also requested to be involved during construction and commissioning of the
power lines so as to ensure community mobilization towards securing of the investment
(Transformers) from theft and vandalism.
The Kenya Forest Service: Concerns of the KFS at the County (CFC) and zonal levels resonated with
those of their counterparts at NEMA.KFS is concerned that;
i) None of REP schemes pass through gazetted forests.
ii) From past experience trees are either excessively lopped or removed to give way for REPs
iii) In most cases trees are removed by REP contractors without consulting the KFS offices on the
ground in complete bleach of the requirements of the forest act.
iv) The KFS requires that all EIA project reports proposed in respect of REP be shared with CFCs for
review and possible comments on impacts on tree resources.
v) The KFS also required to be involved at construction stage to ensure that trees are protected
and to advise on modalities for replacement of trees so lost.
Ministry of public health: At county level, the ministry of public health was only contacted at Wundanyi
under auspices of the District Medical Officer of Health (DMOH) who appreciated the great impact of
rural electrification towards facilitating service delivery by dispensaries. The DMOH however expressed
concern over ability of dispensaries to pay for connection to grid power supply given their very low
budgetary allocation.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
38
Table 5.1: Summary table of stakeholders consulted
Part Level of
consultation
Stakeholder category No Nature of meeting No of
people
met
Part
one
National Level
(General)
KFS 2 Met Deputy Director forest
conservation and Management and
the officer in the legal services
department.
2
KeRRA 1 Met an officer in the survey
department.
1
KeNHA 1 Met with the Manager- Surveyor
Services
1
REA 1 Held several discussions with the
Project Manager and Way leave officer
2
Aberdare/SWECO 1 Held several consultative meetings
with both Project managers and a
supervisor
3
Part
Two
County Level
(General)
County Commissioner 1 County Commissioner visited but was
out of office
0
County Council of Taita
Taveta
Chief Officers of this Council were in a
meeting whole day
Kenya Rural Roads
Authority
1 Held telephone discussion with the
Head of the KERRA sub-office at
Mwatate
1
Kenya Forest Service 3 Met with the County forest
coordinator in Taita Taveta
3
NEMA 1 CDE and CEO were out of office. Held
discussion with the CEO on the phone.
1
Part
Three
District Level
(Scheme
Specific)
Provincial Administration 1 Assistant chief-Mruru/Mwanganga sub
location
1
Ministry Of Agriculture 1 District Agriculture Officer 1
Ministry of Health 1 District Medical Officer of Health 1
Part
Four
Project level
(Specific)
Local residents and
traders
2 1 Baraza at Kamtonga market and 1
semi baraza at Manoa market.
29
Local Dispensary 1 Met the Kenya Certified Nurse Manoa
dispensary
1
Total 18 46
The Kenya Rural Roads Authority: KeRRA was not consulted only at sub regional level at Taita County.
Comments here are borrowed from consultations held with KeRRA officers in Makueni, Kitui and
Machakos under the same contract who made comments as follows:-
i) KeRRA is concerned that contractors for REP do not take time to familiarize with the extent and
alignment of rural roads leading to some power distribution poles being erected in the middle of
the road reserve and thus creating conflicts with either road users or future road development.
ii) KeRRA requires to be consulted during the process of design and construction of power lines
within areas of jurisdiction.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
39
Local Authorities-County and Town Councils: During the visit to Wundanyi, Chief Officers of the Taita
Taveta County Council were locked in a meeting the whole day and were thus not available for
consultation. Views expressed here are based on consultations made with the Kilifi County Council,
Makueni County Council, Wote and Tala Town Councils and the Masaku County Council. Local
authorities raised concerns as follows:-
i) REP should be designed and constructed to utilize existing and anticipated road reserves, taking
care to reserve the 9 m required for road construction. As such REPs should be restricted to
within one metre boundary of road reserves.
ii) Where power poles are cited in private property, they should exploit boundary areas to avoid
conflict with future development.
iii) County Councils are concerned about indiscriminate tree removal to give way to power lines in
market centers. In spite of money having been spent to establish and tend such scenarios, local
authorities should be consulted during the design and construction of power lines within areas
of jurisdiction.
iv) Local authorities stated that contractors doing business within respective areas of jurisdiction
should pay rates as appropriate in line with Cap 265.
Ministry of Agriculture: Concerns were raised as follows:-
• Excessive lopping of fruit trees interferes with food security and the farm based livelihoods.
• Electric poles and way leaves fix the land out of certain uses and can interfere with the farm
economy.
• Supply of electricity was potential to undermine adoption of either renewable energy
technologies such as solar pv biogas, wind etc.
• These comments were found to apply to all schemes.
Ministry of Education: This is one sector that was observed to potentially benefit from electrification of
rural schools.
• Power supply to schools will facilitate replacement of diesel engines in boarding schools and
hence cut down the school operating costs.
• Power supply to schools will improve academic performance through increased time for prep,
reduced generator noise introduction of IT and allied courses.
• Electrical faults and malfunction however have potential to cause fire outbreak and associated
safety hazards.
• Power failure especially in the evening has been known to cause unrest and instability in
schools.
5.2.5 Comments from local stakeholders
Comments from the Public:
The comments are informed by 2 consultative meetings at Manoa market and an FGD held at Kamtonga
market with residents and traders. Their views are as follows:
(i) The public is in favour of the project as it will open up the area and they will benefit from various
investments which will therewith be facilitated by electricity.
(ii) Compensation: For the property that will be affected, the residents wanted to know whether they
will be compensated. More so, they also wanted to know if there will be compensation for poles
erected on private land.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
40
(iii) Beneficiaries: The residents wanted to know whether people who live at a radius of 3km will benefit
from the project.
(iv) Opportunities: Residents wanted to know if the local youth will be employed during the
construction phase.
(v) Route of traverse: residents wanted to know why the line follows corners instead of shortcuts.
(vi) The residents were wondering whether this is another of the political gimmicks.
5.2.6 Comments from local Institutions
The Manoa dispensary
They are in favour of the power distribution to the area as they will be able to offer services that were
previously not offered eg maternity care and laboratory services.
Local schools: It was not possible to get comments from local schools which were already closed at the
time of fieldwork. However, going by interviews with schools from other counties, power supply is
welcome as it will facilitate adoption of IT and computer based learning and school management.
5.3 Salient observation from stakeholders’ consultation
From the foregoing analysis and documentation, salient observation can be deduced as follows.
i. Public support and demand for rural electrification: The public is in support of this project and some
of the benefits they anticipate include:
• Lighting up of villages and village institutions.
• Opportunities will be created through such investments as welding, salons, cybercafés etc which
will not have been possible without electricity.
• Education will be more enhanced and diversified through E-learning and other computer based
academic programmes.
ii. Public apprehension over trees removals: Overwhelmingly indiscriminate and excessive removals of
trees to give way to power lines emerged as the most severe and commonly identified adverse
impact of rural electrification. The same area identified by both local owners and government sector
stakeholders. Removal of trees also sets in questions of compensation to respective owners.
iii. Potential conflict on use of roads reserves owing to misplacement of power distribution.
iv. Conflict over allocation of jobs in the building of power lines.
v. Concerns on the safety and security of power distribution equipment before and after
commissioning
5.4 Modalities for conflict resolution
Some recommendations on approaches to conflict and dispute resolution during project development
are outlined in section 8.45 below.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
41
6 CHAPTER SIX: ANALYSIS OF ALTERNATIVES
6.1 Overview
In sections below, we provide some background to the process that informed formulation of the project
in its current design. Notably, the project was subjected to detailed feasibility studies where diverse
options were considered leading to identification of the project and choice of technological options as
currently proposed. Project alternatives were considered at diverse levels namely; technological
options, route of coverage etc out of which, an overhead distribution line mounted on wooden poles
delivering power to markets within Mwachabo location was selected. Some of the options considered
are briefly reviewed in sections below.
6.2 Levels in evaluating project alternatives
6.2.1 Evaluation of the No Project option
Access to electricity remains low in Kenya and the country has one of the lowest percentage coverage by
electricity among African countries. In Uganda, only 9 percent of the population has access to electricity;
in Kenya, 14 percent; in Congo, 6 percent. In oil-rich Nigeria, the energy demands are nearly twice
national power output and this lack of industrial energy is continents biggest obstacles to development
and a big turnoff for foreign investors. Further, firms operating in Kenya persistently report erratic
power supply as a critical impediment to competitiveness. Expansion of electric power distribution
networks has great potential to redress this matter thereby catalyzing badly needed investment
especially in rural areas.
The proposed Mwachabo power distribution line is being developed as part of a wider national initiative
aimed at supplying power to rural markets and institutions. The no-project scenario would imply
continuation of inadequate power supply and is clearly not desirable for an economy that is struggling to
recover from impacts of political violence and drought. As such, any initiative with potential to increase
the percentage of Kenyan population covered by electricity is economically strategic in line with current
government emphasis on increasing percentage national coverage by electricity particularly in rural
areas.
Provision of additional power supply has been identified as crucial to achievement of the national
development aspirations as elaborated in the national development blue print–the Vision 2030 in which
case, the focus is on modalities for supply rather than the justification of what is clearly a move towards
implementation of government policy.
6.2.2 Options in the selection of the routes of traverse
The first six kilometres of the Mwachabo power distribution line will traverse the Teita Sisal estate
where the core consideration is the need to keep clear of sisal plantations to the extent possible.
Subsequent to this need, the route of traverse was aligned to the reserve of an existing road with the
result that the power distribution line will be longer and possibly more expensive compared to a straight
traverse.
6.3 Choice between diverse distribution technologies
Distribution vs local generation: Grid electric power is available at the Taita Sisal Estate within 6
kilometers of the first load center namely Mwachabo market which makes it much cheaper to tap and
distribute as opposed to local generation. Local generation would also require multiple investment in
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
42
generating stations backed up by distribution lines to the points of consumption and would eventually
end up being more expensive.
In spite of grid electricity being readily available, the high rate of solar radiation averaging 7.2 hrs daily
provide excellent opportunities for tapping and utilizing solar power which should be taken advantage
of.
Overhead versus underground distribution lines: The choice between overhead versus underground
distribution lines was also considered. Indeed, electric power can be distributed by underground power
lines which facilitate distribution across: (i) densely populated urban areas, (ii) areas where land is
unavailable or planning consent is difficult, (iii) rivers and other natural obstacles, (iv) and with
outstanding natural or environmental heritage, (v) areas of significant or prestigious infrastructural
development and land whose value must be maintained for future urban expansion and rural
development, etc. Additionally, underground power lines are;-
• Less subject to damage from extreme weather conditions (mainly lightning, wind and freezing)
• Greatly reduced emission, into the surrounding area, of electromagnetic fields (EMF). All electric
currents generate EMF, but the shielding provided by the earth surrounding underground power
distribution lines restricts their range and power.
• Underground power distribution lines need a narrower surrounding strip of about 1–10 meters
to install, whereas an overhead line requires a surrounding strip of about 20 meters wide to be
kept permanently clear for safety, maintenance and repair.
