Project Profile By the Numbers - Amazon Web Services€¦ · Project Profile What You Should Expect...

1
Project Profile What You Should Expect By the Numbers The Metropolitan Water District of Southern California is making key improvements to the Orange County Feeder, a major pipeline in the regional water system that delivers water to six member agencies in Los Angeles and Orange Counes. The lining that protects the pipe is nearing the end of its service life and requires replacement. Rehabilitaon of this pipeline is required to ensure reliable water supply. For More Informaon Contact: Sal Vazquez (213) 217-6752 | [email protected] Follow us on Social Media @mwdh2o Receive text alerts by texng BRISTOL to 90407 THE METROPOLITAN WATER DISTRICT OF SOUTHERN CALIFORNIA The OC Feeder began operaon in 1941 and is constructed of welded steel Work is occurring at 13 locaons down Bristol St. in Santa Ana & Costa Mesa This feeder delivers nearly 18 million gallons of water per day on average Each locaon will take approximately 10 weeks to complete www.mwdh2o.com Work in Costa Mesa will occur from late July - early September The Northbound #3 lane from Town Center Dr. to Sunflower Ave. will be closed Motorists will be able to make right turns onto both Town Center Dr. & Sunflower Ave. Water supply will not be affected

Transcript of Project Profile By the Numbers - Amazon Web Services€¦ · Project Profile What You Should Expect...

Page 1: Project Profile By the Numbers - Amazon Web Services€¦ · Project Profile What You Should Expect By the Numbers The Metropolitan Water District of Southern California is making

Project Profile

What You Should Expect

By the NumbersThe Metropolitan Water District of Southern California is making key improvements to the Orange County Feeder, a major pipeline in the regional water system that delivers water to six member agencies in Los Angeles and Orange Counties. The lining that protects the pipe is nearing the end of its service life and requires replacement. Rehabilitation of this pipeline is required to ensure reliable water supply.

For More InformationContact: Sal Vazquez

(213) 217-6752 | [email protected]

Follow us on Social Media @mwdh2oReceive text alerts by texting BRISTOL to 90407

THE METROPOLITAN WATER DISTRICT OF SOUTHERN CALIFORNIA

The OC Feeder began operation in 1941 and is constructed of welded steel

Work is occurring at 13 locations down Bristol St. in Santa Ana & Costa Mesa

This feeder delivers nearly 18 million gallons of water per day on average

Each location will take approximately 10 weeks to complete

www.mwdh2o.com

• Work in Costa Mesa will occur from late July - early September• The Northbound #3 lane from Town Center Dr. to Sunflower Ave. will be

closed• Motorists will be able to make right turns onto both Town Center Dr. &