Project on Bid Process

download Project on Bid Process

of 13

Transcript of Project on Bid Process

  • 8/10/2019 Project on Bid Process

    1/13

    CHAPTER NO:-1

    1.Introduction:-

    1.1 General:-

    The project often get delayed and show time and cost overruns as a consequence. The

    importance of bidding document, good biding process and the selection of contractor are

    some of the important prerequisites for the successful completion of a project. The aim of the

    study was to identify factors in bid process management that may lead to project success.

    Subsequently, these factors were ranked by expert for their importance and ability to

    influence the project results. To brainstorming sessions were organized for identifying

    factors, One with a government organization which executes a large number of public

    projects mainly through cost based selection and second with a private developer

    organization which hires contractor through quality based selection process. Twelve factor

    were shortlisted through this process and they were given importance ranking were

    experienced professionals. The mean value and the descriptive statistics were worked out to

    rank the factors. Top five factors in the bidding process, identified by using this process are

    specification , special condition are contract, overall and similar experience, award criteria

    and estimates.

    Government officials in the developing countries face public ire for delay in project

    execution and resultant cost increase. Delay and cost overruns occur in private projects also,

    though the consequences of delay are different. Top five factors featured in the list are

    insufficient equipment, inaccurate time estimate, payment to the contractors, change orders,

    and inaccurate cost estimate. Many factors influence failure and success of a project and

    contractor selection is one of the prominent reasons amongst that.The importance of selecting

    right contractor and having proper bid documents is recognized by the industry and also by

    the researchers. Standard bidding documents have been developed by the owners all over the

    world or they have adopted standard documents developed by world Bank, Asian

    Development Banks, FIDIC and others. However, in the developing countries, bidding

    documents and procedures are yet to be standardized. Even where the process has been

    standardized, the weightage of different selection criteria is a matter of debate.

  • 8/10/2019 Project on Bid Process

    2/13

    Contractors must consider many factors when they develop their bidding strategies.

    Bought on found in his survey (with useable responses from 126 general construction

    contractors from around the Words) that the factors in developing a bidding strategy

    (in descending order of importance to the contractors) are:

    1. Clearness and detail of specifications

    2. Past experience with similar work

    3. Confidence in subcontractor bids

    4. Location of project

    5. Number of competitors

    6. Duration of project

    7. Workload

    8. Market condition (busy or slow)

    9. Size of bid

    10. Opportunity for follow-on work

    11. Relationship with architect/owner

    12. Competitors bid history

    13. Confidence in external events (interest rates, inflation, etc.)

    8.1 Necessity of Bid process Management

    The main objectives of the Bid process management are:

    Choose suitable partner on best possible terms

    Choose partner with skills, experience and resources

    Secure desired service improvement & efficiency

    In todays world, the bid process management has emerged as one of the main activities

    of project management and adequate importance is attached while scheduling of the project

    itself. Due to rapid increase in the project complexities, a delivery partner can be sought right

    at the beginning or at any stages of project. Based on the involvement a project partner may

    be classified as under:

    Owners Consultants

    Programme / Process / Project Management

  • 8/10/2019 Project on Bid Process

    3/13

    Activity Consultants

    Piece-meal Constructions

    EPC/Turnkey

    BOT/BOOT/BOO etc

    Scope Of the project

    The aim of the study was to identify factors in the bid process management that may lead to

    project success. Subsequently, These actors were ranked by experts for their importance and

    ability to influence the project results.

    In this project the main top factors in construction bidding process, identified by using

    this process are specifications, special conditions of contract, overall and similar experience,

    award criteria and estimates. This above factors which affect the effective bidding process

    and communication will work out from the various questionnaire surveys of different

    projects. For this purpose questionnaire are designed accordingly and respective answers

    should be collect from the Government and private project.

    After the overall study of the projects to give the effective suggestion choosing the partnerson the best suitable turns and partners with skills, experience and resources.

    Objective

    1) To study concept of bidding of construction project.

    2) To contractor selection vary between Public and Private projects.

    3) To Analysis the data Educational profile and Work experience on the basis of their

    organizations.

    4) To study the bid process management on various present construction sites.

    5) To discuss and give the effective suggestion on projects often get delayed and increase the

    cost.

    Methodology

  • 8/10/2019 Project on Bid Process

    4/13

    1) The preliminary data which required for the project will be collect from the various

    studies which are already carried out upon this construction bidding. Referring to

    previous research, this study identified by public and private project of project

    finalization. Efficient bidding is the most important term in project finalization process.

    2) To brainstorming sessions were organized for identifying factors, One with a

    government organization which executes a large number of public projects mainly

    through cost based selection and second with a private developer organization which

    hires contractor through quality based selection process.