• Underground power distribution lines pose no hazard to low flying aircraft or to wildlife, and are
significantly safer as they pose no shock hazard (except to the unwary digger).
Some disadvantages of underground power cables:
• Undergrounding is more expensive, since the cost of burying cables is several times greater than
overhead power distribution lines, and the life-cycle cost of an underground power cable is two
to four times the cost of an overhead power distribution line.
• Whereas finding and repairing overhead cable breaks can be accomplished in hours,
underground repairs can take days or weeks, and for this reason redundant lines are run.
• Underground power cables, due to their proximity to earth, cannot be maintained live, whereas
overhead power cables can be.
• Operations are more difficult since the high reactive power of underground cables produces
large charging currents and so makes voltage control more difficult.
Given all these considerations, construction of overhead distribution lines is the option favored by REA.
6.4 Choice of Tower structures
Steel poles: Tubular steel poles are typically used in urban areas, but are more vulnerable to vandalism
especially in isolated areas.
Wood: In Kenya, use of single wood utility pole structures is common in the construction of 33 kV power
distribution lines as proposed for Mwachabo. Construction entails placing a pole in the ground upon
which, one cross arm is fixed at the top end for purpose of supporting insulators and conductors. Wood
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
43
is considered cheaper that other materials and has an overall cost saving of 20-30%. Wood is preferred
for such construction for, in addition to being relatively cheaper, wood has surge voltage insulating
properties which is not found in steel, aluminum or reinforced concrete structures.
Concrete: Use of concrete pylons worldwide is limited by their excessive weight which makes handling
and installation complex.
Aluminum: Where towers must be placed in inaccessible terrain by helicopters, the extra material cost
of aluminum towers will be offset by lower installation cost. Design of aluminum lattice towers is similar
to that for steel, but must take into account lower stress properties inherent to aluminum.
6.5 The preferred option
A comparison of all the options is summarized in table 6.1 below. From the analysis, the proposal to
investment in a medium voltage overhead distribution line based on wooden poles as currently
designed seems to be the preferred option given cost and technical considerations. Any adverse
impacts will be mitigated as per the Environmental and Social Management Plan (ESMP) unveiled in
Chapter Eight Below.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets
(Mwatate Constituency) 33 kV power distribution line
Table 6.1: Analysis of alternatives
Level of
evaluation
Option evaluated Advantages Disadvantages Preferred option Mitigation of
adverse impacts
Project No project scenario Savings to the national
economy, will avoid
environmental and social
costs
Economic losses due to
power outages, slowed
economic growth.
Develop project As per ESMP
Alternatives
in the route
of traverse
Winding as
opposed to straight
course
Less encroachment on sisal
plantations.
Route is longer and more
costly
Longer alignment
along existing road
reserve
Budget for
construction
Choice of
technology
Local generation
vis Distribution
Cut down on distribution
costs, will avoid displacement
and environmental costs
Requires multiple
investments in generating
stations and distribution to
market.
Distribution option As per ESMP
Overhead vs
underground
cables
It is cheaper to develop and
maintain.
High displacement costs and
exposure to accidents and
EMR in OHDLs
Use OHDL As per ESMP
Wooden poles vs
steel and concrete
poles
Wood is cheaper, readily
available and has inherent
surge protect properties.
Sourcing of wood impacts on
natural carbon sink.
Use of wooden
poles.
As per ESMP
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
7 CHAPTER SEVEN: POTENTIAL IMPACTS FROM THE PROJECT
7.1 Generic Social and Environmental Impacts
7.1.1 Outcome of impact prediction
The Mwachabo power distribution line as proposed will require space in terms of both vertical and
horizontal projection and depending on the current physical and social characteristics of this space,
some impacts are likely to be triggered whose analysis is the subject of this chapter.
Impact prediction for this ESIA Study basically relied on four tools namely;-
• The generic checklist for impact prediction issued by NEMA as the Third Schedule to Legal
Notice 101. Appendix 7.1 presents a matrix based on this Schedule.
• The Checklist for Environmental Characteristics developed by the Department of Environmental
Affairs of the Republic of South Africa (Appendix 7.2).
7.1.2 Analysis of impact severity
Predicted impacts were analyzed for severity through screening for diverse attributes/ features
including magnitude, persistence, potential for reversibility, cumulative and tendencies, potential to
occasion secondary and cyclic impacts etc. Potential impacts were subsequently ranked on a scale of 2P,
P, O, N and 2N reflecting Highly Positive, Positive, Neutral, Adverse and Highly Adverse category of
impacts respectively. Table 7.1 below provides a summarized outcome of impact prediction and
interpretation based on application of the four checklists to the design, construction, and operation
phases of the proposed power distribution line and substation.
7.2 Description of potential impacts
7.2.1 Overview of impacts
Scale of impacts: The tally of potential impacts and their trends as identified in respect of the proposed
Mwachabo power distribution line are summarised as follows:-
Impact category Total Long-term
effect
Irreversible
effect
Cumulative
effect
Potential for
secondary impact
Total impacts areas 34 17 3
Positive impacts 17 10
Negative impacts 17 7 2 6 9
Net impact pre
mitigation
0
It must be pointed out that the scope of adverse impacts associated with construction of 35.3
kilometers of a medium voltage power distribution line in an otherwise low density agricultural
settlement is inherently low. Thus, for the proposed Mwachabo power distribution line, a total of 34
impacts out of which 17 are positive were identified. Other trends can be summarized as follows:-
• Only 17 negative impacts are likely to be occasioned by the proposed construction and
operation of the 10 kilometres of power distribution line as proposed and, all are observed to be
of low severity.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
46
• Ten of the 17 positive impacts are likely to be long-term in prevalence while 7 out of 8 adverse
impacts have a long-term effect with 2 of them being potentially irreversible.
• Nine out of sixteen adverse impacts have potential to cause secondary impacts while 6 of them
have cumulative tendency i.e., they have potential to aggravate an already existing problem.
• The project has a marginal net positive impact pre mitigation which will require to be enhanced
through adoption of an effective impact mitigation strategy.
Presentation of impacts: From this analysis, it is apparent that the bulk of adverse impacts (Ns) will
manifest at the construction stage while most benefits (Ps) will be realized during the operation phase.
In line with this trend, impact mitigation will be targeted more on the construction phase activities.
Without exception, all adverse impacts have potential to occasion secondary impacts and thus merit
mitigation. For purposes of this study, impact prediction has captured the three core phases of the
proposed development namely;-Design, Construction and Operation phases. Similarly, impacts analysis
as presented in Table 7.1 has captured and followed all the four phases of the project. Brief highlight of
impacts at each stage of the project are presented in sections below.
7.2.2 Impacts at Design Stage
Positive Impacts of design Stage:
Generally, the design phase is associated with positive impacts mainly manifested through creation of
business opportunities for professionals involved in the design work, support staff hired in the
enumeration survey, etc, while the country benefits from generation of additional planning data which
will influence policy decisions within long time frames. Certainly, the database compiled from design
report will find consumption far beyond the confines of this project.
Adverse impacts at Design Stage:
Adverse impacts would mainly be manifested through site disturbances and accidents associated with
field survey work.
7.2.3 Positive Impacts at Construction Stage
(i)Creation of business opportunities:
The proposed distribution lines will comprise of 35.3 Km of conductors and 5 transformers supported by
126 poles. Construction work wills therefore some modest entail investment estimated at Ksh 41.15
million, the bulk of which will go into procurement of construction material and hiring of the contractor.
Construction of the distribution line will thus open up extensive trade opportunities while other
economic benefits will accrue through creation of employment opportunities for both skilled and semi-
skilled labour engaged in construction. At local level, communities will benefit from short-term
employment opportunities in the construction activity.
(ii)Creation of opportunity for change:
Relocation of buildings and property from the right of way has destabilizing effects to PAPs. However,
the same process provides opportunity to occasion changes such as the need to regularize land and
property subdivisions and transfers, the need to settle boundary disputes, the need to formalize
inheritance etc which, in the long-run provides a stronger foundation for economic growth.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets
(Mwatate Constituency) 33 kV power distribution line
Table 7.1: Matrix for impact prediction and interpretation
Project
Phase
Source of
Impact
Potential Impact Severity
*
Persistence Trigger to
secondary
impacts
Triggers to
cumulative
impacts
Design Stage Design
Studies, field
surveys and
inventories
Creation of temporary opportunities for gainful
employment
P Short-term
Generation of additional site-specific data
/study reports
P Long-term
Capacity building and sensitization P Long-term
Minor accidents during survey work N Short-term Reversible Minor
Construction
Phase
Supply of
materials
Business opportunities in supply and transport
of construction materials
P Short term
Generation of GHG in the transportation of
construction materials
N Short-term Reversible Climate change
and impacts
GHG build-up
Road hazards in material transportation N Short-term Reversible
impacts
Irreversible
impacts
Traffic build up
Construction
work
Short-term opportunities for business and
employment in construction
P Short-term
Revenue to GoK and Local Authorities through
taxes
P Short-term
Opportunity for change P Long-term
Damage of property (tree crops) from ROW
corridor
N Long term Reversible Escalating
poverty
Can aggravate
poverty
Deforestation and loss of Carbon sink from
felling trees
N Long-term Reversible GHG build-up Aggravates a
global concern
Occupational health and safety concerns for
construction crew
N Short-term Reversible Impacts of
injuries and
occasional
death
None
Solid wastes from construction activity N Short-term Reversible Littering,
injuries, etc
Solid waste is a
growing problem
Loss of nesting grounds for avifauna, bees, and
dry season fodder from tree removal
N Long-term Reversible Risks to pop
stability
Increasing loss
due to human
encroachment
Impact on existing and future infrastructures 2N Long-term Reversible Higher costs in
service delivery
Least Concern
Operation Presence of Economic gains from improved and stabilized 2P Long-term
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets
(Mwatate Constituency) 33 kV power distribution line
48
Project
Phase
Source of
Impact
Potential Impact Severity
*
Persistence Trigger to
secondary
impacts
Triggers to
cumulative
impacts
Phase powered lines
power supply
Enhanced delivery of services in medicare,
education, admin, telecommunication, etc
2P Long-term
Financial gains in oil to electricity substitution,
and elimination of maintenance costs for diesel
engines, etc
P Long-term
Employment creation, reduced cost of
investment
2P Long-term
Cutting down on GHG emissions due to
petroleum to electricity substitution
2P Long-term
Reduction in solid waste from lead acid
batteries, dry cells, candle residues, waste oil/
spares from gensets etc
P Long-term
Adverse
impacts from
charged high
voltage power
lines
Exposure to Electromagnetic fields (EMF) N Long-term Irreversible Hazards to
public health
Increasingly a
problem
worldwide
Impact on avifauna and other wildlife from
presence of charged wires
N Long term Reversible Risks to
population
stability
Cumulative
Permanent visual intrusion into space N Long-term Irreversible Rare Intrusion by
power lines a
growing problem
Hazards in attempted vandalism of
transformers
2N Long-term Reversible None This is a grave
concern
nationally.
