 Project Manual 

Mashburn Hall Re‐roof & Deck Replacement  

 

UCA‐18‐108 

 

Bid Date: June 19, 2018 Time: 9:00 a.m. 

Issue Date: May 18, 2018 Mandatory Pre-Bid Meeting: June 5, 2018 Time: 9:00 a.m.

Page 2: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

Index Page 1

UCA Mashburn Hall Reroofing and Index Deck Replacement SMA #1505H

INDEX TO THE PROJECT MANUAL INCLUDING SPECIFICATIONS

MASHBURN HALL REROOFING AND DECK REPLACEMENT University of Central Arkansas

Conway, Arkansas

UCA #18-108 SMA #1505H

Issued: May 18, 2018 DIVISION 00 – BIDDING REQUIREMENTS & CONDITIONS OF THE CONTRACT 001116 Invitation to Bid 002113 Instructions to Bidders 004113 Bid Form 004321 Allowance Form 004322 Unit Prices Form 005213 Agreement Form (Contract) 006113 Performance and Payment Bond 006519.16 Release of Claims Form 006519.19 Consent of Surety Form 007213 General Conditions 007316 Insurance Requirements DIVISION 01 - GENERAL REQUIREMENTS 011000 Summary 012100 Allowances 012200 Unit Prices 012500 Substitution Procedures 012600 Contract Modification Procedures 012900 Payment Procedures 013100 Project Management And Coordination 013200 Construction Progress Documentation 013300 Submittal Procedures 014000 Quality Requirements 014200 References 015000 Temporary Facilities And Controls 016000 Product Requirements Substitution Request Form 017300 Execution 017700 Closeout Procedures 017823 Operation And Maintenance Data 017839 Project Record Documents

Page 3: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

Index Page 2

UCA Mashburn Hall Reroofing and Index Deck Replacement SMA #1505H

DIVISION 02 - EXISTING CONDITIONS 024119 Selective Demolition DIVISION 03 – CONCRETE None in this Contract DIVISION 04 – MASONRY None in this Contract DIVISION 05 – METALS 053100 Steel Decking DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES 061053 Miscellaneous Rough Carpentry DIVISION 07 - THERMAL AND MOISTURE PROTECTION 07015019 Preparation for Reroofing 072100 Thermal Insulation 075423 Thermoplastic Polyolefin (TPO) Roofing 077100 Roof Specialties 079200 Joint Sealants DIVISION 08 – OPENINGS None in this Contract DIVISION 09 – FINISHES 099123 Painting DIVISION 10 – SPECIALTIES None in this Contract DIVISION 11 – EQUIPMENT None in this Contract DIVISION 12 – FURNISHINGS None in this Contract

Page 4: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

Index Page 3

UCA Mashburn Hall Reroofing and Index Deck Replacement SMA #1505H

DIVISION 13 - SPECIAL CONSTRUCTION None in this Contract DIVISION 14 - CONVEYING SYSTEMS None in this Contract END OF INDEX

Page 5: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

INVITATION TO BID

Section 001116 University of Central Arkansas 2125 College Avenue, Suite 2, Conway, AR 72034 Issuing Officer: Jerry Coleman, Buyer Email: [email protected] Phone: 501-450-3173

Bid #: UCA-18-108 Description: Mashburn Hall Reroof & Deck Replacement Construction Coordinator: Kevin Carter Cell: (501) 428-0505 Email: [email protected]

1. You are invited to bid on a General Contract for the reroofing of the Mashburn Hall

Building located on the campus of the University of Central Arkansas hereinafter termed Owner. The bids shall be on a lump sum basis.

2. There will be a Mandatory Pre-Bid Conference meeting held at 9:00 a.m.

on June 5, 2018 in the UCA Police and Outreach Center Conference Room, 2125 College Avenue, Suite 3, Conway, AR 72034. UCA reserves the right to schedule additional meetings.

3. Owner will receive bids until 9:00 a.m. local time, on June 19, 2018. Bids may

be mailed or delivered to the UCA Purchasing Department, 2125 College Avenue, Suite 2, Conway, AR 72034, hereinafter termed UCA. Bids received after this time will not be accepted. Bids will be publicly opened and read aloud at the time and date mentioned. Interested parties are invited to attend. Faxed bids exceeding $20,000.00 will be rejected.

4. UCA, unless designated to another entity, supervises the bidding and awarding of

all construction contracts, approves contract change orders, requests for payment and ensures that on-site observations are accomplished.

5. Prime Bidders may obtain up to three (3) sets of bidding documents, available at

Southern Reprographics, 901 West 7th Street, Little Rock, Arkansas, 72201, (501) 372-4011. Prime Bidders must deposit a check in the amount of $50.00 per set, payable to Stocks Mann Architects, PLC. Deposits will be refunded to all prime bidders who submit a bid and return bidding documents in good condition within ten (10) days after opening bids. A Bidder receiving a contract may retain the bidding documents and the Bidder’s deposit will be refunded. Prime Bidders requiring additional sets and Sub-bidders may purchase bidding documents through Southern Reprographics. Shipping and delivery charges will be in addition to the deposit and are non-refundable. Plans and specs are available in PDF form to Prime Bidders from Stocks Mann Architects, PLC. Prime Bidders may contact via email: Mark Mann, ([email protected]) and plans and specs will be sent via email to the request made. Obtaining bid documents other the listed company is not advisable due to the risks of receiving incomplete or inaccurate information.

Page 6: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

6. Bid Security in the amount of five percent (5%) of the Bid must accompany each Bid in accordance with the Instructions to Bidders.

7. Bidders are hereby notified that any bidder who desires to enter into Contract for

this work must comply with disclosure requirements pursuant to Governor Executive Order 98-04. Submission to UCA of completed Disclosure form will be a condition of the Contract. UCA cannot enter into any contract nor can UCA approve any contract, which does not obligate the contractor to require the submission of Disclosure forms for subcontractors.

8. UCA reserves the rights to reject any and all bids, and to waive any

formalities. Bidders shall conform to the requirements of the Arkansas licensing laws and regulations for contractors, and shall be licensed before his bid is submitted unless the project is federally funded and therefore excepted by Ark. Code Ann. §17-25-315.

9. Pursuant to Ark. Code Ann. § 22-9-203, UCA encourages all small, minority, and

women business enterprises to submit bids for capital improvements. Encouragement is also made to all general contractors that in the event they subcontract portions of their work, consideration is given to the identified groups.

10. Pursuant to Ark. Code Ann. § 22-9-203, In the event that all bids submitted

exceed the amount appropriated for the award of the contract, the state agency or its designated representatives shall have the authority to negotiate an award with the apparent responsible low bidder but only if the low bid is within twenty-five percent (25%) of the amount appropriated.

End of INVITATION TO BID

001116

Page 7: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

INSTRUCTIONS TO BIDDERS

Section 002113 1. BIDDING DOCUMENTS. Bidders may obtain complete sets of Contract

Documents from issuing office designated in the Invitation to Bid. Complete sets of Contract Documents must be used in preparing bids; neither Owner nor Design Professional assume responsibility for errors or misinterpretations resulting from the use of incomplete sets of Contract Documents. Obtaining Contract documents through any source other than the Design Professional listed in the Invitation to Bid is not advisable due to the risks of receiving incomplete or inaccurate information, and the bidder runs the risk of basing bidder’s proposal on such information. The documents obtained through the Design Professional or his representative(s) or UCA are considered the official version and take precedence if any discrepancies occur. The fact that documents used for bidding purposes are named “contract documents“ does not diminish in any way the right of UCA to reject any and all bids and to waive any formality.

2. EXAMINATION OF DRAWINGS, SPECIFICATIONS AND SITE OF WORK.

Bidder shall examine the Contract Documents and visit the project site of work. Bidder shall become familiar with all existing conditions and limitations under which the Work is to be performed, and shall base bid on items necessary to perform the Work as set forth in the Contract Documents. No allowance will be made to Bidder because of lack of such examination or knowledge. The submission of a Bid shall be construed as conclusive evidence that the Bidder has made such examination.

3. INTERPRETATION OF CONTRACT DOCUMENTS DURING BIDDING. 3.1 All references to the Owner shall be interpreted to mean the Agency for whom

the work is being contracted. 3.2 If any person contemplating submitting a Bid is in doubt as to the true meaning

of any part of the Contract Documents or finds discrepancies in or omissions from any part of the Contract Documents, he may submit to the Design Professional a written request for an interpretation or correction thereof not later than five (5) calendar days before Bid opening. In those instances where a Design Professional is not involved with the project, written requests for interpretation or correction may be made to the UCA Purchasing Department within the time frame stated above.

3.3 Address all communications regarding the Contract Documents to the Design

Professional, Stocks Mann Architects, PLC, 401 West Capital, Suite 402, Little Rock, AR 72201. Mark Mann (501-370-9207).

3.4 Interpretation or correction of the Contract Documents will be made only by

Addendum and will be mailed, faxed or delivered to each Bidder of record by the Design Professional; and in those instances where a Design Professional is

Page 8: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

not involved the UCA Purchasing Department shall distribute Addenda in the above referenced manner. UCA will not be responsible for oral explanations or interpretation of the Contract Documents.

3.5 Addenda issued during the bidding period will be incorporated into the Contract

Documents. 4. SUBSTITUTIONS. 4.1 Materials, products, and equipment described in the Contract Documents

establish a standard of required function and a minimum desired quality or performance level, or other minimum dimensions and capacities, to be met by any proposed substitution. Acceptability of substitutions will not be considered during bidding period.

4.2 In some cases, prior approval of material or equipment, or both shall be

obtained from Owner in order to obtain the desired color, size, visual appearance, and other features specified.

5. TYPE OF BID. 5.1 The Work under this Contract will be awarded under a stipulated sum contract

to the lowest responsible base bid amount. No segregated bids or assignments will be considered.

5.2 The estimate of quantities is approximate only and shall be the basis for

receiving unit price bids for each item, but shall not be considered by the Bidder as the actual quantities that may be required for the completion of the proposed work. Bidder shall state a unit price for every item of work named in the Proposal. Bidder shall include, in the unit prices, furnishing of labor, materials, tools, equipment, and apparatus of every description to construct, erect, and finish the Work. The unit price bid for the items shall be shown numerically and in the appropriate spaces provided on the Bid Form. Such figures shall be clear and distinctly legible so that no question can arise as to their intent or meaning. Unit price bids and totals shown in the Bid Form shall not include costs of engineering, advertising, printing and appraising.

6. PREPARATION OF BID. Bid shall be made on an unaltered Bid Form

identical to the form included with the Contract Documents. Fill in all blank spaces and submit one original. Bids shall be signed with name typed below the signature. Where Bidder is a corporation, bids shall be signed with the legal name of the corporation followed by the name of the state of incorporation, contractor’s license number issued by the Contractors Licensing Board, and the signature of an authorized officer of the corporation.

6.1 Bids submitted by a “Joint Venture/Joint Adventure” shall be signed by

representatives of each component part of the Joint Venture. The licenses of each component part of the Joint Venture shall also be listed in the bid submittal. Therefore, joint venture bidders shall indicate at least two (2)

Page 9: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

signatures and two (2) licenses numbers on the Bid Form. Exception: Joint Ventures who have been properly licensed with the Arkansas Contractors Licensing Board as a “Joint Venture” need only to indicate the joint venture license number on the Bid Form. Joint Venture Bidders shall indicate at least two (2) signatures on the bid form even if they are licensed as a joint venture

7. BID GUARANTEE AND BONDS. 7.1 Each bid proposal shall include a bid security in the amount of five percent of

the total bid offered, if the bid is in excess of $35,000.00. The bidder will be required to submit a bidder’s deposit, which includes enclosing a cashiers’ check payable to the order of UCA drawn upon a bank or trust company doing business in Arkansas or by a corporate bid bond in an amount equal to five (5) percent of the bid. The bidder shall include in the bid the bid bond amount so that the bid represents the total cost to the Owner of all work included in the contract.

7.2 The bid bond shall indemnify the Owner against failure of the Contractor to

execute and deliver the contract and necessary bond (Performance and Payment Bond) for faithful performance of the contract. The bid bond shall provide that the contractor or surety must pay the damage, loss, cost and expense subject to the amount of the bid security directly arising out of the Contractor’s default in failing to execute and deliver the contract and bonds.

7.3 Owner will have the right to retain the bid security of bidders to whom an

award is being considered until the Contract has been executed and bonds if required, have been furnished, or until specified time has elapsed so that bids may be withdrawn, or all bids have been rejected.

7.4 Failure to execute the Contract and file an acceptable full payment and

performance bond and proof of liability insurance within 10 working days after the intent to award has been issued to the bidder shall be just cause for the cancellation of the award and forfeiture of the bid bond, which shall become the property of the agency, not as a penalty but in liquidated damages sustained. Award may then be made to the next lowest responsible bidder, or the work may be rebid and constructed under contract or otherwise as the State determines. The low bidder who fails to execute the Contract and submit an acceptable payment and performance bond and proof of liability insurance will not be permitted to bid on any subsequent advertisement of that project.

8. PERFORMANCE AND PAYMENT BOND. Performance and Payment Bonds

are not required for bids $20,000.00 or under, except for roofing projects. For work exceeding $20,000.00, the bidder shall furnish a Performance and Payment Bond in the amount equal to 100 percent of contract price, on a form identical to the Arkansas Statutory Performance and Payment Bond Form included with the Contract Documents as security for faithful performance of the Contract and payment of all obligations arising thereunder within ten days after receipt of the Intent to Award. The bond shall be written by a surety

Page 10: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

company qualified and authorized to do business in the State of Arkansas. The bond shall be executed by a resident or non-resident agent licensed by the State Insurance Commissioner, to represent the surety company. The bond shall be written in favor of the Owner. Bidder shall file the bond with the Circuit Clerk in Faulkner County. Failure to deliver said bonds, as specified, shall be considered as having abandoned the Contract and the bid security will be retained as liquidated damages. The bidder shall include in the bid the Performance and Payment bond amount so that the bid represents the total cost to the Owner of all work included in the contract.

9. SUBCONTRACTORS. Name of principal subcontractors shall be listed where

indicated on the Bid Form in accordance with Ark. Code Ann. § 22-9-204 and the contract documents. All prime contractors, as a condition to perform construction work for and in the State of Arkansas, shall use no other subcontractors when the subcontractor’s portion of the project is $50,000.00 or more, except those qualified and licensed by the Contractors Licensing Board in Mechanical (HVAC), Plumbing, Electrical and Roofing.

A bidder should request clarification from the Design Professional (or UCA Purchasing Department, if no Design Professional exists for the project), if the bidder determines a type of work (mechanical –indicative of HVACR; electrical – indicative of wiring and illuminating fixtures; plumbing; roofing and sheet metal work - indicative of roofing application) is a component of the project, but space has not been provided on the bid form for the listing of such or if the bid form lists a type of work that is not a component of the project. Clarification should be made in accordance with Instruction 3.2.

9.1 For those bids where the listed subcontract work is $50,000.00 or more, the

prime contractor must make a decision as to which subcontractor he intends to use. The prime contractor shall place the names of each subcontractor and indicate whether the amount of the listed work is $50,000.00 or more in the space provided on the Bid Form. The prime contractor may use his own forces to do the listed work however, if the listed work is $50,000.00 or more, the prime contractor must be qualified and licensed by the Arkansas Contractors Licensing Board to perform the listed work. Once the prime contractor determines his own forces will be used, he shall place his name, and indicate in the space provided on the Bid Form whether the amount of the listed work is $50,000.00 or more. Failure to complete the form correctly shall cause the bid to be declared non-responsive, and the bid will not receive consideration.

9.2.1 In the event the amount of the listed subcontract work is below $50,000.00,

the Prime Contractor shall place the names of the person or firm performing the work and indicate in the space provided on the Bid Form whether the listed work is under $50,000.00. Failure to complete the form correctly shall cause the bid to be declared non-responsive, and the bid will not receive consideration.

9.2.2 It shall be mandatory that any subcontractors listed on the Bid Form by the

Prime Contractor is awarded a contract under Ark. Code Ann. § 22-9-204. Prime

Page 11: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

Contractors who submit a bid listing unlicensed subcontractors or use unlicensed subcontractors on a state project or any subcontractor not licensed by the Contractors Licensing Board who perform work having a value of $50,000.00 or more on a state project are subject to a civil penalty, after notice and hearing, of not less than $250.00 nor more than $500.00 and may be suspended from bidding on state projects. In the event that one (1) or more of the subcontractors named by the prime contractor in his successful bid thereafter refuse to perform his contract or offered contract, the prime contractor may substitute another subcontractor, after having obtained prior approval from the design professional and UCA.

