PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311...

234
PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING COUNTY 305 WICK AVENUE, YOUNGSTOWN, OH 44503 OFFICERS OF THE LIBRARY BOARD OF TRUSTEES Dr. David Ritchie President Carole S. Weimer Vice President Mark J. Mrofchak Chief Financial officer Tina McBane Deputy Fiscal Officer Aimee Fifarek Executive Director PREPARED BY: ms consultants, inc. 333 East Federal Street Youngstown, OH 44503 Phone: 330-744-5321 ms project No. 64-12A01 ISSUED FOR BID – OCTOBER 1, 2019

Transcript of PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311...

Page 1: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PROJECT MANUAL

RETAINING WALL AT

POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514

FOR:

THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING COUNTY

305 WICK AVENUE, YOUNGSTOWN, OH 44503

OFFICERS OF THE LIBRARY BOARD OF TRUSTEES Dr. David Ritchie President Carole S. Weimer Vice President Mark J. Mrofchak Chief Financial officer Tina McBane Deputy Fiscal Officer Aimee Fifarek Executive Director

PREPARED BY: ms consultants, inc.

333 East Federal Street Youngstown, OH 44503

Phone: 330-744-5321 ms project No. 64-12A01

ISSUED FOR BID – OCTOBER 1, 2019

Page 2: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 3: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Table of Contents The Public Library of Youngstown & Mahoning County 00 01 10 - 1

SECTION 00 01 10

TABLE OF CONTENTS

PAGES

PROCUREMENT & CONTRACTING REQUIREMENTS GROUP

Division 00 – Procurement & Contracting Requirements Introductory Information

00 01 10 --- Table of Contents ---------------------------------------------------------------------------- 1 – 2 Procurement Requirements

00 11 13 --- Advertisement For Bids -------------------------------------------------------------------- 1 – 1 00 21 13 --- Instructions To Bidders --------------------------------------------------------------------- 1 – 12

Article 1 - Contract Information Article 2 - Bidding Procedures Article 3 - Bid Opening & Consideration of Bids Article 4 - Withdrawal of Bid Article 5 - Bid Estimate Article 6 - Bid Guaranty & Contract Bond Article 7 - Contract Award & Execution

00 31 32 --- Geotechnical Report – Intertek PSI ------------------------------------------------------- 1 - 26 00 41 16 --- Bid Form – Stipulated Sum – General Contract----------------------------------------- 1 – 4 00 43 13 --- Bid Guaranty & Performance Bond ------------------------------------------------------ 1 – 2 00 43 25 --- Proposed Equal Request Form ------------------------------------------------------------- 1 – 2 00 45 13 --- AIA A305 – Contractor’s Qualification Statement ------------------------------------- 1 – 4 00 45 19 --- Non Collusion Affidavit -------------------------------------------------------------------- - 1 – 00 45 36 --- Certificate of Non-Discrimination -------------------------------------------------------- - 1 –

Contracting Requirements 00 52 16 --- AIA A101 – Standard Form of Agreement Between Owner & Contractor --------- 1 – 8 00 52 16 --- AIA A101 – Exhibit A – Insurance & Bonds ------------------------------------------- 1 - 7 00 61 26 --- Warranty Bond ------------------------------------------------------------------------------- 1 - 2 00 62 16 --- Acord Certificate of Insurance ------------------------------------------------------------- - 1 – 00 62 18 --- Certification of Personal Property Tax -------------------------------------------------- - 1 – 00 62 21 --- Unresolved Findings for Recovery ------------------------------------------------------- - 1 – 00 62 76 --- AIA G702/3 – Application & Certificate for Payment --------------------------------- 1 – 2 00 63 13 --- Request For Interpretation Form (RFI) --------------------------------------------------- - 1 – 00 63 63 --- AIA G701 – Change Order Form --------------------------------------------------------- - 1 – 00 65 16 --- AIA G704 – Certificate of Substantial Completion ------------------------------------ - 1 – 00 65 19.13 AIA G706 – Contractor’s Affidavit of Payment of Debts & Claims ----------------- - 1 – 00 65 19.16 AIA G706A – Contractor’s Affidavit of Release of Liens ---------------------------- - 1 – 00 65 19.19 AIA G707 – Consent of Surety to Final Payment -------------------------------------- - 1 – 00 72 16 --- AIA 201 – General Conditions of the Contract for Construction --------------------- 1 – 39 00 73 13 --- Supplementary General Conditions ------------------------------------------------------- 1 – 9 00 73 46 --- Wage Rates ----------------------------------------------------------------------------------- - 1 -

Page 4: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Table of Contents The Public Library of Youngstown & Mahoning County 00 01 10 - 2

SPECIFICATIONS GROUP

GENERAL REQUIREMENTS SUBGROUP Division 01 - General Requirements

01 10 00 --- Summary of Work --------------------------------------------------------------------------- 1 – 2 01 20 00 --- Price & Payment Procedures --------------------------------------------------------------- 1 - 3 01 30 00 --- Administrative Requirements -------------------------------------------------------------- 1 – 3 01 32 16 --- Construction Progress Schedule ----------------------------------------------------------- 1 – 2 01 33 00 --- Submittal Procedures ----------------------------------------------------------------------- 1 – 4 01 40 00 --- Quality Requirements ----------------------------------------------------------------------- 1 – 4 01 50 00 --- Temporary Facilities & Controls ---------------------------------------------------------- 1 – 5 01 60 00 --- Product Requirements ---------------------------------------------------------------------- 1 – 3 01 70 00 --- Execution and Closeout Requirements --------------------------------------------------- 1 – 6

TECHNICAL SPECIFICATIONS

FACILITY CONSTRUCTION SUBGROUP – NOT USED

FACILITY SERVICES SUBGROUP – NOT USED

SITE AND INFRASTRUCTURE SUBGROUP

Division 31 – Not Used

Division 32 – Exterior Improvements 32 32 15 --- Precast Modular Block Gravity Retaining Wall ---------------------------------------- 1 – 7

Divisions 33 thru 35 – Not Used

PROCESS EQUIPMENT SUBGROUP – NOT USED

END OF SECTION

Page 5: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Advertisement For Bids The Public Library of Youngtown & Mahoning County 00 11 13 - 1

SECTION 00 11 13

ADVERTISEMENT FOR BIDS Sealed bids will be received by The Public Library of Youngstown & Mahoning County, 305 Wick Avenue, Youngstown, Ohio 44503 until noon, on Monday, October 14, 2019, and then publicly opened and read aloud for the construction of a new retaining wall at the Poland Public Library, 311 South Main Street, Poland, Ohio 44514. The work consists of removal of existing stone driveway retaining wall and retainage of existing stone at the Poland Library. Replacement of the existing driveway retaining wall with a new structural retaining wall including the installation of a new drainage system. Plans and specifications for the above project can be obtained from Roller Reprographics, 11907 Market Street, North Lima, OH 44452, between the hours of 8:30 a.m. and 4:30 p.m. (Monday through Friday). Phone: 330-549-0377. Each bidder must be a registered plan holder to be eligible to submit a bid for this project. All bids must be accompanied by a Bid Guaranty in the form of either: (1) a Bid Guaranty / Contract Bond for the full amount of the bid, or (2) a certified check, cashier’s check, or letter of credit pursuant to Chapter 1305, ORC, in the amount not

less than ten (10%) of the total amount of the bid pursuant to Chapter 153 of the Ohio Revised Code. The Bid Guaranty shall be made unconditionally payable to The Public Library of Youngstown & Mahoning County. Pre-Bid Meeting will be conducted at 9:00 a.m. on Tuesday, October 8, 2019 at the Poland Village Library, 311 South Main Street, Poland, Ohio 44514. Each individual employed by the Contractor any Sub-contractor and engaged in work on the project under this contract shall be paid the prevailing wage established by the Department of Industrial Relations of the State of Ohio. This shall occur regardless of any contractual relationship that may be said to exist between the Contractor or any Subcontractor and such individual. All contractors and sub-contractors involved with the project will, to the extent practicable, use Ohio products, materialism services, and labor in the implement of their project. Additionally, contractor compliance with Equal Employment Opportunity Requirements of Ohio Administrative Code Chapter 123 and the Governor’s Executive Order 84-9, shall be required. Each bid submitted must have a copy of a current Equal Employment Opportunity (EEO) Certificate of Compliance. The Non-Collusion Affidavit of Prime Bidders must be completed and submitted with all bids. All bids must be identified by marking a sealed envelope – “Retaining Wall – Poland Village Library”. The Owner reserves the right to accept or reject any and all bids, and to waive any informalities on the bids received. The Public Library of Youngstown & Mahoning County Advertise Dates: Tuesday, October 1, 2019 and Monday, October 7, 2019

Page 6: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 7: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 1

SECTION 00 21 13

INSTRUCTIONS TO BIDDERS

PLEASE READ THESE INSTRUCTIONS CAREFULLY. FAILURE TO COMPLY WITH THESE

INSTRUCTIONS MAY RESULT IN THE REJECTION OF YOUR BID.

ARTICLE 1 - CONTRACT INFORMATION

1.1 PROJECT SCHEDULING AND COORDINATION

1.1.1 The time for completion of the Project indicated on the Bid Form shall be the Project time

applicable to the Bidders.

1.1.2 The General Contractor shall be responsible for scheduling the Project, coordinating the

Contractors, and providing other services identified in the Contract Documents. Critical path

scheduling methods shall be provided.

1.1.3 The award of separate Contracts for the Project requires sequential, coordinated and otherwise

interrelated Contractor operations and may involve delays in the progress of any individual

Contractor’s Work. The Contractor with whom the Public Library of Youngstown &

Mahoning County executes a Contract shall assume the status of third party beneficiary to the

Contract of each other Contractor performing Work on the Project.

1.1.4 The Bidder agrees that the bid amount shall cover all expenses due from The Public Library

of Youngstown & Mahoning County resulting from interference, disruption, hindrance or

delay caused by or between Contractors or their agents and employees.

1.1.5 The Bidder agrees that the Bidder will make no claim against The Public Library of

Youngstown & Mahoning County for additional compensation or mitigation of Liquidated

Damages for any such interference, disruption, hindrance or delay, and will accept as full

satisfaction an extension of time which may be provided by The Public Library of

Youngstown & Mahoning County.

1.2 GIVING NOTICE

1.2.1 When any period of time is referred to in the Contract Documents by days, it shall be

computed to exclude the first and include the last day of such period. If the last day of any

such period falls on a Saturday, Sunday, or a legal holiday, such day will be omitted from the

computation and such period shall be deemed to end on the next succeeding day which is not

a Saturday, Sunday, or legal holiday.

1.3 USE OF FACSIMILE TRANSMISSION

1.3.1 Any notice required to be given shall be effective if provided by facsimile transmission, but

such notice shall not be considered official until the original signed document is delivered

pursuant to paragraph ITB 1.3.

Page 8: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 2

1.3.2 Withdrawal of a bid by facsimile transmission will be ineffective unless an original signed

document is received by The Public Library of Youngstown & Mahoning County within two

(2) days of receipt of the facsimile transmission.

ARTICLE 2 - BIDDING PROCEDURES

2.1 EXAMINATION OF CONTRACT DOCUMENTS AND PROJECT SITE

2.1.1 The Bidder shall examine all Contract Documents, including without limitation the Drawings

and Specifications for all divisions of Work for the Project, noting particularly all

requirements which will affect the Bidder’s Work in any way.

2.1.2 Failure of a Bidder to be acquainted with the amount and nature of Work required to complete

any applicable division of the Work, in conformity with all requirements of the Project as a

whole, will not be considered as a basis for additional compensation.

2.1.3 The Bidder shall evaluate the Project site and related Project conditions where the Work will

be performed, including without limitation the following:

2.1.3.1 The condition, layout and nature of the Project site and surrounding area;

2.1.3.2 The availability and cost of labor;

2.1.3.3 The cost of materials, supplies and equipment;

2.1.3.4 The cost of temporary utilities required in the bid;

2.1.3.5 The cost of any permit or license required by a local or regional authority having

jurisdiction over the Project;

2.1.3.7 The generally prevailing climatic conditions;

2.1.3.6 Conditions bearing upon transportation, disposal, handling and storage of materials.

2.2 PRE-BID MEETING

2.2.1 Pre-Bid Meeting date, time and location are specified in Section 00 11 13 – Advertisement

For Bids.

2.3 INTERPRETATION

2.3.1 If the Bidder finds any perceived conflict, error, omission or discrepancy on or between the

Drawings and Specifications, or any of the Contract Documents, the Bidder shall submit a

written request to the Architect for an interpretation or clarification.

2.3.1.1 The Bidder shall be responsible for prompt delivery of such request.

Page 9: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 3

2.3.1.2 In order to prevent an extension of the bid opening, Bidders shall submit all requests

for interpretation to the Architect no later than noon. on Wednesday, October 9,

2019.

2.3.2 The Architect shall issue an Addendum, no later than 72 hours prior to the bid opening,

excluding Saturdays, Sundays and legal holidays, to any and all requests for interpretation of

the Contract Documents and provide a copy to each person of record holding Drawings and

Specifications.

2.3.2.1 The Addenda shall be deemed to have been validly given if the Addenda is issued

and mailed or otherwise furnished to each person of record holding Drawings and

Specifications, pursuant to Section 153.12 ORC. Bidder’s are responsible for

securing a copy of any and all Addenda.

2.3.3 Any interpretation of the Contract Documents made by any party other than the Architect, or

in any manner other than a written Addendum, shall not be binding and the Bidder shall not

rely upon any such interpretation.

2.3.4 The Bidder shall not, at any time after the execution of the Contract, be compensated for a

claim alleging insufficient data, incomplete Contract Documents, or incorrectly assumed

conditions regarding the nature or character of the Work, if no request for interpretation was

made by the Bidder prior to the bid opening.

2.4 STANDARDS

2.4.1 The articles, devices, materials, equipment, forms of construction, fixtures and other items

named in the Specifications to denote kind and quality shall be known as Standards and all

bids shall be based upon those Standards.

2.4.2 Where two or more Standards are named, the Bidder may furnish any one of those Standards.

2.4.3 Items which are not Standards may be used only if accepted pursuant to the requirements of

paragraph ITB 2.5.

2.5 PROPOSED EQUALS

2.5.1 If the Bidder proposes to use an article, device, material, equipment, form of construction,

fixture or other item other than those Standards named, the Bidder shall certify that the item is

equal in quality, and all aspects of performance and appearance, to the Standards specified.

2.5.2 In addition, the Bidder shall submit information to the Architect no later than noon on

Wednesday, October 9, 2019 which information shall include:

2.5.2.1 The name and a complete description of the proposed Equal, including Drawings,

performance and test data, and other information necessary for a complete evaluation.

2.5.2.2 A statement setting forth any changes which the proposed Equal will require in the

Project.

Page 10: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 4

2.5.3 If the Architect approves the proposed Equal as a Standard, the Architect shall, no later than

72 hours prior to the bid opening, excluding Saturdays, Sundays and legal holidays, issue an

Addendum to all Bidders.

2.5.4 If the Architect does not approve the Proposed Equal, the Architect shall inform the Bidder of

the disapproval in writing, no later than 72 hours prior to the bid opening, excluding

Saturdays, Sundays and legal holidays, stating the reason for the disapproval, which decision

shall be final. The Architect shall have the discretion to reject a Proposed Equal for the

reason that the Bidder failed to provide sufficient information to enable the Architect to

completely evaluate the Proposed Equal without delay in the scheduled bid opening.

2.5.5 No consideration shall be given to any Proposed Equal unless submitted to the Architect by

the dates and times specified above.

2.6 BID FORM

2.6.1 Each bid shall be submitted on the Bid Form in a sealed envelope clearly marked as

containing a bid, indicating the Project name on the envelope and the discipline(s) being bid.

2.6.1.1 Any change, alteration or addition in the wording of the Bid Form may cause a bid to

be rejected as nonresponsive.

2.6.1.2 Unless the Bidder withdraws the bid as provided in Article 4 hereof, the Bidder will

be required to comply with all requirements of the Contract Documents, regardless of

whether the Bidder had actual knowledge of the requirements and regardless of any

statement or omission made by the Bidder which might indicate a contrary intention.

2.6.2 The Bidder shall fill in all relevant blank spaces in the Bid Form in ink or by typewriting and

not in pencil.

2.6.2.1 The Bidder shall show all bid amounts in both words and figures. In the case of a

conflict between the words and figures, the amount shown in words shall govern,

where such words are not ambiguous. When the Bidder’s intention and the meaning

of the words are clear, omissions or misspellings of words will not render the words

ambiguous.

2.6.2.2 Any alteration or erasure of items filled in on the Bid Form shall be initialed by the

Bidder.

2.6.3 When an Alternate is listed on the Bid Form, the Bidder shall fill in the applicable blank with

an increased or decreased bid amount. The Public Library of Youngstown & Mahoning

County reserves the right to accept or reject any or all bids on Alternates, in whole or in part,

and in any order.

2.6.3.1 If no change in the bid amount is required, indicate “No Change” or $0 dollars.

2.6.3.2 A blank entry or an entry of “No Bid,” “N/A”, or similar entry on any Alternate will

cause the bid to be rejected as nonresponsive only if that Alternate is selected.

Page 11: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 5

2.6.3.3 If an Alternate is not selected, an entry as listed in paragraph ITB 2.6.3.2 on that

Alternate will not, by itself, render a bid nonresponsive.

2.6.4 If the Bidder is a corporation, partnership or sole proprietorship, an officer, partner or

principal of the Bidder, as applicable, shall print or type the legal name of the Bidder on the

line provided and sign the Bid Form. All signatures must be original.

2.6.5 The Bid Form of the Bidder with whom The Public Library of Youngstown & Mahoning

County executes a Contract shall be incorporated into the Contract as if fully rewritten

therein.

2.7 REQUIRED SUBMITTALS WITH BID FORM

2.7.1 The bid may be rejected as nonresponsive if the Bidder fails to submit the following

submittals with the Bid Form in a sealed envelope:

2.7.1.1 A signed Bond meeting the requirements of Section 153.54 to 153.57, ORC;

2.7.1.2 Power of Attorney of the agent signing for the Surety;

2.7.1.3 Non-Collusion Affidavit. The Bidder will be required to submit a Non-Collusion

Affidavit in the form included in the bid package. This Affidavit shall be executed

and dated before the opening of bids and must accompany the proposal.

2.7.1.4 Unresolved Findings for Recovery

2.7.1.5 Certificate of Non-Discrimination.

2.7.1.6 Contractor’s Qualification Statement.

2.7.2 To expedite the execution of the Contract, it is recommended that the Bidder submit all of the

following with the Bid Form:

2.7.2.1 To support a Bond, a Certificate of Compliance issued by the Department of

Insurance, showing the Surety is licensed to do business in Ohio;

2.7.2.2 Ohio Workers’ Compensation Certificate;

2.7.2.3 If the Bidder is a foreign corporation, i.e., not incorporated under the laws of Ohio, a

Certificate of Good Standing from the Secretary of State showing the right of the

Bidder to do business in the State; or, if the Bidder is a person or partnership, the

Bidder has filed with the Secretary of State a Power of Attorney designating the

Secretary of State as the Bidder’s agent for the purpose of accepting service of

summons in any action brought under Section 153.05, ORC, or under Sections

4123.01 to 4123.94, inclusive, ORC.

2.8 DECLARATION OF PERSONAL PROPERTY TAX AFFIDAVIT

2.8.1 The successful bidder shall be required to execute and submit an affidavit, directed to The

Public Library of Youngstown & Mahoning County, and executed in duplicate. The

Page 12: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 6

successful bidder shall use the affidavit form provided in the project manual. The affidavit

shall be executed and returned within five (5) days of receipt of same by the contractor. The

Ohio Revised Code requires that the affidavit become a part of the contract document, and

also provides that no payment shall be made on any contract for which no such affidavit has

been filed.

2.9 INDEMNITY OF THE OWNER BY THE CONTRACTOR

2.9.1 The Contractor agrees to indemnify The Public Library of Youngstown & Mahoning County

individually and their respective officers, employees and agents from any loss, damage or

expense which any of them may suffer or incur as a result of the bodily injury, sickness,

disease or death of any person, for the damage (including loss of use) of any property, arising

from any negligent act or omission of the Contractor or a sub-contractor or anyone employed

by either of them and from any liens filed by a sub-contractor or materialman.

2.10 PERMITS

2.10.1 The Architect shall furnish to the General Contractor, free of charge, the building permits

approved by the Mahoning County Building Department for the General Contractor to

maintain at the Project site.

2.11 BACKGROUND DRAWINGS

2.11.1 Contractors requiring background drawings will be charged $100.00 per drawing with a

maximum charge of $500.00.

ARTICLE 3 - BID OPENING AND CONSIDERATION OF BIDS

3.1 DELIVERY OF BIDS

3.1.1 It is the responsibility of the Bidder to submit the bid prior to the time scheduled for bid

submission.

3.1.2 If the bid envelope is enclosed in another envelope for the purpose of delivery, the exterior

envelope shall be clearly marked as containing a bid, the Project name and the date of the bid

opening shown on the envelope.

3.1.3 No bid shall be considered if it arrives after the time set for the bid submission.

3.2 BID OPENING

3.2.1 Sealed bids will be received at the office designated in the Advertisement For Bid until the

time stated.

3.2.2 Bids will be publicly opened and read thereafter at Poland Village Library. The public

opening and reading of bids is for informational purposes only and is not to be construed as

an acceptance or rejection of any bid submitted.

Page 13: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 7

3.2.3 The contents of the bid envelope shall be a public record and open for inspection, upon

request, at any time after the bid opening.

3.3 BID OPENING EXTENSION

3.3.1 If any Addendum is issued within 72 hours prior to the published time for the bid opening,

excluding Saturdays, Sundays and legal holidays, the bid opening shall automatically be

extended one (1) week, with no further advertising required, pursuant to Section 153.12,

ORC.

3.4 BID EVALUATION CRITERIA

3.4.1 The Public Library of Youngstown & Mahoning County reserves the right to accept or reject

any or all bids, in whole or in part, and reserves the right to accept or reject any or all

Alternates.

3.4.2 The bid of any Bidder who engages in collusive bidding shall be rejected.

3.4.3 The Public Library of Youngstown & Mahoning County reserves the right to allow any

Bidder a reasonable opportunity to cure a minor irregularity or technical deficiency in a bid,

provided the irregularity or deficiency does not affect the bid amount or otherwise give the

Bidder a competitive advantage.

3.5 BID EVALUATION PROCEDURE

3.5.1 The Contract will be awarded to the most responsible and responsive Bidder as determined at

the discretion of The Public Library of Youngstown & Mahoning County. The following

procedures shall be followed by the Board.

3.5.1.1 In determining which Bidder is the most responsible and responsive, the Board shall

consider the Base Bids and any Alternate or Alternates, if applicable, which the

Board determines to accept.

3.5.1.2 The total of the accepted Alternate(s), if applicable, will be added to the Total Base

Bid for the purpose of determining the most responsible and responsive Bidder.

3.5.1.3 If two Bidders submit the same bid amount and both are determined to be

responsible, the Board reserves the right to select one Bidder by the flip of a coin,

which shall be conducted in the presence of both Bidders and shall be final.

3.5.2 A Bidder for a Contract shall be considered the most responsible and responsive if the

Bidder’s bid responds to the Contract Documents in all material respects and contains no

irregularities or deviations from the Contract Documents which would affect the amount of

the bid or otherwise give the Bidder a competitive advantage.

3.5.2.1 In accordance with Section 9.311, ORC, the bid shall be rejected as nonresponsive if

the Bond is executed by a Surety not licensed in Ohio.

3.5.2.2 If the most responsible and responsive Bidder is not responsive, such Bidder shall be

notified according to paragraph ITB 3.6.

Page 14: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 8

3.5.3 In determining whether a Bidder is responsible, factors to be considered include, without

limitation:

3.5.3.1 The experience of the Bidder;

3.5.3.2 The financial condition of the Bidder;

3.5.3.3 The conduct and performance of the Bidder on previous contracts and prevailing

wage laws;

3.5.3.4 The facilities of the Bidder;

3.5.3.6 The management skills of the Bidder;

3.5.3.7 The ability of the Bidder to execute the Contract properly;

3.5.3.8 The evaluation of a bid below the median of other bids pursuant to paragraph ITB

5.1;

3.5.3.9 A Bidder who submits a bid for Work as a mechanical contractor, i.e., for electrical,

plumbing, heating and ventilating, or air conditioning and refrigeration, may be

required to submit evidence of one of the following:

1) A valid Contractor’s license from an OBC certified county, municipal or

health department that required a test to obtain such license;

2) Certification by the Ohio Construction Industry Examining District; or

3) Registration of certification by an OBC municipality or county for the

preceding consecutive five (5) years, pursuant to demonstration of proof of

bonding and insurance.

3.5.4 The Board shall obtain from the most responsible and responsive Bidder any information the

Board deems appropriate to the consideration of factors showing responsibility. If the most

responsible and responsive Bidder is responsible, the Contract shall be awarded to such

Bidder unless all bids are rejected.

3.5.5 If the most responsible and responsive Bidder is not responsible, and all bids are not rejected,

the Board shall follow the procedure set forth in paragraph ITB 3.5.4 with each next most

responsible and responsive Bidder until the Contract is awarded, all bids are rejected or all

responsive Bidders are determined to be not responsible.

3.6 REJECTION OF BIDS BY THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

COUNTY

3.6.1 If the most responsible and responsive Bidder is not responsive or responsible, the Board shall

reject such bid and notify the Bidder in writing by certified mail of the finding and the reasons

for finding that the Bidder is not responsive or responsible.

Page 15: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 9

3.6.2 A Bidder who is notified in accordance with paragraph ITB 3.6.1 may object to such Bidder’s

rejection by filing a written protest which must be received by the Board within five (5) days

of the notification provided pursuant to paragraph ITB 3.6.1.

3.6.3 Upon receipt of a timely protest, the Board shall meet with the protesting Bidder to hear the

Bidder’s objections.

3.6.3.1 No award of the Contract shall become final until after the Board has met with all

Bidders who have timely filed protests and the award of the Contract is affirmed by

the Board.

3.6.3.2 If all protests are rejected at the Board’s discretion, the award of the Contract shall be

affirmed by the Board or all bids shall be rejected.

3.7 NOTICE OF AWARD

3.7.1 The Board shall notify the apparent successful Bidder that upon satisfactory compliance with

all conditions precedent for Contract execution, within the time specified, the Bidder will be

awarded the Contract.