Disincentive on use of other Renewable Energy
Sources e.g. RETs
2N Long-term Reversible A growing
problem
Net environmental worth of
the project pre-mitigation
17 (17 positive outputs, mainly long-term),
17(17 adverse outputs, 9 long-term, 3 irreversible),
Net score=0 (Net neutral impact before mitigation)
Some adverse impacts
irreversible
*N=low adverse impact; 2N=moderately severe impact; 0= no impact; P=positive impact, 2P= significantly positive impact.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
7.2.4 Negative impacts at Construction Stage
(i) Impacts associated with removal and lopping of trees in the right of way:
By design, 33 kV power lines require little in terms of way leave in which case, their construction does
not entail extensive removal of trees and structures. However, the requirement that all trees
underneath power lines be removed to avoid incidence of accidents from powered lines has impacts as
follows:-
Loss of livelihood: On farm trees are part of the family capital and productive resources which generate
cash income upon harvesting and sale or from harvesting of fruits. Thus premature felling as occasioned
by construction of power lines represents a major loss on the side of the farmer who has spent
resources to nature the trees. In some cases, some families have no hope of ever benefitting from the
proposed power supply in which case, removal of their trees without adequate compensation pushes
them further into poverty.
Degradation of habitat for fauna and flora biodiversity: Removal of tree cover in a marginal climatic
potential area interferes with the survival of dependent vegetation due to loss of shade, stemflow,
nutrient cycling and other ecological support functions performed by mature trees. Further, removal of
mature seeding trees undermines the self-perpetuating capacity of affected species which in addition to
loss of nesting grounds for insects and avifauna, fodder and forage for browsers, shade and shelter etc,
has critical implications to the health of wildlife populations (see plate 7.2).
Plate 7.1: Birds nesting on a tree at Kamtonga market
(iii Hazards associated with transport and delivery of construction materials: Construction of a 35.3
kilometer power distribution line with require about 133 poles and several rolls of concoctors all of
which will be transported by road whose transportation raises concerns in terms of impact on local
roads and safety of other road users (see plate 7.3).
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
50
Plate 7.2: Transportation of construction materials has potential to undermine safety of other road users
(iv) Concerns in the storage of construction materials and components: Privatization of services in
construction of power distribution and distribution lines in Kenya have created a huge demand for
transformers, conductors etc which poses huge challenges in the management of such stores given the
increasing cases of theft of the same. Against such a background, the storage of power distribution
materials worth millions of shillings can easily escalate incidence of crime whereby resultant searches
and arrests serve only to antagonize the project from host communities.
(v) Occupational Health and Safety impacts on workers: Construction, testing and commissioning of a
power distribution line in an area reputed to be infested with wildlife will expose workers to multiple
occupational hazards such as injury and loss of life from accidental falling, motor accidents,
electrocution, mauling by animals, etc which are costly to both affected families in terms of loss of
income and the government through loss of productive labour and increased dependency. Though such
risks prevail only during the construction phase, their impacts can be long lasting depending on the
degree of injury sustained.
(vi) Generation of construction waste: Junk in form of scrap metal, plastics, pvc cords, etc will be
generated from construction activity. Such waste, estimated at 10% of all construction materials has
potential to pose environmental challenges unless appropriately disposed.
7.2.5 Impacts at the Operation Phase
Extension of the distribution lines is potentially very beneficial especially on economic and
environmental fronts. We highlight some of the benefits here below.
Creating opportunities to promote economic growth:
Energy is identified as one of the infrastructural enablers of the ‘’three pillars” of Vision 2030 and with
only 4% of the rural population having access to electricity; the rate of economic development must
remain understandably low. Kenya is therefore expected to use more energy in the commercial sector
on the road to Vision 2030 and as incomes increase and urbanization intensifies, household demand for
energy will also rise. The challenges facing the power sub-sector include a weak power distribution and
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
51
distribution infrastructure, high cost of power, low per capita power consumption and low countrywide
electricity access. Preparations have been made to meet this growth in demand for energy under the
Vision as follows:-
• The government has continued to finance extension of electricity supply in the rural areas as
part of the basic infrastructure to stimulate economic growth and employment creation. This is
intended to increase electricity access in rural areas currently at 4% to 12% by the year 2012.
• The Kenya Electricity distribution Company (KETRACO) has been created with full mandate to
expand the electricity distribution grid and the government is also encouraging the Kenya Power
and Lighting Company to adopt affordable connection policies so as to boost the number of
customers in the rural areas.
• A Rural Electrification Authority (REA) charged with the mandate of implementing the Rural
Electrification Programme came into operation in July 2007. In addition, Ethiopia and Kenya
have undertaken a feasibility study and secured financing to facilitate the transfer of power to
Kenya from a number of large Ethiopian hydropower projects that provide power at lower costs
compared to that generated locally.
Against this background, construction of the proposed Mwachabo power distribution line is seen as a
positive intervention towards implementation of GOK strategies for economic growth especially in rural
areas. Positive benefits will manifest as follows:-
• Provision of electric power will open up market centres to investments such as engineering
services, welding, banking, computer services, etc that are difficult to provide in absence of grid
electricity.
• Electricity supply to rural centres will widen opportunities for gainful employment, human
resource development and rural commerce all of which are recipe for rural transformation.
• Once connected to power distribution networks, some institutions such as schools and water
supply projects currently relying on diesel generators and pump sets will now shift to a relatively
cheaper, cleaner and more reliable energy source and in the process, cut down on financial
strains imposed by purchase of diesel fuels. In the process, schools taking advantage of
continuous supply of electricity will light for longer hours and thus mount more aggressive
study/tuition programmes thus greatly improving on quality of delivery of education.
• Similarly, health institutions connecting to power distribution networks can henceforth adopt
power driven technologies and thus widen the array of services –imaging, immunization,
sterilization, theatre, etc, hitherto difficult to provide.
• Improved lighting in homes will motivate school / college going students to comfortably
undertake evening studies, and women and men will gain some precious time for themselves to
extend income generating work into the evening hours.
• Use of electricity for lighting and heating will also improve quality of indoor ambient conditions
thus improving the health of the people.
Cutting down on smoke and GHG emissions:
Within some urban households, supply of electric power could see a possible reduction in use of
biomass energy such as charcoal and firewood for cooking and heating through adoption of electric
stoves and other energy saving appliances thus improving domestic air quality with a possible impact on
family health. However, owing to economic and social considerations (type and quality of meals), most
rural folk connecting to electricity still opt for charcoal and firewood in cooking instead only preferring
to use electricity for lighting and watching television. Thus, substitution from petroleum fuels to
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
52
electricity will immediately cut down smoke emitted from burning of fuels (in lighting, heating and
motion) and thus improve on air quality for local residents including those operating the gen-sets.
Cutting down on waste oils and spares:
Routine operation and maintenance of diesel-powered engines releases waste oils, spares etc, all of
which are environmentally hazardous especially when in contact with water. The phasing out of diesel
engines upon substitution to electricity will go some way towards eliminating environmental pollution
associated with operation of diesel powered engines.
7.2.6 Adverse impacts from powering and operating the distribution line
Operation of the power distribution line has numerous socio-environmental benefits as enumerated
above. However, for such benefits to be felt down to all intended beneficiaries there is need to insure
against trends and actions with potential to trigger adverse impacts that can erode accrued benefits.
Such potential adverse impacts and their causes are briefly highlighted here below.
Influence on land-use/ future development:
Like any other infrastructure, installation of power lines has a strong influence on any future
development. Thus, given that power lines normally follow existing way leaves, improper siting has
potential to complicate or compromise future development-especially road expansion. This has been
identified as a potential source of conflict with the roads sector. The Roads Act 2007 currently identifies
the Roads Sector as the custodian of all road reserves which requires their total consultation in any
proposed utilization of the road reserve.
Visual intrusion effects:
Construction of a distribution line with 10-14 m high poles supporting conductors where none existed
before will change entire landscapes and introduce visual obstacles where none existed before. This can
be frustrating to local residents who will have to get used to changed neighborhoods and possibly
trends.
Disincentive on use of other energy sources eg RETs:
It is the Policy of the Kenya Government to encourage use other RETs (Renewable Energy Technologies)
such as solar converters, wind-driven generators, etc to supplement supply of grid electricity whose
supply is inadequate to meet peak demand. However, the practice in Kenya is for such practice to be
abandoned once connection to grid electricity is assured. As such, in a country whose firm generation
capacity is inadequate to meet the demand, supply of grid electricity provides a strong dis-incentive
against exploration of other, equally viable options for lighting and heating in rural areas. This is a long-
term trend whose reversal requires intervention at policy level.
Impacts on avifauna:
The Taita Hills and vicinity (Sagalla, Kasigau, etc.) are recognised as Important Bird Areas (IBAs) famous
for the Southern Banded Snake Eagle, Taita Falcon and Abbott's Starling as well as the 3 globally-
endangered species Taita Thrush, Taita White-eye and Taita Apalis which are endemic to these hills.
Birds occasionally find the electrical wires a resting place and are ever in danger of death and injury
from electrocution and collision with bare conductors. The problem is however more pronounced on
transmission lines and towers of 25 m height and above. Thus whenever bare conductors are used in
power transmission, the spacing would be critical as this would affect the lives of birds and especially
those with a wide wingspan. The latter are usually fewer and run a higher risk of elimination due to
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
53
either habitat destruction or other forms of killing and introduction of bare conductors thus increases
threats to survival.
7.2.7 Core concerns about the project
From analysis undertaken elsewhere above, potential adverse impacts from the proposed construction
of a power distribution line are quite modest and of low to moderate severity ranking. Towards
attempting mitigation, two adverse impacts however stand out as follows:-
• Project will displace trees and hence occasion some modest but fundamental economic and
ecological impacts.
• The project is likely to occasion conflict with the Roads Act 2007 over utilization of road
reserves.
Impacts however, have readily available means for mitigation and would therefore not stand in the way
for project implementation. An impact mitigation programme is outlined in sections below.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
54
8 CHAPTER EIGHT: THE ENVIRONMENTAL MANAGEMENT PLAN
8.1 Overview
This chapter outlines the environmental and social management strategy to be pursued in the
development and operation of proposed power distribution lines. The strategy comprises of both
an impact Mitigation Plan and an Environmental and Social Monitoring Plan
8.2 The Impact Mitigation Plan
Preparation of this Project Report has preceded project implementation in which case,
recommendations made here-in have a fair chance of being incorporated into and influence final
outcome of the project design process. This study recommends that findings be incorporated into
project design as a core mitigation strategy. Towards mitigation of specific impacts, action will be taken
as allowed for in Table 8.1 below.
8.3 Mitigation at design stage
The design stage is crucial to impact mitigation for any project. Firstly, at the design stage, projects enjoy
unlimited flexibility which makes alterations possible towards modifying components with potential to
occasion adverse impacts. As such, many potential impacts can easily be offset through modification of
the project design. In the case of proposed power lines, REA should take advantage of the design stage
to engage road sector stakeholders to mutually agree on modalities of using the road reserve. Such an
action will forestall conflict over use of the same space during construction and operation of the power
lines.