9.3. Electrical License Requirement a. No person shall perform electrical work on the contract without

possessing an Arkansas State Master or Journeyman License from the Arkansas State Electrical Examiners Board. All electrical work and apprentice electricians shall be supervised by a Master or Journeyman Electrician on a one to one ratio.

b. All electricians shall have a copy of their license with them and shall be

required to show it to an appropriate inspector upon request.

9.4 Pursuant to Ark. Code Ann. § 22-9- 404, the Bidder may require listed subcontractors (mechanical, plumbing, electrical and roofing/sheet metal) whose bid to the Contractor exceeds $50,000.00 to provide a Performance and Payment Bond to the Bidder.

10. SUBMITTAL. Submit bid on the Bid Form in an opaque, sealed envelope.

Identify the envelope with: project name and number, name of Bidder, and Arkansas Contractors License number; only one bid shall be submitted per State Contractors license number. Submit bids in accordance with the Invitation to Bid. All blanks on the form shall be filled out in ink or be typewritten. Erroneous entries, alterations, and erasures shall be lined out, initialed by the Bidder, and the corrected entry inserted on the Bid Form.

11. MODIFICATION AND WITHDRAWAL. Bidder may withdraw bid at any time

before bid opening and may resubmit up to the date and time designated for receipt of bids. No bid may be withdrawn or modified after time has been called for the bid opening. Oral modifications to bids will not be considered. Bidder may submit written modifications to bid in writing or by facsimile at any time prior to the expiration of the bidding time and date and shall so state the word modification(s) as to not reveal the amount of the original bid. Facsimile modifications shall require written confirmation of the Bidder's signature within 24 hours after bid opening. Should the modification reveal the total bid amount, the entire bid will be rejected.

12. DISQUALIFICATION OF BIDDERS. The State shall have the right to

disqualify bids (before or after opening), which includes but is not limited to, evidence of collusion with intent to defraud or other illegal practices upon the part of the Bidder, to reject a bid not accompanied by the required bid security

Page 12: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

or by other data required by the Contract Documents, or to reject a Bid which is in any way incomplete or irregular.

13. APPLICABLE LAWS. 13.1 Labor. Contractors employed upon the work will be required to conform to the

labor laws of the State of Arkansas and the various acts amendatory and supplementary thereto, and to all the laws, regulations, and legal requirements applicable thereto.

13.2 Discrimination. Bidder shall not discriminate against any employee, applicant

for employment, or subcontractor as provided by law. Bidder shall be responsible for ensuring that all subcontractors comply with federal and state laws and regulations related to discrimination. Upon a final determination by a court or administrative body having proper jurisdiction that the Bidder has violated state or federal laws or regulations, the Owner may impose a range for appropriate remedies up to and including termination of the Contract.

13.3 Taxes. Bidder shall include in the bid all state sales tax, social security taxes,

state unemployment insurance, and all other items of like nature. It is the intent that the bid shall represent the total cost to the Owner of all work included in the contract. There are no provisions for a contractor to avoid taxes by using the tax exempt number of a state agency, board, commission or institutions. Said taxes shall be included in the bid price.

13.4 State licensing laws for Contractors. 13.5 Disclosure. Potential Bidders are hereby notified that any bidder who desires to

enter into a contract not exempted from the disclosure requirements, that disclosure is a condition of the Contract and that UCA cannot enter into any such contract, nor approve any such contract, for which disclosures are not made and the verbiage of paragraphs a, b, and c below will be included in the body of any contract awarded.

Potential Bidders are hereby notified that:

a. Disclosure is required to be a condition of any present or future subcontract for which the total consideration is greater than twenty-five thousand ($25,000)

b. The Contractor shall require any present or future subcontractor, for which the subcontract amount is greater than $25,000.00, to complete and sign the Contract and Disclosure and Certification. The contractor shall ensure that any agreement, current or future between the contractor and a subcontractor for which the total consideration is greater than $25,000.00 shall contain the following:

Failure to make any disclosure required by Governor Executive Order 98-04, or any violation of any rule, regulation or adopted pursuant to that Order, shall be material breach of the term of this subcontract. The party

Page 13: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

who fails to make the required disclosure or who violates the rule, regulation, or policy shall be subject to all legal remedies available to the contractor.

c. The Contractor shall transmit a copy of the subcontractor’s disclosure form to the agency.

13.6 Minority Participation: Pursuant to Ark. Code Ann. § 22-9-203, the State

encourages all small, minority, and women business enterprises to submit bids for capital improvements. Encouragement is also made to all general contractors that in the event they subcontract portions of their work, consideration is given to the identified groups.

13.7 The bidding, award and administration of the contract shall be made pursuant

to Ark. Code Ann. §14-4-1401 et seq., Ark. Code Ann. § 22-9-101 et seq., Ark. Code Ann. § 22-2-101 et seq.

14. LIQUIDATED DAMAGES. The amount of liquidated damages to be assessed

shall be in accordance with the amount indicated in the Contract. Bidder understands and agrees that under the terms of the Contract to be awarded, if the Contractor fails to complete the work within the time limit specified in the Contract, the Contractor shall pay the Owner as Liquidated Damages, and not in the nature of a penalty the sum specified in the Bid Form for each day completion is delayed. It is further understood and agreed by bidder that the said sum fixed as Liquidated Damages is a reasonable sum considering the damages that Owner will sustain in the event of any delay in completion of the Work, and said sum is herein agreed upon and fixed as Liquidated Damages because of difficulty in ascertaining the exact amount of damages that may be sustained by such delay.

15. PREBID CONFERENCE. There will be a Mandatory Pre-Bid Conference

meeting held on June 5, 2018 at 9:00 a.m. in the UCA Police and Outreach Center located at 2125 College Avenue, Suite #3, Conway, AR 72034. All prospective bidders are encouraged to attend. UCA reserves the right to reschedule the Pre-Bid Conference or to schedule additional conferences.

16. OPENING. Bids will be opened as identified in the Invitation to Bid. 17. EVALUATION AND CONSIDERATION OF BIDS. It is the intent of UCA to

award a Contract to the 1owest responsive qualified Bidder provided the bid has been submitted in accordance with the requirements of the Contract Documents and does not exceed the funds certified for the project by more than 25%. UCA shall have the right to waive any formalities in a bid received and to accept the bid which, in UCA's judgment, is in its best interests and upon approval of UCA. UCA shall have the right to accept any or all bids for a period not to exceed 30 days.

17.1 Tie Bids. If two or more sealed bids are equal in amount, meet Bidding Document requirements, and are the lowest received by the time of the bid

Page 14: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

opening, then the apparent low bidder will be determined by lot (placing the name of the tie bidders into a container and drawing one name). The drawing will be conducted by UCA personnel and another person so designated by UCA in the presence of a witness and the tie bidders or representatives. The witness shall be an employee of the State of Arkansas. Documentation of the drawing shall be included on the bid tabulation and be signed by those present. Nothing in the above and foregoing will diminish UCA’s reserved right to reject any and all bids and to waive any formalities.

17.2 Protests. Any actual or prospective bidder who is aggrieved in connection with the project documents or award of a capital improvement contract has the right to protest to the University Vice President of Finance and Administration or the University Agency Purchasing Official. The protest shall be submitted in writing within five (5) business days after the bid opening; in the event a bidder is declared non-responsive or rejected after the five (5) day period, the bidder shall have three (3) business days from the declaration to submit a protest. All protests shall identify the project by bid number or with sufficient detail to identify the project, and shall with specificity, set forth the allegations of the acts or omissions related to the protest. Since time is of the essence in award of all capital improvement contracts, protests and their resolution shall be resolved promptly. Subcontractors or suppliers are not considered bidders under this subsection. Only official representatives of the actual or prospective bidder may submit a protest. This section shall not be construed as a waiver of the State’s right to reject any or all bids and to waive any formalities. The University Vice President of Finance and Administration or the Agency Purchasing Official (performing the bid opening) or a designee of either office shall have authority to settle or resolve a protest of an aggrieved bidder or prospective, concerning the project bid documents, solicitation or award of a contract. The decision of the University will be considered final.

18. EXECUTION OF CONTRACT. 18.1 The apparent low Bidder shall be prepared, if so required by the Owner, to

present evidence of experience, qualifications, and financial ability to carry out the terms of the Contract.

18.2 The successful Bidder will be required to execute an Agreement with the Owner

on a form identical to the Agreement Form included with the Contract Documents and the Performance and Payment Bond and Certification of Insurance within ten days after receipt of the Intent to Award. Failure of the Bidder to do so may result in the Bidder being rejected and could result in disqualification and forfeiture of bid bond.

18.3 The successful Bidder will be required to furnish Owner with proof of insurance,

as prescribed by the General Conditions and Supplementary General Conditions.

Page 15: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

BID FORM Section 004113

BID FROM: BID TO: University of Central Arkansas PROJECT: UCA-18-108 Gentlemen: 1. Having carefully examined the Contract Documents for this project, as well as the

premises and all conditions affecting the proposed construction, the undersigned proposes to provide all labor, materials, services, and equipment necessary for, or incidental to, the construction of the project in accordance with the Contract Documents within the time set forth, for the lump sum base bid of:

$ Dollar Amount Is To Be Shown Numerically $__________________________________________(Alternate see section 012300) Dollar amount to be shown numerically 2. Allowances: See section 012100 and Allowance Signature Form section 004321 3. Ark. Code Ann.§ 22-9-212 requires the contractor to indicate on this bid form the

cost of Trenching Safety Systems. FAILURE TO SHOW THIS COST IF APPLICABLE WILL INVALIDATE THE BID. (NOTE THIS COST SHALL BE INCLUDED IN THE ABOVE BASE BID)

$ Dollar Amount Is To Be Shown Numerically. 4. Completion Date: Bidder agrees that the work will be substantially complete and

ready for final payment within 62 days after receipt of the Purchase Order.

5. The undersigned, in compliance with the Contract Documents for the construction of the above named project, does hereby declare:

a. That the undersigned understands that UCA reserves the right to reject any and all bids and to waive any formality. UCA reserves the right to award by single project or all or none as deemed in the best interest of the university.

b. That if awarded the Contract, the undersigned will enter into an Agreement, on a form identical to the form included in the Contract Documents and execute required performance and payment bonds within ten (10) days after receipt of the Intent to Award, will commence work after the purchase order has been issued and the notice to proceed has been given by the Construction Coordinator, and will complete the

Bid Time: 9:00 a.m. Bid Date: June 19, 2018 Bid Opening Location: 2125 College Avenue, Suite 3, Conway, AR 72034

Page 16: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

Contract fully by Completion Date indicated. Should the undersigned fail to fully complete the work within the above stated time, he shall pay the Owner as fixed, agreed and liquidated damages and not as a penalty, the sum of five hundred dollars ($500) for each calendar day of delay until the work is completed or accepted.

c. The undersigned further agrees that the bid security payable to Owner and accompanying this proposal shall become the property of the Owner as liquidated damages if the undersigned fails to execute the Contract or to deliver the required bonds to the Owner within three (3) days from receipt of the Intent to Award as these acts constitute a breach of the Contractor’s duties.

d. That this bid may not be withdrawn for a period of thirty (30) days after the bid opening.

e. The undersigned understands that the Owner's intent is to construct all facilities proposed within the limits established by the funds appropriated for the project.

f. The names of subcontractors and the nature of the work to be performed by each one have been included on the Bid Form.

g. Bids submitted by a “Joint Venture/Joint Adventure” shall be signed by representatives of each component part of the Joint Venture. The licenses of each component part of the Joint Venture shall also be listed in the bid submittal. Therefore, joint venture bidders shall indicate at least two (2) signatures and two (2) licenses numbers on the Bid Form. Exception: Joint Ventures who have been properly licensed with the Arkansas Contractors Licensing Board as a “Joint Venture” need only to indicate the joint venture license number on the Bid Form. Joint Venture Bidders shall indicate at least two (2) signatures on the bid form even if they are licensed as a joint venture

6. The following documents are attached to and made a condition of this Bid. a. Bid security. b. Listing of Mechanical, indicative of heating, air conditioning, ventilation, and

refrigeration, Plumbing, Electrical, indicative of wiring and illuminating fixtures and Roofing and sheet metal work, indicative of roofing application Subcontractors, if required.

7. The undersigned acknowledges receipt of the addendum as a part of the Contract Documents the following addenda: No. ________________ Dated ______________________________ No. _________________Dated ______________________________ No._________________ Dated ______________________________ No._________________ Dated ______________________________ No._________________ Dated ______________________________ No._________________ Dated ______________________________

Page 17: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

8. Listing of mechanical, plumbing, electrical, roofing, sheet metal and other subcontractors; ALL MECHANICAL, PLUMBING, ELECTRICAL, ROOFING AND SHEETMETAL, TRENCHING, ETC. SUBCONTRACTORS SHALL BE LISTED REGARDLESS OF QUALIFICATIONS, LICENSURES OR WORK AMOUNT. BIDDERS SHOULD CONSULT THE PROJECT MANUAL ON HOW TO FILL OUT THIS FORM. IF APPLICABLE, FAILURE TO LIST THE NAME OF THE SUBCONTRACTOR IN THE SPACE PROVIDED SHALL CAUSE THE BID TO BE DECLARED NON-RESPONSIVE AND THE BID WILL NOT RECEIVE CONSIDERATION. Refer to Section 002113, Instruction to Bidders. PROJECTS NOT REQUIRING THE STATED WORK CAN BE NOTED AS NON-APPLICABLE (N/A). IF THE PRIMARY CONTRACTOR IS PERFORMING THE WORK THEY MUST LIST THEIR NAME IN THE BLANKS BELOW. Indicate the Name(s), of each entity performing the listed work: MECHANICAL (Indicative of HVACR): License #: _________________________________________________________________________ Is the amount of work $50,000.00 or over: Yes___ No ___ PLUMBING: License #: ________________________________________________________________________ Is the amount of work $50,000.00 or over: Yes___ No ___ ELECTRICAL: (Indicative of wiring and illuminating fixtures) License #: ________________________________________________________________________ Is the amount of work $50,000.00 or over: Yes___ No ___ ROOFING AND SHEETMETAL (Indicative of roofing applications) License #: ________________________________________________________________________ Is the amount of work $50,000.00 or over: Yes___ No___ TRENCHING (Indicative of trenching applications) License #: ________________________________________________________________________ Is the amount of work $50,000.00 or over: Yes___ No___ OTHER (Indicative of other applications) License #: _______________________________________________________________________ Contractor Only: Is the amount of work $50,000.00 or over: Yes___ No___ Respectfully Submitted:

Page 18: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

Name of Bidder (Typed or Printed):____________________________________ Address: _________________________________________________________ BY: (Signature and Title): ____________________________________________ Contractor’s License Number or Contractor’s (Joint Venture) License Number(s): ________________________________________________________________ Telephone Number: ________________________________________________ Fax Number: _____________________________________________________ Email Address: _____________________________________________ Federal ID or SSN: _________________________________________________ Date of Bid: _______________________________________________________

End of BID FORM Section 004113

Page 19: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

DOCUMENT 004321 - ALLOWANCE FORM

1.1 BID INFORMATION

A. Bidder: ____________________________________________________.

B. Project Name: Mashburn Hall Reroofing and Deck Replacement.

C. Project Location: University of Central Arkansas, Conway, Arkansas.

D. Owner: University of Central Arkansas.

E. Architect: Stocks-Mann Architects, PLC.

F. Architect Project Number: 1505H.

1.2 BID FORM SUPPLEMENT

A. This form is required to be attached to the Bid Form.

B. The undersigned Bidder certifies that Base Bid submission to which this Bid Supplement is attached includes those allowances described in the Contract Documents and scheduled in Section 012100 "Allowances."

1.3 SUBMISSION OF BID SUPPLEMENT

A. Respectfully submitted this ____ day of ______ ______, 2018.

B. Submitted By:_______________________________(Insert name of bidding firm or corporation).

C. Authorized Signature:___________________________________(Handwritten signature).

D. Signed By:______________________________________________(Type or print name).

E. Title: __________________________________(Owner/Partner/President/Vice President).

END OF DOCUMENT 004321

Page 20: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

DOCUMENT 004322 - UNIT PRICES FORM

1.4 BID INFORMATION

A. Bidder: ____________________________________________________.

B. Project Name: Mashburn Hall Reroofing and Deck Replacement

C. Project Location: University of Central Arkansas, Conway, Arkansas.

D. Owner: University of Central Arkansas.

E. Architect: Stocks-Mann Architects, PLC.

F. Architect Project Number: 1505H.

1.5 BID FORM SUPPLEMENT

A. This form is required to be attached to the Bid Form.

B. The undersigned Bidder proposes the amounts below be added to or deducted from the Contract Sum on performance and measurement of the individual items of Work.

