Project OverviewProject Overview
Ron StrykowskyPrinceton Plasma Physics Laboratory
NSTX Upgrade ProjectOffice of Science Review
LSB B318February 4th, 2014
NSTX-UNSTX-U Supported by
Culham Sci CtrYork U
Chubu UFukui U
Hiroshima UHyogo UKyoto U
Kyushu UKyushu Tokai U
NIFSNiigata UU Tokyo
JAEAInst for Nucl Res, Kiev
Ioffe InstTRINITI
Chonbuk Natl UNFRI
KAISTPOSTECH
Seoul Natl UASIPP
CIEMATFOM Inst DIFFER
ENEA, FrascatiCEA, Cadarache
IPP, JülichIPP, Garching
ASCR, Czech Rep
Coll of Wm & MaryColumbia UCompXGeneral AtomicsFIUINLJohns Hopkins ULANLLLNLLodestarMITLehigh UNova PhotonicsOld DominionORNLPPPLPrinceton UPurdue USNLThink Tank, Inc.UC DavisUC IrvineUCLAUCSDU ColoradoU IllinoisU MarylandU RochesterU TennesseeU TulsaU WashingtonU WisconsinX Science LLC
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 2
Agenda
8:30 AM - 8:50 AM Executive session / Federal Project Director - Tony Indelicato
8:50 AM - 9:20 AM Project Overview — Ron Strykowsky
9:20 AM - 10:05 AM NSTX Centerstack Fabrication — Jim Chrzanowski
10:05 AM - 10:20 AM Break
10:20 AM - 11:20 AM Tour Centerstack Fabrication Area - Jim Chzanowski
11:20 AM - 2:15 PM Follow-up and report writing (includes lunch for committee)
2:15 PM - 2:45 PM Debrief
2:45 PM - 3:00 PM Closeout Presentation
3:00 PM Adjourn
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 3
Contents
• Progress;
– Continued good Technical progress to date
• Performance metrics, Cost, Schedule, Budget, Risks;
– On cost and schedule
• Charge Questions;
– Responsive and complete.
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 4
Good progress on NB, Construction and DCPS since the last review
Neutral Beam DI piping contract completed and tested.
Neutral Beam cabling contract completed.
Neutral Beam Armor being installed
VV feet installation complete.
PF 4/5 support installation complete (exc bay B & L)
Torquing of the upper outer TF support weldments to their final torque levels has been completed
The installation of the MPTS vacuum interfaces has been completed and they have passed leak check
Casing relocated to NSTX high bay for completion of stud installation.
Diagnostics incl racks and cabling re-installation underway
New milling machine purchased and installed at D-site to facilitate fit-ups and installation of hardware.
DCPS; Autotester software ready, MSDplus server funtional, realtime logging tested. On target for May 2014 completion and support of FCPC testing.
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 5
Good progress on the centerstack since the last review
Aqua pour process underway COMPLETE
OH Winding station and taping systems commissioned
OH winding to begin in UNDERWAY. 1st of 4 layers wound.
Final assembly and delivery to the NSTX Test Cell in JUNE 2014
PFC Tiles machined.
PFC Magnetic diagnostics being installed.
CS pedestal delivered and ready for installation.
Inner TF lead extension awarded.
PF1b coil delivered.
Bus bar design completed with fabrication underway
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 6
• Cost – CPI = 0.98 (n/c)
• Schedule– SPI = 0.94 (0.97 last review) (as measured against Sept 2014 early finish)
– Total float = 10 1/2 months to late finish CD-4 (n/c)
• Completion– Forecast = November, 2014 (n/c)
– CD-4 DOE Milestone (Late Finish) = September 2015
• BAC =$86.8 EAC= $89.3 TPC =94.3M
– Last Review; BAC =$85.0 EAC= $87.6
• Cost to date = $71.2 M 80% complete (through December)
– Last Review ; Cost to date = $63.4 M 72% complete (through August)
• Free balance contingency 33%-28%
– Last Review; Free balance contingency 30%-28% Free balance = $5.7M - $5.1M
• Outstanding Risk (rev 24 ) = $3.3M
– Last Review = $3.8M (rev 22)
Good Performance Maintained
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 7
CD-4 SEPT 30 2015
CD-4 SEPT 30 2015
Forecast November 2014
Forecast November 2014
CD-3 Dec 2011CD-3 Dec 2011
Schedule on track for early finish • Critical path continues to be the centerstack fabrication and installation• Keys to meeting schedule• Vendor vetting and oversight • Timely receipt inspection• Overtime• Multiple shifts• Scheduling workshops• Improve efficiency through anticipation• Collaborations with NML (report
available)
• 10 1/2 months float remain