3.7.2 The Board reserves the right to rescind the award of any Contract, before the execution of said

Contract by all parties, without any liability against the Owner.

ARTICLE 4 - WITHDRAWAL OF BID

4.1 WITHDRAWAL OF BID AFTER OPENING

4.1.1 In accordance with Section 9.31, ORC, a Bidder may withdraw a bid from consideration after

the bid opening if the bid amount was substantially lower than the amounts of other bids,

providing the bid was submitted in good faith, and the reason for the bid amount being

substantially lower was a clerical mistake, as opposed to a judgment mistake, and was actually

due to an unintentional and substantial arithmetic error or an unintentional omission of a

substantial quantity of Work, labor or material made directly in the compilation of the bid

amount.

4.2.1.1 Notice of a request to withdraw a bid must be made in writing filed with the Board

within two (2) business days after the bid opening.

4.2.1.2 No bid may be withdrawn under paragraph ITB 4.2.1.1 when the result would be the

awarding of the Contract on another bid to the same Bidder.

4.1.2 If a bid is withdrawn under authority of paragraph ITB 4.2.1.1, the Board may award the

Contract to the next most responsible and responsive Bidder or reject all bids and advertise

for other bids. In the event the Board advertises for other bids, the withdrawing Bidder shall

pay the costs, in connection with the rebidding, of printing new Contract Documents, required

advertising and printing and mailing notices to prospective Bidders, if the Board finds that

such costs would not have been incurred but for such withdrawal.

Page 16: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 10

ARTICLE 5 - BID ESTIMATE

5.1 If the low Bidder is more than 20 percent below the median of all other bids, excluding the price of the

low bid, received for a Contract where the estimate is $100,000 or more, and if the low Bidder is more

than 25 percent below the median of all other bids, excluding the price of the low bid, received for a

Contract where the estimate is less than $100,000, the following procedures shall be followed.

5.1.1 The Architect conducts an interview with the Bidder, the purpose of which is to determine

what, if anything, has been overlooked in the bid, and to analyze the process planned by the

Bidder to complete the Work. The Architect shall submit a written summary of the interview

to the Board.

5.1.2 The Bidder submits a certified financial statement and a list of recent public contracts which

the Bidder has performed to the Board.

5.1.3 The Board reviews and approves the Bidder’s responsibility pursuant to paragraph ITB 3.5.3.

ARTICLE 6 - BID GUARANTY AND PERFORMANCE BOND

6.1 BID GUARANTY

6.1.1 The Bidder must file with the bid a Bond, payable to The Public Library of Youngstown &

Mahoning County in the form of either:

6.1.1.1 A signed Bond meeting the requirements of Section 153.54(B), ORC, for the amount

of the Base Bid plus add Alternates; or

6.1.1.2 A signed Bond in the form of a certified check, cashier’s check or letter of credit, as

provided in Section 153.54(C), ORC. Any letter of credit shall be revocable only by

the Department of Insurance. The amount of the certified check, cashier’s check, or

letter of credit shall be equal to ten (10) percent of the Base Bid plus add Alternates.

6.1.2 The Bond shall serve as an assurance that the Bidder will, upon acceptance of the bid, comply

with all conditions precedent for Contract execution, within the time specified by the Board.

6.1.3 If the blank line on the Bond form is not filled in, the penal sum will be the full amount of the

Base Bid plus add Alternates. If the blank line is filled in, the amount must not be less than

the full amount of the Base Bid plus add Alternates, stated in dollars and cents. A percentage

is not acceptable, pursuant to Section 153.571, ORC.

6.1.4 The Bond must be signed by an authorized agent, with Power of Attorney, from a Surety.

The Bond must be issued by a Surety authorized by the Department of Insurance to transact

business in Ohio.

6.1.5 The requirements of Section 3905.41, ORC, may be applicable to require the Bond be

countersigned by an Ohio resident agent. The Bidder shall determine the applicability of this

provision.

Page 17: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 11

6.1.6 Bonds will be returned to all unsuccessful Bidders 60 days after the bid opening. If used, a

certified check, cashier’s check or letter of credit will be returned to the successful Bidder

upon providing the Bond required by Section 153.54(C), ORC.

6.2 BOND FORFEITURE

6.2.1 If for any reason, other than as authorized by paragraph ITB 4.1.1 or paragraph ITB 6.3, the

Bidder fails to enter into a Contract, and the Board awards the Contract to the next most

responsible and responsive Bidder, the Bidder who failed to enter into a Contract shall be

liable to the Board for the difference between such Bidder’s bid and the bid of the next most

responsible and responsive Bidder or for the penal sum not to exceed ten (10) percent of the

bid amount, whichever is less, pursuant to Section 153.54, ORC.

6.2.2 If the Board then awards a Contract to such next most responsible and responsive Bidder and

such Bidder also fails or refuses to enter into a Contract, the liability of such next most

responsible and responsive Bidder shall, except as provided in paragraph ITB 6.3, be the

amount of the difference between the bid amounts of such next most responsible and

responsive Bidder and the third most responsible and responsive Bidder, but not in excess of

the liability specified in paragraph ITB 4.1.2 Liability on account of an award to any most

responsible and responsive Bidder beyond the third most responsible and responsive Bidder

shall be determined in like manner, pursuant to Section 153.54, ORC.

6.2.3 If the Board does not award the Contract to the next most responsible and responsive Bidder

but resubmits the Project for bidding, the Bidder failing to enter into the Contract shall,

except as provided in paragraph ITB 6.3, be liable to the Board for a penal sum not to exceed

ten (10) percent of such Bidder’s bid amount or the costs in connection with the resubmission,

of printing new Contract Documents, required advertising and printing and mailing notices to

prospective Bidders, whichever is less, pursuant to Section 153.54, ORC.

6.3 PERFORMANCE BOND

6.3.1 If the Bidder enters into a Contract, the Bidder shall, at the time of signing the Contact,

provide a Performance Bond, unless the Bidder previously submitted a Bid with a Bid

Guaranty/Performance Bond at the time of Bid meeting the requirements of Section 153.54,

ORC.

6.3.2 The Bond shall be in the full amount of the Contract to indemnify the Board against all direct

and consequential damages suffered by failure of the Contractor to perform according to the

provisions of the Contract and in accordance with the plans, details, specifications and bills of

material therefore and to pay all lawful claims of Subcontractors, Material Suppliers, and

laborers for labor performed or materials furnished in carrying forward, performing or

completing the Contract.

6.3.3 The Public Library of Youngstown & Mahoning County shall be co-obligees on the Bond.

ARTICLE 7 - CONTRACT AWARD AND EXECUTION

7.1 The award and execution of the Contract is based upon the expectation that the most responsible and

responsive Bidder will comply with all conditions precedent for Contract execution within ten (10)

days of the date of the Notice of Award.

Page 18: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 12

7.1.1 Noncompliance with the conditions precedent for Contract execution within ten (10) days of

the date of the Notice of Award shall be cause for the Board to cancel the Notice of Award

and award the Contract to the next most responsible and responsive Bidder or resubmit the

Contract for bidding, at the discretion of the Board. The Board may extend the time for

submitting the conditions precedent for Contract execution for good cause shown. No

extension shall operate as a waiver of the conditions precedent for Contract execution.

7.2 Pursuant to Section 153.12, ORC, the failure to award and execute the Contract within 60 days of the

bid opening invalidates the entire bid process and all bids submitted, unless the time is extended by

written consent of the Bidder whose bid the Board has accepted, and concurrence of the Board with

such extensions.

7.2.1 If the Contract is awarded within 60 days of the bid opening, any increases in material, labor

and subcontract costs shall be borne by the Bidder without alteration of the amount of the bid.

7.2.2 If the cause of the failure to execute the Contract within 60 days of the bid opening is due to

matters for which the Board is solely responsible, the Contractor shall be entitled to a Change

Order authorizing payment of verifiable increased costs in materials, labor or subcontracts.

7.2.3 If the cause of the failure to execute the Contract within 60 days of the bid opening is due to

matters for which the Contractor is responsible, no request for increased costs will be granted.

7.3 CONDITIONS PRECEDENT FOR EXECUTION OF CONTRACT

7.3.1 Performance Bond. To support the Bond, a Certificate of Compliance issued by the

Department of Insurance, showing the Surety is licensed to do business in Ohio;

7.3.2 Warranty Bond.

7.3.3 Ohio Workers’ Compensation Certificate;

7.3.4 Declaration of Personal Property Tax Delinquency;

7.3.5 Certificate of Insurance (ACORD form is acceptable) and copy of additional insured

endorsement. The Department reserves the right to request a certified copy of the

Contractor’s insurance policies;

7.3.6 If the Bidder is a foreign corporation, i.e., not incorporated under the laws of Ohio, a

Certificate of Good Standing showing the right of the Bidder to do business in the State; or, if

the Bidder is a person or partnership, the Bidder has filed with the Secretary of State a Power

of Attorney designating the Secretary of State as the Bidder’s agent for the purpose of

accepting service of summons in any action brought under Section 153.05, ORC, or under

Sections 4123.01 to 4123.94, inclusive, ORC.

7.4 The Board shall issue the Contractor a Notice to Proceed which shall establish the date for

commencement of the Project time. The Contractor shall, within ten (10) days of the Notice to

Proceed, furnish the Architect the following submittals:

7.4.1 Contract Cost Breakdown;

7.4.2 List of subcontractors applicable to this project.

7.4.3 List of manufacturer’s applicable to this project.

Page 19: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Instructions To Bidders

The Public Library and Youngstown & Mahoning County 00 21 13 - 13

7.5 RIGHT TO ACCEPT OR REJECT PROPOSALS

7.5.1 The Board may consider informal any bid which is not prepared and submitted in accordance

with the provisions of these instructions. The Board reserves the right to reject any or all bids,

to waive any informalities or irregularities in the bids received, and to accept any bid which is

deemed most favorable to the Board.

END OF INSTRUCTIONS TO BIDDERS

Page 20: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 21: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Geotechnical Report The Public Library of Youngstown & Mahoning County 00 31 32 – i

SECTION 00 31 32

GEOTECHNICAL REPORT

PREPARED BY

INTERTEK PSI

DATED: SEPTEMBER 9, 2019

Page 22: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 23: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

Professional Service Industries, Inc. 1280 Trumbull Ave., Girard, OH 44420

(330) 759-0288 (P)

September 9, 2019

ms consultants, inc. 333 East Federal Street Youngstown, Ohio 44503 Attn: Ms. Annissa Neider, AIA, NCARB Re: Geotechnical Engineering Exploration Report

Proposed Retaining Wall & Drainage System

Poland Library 311 S. Main Street Poland, OH PSI Project No. 01393060

Dear Ms. Neider:

Per your request, Professional Service Industries, Inc. (PSI) is pleased to submit this Geotechnical Engineering Services Report for the above referenced project. Included in this presentation are the results of the subsurface exploration and recommendations concerning the design and construction of the proposed retaining wall and drainage system the Poland Library, 311 S. Main Street, Poland, Mahoning County, Ohio. We appreciate the opportunity to have provided you with our geotechnical engineering services and look forward to participation in the construction phase of this project. If you have any questions concerning this report or if we may be of further service in any manner, please contact our office. Respectfully submitted, PROFESSIONAL SERVICE INDUSTRIES, Inc.

Scott Hynes Alagaiya Veeramani, P.E. Branch Manager Director

Page 24: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 25: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

Subsurface Exploration Report

For the

Proposed Retaining Wall & Drainage System Poland Library

311 S. Main Street Poland, Mahoning County, Ohio

Prepared for

ms consultants, inc. 333 East Federal Street Youngstown, OH 44503

Scott Hynes Branch Manager

Prepared by

Professional Service Industries, Inc. 1280 Trumbull Avenue

Girard, OH 44420

A. Veeramani, P.E. Director/Principal Consultant

PSI Project No. 01393060

Page 26: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 27: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

TABLE OF CONTENTS

1 PROJECT INFORMATION ....................................................................................................................... 1 1.1 PROJECT AUTHORIZATION ............................................................................................................... 1 1.2 PROJECT DESCRIPTION ..................................................................................................................... 1 1.3 PURPOSE AND SCOPE OF SERVICES ................................................................................................. 1

2 GEOLOGY AND OBSERVATION OF THE REPORT ..................................................................................... 2 2.1 SITE LOCATION AND DESCRIPTION .................................................................................................. 2 2.2 SITE GEOLOGY .................................................................................................................................. 2 2.3 FIELD DRILLINGOPERATIONS ........................................................................................................... 3 2.4 LAB TESTING ..................................................................................................................................... 3

3 FINDINGS............................................................................................................................................. 3 3.1 BORINGS........................................................................................................................................... 3 3.2 GROUND WATER CONDITION .......................................................................................................... 4

4 ANALYSIS AND RECOMENDATIONS ...................................................................................................... 5 4.1 RETAINING WALL DESIGN ................................................................................................................ 5 4.2 PAVEMENT SUBGRADE PREPARATION ............................................................................................ 5 4.3 PAVEMENT DRAINAGE AND MAINTENANCE ................................................................................... 6

5 CONSTRUCTION CONSIDERATIONS ....................................................................................................... 6 5.1 DRAINAGE AND GROUNDWATER CONSIDERATIONS ...................................................................... 6 5.2 FEDERAL EXCAVATION SAFETY REGULATIONS ................................................................................ 6

6 GEOTECHNICAL RISK ............................................................................................................................ 8 7 REPORT LIMITATIONS .......................................................................................................................... 8 FIGURES FIGURE 1 – SITE VICINITY MAP FIGURE 2 – SOIL BORING LOCATION PLAN LIST OF APPENDICES APPENDIX A – BORING LOGS AND SYMBOLS APPENDIX B – LABORATORY TEST RESULTS APPENDIX C – GENERAL NOTES AND UNIFIED SOIL CLASSIFICATION

Page 28: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 29: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PSI Project No.: 01393060 Proposed Retaining Wall and Drainage System – Poland Library

September 9, 2019

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

1 PROJECT INFORMATION

1.1 PROJECT AUTHORIZATION

The following Table summarizes (in chronological order) the Project Authorization history for the services performed and represented in this report by Professional Service Industries, Inc. (PSI):

PROJECT TITLE: PROPOSED DOLLAR GENERAL

Document / Reference No. Date Requested/Provided By

Request for Proposal 07/22/2019 Ms. Annissa Neider, AIA, NCARB

PSI Proposal No.: 0139-284650 07/23 2019 Scott Hynes & Alagaiya Veeramani of PSI, Inc.

Project Authorization 08/21/2019 Ms. Annissa Neider, AIA, NCARB

1.2 PROJECT DESCRIPTION

According to the provided information and documents, PSI understands that the project is to consist of the construction of a new retaining wall and drainage system at the Poland Library, located at 311 S. Main Street, Poland, Mahoning County, Ohio. Specifically, the new retaining wall will replace the existing cut stone retaining wall which runs along the property’s northeastern boundary, along Yellow Creek. The new drainage system is planned to be located in the northern portion of the parking area. Currently, the site area consists of an asphalt paved parking area with a gravel walking path located between the parking area and the existing retaining wall. The existing parking lot slopes from south to north, with approximately 2-feet of elevation difference across the parking lot. The water level of Yellow Creek is approximately 3 to 4-feet below existing parking lot elevations. Proposed site grading, type and height of the proposed retaining wall and the proposed size and depth of the drainage system were not was available at the time of this report. The geotechnical recommendations presented in this report are based on the available project information, the proposed location and orientation of the retaining wall on the site, and the subsurface materials described in this report. If any of the information noted above is incorrect, please inform PSI in writing so that we may amend the recommendations presented in this report if necessary. PSI will not be responsible for the implementation of its recommendations when it is not notified of changes in the project.

1.3 PURPOSE AND SCOPE OF SERVICES

The purpose of this exploration was to evaluate the soil, rock and groundwater conditions at the site to provide recommendations, from a geotechnical engineering viewpoint, for retaining wall design soil parameters, and other construction considerations. PSI’s contracted scope of services included drilling three (3) soil test borings at the site, one boring in the area of the planned drainage system, and two (2) test borings for the proposed new retaining wall structure. The test borings were drilled to depths of ranging from 13’-10” to 15’-5” below the existing ground surface, select laboratory testing, and preparation of this geotechnical engineering report. This report briefly outlines the testing procedures, presents available project information, describes the site and subsurface conditions, and presents recommendations regarding the following:

Page 30: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PSI Project No.: 01393060 Proposed Retaining Wall and Drainage System – Poland Library

September 9, 2019

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

This report briefly outlines the testing procedures, presents available project information, describes the site and subsurface conditions, and presents recommendations regarding the following:

• Review of geologic setting

• Design soil parameters for retaining wall

• Design parameters for pavement design

• Comments regarding factors that could impact construction and performance of the proposed construction The scope of services did not include an environmental assessment for determining the presence or absence of wetlands, or hazardous or toxic materials in the soil, bedrock, surface water, groundwater, or air on, below, or around this site. Any statements in this report or on the boring logs regarding odors, colors, and unusual or suspicious items or conditions are strictly for informational purposes. PSI’s geotechnical scope also did not include any service to investigate or detect the presence of moisture, mold or other biological contaminants in or around any structure, or any service that was designed or intended to prevent or lower the risk of the occurrence or the amplification of the same. Client should be aware that mold is ubiquitous to the environment with mold amplification occurring when building materials are impacted by moisture. Client should be aware that site conditions are outside of PSI’s control, and that mold amplification will likely occur, or continue to occur, in the presence of moisture. As such, PSI cannot and shall not be held responsible for the occurrence or reoccurrence of mold amplification.

2 GEOLOGY AND OBSERVATION OF THE REPORT

2.1 SITE LOCATION AND DESCRIPTION

The site for the proposed new retaining wall and drainage system are located within the parking area of the Poland Library, located at 311 S. Main Street, Poland, Mahoning County, Ohio. The site Latitude and Longitude is

approximately N 41.023429° and W 80.610824, respectively. Currently, the existing retaining wall along the property’s northeastern boundary with Yellow Creek consists of large cut stone, while the parking area is paved with asphalt concrete. Based on elevations estimated from Google Earth, the surface elevation in the vicinity of the test borings ranged from approximately 1003 to 1005 feet above mean sea level within the parking area, while the elevation of the creek is approximately 999 MSL. The boring elevations provided in this report are approximate. If required by others, the precise test boring elevations and locations should be determined in the field by a professional surveyor.

2.2 SITE GEOLOGY

Based on the glacial and physiographic geologic maps for Ohio, the unconsolidated deposits of loam sheets consist of ground moraine of the Lavery Till from the Wisconsinan Age over Mississippian-age shales, siltstones, sandstones, coal, and limestones of the Pottsville and Allegheny Formation. Information obtained from the Ohio Department of Natural Resources (ODNR) website also indicated that no known abandoned mine was recorded in the vicinity of the site area. “Known and Probable Karst in Ohio” map published by ODNR indicates that no Karst (sink hole) is recorded in the vicinity of the project site.

Page 31: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PSI Project No.: 01393060 Proposed Retaining Wall and Drainage System – Poland Library

September 9, 2019

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

2.3 FIELD DRILLINGOPERATIONS

As discussed in the Purpose and Scope of Services section, a total of three (3) test borings within the proposed retaining wall area. The test boring was drilled to depths of about 13’-10’ to 15’-5” below the existing surface grades. The approximate boring locations are shown on the Boring Location Plan presented in the Appendix of this report. The borings were advanced into the ground using hollow stem augers mounted on an ATV/truck mounted drill rig. The split spoon sampling procedures used during this exploration are in basic accordance with Ohio Department of Transportation Specifications for Subsurface Exploration section 303.7 (Type E1).

2.4 LAB TESTING

The soil samples obtained during the field exploration were transported to the laboratory and visually examined. The soil samples obtained from the drilling operation were tested for moisture content (ASTM D2216), Atterberg limits (ASTM D4318) and grain size analyses (ASTM D6913), The samples were classified in general accordance with the Unified Soil Classification System (USCS). Descriptions and lab test data of the soils encountered in the test boring is provided on the Boring Log included in the Appendix. Groundwater conditions, standard penetration resistances, and other pertinent information are also included. The soil test borings were advanced utilizing 4¼ inch inside diameter, hollow stem auger drilling methods. During the test boring sampling procedure, standard penetration tests were performed at regular intervals to obtain the standard penetration value of the soil. The standard penetration value (N) is defined as the number of blows (“blow counts”) of a 140-pound hammer free falling 30 inches, required to advance the split-spoon sampler a distance of 1 foot into the soil at each sampling increment. The sampler is lowered to the bottom of the drill hole and the number of blows recorded for each of 3 successive increments of 6-inch penetration. The "N" value is obtained by adding the second and third incremental blow count results. The results of the standard penetration test indicate the relative density and comparative consistency of the soils, and thereby provide a basis for estimating the relative strength and compressibility of the soil profile constituents. Select soil samples were later tested in the laboratory to obtain soil material properties for the foundation recommendations. Drilling, sampling, and laboratory testing was accomplished in general accordance with ASTM procedures.

3 FINDINGS

3.1 BORINGS

The subsurface conditions at the project site were explored with three (3) soil test borings drilled within the designated area of the proposed new retaining wall and drainage system. Specifically, two (2) borings were advanced in the area of the proposed retaining wall and one (1) boring was advanced in the area of the planned drainage system. The three (3) test borings within the retaining wall and drainage system area were terminated at depths ranging from 13’-10’ to 15’-5” below existing site grades. The boring locations and depths were determined by ms consultants, inc. and reviewed by PSI prior to drilling. PSI personnel marked the borings in the field using conventional measuring devices, using information derived from our site meeting. PSI recommends that the surface elevations at the boring locations be surveyed prior to construction activities. At the time of PSI’s field activities, the ground surface in the area of the planned drainage system was covered with approximately 8-inches of asphalt pavement, underlain by approximately 24-inches of crushed limestone

Page 32: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PSI Project No.: 01393060 Proposed Retaining Wall and Drainage System – Poland Library

September 9, 2019

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

and slag on top of a layer of geo-fabric. While the ground surface at the area of the proposed retaining wall consisted about 3-inches of sand and gravel. Beneath the asphalt pavement, aggregate base and sand and gravel surface cover, the test borings generally disclosed natural soils extending to depths ranging from approximately 5.5 to 8 feet below existing grade. Based on results of visual classification and select laboratory testing, the soils are classified as Sandy Silty Clay (CL-ML), sandy silt (ML), and Silty Sand (SM) in general accordance with the Unified Soil Classification System (USCS). The standard penetration N-values generally indicate consistencies of stiff within the cohesive soils, and loose to medium dense relative density within the granular soils, based on the Standard Penetration tests. Below the natural soils at test boring locations B-1, the areas bottommost formation encountered consisted of soft to moderately hard weathered sandstone, underlain by interbedded limestone, siltstone and shale. Below the natural soils at test borings B-2, and B-3, the areas bottommost formation encountered consisted of soft to moderately hard weathered sandstone, containing thin coal seams. The above subsurface descriptions are of a generalized nature to highlight the major subsurface stratification features and material characteristics. The boring logs included in the Appendix should be reviewed for specific information at individual boring locations. These records include soil descriptions, stratifications, penetration resistances, and locations of the samples and laboratory test data. The stratifications shown on the boring logs represent the conditions only at the actual boring locations. Variations may occur and should be expected between boring locations. The stratifications represent the approximate boundary between subsurface materials and the actual transition may be gradual. Water level information obtained during field operations is also shown on these boring logs. The samples that were not altered by laboratory testing will be retained for 60 days from the date of this report and then will be discarded.

3.2 GROUND WATER CONDITION

Groundwater was encountered in PSI’s in all three (3) test borings, B-1 thru B-3, during drilling at depths ranging from 4.5 to 7 feet below existing site grades. All three (3) test borings, B-1 thru B-3, were rock cored utilizing water, therefore water readings at the completion of drilling were not recorded. No cave-ins were noted during drillin goperations. Please note that with the proximity of the proposed construction to Yellow Creek, the granular soils observed at this site, and the interface between the soils and bedrock can discharge significant quantities of groundwater into excavations for foundations and utilities. It should also be noted that the groundwater levels at this site, as well as perched water levels and volumes, will fluctuate significantly based on variations in rainfall, snowmelt, evaporation, surface run-off and other related hydrogeologic factors. The groundwater levels in boreholes are often not representative of the actual groundwater level because the boreholes remained open for a relatively short time. The water level measurements presented in this report are the levels that were measured at the time of PSI’s field activities.

Page 33: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PSI Project No.: 01393060 Proposed Retaining Wall and Drainage System – Poland Library

September 9, 2019

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

4 ANALYSIS AND RECOMENDATIONS

4.1 RETAINING WALL DESIGN

The specific type of the proposed retaining wall has not been determined at this time. However, based on the site conditions observed, it is assumed that the planned retaining wall will be supporting soils to a maximum height of approximately 10 feet; therefore, this wall members should be designed as retaining structures. Backfill should consist of granular soils. It is understood that the final surface grades behind the wall will be level with the top of wall. For evaluating the various loading conditions, the following values of the soil parameters and coefficients of lateral earth pressures may be adopted: Total weight of soil, 120 pcf Buoyant weight of soil, 58 pcf

Angle of Internal Friction for 30 (Cohesionless Backfill) Active Coefficient, 0.33 Equivalent Fluid Pressure, 40 pcf (at active) Base Friction Coefficient, 0.35 Allowable Toe Bearing Pressure, soil 2,000 psf Allowable Toe Bearing Pressure, rock 4,000 psf All footings must be placed at a minimum depth of 42 inches below the flow line of the creek in order to protect against frost action. Extreme care should be taken to prevent weakening of the foundation bearing materials because of prolonged atmospheric exposure, construction activity disturbance or an increase in moisture content. A blanket of freely draining materials at least 2 feet thick, or synthetic drain is to be placed against the back face of the walls along their full length. The wall drainage sand or synthetic drain, such as Enkadrain, should be capped with a 2-foot thick layer of cohesive materials to prevent direct surface water ingress. Once the walls are built, over compaction of the materials against the walls is to be avoided under all circumstances so as to prevent undue lateral earth pressures.