As well, the design stage allows for identification and commitment of resources towards impact
mitigation. It is thus hoped that, at this point, REA will identify and commit resources towards
compensating farmers for property to be displaced by the proposed power distribution line project.
8.4 Mitigation at construction stage
8.4.1 Mitigation of impacts associated with tree removal
Mitigation will principally aim at minimizing the number of trees to be removed which will require route
alignment to avoid areas of concentrated trees.
• Where tree removal is inevitable, proposed removalbe coordinated with the County Agricultural
Officer in line with the Agriculture (Farm Forestry) Rules 2009.
• REA will pay just compensation to affected farmers.
• As part of the Corporate Social Responsibility Programme, REA facilitate replacement of all lost
trees so as to rebuild cover vegetation, associated biodiversity and carbon sinks. The target here
is to support recreation of at least 10 ha of woodlots comprised of fruit trees, agroforestry trees
(casuarinas, grevillea and indigenous spp) as will be removed from the ROW. This may take the
form of funds set aside to purchase seedlings for issue to schools or institutions with land to
spare for reforestation.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets
(Mwatate Constituency) 33 kV power distribution line
Table 8.1: Matrix for impact mitigation
Project Phase Source of
Impact
Potential Impact Severity Mitigation Impact after
mitigation
Design Stage Design
Studies, field
surveys and
inventories
Creation of temporary opportunities for
gainful employment
P
Generation of additional site-specific data
/study reports
P
Capacity building and sensitization P
Minor accidents during survey work N Deploy competent staff 0
Construction
Phase
Supply of
materials
Business opportunities in supply and
transport of construction materials
P
Road hazards in material transportation N Contractor to observe the Highway Code 0
Construction
work
Short-term opportunities for business and
employment in construction
P
Revenue to GoK and Local Authorities
through taxes
P
Opportunity for change P
Damage of property (tree crops) from ROW
corridor
N Provide just compensation for any loss P
Generation of GHG in the transportation of
construction materials
N Reduce distances covered in material
sourcing
N
Occupational health and safety concerns for
construction crew
N Deploy sober, competent crew with
supervision. Provide PPEs.
N
Solid wastes from construction activity N Apply the 3 Rs concept. 0
Impact on existing and future infrastructures 2N REA to consult road sector stakeholders in
the design and construction of power lines
in road reserves
N
Operation
Phase
Presence of
power lines
Economic gains from improved and stabilized
power supply
2P
Enhanced delivery of services in medicare,
education, admin, telecommunication, etc
2P
Financial gains in oil to electricity substitution,
and elimination of maintenance costs for
diesel engines, etc
P
Employment creation, reduced cost of
investment
2P
Cutting down on GHG emissions due to 2P
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets
(Mwatate Constituency) 33 kV power distribution line
56
Project Phase Source of
Impact
Potential Impact Severity Mitigation Impact after
mitigation
petroleum to electricity substitution
Reduction in solid waste from lead acid
batteries, dry cells, candle residues, waste
oil/ spares from gensets etc
P
Adverse
impacts from
charged high
voltage power
lines
Exposure to Electromagnetic Fields (EMF) N Threat not fully appreciated N
Impact on avifauna and other wildlife from
presence of charged wires
N Use of insulted conductors 0
Permanent visual intrusion into space N Adoption of insulated conductors which are
compatible with trees
N
Hazards in attempted vandalism of
transformers
2N Public sensitization campaign N
Disincentive on use of other Renewable
Energy Sources e.g. RETs
N REA to mount efforts to promote
alternatives to grid power
N
Net environmental worth of
the project pre-mitigation
17P (17 positive outputs, mainly long-term),
16 (16 adverse outputs, 9 long-term, 3 irreversible),
Net score=1P (Marginal positive impact before
mitigation)
18P (18 positive outputs, mainly long-term),
8N (8 adverse(irreversible) outcomes
Net score=10P (Major positive impact after mitigation)
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
57
8.4.2 Mitigation of potential conflict in the use of road reserves
The Roads Act 2007 identifies the Roads Sector as bona fide custodian of road reserves in Kenya.
However, given that road reserves have traditionally also accommodated other public infrastructure,
there is need to formulated a mutually acceptable code of practice to facilitate coexistence between
roads and other infrastructure. The same will require to be sealed in law in the long run. In the interim,
all sectors targeting to use road reserve for infrastructure development should engage with relevant
road sector stakeholders (KeNHA, KeRRA, KURA) at the planning stage.
8.4.3 Management of Occupational Health and Safety Hazards
Though the scale of the proposed construction is small, it will involve climbing of poles to mount
electrical conductors and insulators which, coupled with activities associated with commissioning of
powered lines are wrought with high inherent risks of accidents. Mitigation will be undertaken as
follows:-
(i) Health and Safety requirements:
The Contractor shall do everything in his power to secure the safety of his crew, third parties and this
property. Towards this, the Contractor shall comply with all standard and legally required health and
safety regulations gazetted under the Occupational Health and Safety Act (OSHA) 2007 and the Factories
and Other Places of Work Regulations and shall submit Method Statements covering the procedures for
the main activities which could generate emergency situations through accidents or neglect of
responsibilities. These situations include, but are not limited to accidents at the work place including
wildlife invested areas, accidental fires; accidental leaks and spillages and vehicle and plant accidents.
Specific to accidents at work place:
• The Contractor shall also ensure that the necessary equipment for work in hazardous area –
protective boots, PPEs, helmets, etc are provided.
• The Contractor shall provide a standard first aid kit to field staff;
• The Contractor shall be responsible for the protection of the public and public property from
any dangers associated with construction activities, and for the safe and easy passage of
pedestrians and traffic in areas affected by the construction activities;
• All works which may pose a hazard to humans and domestic animals are to be protected,
fenced, demarcated or cordoned off as instructed by the RE. If appropriate, symbolic warning
signs must be erected;
• Speed limits appropriate to the vehicles driven are to be observed at all times on access and
haul roads. Operators and drivers are to ensure that they limit their potential to endanger
humans and animals at all times by observing strict safety precautions;
• No unauthorized firearms are permitted on site.
(ii) Fire Prevention and control:
The Contractor shall take all reasonable and precautionary steps to ensure that fires are not started as a
consequence of his activities on site. Activities are specified as follows:-
• The Contractor shall ensure that there is basic fire-fighting equipment available on site;
• Flammable materials should be stored under conditions that will limit the potential for ignition
and the spread of fires;
• Hot’ work activities shall be restricted to a site approved by the RE;
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
58
• Smoking shall not be permitted in those areas where there is a fire hazard. These areas shall
include any areas (e.g. bushlands) where vegetation or other material can make liable the rapid
spread of an initial flame.
• The Contractor shall ensure that all site personnel are aware of the fire risks and how to deal
with any fires that occur. This shall include, but not be limited to regular fire prevention talks
and drills and, posting of regular reminders to staff.
• Any fires that occur shall be reported to the RE immediately and then to the relevant
authorities;
• In the event of a fire, the Contractor shall immediately employ such plant and personnel as is at
his disposal and take all necessary action to prevent the spread of the fire and bring the fire
under control;
• Costs incurred through fire damage will be the responsibility of the Contractor, should the
Contractor’s staff be proven responsible for such a fire.
(iii) Control of Solid Waste:
All storage and construction sites are to be kept clean, neat and tidy at all times. No burying or dumping
of any waste materials, metallic waste, litter or refuse shall be permitted. The Contractor must adhere
to Environmental Management and Co-ordination (Waste Management) Regulations 2006. The
Contractor shall implement measures to minimize waste and develop a waste management plan to
include the following:-
• All personnel shall be instructed to dispose of all waste in a proper manner;
• At all places of work the contractor shall provide litter collection facilities;
• The final disposal of the site waste shall be done at the location that shall be approved by the
RE, after consultation with local administration and local leaders;
• The provision of sufficient bins (preferably vermin and weatherproof) at the camp and work
sites to store the solid waste produced on a daily basis;
• Wherever possible, materials used or generated by construction shall be recovered at the
conclusion of each task for safe disposal including recycling.
• Provision for responsible management of any hazardous waste generated during the
construction works.
(iv) General materials handling, use and storage:
All materials shall be stored within the Contractors camp unless otherwise approved by the RE;
• Stockpile areas shall be approved by the RE;
• All imported fill, soil and/or sand materials shall be free of weeds, litter and contaminants.
Sources of imported materials shall be listed and approved by the RE;
• The Contractor shall ensure that delivery drivers are informed of all procedures and restrictions
(including ‘No go’ areas) required;
• Any electrical or petrol driven pumps shall be equipped and positioned so as not to cause any
danger of ignition of the stored product;
• Collection containers (e.g. drip trays) shall be placed under all dispensing mechanisms for
hydrocarbons or hazardous liquid substances to ensure no contamination from any leaks is
reduced;
• Regular checks shall be conducted by the Contractor on the dispensing mechanisms for all above
ground storage tanks to ensure faulty equipment is identified and replaced in timely manner;
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
59
• Only empty and externally clean tanks may be stored on bare ground. All empty and externally
dirty tanks shall be sealed and stored on an area where the ground has been protected.
8.4.4: Management of Health and Safety Hazards within institutions and market centers
All construction work within school compounds will be confined to non-school days including week
ends. At all times however, the Safety Code promoted by the KPLC will always be observed by the
Contractor.
8.4.5 : Modalities for conflict resolution
In every administrative location within the traversed, the contractor will seek to enlist 2 respected
village elders who will resolve all disputed associated with the power distribution line. This is the same
team who will mobilize the community towards a final handing over meeting where all outstanding
disputes will be addressed before the Contractor hands over the project. The Final payment will only be
released upon submission of minutes from the final handover meeting showing clear attendance and
signed by the said elders’ teams.
8.5 Mitigation of Impacts at Operation Stage
Proposed mitigation activities at this stage are focused on minimizing hazards associated with presence
of electricity. Hazards of electrocution, fire outbreak etc cannot be eliminated entirely. However,
professional design and implementation of electricity supply schemes coupled with implementation of a
public sensitization campaign will greatly reduce incidence of accidents.
Towards promoting use of RETs:
Towards ensuring that supply of grid electricity does not discourage use of other RETs, solutions can
only be sought at policy level. However, adoption of a pricing mechanism that provides electricity
consumers with incentives to conserve grid power through adoption of available conservation packages
including use of RETs is one option towards sustaining the search for alternatives. Indeed, the
disincentive towards search for other energy alternatives is the main drawback associated with supply of
electricity. It is a drawback that has no readily available means for mitigation currently.
Mitigating impacts of electrocution:
Accidental electrocution is mainly mitigated through reservation and maintenance of the wayleave. REA
will undertake routine maintenance of the ROW to clear all vegetation and settlements. . All power
poles will be girdles with spiked wire to discourage climbing and will be fitted with warning (Hatari) signs
to alert all to the danger posed by presence of charged power lines.