C. If the unit price does not affect the Work of this Contract, the Bidder shall indicate "NOT APPLICABLE."

1.6 UNIT PRICES

A. Unit-Price No. 1: Removal and replacement of wet lightweight concrete roof decking.

1. _______________________________________ Dollars ($_____________) per sq. ft.

1.7 SUBMISSION OF BID SUPPLEMENT

A. Respectfully submitted this ____ day of __________ __, 2018.

B. Submitted By:___________________________________(Insert name of bidding firm or corporation).

C. Authorized Signature:____________________________________(Handwritten signature).

D. Signed By:______________________________________________(Type or print name).

E. Title:___________________________________(Owner/Partner/President/Vice President).

END OF DOCUMENT 004322

Page 21: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

AGREEMENT FORM

Section 005213 THIS AGREEMENT entered into this day of , 2018 by and between ________________ , hereinafter referred to as the Contractor, and the University of Central Arkansas, hereinafter referred to as Owner, in accordance with Ark. Code Ann. § 22-2-101 et seq., WITNESSETH:

1. That for and in consideration of the payment by the owner in the amount of $ to be made as set forth in the Contract Documents, the Contractor hereby agrees to furnish all tools, labor, equipment, and materials, and to re-roof and replace the Deck of the Mashburn Hall building in Faulkner County, designated as: Project #: UCA-18-108 Project Name: Mashburn Hall Re-roof and Deck Replacement consisting of construction, more specifically described in the Contract Documents attached hereto and incorporated herein by reference. Contract Documents include the following: the Agreement Form (this instrument); the Invitation to Bid; Instruction to Bidders; Bid Form; all Addenda; Performance and Payment Bond; General Conditions; Drawings and Specifications, Drawings listed in the Specifications; Notice to Proceed; and Change Orders. All construction shall be in exact accord with the Contract Documents filed with the UCA Purchasing Department, located in Conway, AR on June 19, 2018, UCA Purchasing Department shall have direct contract supervision. Said construction shall be to the satisfaction of the UCA Purchasing Department, and in accordance with the laws of the State of Arkansas, and the work shall be subject to inspection and approval at all times by the appropriate state and federal agencies. 2. Owner may at any time during the progress of the work alter, change, subtract from, or add to said Contract Documents without violating this Agreement or the terms thereof. Said changes, alterations, subtractions, or additions shall be set forth in writing in a document referred to as a “Change Order.” Said document shall not be effective unless approved by the UCA Purchasing Office. Once effective, the Change Order shall be attached hereto and incorporated herein by reference and shall be made a condition or term of the Contract Documents. 3. The Contractor agrees, for the consideration set forth in the Bid Form, to begin work after the receipt a purchase order. Complete the work within 62 Days after receipt of the Purchase Order. If the Contractor fails to complete the work within the time limit herein specified, he shall pay to the Owner, as liquidated damages and not in the nature of a penalty, the sum specified in the Bid Form of for each calendar day delayed, it being understood and agreed between the parties hereto that the said sum fixed as liquidated damages is a reasonable sum, considering the damages that Owner will sustain in the event of any such delay, and said amount is herein agreed upon and fixed as liquidated damages because of difficulty of ascertaining the exact amount of damages that may be sustained by such delay. The said sum shall be deducted from the final amount of estimate due the Contractor. 4. Should Contractor be delayed in the execution or completion of the work by the act, neglect or default of UCA, or by any damage by fire, weather conditions or other casualty or event for which the contractor is not responsible, or by general strikes or lockouts caused by

Page 22: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

acts of employees, then any extended period shall be determined and fixed by the Owner with approval given by UCA Purchasing Department. Said extended period shall be the time for a period equivalent to the time lost by reason of any or all of the causes aforesaid, but no such allowance shall be made unless a claim therefore is presented in writing to the Owner within seven calendar days of the occurrence of the event causing the delay. 5. It is mutually agreed between the parties that in the performance of this contract, Contractor is acting independently and in no sense as Agent of the State. Contractor shall not let, assign, or transfer this contract or any interest therein, without the written consent of the Owner. 6. It is agreed and understood between the parties hereto that the Contractor shall accept and the Owner will pay for the work, at the prices stipulated in the Contract Documents, such payment to be in the form of legal tender, and the payment shall be made at the time and in the manner set forth in the Contract Documents. 7. Any laborer or mechanic employed by the Contractor or any Subcontractors for this project, directly on site for the work covered by the Contract Documents, shall be paid a rate of wages required by the Contract Documents. If the Owner discovers that wages less than the rate of wages specified by the Contract Documents have been or are being paid, then the Owner, after giving written notice to the Contractor, will terminate the Contractor’s right to proceed with the project work or such part of the work as to which there has been a failure to pay the required wages and to prosecute the work to completion by contract or otherwise, and the Contractor and his sureties shall be liable to the Owner for any excess costs occasioned thereby. 8. Contractor shall promptly repair, at his own expense and to the satisfaction of the UCA Purchasing Department, damage done by him or his employees or agents at the work site, or to the public property or buildings, or both, and will save UCA harmless from all claims of any person for injury to person or to property occasioned by his act, or the acts of his employees or agents, while in the execution of the work specified. 9. The Owner, or both may terminate this agreement to the extent Owner’s funds are no longer available for expenditures under this agreement. 10. Failure to make any disclosure required by Governor’s Executive order 98-04, or any violation of any rule, regulation, or policy adopted pursuant to that Order, shall be a material breach of terms of this contract. Any contractor, whether an individual or entity, who fails to make the required disclosure or who violates any rule, regulation, or policy shall be subject to all legal remedies available to the Agency.

a) The contractor shall prior to entering any agreement with any subcontractor, for which the total consideration is greater than $25,000.00, require the subcontractor to complete a Contract and Grant Disclosure and Certification Form. The contractor shall ensure that any agreement, current or future between the contractor and a subcontractor for which the total consideration is greater than $25,000.00 shall contain the following: Failure to make any disclosure required by Governor Executive Order 98-04, or any violation of any rule, regulation or adopted pursuant to that Order, shall be a material breach of the term of this subcontract. The party who fails to make the required disclosure or who violates the rule, regulation, or policy shall be subject to all legal remedies available to the contractor.

Page 23: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

(b) The Contractor shall, within ten days of entering into any agreement with a subcontractor, transmit to UCA Purchasing Department; a copy of the Contract and Grant Disclosure and Certification Form and Boycotting of Israel Form signed by the subcontractor. The terms and conditions regarding the failure to disclose and conditions which constitutes material breach of contract and rights of termination and remedies under the Executive Order 98-04 are hereby incorporated within.

11. Nothing in this Contract shall be construed to waive the sovereign immunity of the STATE OF ARKANSAS or any entities thereof.

Executed by the parties who individually represent that each have the authority to enter into this Contract.

CONTRACTOR:

By: ________________________________________________________________ (Signature) ________________________________________________________________ (Print Name) Title: ________________________________________________________________

Firm: ___________________________________________________________

Address: _______________________________________________________________

Date: ________________________________________________________________

APPROVED: UNIVERSITY OF CENTRAL ARKANSAS By: ________________________________________________________________ (Signature)

________________________________________________________________ (Print Name)

Title: ________________________________________________________________

Date: ________________________________________________________________

End of AGREEMENT FORM

Section 005213

Page 24: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

UCA PERFORMANCE BOND AND PAYMENT BOND SECTION 006113

Bond Number:

1) We _______________________________ , (Principal), and

________________________ (Surety), are held and firmly bound, jointly and severally

unto , as Obligee (Owner), in the initial Contract amount of $ _______ said

amount to be deemed a Performance Bond payable to Owner and in the separate amount of

$ _______ said amount to be deemed a Payment Bond payable to proper claimants

such amounts subject to the terms of this Performance Bond and Payment Bond Agreement.

The Principal and Surety state that the Surety is a solvent corporate surety company

authorized to do business in the State of Arkansas and is listed on the current United States

Department of Treasury’s listing of approved sureties.

Principal has by written agreement dated _______ entered into a capital

improvement contract with the Owner for: Mashburn Hall Re-roofing and Deck

Replacement Project # UCA-18-108.

The above referenced Contract is incorporated herein by reference.

2) Under this Performance Bond and Payment Bond Agreement, the Principal and Surety shall be responsible for the following: a. Performance Bond i. The Principal shall faithfully perform the above referenced Contract, which is incorporated herein by reference. ii. In the event that the Principal defaults in its performance of its obligations under the Contract, the Principal and the Surety, jointly and severally, shall indemnify and save harmless the Owner from all cost and damage which the Owner may suffer by reason of Principal’s failure to perform the Contract. Said indemnification shall include, but not be limited to, full reimbursement and repayment to the Owner for all outlays and expenses which the Owner may incur in making good any such default of the Contract by the Principal. b. Payment Bond i. Principal shall pay all persons all indebtedness for labor or material furnished or performed under the Contract and in doing so this obligation shall be null and void. ii. In the event that Principal fails to pay for such indebtedness, such persons shall have a direct right of action against the Principal and Surety, jointly and severally, under this obligation, subject to the Owner’s priority. 3) This Performance Bond and Payment Bond is given in accordance with Arkansas laws and rules, including Ark. Code Ann. § 18-44-501 et seq., §19-4-1401 et seq., and § 22-9-401 et seq. Any changes made in the terms of the Contract, including but not limited to, the amount of the Contract, or in the work to be performed pursuant to the Contract or the giving by the Owner of any extension of time for the performance of the Contract, or any other forbearance on the part of either the Owner or the Principal to the other shall not in any way release the Principal and the Surety or Sureties or either or any of them, their heirs, personal representatives, successors or assigns from their liability hereunder, notice to and consent of

Page 25: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

the Surety or Sureties of any such change, extension or forbearance being are hereby voluntarily waived. In no event shall the aggregate liability of the Surety exceed the greater amount of the Contract, including UCA approved change orders. This Performance Bond and Payment Bond Agreement is binding upon the above named parties, and their successors, heirs, assigns and personal representatives. Executed by the parties who individually represent that each voluntarily enters into and has the authority to enter into this agreement. BY: __________________________________________________________________ Contractor’s (Principal) Signature Date __________________________________________________________________ Print Name BY: __________________________________________________________________ Arkansas Resident Agent or Non Resident Agent Signature (attach Power of Attorney) ______________________________________________________________ Print Name Date Agent’s License Number: Surety Company’s NAIC Number: Surety Address: City, County, State, Zip Code: Business Phone #:

Fax #:

E-Mail:

THIS FORM IS THE ONLY PERFORMANCE AND PAYMENT BOND ACCEPTABLE

Page 26: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

RELEASE OF CLAIMS Section 006519.16

Comes the undersigned, who does hereby swear and affirm that: 1. My name is , and my (printed or typed) address is , doing business as__________ . 2. Pursuant to Contract Number . (project description) and Contract Date excepted as listed below in Paragraph 4, I have paid otherwise satisfied all obligations for all materials and equipment furnished, for all work, labor, and services performed, and for all known claims against the Contractor arising in any manner in connection with the performance of the contract referenced above for which the Owner or his property might in any way be held responsible. 3. To the best of my knowledge, information and belief, excepted as listed below in Paragraph 4, the Releases or Waivers of Claim, attached hereto and incorporated herein, include the Contract, all subcontractors, all suppliers of materials and equipment, and all performers of work, labor or services who have or may have claims against any property of the Owner arising in any manner out of the performance of the Contract referenced above. 4. The Exceptions are: (if none, indicate "none." If required by the Owner, the Contractor shall furnish bond satisfactory to the Owner for each exception.) AFFIANT DATE VERIFICATION STATE OF ARKANSAS ) ) COUNTY OF ) SUBSCRIBED AND SWORN TO before me this of 20 . NOTARY PUBLIC MY COMMISSION EXPIRES:

End of Release of Claims

Section 006519.16

Page 27: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

CONSENT OF SURETY

Section 006519.19 Comes the undersigned, who does hereby swear and affirm that: 1. My name is and I am an authorized representative of a surety company. 2. With regards to the Project Contractor; and Owner; I hereby approve the final payment to the contractor. I agree that the final payment to the contractor shall not relieve the Surety Company of any of its obligations as set forth in the contract with the State of Arkansas and this contractor. AFFIANT DATE VERIFICATION STATE OF ARKANSAS ) ) COUNTY OF ) SUBSCRIBED AND SWORN TO before me this of , 20 . NOTARY PUBLIC MY COMMISSION EXPIRES:

End of CONSENT OF SURETY FORM

006519.19

Page 28: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

GENERAL CONDITIONS Section 007213

ARTICLE 1 -- GENERAL PROVISIONS 1.1 DEFINITIONS 1.1.1 Contract Documents: Contract Documents consist of Agreement; Invitation to

Bid; Instruction to Bidders; the Bid Form; the Bid and the Performance and Payment bonds; General Conditions; Specifications; Drawings; Addenda issued prior to execution of the Contract; all UCA approved Change Orders; other documents listed or referred to in the Agreement; and modifications issued after execution of the Contract and signed by Contractor and Owner, and approved by UCA.

1.1.2 Contract: The Contract Documents form the Contract for construction. The

Contract Documents will not be construed to create a contractual relationship between the Design Professional and Contractor, between the Owner and a subcontractor, between the Owner and Design Professional, or between entities other than the Owner and Contractor; however, a contractual relationship does exist between the Contractor and the agency referred to as Owner for approval purposes.

1.1.3 Work: Construction and services required by the Contract Documents whether

completed or partially completed, include tools, labor, equipment, supplies, transportation, handling, and incidentals provided by the Contractor.

1.1.4 Project: The total capital improvement project described in the Contract

Documents. 1.1.5 Drawings: Graphic and textual portions of the Contract Documents showing the

design, location, and dimensions and size of the Work, generally including plans, elevations, sections, details, schedules, and diagrams.

1.1.6 Specifications: Written requirements for materials, equipment, systems,

standards, and workmanship for the Work, and performance of related services. 1.1.7 Project Manual: Volume, which may include the bidding requirements, forms,

contracting requirements, and the Specifications. 1.1.8 Owner: The person or entity identified as such in the Contract Agreement,

referred to throughout the Contract Documents as singular in number. The term Owner means the Owner and the Owner-authorized representative.

1.1.9 Contractor: The person or entity identified as such in the Contract Agreement,

referred to throughout the Contract Documents as singular in number. The

Page 29: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

term Contractor means the Contractor or the Contractor-authorized representative.

1.1.10 Design Professional (Architect/Engineer/Consultant): The person or entity

identified as such in the Agreement, lawfully licensed to practice architecture or engineering or another field of expertise and under contract to Owner to provide design service, advice, and consultation, referred to throughout the Contract Documents as if singular in number. The term Design Professional means the Architect/Engineer/ Consultant or the authorized representative.

1.1.11 Subcontractor: Any person, firm, or corporation with a direct contract with the

Contractor who acts for or in behalf of the Contractor in executing a portion of the Work. The term subcontractor is referred to as singular in number and means the subcontractor or the subcontractor-authorized representative.

1.1.12 Inspector: A duly authorized representative of UCA and Design Professional,

designated for detailed inspection of materials, construction, workmanship, and methods of construction.

1.1.13 Site: The particular location of that part of the project being considered. 1.1.14 State: The Owner. 1.2 INTENT 1.2.1 The intent of the Contract Documents is to set forth the standards of

construction, the quality of materials and equipment, the guarantees that are to be met, and to include items necessary for proper execution and completion of the Work. The Contract Documents are complementary and what is required by one will be as binding as if required by all. Performance by the Contractor shall be required to the extent consistent with the Contract Documents and reasonably inferable as necessary to produce indicated results.

1.2.2 Organization of the Specifications into divisions, sections, and articles, and

arrangement of Drawings will not control the Contractor in dividing the Work among Subcontractors or in establishing the extent of Work to be performed by any trade.

1.2.3 Unless otherwise stated in the Contract Documents, words which have well-

known technical or construction industry meanings are used in the Contract Documents in accordance with such recognized meanings.

1.3 CAPITALIZATION 1.3.1 Terms capitalized in the Contract Documents include those which are

specifically defined, the titles to numbered sections and articles, identified references to paragraphs, and the titles of other published documents.

