Project Mba Report

download Project Mba Report

of 17

Transcript of Project Mba Report

  • 7/30/2019 Project Mba Report

    1/17

    CONTENES

    1.Acknowledgements

    2.Certificate

    3.HM- Company Profile

    4.Introduction

    5.Problem Definition &Initial Trials

    6.Heat Treatment Process

    7.Fishbone Analysis

    8.Conclusion

  • 7/30/2019 Project Mba Report

    2/17

    CERTIFICATE

    THIS IS TO CERTIFY THAT MANISHA SURESH

    SONAR HAVE COMPLITED

    A PROJECT ON BENDING IN CLUSTER GEAR

    SHAFT ANALYSIS AND SOLUTION ;

    As a part of her training at A.V.TECH,LTD

    PITHUMPUR FROM - 5MARC 2013 TO 5 APRIL

    2013AND HER PERFORMED SATISFACTORILY.

    PROJECT GIDE

    N. K. RAO.

    D G M QARD,

    AVTECH LTD PITHUMPUR.,

  • 7/30/2019 Project Mba Report

    3/17

    ACKNOWLEDGEMENTS

    I Would like to express my sincere gratitude towards

    Mr.N.K.Rao,(DGM,QARD)Hindustan Moters Limited,Pithampur for allowing me to

    undertaken this project.It has been an absolute pleasure to be associated with

    him.I think him for his constant guidance and enlightening insights during my

    short sojourn.

    I would also like to thank Mr.Prashant Sarvastava(HEAD,training Center)for this

    help.I am immensely indebted to Mr.D Ghoshal,Mr.S.SARAF and Mr.H. Srivastava

    (members of Heat Treatment Cell) for their guidance,support and continuous

    efforts without which the successful completion of this project would not have

    been possibal .

    In the end, Iwould like to express my gratitudetowards all the operators,security

    personnel and HR personal who have directly or indirectly contributed in my

    project wok.

  • 7/30/2019 Project Mba Report

    4/17

    HINDUSTAN MOTORS LTD.

    COMPANY PROFILE

    Hindustan Moters Ltd.pioneers in the Indin Automobile sector is one of the

    G.P.Birla&C.K.Birla groups of companies.The company came into existences in

    1942 at Port OKHA. Later the company was shifted to Uttara (W.B)near

    Kolkata.In1944-45 the company entered into collaboration with Nuffield Org. of

    England& started manufacturing Indian model of Moters cars. In subsequent

    years it kept on giving different models: viz Hindustan, Hindustan Land Master M,

    Hindustan Traveler, Hindustan Ambassador, mark 1to4, Ambassador

    Nova&Contessa 1to the Indin customers.

    Various Divisions Of HM

    Name

    div.

    Yea

    r

    Located

    At

    Present

    Collabor

    ators

    Products

    Manufactured

    Hind Moter

    Div1942 Uttarpara,

    West

    Bengal

    NONE Passenger

    Car

    Power

    products

    Div

    1983 Hosur

    Tamilnadu

    Allison,USA

    Twin

    Disc,USA

    Power

    Shift

    transmissionPower

    Unit Div.

    1984 Indore

    M.P.

    Isuzu,japan Diesel, Petrol &

    transmission for

    Ambassador&

    Contessa

  • 7/30/2019 Project Mba Report

    5/17

    1997 Indore

    M.P.

    Mitsubishi

    Motors Crop

    Japan

    Lancer Car

    Engines&

    transmissions

    ChennaiCar Plant

    1997 ChennaiTamilnadu

    MitsubishiMotors

    Crop, japans

    Lancer Car

    RTV 1998 Indore

    M.P.

    OKA Motors

    Crop,Austral

    ia

    RTV

    manufacturing&

    assembling.

  • 7/30/2019 Project Mba Report

    6/17

    THE POWER UNIT PLAt

    The power plant of hml, which was initially the passenger car divisions was

    established in 1984 the division comprised of state of art manufacturing. Thedivision complex, manufacturing fuel-efficient engines and transmission, basically

    for passenger car application the division spread over an area 153- hectare. The

    the total investment in the divisions including the machinery amounted to around

    s- 1840 million. The main Assimilation of technology from Isuzu Japan.

    The production in the division commenced from 1987. At present plant has

    manufacturing capacity of 15000 power unit per annuam. The division can boast

    of ultra modern research and development facilities for design can boat of ultra

    modern research and development facility for design, development and testing of

    engine and transmission. The division also caress out systematic training program

    and in 1995-1996 the division achieved 4 mansday of training per employee per

    year.