8.6 Effectiveness of the Mitigation programme
8.6.1 Viability of Mitigation
Effectiveness of the proposed mitigation programme has been assessed based on analysis of impact
prevalence before and after mitigation (Table 8.2) based on this analysis, this Environmental and Social
Impact Assessment Study observes that, there is a great potential to mitigate adverse impacts and
hence improve the net worth of the proposed distribution lines. From Table 8.2, it is apparent that
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
60
application of mitigation measures as identified and recommended has potential to reduce tally of
adverse impacts (Ns) from 16 to 8 while simultaneously increasing the positive ones (Ps) from 17 to 18.
Thus, subtracting the Ns from the Ps gives an overall net tally of 10P implying a very positive net impact
after mitigation.
Table 8.3: Analysis of impacts scenario before and after mitigation
Nature of impact Pre-mitigation tally Post-mitigation tally
Positives 17P 18P
Negatives 16N 8N
Net 1P 10P
Residue impacts 8N
Irreversible adverse impacts 3 3
Overall, the proposed project enjoys a highly positive benefits profile as it will strongly support
initiatives towards poverty alleviation and reversal of environmental-degradation both of which are
critically important policy aspirations of the Kenya Government. This Study recommends that project
development should proceed but factor in the mitigation measures recommended herein.
Implementation of this EMP will however require close follow-up and scrutiny to ensure achievement
and substance of this esteemed net positive profile of the project. Requirements for monitoring are
explored below.
8.6.2 Prevalence of residue impacts
This study observes that 8 of the 16 adverse impacts associated with the project will persist even after
mitigation. These are the impacts whose probability can be reduced substantially through mitigation but
cannot be eliminated entirely. Their management requires implementation of a strict monitoring
programme as outlined elsewhere below.
8.6.3 Management of decommissioning
Design of power distribution lines assumes an economic life of 25-30 years for wooden poles and 40
years for distribution cables which imply that, at some point, the system will require to be
decommissioned either in whole or by components. Concerns associated with decommissioning would
include occupational health and safety hazards, accumulation of scrap metal waste, electrical
conductors, insulators and other components which apart from taking up productive space would also
pose diverse hazards (health and safety, harboring of vermin, etc) to local inhabitants and their
property. The ESMP unveiled below has explicit requirements for management of decommissioning
phase impacts.
8.7 Monitoring requirements
8.7.1 The concepts
Monitoring involves the collection and analysis of data about project activities. The data should be easy
to collect and easy to understand. The focus of monitoring is to use the knowledge gained to correct and
adjust project implementation and management in order to achieve project objectives. Monitoring
allows project participants to keep track of project activities, to determine whether project objectives
are being achieved, and to make whatever changes are necessary to improve project performance.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga
Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
61
To be successful, monitoring begins with clear project design followed by identification and elaboration
of appropriate criteria and indicators. This document provides guidance about incorporating monitoring
and evaluation elements in each stage of the project cycle.
Indicators and means of verification in M&E: Indicators form the key elements of any monitoring and
evaluation system. The advantage of identifying indicators is that it provides management and staff with
a clear set of targets at each level of performance and ensures that progress can be measured against
the targets. Indicators also make possible the comparison of inputs with the completion of outputs and
achievement of objectives and goals, thus providing the basis for performance evaluation. For purposes
of this Project Report, indicators have been formulated to facilitate monitoring of compliance in
implementing the project.
8.7.2 Procedure for M&E in project development
Table 8.3 below provides the matrix of Environmental and Social Management and Monitoring as
proposed for the development of a 33 kV distribution line. From this plan, it is clear that most mitigation
activity will take place at the construction stage having been allowed for at the design stage. This study
recommends this ESMP to be applied further as follows:-
(i) The ESMP will be integrated into the Design Report- as a standalone chapter and also to
moderate design decisions
(ii) Further, it will be integrated into the BOQs to ensure funding allocation of environmental and
social mitigation.
(iii) Ultimately, Contracts for Construction will bear clauses from the ESMP to ensure that the
contractor is legally bound to implement impact mitigation
The ESMP in table 8.2 provides a detailed framework of issues, indicators and responsibilities in
monitoring the project.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate
Constituency) 33 kV power distribution line
62
Table 8.4: Matrix for Environmental and Social Management and Monitoring (ESMP)
Project Phase Source of
Impact
Potential Impact Mitigation measures Budget
(Ksh 000)
Responsible
Cost Head
Objectively
Verifiable Indicators
Monitoring *
Authority
Design Stage Design
Studies, field
surveys and
inventories
Creation of temporary opportunities for
gainful employment
Generation of additional site-specific data
/study reports
Capacity building and sensitization
Minor accidents during survey work Deploy competent staff Exercise
already
completed
Construction
Phase
Supply of
materials
Business opportunities in supply and
transport of construction materials
Road hazards in material transportation Transporters to follow
highway code
Contract for
material
supply
Contractor Ditto REA BOM
Construction
work
Short-term opportunities for business and
employment in construction
Revenue to GoK and Local Authorities
through taxes
Damage of property (tree crops) from ROW
corridor
Just compensation for all
displaced assets
2,000 REA Negotiated
agreements with
PAPs
REA BOM
REA to support local
reforestation projects
2,000 REA No of seedlings
raised and planted
REA BOM
Occupational health and safety concerns for
construction crew
Deploy sober, competent
crew with supervision.
Provide PPEs.
Contract for
Construction
Contract for
Construction
Clause in contract for
construction
REA BOM
Solid wastes from construction activity Apply the 3 Rs concept. Contract for
construction
Contract for
Construction
Clause in contract for
construction
REA BOM
Mitigation of conflict over use of road
reserve
REA to consult road sector
stakeholders in the design and
construction of power lines in
road reserves
Internal
budget
REA Clause in the REA
code Service Charter
REA BOM
Law review to allow legally Internal REA Draft Bill or REA BOM
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate
Constituency) 33 kV power distribution line
63
Project Phase Source of
Impact
Potential Impact Mitigation measures Budget
(Ksh 000)
Responsible
Cost Head
Objectively
Verifiable Indicators
Monitoring *
Authority
coordinated multiple use of
road reserves
budget Regulations
Operation
Phase
Presence of
powered lines
Economic gains from improved and
stabilized power supply
Enhanced delivery of services in medicare,
education, admin, telecommunication, etc
Financial gains in oil to electricity
substitution, and elimination of
maintenance costs for diesel engines, etc
Employment creation, reduced cost of
investment
Cutting down on GHG emissions due to
petroleum to electricity substitution
Reduction in solid waste from lead acid
batteries, dry cells, candle residues, waste
oil/ spares from gensets etc
Adverse
impacts from
charged high
voltage power
lines
Exposure to Electromagnetic Fields (EMF) Threat not fully appreciated
but small for low voltage lines
Impact on avifauna and other wildlife from
presence of charged wires
Use of insulted conductors Contract for
supervision
Contract for
supervision
Clauses in design
report and contract
REA BOM
Hazards in attempted vandalism of
transformers
REA to mount community
sensitization campaign
1,000 REA No of sensitisation
meetings held
Disincentive on use of other Renewable
Energy Sources e.g. RETs
Outreach programme to
promote alternatives to grid
power
2,000 REA Internal
budget
Ditto REA BOM
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
64
8.7.3 Requirements for Compliance Monitoring
Compliance monitoring will be mainstreamed into the overall project monitoring system.
Compliance monitoring will be based on the ESMP (Table 8.3) and will mainly vest on three
institutions namely the REA in the capacity of Employer, ERC in the capacity of regulator in the
power sector and NEMA in the capacity of environmental regulator. The roles of all stakeholders in
facilitating achievement of project goals are enumerated in sections below. Tools will be used for
monitoring as follows:-
• Completion certificates issued by the Resident Engineer (Supervisor of Works) on behalf of
the REA
• REAs internal monitoring reports
• Monitoring reports submitted to NEMA annually
• Monitoring reports produced by the ERC in capacity of regulator in the power sector.
Overall, the responsibility for securing overall soundness and viability of the project vests with the
REA in the capacity of proponent and employer in this project.
8.8 Roles and Responsibilities in implementing the EMP
This Environmental and Social Impact Assessment identifies several crucial players in executing
impact mitigation measures for the proposed development of 33 kV distribution line. They include:-
The Design Engineer: The design stage of the project is crucial as the point when mitigation
measures are inbuilt into the project design and those with financial implications allowed for in the
BOQs. Given this consideration, the Design Engineer plays a very crucial role in incorporating findings
from the environmental assessment into the project design and ensuring compliance by contractors.
The Project Contractor(s): For purposes of this ESIA, the Project Contractor will play the crucial role
of offsetting impacts associated with construction activities including those along the material
supply chain. Employment of professionally competent contractors is therefore crucial to
achievement of the goals of this ESIA. Clauses binding the contractor to implement impact mitigation
in course of civil works will be inbuilt into the Contract for Works and subsequently supervised by
the Design Engineer.
REA: In its capacity as the Employer in the project the REA has overall responsibility of securing the
technical and economic viability of the REP in line with performance contract and national policy
aspirations. REA will also ensure that the proposed project complies with all statutory requirements.
The National Environment Management Authority-NEMA: EMCA 1999 allows for formation of the
National Environmental Management Authority NEMA as the body charged with overall
coordination of environmental protection in Kenya. To fully pursue this mandate, NEMA has gazette
Legal Notice 101 of June 2003 which among others require that Annual Audit reports be filed for any
project granted Environmental Licensing by the Authority. In line with this regulation, audit reports
in respect of this power distribution line will be filed by REA annually.
The Electricity Regulatory Commission (ERC): Among many functions, the ERC is mandated to
license and undertake technical audit of activities of all players in the Power Sector in Kenya and is
therefore a crucial stakeholder in the power sector. The Standards Act, Chapter 496 of the Laws of
Kenya empowers the ERC to enforce safety regulations and to ensure that electrical apparatus and
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
65
works meet the standards set by the Kenya Bureau of Standards or, where no such standards exist,
with the relevant international standards approved by the Kenya Bureau of Standards.
8.9 Budget for Environmental and Social Mitigation
The sum of Ksh Seven million (7,000,000) will be required to finance both social and environmental
mitigation of the project.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
66
9 CHAPTER NINE: CONCLUSION AND RECOMMENDATIONS
9.1 The Project
The subject of this Project Report is the proposed 35.3 Km long Mwachabo power distribution line
project being developed by the Rural Electrification Authority-REA on behalf of the Kenya
Government. The Report has been prepared for REA by Repcon Associates in line with the
Environmental Management and Coordination Act, 1999 and Legal Notice No. 101 of June 2003. The
report examines the project in terms of the proposed development, possible adverse impacts at
both construction and operation phases and provides an Environmental and Social Plan.
9.2 Study Methodology pursued
The systematic investigative and reporting methodology specified for conduct Project Reports by
Legal Notice 101 of EMCA was adopted in this Study. Baseline data on project design was generated
through discussion with the client and review of project documentation. Opinions formed were
revalidated through field work entailing site investigations and interviews with potentially affected
people and secondary stakeholders.