1.4 INTERPRETATION

Page 30: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

1.4.1 Whenever in these Contract Documents the words "as ordered", "as directed",

"as required", "as permitted", "as allowed", or words or phrases of like import are used, it shall be understood that the order, direction, requirement, permission, or allowance of the Owner and Design Professional is intended.

1.4.2 Whenever in these Contract Documents the word "product" is used, it shall be

understood that the materials, systems, and equipment will be included. 1.4.3 Whenever in these Contract Documents the word "provide" is used, it shall be

understood that it means to "furnish and install". 1.4.4 The Contract Documents frequently omit modifying words such as "all" and

"any" and articles such as "the" and "an", but the fact that a modifier or an article is absent from one statement and appears in another is not intended to affect the interpretation of either statement.

ARTICLE 2 -- OWNER 2.1 LAND 2.1.1 The Owner will provide the lands shown on the Drawings upon which the Work

shall be performed. The Owner will provide a right-of-way for access to the project site.

2.1.2 The Owner will provide base lines for the location of the principle component

parts of the Work with a suitable number of bench marks adjacent to the Work. 2.2 RIGHT OF ENTRY BY OWNER 2.2.1 The Owner and his authorized representative will have the right to enter the

property or location on which the Work shall be constructed. The Owner further reserves the right to construct or have his authorized agents construct such work as the Owner will desire, so long as these operations do not interfere with or delay the work being constructed under this Contract.

2.3 OWNER'S RIGHT TO CARRY OUT THE WORK 2.3.1 If the Contractor defaults or neglects to perform the Work in accordance with

the Contract Documents, including the requirements with respect to the schedule of completion, and fails after ten days written notice from the Owner to correct the deficiencies, the Owner may deduct the cost thereof from the payment then or thereafter due the Contractor.

ARTICLE 3 -- CONTRACTOR 3.1 GENERAL

Page 31: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

3.1.1 The Contractor shall perform the Work in accordance with the Contract Documents. 3.1.2 The Contractor shall furnish labor, materials, equipment, and transportation

necessary for the proper execution of the work unless specifically noted otherwise. The Contractor shall do all the work shown on Drawings and described in Specifications and all incidental work considered necessary to complete the project in a substantial and acceptable manner, and to fully complete the work or improvement, ready for use, occupancy and operation by the Owner. Drawings and Specifications shall be interpreted by the Design Professional or the Owner if no Design Professional exists for the project.

3.1.3 The Contractor shall cooperate with the Owner, Design Professional, inspectors,

and with other contractors on the Project. Contractor shall allow inspectors acting in an official capacity, to have access to the project site.

3.1.4 The Contractor shall determine that the final and completed work on the project

is in accordance with the Contract Documents. The failure of the Design Professional to find or correct errors or omissions in the use of materials or work methods during the progress of the work shall not relieve the Contractor from his responsibility to correct all the defects in the project.

3.1.5 The Contractor shall assist in making final inspections and shall furnish such

labor and equipment as may be required for the final tests of equipment, piping, and structures.

3.2 REVIEW OF FIELD CONDITIONS 3.2.1 Before ordering material or doing Work, the Contractor shall verify all

measurements involved and shall be responsible for the correctness of same. No extra charge or compensation will be allowed on account of difference between actual dimensions and the measurements indicated on Drawings; differences which may be found, shall be submitted to Design Professional for consideration before proceeding with the Work.

3.2.2 Drawings may show the location or existence of certain exposed and buried

utilities as well as existing surface and subsurface structures. The Owner assumes no responsibility for failure to show any or all such utilities and structures on the Drawings or to show such in the exact location. It is mutually agreed such failure will not be considered sufficient basis for claims for extra work or for increasing the pay quantities in any manner unless the obstruction encountered necessitates substantial changes in the lines or grades or requires the building of a special structure.

3.3 REVIEW OF CONTRACT DOCUMENTS 3.3.1 The Contractor shall study and compare Drawings, Specifications, and other

instructions and shall report to the Design Professional at once any error, incon-sistency, or omission discovered.

Page 32: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

3.3.2 In the event of conflict among the Contract Documents, interpretations will be

based on the following order of precedence, stated highest to lowest: a. The Agreement

b. This Division Zero (0) shall control in the event of conflict between this

Division Zero (0) and other Divisions 1 through 14

c. Addenda to Drawings and Specifications with those of later date having precedence.

d. Drawings and Specifications

3.3.3 Since the Contract Documents are complementary, the Contractor shall take no

advantage of any apparent error or omission in the Drawings and Specifications. The Owner or Design Professional shall furnish interpretations as deemed necessary for the fulfillment of the intent of the Drawings and Specifications.

3.3.4 Discrepancies found between the Drawings and Specifications and actual site

conditions or any errors or omissions in the Drawings or Specifications shall be immediately reported to the Design Professional or in the case where a Design Professional is not on the Project, the Owner shall be notified, who shall address such error or omission in writing. Work done by the Contractor after discovery of such discrepancies, errors, or omissions shall be at the Contractor's risk and expense.

3.4 REQUEST FOR SUPPLEMENTARY INFORMATION 3.4.1 The Contractor shall make timely requests of the Owner or Design Professional

for additional information required for the planning and production of the Work. Such requests shall be submitted as required, but shall be filed in ample time to permit appropriate action to be taken by all parties involved so as to avoid delay. Contractor understands and agrees that it is Contractor’s duty to determine the need for, and to request said additional information in writing from the Design Professional by such date as allows Design Professional to provide the information to the Contractor by a date that will not adversely affect Contractor’s ability to complete the Work by the date specified in the Contract.

3.4.2 Additional instructions may be issued by the Design Professional during the

progress of the Work to clarify the Drawings and Specifications or as may be necessary to explain or illustrate changes in the Work.

3.5 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES 3.5.1 Shop Drawings are drawings, diagrams, schedules, and other data specially

prepared for the Work by the Contractor or a Subcontractor, sub-subcontractor, manufacturer, supplier, or distributor to illustrate some portion of the Work.

Page 33: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

3.5.2 Product Data are illustrations, standard schedules, performance charts, instructions, brochures, diagrams, and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work.

3.5.3 Samples are physical examples that illustrate materials, equipment, or

workmanship and establish standards by which the Work will be judged. 3.5.4 The Contractor shall provide shop drawings and other submittals, settings,

schedules, and other drawings as may be necessary for the prosecution of the Work in the shop and in the field as required by the Drawings, Specifications, or Design Professional instructions.

3.6 LABOR AND MATERIALS 3.6.1 Except as otherwise specifically stated in the Contract, the Contractor shall

provide, but not be limited to, all materials, labor, tools, equipment, water, light, heating and cooling, power, transportation, superintendence, temporary construction of every nature, taxes legally collectible because of the work, and all other services and facilities of every nature whatsoever necessary to complete the Work in accordance with the Contract Documents in an orderly and efficient manner. The sequence of construction operations shall follow the schedule of construction as approved by the Design Professional. The Work shall not be discontinued by the Contractor without approval of the Design Professional. Should prosecution of the Work be discontinued for any reason, the Contractor shall notify the Design Professional at least twenty-four hours in advance of resuming the Work.

3.6.2 Materials and equipment furnished under this Contract will be subject to

inspection by the Owner's authorized representative or by independent laboratories. Defective material, equipment, or workmanship may be rejected at any time before the acceptance of the Work even though the defective material, equipment, or workmanship may have been previously overlooked and estimated for payment. The Contractor shall replace defective equipment and material in accordance with the Contract Documents at no additional cost to the Owner.

3.6.3 The Contractor shall provide materials and supplies not subject to conditional

sales agreements, or other agreement reserving unto the seller any right, title, or interest therein. All materials and supplies shall become the property of the Owner upon final acceptance of this Contract by the Owner.

3.6.4 If shop tests are to be conducted, the Contractor shall notify the Owner of such

tests so a representative may witness tests, if desired. 3.6.5 The Contractor may make substitutions only with the consent of the Owner,

after evaluation by the Design Professional, and in accordance with a Change Order.

Page 34: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

3.7 UNAUTHORIZED WORK 3.7.1 Work done without lines and grades having been given or work done beyond

the lines or not in conformity with the grades shown on the Drawings or as provided by the Owner, except as provided herein, and work completed without proper inspection and supervision or any extra or unclassified work completed without written authority and prior agreement shall be at the Contractor's risk. Such unauthorized work, at the option of the Design Professional, may not be measured and paid for and may be ordered removed at the Contractor's expense.

3.8 SUPERINTENDENCE 3.8.1 The Contractor shall supervise and direct the Work. The Contractor shall be

solely responsible for construction means, methods, techniques, sequences, and procedures and for coordinating portions of the Work under the Contract.

3.8.2 The Contractor shall employ a qualified superintendent during the duration of

the Project who is acceptable to the Owner and the Design Professional. The superintendent shall be maintained on the Project site and shall be present on the site at all times work is in progress. The superintendent shall be capable of reading and understanding the Drawings and Specifications and shall have full authority to act in behalf of the Contractor. All directions and instructions given to the Superintendent shall be considered as given to the Contractor and shall be as binding as if given to the Contractor.

3.8.3 Workmanship shall be performed by workmen experienced in their trade and

skilled and experienced for the class of work to which assigned. Any person, including supervisory personnel, who does not show and exhibit skill and proficiency in said work shall be removed by the Contractor and replaced by a competent and experienced workman.

3.8.4 The Contractor shall, at all times, be responsible for the conduct and discipline

of his employees and all Subcontractors and their employees. Disorderly, incompetent or intemperate persons, or persons who commit any crimes or trespass on public or private property in the vicinity of the Work must not be allowed to continue working upon the project which the Contractor has with the State. Any superintendent, foreman or workman employed by the Contractor or a Subcontractor who unreasonably refuses or neglects to comply with the instructions of the Owner, Design Professional, or inspector, shall, at the written request of the Owner or Design Professional, be removed from the work site and shall not be allowed to work further on any portion of the work or another State Project without the approval of the Owner.

3.8.5 The Contractor shall coordinate Work by the various trades to provide uniform

and symmetrical layout and spacing of the exposed components which will affect the finished design and appearance. Where spacing and related locations are not specifically shown on Drawings or where in doubt, the Contractor shall consult the Design Professional prior to installation of that part of the Work.

Page 35: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

3.9 PERMITS, FEES, AND NOTICES 3.9.1 The Contractor shall purchase and secure all applicable permits and licenses

and give all notices necessary and incidental to the prosecution of the Work. However, in accordance with Ark. Code Ann. §22-9-213, public works construction projects conducted by UCA or other state agencies are exempt from permit fees or inspection requirements of county or municipal ordinances.

3.9.2 When new construction under the Contract crosses highways, railroads, streets

or utilities under the jurisdiction of the state, county, city, or other public agency, public utility, or private entity, the Contractor shall secure written permission from the proper authority before executing such new construction. A copy of this written permission shall be filed with the Owner before any work is completed. The Contractor shall furnish a release from the proper authority before final acceptance of the Work. Any bonds required for this Work shall be secured and paid for by the Contractor.

3.10 SAMPLES AND TESTS 3.10.1 The Contractor shall provide samples, materials, and equipment necessary or

required for testing as outlined in the various sections of the Specifications or as directed by the Owner. The Contractor shall pay all costs for testing. Should materials, methods, or systems fail to meet specified standards, the Contractor shall pay all costs for additional testing as required by the Owner.

3.10.2 All tests shall be made by a laboratory approved by the Owner. 3.11 LOCATION, GRADIENT, AND ALIGNMENT 3.11.1 Based upon the site information provided by the Owner, the Contractor shall

develop and make detailed surveys necessary for construction including slope stakes, batter boards, and other working points, lines and elevations.

3.11.2 The Contractor shall report any errors, inconsistencies, or omissions to the

Design Professional as a request for information. 3.11.3 The Contractor shall preserve benchmarks, reference points and stakes, and in

the case of destruction thereof by the Contractor, shall be responsible for damage or mistakes resulting from unnecessary loss or disturbance.

3.12 LAND 3.12.1 Additional land and access thereto not shown on Drawings that may be

required for temporary construction facilities or for storage of materials shall be provided by the Contractor at his expense with no liability to the Owner. The Contractor shall confine his equipment and storage of materials and the operation of his workmen to those areas shown on the Drawings and described in the Specifications, and such additional areas which he may provide or secure as approved by the Owner.

Page 36: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

3.12.2 The Contractor shall not enter upon private property for any purpose without

first obtaining permission. 3.12.3 The Contractor shall be responsible for the preservation of and prevent damage

or injury to all trees, monuments, and other public property along and adjacent to the street and right-of-way. The Contractor shall prevent damage to pipes, conduits and other underground structures, and shall protect from disturbance or damage all monuments and property marks until an authorized agent has witnessed or otherwise referenced their location, and shall not remove monuments or property marks until directed.

3.13 LIMITS OF WORK 3.13.1 The Contractor shall conduct Work and operations so as to cause a minimum of

inconvenience to the public. At any time when, in the opinion of the Owner or Design Professional, the Contractor is obstructing a larger portion of a road, street, or other public right-of-way than is necessary for the proper execution of the Work, the Design Professional may require the Contractor to finish the sections on which work is in progress before work is commenced on any new sections.

3.14 WARRANTY 3.14.1 The Contractor shall warrant that all Work, materials, and equipment furnished

will be free from defects in design, materials, and workmanship and will give successful service under the conditions required. The warranty period for Work, materials, and equipment furnished by the Contractor shall be one year from the date of the written acceptance of the Work as stated in the Substantial Completion Form approved by the Contractor, Owner and Design Professional or the date that UCA approves the final payment request, unless a longer period is agreed upon.

3.15 PATENTS AND ROYALTIES 3.15.1 If the Contractor is required or desires to use any design, device, material or

process covered by letters, patent, or copyright, he shall provide for such use by suitable legal agreement with the patents or Owner. It is mutually understood and agreed that without exception the Contract Sum shall include all royalties or costs arising from patents, trademarks, and copyrights in any way involved in the Work. The Contractor and the surety shall defend, indemnify, and save harmless the Owner and all its officers, agents and employees from all suits, actions, or claims of any character, name and descrip-tion brought for or on account of infringement or alleged infringement by reason of the use of any such patented design, device, material or process of any trademark or copyright used in connection with the Work agreed to be performed under this Contract, and shall indemnify the Owner for any cost, expense, or damage which it may be obliged to pay by reason of any action or actions, suit or suits which may be commenced against the Owner for any such

Page 37: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

infringement or alleged infringement at any time during the prosecution or after the completion of the Work contracted for herein. It is mutually agreed that the Owner may give written notice of any such suit to the Contractor, and thereafter, the Contractor shall attend to the defense of the same and save and keep harmless the Owner from all expense, counsel fees, cost liabilities, disbursements, recoveries, judgments, and executions in any manner growing out of, pertaining to, or connected therewith.

3.16 CLEANING UP 3.16.1 The Contractor shall keep the premises and surrounding area free from

accumulation of waste materials or rubbish caused by operations under the Contract. At completion of the Work, the Contractor shall remove from and about the Project waste materials, rubbish, the Contractor’s tools, construction equipment, machinery, and surplus materials.

3.16.2 If the Contractor fails to clean up as provided in the Contract Documents, the

Owner may do so and the cost thereof shall be charged to the Contractor. ARTICLE 4 -- ADMINISTRATION OF CONTRACT 4.1 DESIGN PROFESSIONAL AUTHORITY 4.1.1 The Design Professional will interpret the requirements of the Contract

Documents and decide matters concerning performance there under on request of the Owner or Contractor.

4.1.2 The Design Professional will provide administration of the Contract as described

in the Contract Documents and will be the Owner’s representative. The Design Professional will decide any and all questions as to the acceptability of materials or equipment furnished, work performed, interpretation of the Drawings and Specifications, rate of progress of the Work, acceptability of the quality of workmanship provided, and other questions as to the fulfillment of the Contract by the Contractor.

4.1.3 The Design Professional will prepare all change orders on the form specified by

UCA. The Design Professional may authorize minor changes in the Work not involving adjustment in Contract Sum or extension of Contract Time and not inconsistent with the intent of the Contract Documents.

4.1.4 The Design Professional and his authorized representatives, UCA will have the

right to enter the property or location on which the Work shall be constructed.

Page 38: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

4.2 CLAIMS 4.2.1 Definition: A claim is a demand or assertion by one of the parties seeking

adjustment, or interpretation of Contract terms, payment of money, extension of time, or other relief with respect to the terms of the Contract. The term includes other disputes and matters in question between the Owner and Contractor arising out of or relating to the Contract. Claims will be initiated by written notice. The responsibility to substantiate claims shall rest with the party making the claim.