• Critical path continues to be the centerstack fabrication and installation• Keys to meeting schedule• Vendor vetting and oversight • Timely receipt inspection• Overtime• Multiple shifts• Scheduling workshops• Improve efficiency through anticipation• Collaborations with NML (report
available)
• 10 1/2 months float remain
Deliver CS to Test Cell JUNE 2014Deliver CS to Test Cell JUNE 2014
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 8
NSTX Upgrade – Milestones on track
Level MilestoneDOE
Commitment Date
Forecast Actual
Level I Receive CD-2 Approval Jan-11 Dec-10Level II Project FDR Jun-11 Jun-11Level I Receive CD-3 Approval Jan-12 Dec-11Level II Receive First Delivery Machined Inner Tf Conductor Jun-12 Apr-12Level II Nstx Complete Operations Jul-12 Sep-11Level II Begin Upgrade Outage Aug-12 Sep-11Level II Award Neutral Beam (NB) Vessel Cap Jun-13 Feb-11Level II Begin Inner Tf Quadrant Fab (Apply Turn Insul #1 Apr-13 Jun-12Level II Complete Assy and Pot Of 4th Inner TF Quadrant Oct-13 Jun-13Level II Complete Fabricate & Test Inner TF/OH Coil Assy Jun-14 May-14Level II NB Cap Installed Oct-14 Jan-13
Deliver Center Stack to the NSTX TC Jun-14Level II Lift In New Centerstack Jan-15 Jul-14Level II Complete ISTP Aug-15 Nov-14Level II Resume Operations Sep-15 Nov-14Level I CD-4 Sep-15 Nov-14
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 9
Detail Schedule Analysis - Startup of OH winding
Commissioning of winding station took 14 weeks longer than planned. While it was not on the critical path it soon became critical and delayed the start of winding by approx 26 work days (approx 5.2 weeks)
Since the start of winding, tasks have progressed as planned. (22 days planned vs 21 days actual )
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 10
Utilized more 2 shift ops reducing schedule by10 work days
Detail Schedule Analysis – VPI & post VPI tasks
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 11
Utilized 2 shift ops reducing schedule by14 work days
Detail Schedule Analysis – Installation and CD-4
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 12
0
10
20
30
40
50
60
70
Jun-
2010
Jul-2
010
Aug
-201
0Se
pt-2
010
Oct
-201
0N
ov-2
010
Dec
-201
0Ja
n-20
11Fe
b-20
11M
ar-2
011
Apr
-201
1M
ay-2
011
Jun-
2011
Jul-2
011
Aug
-201
1Se
pt-2
011
Oct
-201
1N
ov-2
011
Dec
-201
1Ja
n-20
12Fe
b-20
12M
ar-2
012
Apr
-201
2M
ay-2
012
Jun-
2012
Jul-2
012
Aug
-201
2Se
pt-2
012
Oct
-201
2N
ov-2
012
Dec
-201
2Ja
n-20
13Fe
b-20
13M
ar-2
013
Apr
-201
3M
ay-2
013
Jun-
2013
Jul-2
013
Aug
-201
3Se
pt-2
013
Oct
-201
3N
ov-2
013
Dec
-201
3Ja
n-20
14Fe
b-20
14M
ar-2
014
Apr
-201
4M
ay-2
014
Jun-
2014
Jul-2
014
Aug
-201
4Se
pt-2
014
Oct
-201
4N
ov-2
014
Technician labor
Labor on track
• Some leveling of field construction task required• On site electrical subcontractors to augment PPPL staff
• Some leveling of field construction task required• On site electrical subcontractors to augment PPPL staff
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 13
Risks
13
Retirement Date
OH/TF VPI $1,400k April 2014 (cost of rebuilding twice)
Inner TF bundle fab $325k Oct 2013
Serious injury stand-down $188k CD-4
Late vendor delivery on critical path $250k April 2014
I&C add’l capacity $300k June 2014
Diagnostic re-installation $294k April 2014
Hardware fit up issues $347 $477k Sept 2014
Mgmt direct allocations $216k April 2014
Critical skill lost $188k Sept 2014
Other $105k $155k June 2014
Total open $3,288k $3,793 k
Risk Events
• ~$505K net risk retired since last review• ~$505K net risk retired since last review
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 14
“What-if scenarios” bound the cost & schedule risk
14
Current BAC
Current EAC
1B2B
4
2C
3
2A
CD-4
3A
$86,000$86,500$87,000$87,500$88,000$88,500$89,000$89,500$90,000$90,500$91,000$91,500$92,000$92,500$93,000$93,500$94,000$94,500
10/1
/14
10/1
6/14
10/3
1/14
11/1
5/14
11/3
0/14
12/1
6/14
12/3
1/14
1/15
/15
1/30
/15
2/14
/15
3/2/
15
3/17
/15
4/1/
15
4/16
/15
5/1/
15
5/17
/15
6/1/
15
6/16
/15
7/1/
15
7/16
/15
8/1/
15
8/16
/15
8/31
/15
9/15
/15
9/30
/15
CD-4 Forecast
Schedule & Costing Scenarios
Monte carlo risk analysis @ 0%-100% probability. Criticalpath durations 90%-140%
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 15
Charge question #11. Critical Path Construction Efforts:
a) Does the Project team have a realistic, executable schedule for Center Stack (CS) remaining construction efforts?