To identify, predict, analyze and evaluate potential impacts that may emanate from the project,
diverse study methods and tools including use of checklists, matrices, expert opinions and
observations were employed. An Environmental and Social Management Plan comprising an impact
mitigation plan and modalities for monitoring and evaluation were then developed to guide
environmental management during all phases of project development.
9.3 Findings from the Study
9.3.1 Overview of impacts
It must be pointed out that the scope of adverse impacts associated with construction of 35.3
kilometers of a medium voltage power distribution line in an otherwise low density agricultural
settlement is inherently low. Thus for the proposed power line, this study has identified a total of 34
impacts, 17 of which are positive. Other trends in impacts are as follows:-
• Half of the 34 impacts likely to be occasioned by the proposed construction and operation of
the 35.3 kilometres of power distribution line are negative.
• Ten of the 17 positive impacts are likely to be long-term in prevalence while 7 out of 8
adverse impacts have a long-term effect with 2 of them being potentially irreversible.
• Nine out of sixteen adverse impacts have potential to cause secondary impacts while 6 of
them have cumulative tendency i.e., they have potential to aggravate an already existing
problem.
• The project has a net neutral impact pre mitigation which will require to be enhanced
through adoption of an effective impact mitigation strategy.
9.3.2 Nature of the potential positive impacts anticipated
Positive implications of the project emanate from its potential to create short-term business and
employment opportunities to both professional staff and workers during the design phase while, at
construction phase, traders will benefit from opportunities to supply construction material while
locals will be employed in works. Upon commissioning, the project could supply electric power to
one dispensary, several schools and 5 rural trading centers where the potential to unlock business
potential is real. Through adoption of electric power and cutting down on use of fossil fuels, the
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
67
project has potential to favor cutting down on Green House Gas emissions to the benefit of the
global climate.
9.3.3 Nature of the Potential adverse impacts/concerns
Core adverse impacts could include the following:-
Displacement of trees and property: The proposed route of traverse is a semi arid rangeland
dominated by low growing acacia woodland formation whose height is well below the standard
height of power distribution lines in which case potential damage is likely to be minimal.
Hazards to road users: Construction activity including transport of materials to the site and actual
building of the power distribution line poses occupational health and safety hazards to both
construction crew and third parties.
Conflict over use of road reserves: Unless properly coordinated, construction of power lines has
recently been observed to occasion conflicts over the use of road reserves and the same can recur in
regard of proposed power line.
Hazards posed by powered lines: Further, presence of the line changes the local landscaper and
skyline and such intrusion into space is a kind of pollution, not mentioning the perpetual hazards
introduced by presence of a powered line.
9.4 The Environmental and Social Management and Monitoring Plan
An Environmental and Social Management and Monitoring Plan (ESMP) comprising both an Impact
Mitigation Plan (IMP) and Monitoring Plan (MP) has been developed for the project.
9.4.1 The Impact Mitigation Plan:
The bulk of impacts including nuisances, occupational health and safety issues, social impacts of
construction crew etc are associated with construction activity and will thus cease once construction
ends. Requisite intervention has been identified as follows:-
Mitigation of impacts of tree removal: All proposed tree removal will have to be coordinated with
County Agricultural Officers in Line with the Agriculture (Farm Forestry) Rules 2009. Further, REA will
pay just and prompt compensation for all trees removed or lopped. Further, towards rebuilding lost
vegetation cover, REA will identify and support a local group to raise and plant tree seedlings in the
route of traverse. REA will follow and monitor progress of said trees to ensure achievement of
highest survival possible.
Mitigation of Health and safety impact: The Contractor will be bound in contract to implement the
Code of Safety as outlined in 8.4 above. The core mitigation strategy is to optimize on construction
time so as to reduce the time taken to complete all civil works. The Contractor will deploy sober
competent staff working under competent supervisors. In addition to provision of protective gear, all
workers will be covered under the Workman Compensation Scheme.
Mitigation of potential for conflict in use of the road reserves: At the design stage, REA will engage
all road sector stakeholders to agree on mutually acceptable sharing of the target road reserves but
in the long run, this matter will require legal resolution.
Mitigation of hazards associated with presence of a powered line: Towards curbing vandalism of
the power distribution line and associated hazards, the REA will mount public sensitization
campaigns in the affected area and will ensure that the property is promptly handed over to the
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
68
community. As well, the contractor should be held liable for all vandalism during the defect liability
period.
9.4.2 Effectiveness of the Mitigation Plan
Based on analysis of impact prevalence before and after mitigation it is evident that, application of
mitigation measures as identified and recommended has potential to totally eliminate most impacts
and greatly tone down others. However, 8 of the eighteen adverse impacts associated with the
project will persist even after mitigation. These are the impacts whose probability can be reduced
substantially through mitigation but cannot be eliminated entirely. Their management requires
implementation of a strict monitoring programme which has already been outlined within this
report.
9.4.3 Total Cost in Environmental and Social Mitigation
A total Ksh 7 million will be required to offset the social and environmental impacts associated with
the project.
9.5 The Monitoring Strategy
The Mitigation strategy proposed is largely focused on ensuring that mitigation action will be
implemented. Requirements for this are as follows:-
i) The responsibility for ensuring total environmental worth of the proposed project vests with
REA in the capacity of proponent. Towards this, the proponent will retain and deploy the
team of highly motivated environmental and social scientists to monitor and report on all
stages of the project.
ii) The ESMP as outlined above be integrated into the Design Report with appropriate
allocation of funds in the Bills of Quantities.
iii) The Contractor will prepare routine reports which will be ascertained by the Supervising
Consulting Engineer before Payment Certificate can be issued.
iv) The contract for construction should bear clauses binding the contractor to implement
impact mitigation as part of the civil works. Environmental stabilization works will be
covered under the defect liability period.
v) REA will mount own internal monitoring to ensure that impact mitigation has been
implemented and will file annual audit reports with NEMA.
vi) The proposed project will adhere to all other laws of the land and will seek and obtain all
requisite statutory permits.
9.6 Recommendations of this Project Report
The proposed development of a power distribution project is largely aligned to reigning GOK Policies
for national development. The project enjoys a highly positive benefits profile as it will strongly
support initiatives towards poverty alleviation and reversal of environmental-degradation both of
which are critically important policy aspirations of the Kenya Government. This Study recommends
that project development should proceed but factor in the mitigation measures recommended
herein. REA in the capacity of proponent will require to closely monitor activities especially at
construction stage and simultaneously avail funds for environmental and social restoration.
Our recommendation is for the project to be licensed to proceed to the next level of development.
REFERENCES
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
69
1. Foliart D. E., Pollock B. H, G. Mezei, R Iriye, J M Silva, K L Ebi, L Kheifets, M P Link, and R Kavet,
2006:
Magnetic field exposure and long-term survival among children with leukemia. British
Journal of Cancer 16; 94(1): 161-164. Cancer Research UK. 2006
2. ERB (2005): Environmental, Health & Safety Policy Framework for the electric power sub-sector.
ERB Head Office, Nairobi.
3. OGALLO, L. (1979), Rainfall variability in Africa. Monthly Weather Revision, 107: pp. 1133-1139.
4. Republic of Kenya, Ministry of Energy, 2000: Study on Energy, Demand, Supply and Policy
Strategy for Households, Small Scale Industries and Services Establishments in Kenya. Ministry
of Energy, Nairobi.
5. UNEP & WMO, (1991): Greenhouse Gas Inventory Reporting Instructions Final Draft. IPCC Draft
Guidelines for National Greenhouse Gases Inventories Vol I. IPCC & OECD joint programme.
6. UNEP & WMO, 1991): Greenhouse Gas Inventory Reporting Instructions Final Draft. IPCC Draft
Guidelines for National Greenhouse Gases Inventories Vol I. IPCC & OECD joint programme.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
70
APPENDICES:
Appendix 1.1: Statutory registration for Repcon Associates
Appendix 1.2: NEMA registration for Study Team
Appendix 1.3: List of documents and data sources consulted
Appendix 2.1: Bills of Quantities for the power distribution line
Appendix 5.1: Nairobi based consultations
Appendix 5.2: Project specific consultations in Taita Taveta County
Appendix 7.1: Third Schedule to Legal Notice 101
Appendix 7.2: Leopold Matrix
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
71
Appendix 1.1: Statutory registration for Repcon Associates
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
72
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
73
Appendix 1.2: NEMA registration for Study Team
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
74
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
75
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
76
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
77
Appendix 1.3: List of documents and data sources consulted
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
78
REFERENCES
1. Foliart D. E., Pollock B. H, G. Mezei, R Iriye, J M Silva, K L Ebi, L Kheifets, M P Link, and R Kavet, 2006
:
Magnetic field exposure and long-term survival among children with leukemia. British Journal of Cancer
16; 94(1): 161-164. Cancer Research UK. 2006
2. ERB (2005): Environmental, Health & Safety Policy Framework for the electric power sub-sector. ERB Head
Office, Nairobi.
3. OGALLO, L. (1979), Rainfall variability in Africa. Monthly Weather Revision, 107: pp. 1133-1139.
4. Republic of Kenya, Ministry of Energy, 2000: Study on Energy, Demand, Supply and Policy Strategy for
Households, Small Scale Industries and Services Establishments in Kenya. Ministry of Energy, Nairobi.
5. UNEP & WMO, (1991): Greenhouse Gas Inventory Reporting Instructions Final Draft. IPCC Draft Guidelines
for National Greenhouse Gases Inventories Vol I. IPCC & OECD joint programme.
6. UNEP & WMO, 1991): Greenhouse Gas Inventory Reporting Instructions Final Draft. IPCC Draft Guidelines
for National Greenhouse Gases Inventories Vol I. IPCC & OECD joint programme.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
79
Appendix 2.1: Bills of Quantities for the power distribution line
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
80
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
81
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
82
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
83
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
84
Appendix 5.1 Nairobi based consultations
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
85
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
86
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
87
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
88
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
89
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
90
Appendix 5.2: Project specific consultations in Taita Taveta County
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
91
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
92
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
93
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
94
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
95
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
96
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
97
Appendix 7.1: Third Schedule to Legal Notice 101
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
98
THIRD SCHEDULE
GENERAL GUIDELINES FOR CARRYING OUT AN ENVIRONMENTAL
IMPACT ASSESSMENT STUDY
An environmental impact assessment study shall be conducted in accordance with the general
environmental impact assessment guidelines and administrative procedures issued by the
Authority. An environmental impact assessment study shall include the following:
1. Sources of Impact
2. Project Inputs
3. Project Activities
4. Areas of Impact on the Natural and Human Environments
5. Environmental Impacts (General Impacts on the Natural and human Environment)
6. Environmental Guidelines and Standards (National Legislation, International
guidelines. International Conventions and Treaties)
7. Mitigation Measures
8. Environmental Management Plan
9. Environmental Monitoring and Auditing.
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
99
Appendix 7.2: Leopold Matrix
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
100
Summary Matrix of Environmental Impact Assessment for proposed the Mwachabo Market
and Pry/Manoa Disp/ Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate
Constituency) 33kV power distribution line
POTENTIAL IMPACTS OF PROJECT DECISION
1. Agricultural Lands
a) Are there cultivable lands in the area? Yes No Unk
b) Will project decision result in more or improved cultivable land? Yes No Unk
c) Will project decision result in less or damage cultivable land? Yes No Unk
ESTIMATE IMPACT ON AGRICULTURAL LAND:
ND HA MA LA LA O LB HB
2. Soil Erosion
a) Will project decision help to prevent soil loss or erosion Yes No Unk
b) Will project decision directly cause or worsen soil loss or
erosion?