    3) From the above overall study there are twelve factors were shortlisted through this

    process and they were given importance ranking by experienced professionals, for

    project finalization.

    Table 1:Important Factors In Bid Process Management

    SI. No. Factors

    1 Bidding process

    1.1 Splitting the contract packages/ Work Packages

    1.2 Sequence of awarding contracts

    1.3 Award Criteria

    2 Bidding Documents

    2.1 Bills of Quantities &Estimated cost

    2.2 Tender Drawings

    2.3 Specifications

    2.4 Special Conditions of contract

    2.5 Standard Bidding &contract Document

    3 Contractor Qualification Criteria

    3.1 Overall &Similar Experience

    3.2 Financial Capacity

    3.3 Bid Capacity

    3.4 Proposed development of tools, equipment& plant

    for given project

    4) The whole bid process management study applies on live construction private or

    government projects. And what are the actual bidding on live work and theoretical

  • 8/10/2019 Project on Bid Process

    5/13

    studies. On the live project on bidding process questionnaire survey should be carried

    out.

    5)

    In the last step of the project, the analysis carry out on the above theoretical study and

    the questionnaire survey, the suggestion if any given to the management team. As the

    management can better understand and improve the bidding process management by

    selection of contractor, education profile, work experience, count and ranking were

    calculated by data analysis.

    1.1. ORGANIZATION OF PROJECT

    The thesis format follows the logical steps of literature review, establishing the

    questionnaires, developing the methodology, gathering and analyzing data and

    drawing conclusions. The project stage-I involves following chapters:

    1)

    The second chapter deals with the literature survey related to the construction

    bidding in private and public project in construction industry. This review determined

    the context of the research study and positioned this work relative to previous

    research. This chapter will help to selection of contractor on the basic of pre-

    qualification and many previous skills and knowledge.

    2)

    The third chapter deals with to study bid process management for finalization of

    construction project.This chapter will provide total information about the role of

    coordination in construction industry in India and effect of goal achievement on

    performance of project.

    3) The fourth chapter deals with the success of project finalization for construction

    project. In this chapter the questionnaire was designed on the basis of bid process

    management. The questionnaires are designed on the basis of eight coordination

    methods.

    The data collection will be obtained from the designed questionnaire. For this data

    collection of two major construction projects were selected. The observed result is

    tabulated and thereafter the result analysis is carried out. The last step of the project is

    to give suggestion for successful bid process management for project finalization.

  • 8/10/2019 Project on Bid Process

    6/13

    CHAPTER 2

    2. LITERATURE SURVEY

    2.1. INTRODUCTION

    Generally, successful completion of construction projects requires many important

    processes and one of them is the bidding process. During the bidding process,

    selecting the most appropriate contractors to execute the project seems to be quite

    difficult. Contractor selection plays a vital role in the overall success of any construction

    project. Clients generally need the best criteria in selecting contractors in order to get

    best results in term of cost, time, and quality for their projects. Historically, clients

    usually award the contract to the lowest bidder during tendering. Despite the guidelines

    that exist in the literature in selecting main contractors; in real practice, Other country

    construction clients individually have their preferred criteria different from those

    obtained in the literature. The main threat here is that clients do make costly mistakes in

    their decisions to award the contracts to unqualified contractors and this would

    eventually have damaging consequences on the project and clients investment. It

    therefore became necessary to examine the different criteria adopted by clients in

    selection contractors in order to find out the most criteria that clients should focus on

    when awarding construction contracts to main contractors. To this regard, this paper is

    aimed at identifying and ranking the actual criteria used by clients in real practice for the

    selection of main contractors in India.

    Bidding Process

    Traditional Procurement system involve pre-qualification ,short-listing ,bid evaluation

    processes including those involving designbuild types of

    contracts(palaneeswaran,20000).Overall bidding process is linear and compartmentalized and

    follows design ,bid and construction process (Hallowell,2009).In the traditional system ,

    client or owner hires the designer who prepares the designs and estimates. The client floats

    tenders based on this estimates and drawings . Interested contractors bid for the project and

    they are typically selected by the least cost criteria amongst all technically qualified

    contractors .This least cost criterion is widely debated but used selection method at least in

    the developing countries such as India.

  • 8/10/2019 Project on Bid Process

    7/13

  • 8/10/2019 Project on Bid Process

    8/13

    organizations where they are concerned with the top quality. In government organizations,

    when there are mini projects with the same departments and that too on a regular basis, the

    maintain the list of prequalified bidders. The shortlisted bidders are generally asked to submit

    financial bid for the given project. This reduces the time of technical evaluation.