    During their journey owards excellence him, pithumpur got iso9001 accreditation

    in 1994, in addition to this they were certified as iso9001 accreditation in 1994. In

    addition to this, they were certified as Iso14001 Company for their environmental

    management system implementation in November 200. The journey for

    excellence system implementation in November 2000. The journey for the

    excellence continues with the effort in embracing total productive method as a

    religion with the effort in embracing total productive maintenances as a religion

    in addition to institutionalizing qs9000 standards.

  • 7/30/2019 Project Mba Report

    7/17

    Introduction

    by Hindustan motors ltd. KNOWN AS THE CLUSTER GEARS SHAFTS . YHE c.g.s. THE c.g.s IS A

    PART OF THE TRANSMISSION ASSEMBLY ASSEMLED IN H.M. LTD, PITHUMPUR FOR MAHINDRA

    AND MAHINDRA The focus of my project is a component manufactures BOLERO.

    THE MANUFACTURING PROCESS OF c.g.s. involves the following steps.

    1- Forging- the shaft is forged at HMS uttarpara plant situated in west Bengaland sent to pithumpur for further processes.

    2- Machining- the various machining operation that are carried out on theforged shaft are 1- facing and cent ring , 2- turning,3-thread cutting , 4-

    gear hobbling & shaping, 5- splint rolling- , 6- gear shaving. All the above

    operation are carried out on cnc machine.

    3- Heat treatmentthe heat treatment procesis is the most important stepin the manufacturing of cluster gear shaft, since it is this stage which

    imparts the component the required strength need to withstand normal

    and terosinal stress of varying magnitude, to which it is subjected. This

    phase basically consist of the fooling step which have been discussed in

    detail since this is the main area of my study 1- carburizing and hardening,

    tempering.

    4- Hard grinding- after the heat treatment process the cgs is sent for hardgrinding. This is the final machining operation before the C.G.S. is sent for

    assembly. This stage ensures the desired surface finish on the component

    5-

  • 7/30/2019 Project Mba Report

    8/17

    Heat treatment process-

    The fooling text contains a study of the process to which the cluster gear shaft is

    subjected in the heat treatment shop. The list of processes is under-

    1- Prewashing2- 2- carburizing and hardening,

    3- 3- post washing4- 4-tempering;

    5- - shot blasting,6- Straightening

    7- Induction annealing.1- Prewashing this phase is carried out to free the

    component from oil, dust and any undesirable surface

    deposit. The process is carried out in a specially designed

    washing Mac to 1 hr to be complied.

    2- -carburizing &hardening- carburizing is the absorption anddiffusion of carbon in to solid ferrous alloy by heating to a

    temperature usually above Ac3 fec diagram in contact with

    a suitable carbonaceous material gas carburizing usesCARBON FROM A HYDROCARBON GAS AND EASILY

    VAPORISED HYDROCARBON LIQUID O PRODUCE A HARD

    SURFACE on steel mpart . The main function of carburizing

    is to produce a hard surface layer on steel part. The main

    function of gas carburizing is to be providing adequate

    supply of carbon for absorption and diffusion into the steel.

    a common commercial practice is to use an endothermic

    gas is carrier that is enriched with one of the hydrocarbongases the atmosphere inside the furnace is combustible

    and toxic while the medium reducing. Hardening means

    increasing the hardness by a suitable heat treatment

    process which involves heating the components above the

    austenising temperature for a certain pre-determined

  • 7/30/2019 Project Mba Report

    9/17

    period of time and then rapidly cooling it by quenching it

    in suitable the result obtain are unsatisfactory as far as

    he improvement in the value of bending in the cluster

    gear shaft is concerned, as percentage improvement in the

    result is almost negligible we may infer that the changing of

    oil has not shown any improvement in bending however

    the shaft cell reported an improvement in the lead profile

    which was positive sign.

    3- 4- priestesses- one of the causes of bending can beattributed to the pre-stress in the component developed

    during the additional stress during the machine stage. The

    forged components supplied the company not normalized

    as per the specification of the input material. As the

    component pass through various machining operation

    these stress are compensated during quenching in the from

    of bending and distortion.

    4- To prove the fact we conduct 2- trials in which the changewas pre- heated to relive any forging or matching stress

    before being subjected to hardening and quenching the

    experiment was carried out on charge no 8192/8198 thepreheating carried out in tempering furnace at a

    temperature of 500.dc, for a duration of 60min. the result

    of the trials are attached in the fooling pages

    5- D. METHOD- analysis these variable- i- time, temperature,and pressure- the time temperature for various processes

    is already specified on the process sheaf and is proved to

    be correct the prescribe time , temperature and pressure

    are mentioned on various machine the case depth andhardness values thus obtained are within specification.