Yes No Unk
c) Could project decision indirectly lead to practices that could
cause soil loss or erosion? Yes No Unk
d) Is it necessary to consult a soils scientist Yes No Unk
ESTIMATED IMPACT ON SOIL EROSION:
ND HA MA LA LA O LB HB
3. Slope Stability
a) Does project decision involve actual modification of slopes Yes No Unk
b) Will project decision affect stability of slopes indirectly Yes No Unk
c) Will project decision result in slope stability? Yes No Unk
d) Could project decision cause people livestock or property to be
located where existing unstable slopes could be a hazard?
Yes No Unk
e) Is it necessary to consult a geo-technical engineer? Yes No Unk
ESTIMATED IMPACT ON SLOPE STABILITY:
ND HA MA LA LA O LB HB
4. Energy - Mineral Resources
a) Do energy - mineral resources exist in project area? Yes No Unk
b) Will project decision help to develop, now or in the future,
important energy-mineral resources?
Yes No Unk
c) Will project decision cause significant consumption of additional Yes No Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
101
energy -mineral resources such as engine fuels?
d) Could project decision prevent or impede future development of
essential energy-mineral resources?
Yes No Unk
e) Is it necessary to consult with a minerals agency or mining
engineer?
Yes No Unk
ESTIMATED IMPACT ON ENERGY/ MINERAL RESOURCES:
ND HA MA LA LA O LB HB
5. Surface Water Quantity
a) Do surface water resources exist in project area? Yes No Unk
b) Is information available on present and future demands on water
resources as result of the project?
Yes No Unk
c) Will project decision help to increase or preserve available
surface water supplies by such things as improved drainage / run-
off conditions?
Yes No Unk
d) Will project decision increase demand or cause loss of available
surface water directly or indirectly?
Yes No Unk
e) Is it necessary to consult a hydrologist? Yes No Unk
ESTIMATED IMPACT ON SURFACE WATER QUANTITY:
ND HA MA LA LA O LB HB
6. Surface Water Quality
a) Is information available on present water quality? Yes No Unk
b) Will project decision lead to additional natural or man made
discharges into surface waters?
Yes No Unk
c) Will project decision help to improve or protect surface water
quality?
Yes No Unk
d) Could project decision cause deterioration of surface water
quality either directly or indirectly?
Yes No Unk
e) Is it necessary to consult a water quality engineer or agency? Yes No Unk
ESTIMATED IMPACT ON SURFACE WATER QUALITY:
ND HA MA LA LA O LB HB
7. Ground Water Quantity
a) Do ground water resources exist in project area? Yes No Unk
b) Is information available on present and future demands on water
resources as result of the project?
Yes No Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
102
c) Will project decision help to increase or preserve available ground
water supplies by such things as improving recharge conditions?
Yes No Unk
d) Will project decision increase demand or cause loss of available
ground water either directly or indirectly?
Yes No Unk
e) Is it necessary to consult a hydrogeologis? Yes No Unk
ESTIMATED IMPACT ON GROUNDWATER QUALITY:
ND HA MA LA LA O LB HB
8. Ground Water Quality
a) Is information available on present water quality? Yes No Unk
b) Will project decision cause any natural or man made discharges
into ground aquifers?
Yes No Unk
c) Could project decision cause deterioration of ground water quality? Yes No Unk
d) Could project decision cause deterioration of ground water quality
either directly or indirectly?
Yes No Unk
e) Is it necessary to consult a ground water quality specialist? Yes No Unk
ESTIMATED IMPACT ON GROUND WATER QUALITY.
ND HA MA LA LA O LB HB
9. Air Quality
a) Is information available on existing air quality? Yes No Unk
b) Will project decision produce any air emission directly? Yes No Unk
c) Will project decision help to reduce existing air pollution sources
such as open burning operations?
Yes No Unk
d) Could project decision lead to practices that worsen air quality such
as causing increased road traffic or industrialization?
Yes No Unk
e) Could project decision lead to a change in engine use or fuel
combination that could cause serious air problems?
Yes No Unk
ESTIMATED IMPACT ON AIR QUALITY:
ND HA MA LA LA O LB HB
10. Noise
a) Is noise now a problem in project area? Yes No Unk
b) Will project help in reducing undesirable noise conditions? Yes No Unk
c) Will project cause temporary or sustained increases in noise
generation conditions such as heavy machinery or road travel?
Yes No Unk
d) Could project cause movements of people to high noise level Yes No Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
103
locations?
e) Is it necessary to consult a noise specialist? Yes No Unk
ESTIMATED IMPACT ON AIR QUALITY:
ND HA MA LA LA O LB HB
11. Aquatic Ecosystems
a) Are there any aquatic ecosystems of which the types listed below
which, by nature of their size, abundance or type, can be considered
significant or unique?
River?
Streams?
Lakes?
Ponds?
Yes No Unk
b) Are these systems essentially:
Pristine?
Moderately degraded?
Severely degrade?
Ponds?
Yes
Yes
Yes
No
No
No
Unk
Unk
Unk
c) Are these systems used by the local people:
i) Consumptively
For drinking water?
For Irrigation?
For livestock?
ii) Non-consumptively
For washing and bathing?
For waste Disposal?
For Transportation?
For Harvest of non-domesticated
plants or animals as food, fiber
animals as food, fiber fur or other
useful products?
Yes
Yes
Yes
No
No
No
Unk
Unk
Unk
d) Will the project directly affect consumption use of water? Yes No Unk
e) Will the project directly or indirectly affect either non-consumptive
or consumptive uses of these ecosystems by:
Use or production of toxic material (both during
construction and / operation) which might enter these
systems?
Alteration of drainage?
Increasing erosion?
Causing increase in populations so as to place added stress
on their systems?
Yes
Yes
Yes
Yes
No
No
No
No
Unk
Unk
Unk
Unk
ESTIMATED IMPACT ON AQUATIC ECOSYSTEMS:
ND HA MA LA LA O LB HB
12. Wetland Ecosystems
b) Are these systems
Pristine?
Yes
No
Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
104
Moderately degraded?
Severely degraded?
Yes
Yes
No
No
Unk
Unk
c) Are these systems used by local people For:
Drinking water?
Livestock Water?
Washing and Bathing?
Waste Disposal?
Agriculture?
Harvest on non-domesticate plants or animals as food, fur, or
fiber?
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
Unk
Unk
Unk
Unk
Unk
Unk
e) Will the project either directly or indirectly affect wetlands by:
Changing population or land use practices so as to
increase Drainage of wetlands for use as agricultural, industrial
or urban land?
Use or production (either during construction and /
operation of toxic materials which might enter wetlands?
Use the water directly?
Alter drainage patterns so as to affect wetlands?
Increase erosion so as to affect wetlands?
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
Unk
Unk
Unk
Unk
Unk
ESTIMATED IMPACT ON WET LAND ECOSYSTEMS:
ND HA MA LA LA O LB HB
13. Terrestrial Ecosystems
a) Are there any aquatic ecosystems of which the types listed below
which, by nature of their size, abundance or type, can be
considered significant or unique?
Forest?
Savanna?
Grassland?
Desert?
Yes
Yes
Yes
Yes
No
No
No
No
Unk
Unk
Unk
Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
105
b) Are these ecosystem:
Pristine?
Moderately degraded?
Severely Degraded?
Yes
Yes
Yes
No
No
No
Unk
Unk
Unk
c) Are these present trends towards alteration of these ecosystems
through cutting, burning, etc. to produce agricultural, industrial, or
urban land?
Yes
No
Unk
d) Does the local population use these ecosystems to obtain non-
domesticated:
Food plants?
Medicinal Plants
Wood Products?
Fiber?
Fur?
Food Animals?
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
Unk
unk
Unk
Unk
Unk
Unk
e) Will the project require clearing or alteration of:
Small areas of land in these ecosystems?
Moderate areas of land in these ecosystems?
Large areas of land in these ecosystems?
Yes
Yes
Yes
No
No
No
Unk
Unk
Unk
f) Does the project rely on any raw materials (wood, fiber) from
these Ecosystems?
Yes
No
Unk
g) Will the project decrease use of products from these
ecosystems by producing or providing substitute
materials?
Yes
No
Unk
h) Will the project cause increased population growth in
the area, bringing about increased stress on these
ecosystem?
Yes
No
Unk
ESTIMATE IMPACT ON TERRESTRIAL ECOSYSTEMS:
ND HA MA LA LA O LB HB
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
106
14. Endangered species
a) Is the existence of endangered species in the project
area:
Very unlikely
Probable
Highly probable
Documented fact
Yes
Yes
Yes
Yes
No
No
No
No
Unk
Unk
Unk
Unk
b) Are these species:
Of scientific interest only?
Of scientific interest and highly sought after by
local people for food, hides, sale to animal
dealers.
Yes
No
Unk
c) Will the project affect the habitat of these animals:
Directly by destruction of habitat?
Indirectly by altering habitat through changing
drainage, land use?
Yes
Yes
No
No
Unk
Unk
d) Will the project increase ease of access to these
habitats?
Yes No Unk
e) Will the project increase population in the project are,
thus placing increased pressure on these species and /
or on their habitat?
Yes No Unk
ESTIMATED IMPACT ON ENDANGERED SPECIES
ND HA MA LA O LB HB
15. Migratory Species
a) In the project area are there any:
Migratory fish
Migratory birds
Yes
Yes
No
No
Unk
Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
107
Migratory animals Yes No Unk
b) Are these species used by local people for food, fur, or
other products?
Yes
No.
Unk
c) Will the project require any dams, roads, pipelines or
other alignments which could interfere with these
migratory animals?
Yes
No
Unk
d) Will the project destroy any habitat (resting, feeding
reproductive) which are critical to these species?
Yes
No
Unk
e) Will increased population place additional stress on
these species?
Yes
No
Unk
ESTIMATED IMPACT ON MIGRATORY SPECIES
ND HA MA LA O LB HB
16. Beneficial Plants
a) Do non domesticated plants occur in the project area
which are used or sold by local peoples as:
Food?
Fiber?
Ornament?
Forage?
Building Materials
Yes
Yes
Yes
Yes
No
No
No
No
No
Unk
Unk
Unk
Unk
Unk
b) Do these plants occur in :
Undisturbed habitat?
Moderately disturbed habitat?
Severely disturbed habitat?