    Conceptunal Model For Contractor Selection

    A conceptual model has been structured for contractor selection including bid price

    and non-price criteria in relation to Article 40 of PPL 4734 and also taking into account the

    needs of public clients. In structuring the model, most of non-price evaluation criteria that

    may not

    be translated into numerical impact data are eliminated in order to avoid the subjective

    evaluation of contractors and others are grouped according to similarities and relations

    between them. In the model non-price criteria are grouped at 9 main headings as Contractors

    Organization, Past Performance, Past Experience, Plant and Equipment, Personnel, Project

    Management, Quality Management, Health and Safety Management, Environmental

    Management. Each main criteria has its own sub-criteria as shown in Table 1. Price criteria

    refers to the lowest cost in evaluation process. The model enables the user to designate the

    weighting of non-price and price criteria depending on the needs and wants of the clients

    and/or projects.

    Non-price evaluation criteria for contractor selection given below

    Contractors Organization

    Past Performance

    Past Experience

    Plant and Equipment

    Personnel

    Project Management

    Quality Management

    Health and Safety Management

    Environmental

    Management

  • 8/10/2019 Project on Bid Process

    9/13

    FACTORS AFFECTING THE BID/NO BID DECISION

    The study aim and objectives necessitated the identification of the various factors that

    have been found to influence the bid / no bid decision. The review of the literature resulted in

    identifying 94 potential factors affecting a contractors bid/ no bid decision. These 94 factorswere drawn together from the sources shown in Table

    1. The factors identified were then divided to ten groups. The groups were developed on an

    intuitive issues, including project characteristics, business benefits, the client characteristics,

    the contract, project finance, company characteristics/ situation, firms' previous experience,

    bidding situation, economic situation, and competition.

    Factors affecting the bid & identified from the literature review

    1 Project characteristics:

    1. Size of contract in SR

    2. Duration of the project

    3. Type of project

    4. Job start time

    5. Methods of construction (manually, mechanically)

    6. Location of the project

    7. Type of equipment required

    8. Type of labour required

    9. Site clearance of obstruction

    10. Degree of build ability

    11. Site accessibility.

    12. The projects' stakeholders

    13. Design quality

    14. Design team

    15. Local climate

    16. Public exposure

    17. Degree of technological difficulties

    18. Safety hazards

    19. Completeness of drawings and specification

    19. Degree of difficulties

  • 8/10/2019 Project on Bid Process

    10/13

    20. Type of procurement methods

    21. Degree of possible alternative design to

    reduce cost

    22. Expecting date of commencing

    23. Pubic objection

    2 Business benefits:

    1. The benefits expected in terms of the

    company reputation

    2. Need for continuity in employment of key

    personal and work force

    3. Establishing long relationship with the client

    3 The client characteristics:

    1. Local custom

    2. Relationship with the owner

    3. The client reputation among other contractors,

    with whom they had worked

    4. The client requirements

    5. Owner (Private, Public)

    6. Prompt payment habit of the client

    7. The client financial capacity

    8. Size of client

    4 The contract:

    1. Type of contract

    2. Clearness of the work and specifications

    3. The ability of modifying the contract

    4. The ability of portion subcontracted to others

    5. Fines for delay

    6. Type and number of supervisory and labor required

    7. Consultants interpretation of the specification

    8. Use of nominated sub-contractor

    9. The contract special requirements

    10. Contract conditions

  • 8/10/2019 Project on Bid Process

    11/13

    5 Project finance

    1. Original price estimated by the client

    2. Work capital required to start the job

    3. The possibility of delay or shortage on payment

    4. Project cash flow

    5. The project mark-up size

    6. Percentage of insurance premium

    7. Anticipated value of liquidated damage

    8. Tax liability

    9. Financial goals of the company

    10. Degree of difficulties in obtaining bank loan

    11. Market share

    6 Company characteristics/situation

    1. Availability of required cash

    2. Ability of doing the job

    3. Availability of required equipment

    4. Availability of qualified human resources

    5. Uncertainty in cost estimate

    6. Need for work

    7. General (office) overhead

    8. Current work load

    9. Reliability level of subcontractors

    10. The project is matching the company strategy and future vision

    11. Strength in industry

    12. Specific features that provide competitive advantage

    13. Availability of qualified sub-contractors

    14. Familiarity with site condition

    15. Strength of business partner/ subsidiaries

    16. Company ability of design involvement and innovation

    7 Firms' previous experience

    1. Past experience with similar project

    2. Past profit in similar job

  • 8/10/2019 Project on Bid Process

    12/13

  • 8/10/2019 Project on Bid Process

    13/13

    CHAPTER NO 3

    To Contractor Selection Vary Between Public And Private

    Projects.Introduction