4.2 PAVEMENT SUBGRADE PREPARATION

PSI’s scope of services did not include sampling and California Bearing Ratio (CBR) testing of existing subgrade soils or potential sources of imported fill for the specific purpose of a detailed pavement analysis. Instead, this report outlines recommended procedures for pavement subgrade preparation. Based on past experience with silty clay glacial drift soils (i.e. the type of soils encountered at this site) a minimum CBR value of 4 can likely be achieved by preparing the pavement subgrade as outlined in the Site Preparation section of this report. PSI recommends that the moisture content of the subgrade should be maintained between –2% and +3% of the optimum at the time of paving. It may require rework when the subgrade is either excessively desiccated or excessively wet. Fill material, if needed to establish the required pavement grade, must be performed in accordance with the procedures outlined in the Site Preparation section of this report. The edges of compacted fill should extend a minimum 2 feet beyond the edges of the pavement, or a distance equal to the depth of fill beneath the pavement, whichever is greater. Construction traffic should be minimized to prevent unnecessary disturbance of the pavement subgrade. Disturbed areas, as verified by PSI, should be removed and replaced with properly compacted material.

Page 34: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PSI Project No.: 01393060 Proposed Retaining Wall and Drainage System – Poland Library

September 9, 2019

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

Asphalt Pavement Section The granular base course should be built at least 2 feet wider than the pavement on each side to support the tracks of the slipform paver. This extra width is structurally beneficial for wheel loads applied at pavement edge. The asphalt binder course should be compacted to a range of 93.0% to 97.4% of the Maximum Theoretical Density as determined by ASMT D2041. Asphaltic surface mixture should be compacted to a range of 92.5% to 97.4% of the Maximum Theoretical Density as determined by ASTM D2041. Asphaltic concrete mix designs should be reviewed to determine if they are consistent with the recommendations given in this report.

4.3 PAVEMENT DRAINAGE AND MAINTENANCE

PSI recommends pavements be sloped to provide rapid surface drainage. Water allowed to pond on or adjacent to the pavement could saturate the subgrade and cause premature deterioration of the pavements, and removal and replacement may be required. Consideration should be given to the use of interceptor drains to collect and remove water collecting in the granular base. Interceptor drains could be incorporated with the storm drains located within the pavement areas. Periodic maintenance of the pavement should be anticipated. This should include sealing of cracks and joints and by maintaining proper surface drainage to avoid ponding of water on or near the pavement areas. Underdrains, sub-drains and under slab drains will not prevent moisture vapor that can cause mold growth.

5 CONSTRUCTION CONSIDERATIONS

5.1 DRAINAGE AND GROUNDWATER CONSIDERATIONS

Groundwater was encountered at the test boring location during drilling operations to the depths about 4.5 to 7 feet below the existing surface grades. However, groundwater levels can change and could be encountered during foundation excavation and construction. If groundwater is encountered during excavation, a gravity drainage system, sump pump or other conventional dewatering procedure, as deemed necessary by the field conditions, should be implemented throughout construction such that the groundwater is controlled and maintained at an elevation of at least 2 feet below the excavation bottom at all times. Every effort should be made to keep the excavations dry if water is encountered.

5.2 FEDERAL EXCAVATION SAFETY REGULATIONS

In Federal Register, Volume 54, No. 209 (October, 1989), the United States Department of Labor, Occupational Safety and Health Administration (OSHA) amended its "Construction Standards for Excavations, 29 CFR, Part 1926, Subpart P." This document was issued to better insure the safety of workers entering trenches or excavations. It is mandated by this federal regulation that all excavations, whether they be utility trenches, basement excavations or foundation excavations, be constructed in accordance with the new OSHA guidelines. It is our understanding that these regulations are being strictly enforced. If they are not followed closely, the owner and the contractor could be liable for substantial penalties.

Page 35: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PSI Project No.: 01393060 Proposed Retaining Wall and Drainage System – Poland Library

September 9, 2019

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

The contractor is solely responsible for designing and constructing stable, temporary excavations and should shore, slope, or bench the sides of the excavations as required to maintain stability of both the excavation sides and bottom. The contractor's "responsible person" as defined in "CFR Part 1926," should evaluate the soil exposed in the excavations as part of the contractor's safety procedures. In no case should slope height, slope inclination, or excavation depth, including utility trench excavation depth, exceed those specified in local, state, and federal safety regulations. We are providing this information solely as a service to our client. PSI is not assuming responsibility for construction site safety or the contractor's activities; such responsibility is not being implied and should not be inferred. If the excavations are left open and exposed to the elements for a significant length of time, desiccation of the clays may create minute shrinkage cracks which could allow large pieces of clay to collapse or slide into the excavation. Materials removed from the excavation should not be stockpiled immediately adjacent to the excavation, inasmuch as this load may cause a sudden collapse of the embankment.

Page 36: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PSI Project No.: 01393060 Proposed Retaining Wall and Drainage System – Poland Library

September 9, 2019

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

6 GEOTECHNICAL RISK

The concept of risk is an important aspect of the geotechnical exploration. The primary reason for this is that the analytical methods used to develop geotechnical recommendations do not comprise an exact science. The analytical tools which geotechnical engineers use are generally empirical and must be used in conjunction with engineering judgment and experience. Therefore, the solutions and recommendations presented in the geotechnical exploration should not be considered risk-free and, more importantly, are not a guarantee that the interaction between the soils and the proposed structure will perform as planned. The engineering recommendations presented in the preceding section constitutes PSI’s professional estimate of those measures that are necessary for the proposed structure to perform according to the proposed design based on the information generated and referenced during this exploration, and PSI’s experience in working with these conditions.

7 REPORT LIMITATIONS

The recommendations submitted in this report are based on the available subsurface information developed by PSI and on the design, information furnished by Ms. Annissa Neider, AIA, NCARB, Project Manager of ms consultants, inc for the proposed project. If there are any revisions to the plans for the proposed project, or if deviations from the subsurface conditions noted in this report are encountered during construction, PSI should be retained to determine if changes in the recommendations are required. If PSI is not retained to perform these functions, PSI will not be responsible for the impact of those conditions on the geotechnical recommendations for the project. The Geotechnical Engineer warrants that the findings, recommendations, specifications, or professional advice contained herein, have been presented after being prepared in accordance with generally accepted professional engineering practice in the fields of foundation engineering, soil mechanics and engineering geology. No other warranties are implied or expressed. After the plans and specifications are complete, it is recommended that PSI be provided the opportunity to review the final design drawings and specifications, in order to verify that the earthwork and foundation recommendations are properly interpreted and implemented. At that time, it may be necessary to submit supplementary recommendations. This report has been prepared for the exclusive use of ms consultants, inc. for the specific application to the proposed retaining wall and drainage system project for the Poland Library, located at 311 S. Main Street, Poland, Mahoning County, Ohio.

Page 37: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PSI Project No.: 01393060 Proposed Retaining Wall and Drainage System – Poland Library

September 9, 2019

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

FIGURES

FIGURE No. 1 Site Vicinity Map FIGURE No. 2 Soil Boring Location Plan

Page 38: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 39: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

Professional Service Industries, Inc.

PROJECT NO. : 01393060

PROJECT: POLAND LIBRARY RETAINING WALL

LOCATION: 311 S. MAIN STREET POLAND, OHIO1280 Trumbull Avenue, Suite B, Girard, OH 44420Site Vicinity Plan

phone 330-759-0288 fax 330-759-0923

NORTHSITE AREA

Page 40: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 41: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

Professional Service Industries, Inc.

PROJECT NO. : 01393060

PROJECT: POLAND LIBRARY RETAINING WALL

LOCATION: 311 S. MAIN STREET POLAND, OHIO

1280 Trumbull Avenue, Suite B, Girard, OH 44420 Boring Location Planphone 330-759-0288 fax 330-759-0923

B-1

B-2

B-3

NORTH

Page 42: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 43: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PSI Project No.: 01393060 Proposed Retaining Wall and Drainage System – Poland Library

September 9, 2019

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

APPENDIX A – BORING LOGS AND SYMBOLS

Page 44: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 45: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

1

2

3

45

6

7

17

18

0

52

1

55

Asphalt

FILL

ML

WeatheredSandstone

InterbeddedLimestone

11

20

0

14

20

7

LL = 20PL = 18

8" AsphaltMedium Dense, moist, gray, Slag andLimestone with Geo-Fabric (FILL)

Loose to Medium Dense, moist, gray, SandySilt (ML)

Soft, gray and black, Weathered Sandstonewith Coal fragments

Interbedded Limestone (50%), Siltstone(40%), Shale (10%)Limestone: gray, slightly weathered tomoderately weathered, strong, slightyfractured, slightly fossiliferous; ranges inthickness from 0.4' to 1.5'

Siltstone: light gray, severely weathered, toslightly weathered, weak to strong, fractured,calcareous; thickness of 2'

Shale: dark gray, slightly weathered tomoderately weathered, slightly strong,laminated to very thin, highly fractured,slightly fossiliferous; ranges in thickness from0.2' to 0.3'

Core Data: Run # - 10' 5"' to 15' 5" Recovery - 92% Longest Piece - 18" RQD - 58%@ 11' Qu = 7,300 psi

End of Boring @ 15' 5"

Water Encountered @ 4' 6"

19-12-8N=20

1-2-1N=3

5-9-10N=19

50/5"50/3"

50/1"

PROJECT NO.: 01393060PROJECT: Poland Library Retaining Wall

Dep

th, (

feet

)

STRENGTH, tsf

AdditionalRemarks

US

CS

Cla

ssifi

catio

n

0

Qp

Sam

ple

Typ

e

2.0

0

Moi

stur

e, %

MoistureMATERIAL DESCRIPTION

STANDARD PENETRATIONTEST DATA

N in blows/ft

Qu

Sam

ple

No.

Gra

phic

Log

50

PL

Ele

vatio

n (f

eet)

LL

4.0

25

Rec

over

y (in

ches

)

While Drilling

Upon Completion

Delay

1000

995

990

LATITUDE:LONGITUDE:

LOCATION: S. Main Street

feet

4.5 feet

Wat

er

DRILLER: Kevin Little

Professional Service Industries, Inc.1280 Trumbull AvenueGirard, OH 44420Telephone: (330) 759-0288 Poland, Ohio

SP

T B

low

s pe

r 6-

inch

(S

S)

DATE STARTED: 8/27/19

BENCHMARK: N/A

The stratification lines represent approximate boundaries. The transition may be gradual. Sheet 1 of 1

DRILL COMPANY: Ridgeway Drilling, Inc.

STATION: N/A OFFSET: N/A

LOGGED BY: Mike WirtzDRILL RIG: Truck D-50

REVIEWED BY: Scott Hynes

EFFICIENCY N/A Parking LotHAMMER TYPE: Automatic BORING LOCATION:

0

5

10

15

DATE COMPLETED: 8/27/19 BORING B-1

ELEVATION: 1004.675 ft

COMPLETION DEPTH 15.4 ft

N/ADRILLING METHOD: Hollow Stem AugerSAMPLING METHOD: 2-in SS

REMARKS:

>>>>

>>

>>

Page 46: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

1

2

3

4

5

21

18

15

5

59

Sandand

Gravel

CL-ML

SM

WeatheredSandstone

Sandstone

10

22

11

7

3" Sand and GravelStiff, moist, brown, Sandy Silty Clay, tracerock fragments (CL-ML)

Loose to Medium Dense, moist, gray andblack, Silty Sand with Coal fragments (SM)

Medium Hard to Moderately Hard, gray,coarse, Weathered Sandstone

Sandstone: gray and black, slightlyweathered, slightly to moderately strong,coarse grained, laminated to thin bedded,moderately fractured to fractured, containsthin coal layers.

Core Data: Run #1 - 9' to 14' Recovery - 98% Longest Piece - 18" RQD - 52%

@ 9.75' Qu = 3,650 psi

End of Boring @ 14'

Water Encountered @ 7'

5-9-5-7

5-3-7

8-12-50/3"

50/6"

PROJECT NO.: 01393060PROJECT: Poland Library Retaining Wall

Dep

th, (

feet

)

STRENGTH, tsf

AdditionalRemarks

US

CS

Cla

ssifi

catio

n

0

Qp

Sam

ple

Typ

e

2.0

0

Moi

stur

e, %

MoistureMATERIAL DESCRIPTION

STANDARD PENETRATIONTEST DATA

N in blows/ft

Qu

Sam

ple

No.

Gra

phic

Log

50

PL

Ele

vatio

n (f

eet)

LL

4.0

25

Rec

over

y (in

ches

)

While Drilling

Upon Completion

Delay

1005

1000

995

LATITUDE:LONGITUDE:

LOCATION: S. Main Street

feet

7 feet

Wat

er

DRILLER: Kevin Little

Professional Service Industries, Inc.1280 Trumbull AvenueGirard, OH 44420Telephone: (330) 759-0288 Poland, Ohio

SP

T B

low

s pe

r 6-

inch

(S

S)

DATE STARTED: 8/27/19

BENCHMARK: N/A

The stratification lines represent approximate boundaries. The transition may be gradual. Sheet 1 of 1

DRILL COMPANY: Ridgeway Drilling, Inc.

STATION: N/A OFFSET: N/A

LOGGED BY: Mike WirtzDRILL RIG: Truck D-50

REVIEWED BY: Scott Hynes

EFFICIENCY N/A Rivers EdgeHAMMER TYPE: Automatic BORING LOCATION:

0

5

10

DATE COMPLETED: 8/27/19 BORING B-2

ELEVATION: 1005.685 ft

COMPLETION DEPTH 14.0 ft

N/ADRILLING METHOD: Hollow Stem AugerSAMPLING METHOD: 2-in SS

REMARKS:

>>

>>

>>

>>

>>

Page 47: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

1

2

3

4

5

20

17

18

4

55

Sandand

Gravel

CL-ML

SM

WeatheredSandstone

WeatheredSandstoneInterbedded

withCoal

10

24

14

12

Non-Plastic

3" Sand and GravelStiff, moist, brown, Sandy Silty Clay, tracerock fragments (CL-ML)

Loose, moist, brown and black, Silty Sand(SM)

Soft to Moderately Hard, gray, coarse,Weathered Sandstone

Sandstone: gray and black, slightlyweathered, slightly to moderately strong,coarse grained, laminated to thin bedded,moderately fractured to fractured, containsvery thin to thin coal layers

Core Data: Run #1 - 8' 10" to 13' 10" Recovery - 92% Longest Piece - 7" RQD - 18%

@ 10.25' Qu = 4,220 psi

End of Boring @ 13' 10"

Water encountered @ 4' 6"

5-6-5-3N=11

5-4-3N=7

5-5-6N=11

50/4"

PROJECT NO.: 01393060PROJECT: Poland Library Retaining Wall

Dep

th, (

feet

)

STRENGTH, tsf

AdditionalRemarks

US

CS

Cla

ssifi

catio

n

0

Qp

Sam

ple

Typ

e

2.0

0

Moi

stur

e, %

MoistureMATERIAL DESCRIPTION

STANDARD PENETRATIONTEST DATA

N in blows/ft

Qu

Sam

ple

No.

Gra

phic

Log

50

PL

Ele

vatio

n (f

eet)

LL

4.0

25

Rec

over

y (in

ches

)

While Drilling

Upon Completion

Delay

1005

1000

995

LATITUDE:LONGITUDE:

LOCATION: S. Main Street

feet

4.5 feet

Wat

er

DRILLER: Kevin Little

Professional Service Industries, Inc.1280 Trumbull AvenueGirard, OH 44420Telephone: (330) 759-0288 Poland, Ohio

SP

T B

low

s pe

r 6-

inch

(S

S)

DATE STARTED: 8/27/19

BENCHMARK: N/A

The stratification lines represent approximate boundaries. The transition may be gradual. Sheet 1 of 1

DRILL COMPANY: Ridgeway Drilling, Inc.

STATION: N/A OFFSET: N/A

LOGGED BY: Mike WirtzDRILL RIG: Truck D-50

REVIEWED BY: Scott Hynes

EFFICIENCY N/A Rivers EdgeHAMMER TYPE: Automatic BORING LOCATION:

0

5

10

DATE COMPLETED: 8/27/19 BORING B-3

ELEVATION: 1005.944 ft

COMPLETION DEPTH 13.8 ft

N/ADRILLING METHOD: Hollow Stem AugerSAMPLING METHOD: 2-in SS

REMARKS:

>>

>>

Page 48: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 49: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PSI Project No.: 01393060 Proposed Retaining Wall and Drainage System – Poland Library

September 9, 2019

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

APPENDIX B – LABORATORY RESULTS

Page 50: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 51: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

75

80

85

90

95

100

0.0010.010.1110100

2

Clay Size < 0.002 mm

Sandy Silt (ML)

Silty Sand (SM)

COBBLES

14

Specimen Identification

Specimen Identification

PI Cc

D10

41 3/4 100 140

U.S. SIEVE OPENING IN INCHES

3

D60

0.071

0.177

7

4.75

0.012

0.087 0.01

200

fine

GRAIN SIZE DISTRIBUTION

20 301.5

coarse medium

3.5

3.5

Classification

D100

50

60.8

23.5

18

NP

2

NP

6

Cu

fine

SANDSILT OR CLAY

GRAVEL

1/23/8

HYDROMETER

3

GRAIN SIZE IN MILLIMETERS

PE

RC

EN

T F

INE

R B

Y W

EIG

HT

40

U.S. SIEVE NUMBERS

4

B-1

B-3

LL PL

18.00

6 810

%Gravel %Sand %Silt %Clay

B-1

B-3 4.38

60

coarse

D30

3.5

3.5

16

20

NP

38.7

76.5

0.5

0.0

Project:PSI Job No.:Location:

Poland Library Retaining Wall01393060S. Main StreetPoland, Ohio

Professional Service Industries, Inc.

1280 Trumbull Avenue

Girard, OH 44420

Telephone: (330) 759-0288

Fax: (330) 759-0923

Page 52: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 53: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

0

10

20

30

40

50

60

0 20 40 60 80 100

LL

PSI Job No.:Project:Location:

01393060Poland Library Retaining WallS. Main StreetPoland, Ohio

Fines

PLASTICITY

INDEX

CL

2

NP

20

NP

PI

CH

CL-ML

Classification (*Visual)

ML

Boring Depth (ft) PL

LIQUID LIMIT

MH

60.8

23.5

Sandy Silt (ML)

Silty Sand (SM)

ATTERBERG LIMIT RESULTS

18

NP

Professional Service Industries, Inc.

1280 Trumbull Avenue

Girard, OH 44420

Telephone: (330) 759-0288

Fax: (330) 759-0923

3.5

3.5

B-1

B-3

Page 54: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 55: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

PSI Project No.: 01393060 Proposed Retaining Wall and Drainage System – Poland Library

September 9, 2019

---------------------------------------------------------------------------------------------------------------------------------------------------

www.intertek.com/building

APPENDIX C – GENERAL NOTES AND UNIFIED SOIL CLASSIFICATON

Page 56: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 57: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

GENERAL NOTES

SAMPLE IDENTIFICATION

SOIL PROPERTY SYMBOLS

SFA:

HSA:

M.R.:

R.C.:H.A.:P.A.:

DescriptionFlat:

Elongated:Flat & Elongated:

DescriptionAngular:

Subangular:

Subrounded:

Rounded:

Criteria Particles with width/thickness ratio > 3Particles with length/width ratio > 3Particles meet criteria for both flat andelongated

Descriptive TermTrace:

With:Modifier:

Size Range Over 300 mm (>12 in.)75 mm to 300 mm (3 in. to 12 in.)19 mm to 75 mm (¾ in. to 3 in.)4.75 mm to 19 mm (No.4 to ¾ in.)2 mm to 4.75 mm (No.10 to No.4)0.42 mm to 2 mm (No.40 to No.10)0.075 mm to 0.42 mm (No. 200 to No.40)0.002 mm to 0.075 mm<0.002mm to <0.005 mm depending on agency

Component Boulders:Cobbles:

Coarse-Grained Gravel:Fine-Grained Gravel:

Coarse-Grained Sand:Medium-Grained Sand:

Fine-Grained Sand:Silt:

Clay:

SS:

ST:BS:PM:

CPT-U:

ANGULARITY OF COARSE-GRAINED PARTICLESRELATIVE DENSITY OF COARSE-GRAINED SOILS

N - Blows/foot

0 - 44 - 1010 - 3030 - 5050 - 80

80+

Relative Density

Very LooseLoose

Medium DenseDense

Very DenseExtremely Dense

Split-Spoon - 1 3/8" I.D., 2" O.D., except wherenoted.Shelby Tube - 3" O.D., except where noted.Bulk SamplePressuremeterCone Penetrometer Testing with Pore-PressureReadings

DRILLING AND SAMPLING SYMBOLS

RELATIVE PROPORTIONS OF FINES% Dry Weight

< 5%5% to 12%

>12%

Page 1 of 2

The Unified Soil Classification System (USCS), AASHTO 1988 and ASTM designations D2487 and D-2488 areused to identify the encountered materials unless otherwise noted. Coarse-grained soils are defined as havingmore than 50% of their dry weight retained on a #200 sieve (0.075mm); they are described as: boulders,cobbles, gravel or sand. Fine-grained soils have less than 50% of their dry weight retained on a #200 sieve;they are defined as silts or clay depending on their Atterberg Limit attributes. Major constituents may be addedas modifiers and minor constituents may be added according to the relative proportions based on grain size.

Standard "N" penetration: Blows per foot of a 140 pound hammer falling 30 inches on a 2-inch O.D.Split-Spoon.A "N" penetration value corrected to an equivalent 60% hammer energy transfer efficiency (ETR)Unconfined compressive strength, TSFPocket penetrometer value, unconfined compressive strength, TSFMoisture/water content, %Liquid Limit, %Plastic Limit, %Plasticity Index = (LL-PL),%Dry unit weight, pcfApparent groundwater level at time noted

Criteria Particles have sharp edges and relatively planesides with unpolished surfacesParticles are similar to angular description, but haverounded edgesParticles have nearly plane sides, but havewell-rounded corners and edgesParticles have smoothly curved sides and no edges

N:

N60:Qu:Qp:

w%:LL:PL:PI:

DD:, ,

Solid Flight Auger - typically 4" diameter flights,except where noted.Hollow Stem Auger - typically 3¼" or 4¼ I.D.openings, except where noted.Mud Rotary - Uses a rotary head with Bentoniteor Polymer SlurryDiamond Bit Core SamplerHand AugerPower Auger - Handheld motorized auger

GRAIN-SIZE TERMINOLOGY PARTICLE SHAPE

Page 58: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

GENERAL NOTES

QU - TSF N - Blows/foot Consistency

0 - 22 - 44 - 8

8 - 1515 - 3030 - 50

50+

Criteria Absence of moisture, dusty, dry to the touchDamp but no visible waterVisible free water, usually soil is below water table

RELATIVE PROPORTIONS OF SAND AND GRAVEL% Dry Weight

< 15%15% to 30%>30%

Descriptive TermTrace:

With:Modifier:

0 - 0.250.25 - 0.500.50 - 1.001.00 - 2.002.00 - 4.004.00 - 8.00

8.00+

MOISTURE CONDITION DESCRIPTION

Page 2 of 2

CONSISTENCY OF FINE-GRAINED SOILS

DescriptionBlocky:

Lensed:Layer:Seam:

Parting:

DescriptionStratified:

Laminated:

Fissured:

Slickensided:

STRUCTURE DESCRIPTION

QU - TSF

Extremely SoftVery Soft

SoftMedium Hard

Moderately HardHard

Very Hard

SCALE OF RELATIVE ROCK HARDNESS ROCK BEDDING THICKNESSESConsistency

Criteria Alternating layers of varying material or color withlayers at least ¼-inch (6 mm) thickAlternating layers of varying material or color withlayers less than ¼-inch (6 mm) thickBreaks along definite planes of fracture with littleresistance to fracturingFracture planes appear polished or glossy,sometimes striated

Criteria Greater than 3-foot (>1.0 m)1-foot to 3-foot (0.3 m to 1.0 m)4-inch to 1-foot (0.1 m to 0.3 m)1¼-inch to 4-inch (30 mm to 100 mm)½-inch to 1¼-inch (10 mm to 30 mm)1/8-inch to ½-inch (3 mm to 10 mm)1/8-inch or less "paper thin" (<3 mm)

DescriptionDry:

Moist:Wet:

DescriptionVery Thick Bedded

Thick BeddedMedium Bedded

Thin BeddedVery Thin BeddedThickly LaminatedThinly Laminated

2.5 - 1010 - 50

50 - 250250 - 525

525 - 1,0501,050 - 2,600

>2,600

(Continued)

Component Very Coarse Grained

Coarse GrainedMedium Grained

Fine GrainedVery Fine Grained

GRAIN-SIZED TERMINOLOGY(Typically Sedimentary Rock)

ROCK VOIDSVoids

PitVug

CavityCave

Void Diameter <6 mm (<0.25 in)6 mm to 50 mm (0.25 in to 2 in)50 mm to 600 mm (2 in to 24 in)>600 mm (>24 in)

ROCK QUALITY DESCRIPTIONRQD Value

90 -10075 - 9050 - 7525 -50

Less than 25

Size Range >4.76 mm2.0 mm - 4.76 mm0.42 mm - 2.0 mm0.075 mm - 0.42 mm<0.075 mm

Rock generally fresh, joints stained and discolorationextends into rock up to 25 mm (1 in), open joints maycontain clay, core rings under hammer impact.

Rock mass is decomposed 50% or less, significantportions of the rock show discoloration andweathering effects, cores cannot be broken by handor scraped by knife.

Rock mass is more than 50% decomposed, completediscoloration of rock fabric, core may be extremelybroken and gives clunk sound when struck byhammer, may be shaved with a knife.