b) Does the project have adequate resources and the appropriate skills mix to execute the remainder of the project per the plan?
• After initial startup issues with the OH winder, tasks have been progressing on schedule.
• Utilization of additional 2 shift operations have prevented schedule slip.
• Use of Saturdays still available to advance schedule and/or buffer against future delays.
• Overall the current staff levels on-board are adequate to execute the project schedule. Additional electrical labor will be augmented by our on-site BOA. Critical skills (i.e. welders, crane operators, machinists) work priorities managed via the Work Control Center (daily morning meetings.
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 16
Charge question #2
2. Baseline Cost and Schedule: a)Are the current project cost and schedule projections consistent with the approved baseline cost and schedule? b)Is the contingency remaining adequate for the risks that remain?
•The project is 10 1/2 months ahead of our CD-4 milestone.
•Reasonable contingency remains to complete the project. This conclusion is based monthly updates of our EAC’s as well as several schedule/cost “what-if” exercises.
•$505K net reduction in risks identified.
•Project schedule contingency is 10 1/2 months, cost contingency range is 33%-28% (ref 26.6% baselined at CD-2 )
•The project is 80% complete compared to 72% at the last review.
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 17
Charge question #33. Management: Evaluate the management structure as to its adequacy to deliver the scope within budget and schedule. a) Are risks being actively managed? b)Has the project responded satisfactorily to the recommendations from the previous project reviews?
•The key management personnel required to deliver the baseline are still in place within the project organization. This includes DOE Federal Project Director and senior laboratory leadership.
•The project has reacted effectively to resolve technical issues that have arisen.
•Communication amongst the project team, senior PPPL management and DOE has provided transparency into all aspects of the project.
•Project risk identified in our updated risk registry. Mitigation plans being implemented (e.g. coordination meetings, procedures, training, mockups, R&D, trials).
•Previous review recommendations reconciled - see next slide
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 18
Charge question #3 continued
3-b. Previous review recommendations:
1.Identify lower risk CS tasks that can be performed by additional personnel or off-shift to gain schedule contingency.
• Continually being evaluated i.e., Casing moved to D-site to facilitate field crews support.
2.Generate an interim milestone for DCPS for earlier commissioning of a reduced scope system able to support all system testing and initial machine operation.
• Simple over-current calculations developed.• Interim milestones being tracked toward a May 2014 completion date.
3.Include schedule contingency impacts in the ECP forms for the future ECPs.
• Implemented in the ECP log for impacts to the critical path.
4.The EAC calculation should include items and activities that are likely to occur.
• Concur and included
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 19
Charge question #3 continued
3-b. Previous review recommendations:
5. Ensure risk register is updated and maintained • Concur and updated twice since the last review. Changes are color
coded.
6. Evaluate a broader range of likely project outcomes to better understand and communicate with DOE the limits of cost and schedule contingencies to ensure project success by November 1, 2013.
• Completed and transmitted to DOE October 2013. Updated January 2014. (ref slide 14)
7. Work with the Site Office and program develop a focused “end game plan” to monitor and communicate critical project activities to better ensure project success by November 1, 2013.
• Detail critical path schedule updated, track, and posted weekly (ref slides 9-11)
• Weekly “rollover” meetings review all tasks for CD-4 and start-up.
8. Action Item; Site Office to schedule a status review in mid-January 2014.
• Completed February 4th, 2014
NSTX-UNSTX-U NSTX Upgrade Project – Office of Science Review – February 4th 2014 20
Summary
• Project personnel have maintained a safe working environment.
• The project continues to make good technical progress.
• The project is on schedule and cost with adequate contingency to finish.
• The project is sufficiently staffed to meet schedule.
• The project is on track for meeting CD-2 baseline within OFES budgetary guidance.
• Project personnel have maintained a safe working environment.
• The project continues to make good technical progress.
• The project is on schedule and cost with adequate contingency to finish.
• The project is sufficiently staffed to meet schedule.
• The project is on track for meeting CD-2 baseline within OFES budgetary guidance.