    6- Quenching process- large bending stresses are generatedduring quenching since. The component at very high

    temperature 920 dc is suddenly cooled. The causes

    distortion in component, in earlier trials to study the effect.

  • 7/30/2019 Project Mba Report

    10/17

    Slow quenching was also done but this did not yield any

    encoring result, so was ruled out. Flow quenching oil into

    the f/c may have some effect on bending. So to get a

    uniforms flow over components, additional guard besides

    the fixtures was put inside the machine, even this did not

    produce any improvement in terms of reduced distortion

    so this factor was ruled as well. Quenching oil- one of the

    possible reason for increasing bending could be attribute to

    the quenching oil being used. in one of the earlier trials in

    conducted at hm , a step was taken to change the

    quenching oil altogether these the older mt-355 was

    replaced by an oil- vedol quenching hm, thus is more

    viscous than the former

    7- Ch no 5359 mt-355- oil charge qty-77 no.8- Range mm no of compo % remark.9- 0.00-0.06 18 23 good10- 0.17-0.10 18 23 fair11- 0.11-0.15 13 16 bad12- >0.15 28 36 very bad13- Visual case depth- 0.6-1.0 mm. microstructure- case- finetempered mrtensite, no carbide network allowed. Retain

    austenite, 40% maximum, and core- low carbon tempered

    martensite lctm + bainite.

    14-15-16-17-18-19-20- Medium. Case hardening is generics term covering several

    processes applicable to steel that change the chemical

    composition of the surface layer by absorption of carbon,

  • 7/30/2019 Project Mba Report

    11/17

    nitrogen etc. the process used for doing case hardening

    involves carburizing followed by quenching.

    21- Initial trials- we conducted 3 trials initially on chargenumbers 8160,8162,8163 with a view toa- learn more

    about heat the treatment process under studys- get an

    insight into the nature of the problem and the variable

    concerning it . the result of the run outs observed on the

    cluster gear shafts in these trials have been attached in the

    subsequent pages they have been summarized as under.

    Trial charge no no of components Avg run out

    1 8160 77 0.17mm bad

    2 8162 77 0.147mm bad3 8163 77 0.15mm bad

    THE AVERAGE RUNOUT AT SECTIONSA In cluster gear shaft of all 3 trials was

    found to be 0.155mm or 155 microns which is well above the specified tolerance

    of 0.04mm or 40micron. A runout of this magnitude required considerable

    prevent this problem occurring that the heat treatment stage.straighting action o

    brings the component within the specified limits. Which is not advisable? Since it

    may damage the shaft .hence it is of utmost importance to

    Note- it nuts be noted the forging applied to H.M. As against being normalized

    xcm318 harden and tempered forging of a required material is supplied.

    c- Jigging and fixtering- the fixture which the component mounted may be faulty

    the fixtures may have bends in themselves or the initial mounting may be

    incorrect, but the fixtures have been thoroughly cheacked for such inherent faults

    and any such possibility seen ruled out.

    Gauges /calibrations- various gauges on different machine are checked for

    performance. Monitored and calibrated on regular basis. Therefore this factor

    canbe ruled out as a possible cause of bending.

  • 7/30/2019 Project Mba Report

    12/17

    Condition of fixture- various possible activity is carried out observe no issue.,

    furnace and heating pattern - one of the possible causes for large magnitude of

    distortions, / bending during heat treatment can be non uniform heating in sealed

    quenching furnace this result in to localize thermal stress which are ultimately

    compensated in bending.

    This fact had to be suited in depth so as to evaluate its validity. In the given

    context. We conclude three trials chq no 8163, 8192, 8198, and drew up location

    wise bending pattern for each charge. these pattern have been attached pages,

    when the pattern have been attained in the subsea pages, when these pattern

    were studied for any observable trends that indicated any discrepancy in the

    furnace heating pattern they did not revel any such trend thus we conclude that

    the furnace were functinating normally and the problem being discussed couldnot be the functioning normally and the problem being discussed could not be

    attribute to them.

    Problem definition-it has been observed thatduring the heat treatment processthe cluster gearshift undergoes bending of the order of 150-200 micron. 0.15 to0.25 mm. as against specified tolerance. Of 40 microns 0.04. a measurement of

    runouts of components before and after heat treatment process, illustrate this

    fact. These bending make it necessary for a large amount straightening operationto be carryout since apply high lod is not avlable and its twist and effect the

    component. Adversely hence it is very important that is bending remove, the

    cluster gear shaft is a critical component of the transimation assembly and any

    short case in its quality is reflected on the functioning of the entire unit./, our

    project task would be study the heat treatment process , they various factor

    concerning and affecting it, identifying the possible reason for bending and

    suggesting measure to eliminate it.