Rock Mass DescriptionExcellent

GoodFairPoor

Very Poor

DEGREE OF WEATHERINGSlightly Weathered:

Weathered:

Highly Weathered:

Criteria Cohesive soil that can be broken down into smallangular lumps which resist further breakdownInclusion of small pockets of different soilsInclusion greater than 3 inches thick (75 mm)Inclusion 1/8-inch to 3 inches (3 to 75 mm) thickextending through the sampleInclusion less than 1/8-inch (3 mm) thick

Very SoftSoft

Firm (Medium Stiff)Stiff

Very StiffHard

Very Hard

Page 59: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

OH

CH

MH

OL

CL

ML

SC

SM

SP

COARSEGRAINED

SOILS

SW

TYPICALDESCRIPTIONS

WELL-GRADED GRAVELS, GRAVEL -SAND MIXTURES, LITTLE OR NOFINES

POORLY-GRADED GRAVELS,GRAVEL - SAND MIXTURES, LITTLEOR NO FINES

SILTY GRAVELS, GRAVEL - SAND -SILT MIXTURES

LETTERGRAPHSYMBOLSMAJOR DIVISIONS

SOIL CLASSIFICATION CHART

PT

GC

GM

GP

GW

CLAYEY GRAVELS, GRAVEL - SAND -CLAY MIXTURES

WELL-GRADED SANDS, GRAVELLYSANDS, LITTLE OR NO FINES

POORLY-GRADED SANDS,GRAVELLY SAND, LITTLE OR NOFINES

SILTY SANDS, SAND - SILTMIXTURES

CLAYEY SANDS, SAND - CLAYMIXTURES

INORGANIC SILTS AND VERY FINESANDS, ROCK FLOUR, SILTY ORCLAYEY FINE SANDS OR CLAYEYSILTS WITH SLIGHT PLASTICITY

INORGANIC CLAYS OF LOW TOMEDIUM PLASTICITY, GRAVELLYCLAYS, SANDY CLAYS, SILTY CLAYS,LEAN CLAYS

ORGANIC SILTS AND ORGANICSILTY CLAYS OF LOW PLASTICITY

INORGANIC SILTS, MICACEOUS ORDIATOMACEOUS FINE SAND ORSILTY SOILS

INORGANIC CLAYS OF HIGHPLASTICITY

ORGANIC CLAYS OF MEDIUM TOHIGH PLASTICITY, ORGANIC SILTS

PEAT, HUMUS, SWAMP SOILS WITHHIGH ORGANIC CONTENTS

CLEANGRAVELS

GRAVELS WITHFINES

CLEAN SANDS

(LITTLE OR NO FINES)

SANDS WITHFINES

LIQUID LIMITLESS THAN 50

LIQUID LIMITGREATER THAN 50

HIGHLY ORGANIC SOILS

GRAVELAND

GRAVELLYSOILS

(APPRECIABLEAMOUNT OF FINES)

(APPRECIABLEAMOUNT OF FINES)

(LITTLE OR NO FINES)

FINEGRAINED

SOILS

SANDAND

SANDYSOILS

SILTSAND

CLAYS

SILTSAND

CLAYS

MORE THAN 50%OF MATERIAL ISLARGER THANNO. 200 SIEVE

SIZE

MORE THAN 50%OF MATERIAL ISSMALLER THANNO. 200 SIEVE

SIZE

MORE THAN 50%OF COARSEFRACTION

PASSING ON NO.4 SIEVE

MORE THAN 50%OF COARSEFRACTION

RETAINED ON NO.4 SIEVE

NOTE: DUAL SYMBOLS ARE USED TO INDICATE BORDERLINE SOIL CLASSIFICATIONS

Page 60: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

P Plot instersection of PI and LL as determined by Atterberg Limits Tests.

L Data points above A LINE indicated Clay soils, those below the A LINE

A indicate Silt.

S 70

T

I 60

C (A LINE)

I 50 CH

T CL ( Clays )

Y 40

I 30

N

D 20

E

X 10

7

(Pl, %) 0 4

0 10 20 30 40 50 60 70 80 90 100

Cu = D 60 1 < Cc =

D 10

above A Line, PI > 7

Cu = D 60 1 < Cc =

D 10

below A Line, PI < 4

above A Line, PI > 7

( Silts )

dual symbols( CL - ML )

silty clays, lean clays

Inorganic clays of high plasticity fat clays

OL Organic silts and organic silty clays of low plasticity

MH

CH

OH

Pt

Inorganic silts, micaceous or diatomaceous fine sandy or silty soils, plastic

silts

Organic clays of medium to high plasticity

Peat and other highly organic soils

MH or OH

SM

GM

GC

GP Does not meet all requirements for GW

Clayey gravels, gravel-sand-clay

mixtures

ML or clayey silts with slight plasticity

Inorganic silts, very fine sands, rock flour, silty or clayey fine sands

Inorganic clays of low to medium plasticity, gravelly clays, sandy clays,

CL

ASTM Designation D - 2487

Based upon percentage of material

Less than 5% GW, GP, SW, SP

passing No. 200 sieve classify as:

United Soil Classification System

More than 12%

5% to 12%

GM, GC, SM, SC

< 3GW

Well graded gravels, gravel-

sand mixtures, little or no fines

Borderline, use

LIQUID LIMIT (LL, %)

ML or OL

on No.4 sieve)

than 50% retained

> 4

D 10 * D 60

sand mixtures, little or no fines

[ D 30 ] 2

below A Line, PI < 4

in shaded area

4 < PI < 7

Gravels (More

Silty gravels, gravel-sand-silt

mixtures

Poorly graded gravels, gravel-

Dual Symbols

mixtures

Well graded sands, gravelly

sands, little or no fines

Poorly graded sands, gravelly

sands, little or no fines

in shaded area

Dual Symbols

4 < PI < 7

> 6 [ D 30 ] 2

D 10 * D 60

< 3

Does not meet all requirements for SW

200 sieve)

Silty sands, sand-silt mixtures

Clayey sands, sand-clay

Sands (More

than 50% passing

a No. 4 sieve)

SC

SW

SP

Coarse Grained

Soils

(More than half of

is larger than No.

Highly Organic

Soil

Silts & Clays

(LL greater than 50)

Silts & Clays

(LL less than 50)

than No. 200 sieve)

material is smaller

(More than half of

Fine Grained

Soils

Page 61: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Bid Form The Public Library of Youngstown & Mahoning County 00 41 16 – 1

SECTION 00 41 16

BID FORM NOTE 1: The wording of this Proposal shall be retained throughout, without change, alterations or

additions. Any change in the wording may cause the Proposal to be rejected as not complying with the law.

NOTE 2: The Form of Proposal shall be accompanied by a BID GUARANTY meeting the

requirements of Section 153.54 of the Ohio Revised Code for the full amount of the bid. Noncompliance with the requirements pertaining to the BID GUARANTY will cause the Proposal to be rejected as not complying with the law.

NOTE 3: The attention of the bidder is called to the special conditions regarding STANDARDS-

SUBSTITUTIONS. PROPOSAL OF __________________________ hereinafter called Bidder, A *Corporation, organized and existing under the laws of the State of __________________, a *Partnership, or an individual doing business as ________________________________________. TO: The Public Library of Youngstown & Mahoning County 305 Wick Avenue Youngstown, Ohio 44503

The Bidder, in compliance with the Advertisement for the Retaining Wall for the Poland Village Library and having examined the Plans and Specifications, with related documents and the Site of the proposed work, and being familiar with all of the conditions surrounding the construction of the proposed Project, including the availability of materials and labor, hereby proposes to furnish all labor, equipment, materials, and supplies to construct the Project in accordance with the Contract Documents within the time set therein, at the prices stated below. These prices are to cover all expenses incurred in performing the work required under the Contract Documents, of which this Proposal is part and having also received, read and taken into account the following Addenda: Addendum No. Date of Receipt ____________________________________ _____________________________ ____________________________________ _____________________________ ____________________________________ _____________________________ ____________________________________ _____________________________ It is understood and agreed that work embodied in this Contract shall be completed as scheduled below, following authorization to proceed with work unless an extension of time is granted by Board of Trustees.

Page 62: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Bid Form The Public Library of Youngstown & Mahoning County 00 41 16 – 2

WORK IS TO BEGIN ON OR ABOUT MONDAY, OCTOBER 28, 2019 AND IS TO BE COMPLETED WITHIN SIXTY (60) CONSECUTIVE CALENDAR DAYS.

Upon failure to have all Work completed within the period of time above specified, The Public Library of Youngstown and Mahoning County shall be entitled to retain or recover from the Contractor, as Liquidated Damages, and not as a penalty, the amounts set forth in the following table for each and every calendar day thereafter until Contract Completion. The Board’s right to recover Liquidated Damages shall not substitute for any right of recovery for additional costs incurred should the Contractor fail to complete the Contract according to the Contract Documents. LIQUIDATED DAMAGES:

Dollar Amount of Contract Dollars Per Day

$1.00 to $50,000.00 $150.00

$50,000.01 to $150,000.00 $250.00

$150,000.01 to $500,000.00 $500.00

$500,000.01 to $2,000,000.00 $1,000.00 $2,000,000.01 to $5,000,000.00 $2,000.00

BASE BID PROPOSAL: The Undersigned Bidder proposes to perform all work for the applicable Contract in accordance with the Contract Documents for the following sums. All items must be completely filled in. ITEM 1: GENERAL CONTRACT BASE BID (Include a $5,000.00 Allowance for payment of Building Permit) ALL LABOR AND MATERIALS, for the sum of:..........$____________________________

Sum in words:____________________________________________________________ The Bidder shall fill in all relevant blank spaces in the Bid Form in ink or by typewriting and not in pencil. The Bidder shall show all bid amounts in both words and figures. In the case of a conflict between the words and figures, the amount shown in words shall govern, where such words are not ambiguous. When the Bidder’s intention and the meaning of the words are clear, omissions or misspellings of words will not render the words ambiguous. Any alteration or erasure of the items filled in on the Bid Form shall be initialed by the Bidder BID GUARANTY Bidder must submit with the Form of Proposal one of the following Bid Guaranties meeting the requirements of Section 153.54 of the Ohio Revised Code:

Page 63: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Bid Form The Public Library of Youngstown & Mahoning County 00 41 16 – 3

1) Bidder is cautioned that the Bid Guaranty required by Section 153.54 (B) ORC be submitted on attached Bid Guaranty and Performance Bond, and that the Bond is signed by both the Surety (Sureties) and the Bidder. Name and address of endorsers shall also be typed immediately below the signatures. IF THE AMOUNT IS LEFT BLANK, THE PENAL SUM OF THE BID GUARANTY AND PERFORMANCE BOND WILL BE THE FULL AMOUNT OF THE PRINCIPAL'S BASE BID PLUS ADD ALTERNATES; ALTERNATIVELY, IF COMPLETED, THE AMOUNT MUST BE NOT LESS THAN THE FULL AMOUNT OF THE BASE BID PLUS ADD ALTERNATES, STATED IN DOLLARS AND CENTS. A PERCENTAGE IS NOT ACCEPTABLE. The requirements of Section 3905.41 of the Ohio Revised Code may be applicable to require the Bid Guaranty and Performance Bond to be countersigned by an Ohio resident agent. It is the duty of the bidder to determine the applicability of Section 3905.41. Noncompliance with Section 3905.41 will cause the bidder's proposal to be rejected.

2) In lieu of the Bid Guaranty and Performance Bond required above in Note "C" a), the bidder

may submit the Bid Guaranty required by Section 153.54, ORC in the form of a Certified Check, Cashier's Check, or Letter of Credit pursuant to Chapter 1305 Ohio Revised Code and shall be equal to ten percent (10%) of the total bid. The Bid Guaranty shall be payable to the Public Library of Youngstown and Mahoning County.

3) The most responsible and responsive bidder will be required to furnish a Performance Bond

for full amount of award if Paragraph #2 above is utilized. Bidder is cautioned to bid on the "Standards" specified and to enter on the "Proposed Equal" form, all material which the Bidder wishes to have considered for a possible equal. Any proposed equal must conform to the Instructions To Bidders, Paragraph 2.5. In submitting this Bid, it is understood that the right is reserved by the Board of Trustees to reject any or all bids. It is agreed that this Proposal may not be withdrawn for a period of sixty (60) days from the opening thereof. BIDDER’S CERTIFICATION The Bidder hereby acknowledges that the following representations in this bid are material and not mere recitals:

1. Bidder has read and understands the Contract Documents and agrees to comply with all requirements of the Contract Documents, regardless of whether the Bidder has actual knowledge of the requirements and regardless of any statement or omission made by the Bidder which might indicate a contrary intention.

2. The Bidder represents that the bid is based upon the Standards specified by the Contract

Documents. 3. Bidder has visited the site, become familiar with local conditions and has correlated personal

observations about the requirements of the Contract Documents. The Bidder has no outstanding questions regarding the interpretation of the Contract Documents.

4. Bidder understands that the award of separate contracts for the Project will require

sequential, coordinated and interrelated operations which may involve delays in the progress

Page 64: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Bid Form The Public Library of Youngstown & Mahoning County 00 41 16 – 4

of the Bidder’s Work. The bidder agrees that the bid amount shall cover all expenses due from the Board resulting from interference, disruption, hindrance or delay caused by or between Contractors or their agents and employees.

If the undersigned is notified of the acceptance of this Proposal within sixty (60) calendar days from the time set for opening bids, he agrees to execute a contract for the above work for the stated compensation in the form of the agreement included in the Project Manual in accordance with the Contract Documents. If an Individual, Sign Below: _________________________________________ _________________________________________ NAME POST OFFICE ADDRESS If a Partnership, Sign Below: _________________________________________ _________________________________________ NAME POST OFFICE ADDRESS _________________________________________ _________________________________________ NAME POST OFFICE ADDRESS If a Corporation, Sign Below: _________________________________________ _________________________________________ NAME POST OFFICE ADDRESS Incorporated under the laws of the State of Ohio _________________________________________

BY _____________________________ Title of Officer Signing

Name, business address, phone, fax & e-mail of Bidder to which all formal notices shall be sent: ___________________________________________________________________________________ ___________________________________________________________________________________

END OF BID FORM

Page 65: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Bid Guaranty & Contract Bond The Public Library of Youngstown & Mahoning County 00 43 13 - 1

BID GUARANTY AND CONTRACT PERFORMANCE AND PAYMENT BOND

(O.R.C. § 153.571)

KNOW ALL PERSONS BY THESE PRESENTS, that we, the undersigned as Principal (Contractor) and as sureties are (Sureties) hereby held and firmly bound unto the as obligee in the penal sum of the dollar amount of the bid submitted by the principal to the obligee on , 2019, to undertake the project known as . (Project) The penal sum referred to herein shall be the dollar amount of the principal’s bid to the obligee, incorporating any additive or deductive Alternates made by the principal on the date referred to above to the obligee, which are accepted by the obligee. In no case shall the penal sum exceed the amount of Dollars ($ ). If the foregoing blank is not filled in, the penal sum will be the full amount of the principal’s bid, including add Alternates. Alternatively, if the blank is filled in, the amount stated must not be less than the full amount of the bid including add Alternates, in dollars and cents. A percentage is not acceptable. For the payment of the penal sum well and truly to be made, we hereby jointly and severally bind ourselves, our heirs, executors, administrators, successors, and assigns. Signed this day of , 2019. THE CONDITION OF THE ABOVE OBLIGATION IS SUCH that whereas the above named principal has submitted a bid for work on the Project. Now, therefore, if the obligee accepts the bid of the principal and the principal fails to enter into a proper contract in accordance with the bid, plans, details, specifications, and bills of material; and in the event the principal pays to the obligee the difference not to exceed ten percent (10%) of the penalty hereof between the amount specified in the bid and such larger amount for which the obligee may in good faith contract with the next lowest bidder to perform the work covered by the bid; or in the event the obligee does not award the contract to the next lowest bidder and resubmits the project for bidding, the principal pays to the obligee the difference not to exceed ten percent (10%) of the penalty hereof between the amount specified in the bid, or the costs, in connection with the resubmission, of printing new contract documents, required advertising, and printing and mailing notices to prospective bidders, whichever is less, then this obligation shall be null and void; otherwise to remain in full force and effect; if the obligee accepts the bid of the principal and the principal within ten (10) days after the awarding of the contract enters into a proper contract in accordance with the bid, plans, details, specifications, and bills of material, which said contract is made a part of this bond the same as though set forth herein. Now also, if the said principal shall well and faithfully do and perform the things agreed by said principal to be done and performed according to the terms of said contract; and shall pay all lawful claims of subcontractors, materialmen, and laborers, for labor performed and materials furnished in the carrying

Page 66: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Bid Guaranty & Contract Bond The Public Library of Youngstown & Mahoning County 00 43 13 - 2

forward, performing, or completing of said contract; we agreeing and assenting that this undertaking shall be for the benefit of any materialman or laborer having a just claim, as well as for the obligee herein; then this obligation shall be void; otherwise the same shall remain in full force and effect, it being expressly understood and agreed that the liability of the surety for any and all claims hereunder shall in no event exceed the penal amount of this obligation as herein stated. The said surety hereby stipulates and agrees that no modifications, omissions, or additions in or to the terms of the said contract or in or to the plans or specifications therefore shall in any way affect the obligations of said surety on its bond. The said surety further stipulates that it is authorized to execute bonds in the State of Ohio and that the liability incurred is within the limits of Section 3929.02 of the Ohio Revised Code. Signed and sealed this day of , 2019. (Principal) (Seal) By: Its: (Title) (Surety) (Seal) By: Its: (Title) (Address) (Name of Surety’s Agent) (Address of Surety’s Agent) (Telephone Number of Surety’s Agent) (Fax Number of Surety’s Agent)

Page 67: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Proposed Equal Request Form The Public Library of Youngstown & Mahoning County 00 43 25 - 1

SECTION 00 43 25 PROPOSED EQUAL REQUEST FORM ATTN: ANNISSA NEIDER, ms consultants, inc., 333 East Federal St., Youngstown, OH 44503 PROJECT: RETANING WALL – POLAND VILLAGE LIBRARY LOCATION: 311 SOUTH MAIN STREET, POLAND, OHIO 44514 BID DATE: _________________________________

SPECIFICATION SECTION: Specified Item: PROPOSED EQUAL:

Attach complete catalog, spec data, and lab tests (if applicable). 1. What effect will the proposed equal have on dimensions, gauges, etc., indicated in Contract Documents?

2. What effect will the proposed equal have on piping, ductwork, etc., indicated in Contract Documents? 3. What effect will the proposed equal have on other trades? 4. What effect will the proposed equal have on the construction schedule?

Page 68: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Proposed Equal Request Form The Public Library of Youngstown & Mahoning County 00 43 25 - 2

5. What are differences in quality/performance between the proposed equal and the specified product?

6. Manufacturer’s Guarantees of the specified products and proposed products are:

Same: Different (explain):

7. List availability of:

Maintenance Services: Replacement Materials:

8. If the proposed equal request is accepted, it will result in: 9. There are are no license fees and royalties pending on the proposed equal. SUBMITTED BY: Signature: Date: ARCHITECT’S/ENGINEER’S REVIEW COMMENTS: _____Accepted _____Received Too Late _____Accepted as Noted _____Not Accepted _____Rejected Due to Incomplete Information. Resubmit. Signature: Date: Remarks:

Page 69: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Contractor’s Qualification Statement The Public Library of Youngstown & Mahoning County 00 45 13 – i

SECTION 00 45 13

AIA A305 – CONTRACTOR’S QUALIFICATION

STATEMENT

Page 70: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 71: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA®

Document A305TM – 1986 Contractor's Qualification Statement

AIA Document A305™ – 1986. Copyright © 1964, 1969, 1979 and 1986 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:15:25 on 03/14/2007 under Order No.1000259282_2 which expires on 9/15/2007, and is not for resale. User Notes: 00 45 13 - Pages 1 - 400 45 13 - Pages 1 - 400 45 13 - Pages 1 - 4 (773107539)

1

ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.

This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.

This form is approved and recommended by the American Institute of Architects (AIA) and The Associated General Contractors of America (AGC) for use in evaluating the qualifications of contractors. No endorsement of the submitting party or verification of the information is made by AIA or AGC.

ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.

The Undersigned certifies under oath that the information provided herein is true and sufficiently complete so as not to be misleading. SUBMITTED TO: ADDRESS: SUBMITTED BY: NAME: ADDRESS: PRINCIPAL OFFICE: [ ] Corporation

[ ] Partnership

[ ] Individual

[ ] Joint Venture

[ ] Other

NAME OF PROJECT (if applicable): TYPE OF WORK (file separate form for each Classification of Work): [ ] General Construction

[ ] HVAC

[ ] Electrical

[ ] Plumbing

[ ] Other (please specify)

§ 1. ORGANIZATION § 1.1 How many years has your organization been in business as a Contractor? § 1.2 How many years has your organization been in business under its present business name?

§ 1.2.1 Under what other or former names has your organization operated?

§ 1.3 If your organization is a corporation, answer the following:

§ 1.3.1 Date of incorporation: § 1.3.2 State of incorporation: § 1.3.3 President's name: § 1.3.4 Vice-president's name(s)

Page 72: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA Document A305™ – 1986. Copyright © 1964, 1969, 1979 and 1986 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:15:25 on 03/14/2007 under Order No.1000259282_2 which expires on 9/15/2007, and is not for resale. User Notes: 00 45 13 - Pages 1 - 400 45 13 - Pages 1 - 400 45 13 - Pages 1 - 4 (773107539)

2

§ 1.3.5 Secretary's name: § 1.3.6 Treasurer's name:

§ 1.4 If your organization is a partnership, answer the following:

§ 1.4.1 Date of organization: § 1.4.2 Type of partnership (if applicable): § 1.4.3 Name(s) of general partner(s)

§ 1.5 If your organization is individually owned, answer the following:

§ 1.5.1 Date of organization: § 1.5.2 Name of owner:

§ 1.6 If the form of your organization is other than those listed above, describe it and name the principals: § 2. LICENSING § 2.1 List jurisdictions and trade categories in which your organization is legally qualified to do business, and indicate registration or license numbers, if applicable. § 2.2 List jurisdictions in which your organization's partnership or trade name is filed. § 3. EXPERIENCE § 3.1 List the categories of work that your organization normally performs with its own forces. § 3.2 Claims and Suits. (If the answer to any of the questions below is yes, please attach details.)

§ 3.2.1 Has your organization ever failed to complete any work awarded to it? § 3.2.2 Are there any judgments, claims, arbitration proceedings or suits pending or outstanding against

your organization or its officers? § 3.2.3 Has your organization filed any law suits or requested arbitration with regard to construction

contracts within the last five years?

§ 3.3 Within the last five years, has any officer or principal of your organization ever been an officer or principal of another organization when it failed to complete a construction contract? (If the answer is yes, please attach details.)

Page 73: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA Document A305™ – 1986. Copyright © 1964, 1969, 1979 and 1986 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:15:25 on 03/14/2007 under Order No.1000259282_2 which expires on 9/15/2007, and is not for resale. User Notes: 00 45 13 - Pages 1 - 400 45 13 - Pages 1 - 400 45 13 - Pages 1 - 4 (773107539)

3

§ 3.4 On a separate sheet, list major construction projects your organization has in progress, giving the name of project, owner, architect, contract amount, percent complete and scheduled completion date.

§ 3.4.1 State total worth of work in progress and under contract:

§ 3.5 On a separate sheet, list the major projects your organization has completed in the past five years, giving the name of project, owner, architect, contract amount, date of completion and percentage of the cost of the work performed with your own forces.

§ 3.5.1 State average annual amount of construction work performed during the past five years:

§ 3.6 On a separate sheet, list the construction experience and present commitments of the key individuals of your organization. § 4. REFERENCES § 4.1 Trade References: § 4.2 Bank References: § 4.3 Surety:

§ 4.3.1 Name of bonding company: § 4.3.2 Name and address of agent:

§ 5. FINANCING § 5.1 Financial Statement.

§ 5.1.1 Attach a financial statement, preferably audited, including your organization's latest balance sheet and income statement showing the following items:

Current Assets (e.g., cash, joint venture accounts, accounts receivable, notes receivable, accrued income, deposits, materials inventory and prepaid expenses); Net Fixed Assets; Other Assets; Current Liabilities (e.g., accounts payable, notes payable, accrued expenses, provision for income taxes, advances, accrued salaries and accrued payroll taxes);

Page 74: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA Document A305™ – 1986. Copyright © 1964, 1969, 1979 and 1986 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:15:25 on 03/14/2007 under Order No.1000259282_2 which expires on 9/15/2007, and is not for resale. User Notes: 00 45 13 - Pages 1 - 400 45 13 - Pages 1 - 400 45 13 - Pages 1 - 4 (773107539)

4

Other Liabilities (e.g., capital, capital stock, authorized and outstanding shares par values, earned surplus and retained earnings).

§ 5.1.2 Name and address of firm preparing attached financial statement, and date thereof: § 5.1.3 Is the attached financial statement for the identical organization named on page one? § 5.1.4 If not, explain the relationship and financial responsibility of the organization whose financial

statement is provided (e.g., parent-subsidiary).

§ 5.2 Will the organization whose financial statement is attached act as guarantor of the contract for construction? § 6. SIGNATURE § 6.1 Dated at this day of

Name of Organization: By: Title:

§ 6.2 M being duly sworn deposes and says that the information provided herein is true and sufficiently complete so as not to be misleading.

Subscribed and sworn before me this day of 20 Notary Public: My Commission Expires:

Page 75: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Non-Collusion Affidavit The Public Library of Youngstown & Mahoning County 00 45 19 - 1

NON-COLLUSION AFFIDAVIT STATE OF _________________ )

) SS: COUNTY OF _________________ ) , being first duly sworn, deposes and says that he/she is

(sole owner, a partner, president) of , the party making

the foregoing proposal or bid; that such bid is genuine and not collusive or sham; that said proposer/bidder

has not colluded, conspired, connived, or agreed directly or indirectly, with any bidder or person to put in a

sham proposal or bid, or that such person shall refrain from proposing/bidding, and has not in any manner,

directly or indirectly, sought by agreement or collusion or communication or conference, with any person, to

fix the bid price of affiant or any other bidder, or to fix any overhead, profit, or cost element of said

proposal/bid price, or of that of any other proposer/bidder, or to secure any advantage against The Public

Library of Youngstown and Mahoning County or any person or persons interested in the proposed

agreement/contract, and that all statements contained in said proposal or bid are true; and further, that such

proposer/bidder has not directly or indirectly, submitted this proposal or bid, or the contents thereof, or

divulged information or data relative thereto to any association or to any member or agent thereof.

_________________________________

Affiant

Sworn to and subscribed before me this ____________ day of _______________, 2019.

____________________________, Notary Public in and for _____________ County, Ohio.

My commission expires: ____________________ (SEAL)

Page 76: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 77: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Certificate of Non-Discrimination The Public Library of Youngstown & Mahoning County 00 45 36 – 1

SECTION 00 45 36

CERTIFICATE OF NON-DISCRIMINATION

The undersigned, agrees as an integral part of this Contract and part of the consideration

therefore, that they will comply with Sections 153.59 and 153.60 of the Ohio Revised Code and

not directly or indirectly discriminate and/or intimidate in the employment of persons or firms

because of race, sex, religion, handicap, national origin or ancestry.

