Project Plan

22
Mohammad Yousef Project Plan 4/23/14 MGMT404 Professor: Keith Earnshaw 1

Transcript of Project Plan

Mohammad Yousef

Project Plan

4/23/14

MGMT404

Professor: Keith Earnshaw

1

Table of Contents

Page 3: Project Charter

Page 8: Scope Statement

Page 13: Work Breakdown Structure

Page 14: Network Diagram

Page 15: Risk Management Plan

Page 17: Resource Management Plan

Page 18: Communication management plan

2

Project Charter

Project Name

Design and installation of a computer network for Fortify Satellite Office

Project Number

1

Project Manager

Mohammad Yousef Prioritization 1

Owner(s)

Keith Earnshaw

Start Date: 3/09/2014

Scheduled Completion Date:

4/01/2014

Mission/ Purpose

What is your project going to accomplish? How does this project relate to overall goals and objectives of the company? It is part of a program or larger project?

To design and install a computer network for the new Fortify Satellite office based on network and user requirements.

SOW What will this project create? What is the product of the project? At a high level, how do you plan on doing the work of the project? What are the high-level deliverables for this project?

This project will create a new network for the new office of Fortify based on their user requirements. It will allow the staff of Fortify to work efficiently and keep up productivity. The product of this project is a new computer network system. I plan on first going over the requirements of the network provided by the company (Fortify). Based on how many users and network requirements, and office/building specs, I will decide the necessary equipment and hardware. I will then go on sight to draw blueprints of the design of the network for the office. I plan on doing the project with my team on sight. All installation, implementation, and configurations will be done on sight. The deliverables for this project is to have a a proper, efficient network to allow the staff to work productively.

3

Objectives What objectives, if any, of the company is this project designed to meet?

1.) Fast connection and easily accessible network2.) Quality VoIP to ensure best customer service by staff3.) Design and install quality equipment and configurations to have lowest

possibilities of network failure. 4.) Complete in a timely fashion in order to allow staff members to begin

working in the new office.

Business Need

Why should we do this project? What will be gained, changed, or modified? Is there a financial or business reason to do this project? This area should contain any feasibility studies, NPV, PI, PB, or PBD used to advance the project.

The project must be done to allow new satellite office to be used. The staff can not start working in the new office location unless they have network connectivity. Fortify is a growing company and is constantly expanding and creating new offices all over the world. In order to work from a satellite office, there must be an efficient network in place to allow communication between office and HQ as well as clients. Without a network in place, the staff will be useless and not be able to communicate to the outside world or get any work done. A quality network is essential for staff members in the Chicago office to succeed.

Project Manager and Stakeholders

Who will lead this project? Who are the major stakeholders?

I will lead the project in designing and supervising the team to install, implement, and configure the network.

The major project stake holders are the staff of the new office and upper management of Fortify approving the project and approving the budget.

Milestones What are the key milestone dates associated with the project?

Initial consultancy - 3/15/2014

4

Design and planning - 3/20/2014 Implementation - 4/01/2014 Troubleshooting – 4/02/2014 Training – 4/10/2014

Budget What is the order-of-magnitude budget for this project?

$8,500 (-$2,125) (+$2,975)

User Acceptance Criteria/Quality

What are the minimum success criteria as defined by the key stakeholders?

A working computer network system and VoIP service

High-Level Project Assumptions

What are the assumptions on which the project is based?

The assumptions of this project are the network will be working properly with minimal network failure and will be completed by the quotes time in order to move the staff into the new office.

High-Level Project Constraints

What are the major limiting factors that affect the project?

There are not many constraints besides the budget. If we can meet at the agreed budget, there should be no other constraints. The timeline has been agreed between both parties and is easily manageable within the given time request.

Exclusions and Boundaries

What are the boundaries of the project? What is to be included and what is to be excluded from the project?

Exclusions include

5

1.) Admin access to staff members2.) Network failure due to uncontrollable circumstances (i.e. natural

disasters/weather related, service providers network failure, and building network failures)

Major Risks

What are the major risks affecting the project?

The major risks involved are going over budget and unforeseeable/network network failures.

KEY STAKEHOLDERS

Project Manager Authority Level

Legitimate

Project Core Team

Mohammad Yousef – Design and Supervision

6

Adam Case – Implementation

Sam Hughes – Implementation

Drake Seems - Training

Subject Matter Experts (SMEs) (include company and channel designations if applicable)

Fortify

APPROVALS

Type Name Signature DateProject Manager Approval:

Mohammad Yousef03/09/14

Customer/Sponsor Approval:

Robert Grady 03/09/14

7

Project Scope Statement

Project Name Design and installation of a computer network for Fortify Satellite Office

Project Number

1

Project Manager Mohammad Yousef Prioritization 1

Owner(s) Keith Earnshaw

Statement of Work—Project Description andProject Product

This project will create a new network for the new office of Fortify based on their user requirements. It will allow the staff of Fortify to work efficiently and keep up productivity.