4.2.2 Claims of the Contractor or the Owner: Claims regarding the Work of the

Contract shall be referred initially to the Design Professional for a decision. The Design Professional will review claims, and 1) reject in whole or in part; 2) approve the claim; 3) suggest a compromise; 4) advise the parties that the Design Professional is unable to resolve the claim.

4.2.3 Claims for Concealed or Unknown Conditions: If new and unforeseen items of

work are discovered, which cannot be covered by any item or combination of items for which there is a Contract Sum, then the Contractor shall notify the Design Professional as quickly as reasonably possible and shall not continue working on the discovered new or unforeseen items without express written permission from the Design Professional. The Contractor shall complete such work and furnish such materials as may be required for the proper completion or construction of the work contemplated upon written Change Order from the Design Professional as approved by the Owner. Work shall be performed in accordance with the Contract Documents.

4.2.4 Claims for Extensions of Time: The Contractor shall provide written notice to

Design Professional within ten days stating the cause of the delay and request an extension of Contract Time. The Design Professional will act on the request in writing. The extension of time shall be for a period equivalent to the time lost by reasons indicated. No extension of time shall be effective until included in a Change Order approved by the Design Professional and UCA.

4.2.5 Claims for Changes in the Work: The Contractor shall provide written notice to

Design Professional within ten calendar days after the receipt of instructions from the Owner, as approved by the Design Professional, to proceed with changes in the Work and before such Work is commenced. Changes in the Work shall not be commenced before the claim for payment has been approved, except in emergencies endangering life or property. The Contractor's itemized estimate sheets showing labor and material shall be submitted to the Design Professional. The Owner's order (Change Order) for changes in the Work shall specify any extension of the Contract Time and one of the following methods of payment:

a. Unit prices or combinations of unit prices, which formed the basis of the

original Contract.

Page 39: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

b. A lump sum fee based on the Contractor's estimate, approved by the Design Professional and accepted by the Owner.

c. The actual cost of the Work plus an allowance of 12 percent and 5

percent for the General Contractor and Subcontractor, respectively. 4.2.6 Claims for Additional Costs: In case of an emergency which threatens loss or

injury of property or safety of life, the Contractor shall be allowed to act, without previous instructions from the Design Professional, in a diligent manner. The Contractor shall notify the Design Professional immediately thereafter. Any claim for compensation by the Contractor due to such extra work shall be promptly submitted, but in no case more than 7 calendar days following the event causing the emergency, to the Design Professional for consideration. The amount of reimbursement claimed by the Contractor on account of any emergency action shall be determined in the manner provided under these General Conditions. No agreement to pay costs for additional work shall be effective until included in a Change Order approved by the Contractor, the Design Professional and UCA.

ARTICLE 5 -- SUBCONTRACTORS 5.1 ASSIGNMENT OF CONTRACT 5.1.1 Neither the Owner nor the Contractor shall have the right to sublet, sell,

transfer, assign, or otherwise dispose of the “Contract” or any portion thereof without written consent of the other party. No assignment, transfer, or subletting, even with the proper consent, shall relieve the Contractor of his liabilities under this Contract. Should any Assignee or Subcontractor fail to perform the work undertaken by him in a satisfactory manner, with UCA approval, has the right to annul and terminate the Assignee's or Subcontractor's contract on the project.

5.2 SUBCONTRACTS 5.2.1 The subcontracting of the whole or any part of the Work to be done under this

Contract will not relieve the Contractor of his responsibility and obligations. All transactions of the Owner or Design Professional shall be with the Contractor. Subcontractors will be considered only in the capacity of employees or workmen and shall be subject to the same requirements as to character and competency.

5.2.2 The Contractor shall discharge or otherwise remove from the project any

Subcontractor that the Owner or the Design Professional has reasonably determined as incompetent or unfit.

5.2.3 The Contractor may not change those Subcontractors listed on the proposal

without the written approval of the Owner, Design Professional. The Contractor shall submit written evidence, which includes but is not limited to, that the substituted contractor is costing the same amount of money or less and if costing less, that the saving will be deducted from the total contract of the

Page 40: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

prime contractor and rebated to the Owner prior to any approval. The Contractor shall submit his request to the design professional who then shall review the request, if approved, the request and approval shall be forwarded to the Owner. The Owner shall then review the request and accompanying paperwork and if approved, shall forward the approval and the accompanying documents to UCA. UCA shall review all of the documents. UCA shall provide written notification to the Contractor and the Design Professional as its determination. The Contractor shall not be relieved of any liabilities under this Contract, but shall be fully responsible for any Subcontractor or work by said Subcontractor where Subcontractor is employed by the Contractor to perform work under this Contract. Nothing contained in the Contract Documents shall create contractual relations between any Subcontractor and the State.

5.2.4 No officer, agent, or employee of the Owner, including the Design Professional,

shall have any power or authority to bind the Owner or incur any obligation in his behalf to any Subcontractor, material supplier or other person in any manner whatsoever.

ARTICLE 6 - CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS 6.1 OTHER CONTRACTS 6.1.1 The Owner reserves the right to award other contracts in connection with the

Project. The Contractor shall cooperate with the other contractors with regard to the storage of materials and equipment, access to the site, and execution of their work. It shall be the Contractor's responsibility to inspect the work of other contractors which will affect the work of this Contract and to report to the Owner irregularities which will not permit him to complete his work in a satisfactory manner or in the time allotted. Failure to so report shall constitute an acceptance of the work of other contractors.

6.2 DEPENDENCE ON OTHERS 6.2.1 If any part of the Contractor's work depends for proper execution or results

upon the work of the Owner or any separate contractor, the Contractor shall, prior to proceeding with the work, promptly report to the Design Professional any apparent discrepancies or defects in such other work that render it suitable for such proper execution and results. Failure of the Contractor to so report shall constitute an acceptance of the work.

ARTICLE 7 -- CHANGES IN THE WORK 7.1 GENERAL 7.1.1 The Owner may, as the need arises, without invalidating the Contract, order

changes in the work in the form of additions, deletions, or modifications. Compensation to the Contractor for additional work or to the Owner for deductions in the work and adjustments for the time of completion shall be adjusted at the time of ordering such change.

Page 41: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

7.1.2 Additional work shall be done as ordered in writing by the Owner. The order shall state the location, character, and amount of extra work. All such work shall be executed under the conditions of the Contract, subject to the same inspections and tests.

7.1.3 The Design Professional and the Owner reserve and shall have the right to

make changes in the Contract Documents and the character or quantity of the work as may be considered necessary or desirable to complete fully and accept-ably the proposed construction in a satisfactory manner.

7.2 CHANGE ORDERS 7.2.1 A Change Order is a written instrument, prepared by the Design Professional

and approved by UCA stating their agreement upon the following, separately or in any combination thereof:

a. Description and details of the work. b. Amount of the adjustment in the Contract Sum. c. Extent of the adjustment in the Contract Time. d. Terms and conditions of the Contract Documents. 7.2.2.1 Change Order requests by the Contractor shall be submitted in a

complete itemized breakdown, acceptable to the Design Professional and UCA.

7.2.2.2 Where unit prices are stated in the Contract, Contractor should submit

an itemized breakdown showing each unit price and quantities of any changes in the Contract Amount. The value of all such additions and deductions shall then be computed as set forth in Paragraph 7.2.2.3.

7.2.2.2 The Contractor shall present an itemized accounting together with appropriate supporting data for the purposes of considering additions or deductions to the Contract Amount. Supporting data shall include but is not limited to the following:

a. Costs of labor, including social security, old age and unemployment insurance, fringe benefits required by agreement or custom, and worker or workmen’s compensation insurance;

b. Cost of materials, supplies and equipment, including cost of transportation, whether incorporated or consumed;

c. Rental costs of machinery and equipment, exclusive of hand tools,

whether rented from the Contractor or others;

d. Costs of premiums for all bonds and insurance, permit fees, and sales, use of similar taxes related to the Work; and

Page 42: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

e. Additional costs of supervision and field office personnel directly attributable to the change.

The burden of proof of cost rests upon the Contractor. Contractor agrees that UCA’s Representative shall have the right, at reasonable times, to inspect and audit the books and records of Contractor to verify the propriety and granting of such cost.

7.2.2.3 Compute requests for changes be they additions or deductions as follows:

a. For work performed by the Contract:

Net Cost of Materials a.___________________ State Sales Tax b.___________________ Net Placing Cost c.___________________ W.C. Insurance Premium and FICA Tax d.___________________ Subtotal of a+b+c+d Overhead and Profit, 12% x (a+b+c+d) e.___________________ Allowable Bond Premium f.___________________ TOTAL COST a+b+c+d+e+f ____________________

b. Credit for work deleted shall be computed as outlined in 7.2.2.3 a. through e., except the Contractor’s share of overhead and profit percentage is seven percent.

c. For added work performed by Subcontractors: Subcontractors shall

compute their work as outlined in 7.2.2.3 a. through e. To the cost of that portion of the work (Change) that is performed by the Subcontractor, the Contractor shall add an Overhead and Profit Change of five percent plus the Allowable Bond Premium.

d. For work deleted by a Subcontractor: Subcontractors shall compute

their work as outlined in 7.2.2.3 a through e, except that the overhead and profit shall be seven percent and the Contractor’s overhead and profit shall be five percent.

7.3 PAYMENT FOR CHANGES IN THE WORK 7.3.1 All changes in the Work will be paid for in the manner indicated in Article 4,

Paragraph 4.2, and the compensation thus provided shall be accepted by the Contractor as payment in full for the use of small tools, superintendent's services, premium on bond, and all other overhead expenses incurred in the prosecution of such work.

Page 43: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

7.3.2 The Owner shall not be deemed to have agreed to any costs for additional work, to have agreed to additional time for completion, or to have agreed to any other change in the terms and conditions of the Contract Documents until Owner, Design Professional and Contractor have executed a Change Order to this Contract, and the Change Order is approved by UCA.

ARTICLE 8 -- TIME 8.1 DEFINITIONS 8.1.1 Contract Time is the period of time identified in the Contract Documents for

Substantial Completion of the Work, including authorized adjustments made as part of Change Orders agreed to by the Contractor Design Professional and UCA.

8.1.2 Date for commencement of the Work is the fifth calendar day following the date

of mailing, by regular mail, of the Notice to Proceed, unless otherwise stated in the Contract.

8.1.3 Date of Substantial Completion is the date certified by the Design Professional

and UCA. 8.2 PROGRESS 8.2.1 Time limits identified in the Contract Documents are of the essence of the

Contract. The Contractor confirms that the Contract Time is a reasonable period of time for performing the Work.

8.3 HOLIDAYS 8.3.1 New Year's Day, Robert E. Lee/Dr. Martin Luther King's Birthday, President’s

Birthday, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day and the day thereafter, Christmas Eve and Christmas Day will be considered as being legal holidays; no other days will be considered unless declared by the Governor of the State of Arkansas through an Executive Order or Proclamation. No Design Professional clarifications, observations, or State inspections will be provided on legal holidays.

8.4 DELAYS 8.4.1 Delays beyond the Contractor's control occasioned by an act or omission on the

part of the Owner, strikes, fires, additions to the work, delays by any separate contractor employed by the Owner, extremely abnormal weather conditions, or other delays beyond the Contractor’s control may, if agreed to by Change Order by the Contractor, the Design Professional and entitle the Contractor to an extension of time in which to complete the work. While such delays may be just cause for an extension of the Contract Time, the Contractor shall not have a claim for damages for any such cause or delay.

Page 44: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

8.5 INCLEMENT WEATHER

8.5.1 Include in construction time stated in Contract documents an allowance for

calendar days per month which, according to the following inclement weather table may not be available for construction out-of-doors (normal inclement weather).

January (7) April (7) July (6) October (3) February (5) May (8) August (4) November (6) March (7) June (6) September (6) December (4)

8.5.2 Contract time will not be extended due to normal inclement weather unless the

Contractor can substantiate, to satisfaction of Architect, that greater-than-normal inclement weather occurred, considering the full term of contract Time, using a 5-year average of accumulated record mean values from climatological data compiled by the U.S. Department of commerce National Oceanic and Atmospheric Administration for the project local, and that alleged greater-than-normal inclement weather actually delayed work or portions of work. All inclement weather day extension submittals must be submitted to the Architect for review and approval by the 15th of the following month.

ARTICLE 9 -- PAYMENTS AND COMPLETION 9.1 CONTRACT SUM 9.1.1 The Contractor shall accept the compensation, as herein provided, in full

payment for furnishing all materials, equipment, labor, tools, and incidentals necessary to complete the Work and for performing all Work contemplated and embraced under the Contract; also for loss or damage arising from the nature of the Work, from the action of the elements or from any unforeseen difficulties which may be encountered during the prosecution of the Work until the final acceptance by the Design Professional and Owner and for all risks of every description connected with the prosecution of the Work, for all expenses incurred in consequence of the suspension or discontinuance of the Work as specified, for any infringement of patent, trademark, or copyright, and for completing the Work according to the Contract Documents. Neither the payment of any estimate nor of any retained percentage shall relieve the Contractor of any obligation to make good any defective work or material.

9.1.2 No moneys payable under Contract or any part thereof, except the estimate for

the first month or period, shall become due and payable if the Owner so elects until the Contractor shall satisfy the said Owner that he has fully settled or paid

Page 45: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

for all materials and equipment used in or on the Work and labor done in connection therewith, and the Owner, if he so elects, may pay any or all such bills wholly or in part and deduct the amount or amounts so paid from any monthly or final estimate excepting the first estimate.

9.1.3 In the event the surety on any contract or payment bond given by the Contractor becomes insolvent, or is placed in the hands of a receiver, or has the right to do business in a state revoked as provided by law, the Owner may at its election withhold payment of any estimate filed or approved by the Design Professional until the Contractor shall give a good and sufficient bond in lieu of the bond so executed by such surety. Any and all subsequent bonds shall be filed with the Circuit Clerk of the County in which the Work is being performed.

9.2 SCHEDULE OF VALUES 9.2.1 The Contractor shall submit to the Design Professional a schedule of values for

each part of the Work. The schedule shall be a complete breakdown of labor and materials for the various parts of the Work including an allowance for profit and overhead. The total of these amounts shall equal the Contract Sum. The approved schedule of values shall be used as a basis for the monthly payments to the Contractor. In applying for the monthly payment, the Contractor shall show a detailed account of work accomplished in conformity with the schedule.

9.3 MEASUREMENT OF QUANTITIES 9.3.1 The Contractor shall be paid for all Work performed under the Contract based

on Design Professional computations of as-built quantities and the Contractor's Contract Sum. This payment shall be full compensation for furnishing all supplies, materials, tools, equipment, transportation, and labor required to do the Work; for all loss or damage, because of the nature of the Work, from the action of the elements or from any unforeseen obstruction or difficulty which may be encountered in the prosecution of the Work and for which payment is not specifically provided for all or any part of the Work; and for well and faithfully completing the Work in accordance with the Contract Documents. The method of computation and payment for each item shall be as set forth in the Specifications.

9.4 REQUESTS FOR PAYMENT 9.4.1 The Contractor may submit periodically, but not more often than once each

month, a Request for Payment for work completed. When unit prices are specified in the Contract Documents, the Request for Payment shall be based on the quantities completed.

9.4.2 Unless otherwise provided in the Contract Documents, payments will be made

on account of materials or equipment not incorporated in the Work but delivered and suitably stored at the site, and if approved in advance by the Owner, payments may similarly be made for materials or equipment suitably stored at some other location agreed upon in writing. Payments for materials

Page 46: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

or equipment stored on or off the site shall be conditioned upon submission by the Contractor of bills of sale or such other procedures satisfactory to the Owner and the Design Professional to establish the Owner's title to such materials or equipment or otherwise protect the Owner's interest including applicable insurance and transportation to the site for those materials and equipment stored off the site.

9.4.3 The Contractor shall furnish the Design Professional all reasonable facilities and

job tickets required for obtaining the necessary information relative to the progress and execution of the Work and the measurement of quantities. Each Request for Payment shall be computed from the work completed on all items listed in the approved schedule of values less retainage as indicated in Paragraph 9.5.2.

9.5 PERIODIC ESTIMATES FOR PAYMENT 9.5.1 Unless otherwise stated in the Specifications, the Owner shall cause the Design

Professional to prepare an Estimate for Payment to the Contractor each month. The Design Professional will make the estimate for the materials complete in place and the amount of work performed in accordance with the Contract between the twenty-fifth day of the month and the fifth day of the succeeding month.