Date: __________________ Signed: _________________________________ _________________________________ Title __________________________________ Firm

Page 78: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 79: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Construction Contract The Public Library of Youngstown & Mahoning County 00 52 16 – i

SECTION 00 52 16

AIA A101 – 2017 - STANDARD FORM OF AGREEMENT

BETWEEN OWNER & CONTRACTOR

Page 80: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 81: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA®

Document A101TM – 2017 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:43:12 ET on 08/22/2019 under Order No.6248540456 which expires on 09/20/2019, and is not for resale. User Notes: (947277431)

1

ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.

This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.

The parties should complete A101™–2017, Exhibit A, Insurance and Bonds, contemporaneously with this Agreement. AIA Document A201™–2017, General Conditions of the Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified.

ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.

AGREEMENT made as of the « » day of « » in the year « » (In words, indicate day, month and year.) BETWEEN the Owner: (Name, legal status, address and other information) « »« » « » « » « » and the Contractor: (Name, legal status, address and other information) « »« » « » « » « » for the following Project: (Name, location and detailed description) « » « » « » The Architect: (Name, legal status, address and other information) « »« » « » « » « » The Owner and Contractor agree as follows.

Page 82: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:43:12 ET on 08/22/2019 underOrder No.6248540456 which expires on 09/20/2019, and is not for resale. User Notes: (947277431)

2

TABLE OF ARTICLES 1 THE CONTRACT DOCUMENTS 2 THE WORK OF THIS CONTRACT 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION 4 CONTRACT SUM 5 PAYMENTS 6 DISPUTE RESOLUTION 7 TERMINATION OR SUSPENSION 8 MISCELLANEOUS PROVISIONS 9 ENUMERATION OF CONTRACT DOCUMENTS EXHIBIT A INSURANCE AND BONDS ARTICLE 1 THE CONTRACT DOCUMENTS The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary, and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9. ARTICLE 2 THE WORK OF THIS CONTRACT The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others. ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be: (Check one of the following boxes.)

[ « » ] The date of this Agreement.

[ « » ] A date set forth in a notice to proceed issued by the Owner.

[ « » ] Established as follows: (Insert a date or a means to determine the date of commencement of the Work.)

« »

If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this Agreement. § 3.2 The Contract Time shall be measured from the date of commencement of the Work. § 3.3 Substantial Completion § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work: (Check one of the following boxes and complete the necessary information.)

[ « » ] Not later than « » ( « » ) calendar days from the date of commencement of the Work.

Page 83: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:43:12 ET on 08/22/2019 underOrder No.6248540456 which expires on 09/20/2019, and is not for resale. User Notes: (947277431)

3

[ « » ] By the following date: « »

§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates:

Portion of Work Substantial Completion Date

§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5. ARTICLE 4 CONTRACT SUM § 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract. The Contract Sum shall be « » ($ « » ), subject to additions and deductions as provided in the Contract Documents. § 4.2 Alternates § 4.2.1 Alternates, if any, included in the Contract Sum:

Item Price

§ 4.2.2 Subject to the conditions noted below, the following alternates may be accepted by the Owner following execution of this Agreement. Upon acceptance, the Owner shall issue a Modification to this Agreement. (Insert below each alternate and the conditions that must be met for the Owner to accept the alternate.)

Item Price Conditions for Acceptance

§ 4.3 Allowances, if any, included in the Contract Sum: (Identify each allowance.)

Item Price

§ 4.4 Unit prices, if any: (Identify the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable.)

Item Units and Limitations Price per Unit ($0.00)

§ 4.5 Liquidated damages, if any: (Insert terms and conditions for liquidated damages, if any.) « » § 4.6 Other: (Insert provisions for bonus or other incentives, if any, that might result in a change to the Contract Sum.) « »

Page 84: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:43:12 ET on 08/22/2019 underOrder No.6248540456 which expires on 09/20/2019, and is not for resale. User Notes: (947277431)

4

ARTICLE 5 PAYMENTS § 5.1 Progress Payments § 5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents. § 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as follows: « » § 5.1.3 Provided that an Application for Payment is received by the Architect not later than the « » day of a month, the Owner shall make payment of the amount certified to the Contractor not later than the « » day of the « » month. If an Application for Payment is received by the Architect after the application date fixed above, payment of the amount certified shall be made by the Owner not later than « » ( « » ) days after the Architect receives the Application for Payment. (Federal, state or local laws may require payment within a certain period of time.) § 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. The schedule of values shall be prepared in such form, and supported by such data to substantiate its accuracy, as the Architect may require. This schedule of values shall be used as a basis for reviewing the Contractor’s Applications for Payment. § 5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment. § 5.1.6 In accordance with AIA Document A201™–2017, General Conditions of the Contract for Construction, and subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows: § 5.1.6.1 The amount of each progress payment shall first include:

.1 That portion of the Contract Sum properly allocable to completed Work;

.2 That portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction, or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing; and

.3 That portion of Construction Change Directives that the Architect determines, in the Architect’s professional judgment, to be reasonably justified.

§ 5.1.6.2 The amount of each progress payment shall then be reduced by:

.1 The aggregate of any amounts previously paid by the Owner;

.2 The amount, if any, for Work that remains uncorrected and for which the Architect has previously withheld a Certificate for Payment as provided in Article 9 of AIA Document A201–2017;

.3 Any amount for which the Contractor does not intend to pay a Subcontractor or material supplier, unless the Work has been performed by others the Contractor intends to pay;

.4 For Work performed or defects discovered since the last payment application, any amount for which the Architect may withhold payment, or nullify a Certificate of Payment in whole or in part, as provided in Article 9 of AIA Document A201–2017; and

.5 Retainage withheld pursuant to Section 5.1.7. § 5.1.7 Retainage § 5.1.7.1 For each progress payment made prior to Substantial Completion of the Work, the Owner may withhold the following amount, as retainage, from the payment otherwise due: (Insert a percentage or amount to be withheld as retainage from each Application for Payment. The amount of retainage may be limited by governing law.) « »

Page 85: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:43:12 ET on 08/22/2019 underOrder No.6248540456 which expires on 09/20/2019, and is not for resale. User Notes: (947277431)

5

§ 5.1.7.1.1 The following items are not subject to retainage: (Insert any items not subject to the withholding of retainage, such as general conditions, insurance, etc.) « » § 5.1.7.2 Reduction or limitation of retainage, if any, shall be as follows: (If the retainage established in Section 5.1.7.1 is to be modified prior to Substantial Completion of the entire Work, including modifications for Substantial Completion of portions of the Work as provided in Section 3.3.2, insert provisions for such modifications.) « » § 5.1.7.3 Except as set forth in this Section 5.1.7.3, upon Substantial Completion of the Work, the Contractor may submit an Application for Payment that includes the retainage withheld from prior Applications for Payment pursuant to this Section 5.1.7. The Application for Payment submitted at Substantial Completion shall not include retainage as follows: (Insert any other conditions for release of retainage upon Substantial Completion.) « » § 5.1.8 If final completion of the Work is materially delayed through no fault of the Contractor, the Owner shall pay the Contractor any additional amounts in accordance with Article 9 of AIA Document A201–2017. § 5.1.9 Except with the Owner’s prior approval, the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site. § 5.2 Final Payment § 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Contractor when

.1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct Work as provided in Article 12 of AIA Document A201–2017, and to satisfy other requirements, if any, which extend beyond final payment; and

.2 a final Certificate for Payment has been issued by the Architect. § 5.2.2 The Owner’s final payment to the Contractor shall be made no later than 30 days after the issuance of the Architect’s final Certificate for Payment, or as follows: « » § 5.3 Interest Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated below, or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located. (Insert rate of interest agreed upon, if any.) « » % « » ARTICLE 6 DISPUTE RESOLUTION § 6.1 Initial Decision Maker The Architect will serve as the Initial Decision Maker pursuant to Article 15 of AIA Document A201–2017, unless the parties appoint below another individual, not a party to this Agreement, to serve as the Initial Decision Maker. (If the parties mutually agree, insert the name, address and other contact information of the Initial Decision Maker, if other than the Architect.) « » « » « » « »

Page 86: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:43:12 ET on 08/22/2019 underOrder No.6248540456 which expires on 09/20/2019, and is not for resale. User Notes: (947277431)

6

§ 6.2 Binding Dispute Resolution For any Claim subject to, but not resolved by, mediation pursuant to Article 15 of AIA Document A201–2017, the method of binding dispute resolution shall be as follows: (Check the appropriate box.)

[ « » ] Arbitration pursuant to Section 15.4 of AIA Document A201–2017

[ « » ] Litigation in a court of competent jurisdiction

[ « » ] Other (Specify)

« » If the Owner and Contractor do not select a method of binding dispute resolution, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims will be resolved by litigation in a court of competent jurisdiction. ARTICLE 7 TERMINATION OR SUSPENSION § 7.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A201–2017. § 7.1.1 If the Contract is terminated for the Owner’s convenience in accordance with Article 14 of AIA Document A201–2017, then the Owner shall pay the Contractor a termination fee as follows: (Insert the amount of, or method for determining, the fee, if any, payable to the Contractor following a termination for the Owner’s convenience.) « » § 7.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201–2017. ARTICLE 8 MISCELLANEOUS PROVISIONS § 8.1 Where reference is made in this Agreement to a provision of AIA Document A201–2017 or another Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract Documents. § 8.2 The Owner’s representative: (Name, address, email address, and other information) « » « » « » « » « » « » § 8.3 The Contractor’s representative: (Name, address, email address, and other information) « » « » « » « » « » « » § 8.4 Neither the Owner’s nor the Contractor’s representative shall be changed without ten days’ prior notice to the other party.

Page 87: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:43:12 ET on 08/22/2019 underOrder No.6248540456 which expires on 09/20/2019, and is not for resale. User Notes: (947277431)

7

§ 8.5 Insurance and Bonds § 8.5.1 The Owner and the Contractor shall purchase and maintain insurance as set forth in AIA Document A101™–2017, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum, Exhibit A, Insurance and Bonds, and elsewhere in the Contract Documents. § 8.5.2 The Contractor shall provide bonds as set forth in AIA Document A101™–2017 Exhibit A, and elsewhere in the Contract Documents. § 8.6 Notice in electronic format, pursuant to Article 1 of AIA Document A201–2017, may be given in accordance with AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, if completed, or as otherwise set forth below: (If other than in accordance with AIA Document E203–2013, insert requirements for delivering notice in electronic format such as name, title, and email address of the recipient and whether and how the system will be required to generate a read receipt for the transmission.) « » § 8.7 Other provisions: « » ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS § 9.1 This Agreement is comprised of the following documents:

.1 AIA Document A101™–2017, Standard Form of Agreement Between Owner and Contractor

.2 AIA Document A101™–2017, Exhibit A, Insurance and Bonds

.3 AIA Document A201™–2017, General Conditions of the Contract for Construction

.4 AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, dated as indicated below: (Insert the date of the E203-2013 incorporated into this Agreement.)

« »

.5 Drawings

Number Title Date

.6 Specifications

Section Title Date Pages

.7 Addenda, if any:

Number Date Pages

Portions of Addenda relating to bidding or proposal requirements are not part of the Contract Documents unless the bidding or proposal requirements are also enumerated in this Article 9.

.8 Other Exhibits:

(Check all boxes that apply and include appropriate information identifying the exhibit where required.)

[ « » ] AIA Document E204™–2017, Sustainable Projects Exhibit, dated as indicated below:

(Insert the date of the E204-2017 incorporated into this Agreement.)

« »

Page 88: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 byThe American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 16:43:12 ET on 08/22/2019 underOrder No.6248540456 which expires on 09/20/2019, and is not for resale. User Notes: (947277431)

8

[ « » ] The Sustainability Plan:

Title Date Pages

[ « » ] Supplementary and other Conditions of the Contract:

Document Title Date Pages

.9 Other documents, if any, listed below:

(List here any additional documents that are intended to form part of the Contract Documents. AIA Document A201™–2017 provides that the advertisement or invitation to bid, Instructions to Bidders, sample forms, the Contractor’s bid or proposal, portions of Addenda relating to bidding or proposal requirements, and other information furnished by the Owner in anticipation of receiving bids or proposals, are not part of the Contract Documents unless enumerated in this Agreement. Any such documents should be listed here only if intended to be part of the Contract Documents.)

« »

This Agreement entered into as of the day and year first written above.

OWNER (Signature) CONTRACTOR (Signature)

« »« » « »« » (Printed name and title) (Printed name and title)

Page 89: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A02 - Bus & Concession Facilities Construction Contract – Exhibit A Edison Local School District 00 52 16 – i

SECTION 00 52 16

AIA A101 – 2017 - STANDARD FORM OF AGREEMENT

BETWEEN OWNER & CONTRACTOR

EXHIBIT A – INSURANCE & BONDS

Page 90: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 91: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 92: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 93: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 94: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 95: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 96: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 97: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 98: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 99: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Warranty Bond The Public Library of Youngstown & Mahoning County 00 61 26 - 1

SECTION 00 61 26

WARRANTY BOND KNOW ALL MEN BY THESE PRESENTS, that we as Principal, and as Surety are held and firmly bound unto The Public Library of Youngstown and Mahoning County (hereinafter called the Obligee) in the sum of DOLLARS ($ ) for the

payment of which sum will and truly to be made, we bind ourselves, our heirs, executors, administrators,

jointly, and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Principal entered into a certain contract, hereto attached, with the Owner dated , 20 for: NOW THEREFORE, if the Principal shall remedy without cost to the Obligee any defects which develop

during a period of one (1) year from the date of substantial completion and acceptance of the work

performed under said contract provided such defects, in the judgement of the Obligee of his successor

having jurisdiction in the premises, are caused by defective or inferior materials or workmanship, then this

obligation shall be void; otherwise to remain in full force or virtue.

IN WITNESS WHEREOF, the above-bounden parties have executed this instrument under their several seals this day of , 20_____, the name and corporate seal of

each corporate party being hereto affixed and these presented duly signed by its undersigned representative,

pursuant to authority of its governing body.

Page 100: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Warranty Bond The Public Library of Youngstown & Mahoning County 00 61 26 - 2

IN PRESENCE OF: (Seal) (Individual Principal) (Address) (Business Address) (Seal) (Individual Principal) (Address) (Business Address) ATTEST:

(Corporate Principal)

(Business Address)

By: (Affix Corporate Seal)

(Corporate Surety)

WITNESS: By: (Corporate Surety)

(Business Address)

By: (Affix Corporate Seal) The rate of premium on this bond is per thousand. Total amount of premium charged, $ .

(The above must be filled in by Corporate Surety.)

Page 101: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Acord Cert. of Insurance Title Page The Public Library of Youngstown & Mahoning County 00 62 16 – 1

SECTION 00 62 16

ACORD CERTIFICATE OF INSURANCE

Page 102: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 103: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 104: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 105: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Certificate of Personal Property Tax The Public Library of Youngstown & Mahoning County 00 62 18 – 1

SECTION 00 62 18 CERTIFICATION OF PERSONAL PROPERTY TAX DATE _________________ TO: The Public Library of Youngstown & Mahoning County 305 Wick Avenue Youngstown, OH 44503

RE: Contractor’s Affidavit of Compliance with Ohio Revised Code, Chapter 5719.042* State of Ohio County of _________________________________ I, hereby make oath and say that:

1. He is the of , the firm that submitted the attached bid.

2. At the time the bid was submitted, the firm named above (was) (was not) charged with

delinquent personal property taxes on the general tax list of personal property in County, Ohio

2. (If Applicable) The amount due and unpaid in delinquent personal property taxes is $

and the penalties and interest on the same are $ .

Contractor

BY - Signature

Title

Sworn to before me and subscribed in my presence at ,

the day of , 2019.

County, Ohio Notary Public in and for

My commission expires

*Sworn statement required by Ohio Revised Code as to the status of Bidder’s (Company’s) personal property taxes.

THIS AFFIDAVIT MUST BE SIGNED BEFORE THE PROJECT CAN BE AWARDED

Page 106: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 107: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Unresolved Findings for Recovery The Public Library of Youngstown & Mahoning County 00 62 21 - 1

SECTION 00 62 21

COMPLIANCE WITH ORC SECTION 9.24 AFFIDAVIT

Unresolved Findings for Recovery

ORC Section 9.24 prohibits entities who have unresolved findings for recovery issued by the Auditor of State from entering into pubic contracts.

Official Corporation / Company Name

as the Bidder of the following Contract:

Name of Client

Title of Project

obtained through the competitive bidding process, does hereby certify that we do / do not (circle one) have any unresolved findings for recovery issued by the Auditor of State. Official Corporation / Company Name Address City Telephone Authorized Signature Title Date

Page 108: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 109: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 - Retaining Wall – Poland Village Library Application For Payment Title Page The Public Library of Youngstown & Mahoning County 00 62 76 – 1

SECTION 00 62 76

AIA G702 / 703 – APPLICATION &

CERTIFICATE FOR PAYMENT FORM

Page 110: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 111: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

1

PROJECT: APPLICATION NO::

PERIOD TO: :

CONTRACT FOR: :

VIA CONTRACT DATE: :

ARCHITECT: PROJECT NOS: / / :

a. 0$0.00 )=

b. 0 day of$0.00 )=

$0.00Total Retainage (Lines 5a + 5b or Total in Column I of G703)……………………

$0.00

$0.00

State of:

Subscribed and sworn to before% of Stored Material

(Column D + E on G703: me this

County of:

ARCHITECT'S CERTIFICATE FOR PAYMENT

$0.00

(Line 4 Less Line 5 Total)$0.006. TOTAL EARNED LESS RETAINAGE…………………………………………….

$0.00

My Commission expires:

Notary Public:

This Certificate is not negotiable. The AMOUNT CERTIFIED is payable only to the Contractor named herein. Issuance, payment and acceptance of payment are without prejudice to any rights of the Owner or Contractor under this Contract.

By:

ARCHITECT:

AMOUNT CERTIFIED………………………………………………………

Date:

$0.00(Attach explanation if amount certified differs from the amount applied. Initial all figures on this Application and on the Continuation Sheet that are changed to conform with the amount certified.)

7. LESS PREVIOUS CERTIFICATES FOR PAYMENT………………………………..In accordance with the Contract Documents, based on on-site observations and the data comprising this application, the Architect certifies to the Owner that to the best of the Architect's knowledge, information and belief the Work has progressed as indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractor is entitled to payment of the AMOUNT CERTIFIED.

9. BALANCE TO FINISH, INCLUDING RETAINAGE

AIA® Document G702™ – 1992

Application and Certificate for Payment

FROM

TO OWNER:OWNER

ARCHITECTCONTRACTOR

Distribution to:blank

FIELD

001

General Construction

CONTRACTOR'S APPLICATION FOR PAYMENT

CONTRACTOR:

$0.00

CONTRACTOR:$0.00

The undersigned Contractor certifies that to the best of the Contractor's knowledge, information and belief the Work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for Work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.

Date:By:

$0.00

Application is made for payment, as shown below, in connection with the Contract.Continuation Sheet, AIA Document G703, is attached.

TOTALS

Total changes approved in previous months by Owner

$0.00$0.00

$0.00$0.00

$0.00$0.00

NET CHANGES by Change Order

$0.00

(Line 3 less Line 6)

Total approved this Month

$0.00

(Line 6 from prior Certificate)

DEDUCTIONSADDITIONS

$0.00

8. CURRENT PAYMENT DUE………………………………………………………

CHANGE ORDER SUMMARY

4. TOTAL COMPLETED & STORED TO DATE (Column G on G703)……………….5. RETAINAGE:

(Column F on G703:

1. ORIGINAL CONTRACT SUM………………………………………………………2. NET CHANGE BY CHANGE ORDERS………………………………………………3. CONTRACT SUM TO DATE (Line 1 ± 2) ………………………………………..

% of Completed Work

Page 112: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 113: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

1

A B C D E F H I

FROM PREVIOUS

APPLICATION

(D + E)

THIS PERIOD

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

GRAND TOTAL 0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00

RETAINAGE

(IF VARIABLE

RATE)

BALANCE TO

FINISH

(C - G)

%

(G ÷ C)

ARCHITECT'S PROJECT NO:

AIA® Document G703™ – 1992

APPLICATION NO:

Continuation Sheet

AIA Document, G702TM

–1992, Application and Certification for Payment, or G736TM

–2009,

Project Application and Project Certificate for Payment, Construction Manager as Adviser Edition,

containing Contractor's signed certification is attached.

In tabulations below, amounts are in US dollars.

Use Column I on Contracts where variable retainage for line items may apply.

APPLICATION DATE:

003

PERIOD TO:

ITEM

NO.

SCHEDULED

VALUE

WORK COMPLETED

DESCRIPTION OF

WORK

TOTAL

COMPLETED AND

STORED TO DATE

(D + E + F)

MATERIALS

PRESENTLY

STORED

(NOT IN D OR E)

GLabel 10Applica Application Period To:

LLLLC. G.

Page 114: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 115: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library RFI Form The Public Library of Youngstown & Mahoning County 00 63 13 – 1

ms consultants, inc. 333 East Federal Street Youngstown, OH 44503 Phone : 330-744-5321 Fax : 330-744-5256

REQUEST FOR INFORMATION

PROJECT: Retaining Wall – Poland Village Library RFI # ARCH. PROJECT NO: 64-12A01 Date: Response by (date): TO: Annissa Neider E-Mail: [email protected] ms Fax: 330-744-5256 FROM :

1) CONTRACT DOCUMENT REFERENCE SPECIFICATIONS: DRAWINGS:

2) DESCRIPTION: Signed By:

3) REPLY: Signed By: Date of Reply:

Page 116: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 117: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Change Order Form Title Page The Public Library of Youngstown & Mahoning County 00 63 63 – 1

SECTION 00 63 63

AIA G701 – CHANGE ORDER FORM

Page 118: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 119: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA®

Document G701TM – 2001 Change Order

AIA Document G701™ – 2001. Copyright © 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 09:24:12 on 11/18/2016 under Order No.7852622455_1 which expires on 09/17/2017, and is not for resale. User Notes: (878332473)

1

PROJECT (Name and address): CHANGE ORDER NUMBER: OWNER:

ARCHITECT:

CONTRACTOR:

FIELD:

OTHER:

DATE:

TO CONTRACTOR (Name and address): ARCHITECT’S PROJECT NUMBER:

CONTRACT DATE:

CONTRACT FOR:

THE CONTRACT IS CHANGED AS FOLLOWS: (Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives) The original Contract Sum was $ 0.00The net change by previously authorized Change Orders $ 0.00The Contract Sum prior to this Change Order was $ 0.00The Contract Sum will be increased by this Change Order in the amount of $ 0.00The new Contract Sum including this Change Order will be $ 0.00

The Contract Time will be increased by Zero (0) days. The date of Substantial Completion as of the date of this Change Order therefore is NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. ARCHITECT (Firm name) CONTRACTOR (Firm name) OWNER (Firm name)

ADDRESS ADDRESS ADDRESS

BY (Signature) BY (Signature) BY (Signature)

(Typed name) (Typed name) (Typed name)

DATE DATE DATE

Page 120: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 121: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Substantial Completion Title Page The Public Library of Youngstown & Mahoning County 00 65 16– 1

SECTION 00 65 16

AIA G704 – CERTIFICATE OF SUBSTANTIAL COMPLETION

Page 122: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 123: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA®

Document G704TM – 2000 Certificate of Substantial Completion

AIA Document G704™ – 2000. Copyright © 1963, 1978, 1992 and 2000 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 09:39:40 on 11/18/2016 under Order No.7852622455_1 which expires on 09/17/2017, and is not for resale. User Notes: (1984186739)

1

PROJECT: PROJECT NUMBER: / CONTRACT FOR: CONTRACT DATE:

OWNER:

ARCHITECT:

CONTRACTOR:

FIELD:

OTHER:

(Name and address)

TO OWNER: TO CONTRACTOR: (Name and address) (Name and address)

PROJECT OR PORTION OF THE PROJECT DESIGNATED FOR PARTIAL OCCUPANCY OR USE SHALL INCLUDE: The Work performed under this Contract has been reviewed and found, to the Architect’s best knowledge, information and belief, to be substantially complete. Substantial Completion is the stage in the progress of the Work when the Work or designated portion is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use. The date of Substantial Completion of the Project or portion designated above is the date of issuance established by this Certificate, which is also the date of commencement of applicable warranties required by the Contract Documents, except as stated below: Warranty Date of Commencement

ARCHITECT BY DATE OF ISSUANCE A list of items to be completed or corrected is attached hereto. The failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. Unless otherwise agreed to in writing, the date of commencement of warranties for items on the attached list will be the date of issuance of the final Certificate of Payment or the date of final payment. Cost estimate of Work that is incomplete or defective: $0.00 The Contractor will complete or correct the Work on the list of items attached hereto within Zero (0) days from the above date of Substantial Completion.

CONTRACTOR BY DATE The Owner accepts the Work or designated portion as substantially complete and will assume full possession at (time) on (date).

OWNER BY DATE The responsibilities of the Owner and Contractor for security, maintenance, heat, utilities, damage to the Work and insurance shall be as follows: (Note: Owner’s and Contractor’s legal and insurance counsel should determine and review insurance requirements and coverage.)

Page 124: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 125: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Contractor’s Affidavit of Payment of Debts & Claims Title Sheet The Public Library of Youngstown & Mahoning County 00 65 19.13 – i

SECTION 00 65 19.13

AIA G706 – CONTRACTOR’S AFFIDAVIT OF

PAYMENT OF DEBTS & CLAIMS

Page 126: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 127: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA®

Document G706TM – 1994 Contractor's Affidavit of Payment of Debts and Claims

AIA Document G706™ – 1994. Copyright © 1970 and 1994 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:05:17 on 03/14/2007 under Order No.1000259282_2 which expires on 9/15/2007, and is not for resale. User Notes: 00 65 19.13 - 1 (1079646372)

1

PROJECT: (Name and address) ARCHITECT’S PROJECT NUMBER: OWNER: ARCHITECT:

CONTRACTOR: SURETY: OTHER:

CONTRACT FOR: TO OWNER: (Name and address) CONTRACT DATED:

STATE OF: COUNTY OF: The undersigned hereby certifies that, except as listed below, payment has been made in full and all obligations have otherwise been satisfied for all materials and equipment furnished, for all work, labor, and services performed, and for all known indebtedness and claims against the Contractor for damages arising in any manner in connection with the performance of the Contract referenced above for which the Owner or Owner's property might in any way be held responsible or encumbered. EXCEPTIONS: SUPPORTING DOCUMENTS ATTACHED HERETO: CONTRACTOR: (Name and address)

1. Consent of Surety to Final Payment. Whenever Surety is involved, Consent of Surety is required. AIA Document G707, Consent of Surety, may be used for this purpose

Indicate Attachment Yes No

BY: The following supporting documents should be attached hereto if required by the Owner:

(Signature of authorized representative)

1. Contractor's Release or Waiver of Liens,

conditional upon receipt of final payment. (Printed name and title)

2. Separate Releases or Waivers of Liens from Subcontractors and material and equipment suppliers, to the extent required by the Owner, accompanied by a list thereof.

