Project Ppt
-
Upload
channadbit -
Category
Documents
-
view
124 -
download
1
Transcript of Project Ppt
MONITORING AND CONTROLING OF SUBSTATION USING SCADA
MONITORING AND CONTROLING OF SUBSTATION USING SCADA
INTERNAL GUIDEMr.RavindraDBIT,Banglore-74
EXTERNAL GUIDEMr.Varaprasad Rao.ANAL,Banglore-17
Presentation By:Santosh.K (1DB09EE404)
Sanketh.M.S (1DB08EE034)Siddalingesh.G.A (1DB09EE406)
Channabasavaiah.M.S (1DB09EE400)
INTRODUCTON:
Early electrical substations required manual switching or adjustment of equipment, and manual collection of data for load, energy consumption, and abnormal events. As the complexity of distribution networks grew, it became economically high.
To overcome the above difficulties we using supervisory control and data acquisition (SCADA) for automatic monitoring and controlling of substation.
SCADA usually refers to centralized system which monitor and control entire substation. Control actions are performed automatically by PLC(programmable logic controller). While the SCADA system monitors overall performance. Using SCADA in substation detection of fault is fast, accurate in operation, compactness, simplicity in circuit.
A:Primary power lines' side B:Secondary power lines' side
1.Primary power lines 2.Ground wire 3.Overhead lines 4.Transformer for measurement of electric voltage 5.Disconnect switch 6.Circuit breaker 7.Current transformer 8.Lightning arrester 9.Main transformer 10.Control building 11.Security fence 12.Secondary power lines
SCHEMATIC DIAGRAM OF ELECTRICAL DISTRIBUTION SUBSTATION
BLOCK DIAGRAM
SCADA
MODBUS serial link
CONVERTER CONVERTER PLC
Control devices Data storage
ETHERNET
Advantages of PLCs
• Less wiring.• Wiring between devices and relay contacts are done in the PLC
program.• Easier and faster to make changes.• Trouble shooting aids make programming easier and reduce
downtime.• Reliable components make these likely to operate for years
before failure.
•- Developed to replace relays in the late 1960s
•- Costs dropped and became popular by 1980s
•- Now used in many industrial designs
PLC Origin
7
Major Components of a Common PLC
PROCESSOR
POWERSUPPLY
I MN O P D U UT L E
O M U OT DP UU LT E
PROGRAMMING DEVICE
From SENSORS
Pushbuttons,contacts,
limit switches,etc.
ToOUTPUT
Solenoids, contactors,
alarmsetc.
8
PLC
INPUTS
OUTPUTS
MOTOR
LAMPCONTACTOR
PUSHBUTTONS
CONTROL CIRCUIT FOR CONTACTOR
10
N.O
C
L2 L1
L1 L2
OUTPUT MODULEWIRING
MOTOR
CONTACTOR
O:4
0CONTACTOR
LADDER PROGRAM
L1 L2
FIELD WIRING
•SOLENOID•VALVES•LAMP•BUZZER
APPLICATIONS: •Circuit breakers and Isolators •Transformer cooling•Multiple fault detection•Switching operation•Measurement and data storage
ADVANTAGES•System is more efficient and reliable•Higher accuracy can be achieved•It reduces time delay•Monitoring and storage of data•Replacing human operators in tasks thatinvolve hard physical or dangerous work
Microprocessor based multi-functional numerical relays provide reliable solution to complex protection functions with increased Mean Time Between Failure (MTBF). These relays play a significant role in automation, protection and control of transmission equipment in substation. Numerical relays have limited control applications. Therefore, in order to operate these relays remotely, a SCADA system using MODBUS communication has been designed and developed. Numerous numbers of relays have been installed at a fully loaded substation. Different performance parameters are evaluated and circuit breaker operations have been Monitored.
CONCLUSION
THANK YOU