9.5.2 From the total of the amount estimated to be paid, an amount equal to five

(5) percent of the total completed shall be retained from each payment request. All sums withheld by the Owner and requested in a Final Pay Request prepared by the Owner or Contractor will be paid to the Contractor within 30 days after the Contract has been completed and the work approved by UCA. No retainage will be withheld on that amount of the progress payment pertaining to the cost of materials stored at the site or within a bonded warehouse.

9.6 PAYMENT FOR INCREASED OR DECREASED QUANTITIES 9.6.1 When alterations in the quantities of work not requiring Contract modifications

are ordered and performed, the Contractor shall accept payment in full at the Contract Sum, for the actual quantities of work accomplished. No allowance will be made for anticipated profits. Increased or decreased work involving Contract modifications shall be paid for as stipulated in such Contract modifications

9.7 DESIGN PROFESSIONAL'S ACTION ON A REQUEST FOR PAYMENT (See

9.9) 9.7.1 The Owner shall cause the Design Professional to, within five working days plus

time required for transmittal from one party to another, act on a Request for Payment by the Contractor in one of the following:

a. Approve the Request for Payment as submitted by the Contractor, and

transmit same to the Owner.

Page 47: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

b. Approve an adjusted amount, as the Design Professional will decide is

due the Contractor informing the Contractor in writing of the reason for the adjusted amount, and transmit same to the Owner.

c. Withhold the Request for Payment submitted by the Contractor

informing the Contractor, and UCA in writing of the reason for with-holding the request.

9.8 OWNER'S ACTION ON A REQUEST FOR PAYMENT AND FINAL

PAYMENT (See 9.9) 9.8.1 The Owner will, within five working days plus transmittal time between the

various state agencies involved, act on a Request for Payment (not Final) after approval by the Design Professional by one of the following:

a. Approve the Request for Payment as approved by the Design

Professional, process the payment. b. Approve payment of an adjusted amount as the Owner will decide is due

the Contractor, informing the Contractor and, the Design Professional in writing of the reason for the adjusted amount of payment.

c. Withhold the Request for Payment informing the Contractor, and the

Design Professional in writing of the reason for withholding the payment. 9.8 ARKANSAS STATE AGENCIES ACTION ON A REQUEST FOR PAYMENT 9.8.1 The State shall process payments in accordance with Ark. Code Ann. §19-4-

1411, which establishes the time limits for the Design Professional, the Owner, and the Department of Finance and Administration. It also authorizes the Chief Fiscal Officer of the State to investigate any complaints of late payments and assess penalties for late payment. Complaints shall be addresses to “Chief Fiscal Officer of the State: Department of Finance and Administration; 1509 West Seventh Street, Suite 401; Post Office Box 3278; Little Rock, AR 72203-3278.

9.9 WITHHOLDING PAYMENT 9.9.1 The Design Professional or the State may withhold payment for contested

issues, including but not limited to, defective work on the project; evidence indicating the probable filing of claims by other parties against the Contractor related to the project; damage caused to another contractor; reasonable evidence that Work cannot be completed for the unpaid balance of the Contract Sum or within Contract Time or failure of the Contractor to make payments on materials, equipment or labor to subcontractors. It is the responsibility of the contesting party to notify the Contractor in writing that payment has been contested and the reasons why. The notification must be done within the timeframe specified for processing of payment under Ark. Code Ann. §19-4-1411.

Page 48: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

9.10 PAYMENT FOR UNCORRECTED WORK 9.10.1 Should the Design Professional direct the Contractor not to correct work that

has been damaged or that was not performed in accordance with the Contract Documents, an equitable deduction from the Contract Sum shall be made to compensate the Owner for the uncorrected work. The Design Professional shall determine the amount of the equitable deduction.

9.11 PAYMENT FOR REJECTED MATERIALS AND WORK 9.11.1 The removal of rejected Work and materials and the re-execution of acceptable

work by the Contractor shall be at the expense of the Contractor. The Contractor shall pay the cost of replacing the work of other contractors destroyed or damaged by the removal of the rejected work or materials and the subsequent replacement with acceptable work.

9.12 DATE OF SUBSTANTIAL COMPLETION 9.12.1 A Certificate of Substantial Completion, which shall establish the Date of

Substantial Completion, shall state the responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to work, and insurance and shall fix the time within which the Contractor shall complete the items listed therein. Warranties required by the Contract Documents shall commence on the Date of Substantial Completion, unless another timeframe is stated in the Certificate of Substantial Completion. The Certificate of Substantial Completion shall not become effective until approved by UCA.

9.13 FINAL COMPLETION AND PAYMENT BY OWNER 9.13.1 The Contractor shall furnish a letter from the Design Professional attached to

the Contractor's final estimate, which shall include all retainage withheld, certifying that the Design Professional has received and approved all guarantees, bonds, maintenance and operation manuals, air balance data, shop drawings, catalog data, and record documents specified in the Contract Documents.

9.13.2 Before final payment, the Contractor shall furnish to the Design Professional

executed copies of the Release of Claims and Consent of the Performance and Payment Bond Surety for Final Payment. Items listed in this Section Nine (9) shall be submitted with and at the same time as the final estimate to the Design Professional and shall be promptly delivered by the Design Professional to the Owner. No final payment or release of retained amounts shall be made without complete compliance with this Section Nine (9), and approval by UCA of the Final Pay Request, which shall include payment of all retained amounts,

9.14.3 Any claim by the Contractor to the Owner for interest on a delinquent final

payment shall only be made pursuant to Ark. Code Ann. § 22-9-205. 9.14 PARTIAL OCCUPANCY OR USE 9.14.1 The Owner may occupy or use any completed or partially completed portion of

the Work provided such use or occupancy is consented to by the insurer and

Page 49: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

authorized. The Contractor will prepare a list of items to be completed or corrected before partial acceptance. Upon receipt of the Contractor’s list, the Design Professional will make an inspection to determine whether the Work or portion thereof is substantially complete. No portion of the work shall be considered substantially complete unless described in a Certificate of Substantial Completion Form approved by the Contractor, Owner, and Design Professional.

9.14.2 The Design Professional will prepare a Certificate of Substantial Completion

which shall establish the date of Substantial Completion, shall state the responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to Work and insurance, identify work items to be corrected or completed by the contractor and shall fixing the time within which the Contractor shall complete the items listed therein. Warranties required by the Contract Documents shall commence on the Date of Substantial Completion, unless another timeframe is stated in the Certificate of Substantial Completion. No retained amounts shall be paid until the Contractor, Design Professional and the Owner approve a Certificate of Substantial Completion for all of the Work unless specifically provided for by this contract, and all other conditions for final acceptance of this Work are met to the satisfaction of the Owner.

9.15.3 Instances where some of the Work is “sectioned” out and substantially

completed, the retained amounts shall not be paid until the final Certificate of Substantial Completion of the entire Work is approved by the Contractor, Design Professional and the Owner and all other conditions of this Section Nine (9) are met by the Contractor.

9.15 FINAL INSPECTION 9.15.1 Tests, inspections, and approvals of portions of the Work required by the

Contract Documents, laws, ordinances, or any public authority having jurisdiction shall be made at the appropriate time. The Contractor shall give the Design Professional timely notice of when and where tests and inspections shall be made so that the Design Professional may be present. The Contractor shall make arrangements for the testing and inspection with an independent testing laboratory.

9.15.2 The Contractor shall ensure that the final completed work is in accordance with

the Contract Documents. Required certificates of testing and inspection shall be secured by the Contractor and delivered to the Design Professional, unless otherwise required by the Contract Documents.

9.16 ASSIGNMENT OF WARRANTIES 9.16.1 All warranties of materials and workmanship running in favor of the Contractor

shall be transferred and assigned to the Owner on completion of the Work and at such time as the Contractor receives final payment.

Page 50: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

9.16.2 In case of warranties covering work performed by subcontractors, such warranties shall be addressed to and in favor of the Owner. The Contractor shall be responsible for delivery of such warranties to the Owner prior to final acceptance of the work.

9.16.3 Delivery of guarantees or warranties shall not relieve the Contractor from any

obligation assumed under any provision of the Contract. All warranties shall be for one year from the date of Substantial Completion of the Project, unless extended otherwise

9.17 ACCEPTANCE AND FINAL PAYMENT 9.17.1 Upon receipt of written notice that the Work is ready for final inspection, the

Design Professional together with UCA will conduct such inspection and when the Design Professional determines the work is acceptable to the Design Professional, UCA and the Design Professional shall certify his acceptance to the Owner. Final Payment shall be the Contract Sum plus approved Change Order additions less approved Change Order deductions and less previous payments made. The Contractor shall furnish evidence that he has fully paid all debts for labor, materials, and equipment incurred in connection with the Work. The Owner, upon approval by the Design Professional of all documentation to be provided by the contractor in accordance with this Section 9, and approval by the Design Professional, Contractor and Owner of the Certificate of Substantial Completion will accept the Work and release the Contractor, except as to the conditions of the Performance and Payment Bond, any legal rights of the Owner, required guarantees and correction of faulty work after Final Payment, and shall authorize payment of the Contractor's final Request for Payment. The Contractor must allow sufficient time between the time of completion of the work and approval of the final Request for Payment for the Design Professional to assemble and check the necessary data.

9.17.2 Acceptance of final payment by the Contractor shall constitute waiver of all

claims by the Contractor except those previously made in writing and identified by the Contractor as unsettled at the time of the final Request for Payment. Any claims for interest on delinquent payments shall be made pursuant to Ark. Code Ann. § 22-9-205.

ARTICLE 10 -- PROTECTION OF PERSONS AND PROPERTY 10.1 GENERAL 10.1.1 The Contractor shall at all times exercise precaution for the safety of employees

on the Project and of the public, and shall comply with all applicable provisions of federal, state and municipal safety laws and applicable building and construction codes. The Contractor shall provide and maintain passageways, guard fences, lights, and other facilities for protection required by all applicable laws. All machinery, equipment, and other physical hazards shall be guarded in accordance with all federal, state or municipal laws or regulations.

Page 51: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

10.1.2 The Work, from commencement to completion, and until written acceptance by the Design Professional, and the Owner or to such earlier date or dates when the Owner may take possession and control in accordance with Section Nine (9) of these General Conditions, shall be under the charge and control of the Contractor and during such period of control by the Contractor, all risks in connection therewith shall be borne by the Contractor. The Contractor shall make good and fully repair all damages to the Project by reason of the Contractor’s negligence, and make good on all injuries to persons caused by any casualty or cause by reason of the Contractor's negligence. The Contractor shall adequately protect adjacent Property as provided by law and the Contract Documents. The Contractor shall hold the Owner harmless from any and all claims for injuries to persons or for damage to property during the control by the Contractor of the project or any part thereof.

10.1.3 The Contractor shall at all times so conduct the Work as to ensure the least

possible obstruction to traffic, to the general public, and the residents in the vicinity of the Work, and to ensure the protection of persons and property. No road, street, or highway shall be closed to the public except with the permission of the Owner and proper governmental authority. Fire hydrants on or adjacent to the Work shall be kept accessible to fire-fighting equipment at all times. The local fire department shall be notified of the temporary closing of any street.

ARTICLE 11 -- INSURANCE AND BONDS 11.1 CONTRACTOR’S LIABILITY INSURANCE 11.1.1 The Contractor shall secure and maintain in force during this Contract such

insurance as is specified within the Contact Documents, from an insurance company authorized to write the prescribed insurance in the jurisdiction where the Project is located as will protect the Contractor, his subcontractors, and the Owner from claims for bodily injury, death, or property damage which may arise from operations under this Contract. The Contractor shall not commence work under this Contract until he has obtained all the insurance required, has filed the Certificate of Insurance with the Owner, and the certificate has been approved by the Owner. Each insurance policy shall contain a clause providing that it shall not be canceled by the insurance company without written notice to the Owner of intention to cancel.

11.1.2 Workman's Compensation and Employer's Liability Insurance in statutory limits

shall be secured and maintained as required by the laws of the State of Arkansas. This insurance shall cover all employees who have performed any of the obligations assumed by the Contractor under these Contract Documents including Employer's Liability Insurance. This insurance shall protect the Contractor against any and all claims resulting from injuries, sickness, disease, or death to employees engaged in work under this Contract.

11.1.3 Comprehensive General Liability Insurance, including automobile and truck

liability. Prior to blasting, the Contractor shall furnish Certificate of Insurance, which shall certify that damage caused by blasting is within the coverage of his

Page 52: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

Comprehensive General Liability Insurance to the full limits thereof. Hired and non-owned automobile insurance for automobiles and trucks shall include hired and non-owned automobile coverage.

11.1.4 Contractor's Protective Liability Insurance: The Contractor shall indemnify and

save harmless the Owner from and against all losses and all suits, claims, demands, judgments, actions, and payments of every description and nature brought or recovered against him by reason of any omission or act of the Contractor, his agents, or employees in the execution of the Work or in the guarding of it. The Contractor shall secure and maintain protective liability insurance in the name of the Owner and the Contractor covering them from contingent liability under this Contract.

11.1.5 Builder's Risk and Fire Insurance: The Contractor shall procure and maintain

during the life of this Contract Builder's Risk Insurance fire, lightning, extended coverage, vandalism, and property theft on the insurable portion of the Project on a 100 percent completed value basis against damage to the equipment, structures, or material. The Owner and the Contractor, as their interests may appear, shall be named as the Insured.

11.1.6 Proof of Insurance: The Contractor shall maintain the insurance coverage’s

required by this contract (see Section 007316 Insurance requirements) throughout the term of this contract, and shall furnish the Owner with certificates showing the type, amount, class of operations covered, effective dates and dates of expiration of policies. Such certificates shall also contain substantially the following statement: "The insurance covered by this certificate will not be canceled, or materially altered except after 15 days prior written notice has been received by the Owner."

11.2 BONDS 11.2.1 Performance and Payment Bond: The Contractor shall, at the time of execution

of the Contract, furnish bonds covering faithful performance of the Contract and the payment of obligations. Performance and Payment bond, and any amendments thereto, shall be filed with the circuit clerk office in the County Courthouse of the county where the work shall be performed.

ARTICLE 12 -- UNCOVERING AND CORRECTION OF WORK 12.1 EXAMINATION OF COMPLETED WORK 12.1.1 If any portion of the work should be covered contrary to the request of the

Owner, Design Professional, or Inspector or to requirements specifically expressed in the Contract Documents, it must, if required in writing by the Owner, Design Professional, or Inspector, be uncovered for his observation and replaced at the Contractor's expense.

12.2 DEFECTIVE WORK

Page 53: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

12.2.1 Defective work, whether through the use of defective materials, the result of poor workmanship, or any other cause, shall be removed within ten days after notice is given by the Owner or Design Professional. The Work and affected materials and equipment shall be removed and replaced as necessary to comply with the Contract Documents without additional cost to the Owner. The fact that the defective work may have been previously overlooked by the Design Professional shall not constitute acceptance.

12.3 REJECTED MATERIALS 12.3.1 Materials which do not conform to the requirements of the Contract Documents,

are not equal to samples approved by the Design Professional, or are in any way unsuited or unsatisfactory for the purpose for which intended, shall be rejected. Defective materials shall be removed within ten days after notice by the Design Professional. The materials shall be replaced with new materials as necessary to comply with the Contract Documents at no additional cost to the Owner. The fact that the defective material may have been previously over-looked by the Design Professional shall not constitute acceptance.

12.3.2 Should the Contractor fail to remove and replace rejected material within the

specified ten days after written notice to do so, the Owner may remove and replace the material and deduct the cost from the Contract Sum.

12.4 CORRECTION OF FAULTY WORK AFTER FINAL PAYMENT 12.4.1 The approval of the final Request for Payment by the Design Professional and

the making of the final payment by the Owner to the Contractor shall not relieve the Contractor of responsibility to correct faulty materials or workmanship promptly after receipt of written notice from the Owner. The Owner shall give such notice of faulty materials or workmanship promptly, after discovery of the condition. If the Contractor fails to correct the defects, promptly, after receipt of written notice from Owner, the Owner may have the work corrected at the Contractor’s expense.

ARTICLE 13 -- MISCELLANEOUS PROVISIONS 13.1 GOVERNING LAW 13.1.1 The Contract shall be governed by the laws and regulations of the STATE OF

ARKANSAS. Venue for any administrative action or judicial proceedings shall be Pulaski County, Arkansas. Nothing in these General Conditions shall be construed to waive the sovereign immunity of the STATE OF ARKANSAS or any entities thereof.