Subscribed and sworn to before me on this date:

Notary Public: 3. Contractor's Affidavit of Release of Liens (AIA

Document G706A). My Commission Expires:

Page 128: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 129: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Affidavit of Release of Liens Title Page The Public Library of Youngstown & Mahoning County 00 65 19.16 – i

SECTION 00 65 19.16

AIA G706A – CONTRACTOR’S AFFIDAVIT OF

RELEASE OF LIENS

Page 130: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 131: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA®

Document G706ATM – 1994 Contractor's Affidavit of Release of Liens

AIA Document G706A™ – 1994. Copyright © 1982 and 1994 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:06:13 on 03/14/2007 under Order No.1000259282_2 which expires on 9/15/2007, and is not for resale. User Notes: 00 65 19.16 - 1 (1597430499)

1

PROJECT: (Name and address) ARCHITECT’S PROJECT NUMBER: OWNER:

ARCHITECT:

CONTRACTOR:

SURETY:

OTHER:

CONTRACT FOR: TO OWNER: (Name and address) CONTRACT DATED:

STATE OF: COUNTY OF: The undersigned hereby certifies that to the best of the undersigned's knowledge, information and belief, except as listed below, the Releases or Waivers of Lien attached hereto include the Contractor, all Subcontractors, all suppliers of materials and equipment, and all performers of Work, labor or services who have or may have liens or encumbrances or the right to assert liens or encumbrances against any property of the Owner arising in any manner out of the performance of the Contract referenced above. EXCEPTIONS: SUPPORTING DOCUMENTS ATTACHED HERETO: CONTRACTOR: (Name and address)

1. Contractor's Release or Waiver of Liens, conditional upon receipt of final payment.

2. Separate Releases or Waivers of Liens from

Subcontractors and material and equipment suppliers, to the extent required by the Owner, accompanied by a list thereof.

BY: (Signature of authorized

representative)

(Printed name and title) Subscribed and sworn to before me on this date:

Notary Public: My Commission Expires:

Page 132: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 133: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Consent of Surety to Final Payment The Public Library of Youngstown & Mahoning County 00 65 19.19 – i

SECTION 00 65 19.19

AIA G707 – CONSENT OF SURETY

TO FINAL PAYMENT

Page 134: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 135: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

AIA®

Document G707TM – 1994 Consent Of Surety to Final Payment

AIA Document G707™ – 1994. Copyright © 1982 and 1994 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:07:08 on 03/14/2007 under Order No.1000259282_2 which expires on 9/15/2007, and is not for resale. User Notes: 00 65 19.19 - 1 (2229951080)

1

PROJECT: (Name and address) ARCHITECT’S PROJECT NUMBER: OWNER:

ARCHITECT:

CONTRACTOR:

SURETY:

OTHER:

CONTRACT FOR: TO OWNER: (Name and address) CONTRACT DATED:

In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the (Insert name and address of Surety)

, SURETY, on bond of (Insert name and address of Contractor)

, CONTRACTOR, hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve the Surety of any of its obligations to (Insert name and address of Owner)

, OWNER, as set forth in said Surety's bond. IN WITNESS WHEREOF, the Surety has hereunto set its hand on this date: (Insert in writing the month followed by the numeric date and year.) (Surety)

(Signature of authorized representative)

Attest: (Seal): (Printed name and title)

Page 136: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 137: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library General Conditions The Public Library of Youngstown & Mahoning County 00 72 00 – i

SECTION 00 72 00

AIA A201 – 2007 - GENERAL CONDITIONS OF THE

CONTRACT FOR CONSTRUCTION

Page 138: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 139: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 140: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 141: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 142: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 143: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 144: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 145: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 146: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 147: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 148: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 149: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 150: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 151: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 152: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 153: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 154: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 155: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 156: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 157: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 158: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 159: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 160: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 161: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 162: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 163: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 164: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 165: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 166: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 167: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 168: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 169: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 170: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 171: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 172: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 173: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 174: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 175: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 176: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 177: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 178: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 179: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Supplementary General Conditions The Public Library of Youngstown & Mahoning County 00 73 00 – 1

SECTION 00 73 00

SUPPLEMENTARY GENERAL CONDITIONS ARTICLE 1 - GENERAL PROVISIONS 1.1 BASIC DEFINITIONS 1.1.1 Add the following to paragraph 1.1.1 of the AIA General Conditions:

1. Wherever the words "Approved", "Satisfactory", "Directed", "Submitted", "Inspected", or similar words or phrases are used, it shall be assumed that the word "Architect" follows the verb as the object of the clause, such as, "Approved by the Architect". The word “Provide” shall mean “furnish and install”. Refer to Article 4 of the General Conditions.

2. Wherever the word "Architect" appears in the Contract Documents, it shall be

construed to mean ms consultants, inc., 333 East Federal Street, Youngstown, Ohio 44503.

3. The term "Sub-Contractor" shall be considered synonymous and shall refer to those

individuals, organizations and members of those organizations contracting with the prime contractor to execute certain portions of the work.

4. Wherever the words "Owner" or “Board of Trustees” appears in the Contract

Documents, it shall be construed to mean The Public Library of Youngstown & Mahoning County, 305 Wick Avenue, Youngstown, OH 44503.

5. General Trades Contractor - the Contractor for all parts of the work except those for

which separate provision is made in the Proposed Work. The Contractor responsible for scheduling the Project, coordinating the Contractors and providing other services identified in the Contract Documents.

6. Work – labor or material, or both.

7. Proposal - the form in which is set forth the lump sum for each division or

combination of divisions of the work called for, and the alternates and unit prices called for.

8. Approved Equal - approved by the Architect PRIOR to bidding.

9. Addendum - a letter or form clarifying, amending or interpreting the Contract

Documents issued before the receipt of bids.

10. Reasonable Time - whenever a reasonable time is specified in any of the Contract Documents. The time allowed shall be seventy-two (72) hours, weekends and holidays excluded, unless otherwise specifically provided.

Page 180: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Supplementary General Conditions The Public Library of Youngstown & Mahoning County 00 73 00 – 2

1.2 EXECUTION, CORRELATION, AND INTENT Add the following to Article 1.2 of AIA General Conditions:

1.2.4 Any reference to known standard Specifications, manufacturer's recommendations, etc. shall mean and intend latest edition of such at the time of bidding. Unless otherwise specified, each Contractor shall supply all labor, transportation, materials, apparatus, fuel, heat, scaffolding and tools necessary for the entire and proper completion of the work and shall install, maintain and remove all equipment of the construction and be responsible for safe, proper and lawful construction, maintenance and use of same and shall construct the work in the best and most workmanlike manner as shown on the drawings and schedules, stated in the Specifications or reasonably implied therefrom, all in accordance with the Contract Documents to provide the Owner with a "complete" building and environs.

1.2.5 If in the Contractor's opinion, any work is indicated on drawings, or specified in

such a manner as will make it impossible to produce first class work, or should discrepancies appear between Drawings and Specifications, he shall refer same to the Architect in writing for interpretation before proceeding with work. If the Contractor fails to make such reference, no excuse will therefore, be entertained for failure to carry out work in satisfactory a manner.

1.2.6 Should any bidder find discrepancies in or omissions from the Drawings or

Specifications, or should he be in doubt as to their meaning he shall at once notify the Architect who will send written instructions to all bidders. The Contractor reserves the right to correct purely typographical errors.

1.2.7 Any written instructions issued by the Architect during time of bidding are to be

covered in proposals and in choosing a contract they will become a part thereof. It is the responsibility of the bidder to determine that he has received all Bulletins and Addenda issue.

ARTICLE 2 - OWNER

The following Article 2.1 – General is to be modified as follows: 2.1.1 Is to be deleted in its entirety. 2.1.2 Delete this Article and replace as follows: Ohio Revised Code, Sections 1311.25 through 1311.32 – Public Improvements Mechanics Liens Law is incorporated herein. ARTICLE 3 - CONTRACTOR 3.3 SUPERVISION AND CONSTRUCTION PROCEDURES 3.3.1 Add the following to paragraph 3.3.1 of the AIA General Conditions:

1. The Contractor shall immediately upon entering the project for the purpose of beginning work, locate all general reference points and take such action as necessary

Page 181: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Supplementary General Conditions The Public Library of Youngstown & Mahoning County 00 73 00 – 3

to prevent their destruction. He shall lay out his own work and be responsible for all lines, elevations and measurements of the building, demolition work, utilities, and any other work to be executed by him under the contract. The Contractor shall verify grades, lines, levels, and dimensions indicated on the drawings and shall notify the Architect of errors or inconsistencies before commencing work. The Contractor shall establish and maintain a permanent bench mark, batter boards, level and grades and shall layout the exact location of all walls, partitions, openings, etc. He shall employ experienced and competent engineers and exercise proper precautions to verify the figures shown on the drawings for laying out work, and will be held responsible for any error resulting from his failure to exercise such precautions.

3.5 WARRANTY 3.5.1 Add the following to Section 3.5.1 of the AIA General Conditions:

1. Except where otherwise noted in the Specifications, the Contractor shall guarantee his workmanship and materials for a period one (1) year from the date of acceptance by the Owner, and shall leave the work in perfect order at completion. Should defects develop within the guarantee period, the Contractor shall, upon written notice of same, remedy the defects and reimburse the Owner for all damage to other work, whether caused by the defects or the work of correcting same. Guarantees, if any, extending beyond said one (1) year period, shall be specifically provided for in the Contract Documents.

2. By mutual agreement, the Owner may occupy a portion or portions of the Building

and Environs prior to total project completion. Acceptance of any work by the Owner shall be accomplished by the issuance of a Certificate of Substantial Completion, a copy of which shall be promptly sent to the Contractor(s) involved. From the date of the issuance of such certificate, the Contractor(s) shall be relieved of obligation to maintain the portion of the premises accepted but shall remain obligated to correct any "punch list" items then uncorrected. Responsibility shall also continue for all latent defects covered by the guarantee described above, and insurance shall continue to be carried to protect both the Owner and the Contractor's firm for workmen engaged on contingency items.

3.6 TAXES

Delete Paragraph 3.6.1, change to read as follows:

3.6.1 Materials purchased for use or consumption with the proposed work will be exempt from the State of Ohio Sales Tax as provided for in Section 5739.02 of the Revised Code of Ohio and also from the State of Ohio Use Tax, Section 5741.01.

3.7 PERMITS, FEES AND NOTICES 3.7.1 Add the following to Paragraph 3.7.1:

The Contractor will pay and obtain approval for the building permits. The General Contractor shall

Page 182: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Supplementary General Conditions The Public Library of Youngstown & Mahoning County 00 73 00 – 4

obtain the approved set of documents from the Architect prior to beginning work. Each Contractor is responsible for securing and paying for any and all additional permits, governmental fees, tap fees, licenses, storm sewer fees, sanitary tap fees, water tap fees, and all inspections necessary for the proper execution and completion of his work.

3.12 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES Add the following to Section 3.12 of the AIA General Conditions:

Refer to Section 01 33 00 – Submittal Procedures for Additional Requirements.

3.15 CLEANING-UP Add the following to paragraph 3.15.1 of the AIA General Conditions:

1. Refer to Section 01 70 00 – Execution and Closeout Requirements for additional requirements.

ARTICLE 5 SUB-CONTRACTORS 5.1 DEFINITION 5.1.2 Add the following to paragraph 5.1.2 of the AIA General Conditions:

1. Each Subcontractor agrees to be bound to the Prime Contractor by the terms of the Contract, General, Supplementary and Special Conditions, Drawings and Specifications and to assume toward the Contractor all obligations and responsibilities the Prime Contractor, by those documents, assumes toward the Owner.

ARTICLE 7 - CHANGES IN WORK

Add the following to Article 7 of the AIA General Conditions: 7.5 Refer to Section 01 20 00 – Price & Payment Procedures for additional requirements. ARTICLE 9 - PAYMENTS AND COMPLETION Add the following to Sub-Article 9.6 - Progress Payments: 9.6.8 APPLICATION FOR PAYMENT

1. State of Ohio Prevailing Wage requirements apply to the payment for labor under the contract for construction. Each Contractor and subcontractor must pay wages on a weekly basis and complete and provide to the Owner, through the Architect payroll reports. The

Page 183: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Supplementary General Conditions The Public Library of Youngstown & Mahoning County 00 73 00 – 5

Contractor shall submit monthly to the Architect an itemized Application for Payment for Work performed based upon the Contract Cost Breakdown. - The Application for Payment shall be supported by data substantiating the

Contractor’s right to payment. The Contractor shall supply such additional documentation as the Architect may request in connection with each payment to the Contractor.

- The Contractor shall list on the Application for Payment any approved Change

Orders processed and performed during the time covered by the Application for Payment.

2. Payment of an approved Application for Payment shall be made within 30 days from the date

of approval by the Architect.

- The Owner reserves the right to require proof of the renewal of required insurance as a condition precedent to payment.

9.6.9 LABOR

1. Partial payments to the Contractor for labor performed under either a Unit Price or lump sum Contract shall be made at the rate of 92 percent of the amount invoiced through the Application for Payment which shows the total Contract Completion at 50 percent or greater, pursuant to Section 153.13, ORC.

2. After the contract is 50 percent complete, as evidenced by payments in the amount of at least

50 percent of the Contract price to the Contractor, no additional retainage will be withheld. 9.6.10 MATERIAL

1. The Owner shall pay to the Contractor a sum at the rate of 92 percent of the invoice cost, not

to exceed the bid amount in a Unit Price or lump sum Contract, for material delivered on the site of the Project, or other point in the vicinity of the Project, or other storage site approved by the Architect, provided the Contractor provides the following information with the Application for Payment:

- A list of the fabricated materials consigned to the Project, giving the place of

storage, together with copies of invoices, in order to verify quantity and cost.

- A certification of materials stored off site, prepared by the Contractor and signed by the Architect to evidence that the materials are in conformity with the Specifications and have been tagged with the Project name and number for delivery to the Project. All costs incurred by the Architect to visit a storage site, other than the areas adjacent to the Project, shall be paid by the Contractor.

2. The balance of such invoiced cost shall be paid when such material is incorporated into and

becomes a part of the Project.

3. When payment is allowed on account of material delivered on the site of the Project or in the vicinity thereof or under the possession and control of the Contractor but not yet

Page 184: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Supplementary General Conditions The Public Library of Youngstown & Mahoning County 00 73 00 – 6

incorporated therein, such material shall become the property of the Owner, but if such material is stolen, destroyed, or damaged by casualty before being used, the Contractor will be required to replace it at the Contractor’s expense, pursuant to Section 153.514, ORC.

4. Completed line items concealed, underground and buried and not subject to final Punch List

may be paid for at the rate of 100 percent. Completed line items subject to a final Punch List requiring testing or start-up shall be paid at the rate of 98 percent.

9.6.11 RETAINAGE

1. When the major portion of the Project is occupied or in use, and there exists no other reason to withhold Retainage, the retained percentages held in connection with such portion may, upon request of the Contractor, be released and paid to the Contractor, withholding only that amount necessary to assure completion, in the discretion of the Owner and upon consent of the Contractor’s surety.

- Any reduction or release of Retainage, or portion thereof, shall not be a waiver of

the Owner’s right to Retainage in connection with other payments to the Contractor, or any other right or remedy the Owner has under the Contract Documents at law or in equity.

- Funds retained, but not previously paid shall be released to the Contractor within 30

days of approval of a final pay request by the Owner and execution of the certificate of Substantial Completion by the Architect and consent of the Contractor’s surety.

2. Upon consent by the Contractor’s Surety, the Owner may, pursuant to Section 153.80(B)(2),

reduce the amount of funds retained for the faithful performance of Work by 50 percent of the amount of funds required to be retained, provided the Contractor’s Surety remains responsible for all damages that may be caused due to default by the Contractor, including without limitation, the following:

- Completion of the Work; - All delay claims;

- All liquidated damages; and

- All additional expenses incurred by the Owner.

3. Refer to Section 01 20 00 – Price & Payment Procedures for additional requirements. ARTICLE 10 - PROTECTION OF PERSONS AND PROPERTY 10.2.1 Add the following to paragraph 10.2.1 of the AIA General Conditions:

When or where any direct or indirect damage or injury is done to public or private property by or on account of any act, omission, neglect or misconduct in the execution of the work, or in consequence of the nonexecution thereof by the Contractor, he shall restore at his own expense such property to a

Page 185: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Supplementary General Conditions The Public Library of Youngstown & Mahoning County 00 73 00 – 7

condition similar or equal to that existing before such damage or injury was done, by repairing, rebuilding or otherwise restoring as may be directed, or he shall make good such damage or injury in an acceptable manner.

10.2.2 Add the following paragraph 10.2.2 to the AIA General Conditions:

The Contractor is required to meet the applicable safety requirements of the Ohio Industrial Commission in the Publication IC-3. The Contractor shall take all necessary precautions to comply with pollution control laws, rules or regulations of Federal, State or Local agencies.

ARTICLE 11 - INSURANCE Delete paragraphs 11.1 thru 11.4.2 entirely. Change to read as follows: 11.1 REQUIRED INSURANCE: In accordance with the Specifications, the Contractor, without

restricting the obligations and liabilities assumed under the Contract Documents, shall at his own cost and expense purchase and maintain in force until final acceptance of his work, the forms of insurance described in Section 00 52 16 – AIA A101 – 2017 - Exhibit A – Insurance and Bonds.

INDEMNIFICATION The Contractor shall indemnify and hold harmless the Owner, the Resident

Engineer and the Consulting Engineers, and their officers, representatives, agents and employees from and against all claims, damages, losses, and expenses, including attorneys' fees arising out of or resulting from the performance of the work, provided that any such claim, damage, loss or expense is caused in whole or in part by any negligent act or omission of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified hereunder.

In any and all claims against the Owner, the Resident Engineer or the Consulting Engineers, or any of their officers, representatives, agents or employees by any employee of the Contractor, and subcontractor, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, the indemnification obligation of the Contractor under this Section shall not be limited in any way be any limitation on the amount or type of damages, compensation, or benefits payable by or for the Contractor or any subcontractor under workers' compensation acts, disability benefit acts, or other employee benefit acts. C. Builders Risk/Installation Floater

1. Types of Coverage

All risk including subsidence and theft of materials from the job site. Such coverage shall include all vehicles owned, non-owned, and hired. Builder’s Risk Insurance must be maintained on a 100% basis by the Contractor until the Project Facilities are completed and accepted by the Owner, the Owner or (at the option of the Owner) the contractor shall maintain Builders Risk Insurance (fire and extended coverage) on a 100 percent basis (completed value form) on the insurable portion of the Project Facilities for the benefit of the Director, the Owner, the prime contractor, and all subcontractors, as their respective interests may appear. This coverage shall reference the Owner as the insured entity.

Page 186: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Supplementary General Conditions The Public Library of Youngstown & Mahoning County 00 73 00 – 8

2. Limits of Liability

The limit of liability for the coverage noted above shall be not less than the amount of the Contract.

11.2 Builders Risk

1. Builder’s Risk Insurance will be purchased by the General Contractor.

ARTICLE 13 - MISCELLANEOUS PROVISIONS 13.5.1 Add the following to Section 13.5.1 of the AIA General Conditions:

(1) The Contractor shall leave his ladders, platforms or scaffold in place for a sufficient length of time and in such a manner to permit the Architect or Inspector to safely examine the work performed.

13.5.7 Add the following to Section 13.5.7 of the AIA General Conditions:

(1) Underground Utilities (Section 153.64 ORC) The prime contractor(s) shall, at least two (2) working days, excluding, Saturdays, Sundays, and legal holidays, prior to commencing construction operations in the project area which may involve underground utility facilities, cause notice to be given to the Registered Underground Utility Services (“Services)”) and the owners of underground utility facilities shown on the plans and specifications who are not member of such Services, in writing, by telephone, or in person. Where notice is given in writing by certified mail, the return receipt signed by any person to whom the notice is delivered, shall be conclusive proof of notice. The Owner of the underground utility facility shall within forty-eight (48) hours, excluding Saturdays, Sundays, and legal holidays, after notice is received, stake, mark, or otherwise designate the location of the underground utility facilities in the construction area in such a manner as to indicate their course together with the approximate depth at which they were installed. The marking or locating shall be coordinated to stay approximately two (2) days ahead of the planned construction. The contractor shall alert immediately the occupants of nearby premises as to any emergency that he may create or discover at or near such premises. The contractor shall report immediately to the Owner or operator the underground facility any break or lead on its lines or any dent, gouge, groove, or other damage to such lines or their coating of cathodic protection, made or discovered in the course of their excavation. The prime contractor(s), so identified in the specification, regardless of his subcontractors at any tier, is solely responsible for complying with these requirements for underground utility facilities in the project area.

Page 187: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Supplementary General Conditions The Public Library of Youngstown & Mahoning County 00 73 00 – 9

ARTICLE 15 - CLAIMS AND DISPUTES 15.2.5 Delete from the last sentence, “but subject to mediation……to binding dispute resolution” and

replace with “but subject to litigation”. 15.2.6 Delete “mediation” and “mediate” and replace with “litigation” and “litigate”.

END OF SUPPLEMENTARY GENERAL CONDITIONS

Page 188: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 189: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Wage Rates The Public Library of Youngstown & Mahoning County 00 73 46 - 1

SECTION 00 73 46

WAGE RATES Prevailing Wage Act The State Prevailing Wage Act shall apply to this project. Contractors shall obtain prevailing wages from the following website: http://www.com.ohio.gov/laws/PrevailingWageLaw.aspx. Contractors are responsible for compliance with the law, including the following specific requirements:

1. All workmen employed by this project shall be paid not less than the minimum wage rates which have been determined by the Secretary of Labor.

2. Each Contractor and Subcontractor shall keep an accurate record showing the name, craft and the actual hourly rate of wage paid to each workman employed by him in connection with this public work. This record shall be preserved for two years from the date of the project. This record shall be open to the inspection of the Owner, or representative thereof, and to the Secretary of Labor.

3. Contractors and subcontractors shall post the general prevailing minimum wages for each craft and classification involved, as determined by the Secretary of Labor and in a prominent and easily accessible place at the site of the work.

4. At the completion of the work and as a prerequisite for acceptance by the Owner, each Contractor and subcontractor shall file statements with the Owner of the names and amounts of unpaid wages.

5. Each Contractor and subcontractor shall file a statement each week under oath and in form satisfactory to the Secretary certifying that all workmen have been paid wages in strict conformity with the provisions, if any wages remain unpaid, to set forth the amount of wages due and owing to each workmen respectively.

6. Contractors and subcontractors shall make employees available for interviews by the Owner or representative thereof or to the Secretary of Labor on a reasonable basis. Interviews shall be limited to the employee’s name, address, dates worked on the project, hourly rate, job classification, duties, tools and equipment utilized and comments regarding compliance with the labor standards.

Page 190: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 191: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Summary The Public Library of Youngstown & Mahoning County 01 10 00 – 1

SECTION 01 10 00 SUMMARY PART 1 GENERAL 1.1 SECTION INCLUDES

A. Project Description.

B. Contractor use of site and premises. C. Owner’s Right to Maintain Operations. D. Owner Occupancy

1.2 PROJECT DESCRIPTION

A. Perform Work under a General Construction, stipulated sum contract with the Owner in accordance with the Conditions of Contract.

B. Removal of existing stone driveway retaining wall and retainage of existing stone at the Poland

Library. Replacement of the existing driveway retaining wall with a new structural retaining wall including the installation of a new drainage system.

C. Contractor shall carefully remove block along the north and south wall, load and move block to

storage area shown on plans. Block shall be stacked neatly, for reuse by others. Contractor shall secure storage area with temporary chain link fencing, 6 ft. in height. The temporary fence shall become the property of the Owner.

D. Contractor shall remove existing wall anchor system to allow for construction of new wall.

Contractor to dispose of existing wall anchor system. E. Contractor shall excavate behind removed wall to allow for construction of new wall as per

manufacturer’s recommendations. F. Contractor shall shore and support excavated area to allow construction of new north-south wall. G. Contractor shall coordinate work with the property Owner to the west of the Library. This

property’s driveway access shall be maintained by the Contractor. H. Contractor shall provide traffic maintenance in accordance with ODOT 614 – Maintaining Traffic.

Contractor shall provide two-way traffic in and out of the only access drive to the Library during normal Library operating hours. This drive access is adjacent to the wall to be removed and replaced. Contractor shall restrict parking in certain areas of the lot, at the approval of the Owner, to allow for completion of the work and transfer of removed blocks to the designated storage area, as per plan.

I. Contractor shall construct wall in accordance with the block manufacturer’s specifications

including excavation and installation of aggregate bedding material to the specified elevations,

Page 192: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Summary The Public Library of Youngstown & Mahoning County 01 10 00 – 2

installation of the sub-drainage piping as per plan, excavation and installation of the sub-drain piping from the wall location to the catch basin, complete with connection to the catch basin and repair of asphalt pavement as per plan.

J. On the property adjacent to the Library entrance drive, Contractor shall remove existing white

vinyl fencing along the entire length of the north / south wall and store the fence in a safe location to be re-installed by the Contractor following the completion of the new wall construction, as per plan.

K. On the property adjacent to the Library entrance drive, Contractor shall remove and dispose of

existing driveway curbing as required for the construction of the new wall. Following the completion of the new wall, the Contractor shall construct a new length of ODOT Type 6 concrete curb, in kind, to replace the curbing removed.

L. On the property adjacent to the Library entrance drive, Contractor shall saw cut, remove, and

dispose of the existing driveway asphalt as required for the construction of the new wall. Following the completion of the new wall, the Contractor shall repair the asphalt driveway in kind, to replace the asphalt pavement removed.

M. The Owner shall provide all temporary work permits from the adjacent property owner, for the

Contractor to complete this project. N. Contractor shall carefully remove block along the north-south wall so as to not damage any

existing pavement. Longitudinally saw-cut existing library driveway as required for installation of new retaining wall and replace at engineer’s direction. Repair of pavement shall be at the Contractor’s expense and no additional cost to the project.