Yes
Yes
Yes
No
No
No
Unk
Unk
Unk
c) Are these plants:
Utilized heavily?
Utilized moderately?
Yes
Yes
No
No
Unk
Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
108
Utilized only occasionally? Yes No Unk
d) Is this use:
Peculiar to the local population?
Universal in the region / country?
Yes
Yes
No
No
Unk
Unk
e) Will the project:
Decrease habitat for these plants?
Increase access to these plants?
Provide substitute products or the necessary money
to replace the use of these plants through increased
population?
Yes
Yes
Yes
No
No
No
Unk
Unk
Unk
ESTIMATED IMPACT ON BENEFICIAL PLANTS
ND HA MA LA LA O LB HB
17. Beneficial Animals
a) Do non domesticated animals occur in the project area
which are used or sold by local people as:
Souvenir products?
Food?
Fur?
Pets?
Yes
Yes
Yes
Yes
No
No
No
No
Unk
Unk
Unk
Unk
b) Do these animals occur in:
Undisturbed habitats?
Moderately disturbed habitat?
Severely disturbed habitat?
Yes
Yes
Yes
No
No
No
Unk
Unk
Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
109
c) Are these animals:
Utilized heavily?
Utilized moderately?
Utilized only occasionally?
Yes
Yes
Yes
No
No
No
Unk
Unk
Unk
d) Is this use:
Peculiar to the local population?
Universal in the region/county?
Yes
Yes
No
No
Unk
Unk
e) Will the project:
Decrease habitat for these animals?
Increase habitat for these animals?
Increase access to these animals?
Provide substitute products or the necessary
money to replace the use of these animals?
Increase use of these animals through increased
population?
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
Unk
Unk
Unk
Unk
Unk
ESTIMATED IMPACT ON BENEFICIAL ANIMALS:
ND HA MA LA LA O LB HB
18. Pest Plants
a) Are there currently any pest plant problems in the
project area?
Yes
No
Unk
b) Are there any potential pest plant species known to
exist in the project area?
Yes
No
Unk
c) Are these pest plants associated with:
Severely disturbed land?
Agricultural land?
Stagnant or polluted water?
Yes
Yes
Yes
No
No
No
Unk
Unk
Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
110
d) Will the project:
Increased habitat for pest plants?
Decreased habitat for pest plants?
Provide opportunity for control of pest plants?
Increase the possibility of introduction of pest
plants through increased commerce?
Yes
Yes
Yes
Yes
No
No
No
No
Unk
Unk
Unk
Unk
ESTIMATED IMPACT ON PEST PLANTS:
ND HA MA LA O LB HB
19. Pest Animals
a) Are there currently any problems with pest animals in
the project area?
Yes
No
Unk
b) Are there any animals in the project area which, under
altered ecological conditions, have the potential for
becoming pest species
Yes
No
Unk
c) Are these species associated with:
Severely disturbed land?
Agricultural land?
Aquatic Habitats?
Yes
Yes
Yes
No
No
No
Unk
Unk
Unk
d) Will the project:
Increased habitat for pest animals?
Decreased habitat for pest animals?
Provide opportunity for control of pest animals?
Increase the possibility of introduction of pest
animals through increased commerce?
Provide the opportunity for control of pest
animals?
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
Unk
Unk
Unk
Unk
Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
111
ESTIMATED IMPACT ON PEST ANIMALS:
ND HA MA LA O LB HB
20. Disease Vectors
a) Are the known disease problems in the project area
transmitted through vector species such as mosquitoes,
flies, snails, etc?
Yes
No
Unk
b) Are these vector species associated with :
Aquatic habitats?
Forest habitats?
Agricultural habitats?
Degraded habitats?
Human settlements?
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
Unk
Unk
Unk
Unk
Unk
c) Will the project:
Increase vector habitat?
Decrease vector habitat?
Vector control?
Yes
Yes
Yes
No
No
No
Unk
Unk
Unk
d) Will the project work force be possible source of
introduction of disease vectors not currently found in
the project areas?
Yes
No
Unk
e) Will increased access to any commerce with the
project area be a possible source of disease vectors
not presently occurring in the project area?
Yes
No
Unk
f) Will the project provide opportunities for vector
control through improved standards of living?
Yes
No
Unk
ESTIMATED IMPACT ON DISEASE VECTORS:
ND HA MA LA LA O LB HB
21: Disease Vectors
a) Are vector-borne diseases an important part of the
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
112
local public health situation? Yes No Unk
b) Are these clinics or other disease control programs in
operation or planned for the area?
Yes
No
Unk
c) Will the project decision result in an increase in
disease vector density or distribution?
Yes
No
Unk
d) Will the project decision result in workers of other
persons entering the area with contagious or vector
borne diseases?
Yes
No
Unk
e) Will the project decision result in clearing operations
that could expose workers to disease vectors?
Yes
No
Unk
g) Will the project decision increase the hazard of
accident to the local population to receive health
care?
Yes
No
Unk
h) Is it necessary to consult with a public health
specialist?
Yes
No
Unk
ESTIMATED IMPACT ON PUBLIC HEALTH:
ND HA MA LA O LB MB HB
22. Resource/Land-use
a) Are the natural resources of the area under intensive
use pressure?
Yes
No
Unk
b) Are lands in the project area intensively developed? Yes No Unk
c) Will the project decision increase pressure on land
resources?
Yes
No
Unk
d) Will the project decision result in workers or other
persons entering the area with contagious or vector
borne disease?
Yes
No
Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
113
e) Will the project decision result in clearing operations
that could expose workers to disease vectors?
Yes
No
Unk
f) Will the project decision increase the hazard of
accident to the local population?
Yes
No
Unk
g) Will the project decision improve opportunities for
the local population to receive health care?
Yes No Unk
h) Is it necessary to consult with a public health
specialist?
Yes No Unk
ESTIMATED IMPACT ON PUBLIC HEALTH
ND HA MA LA LA O LB HB
Conventional / Non-conventional Energy sources
a) Will the project increase the demand for conventional
energy sources (petroleum, hydropower)?
Yes
No
Unk
b) Will the project increase the demand for
nonconventional energy sources (fuelwood, dung,
agricultural wastes)?
Yes
No
Unk
c) Should an energy planner be consulted? Yes No Unk
ESTIMATED IMPACT ON ENERGY SOURCES:
ND HA MA LA O LB HB
23. Distribution Systems
a) Are the production / distribution networks for agricultural
and manufactured commodities fully understood?
Yes
No
Unk
b) Will the project decision enhance the equitable
distribution of these products?
Yes
No
Unk
c) Will the project decision increase the demand for certain
commodities within or outside the area?
Yes
No
Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
114
d) Will the project decision decrease the demand for
certain locally produced goods?
Yes
No
Unk
e) Will the project decision improve the ease with which
consumers in the area obtain commodities?
Yes
No
Unk
f) Will the project decision improve the ease with which
consumers in the area obtain commodities?
Yes
No
Unk
f) Is it necessary to consult a social anthropologist? Yes No Unk
ESTIMATED IMPACT ON DISTRIBUTION SYSTEMS
ND HA MA LA O LB HB
25. Employment
a) Is there potential work force in the area fully employed? Yes No Unk
b) Will the project decision substantially increase the rate
of employment?
Yes
No
Unk
c) Will the project decision remove job opportunities in the
area?
Yes
No
Unk
d) Will the project decision result in drawing workers from
other local employers?
Yes
No
Unk
e) Is it necessary to consult with a socioeconomist? Yes No Unk
ESTIMATED IMPACT ON EMPLOYMENT
ND HA MA LA LA O LB HB
26. At-Risk Population
a) Are the adverse impacts of the project unequally
distributed in the target population?
Yes
No
Unk
b) Have the at-risk groups been identified? Yes No Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
115
c) Have all possible actions been identified that would
lessen the impact on at-risk groups?
Yes
No
Unk
d) Is the assistance of a social anthropologist required to
adequately answer these questions?
Yes No Unk
ESTIMATED IMPACT ON AT-RISK POPULATION
ND HA MA LA LA O LB HB
27. Migrant population
a) Are there presently certain mobile groups in the target
population?
Yes
No
Unk
b) Will the project decision result in immigration of people
to the area?
Yes
No
Unk
c) Are local institutions and agencies adequately geared to
handle this influx?
Yes
No
Unk
d) Will the project decision result in the movement of
people out of the area?
Yes
No
Unk
e) Can their probable destinations be predicted? Yes No Unk
f) Are local institutions and agencies or receiving agencies
able to handle these migrant groups?
Yes
No
Unk
g) Is it necessary to consult a social anthropologist? Yes No Unk
ESTIMATE IMPACT ON MIGRANT POPULATION
ND HA MA LA O LB HB
28. Community Stability
a) Are the interrelationships of various social groups in the
project area understood?
Yes
No
Unk
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
116
b) Will the project decision establish institutions that will
improve these interrelationships?
Yes
No
Unk
c) Will the project decision establish create competition
among social groups that would reduce community
cohesion?
Yes No Unk
d) Is it necessary to consult a social anthropologist? Yes No Unk
ESTIMATED IMPACT ON COMMUNITY STABILITY
ND HA MA LA O LB HB
29. Cultural and Religious Values
a) Have studies been conducted of the cultural values of
the project area?
Yes
No
Unk
b) Are the cultural characteristics unique to the project area
adequately known?
Yes
No
Unk
c) Will the project decision adversely affect the religious
attitudes of area residents?
Yes
No
Unk
d) Are there special superstitions or religious taboos that
will affect the acceptance of the project by the target
population?
Yes
No
Unk
e) Is it necessary to consult a social anthropologist? Yes No Unk
ESTIMATED IMPACT ON CULTURAL AND RELIGIOUS VALUES
ND HA MA LA O LB MB HB
30. Tourism and Recreation
a) Is there at present a significant degrees of tourism in the
area?
Yes
No
Unk
b) Is there un-exploited tourism or recreation potential in the
area?
Yes
No
Unk
c) Will the project decision result in more effective
The Rural Electrification Authority: Project Report for the proposed Mwachabo Market & Pry/Manoa Disp/
Chunga Unga, Dighai, Kamtonga and Mkuki Markets (Mwatate Constituency) 33 kV power distribution line
117
utilization of present or future tourism opportunities? Yes No Unk
d) If so, will this adversely affect an existing or potential
tourist or recreation attraction?
Yes
No
Unk
e) Will the project decision adversely affect an existing or
potential tourist or recreation attraction?
Yes
No
Unk
ESTIMATED IMPACT ON TOURISM AND RECREATION
ND HA MA LA O LB MB HB
31. Nutrition
a) Have adequate data been gathered on the nutritional
levels in the project area?
Yes
No
Unk
b) Do these data differentiate among various population
sub-groups, by age, sex or social level?
Yes
No
Unk
C) Will the project decision result in changed food habits
in the target population?
Yes
No
Unk
d) Will these changes result in improved nutritional
characteristics?
Yes
No
Unk
e) Are the services of a nutrition specialist required? Yes No Unk
ESTIMATED IMPACT ON NUTRITION
ND HA MA LA O LB MB HB