We intend to do this by installing and implementing top of the line equipment and correct configurations based on the users requirements. We plan on using only Cisco equipment (i.e. routers, switches, etc) All of our techs are well rehearsed in network design and have their Cisco certifications. This will all benefit the project and assure that everything goes accordingly.

The product of this project is a new computer network system. I plan on first going over the requirements of the network provided by the company (Fortify). Based on how many users and network requirements, and office/building specs, I will decide the necessary equipment and hardware. I will then go on sight to draw blueprints of the design of the network for the office. I plan on doing the project with my team on sight. All installation, implementation, and configurations will be done on sight. The deliverables for this project is to have a a proper, efficient network to allow the staff to work productively.

We believe that we will need a total of 1 Cisco Router, 2 Cisco access point, 1 Cisco 24 port switch, 300 feet of cat 6 cables, and 6 Cisco VoIP phones. Our techs will install all the equipment first. They will then run the cables so they are not in the way. We well then configure the network, test, and trouble shoot for any issues.

8

Project Deliverables

1.) The network will be working properly with minimal network failure and will be completed by the quotes time in order to move the staff into the new office.

5.) Fast connection and easily accessible network6.) Quality VoIP to ensure best customer service by staff7.) Design and install quality equipment and configurations to have lowest

possibilities of network failure. 8.) Complete in a timely fashion in order to allow staff members to begin working

in the new office.

Project Objectives

1.) Fast connection and easily accessible network2.) Quality VoIP to ensure best customer service by staff3.) Design and install quality equipment and configurations to have lowest

possibilities of network failure. 4.) Complete in a timely fashion in order to allow staff members to begin

working in the new office.5.) Keep the cost of the project under the estimated budget which was $8,500

(-$2,125) (+$2,975)6.) We arrived at this number through the use of the following equation:

Budget Estimate (Variance of -10% to +25%)

Project Assumptions

The assumptions of this project are the network will be working properly with minimal network failure and will be completed by the quotes time in order to move the staff into the new office.

Project Constraints

There are not many constraints besides the budget. If we can meet at the agreed budget, there should be no other constraints. The timeline has been agreed between both parties and is easily manageable within the given time request.

Exclusions Exclusions include

3.) Admin access to staff members4.) Network failure due to uncontrollable circumstances (i.e. natural

disasters/weather related, service providers network failure, and building network failures)

Acceptance Criteria

A working computer network system and VoIP service with minimal network failures. The VoIP service must have good call quality and maintain a 90% up time. If updates are required and network and VoIP services will be down, we must give a 2 week notice before hand for quality assurance from Fortify to customers.

Technical Hardware Cisco UCS C210M2 for non NEBs Compliant Systems

9

Requirements

Software Linux RedHat RHEL 5 Update 3 or Update 5 (64 bit).

See Linux Update Requirements for details on the required Linux updates.

CPU Type 6-core (Cisco UCS C210M2)

CPU Number 6

CPU Speed 3 GHz

Memory (RAM) 32 GB or greater

Swap Space 32 GB or greater

Storage • Cisco UCS C210M2—Expansion, Performance, and Reliability Option

– For OS: One 146 GB SAS 15K RPM Drive

– For database using RAID10: Six 146 GB SAS 15K RPM Drives

– For backups using RAID10: Four 300 GB SAS 10K RPM Drives

– Requires usage Of LSI MegaRAID Controllers

– Dual PowerSupply

• Cisco UCS C210M2—Performance Option

– For OS: One 146 GB SAS 15K RPM Drive

– For database using RAID10: Six 146 GB SAS 15K RPM Drives

– For backups: One 600 GB SAS 10K RPM Drive

– Requires Usage Of LSI MegaRAID Controllers

• Cisco UCS C210M2—Basic Option With Additional Performance

– For OS: One 146 GB SAS 15K RPM Drive

– For database using RAID0: Two 300 GB SAS 10K RPM Drives

– For backups: One 600 GB SAS 10K RPM Drive

10

– Uses LSI Mezzanine RAID Controller

• Cisco UCS C210M2—Basic Option

– For OS: One 146 GB SAS 15K RPM Drive

– For database: One 300 GB SAS 10K RPM Drives

– For backups: One 600 GB SAS 10K RPM Drive

– Uses LSI Mezzanine RAID Controller

APPROVALS

Type Name Signature DateProject Manager Approval: Mohammad Yousef

03/23/14

Customer/Sponsor Approval: Robert Grady

03/23/14

11

Work Breakdown Structure

12

Network Diagram

13

14

Risk Management Plan

15

16

Resource Management Plan

17

Communication Management Plan

18