O. Contractor shall provide all necessary clearing and grubbing, erosion control, storm water pollution

prevention, construction layout stakes, mobilization, bonds and insurance. P. At the end of each work day and on weekends, Contractor shall make sure site is clean and safe and

that all equipment and material stored on site so as not to restrict access to the Library during hours of operation.

1.3 CONTRACTOR USE OF SITE AND PREMISES

A. Access to Site: Site is currently developed with paved areas. Contractor staging and work areas will be defined during the preconstruction meeting.

B. All roads must be accessible during entire construction period.

C. Construction Operations: Limited to areas noted on drawings.

D. Time Restrictions for Performing Work: 7:00 a.m. to 5:00 p.m.

E. Utility outages and shutdown must be coordinated with and approved by the Owner.

1.4 OWNER’S RIGHT TO MAINTAIN OPERATIONS

A. Contractors shall be subject to such rules and regulations for the conduct of the Work as the Owner

Page 193: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Summary The Public Library of Youngstown & Mahoning County 01 10 00 – 3

may establish. Violators shall be promptly removed from the Site. B. Employees shall be properly and completely clothed while working. Bare torsos, legs and feet will

not be allowed. Possession or consumption of alcoholic beverages or drugs, tobacco or other noxious behavior on the Site is strictly prohibited. Violators shall be promptly removed from the Site. Smoking is not permitted on the property or within the buildings.

C. Absolutely no fire arms, other deadly weapons, or dangerous ordinances are permitted on this

project per Ohio Revised Code Section 2923.122.

1.5 OWNER OCCUPANCY A. Cooperate with Owner to minimize conflict, and to facilitate Owner's operations.

B. Schedule the Work to accommodate Owner occupancy.

1.6 ODOT REFERENCES

A. Whenever in these specifications a reference is made to a particular section of the Ohio Department of Transportation Specifications, it shall mean the Standard Specifications of the State of Ohio, Department of Transportation, Construction and Material Specifications, current edition. This document shall be used for this improvement and is hereby adopted as supplementary specifications, as noted on the plans and specifications. 1. Whenever, in the above referenced specifications, the terms “Administrator” or “Director” or

“Engineer” or “Inspector” are used, it shall be interpreted to mean the Engineer, or his authorized representative. Whenever in the referenced specifications the terms “Department” or “Agency” are used, it shall be interpreted to mean the Project Engineer. Whenever, in the reference specifications, the term “Laboratory” is used, it shall be interpreted to mean a Laboratory selected by the Owner and Engineer.

2. Only the Technical Specifications as noted will apply; then General Provisions. PART 2 PRODUCTS

Not Used. PART 3 EXECUTION

Not Used.

END OF SECTION

Page 194: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 195: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Price & Payment Procedures The Public Library of Youngstown & Mahoning County 01 20 00-1

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES PART 1 GENERAL 1.1 SECTION INCLUDES

A. Allowances

B. Schedule of values. C. Applications for payment. D. Change procedures. E. Defect assessment. 1.2 ALLOWANCES

A. Bidders to include a cash allowance of $5,000.00 for payment of the building permit.

B. Differences in costs will be adjusted by Change Order and any remaining balance will be credited to the Owner.

1.3 SCHEDULE OF VALUES

A. Submit a printed schedule on AIA Form G703 - Application and Certificate for Payment Continuation Sheet.

B. Submit Schedule of Values in duplicate within ten (10) days after date established in Notice to

Proceed. C. Format: Utilize the Table of Contents of this Project Manual. Identify each line item with number

and title of the major specification Section. Identify site mobilization, bonds and insurance, General Conditions, progress and final cleaning.

D. Include within each line item, a direct proportional amount of Contractor's overhead and profit.

E. Revise schedule to list approved Change Orders, with each Application For Payment.

1.3 APPLICATIONS FOR PAYMENT

A. Submit three (3) copies of each application on AIA Form G702 - Application and Certificate for Payment and AIA G703 - Continuation Sheet.

B. Content and Format: Utilize Schedule of Values for listing items in Application for Payment. C. Submit an updated construction schedule with each Application for Payment.

Page 196: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Price & Payment Procedures The Public Library of Youngstown & Mahoning County 01 20 00-2

D. Payment Period: Thirty days (30). E. Submit with transmittal letter as specified for Submittals in Section 01 33 00. F. Submit Release of Liens - AIA Document G706A - File with each Application For Payment

(excluding the first payment). Document shall be staggered by one (1) payment period. 1.4 CHANGE PROCEDURES

A. The Architect will advise of minor changes in the Work not involving an adjustment to Contract Sum/Price or Contract Time by issuing supplemental instructions on AIA Form G710.

B. The Architect may issue a Bulletin which includes a detailed description of a proposed change with

supplementary or revised Drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required and the period of time during which the requested price will be considered valid. Contractor will prepare and submit an estimate within seven (7) days unless a different period of time is listed in the respective Bulletin.

C. The Contractor may propose changes by submitting a request for change to the Architect,

describing the proposed change and its full effect on the Work. Include a statement describing the reason for the change, and the effect on the Contract Sum/Price and Contract Time with full documentation and a statement describing the effect on Work by separate or other Contractors.

D. Stipulated Sum: Based on Bulletin and Contractor's fixed price quotation or Contractor's request

for a Change Order as approved by Architect. E. Unit Price Change Order: For contract unit prices and quantities, the Change Order will be

executed on a fixed unit price basis. For unit costs or quantities of units of work which are not pre-determined, execute Work under a Construction Change Directive. Changes in Contract Sum/Price or Contract Time will be computed as specified for Change Order.

F. Construction Change Directive: Architect may issue a directive, on AIA Form G713 Construction Change Directive signed by the Owner, instructing the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work, and designate method of determining any change in Contract Sum/Price or Contract Time. Promptly execute the change.

G. Time and Material Change Order: Submit itemized account and supporting data after completion

of change, within time limits indicated in the Conditions of the Contract. Architect will determine the change allowable in Contract Sum/Price and Contract Time as provided in the Contract Documents.

H. Maintain detailed records of work done on Time and Material basis. Provide full information

required for evaluation of proposed changes, and to substantiate costs for changes in the Work. I. Document each quotation for a change in cost or time with sufficient data to allow evaluation of the

quotation. J. Change Order Forms: AIA G701 Change Order. K. Execution of Change Orders: Architect will issue Change Orders for signatures of parties as

Page 197: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Price & Payment Procedures The Public Library of Youngstown & Mahoning County 01 20 00-3

provided in the Conditions of the Contract. L. Correlation Of Contractor Submittals:

1. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Sum.

2. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust times for other items of work affected by the change, and resubmit.

3. Promptly enter changes in Project Record Documents.

1.5 DEFECT ASSESSMENT

A. Acceptance of non-conforming work shall comply with AIA 201, 2007 Edition, Paragraph 12.3, as modified.

PART 2 PRODUCTS - Not Used. PART 3 EXECUTION - Not Used.

END OF SECTION

Page 198: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 199: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Administrative Requirements The Public Library of Youngstown & Mahoning County 01 30 00 – 1

SECTION 01 30 00 ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.1 SECTION INCLUDES

A. Coordination and project conditions.

B. Preconstruction meeting. C. Progress meetings.

D. Preinstallation meetings.

E. Equipment electrical characteristics and components.

1.2 RELATED SECTIONS

A. Section 01 10 00 – Summary of Work

B. Section 01 33 00 – Submittals 1.3 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later.

B. Verify utility requirements and characteristics of operating equipment are compatible with building

utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

C. Coordinate space requirements, supports, and installation of mechanical and electrical Work which

are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the

construction. Coordinate locations of fixtures and outlets with finish elements. E. After Owner occupancy of premises, coordinate access to site for correction of defective Work and

Work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

Page 200: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Administrative Requirements The Public Library of Youngstown & Mahoning County 01 30 00 – 2

1.4 PRECONSTRUCTION MEETING

A. Architect will schedule a meeting after Notice to Proceed.

B. Attendance Required: Owner, Architect, and Contractor representatives.

C. Agenda: 1. Designation of personnel representing the parties in Contract, and the Architect. 2. Procedures and processing of field decisions, submittals, substitutions, applications for

payments, proposal request, Change Orders, and Contract closeout procedures. 3. Scheduling.

D. Architect will record minutes and distribute copies to participants. 1.5 PROGRESS MEETINGS

A. Architect will schedule and administer meetings throughout progress of the Work every other week.

B. Attendance Required: Job superintendent, major Subcontractors and suppliers, Owner, Architect as

appropriate to agenda topics for each meeting.

C. Agenda: 1. Review minutes of previous meetings. 2. Review of Work progress. 3. Field observations, problems, and decisions. 4. Identification of problems which impede planned progress. 5. Review of submittals schedule and status of submittals. 6. Review of off-site fabrication and delivery schedules. 7. Maintenance of progress schedule. 8. Corrective measures to regain projected schedules. 9. Planned progress during succeeding work period. 10. Coordination of projected progress. 11. Maintenance of quality and work standards. 12. Effect of proposed changes on progress schedule and coordination. 13. Other business relating to Work.

D. Architect will record minutes and distribute copies to participants.

1.6 PREINSTALLATION MEETING

A. When required in individual specification sections, convene a preinstallation meeting at the site prior to commencing work of the section.

B. Require attendance of parties directly affecting, or affected by, work of the specific section.

C. Notify Architect seven days in advance of meeting date.

Page 201: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Administrative Requirements The Public Library of Youngstown & Mahoning County 01 30 00 – 3

D. Prepare agenda and preside at meeting:

1. Review conditions of installation, preparation and installation procedures. 2. Review coordination with related work.

E. Record minutes and distribute copies to participants, and those affected by decisions made.

PART 2 PRODUCTS NOT USED PART 3 EXECUTION NOT USED END OF SECTION

Page 202: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 203: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Construction Progress Schedule The Public Library of Youngstown & Mahoning County 01 32 16 - 1

SECTION 01 32 16 CONSTRUCTION PROGRESS SCHEDULE PART 1 GENERAL 1.1 CONSTRUCTION SCHEDULE

A. The General Contractor shall prepare the Construction Schedule for the Project. Critical path scheduling methods shall be provided. 1. Within seven (7) days of the date of the Notice to Proceed, the General Contractor shall

furnish to each Subcontractor, the Owner and the Architect a proposed schedule for the prosecution of the Work under the General Contractor’s Contract.

2. The Contractors shall, within seven (7) days of receipt of the General Contractor’s proposed schedule, prepare a proposed schedule to coordinate the Contractor’s Work with the Work of the General Contractor and submit such proposed schedule to the General Contractor.

B. The Contractors shall cooperate with the General Contractor to prepare a proposed Construction

Schedule which shall include, without limitation, the following information. 1. A graphic presentation of the sequence of the Work for the Project which includes, without

limitation, the Contractor’s resource loading curve; 2. Shop Drawing review and approval, product procurement, fabrication, shop inspection, and

delivery dates including lead times; 3. Each phase of the Work, including Punch List, Project close-out requirements, Contract

Completion and occupancy; 4. Milestone dates that are required by the Contract Documents; 5. The critical path of the Work; 6. Disruptions and shutdowns due to other operations, facilities and functions, if any; 7. The Contractor’s signature.

C. The General Contractor shall submit to the Architect within 30 days of the date of the Notice to

Proceed, a proposed Construction Schedule signed by all Contractors. 1. Upon receipt of the proposed Construction Schedule, the Architect shall review and approve

the Construction Schedule and submit a copy of the Construction Schedule and schedule of submittals to the Owner.

2. No payment will be made without a Construction Schedule approved by all the Contractors, the Architect and the Owner.

D. The Contractors shall, on a weekly basis, prepare and submit to the General Contractor a written

report describing activities begun or finished during the preceding week. Work in progress, expected completion of the Work, a projection of all activities to be started or finished in the following two (2) weeks, including without limitation, the Contractor’s resource loading curve associated with such Work and any other information requested by the General Contractor.

E. The General Contractor shall provide monthly progress reports to the Architect which shall include

recommendations for adjusting the Construction Schedule to meet milestone completion and Contract Completion dates. 1. When it is apparent to the General Contractor or the Architect that critical path activities,

scheduled milestone completion dates, or Contract Completion dates will not be met, the General Contractor shall propose an affirmative plan to avoid or minimize any delay.

Page 204: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Construction Progress Schedule The Public Library of Youngstown & Mahoning County 01 32 16 - 2

2. Such a plan may include, without limitation, increasing the Contractor’s workforce in such quantities as will eliminate the backlog of Work; increasing the number of working hours per shift, shifts per workday, workdays per week, the amount of construction equipment, or any combination thereof; rescheduling of activities to achieve maximum practical concurrence of Work efforts.

F. The General Contractor shall update the Construction Schedule on a monthly basis.

1. The updated Construction Schedule shall be signed by the Contractor which shall serve as an affirmation that the Contractor can meet the requirements of the updated Construction Schedule.

2. The updated Construction Schedule shall be submitted to the Architect who shall review and approve it and submit a copy to the Owner.

3. No payment will be made without an updated Construction Schedule approved by all the Contractors, the Architect, and the Owner.

PART 2 PRODUCTS

Not Used. PART 3 EXECUTION

Not Used. END OF SECTION

Page 205: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Submittal Procedures The Public Library of Youngstown & Mahoning County 01 33 00 - 1

SECTION 01 33 00 SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 SECTION INCLUDES

A. Submittal procedures.

B. Construction progress schedules.

C. Product Data.

D. Shop Drawings.

E. Samples.

F. Test Reports 1.2 RELATED SECTIONS

A. Section 01 40 00 - Quality Requirements: Manufacturers' field services and reports.

B. Section 01 70 00 – Execution and Closeout Requirements: Contract warranties, bonds, manufacturers' certificates, and closeout submittals.

1.3 REFERENCES

A. AGC (Associated General Contractors of America) publication "The Use of CPM in Construction - A Manual for General Contractors and the Construction Industry".

1.4 SUBMITTAL PROCEDURES

A. Transmit each submittal with Architect accepted form.

B. Sequentially number the transmittal form. Revise submittals with original number and a sequential alphabetic suffix.

C. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and

specification section number, as appropriate. D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of

Products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with the requirements of the Work and Contract Documents.

E. Schedule submittals to expedite the Project, and deliver to Architect at business address.

Coordinate submission of related items.

Page 206: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Submittal Procedures The Public Library of Youngstown & Mahoning County 01 33 00 - 2

F. For each submittal for review, allow 15 days excluding delivery time to and from the contractor.

G. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.

H. Provide space for Contractor and Architect review stamps.

I. When revised for resubmission, identify all changes made since previous submission.

J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any

inability to comply with requirements.

K. Submittals not requested will not be recognized or processed. 1.5 CONSTRUCTION PROGRESS SCHEDULES

A. Submit initial schedules within seven (7) days after date established in Notice to Proceed. After review, resubmit complete schedule within ten (10) days.

B. Submit revised Progress Schedules with each Application for Payment.

C. Distribute copies of reviewed schedules to Project site file, subcontractors, suppliers, and other

concerned parties.

D. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules.

1.6 PRODUCT DATA

A. Product Data For Review: 1. Submitted to Architect for review for the limited purpose of checking for conformance

with information given and the design concept expressed in the contract documents. 2. After review, provide copies and distribute in accordance with Submittal Procedures

article above and for record documents purposes described in Section 01 70 00 – Execution Requirements.

B. Product Data For Information: Submitted for the Architect’s knowledge as contract administrator.

C. Product Data For Project Close-out: Submitted for the Owner's benefit during and after project

completion.

D. Submit the number of copies which the Contractor requires, plus one copy which will be retained by the Architect.

E. Mark each copy to identify applicable products, models, options, and other data. Supplement

manufacturers' standard data to provide information specific to this Project.

F. Indicate Product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

Page 207: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Submittal Procedures The Public Library of Youngstown & Mahoning County 01 33 00 - 3

G. After review distribute in accordance with the Submittal Procedures article above and provide copies for record documents described in Section 01 70 00 – Execution and Closeout Requirements.

1.6 SHOP DRAWINGS

A. Shop Drawings: Submit to Architect for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents. Produce copies and distribute in accordance with Submittal Procedures article and for record documents purposes described in Section 01 70 00 - Execution and Closeout Requirements.

B. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

C. When required by individual specification sections, provide shop drawings signed and sealed by

professional engineer responsible for designing components shown on shop drawings. 1. Include signed and sealed calculations to support design. 2. Submit drawings and calculations in form suitable for submission to and approval by

authorities having jurisdiction. 3. Make revisions and provide additional information when required by authorities having

jurisdiction. D. Submit the number of copies which Contractor requires, plus two copies which will be retained by

Architect.

1.7 SAMPLES

A. Samples: Submit to Architect for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents. Produce duplicates and distribute in accordance with Submittal Procedures article and for record documents purposes described in Section 01 70 00.

B. Samples For Selection as Specified in Product Sections:

1. Submit to Architect for aesthetic, color, or finish selection. 2. Submit samples of finishes from the full range of manufacturers' standard colors, textures,

and patterns for Architect selection. 3. After review, produce duplicates and distribute in accordance with Submittal Procedures

article and for record documents purposes described in Section 01 70 00.

C. Submit samples to illustrate functional and aesthetic characteristics of the product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

D. Include identification on each sample, with full Project information.

E. Submit the number of samples specified in individual specification sections; one of which will be

retained by Architect.

F. Reviewed samples which may be used in the Work are indicated in individual specification sections.

Page 208: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Submittal Procedures The Public Library of Youngstown & Mahoning County 01 33 00 - 4

G. Samples will not be used for testing purposes unless specifically stated in the specification section. 1.8 TEST REPORTS A. Submit for the Architect’s knowledge as contract administrator for the Owner.

B. Submit test reports for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

PART 2 PRODUCTS

Not Used. PART 3 EXECUTION

Not Used. END OF SECTION

Page 209: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Quality Requirements The Public Library of Youngstown & Mahoning County 01 40 00-1

SECTION 0 1 40 00 QUALITY REQUIREMENTS PART 1 GENERAL 1.1 SECTION INCLUDES

A. Quality Control - Control of Installation.

B. Tolerances

C. References

D. Testing and Inspection Services.

1.2 RELATED SECTIONS

A. Section 01 33 00 – Submittal Procedures: Submission of manufacturers' instructions and certificates.

B. Section 01 60 00 – Product Requirements: Requirements for material and product quality.

1.3 QUALITY CONTROL AND CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from

Architect before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Perform Work by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the

manufacturer. G. Secure products in place with positive anchorage devices designed and sized to withstand stresses,

vibration, physical distortion, or disfigurement. 1.4 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable Work. Do not permit tolerances to accumulate.

Page 210: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Quality Requirements The Public Library of Youngstown & Mahoning County 01 40 00-2

B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract

Documents, request clarification from Architect before proceeding.

C. Adjust products to appropriate dimensions; position before securing Products in place. 1.5 REFERENCES

A. For products or workmanship specified by association, trade, or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current on date of Contract Documents, except where

a specific date is established by code.

C. Obtain copies of standards where required by product specification sections. D. When specified reference standards conflict with Contract Documents, request clarification from

Architect before proceeding.

E. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of the Architect shall be altered from the Contract Documents by mention or inference otherwise in any reference document.

1.6 TESTING & INSPECTION SERVICES

A. Owner will employ and pay for specified services of an independent firm to perform testing and inspection as required.

B. The independent firm will perform tests, inspections and other services specified in individual specification sections and as required by the Architect.

1. Laboratory: Authorized to operate in location in which Project is located. 2. Laboratory Staff: Maintain a full time registered Engineer on staff to review services. 3. Testing Equipment: Calibrated at reasonable intervals with devices of an accuracy traceable

to either National Bureau of Standards or accepted values of natural physical constants. C. Testing, inspections and source quality control may occur on or off the project site. Perform off-

site testing as required by the Architect or the Owner. D. Reports will be submitted by the independent firm to the Architect and Contractor, in duplicate,

indicating observations and results of tests and indicating compliance or non-compliance with Contract Documents.

E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools,

storage, safe access, and assistance by incidental labor as requested. 1. Notify Architect and independent firm 24 hours prior to expected time for operations

requiring services. 2. Make arrangements with independent firm and pay for additional samples and tests required

for Contractor's use.

Page 211: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Quality Requirements The Public Library of Youngstown & Mahoning County 01 40 00-3

F. Testing and employment of testing agency or laboratory shall not relieve Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

G. Re-testing or re-inspection required because of non-conformance to specified requirements shall be

performed by the same independent firm on instructions by the Architect. Payment for re-testing or re-inspection will be charged to the Contractor by deducting testing charges from the Contract Sum/Price.

H. Agency Responsibilities: 1. Test samples of mixes submitted by Contractor. 2. Provide qualified personnel at site. Cooperate with Architect and Contractor in performance

of services. 3. Perform specified sampling and testing of products in accordance with specified standards. 4. Ascertain compliance of materials and mixes with requirements of Contract Documents. 5. Promptly notify Architect and Contractor of observed irregularities or non-conformance of

Work or products. 6. Perform additional tests required by Architect.

I. Agency Reports: After each test, promptly submit two copies of report to Architect and to

Contractor. When requested by Architect, provide interpretation of test results. Include the following: 1. Date issued. 2. Project title and number. 3. Name of inspector. 4. Date and time of sampling or inspection. 5. Identification of product and specifications section. 6. Type of inspection or test. 7. Date of test. 8. Results of tests. 9. Conformance with Contract Documents.

J. Limits On Testing Authority:

1. Agency or laboratory may not release, revoke, alter, or enlarge on requirements of Contract Documents.

2. Agency or laboratory may not approve or accept any portion of the Work. 3. Agency or laboratory may not assume any duties of Contractor. 4. Agency or laboratory has no authority to stop the Work.

1.7 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary.

B. Report observations and site decisions or instructions given to applicators or installers that are

supplemental or contrary to manufacturers' written instructions.

C. Refer to Section 01 33 00 - Submittal Procedures, Manufacturers' Field Reports article.

Page 212: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Quality Requirements The Public Library of Youngstown & Mahoning County 01 40 00-4

PART 2 PRODUCTS

Not Used. PART 3 EXECUTION 3.1 EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural support or attachment of new Work being

applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

D. Verify that utility services are available, of the correct characteristics, and in the correct locations. 3.2 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.

END OF SECTION

Page 213: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Temporary Facilities & Controls The Public Library of Youngstown & Mahoning County 01 50 00 - 1

SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS PART 1 GENERAL 1.1 SECTION INCLUDES

A. Temporary Utilities: (Coordinate with Owner any utilities required.) 1. Temporary electricity including usage. 2. Temporary lighting for construction purposes. 3. Cellular and E-mail service. 4. Temporary water service. 5. Temporary sanitary facilities.

B. Construction Facilities: 1. Vehicular access. 2. Parking.

3. Progress cleaning and waste removal.

C. Temporary Controls: 1. Traffic Maintenance.

2. Enclosures and fencing. 3. Water control. 4. Dust control. D. Removal of utilities, facilities, and controls. 1.2 TEMPORARY ELECTRICITY

A. Paid for by the Owner. Additional distribution by the Electrical Contractor.

B. Provide power outlets for construction operations, with branch wiring and distribution boxes located

as required. Provide flexible power cords as required. C. Provide adequate distribution equipment, wiring, and outlets to provide single phase branch circuits

for power and lighting. 1. Provide 20 ampere duplex outlets, single phase circuits for power tools for every 500 sq ft of

active work area. All circuits to be GFCI. 2. Provide 20 ampere, single phase branch circuits for lighting.

1.3 TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES

A. Provide and maintain any additional incandescent lighting necessary for construction operations to

achieve a minimum lighting level of 70 FC if required. B. Provide and maintain 50 FC to exterior staging and storage areas after dark for security purposes.

Page 214: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Temporary Facilities & Controls The Public Library of Youngstown & Mahoning County 01 50 00 - 2

C. Provide branch wiring from power source to distribution boxes with lighting conductors, pigtails, and lamps as required.

D. Maintain lighting and provide routine repairs.

1.4 CELLULAR TELEPHONE SERVICE

A. Provide, maintain and pay for continuous cellular telephone service for project superintendent and any assistant superintendents.

1.5 E-MAIL SERVICE

A. Provide, maintain and pay for continuous e-mail accounts for project superintendent and any assistant superintendents.

1.6 TEMPORARY WATER SERVICE

A. Owner will provide and pay for suitable quality water service as needed to maintain specified conditions for construction operations.

B. General Trades Contractor shall extend branch piping with outlets located so water is available by

hoses with threaded connections. Provide temporary pipe insulation to prevent freezing. 1.7 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures. Existing facility use is not permitted. Provide at time of project mobilization.

B. At end of construction, return facilities to same or better condition as original condition. 1.8 VEHICULAR ACCESS (By General Trades Contractor):

A. Provide unimpeded access for emergency vehicles. Maintain 30 foot width driveways with turning space between the existing facility and around combustible materials.

B. Provide and maintain access to fire hydrants and control valves free of obstructions. C. Provide means of removing mud from vehicle wheels before entering streets. D. Designated roads only may be used for construction traffic. 1.9 PARKING

A. Parking only in designated areas. B. Equipment and material storage in designated areas. C. Maintenance: Maintain traffic and parking areas in a sound condition free of excavated material,

construction equipment, products, mud, snow, and ice.

Page 215: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Temporary Facilities & Controls The Public Library of Youngstown & Mahoning County 01 50 00 - 3

D. Mud From Site Vehicles (By General Trades Contractor): Provide means of removing mud from vehicle wheels before entering streets.

1.10 PROGRESS CLEANING AND WASTE REMOVAL

A. During the progress of the Work, each contractor shall be responsible for the removal of all waste materials and rubbish attributable to the Work to an appropriate disposal site designated by the General Trades Contractor. The General Trades Contractor shall perform daily broom cleaning in the area of the Contractor’s Work. 1. The General Trades Contractor shall, at the end of each working day or as directed by the

Architect remove all waste materials and rubbish from the Project. 2. The General Trades Contractor shall, as required for the Project or as directed by the

Architect, remove any waste materials or rubbish from areas adjacent to the Project. 3. The General Trades Contractor shall provide and maintain a minimum of one, 30 gallon trash

receptacle for every 500 sq. ft. of building area. Trash receptacle shall be located throughout building.