13.1.2 The Contractor shall give all notices and comply with all federal, state, and local

laws, ordinances, and regulations in any manner affecting the conduct of the Work. The Contractor shall indemnify and save harmless the Owner against any claim or liability arising from or based on the violation of any such law, ordinance, regulation, order, or decree whether by himself or his employees.

Page 54: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

13.1.3 The Contractor shall comply with the laws of the local, state, and federal

government regarding wages and hours of labor. 13.2 WRITTEN NOTICE 13.2.1 Consider as served when delivered in person or sent by certified or registered

mail to the individual, firm, or corporation or to the last business address of such known to him who serves the notice.

13.2.2 The written Notice to Proceed with the Work shall be issued by the Design

Professional after the execution of the Contract by the Owner. The Contractor shall begin and prosecute the Work and uninterruptedly in a manner that will complete the Work within the time limits stated in the Contract.

13.3 TESTS AND INSPECTIONS 13.3.1 All materials and each and every part of the Work shall be subject at all times

to inspection by the Owner, Design Professional, or the Inspector. The Contractor shall be held to the intent of the Contract Documents in regard to quality of materials, equipment, and workmanship, and the diligent execution of the Contract. The inspection may extend to and include plant, shop, or factory inspection of material furnished. The Contractor agrees to allow Federal or State inspectors, acting in an official capacity, to have access to the job site.

13.3.2 The Owner, Design Professional and the Inspector shall be allowed access to all

parts of the Work and shall be furnished with such information and assistance by the Contractor as is required to make a complete and detailed inspection for ascertaining if the Work as performed is in accordance with the requirements and the Contract Documents.

13.3.3 Inspectors shall only have authority to suspend any work in a life-threatening

situation, which is being improperly done, subject to the final decision of the Owner or Design Professional. Inspectors shall have no authority to permit deviations, or to relax provisions of the Contract Documents without the written permission or instruction of the Owner or Design Professional, or delay the Contractor by failing to work with reasonable promptness.

13.4 VERBAL AGREEMENTS 13.4.1 No verbal objection, order, claim, or notice by any of the parties involved to the

other parties shall affect or modify any of the terms or obligations contained in the Contract Documents. None of the terms or provisions of the Contract Documents shall be considered waived or modified unless the waiver or modification thereof is in writing, and agreed upon by the parties in the form of a Change Order approved by the Design Professional, Contractor and UCA, and no evidence shall be introduced in any proceeding of any other waiver or modification.

Page 55: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

ARTICLE 14 -- TERMINATION OR SUSPENSION OF THE CONTRACT 14.1 SUSPENSION OF WORK 14.1.1 The work or any portion thereof may be suspended at any time by the Owner

provided that the Owner gives the Contractor written notice of the suspension. The notice shall set forth the date on which the work is to be suspended and the date on which the work is to be resumed. The Contractor shall resume the work upon written notice from the Owner within ten days after the date set forth in the notice of suspension.

14.1.2 The Owner will have the authority to suspend the work, wholly or in part, for such period of time as deemed necessary. The suspension may be due to unsuitable weather, or such other conditions as are considered unfavorable for the proper prosecution of the work, or the failure on the part of the Contractor to fulfill the provisions of the Contract. Failure to supply material, equipment, or workmanship meeting the requirements of the Contract Documents shall be just cause for suspension of the Work. The Contractor shall not have the right to suspend operations without the Design Professional or Owner's permission.

14.2 TERMINATION BY OWNER FOR CAUSE 14.2.1 The Owner will have the right to terminate the Contract upon giving ten days

written notice of the termination to the Contractor and the Contractor’s surety, in the event of any default by the Contractor and upon written notice from the Design Professional to the Owner that sufficient cause exists to justify such action. In the event of termination of the Contract, the Owner may take possession of the Work and of all materials, tools, and equipment and construction equipment and machinery thereon and may finish the work by whatever method he may select. If the Owner does not elect to use his own forces, the surety shall furnish a competent licensed contractor within 10 working days from the written notice to the surety.

14.2.2 It shall be considered a default by the Contractor whenever he shall become

insolvent; declare bankruptcy assigns assets for the benefit of his creditors; fails to provide qualified superintendence, proper materials, competent subcontractors, competent workmen; fails to make prompt payments for labor, materials, or equipment; disregards or violates provisions of the Contract Documents; disregards the Owner’s, or the Design Professional’s instructions; fails to prosecute the Work according to the approved schedule of completion, including extensions thereof as provided for by approved Change Orders; and fails to start the Work on the date established in the Notice to Proceed.

14.3 TERMINATION BY OWNER FOR CONVENIENCE The Owner will have the right to terminate the Contract for Convenience and

without cause upon giving ten days written notice of the termination to the Contractor and Contractor’s surety and UCA. Once notice is received, the Contractor shall: cease all operations as indicated by the written notice and take necessary actions or at the Owner’s direction as indicated by the written notice, for the protection and preservation of the work; and terminate existing

Page 56: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

subcontractors and purchase orders upon the effective termination date as indicated in the notice and not enter into any contracts involving subcontractors or purchase orders.

If the contract is terminated upon the convenience of the Owner, the

Contractor is entitled to receive payment for the work executed and accepted by the Owner, and the overhead and profit credit amount of 7% of the work that was left to be performed in the contract.

ARTICLE 15 – ALTERNATIVE DISPUTE RESOLUTION 15.1 MEDIATION 15.1.1 In the event of any dispute regarding the Contractor, Architect, Engineer, and/or Owner (hereinafter referred to as party/parties for this section only) under this Agreement, the party shall notify the appropriate UCA Administrator (UCA Purchasing Director) in writing. The UCA Administrator or his designee will then attempt to negotiate a settlement of the dispute between the parties. 15.1.2 If the UCA Administrator, or designee, determines he is unable to negotiate a settlement between the parties, the parties may participate in mediation. A request for mediation must be made in writing to the Owner and the parties shall agree upon the location of the mediation. A Mediator mutually agreed upon by the parties shall conduct the mediation process. Mediation shall be voluntary, non-binding and all proceedings in connection with such shall be subject to this Agreement and applicable provisions of Arkansas law. Any mediation fees shall be borne equally between the parties. The parties shall coordinate mediation and the Owner shall notify of any mediation prior to it taking place. UCA Administrator or his designee may view any and all mediation proceedings. Any settlements arising out of the mediation process must be approved by UCA. 15.1.3 Notwithstanding anything to the contrary contained herein, if any dispute arises between the Parties, whether or not it requires at any time the use of dispute resolution procedures described above, in no event, nor for any reason, shall the Contractor, Architect, or Engineer interrupt the provision of services/performance to the Owner, or perform any other action that prevents, slows down, or reduces, in any way, the provisions of the Agreement unless: (a) authority to do so is granted by UCA and approved by UCA or (b) the Agreement has been terminated by the UCA. Nothing in these contract documents, including the use of mediation, shall be construed to waive the sovereign immunity of the State of Arkansas or any entities thereof. 15.2. ARBITRATION 15.2.1 In the event of any dispute regarding the Contractor, Architect, Engineer, and/or Owner (hereinafter referred to as party/parties for this section only) under this Agreement, the party shall notify the appropriate UCA Administrator (Purchasing

Page 57: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

Director) in writing. The UCA Administrator or his designee will then attempt to negotiate a settlement of the dispute between the parties. 15.2.2 Claims, disputes and other matters in question between the parties may be decided by arbitration if the UCA Administrator, or designee, determines he is unable to negotiate a settlement (due to time or other reasons) between the parties, and/or the parties are unwilling to have UCA negotiate and/or the parties are unable to settle the dispute, and these issues were not resolved by mediation. Requests for arbitration must be made in writing to the Owner. The parties shall agree upon the Arbitrator, process and procedures and the location of arbitration. Arbitration while voluntary shall be binding and all proceedings in connection with such shall be subject to this Agreement and applicable provisions of Arkansas law. Any arbitration fees shall be borne equally between the parties. The parties shall coordinate arbitration and the Owner shall notify of any arbitration prior to it taking place. UCA Administrator or his designee may view any and all arbitration proceedings. 15.2.3 Notwithstanding anything to the contrary contained herein, if any dispute arises between the Parties, whether or not it requires at any time the use of dispute resolution procedures described above, in no event, nor for any reason, shall the Contractor, Architect, or Engineer interrupt the provision of services/performance to the Owner, or perform any other action that prevents, slows down, or reduces, in any way, the provisions of the Agreement unless: (a) authority to do so is granted by UCA and approved by UCA or (b) the Agreement has been terminated by UCA. Any award rendered by the arbitrator shall be final. Nothing in these contract documents, including the use of arbitration, shall be construed to waive the sovereign immunity of the State of Arkansas or any entities thereof.

End of SECTION 007213 GENERAL CONDITIONS

Page 58: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

CONTRACTOR’S INSURANCE REQUIREMENTS Section 007316

(1) Commercial General Liability: The Contractor shall obtain, at Contractor’s expense, and keep in effect during the term of the contract, Commercial General Liability insurance covering bodily injury and property damage containing minimum limits of one million dollars ($1,000,0000) written on a per occurrence form with a two million dollars ($2,000,000) aggregate limit. This insurance shall include personal injury coverage with employment exclusion deleted, and contractual liability. Such coverage shall include products and completed operations and shall not be excluded under the commercial general liability insurance. Nothing shall prohibit the University from requiring increased amounts than stated herein. (2) Umbrella Liability: The Contractor shall be required to furnish umbrella liability coverage, and keep in effect during the term of the contract which provides excess limits over the primary coverage. Agencies must refer to the recommendation of the Risk Management division of the Arkansas Insurance Department on the minimum amount of coverage. (3) Automobile Liability: The Contractor shall obtain, at Contractor’s expense and keep in effect during the term of the contract, automobile liability insurance including hired and non-owned coverage in minimum amounts of one million dollars (1,000,000) per occurrence. (4) Workers’ Compensation and Employers’ Liability: The Contractor, its subcontractors, if any and all employee providing work, labor or materials used in connection with this work. (5) Contractor’s Equipment: (a) The Contractor shall be responsible for any loss, damage or destruction of its own property or that of any subcontractor’s equipment and materials used in connection with this work. (b) Contractor will purchase at Contractor’s own sole cost and expense such policy to cover contractor’s owned property. (c) Contractor will provide waiver of subrogation to Owner. (d) Pollution Liability: If requested by Owner at any time, Contractor shall, at Contractor’s expense, obtain and maintain in force and effect for the term of the contract Pollution Liability Insurance covering losses caused by pollution conditions that result from the performance of the Contract. This requirement also applies to any consultant or contractor engaged by Contractor or performing construction, geotechnical, well drilling, abatement activities or contractor services. (e) Pollution Liability Insurance shall cover Owner costs and liabilities attributable to bodily injury; property damage, including loss of use of damaged property or of

Page 59: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

property that has not been physically injured; clean-up cost; and defenses, including costs and expenses (including attorney’s fees) incurred in the investigation, defense or settlement of claims. Contractor shall maintain such insurance in an amount of at least two million dollars (2,000,000) per loss with annual aggregate of at least five million dollars ($5,000,000). Nothing shall prohibit the University from increasing the amounts stated herein. (f) If coverage is written on a claims-made basis, Contractor represents that any retroactive dates applicable to coverage under the policy precedes the effective date of the letter; and that continuous coverage will be maintained or an extended discovery period will be exercised for a period of three (3) years or as required by law beginning from the time that services under the contract are completed. (g) If the scope of work as defined in this Contract includes the disposal of any hazardous or non-hazardous materials from the Projects site, the Contractor must furnish to the owner evidence of pollution liability insurance maintained by the disposal site operator for losses arising from the insured facility accepting waste under this Contract. Such coverage must be maintained in amounts conforming to applicable laws, rules and regulations. (h) Remediation: Remediation Contractor shall provide liability insurance for the removal or remediation of asbestos including the transportation and disposals of asbestos waste materials from the Project site. Limits of insurance shall be not less than those required under the Commercial General Liability policy. Depending on the nature and amount of asbestos to be removed/abate, Owner may request higher limits than those required by the Commercial General Liability policy. (i) Additional Requirements: All policies shall be provided by insurers qualified to write the respective insurance in the State of Arkansas, be in such form and include such provision as are generally considered standard provisions for the type of insurance involved.

END OF SECTION 007316 CONTRACTOR’S INSURANCE REQUIREMENTS

Page 60: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

The Architect of Record for the Specifications for the Mashburn Hall Reroofing and Deck Replacement, University of Central Arkansas, Conway, Arkansas, is Stocks-Mann Architects, PLC.

Issue Date: May 18, 2018

I hereby certify that these specifications have been prepared by me, or under my supervision. I further certify that to the best of my knowledge these specifications are as required by law and in compliance with the Arkansas Fire Prevention Code for the State of Arkansas. _________________________________________ R. Mark Mann Arkansas Registration No. 1509

5/18/18

Page 61: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

011000 Page 1

UCA Mashburn Hall Reroofing and SUMMARY Deck Replacement SMA #1505H

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Identification: Project consists of reroofing and reroofing / metal deck replacement on portions of Mashburn Hall .

1. Project Location: Mashburn Hall, University of Central Arkansas, 201 Donaghey Ave., Conway, Arkansas.

B. Owner: University of Central Arkansas, 201 Donaghey Ave., Conway, Arkansas.

1. Owner's Representative: Gus Hickey, Construction Inspector, Physical Plant; (501) 339-4061.

C. Architect: Stocks-Mann Architects, PLC, 401 W. Capitol, Suite 402, Little Rock, Arkansas 72201.

D. The Work will consist of the reroofing of approximately 13,810 square feet of roof area and the replacement of 3,485 square feet of existing metal deck.

E. Project will be constructed under a general construction contract.

1.2 USE OF PREMISES

A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

B. Use of Site: Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances. b. Schedule deliveries to minimize space and time requirements for storage of

materials and equipment on-site.

C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

Page 62: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

011000 Page 2

UCA Mashburn Hall Reroofing and SUMMARY Deck Replacement SMA #1505H

1.3 COORDINATION WITH OCCUPANTS

A. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.

1. Architect will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner acceptance of the completed Work.

2. Obtain a Certificate of Occupancy from authorities having jurisdiction before limited Owner occupancy.

3. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems serving occupied portions of Work.

4. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work.

1.4 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 3:30 p.m., Monday through Friday, unless otherwise coordinated with UCA.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Owner not less than three days in advance of proposed utility interruptions. 2. Obtain Owner's written permission before proceeding with utility interruptions.

D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.

1. Notify Owner not less than two days in advance of proposed disruptive operations. 2. Obtain Owner's written permission before proceeding with disruptive operations.

E. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.

F. Controlled Substances: Use of tobacco products and other controlled substances on Project site is not permitted.

1.5 SPECIFICATION FORMATS AND CONVENTIONS

Page 63: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

011000 Page 3

UCA Mashburn Hall Reroofing and SUMMARY Deck Replacement SMA #1505H

A. Specification Format: The Specifications are organized into Divisions and Sections using the 16-division format and CSI/CSC's "MasterFormat" numbering system.

B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.

2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

Page 64: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012100 Page 1

UCA Mashburn Hall Reroofing and ALLOWANCES Deck Replacement SMA #1505H

SECTION 012100 - ALLOWANCES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements governing the following:

1. Unit-cost allowances.

B. Related Requirements:

1. Section 012200 "Unit Prices" for procedures for using unit prices, including adjustment of quantity allowances when applicable.

1.2 SELECTION AND PURCHASE

A. At the earliest practical date after award of the Contract, advise Architect of the date when final selection and purchase of each product or system described by an allowance must be completed to avoid delaying the Work.

B. At Architect's request, obtain proposals for each allowance for use in making final selections. Include recommendations that are relevant to performing the Work.

C. Purchase products and systems selected by Architect from the designated supplier.

1.3 ACTION SUBMITTALS

A. Submit proposals for purchase of products or systems included in allowances in the form specified for Change Orders.

1.4 INFORMATIONAL SUBMITTALS

A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.

B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.

C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.

Page 65: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012100 Page 2

UCA Mashburn Hall Reroofing and ALLOWANCES Deck Replacement SMA #1505H

1.5 COORDINATION

A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.

1.6 UNIT-COST ALLOWANCES

A. Allowance shall include cost to Contractor of specific products and materials ordered by Owner under allowance and shall include taxes, freight, delivery to Project site, receiving and handling at Project site, labor, installation, overhead and profit.