    Summary of result-

    the result of run out at section a 0f

    charge nos- 8192/8198 are summarized as below.

  • 7/30/2019 Project Mba Report

    13/17

    Trial ch.no. no of comp avg-runout comment

    4 8192 47of 77 recorded 0.073mm very good

    5 8198 77 0.061 very good.

    The average run out of stress relive cluster gear shaft was found to be 0.067

    microns. In comparison to our initial trials where the avg run out 0.155mm, we

    see a 56.7% reduction in the run out. Section a

    As it is evident the next page which illustrate, it is worth nothing in the ch no

    8198, sixe component 8198. Sixe components were such that they did not require

    any straightening action at all. These are very positive sign which were not

    observe earlier.

    FISHBONE ANALYSIS

    The fish bones analysis is done on the basis of four aspects that govern a

    components process of manufactures. As depicted in the diagram, the fishbone

    analysis for cgs is follows-

    a- Man- loading-The loading of components is performed by unskilled operators. Since

    before being loaded into the furnace, the arrangement is cross checked for

    correct loading style and pattern, thus the possibility of this fact being

    responsible for bending is ruled out.Further, if this was the reason

    responsible for increased bending than it would have been observed only in

    a few components which had been erroneously loaded, but repeated

    bending discards mishandling as a cause.ii. Monitoring

    Although most of the controls are electronic and automatic, but human

    supervision is essential to ensure problem free running of the process. If

    lack of monitoring had been the reason for increased bending then it would

  • 7/30/2019 Project Mba Report

    14/17

    have been observed only in a specific charge, but repeated patterns

    eliminate this as one of the probable causes of bending.

    iii.STRAIGHTENING

    The straightening operation is one operation which relies heavily on the skill of

    the operator , but since the bending occurs before the operations i.e. during heat

    treatment hence these bending occurs before the operation i.e. during heat

    treatment hence these bending occur before these operation i.e. during heat

    treatment hence these bending cannot be attribute to these operation mistake

    can be made during measurement of run outs but practically this will not lead to

    error of the magnitude. But practically this will not lead to errors of the

    magnitude.

    b- Material-c- Composition- the material specification for cluster gear shaft is as follow

    material xscm318 low carbon alloy steel , input specification, annealed/

    normalized 160/220 b.h.n out put specification- surface hardness 58

    h.r.core hardness 30-45 hrc , effective case depth, 0.5-.8 mm.

    d- Fishbone digram:-

    Material man

    Composition loading

    Straightinig

    monitoring

    Time/tmp/pressure bending in c.g.s.

    Time/ temp/pressure fixtures sqf/c heating

    pattern

  • 7/30/2019 Project Mba Report

    15/17

    Quenching process gauges condition of machine

    .quencing oil used

  • 7/30/2019 Project Mba Report

    16/17

    1- Every components is checked for the magnitude of distortion bending it hasundergoes during heat treatment this is done by measuring run out at

    section a , c. b. , dial gauges with a least count of 0.01 mm i.e. 10 micron are

    employed for these a common trends has bents section that the run outs

    increases dia the run out is seen to be increasing , second step of

    straitening operation is to apply mechanical load on the bent section

    primarily section b & c to minimize the run out so that component fall

    within the specified tolerance the load is usually not applied on section a

    which being greater in cross section is susceptible to d damage.

    2- These straightening machine used is based on hydraulics control and hasbeen manufacture by galdabini Italy. The machine has max load capacity of

    50 tons. But the maximum load during the straightening of cgs is kept 5 tons.

    It must be noted that he straightening operation is largely depends on the

    operators skills. It always advisable may handle the operations.

    3- Induction annealing- the last operation on the cgs involves the localizedheating in threaded portion of the mentioned area by means of electrical

    induction to a certain temperature followed by gradual cooling in air

    annulled is carried out to soften the threaded portion, the induction

    annealing machine has been made by ema- india.after induction annealing

    the component is sent for hard grinding before finally being dispatched forassembly.

    4- Conclusion-5- After studying the result of trials, we can conclude that stress reliving the

    components has yielded good result. Thid illustrate the fact that the

    component yielded extremely good result. The illustrates the fact that the

    components carry a large magnitude of machining stresses prior to heat

    treatment.

  • 7/30/2019 Project Mba Report

    17/17