B. If the Contractor fails to clean up during the progress of the Work, the provision of paragraph 6.3 of

the General Conditions shall be invoked. C. If the Contractor fails to maintain the areas adjacent to the Project clean and free of waste materials

and rubbish, upon written notification by the Architect, the Owner shall direct the local jurisdiction having responsibility for the area to clean the area. 1. The cost of cleaning the area adjacent to the Project shall be deducted from the responsible

Contractor as the Architect recommends. 2. The decision of the Architect shall be final.

1.11 TRAFFIC REGULATIONS (All Contractors)

A. Haul Routes: Consult with Authority having jurisdiction, establish public thoroughfares to be used for haul routes and site access.

1.12 BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas and to protect existing facilities and adjacent properties from damage from construction operations and demolition.

B. Provide barricades required by governing authorities for public rights-of-way.

1.13 WATER CONTROL

A. Maintain excavations free of water. Provide, operate, and maintain pumping equipment. B. Protect site from puddling or running water. Provide water barriers as required to protect site from

soil erosion. 1.14 DUST CONTROL

A. Execute Work by methods to minimize raising dust from construction operations.

Page 216: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Temporary Facilities & Controls The Public Library of Youngstown & Mahoning County 01 50 00 - 4

B. Provide positive means to prevent air-borne dust from dispersing into atmosphere. 1.15 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Remove temporary utilities, equipment, facilities, materials, prior to Substantial Completion inspection.

B. Remove underground installations to a minimum depth of 2 feet unless noted otherwise. C. Clean and repair damage caused by installation or use of temporary work. D. Restore existing and permanent facilities used during construction to original condition. Restore

permanent facilities used during construction to specified condition.

PART 2 PRODUCTS - Not Used.

PART 3 EXECUTION - Not Used.

END OF SECTION

Page 217: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Product Requirements The Public Library of Youngstown & Mahoning County 01 60 00 – 1

SECTION 01 60 00 PRODUCT REQUIREMENTS PART 1 GENERAL 1.1 SECTION INCLUDES

A. Products.

B. Product delivery requirements.

C. Product storage and handling requirements.

D. Product options.

E. Product substitution procedures. 1.2 PRODUCTS

A. Do not use materials and equipment removed from existing premises, except as specifically permitted by the Contract Documents.

B. Provide interchangeable components of the same manufacture for components being replaced.

1.3 PRODUCT DELIVERY REQUIREMENTS

A. Transport and handle Products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and Products are undamaged.

C. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement,

or damage. 1.4 PRODUCT STORAGE AND HANDLING REQUIREMENTS

A. Store and protect products in accordance with manufacturers' instructions. B. Store with seals and labels intact and legible.

C. Store sensitive Products in weather tight, climate controlled enclosures in an environment favorable

to product.

D. For exterior storage of fabricated products, place on sloped supports above ground.

E. Provide bonded off-site storage and protection when site does not permit on-site storage or protection.

Page 218: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Product Requirements The Public Library of Youngstown & Mahoning County 01 60 00 – 2

F. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.

G. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with

foreign matter.

H. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.

I. Arrange storage of products to permit access for inspection. Periodically inspect to verify products

are undamaged and are maintained in acceptable condition. 1.5 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:

Submit a request for substitution for any manufacturer not named in accordance with the following article.

1.6 PROPOSED EQUALS

A. Refer to Instructions to Bidders: Paragraph 2.5.

1.7 SUBSTITUTIONS

A. Instructions to Bidders specify time restrictions for submitting requests for proposed equals during the bidding period to requirements specified in this section.

B. Substitutions during construction may be considered when a product becomes unavailable through

no fault of the Contractor. C. Document each request with complete data substantiating compliance of proposed Substitution with

Contract Documents. D. A request constitutes a representation that the Contractor:

1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product.

2. Will provide the same warranty for the Substitution as for the specified product. 3. Will coordinate installation and make changes to other Work which may be required for the

Work to be complete with no additional cost to Owner. 4. Waives claims for additional costs or time extension which may subsequently become

apparent. 5. Will reimburse Owner and Architect for review or redesign services associated with re-

approval by authorities.

Page 219: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Product Requirements The Public Library of Youngstown & Mahoning County 01 60 00 – 3

E. Substitutions will not be considered when they are indicated or implied on Shop Drawing or Product Data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.

F. Substitution Submittal Procedure:

1. Submit three copies of request for Substitution for consideration. Limit each request to one proposed Substitution.

2. Submit Shop Drawings, Product Data, and certified test results attesting to proposed project equivalence. Burden of proof is on proposer.

3. Architect will notify Contractor in writing of decision to accept or reject request.

PART 2 PRODUCTS

Not Used. PART 3 EXECUTION

Not Used. END OF SECTION

Page 220: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 221: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Execution & Closeout Requirements The Public Library of Youngstown & Mahoning County 01 70 00-1

SECTION 01 70 00 EXECUTION REQUIREMENTS PART 1 GENERAL 1.1 SECTION INCLUDES

A. Closeout procedures.

B. Final cleaning. C. Protecting installed construction.

D. Project record documents.

E. Operation & Maintenance Data.

F. Product warranties and product bonds.

G. Maintenance service.

1.2 CLOSEOUT PROCEDURES

A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Architect's review. Contractor to submit punch list to Architect prior to his walk-through of the site.

B. Provide submittals to Architect that are required by governing or other authorities.

C. Submit final Application for Payment identifying total adjusted Contract Sum, previous payments,

and sum remaining due. 1.3 FINAL CLEANING (By General Contractor unless otherwise noted).

A. Prior to Final Project Acceptance by General Contractor, unless authorized, clean the site of all waste materials and rubbish attributable to the Work, including without limitation: 1. Remove labels that are not permanent, remove marks, stains and soiled spots from

finished surfaces.

2. Remove dust, dirt, marks, stains, paint droppings and other blemishes and leave in polished condition all equipment and material with exposed finished surfaces.

3. Clean exposed exterior hard-surfaced finishes to a dust-free condition, free of stains, films

and similar foreign substances.

4. Sweep paved areas broom clean, rake grounds that are neither paved nor planted to a smooth even-textured surface, and broom clean and damp mop concrete floors.

5. Remove all waste materials and rubbish from all surfaces.

Page 222: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Execution & Closeout Requirements The Public Library of Youngstown & Mahoning County 01 70 00-2

B. Should any Work be performed after a final cleaning by the Contractor, the Contractor responsible for such Work shall clean any affected area again as provided above so that upon Contract Completion, the premises shall be left ready for occupancy by the Owner.

C. Final cleaning shall be done to the reasonable satisfaction of the Architect and the Owner.

1. If the Contractor fails to clean up at completion of the Work, the provision of paragraph 6.3 of the General Conditions will be invoked.

2. If a dispute arises among Contractors as to responsibility for final cleaning, the Architect may authorize another Contractor, or engage a qualified cleaning company, to perform the clean up and deduct the cost from amounts due to those Contractors responsible as the Architect recommends. The decision of the Architect on the responsibility for such cost shall be final.

D. Each contractor shall remove his waste and surplus materials, rubbish, and construction facilities

from the site. 1.4 PROTECTING INSTALLED CONSTRUCTION

A. Protect installed work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed products. Control activity in immediate

work area to prevent damage.

C. Provide protective coverings at walls, jambs, sills and soffits of openings.

D. Prohibit traffic or storage upon waterproofed or roofed surfaces. If traffic or activity is necessary obtain recommendations for protection from waterproofing or roofing material manufacturer.

1.5 PROJECT RECORD DOCUMENTS

A. Maintain on site one set of the following record documents; record actual revisions to the Work: 1. Drawings. 2. Specifications. 3. Addenda. 4. Change Orders and other modifications to the Contract. 5. Reviewed Shop Drawings, Product Data, and Samples. 6. Manufacturer’s instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress, not less than weekly.

E. Specifications: Legibly mark and record at each Product section description of actual Products

installed, including the following: 1. Manufacturer’s name and product model and number. 2. Product substitutions or alternates utilized. 3. Changes made by Addenda and modifications.

Page 223: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Execution & Closeout Requirements The Public Library of Youngstown & Mahoning County 01 70 00-3

F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction

including: 1. Measured depths of foundations in relation to finish main floor datum. 2. Measured horizontal and vertical locations of underground utilities and appurtenances,

referenced to permanent surface improvements. 3. Measured locations of internal utilities and appurtenances concealed in construction,

referenced to visible and accessible features of the Work. 4. Field changes of dimension and detail. 5. Details not on original Contract drawings.

G. Submit documents to Architect with claim for final Application for Payment.

1.6 OPERATION AND MAINTENANCE DATA

A. Submit data bound in 8-1/2 x 11 inch, (A4) text pages, three D side ring binders with durable plastic covers; 2 inch maximum ring size. When multiple binders are used, correlate data into related consistent groupings.

B. Cover: Identify each binder with typed or printed title OPERATION AND MAINTENANCE

INSTRUCTIONS; identify title of Project; identify subject matter of contents.

C. Provide tabbed dividers for each separate product and system, with typed description of product and major component parts of equipment.

D. Text: Manufacturer’s printed data, or typewritten data on 24 pound paper.

E. Drawings: Provide with reinforced punched binder tab. Bind in with text; fold larger drawings to

size of text pages. F. Contents: Prepare a Table of Contents for each volume, with each Product or system description

identified, in three parts as follows: 1. Part 1: Directory, listing names, addresses, and telephone numbers of Architect,

Contractor, Subcontractors, and major equipment suppliers. 2. Part 2: Operation and maintenance instructions, arranged by system and subdivided by

specification section. For each category, identify names, addresses, and telephone numbers of Subcontractors and suppliers. Identify the following: a. Significant design criteria. b. List of equipment. c. Parts list for each component. d. Operating instructions. e. Maintenance instructions for equipment and systems. f. Maintenance instructions for special finishes, including recommended cleaning

methods and materials, and special precautions identifying detrimental agents. 3. Part 3: Project documents and certificates, including the following:

a. Shop drawings and product data. b. Certificates. c. Originals of warranties and bonds.

Page 224: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Execution & Closeout Requirements The Public Library of Youngstown & Mahoning County 01 70 00-4

G. Submit draft copy of completed volumes seven days prior to Substantial Completion. This copy

will be reviewed and returned after final inspection, with Architect’s comments. Revise content of all document sets as required prior to final submission.

H. Submit two sets of revised final volumes, within 10 days after Substantial Completion.

I. Materials and Finishes:

1. Building Products, Applied Materials, and Finishes: Include product data, with catalog number, size, composition, and color and texture designations.

2. Instructions for Care and Maintenance: Include manufacturer’s recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance.

3. Moisture Protection and Weather Exposed Products: Include product data listing applicable reference standards, chemical composition, and details of installation. Provide recommendations for inspections, maintenance, and repair.

4. Additional Requirements: As specified in individual product specification sections. 1.7 PRODUCT WARRANTIES AND PRODUCT BONDS

A. Obtain warranties and bonds executed in duplicate by responsible subcontractors suppliers, and manufacturers, include in Operation and Maintenance Manual.

B. Execute and assemble transferable warranty documents and bonds from subcontractors, suppliers,

and manufacturers.

C. Verify that documents are in proper form, contain full information, and are notarized.

D. Co-execute submittals when required. 1.8 MAINTENANCE SERVICE

A. Furnish service and maintenance of components as called for in specification sections.

B. Maintenance service shall not be assigned or transferred to any agent or Subcontractor without prior written consent of the Owner.

1.9 CLOSE-OUT REQUIREMENTS (Includes, but is not necessarily limited to the following):

A. Each Prime Contractor shall provide close-out documents, products, spare parts, maintenance and extra materials in quantities specified in individual specification Sections, and as follows: 1. Contractor’s Affidavit of Payment of Debts and Claims. 2. Contractor’s Affidavit of Release of Liens. 3. Consent of Surety to Final Payment. 4. List of Punch List or Work items not completed. 5. One (1) set of record drawings as described herein. 6. Final Payment Request. 7. Review individual specification sections and furnish extra materials which may be

required not listed herein. 8. Warranty for one (1) year for all work, including starting and expiration dates.

Page 225: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall – Poland Village Library Execution & Closeout Requirements The Public Library of Youngstown & Mahoning County 01 70 00-5

9. Warranties required beyond one (1) year as specified in the individual specification sections.

10. Operating instructions and maintenance manuals. PART 2 PRODUCTS

Not Used. PART 3 EXECUTION Not Used. END OF SECTION

Page 226: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING
Page 227: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall - Poland Village Library Precast Modular Block Gravity Retaining Wall The Public Library of Youngstown and Mahoning County 32 32 15 – 1

SECTION 32 32 15

PRECAST MODULAR BLOCK GRAVITY RETAINING WALL

PART 1 GENERAL

1.01 SUMMARY

A. This Section includes furnishing all materials and labor required for the design and construction of a precast concrete modular block (PMB) retaining wall without geosynthetic reinforcement. Precast modular block retaining wall blocks under this section shall be cast utilizing a wet-cast concrete mix.

B. Scope of Work: The work shall consist of furnishing materials, labor, equipment and supervision for the construction of a precast modular block (PMB) retaining wall structure in accordance with the requirements of this section and in acceptable conformity with the lines, grades, design and dimensions shown in the project site plans.

C. Drawings and General Provisions of the Contract, including General and Supplementary Conditions, Divison 32 apply to this Section.

1.02 REFERENCES

A. Where the specification and reference documents conflict, the more stringent requirement is applicable.

B. Definitions: 1. Precast Modular Block (PMB) Unit – machine-placed, “wet cast” concrete modular block

retaining wall facing unit. 2. Geotextile – a geosynthetic fabric manufactured for use as a separation and filtration medium

between dissimilar soil materials. 3. Drainage Aggregate – clean, crushed stone placed within and immediately behind the precast

modular block units to facilitate drainage and reduce compaction requirements immediately adjacent to and behind the precast modular block units.

4. Unit Core Fill – clean, crushed stone placed within the hollow vertical core of a precast modular block unit.

5. Foundation Zone – soil zone immediately beneath the leveling pad. 6. Retained Zone – soil zone immediately behind the drainage aggregate and wall infill for wall

sections designed as modular gravity structures. 7. Leveling Pad – hard, flat surface upon which the bottom course of precast modular blocks are

placed. The leveling pad may be constructed with crushed stone or cast-in-place concrete. A leveling pad is not a structural footing.

8. Wall Infill – the fill material placed and compacted between the drainage aggregate and the excavated soil face in retaining wall sections designed as modular gravity structures.

Page 228: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall - Poland Village Library Precast Modular Block Gravity Retaining Wall The Public Library of Youngstown and Mahoning County 32 32 15 – 2

C. Reference Standards 1. Design LRFD Bridge Design Specifications, 7th Edition, 2014.

a. Ohio Building Code. b. Design Manual for Segmental Retaining Walls, National Concrete Masonry Association,

3rd Edition, 2010

2. Precast Modular Block Units a. ACI 201 – Guide to Durable Concrete b. ACI 318 – Building Code Requirements for Structural Concrete c. ASTM C1776 – Standard Specification for Wet-Cast Precast Modular Retaining Wall

Units. d. ASTM D6638 – Standard Test Method for Determining Connection Strength Between

Geosynthetic Reinforcement and Segmental Concrete Units (Modular Concrete Blocks). e. ASTM D6916 – Standard Test Method for Determining Shear Strength Between

Segmental Concrete Units (Modular Concrete Blocks).

3. Geosynthetics a. AASHTO M 288 – Geotextile Specification for Highway Applications.

4. Soils a. AASHTO M 145 – AASHTO Soil Classification System.

5. Drainage Pipe

a. ASTM D3034 – Standard Specification for Type PSM Poly (Vinyl Chloride) (PVC) Sewer Pipe and Fittings.

1.03 ADMINISTRATIVE REQUIREMENTS

A. Preconstruction meeting will be scheduled per the requirements of section 01 30 00. The meeting will cover the following items for the retaining wall. 1. Retaining Wall Supplier will review the installation requirements for the retaining wall

including but not limited to the following. a. The required bearing capacity of soil below the retaining wall structure. b. The required shear strength of fill soil in the retained and foundation zones.

1.04 SUBMITTALS

A. Reference Section 01 33 00 for Submittal procedures and requirements. Submittal for the retaining wall will include the following. 1. Retaining wall layout. 2. Concrete mix design for retaining wall units. 3. Drainage pipe layout and specification. 4. Geotextile specification. 5. Retaining wall calculations sealed by an engineer registered in the state of Ohio.

Page 229: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall - Poland Village Library Precast Modular Block Gravity Retaining Wall The Public Library of Youngstown and Mahoning County 32 32 15 – 3

1.05 QUALITY ASSURANCE

A. Retaining Wall Manufacturer. The Retaining Wall Manufacturer shall have a minimum of five years of experience in the design and fabrication of precast modular concrete retaining walls of the type describe in the drawings and specified here in.

B. Retaining Wall Installer. The Retaining Wall Installer shall have a minimum of five years of experience in the design and fabrication of precast modular concrete retaining walls of the type describe in the drawings and specified here in.

1.06 DELIVERY, STORAGE AND HANDLING

A. Contractor shall store and handle all materials in accordance with the manufacturer’s recommendations as specified herein and in a manner that prevents deterioration or damage due to moisture, temperature changes, contaminants, corrosion, breaking, chipping, UV exposure or other causes. Damaged materials shall not be incorporated into the work.

PART 2 PRODUCTS

2.01 PRECAST MODULAR BLOCK RETAINING WALL UNITS

A. All units shall be wet-cast precast modular retaining wall units conforming to ASTM C1776.

B. All units for the project shall be obtained from the same manufacturer.

C. Concrete must have a minimum 28-day compressive strength of 4,000 psi (Test method ASTM C39).

D. Maximum water cement ratio, nominal maximum aggregate size, aggregate class designation, air content and slump allowances per precast modular block manufacturer’s design allowances.

E. The precast modular block unit face texture shall be selected by the owner from the available range of

textures available from the precast modular block manufacturer.

F. The block color shall be selected by the owner from the available range of colors available from the precast modular block manufacturer.

G. All precast modular block units shall be sound and free of cracks or other defects that would interfere

with the proper installation of the unit, impair the strength or performance of the constructed wall. PMB units to be used in exposed wall construction shall not exhibit chips or cracks in the exposed face or faces of the unit that are not otherwise permitted.

H. Preapproved Manufacturers.

1. Manufacturers of Redi-Rock Retaining Wall Systems as licensed by Redi-Rock International, LLC, 05481 US 31 South, Charlevoix, MI 49720 USA; telephone (866) 222-8400; website www.redi-rock.com.

Page 230: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall - Poland Village Library Precast Modular Block Gravity Retaining Wall The Public Library of Youngstown and Mahoning County 32 32 15 – 4

2. Proposed Equals: In accordance with Instructions To Bidders.

2.02 GEOTEXTILE

A. Nonwoven geotextile fabric shall be placed as indicated on the retaining wall construction shop drawings. Additionally, the nonwoven geotextile fabric shall be placed in the v-shaped joint between adjacent block units on the same course. The nonwoven geotextile fabric shall meet the requirements Class 3 construction survivability in accordance with AASHTO M 288.

B. Preapproved Nonwoven Geotextile Products

1. Mirafi 140N 2. Propex Geotex 451 3. Skaps GT-142 4. Thrace-Linq 140EX 5. Carthage Mills FX-40HS 6. Stratatex ST 142

2.03 DRAINAGE AGGREGATE AND WALL INFILL

A. Drainage aggregate (and wall infill for retaining walls designed as modular gravity structures) shall be a durable crushed stone conforming to No. 57 size per ASTM C33 with the following particle-size distribution requirements per ASTM D422:

U.S. Standard Sieve Size

% Passing

1-½” (38 mm) 100 1” (25 mm) 95-100 ½” (13 mm) 25-60 No. 4 (4.76 mm) 0-10 No. 8 (2.38 mm) 0-5

2.04 LEVELING PAD

A. Crushed stone used for construction of a granular leveling pad shall meet the requirements of the drainage aggregate and wall infill in section 2.03 or a preapproved alternate material.

B. Concrete used for construction of an unreinforced concrete leveling pad shall satisfy the criteria for

AASHTO Class B. The concrete should be cured a minimum of 12 hours prior to placement of the precast modular block wall retaining units and exhibit a minimum 28-day compressive strength of 2,500 psi (17.2 MPa).

Page 231: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall - Poland Village Library Precast Modular Block Gravity Retaining Wall The Public Library of Youngstown and Mahoning County 32 32 15 – 5

2.05 DRAINAGE

A. Drainage Pipe 1. Drainage collection pipe shall be 6 inch conduit, Type E, ODOT 707.41, non-perforated from

the wall drain to catch basin. This pipe shall have 4 rows of perforations. The wall drain shall be perforated, 6 inch diameter, 4 rows of perforations, Type E, ODOT 707.

B. Preapproved Drainage Pipe Products

1. Pipe shall meet ODOT 707.41, PVC or equal. 2. Proposed Equals: In accordance with Instructions To Bidders, Article 2.5.

PART 3 EXECUTION

3.01 GENERAL

A. All work shall be performed in accordance with OSHA safety standards, state and local building codes and manufacturer’s requirements.

B. The Contractor is responsible for the location and protection of all existing underground utilities. Any

new utilities proposed for installation in the vicinity of the retaining wall, shall be installed concurrent with retaining wall construction. The Contractor shall coordinate the work of subcontractors affected by this requirement.

C. New utilities installed below the retaining wall shall be backfilled and compacted to a minimum of

98% maximum dry density per ASTM D698 standard proctor. D. The Contractor is responsible to ensure that safe excavations and embankments are maintained

throughout the course of the project.

3.02 EXAMINATION

A. Prior to construction, the Contractor shall examine the areas in which the retaining wall will be constructed to evaluate compliance with the requirements for installation tolerances, worker safety and any site conditions affecting performance of the completed structure. Installation shall proceed only after unsatisfactory conditions have been corrected.

3.03 PREPARATION

A. Fill Soil. 1. The Contractor shall verify that retained backfill material placed within a horizontal distance of

one (1.0) times the wall height behind the wall blocks satisfies the criteria of this section. 2. The Contractor shall verify that any fill soil installed in the foundation and retained soil zones of

the retaining wall satisfies the specification of the Retaining Wall Manufacturer as shown on the reviewed shop drawings.

Page 232: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall - Poland Village Library Precast Modular Block Gravity Retaining Wall The Public Library of Youngstown and Mahoning County 32 32 15 – 6

B. Excavation. 1. The Contractor shall excavate to the lines and grades required for construction of the precast

modular block retaining wall as shown on the reviewed shop drawings. The Contractor shall minimize over-excavation.

2. Over-excavated soil shall be replaced with compacted fill in conformance with the geotechnical report provided.

C. Foundation Preparation.

1. Foundation soils found to be unsatisfactory beyond the specified undercut limits shall be undercut and replaced with approved fill.

2. Following excavation for the leveling pad the Contractor will have the shear strength of the in-situ soil verified. If the shear strength of the in-situ soil does not meet project requirements the Contractor will immediately stop work and notify the Owner.

D. Leveling Pad.

1. The leveling pad shall be constructed to provide a level, hard surface on which to place the first course of precast modular block units. The leveling pad shall be placed in the dimensions shown on the reviewed retaining wall shop drawings and extend to the limits indicated.

2. Crushed Stone Leveling Pad. Crushed stone shall be placed in uniform maximum lifts of 6”. The crushed stone shall be compacted by a minimum of 3 passes of a vibratory compactor capable of exerting 2,000 lb of centrifugal force.

3. Unreinforced Concrete Leveling Pad. The concrete shall be placed in the same dimensions as those required for the crushed stone leveling pad.

3.04 PRECAST MODULAR BLOCK WALL SYSTEM INSTALLATION

A. The precast modular block structure shall be constructed in accordance with the reviewed shop

drawings, these specifications and the recommendations of the retaining wall system component manufacturers. Where conflicts exist between the manufacturer’s recommendations and these specifications, the more stringent requirement shall prevail.

B. Drainage components. Pipe, geotextile and drainage aggregate shall be installed as shown on the

reviewed shop drawings.

C. Precast Modular Block Installation 1. Precast Modular Block Retaining wall will be placed per manufacturer’s written instructions

and the reviewed shop drawings.

D. Construction Tolerance. Allowable construction tolerance of the retaining wall shall be as follows: 1. Deviation from the design batter and horizontal alignment, when measured along a 10’ straight

wall section, shall not exceed 3/4”. 2. Deviation from the overall design batter shall not exceed 1/2 inch per 10 Ft. of wall height. 3. The maximum allowable offset (horizontal bulge) of the face in any precast modular block joint

shall be 1/2 inch.

Page 233: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING

64-12A01 – Retaining Wall - Poland Village Library Precast Modular Block Gravity Retaining Wall The Public Library of Youngstown and Mahoning County 32 32 15 – 7

4. The base of the precast modular block wall excavation shall be within 2 inches of the staked elevations, unless otherwise approved by the Inspection Engineer.

5. Differential vertical settlement of the face shall not exceed 1Ft. along any 200 Ft. of wall length. 6. The maximum allowable vertical displacement of the face in any precast modular block joint

shall be 1/2 inch. 7. The wall face shall be placed within 2 inches of the horizontal location staked.

3.05 WALL INFILL AND BACKFILL PLACEMENT

A. Wall infill and backfill placement will be placed per manufacturer’s written instructions and the reviewed shop drawings.

3.06 OBSTRUCTIONS IN THE INFILL ZONE

A. Contractor shall make all required allowances for obstructions behind and through the wall face in accordance with the reviewed shop drawings.

B. Should unplanned obstructions become apparent for which the reviewed shop drawings do not

account, the affected portion of the wall shall not be constructed until the condition is reviewed by the Retaining Wall Manufacturer.

3.07 COMPLETION

A. For walls supporting unpaved areas, a minimum of 12 inches of compacted, low-permeability fill shall be placed over the granular wall infill zone of the precast modular block retaining wall structure. The adjacent retained soil shall be graded to prevent ponding of water behind the completed retaining wall.

B. The Contractor shall confirm that the as-built precast modular block wall geometries conform to the

requirements of this section. The Contractor shall notify the Owner of any deviations.

END OF SECTION

Page 234: PROJECT MANUAL - libraryvisit.org...PROJECT MANUAL RETAINING WALL AT POLAND VILLAGE LIBRARY 311 South Main Street, Poland, OH 44514 FOR: THE PUBLIC LIBRARY OF YOUNGSTOWN & MAHONING