1.7 UNUSED MATERIALS

A. Return unused materials purchased under an allowance to manufacturer or supplier for credit to Owner, after installation has been completed and accepted.

1. If requested by Architect, prepare unused material for storage by Owner when it is not economically practical to return the material for credit. If directed by Architect, deliver unused material to Owner's storage space. Otherwise, disposal of unused material is Contractor's responsibility.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.

3.2 PREPARATION

A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.

3.3 SCHEDULE OF ALLOWANCES

A. Allowance No. 1: Unit Cost Allowance: Include the removal of 700 square feet of 2 ½ inch- thick wet lightweight concrete roof deck and replacement with 2 ½ inches of rigid polyisocyanurate roofing insulation board.

1. This allowance includes material cost receiving, handling, and installation and Contractor overhead and profit.

Page 66: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012100 Page 3

UCA Mashburn Hall Reroofing and ALLOWANCES Deck Replacement SMA #1505H

2. Coordinate quantity allowance adjustment with corresponding unit-price requirements in Section 012200 "Unit Prices."

B. Allowance No. 2: Lump Sum Allowance. Include the sum of $7,000.00 to remove and replace rusted through metal deck in the northwest roof area with same profile and gauge as existing. 1. This allowance includes material cost demolition, receiving, handling, and installation and

Contractor overhead and profit.

C. Allowance No. 3: Lump Sum Allowance. Include the sum of $3,000.00 to remove surface rust from existing metal deck in the northwest roof area and paint with rust inhibitive paint. 1. This allowance includes material cost, receiving, handling and installation and Contractor

overhead and profit.

D. Allowance No. 4: Lump Sum Allowance. Include the sum of $2,500.00 for drain inserts for damaged drains. 1. This allowance includes material cost, receiving, handling and installation and Contractor

overhead and profit.

E. Allowance No. 5: Lump Sum Allowance. Include the sum of $7,000.00 to remove and replace deteriorated existing pressure treated wood with new pressure treated wood in sizes to match existing in areas not scheduled for removal. 1. This allowance includes material cost, receiving, handling and installation and Contractor

overhead and profit.

F. Allowance No. 6: Lump Sum Allowance. Include the sum of $2,000 for cleaning of new TPO roof membrane. 1. This allowance includes material cost, receiving, handling and installation and Contractor

overhead and profit.

END OF SECTION 012100

Page 67: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012200 Page 1

UCA Mashburn Hall Reroofing and UNIT PRICES Deck Replacement SMA #1505H

SECTION 012200 - UNIT PRICES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for unit prices.

B. Related Requirements:

1. Section 012100 "Allowances" for procedures for using unit prices to adjust quantity allowances.

1.2 DEFINITIONS

A. Unit price is an amount incorporated into the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.

1.3 PROCEDURES

A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.

B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.

C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.

D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.

Page 68: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012200 Page 2

UCA Mashburn Hall Reroofing and UNIT PRICES Deck Replacement SMA #1505H

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 SCHEDULE OF UNIT PRICES

A. Unit Price No. 1 – Removal and Replacement of Wet Lightweight Concrete Decking:

1. Description: Removal of 2 ½ inch thick wet lightweight concrete roof decking and replacement with 2-1/2 inches of rigid polyisocyanurate roof insulation according to Section 075423 "Thermoplastic Polyolefin (TPO) Roofing.

2. Unit of Measurement: Square foot of lightweight concrete roof decking.

END OF SECTION 012200

Page 69: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

SUBSTITUTION REQUEST

(After the Bidding Phase) Project:

To:

Re:

Substitution Request Number: From: Date: A/E Project Number: Contract For:

Specification Title: Description:

Section: Page: Article/Paragraph: Proposed Substitution: Manufacturer: Address: Phone: Trade Name: Model No.: Installer: Address: Phone: History: New product 2-5 years old 5-10 yrs old More than 10 years old Differences between proposed substitution and specified product:

Point-by-point comparative data attached - REQUIRED BY A/E Reason for not providing specified item: Similar Installation:

Project: Architect:

Address: Owner:

Date Installed: Proposed substitution affects other parts of Work: No Yes; explain Savings to Owner for accepting substitution: ($ ). Proposed substitution changes Contract Time: No Yes [Add] [Deduct] days.

Supporting Data Attached: Drawings Product Data Samples Tests Reports Copyright 1996, Construction Specification Institute, 601 Madison Street, Alexandria, VA 22314-1791

Page of September 1996 CSI Form 13.1A

Page 70: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

SUBSTITUTION REQUEST

(Continued) The Undersigned certifies: Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product. Same warranty will be furnished for proposed substitution as for specified product. Same maintenance service and source of replacement parts, as applicable, is available. Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule. Cost data as stated above is complete. Claims for additional costs related to accepted substitution which may subsequently become

apparent are to be waived. Proposed substitution does not affect dimensions and functional clearances. Payment will be made for changes to building design, including A/E design, detailing, and construction costs caused by the

substitution. Coordination, installation, and changes in the Work as necessary for accepted substitution will be complete in all respects. Submitted by: Signed by: Firm: Address:

Telephone: Attachments: A/E's REVIEW AND ACTION

Substitution approved - Make submittals in accordance with Specification Section 01330. Substitution approved as noted - Make submittals in accordance with Specification Section 01330. Substitution rejected - Use specified materials. Substitution Request received too late - Use specified materials.

Signed by: Date: Additional Comments: Contractor Subcontractor Supplier Manufacturer A/E

Copyright 1996, Construction Specification Institute, 601 Madison Street, Alexandria, VA 22314-1791

Page of September 1996 CSI Form 13.1A

Page 71: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012500 Page 1

UCA Mashburn Hall Reroofing and SUBSTITUTION PROCEDURES Deck Replacement SMA #1505H

SECTION 012500 - SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Section:

1. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

1.2 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1.3 ACTION SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use facsimile of form provided in the Project Manual at the end of this Section.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.

b. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable specification section. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested. f. Certificates and qualification data, where applicable or requested. g. List of similar installations for completed projects with project names and

addresses and names and addresses of architects and owners.

Page 72: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012500 Page 2

UCA Mashburn Hall Reroofing and SUBSTITUTION PROCEDURES Deck Replacement SMA #1505H

h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

i. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

j. Cost information, including a proposal of change, if any, in the Contract Sum. k. Contractor's certification that proposed substitution complies with requirements in

the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

l. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Architect will notify Contractor of acceptance or rejection of proposed substitution within 14 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order or Architect's Supplemental Instructions for minor changes in the Work.

b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.

1.4 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately upon discovery of need for change, but not later than 14 days prior to time required for preparation and review of related submittals.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Requested substitution will not adversely affect Contractor's construction schedule.

Page 73: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012500 Page 3

UCA Mashburn Hall Reroofing and SUBSTITUTION PROCEDURES Deck Replacement SMA #1505H

c. Requested substitution has received necessary approvals of authorities having jurisdiction.

d. Requested substitution is compatible with other portions of the Work. e. Requested substitution has been coordinated with other portions of the Work. f. Requested substitution provides specified warranty. g. If requested substitution involves more than one contractor, requested substitution

has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Architect will consider requests for substitution if received within 60 days after the Notice of Award.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied:

a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.

b. Requested substitution does not require extensive revisions to the Contract Documents.

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

d. Requested substitution will not adversely affect Contractor's construction schedule. e. Requested substitution has received necessary approvals of authorities having

jurisdiction. f. Requested substitution is compatible with other portions of the Work. g. Requested substitution has been coordinated with other portions of the Work. h. Requested substitution provides specified warranty. i. If requested substitution involves more than one contractor, requested substitution

has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

PART 3 - EXECUTION (Not Used)

END OF SECTION 012500

Page 74: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012600 Page 1

UCA Mashburn Hall Reroofing and CONTRACT MODIFICATION PROCEDURES Deck Replacement SMA #1505H

SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section specifies administrative and procedural requirements for handling and processing Contract modifications.

1.2 MINOR CHANGES IN THE WORK

A. Architect will issue supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on "Architect's Supplemental Instructions" document.

1.3 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Proposal Requests issued by Architect are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.

2. Within ten (10) days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

B. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

Page 75: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012600 Page 2

UCA Mashburn Hall Reroofing and CONTRACT MODIFICATION PROCEDURES Deck Replacement SMA #1505H

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

5. Comply with requirements in Division 1 Section "Product Requirements" if the proposed change requires substitution of one product or system for product or system specified.

C. Proposal Request Form: Use AIA Document G709.

1.4 ADMINISTRATIVE CHANGE ORDERS

A. Allowance Adjustment: See Section 012100 "Allowances" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of allowances.

1.5 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G701.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012600

Page 76: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012900 Page 1

UCA Mashburn Hall Reroofing and PAYMENT PROCEDURES Deck Replacement SMA #1505H

SECTION 012900 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.

B. Related Requirements:

1. Section 012100 "Allowances" for procedural requirements governing the handling and processing of allowances.

2. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.

3. Section 013200 "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule.

4. Section 017700 "Closeout Procedures" for requirements for Project closeout procedures associated with final payment application.

1.2 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.

1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including Application for Payment forms with Continuation Sheets.

2. Submit the Schedule of Values to Architect at earliest possible date but no later than seven days before the date scheduled for submittal of initial Applications for Payment.

3. Subschedules: Where the Work is separated into phases requiring separately phased payments, provide subschedules showing values correlated with each phase of payment.

B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the Schedule of Values:

a. Project name and location. b. Name of Architect. c. Architect's project number. d. Contractor's name and address. e. Date of submittal.

2. Arrange the Schedule of Values in tabular form with separate columns to indicate the following for each item listed:

a. Related Specification Section or Division. b. Description of the Work.

Page 77: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012900 Page 2

UCA Mashburn Hall Reroofing and PAYMENT PROCEDURES Deck Replacement SMA #1505H

c. Name of subcontractor. d. Name of manufacturer or fabricator. e. Name of supplier. f. Change Orders (numbers) that affect value. g. Dollar value.

1) Percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.

3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Provide several line items for principal subcontract amounts, where appropriate.

4. Round amounts to nearest whole dollar; total shall equal the Contract Sum. 5. Provide a separate line item in the Schedule of Values for each part of the Work where

Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

6. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

7. Each item in the Schedule of Values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.

8. Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Change Orders result in a change in the Contract Sum.

1.3 APPLICATIONS FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner.

1. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.

B. Payment Application Times: The date for each progress payment is indicated in the General Conditions. The period of construction Work covered by each Application for Payment is the period indicated in the General Conditions.

C. Payment Application Forms: Use AIA Document G702 and AIA Document G703 Continuation Sheets as form for Applications for Payment.

D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.

1. Entries shall match data on the Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions were made.

Page 78: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012900 Page 3

UCA Mashburn Hall Reroofing and PAYMENT PROCEDURES Deck Replacement SMA #1505H

2. Include amounts of Change Orders issued before last day of construction period covered by application.

E. Transmittal: Submit five signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

F. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from every entity who is lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.

1. Submit partial waivers on each item for amount requested, before deduction for retainage, on each item.

2. When an application shows completion of an item, submit final or full waivers. 3. Owner reserves the right to designate which entities involved in the Work must submit

waivers. 4. Waiver Delays: Submit each Application for Payment with Contractor's waiver of

mechanic's lien for construction period covered by the application.

a. Submit final Application for Payment with or preceded by final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.

G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors. 2. Schedule of Values. 3. Contractor's Construction Schedule (preliminary if not final). 4. Submittals Schedule (preliminary if not final). 5. List of Contractor's staff assignments. 6. Copies of building permits. 7. Copies of authorizations and licenses from authorities having jurisdiction for performance

of the Work. 8. Certificates of insurance and insurance policies. 9. Performance and payment bonds. 10. Data needed to acquire Owner's insurance. 11. Substitution Requests.

H. Application for Payment at Substantial Completion: After issuing the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

Page 79: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

012900 Page 4

UCA Mashburn Hall Reroofing and PAYMENT PROCEDURES Deck Replacement SMA #1505H

I. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements. 2. Insurance certificates for products and completed operations where required and proof

that taxes, fees, and similar obligations were paid. 3. Updated final statement, accounting for final changes to the Contract Sum. 4. AIA Document G706-1994, "Contractor's Affidavit of Payment of Debts and Claims." 5. AIA Document G706A-1994, "Contractor's Affidavit of Release of Liens." 6. AIA Document G707-1994, "Consent of Surety to Final Payment." 7. Evidence that claims have been settled. 8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of

date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012900

Page 80: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013100 Page 1

UCA Mashburn Hall Reroofing and PROJECT MANAGEMENT AND COORDINATION Deck Replacement SMA #1505H

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Coordination drawings. 2. Requests for Information (RFIs). 3. Project meetings.

B. Related Requirements:

1. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

1.2 DEFINITIONS

A. RFI: Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.

1.3 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract. 3. Drawing number and detail references, as appropriate, covered by subcontract.

1.4 COORDINATION

A. Coordination: Coordinate construction operations included in various Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.

Page 81: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013100 Page 2

UCA Mashburn Hall Reroofing and PROJECT MANAGEMENT AND COORDINATION Deck Replacement SMA #1505H

3. Make adequate provisions to accommodate items scheduled for later installation.

B. If necessary, prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule. 2. Preparation of the Schedule of Values. 3. Installation and removal of temporary facilities and controls. 4. Delivery and processing of submittals. 5. Progress meetings. 6. Preinstallation conferences. 7. Project closeout activities. 8. Startup and adjustment of systems.

1.5 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, where installation is not completely shown on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid.

2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings.

Page 82: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013100 Page 3

UCA Mashburn Hall Reroofing and PROJECT MANAGEMENT AND COORDINATION Deck Replacement SMA #1505H

3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.

4. Structural Penetrations: Indicate penetrations and openings required for all disciplines. 5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of

embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

6. Review: Architect will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility.

1.6 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Architect will return RFIs submitted to Architect by other entities controlled by Contractor with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name. 2. Project number. 3. Date. 4. Name of Contractor. 5. Name of Architect. 6. RFI number, numbered sequentially. 7. RFI subject. 8. Specification Section number and title and related paragraphs, as appropriate. 9. Drawing number and detail references, as appropriate. 10. Field dimensions and conditions, as appropriate. 11. Contractor's suggested resolution. If Contractor's solution(s) impacts the Contract Time

or the Contract Sum, Contractor shall state impact in the RFI. 12. Contractor's signature. 13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

C. Architect's Action: Architect will review each RFI, determine action required, and respond. Allow seven working days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day.

1. The following RFIs will be returned without action:

a. Requests for approval of submittals. b. Requests for approval of substitutions.

Page 83: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013100 Page 4

UCA Mashburn Hall Reroofing and PROJECT MANAGEMENT AND COORDINATION Deck Replacement SMA #1505H

c. Requests for coordination information already indicated in the Contract Documents.

d. Requests for adjustments in the Contract Time or the Contract Sum. e. Requests for interpretation of Architect's actions on submittals. f. Incomplete RFIs or inaccurately prepared RFIs.

2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt of additional information.

3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect in writing within 10 days of receipt of the RFI response.

D. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log at each Project Meeting. Include the following:

1. Project name. 2. Name and address of Contractor. 3. Name and address of Architect. 4. RFI number including RFIs that were dropped and not submitted. 5. RFI description. 6. Date the RFI was submitted. 7. Date Architect's response was received.

E. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within seven days if Contractor disagrees with response.

1. Identification of related Minor Change in the Work, and Proposal Request, as appropriate.

1.7 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Architect of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees. 3. Minutes: Record significant discussions and agreements achieved. Distribute the

meeting minutes to everyone concerned, including Owner and Architect, within 3 days of the meeting.

B. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to Owner and Architect, but no later than five days after execution of the Agreement. Hold the conference at Project site or another convenient location. Conduct the meeting to review responsibilities and personnel assignments.

Page 84: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013100 Page 5

UCA Mashburn Hall Reroofing and PROJECT MANAGEMENT AND COORDINATION Deck Replacement SMA #1505H

1. Attendees: Authorized representatives of Owner, Architect, and their consultants; Contractor and its superintendent; major subcontractors; manufacturers; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Tentative construction schedule. b. Phasing. c. Critical work sequencing and long-lead items. d. Designation of key personnel and their duties. e. Procedures for processing field decisions and Change Orders. f. Procedures for RFIs. g. Procedures for testing and inspecting. h. Procedures for processing Applications for Payment. i. Distribution of the Contract Documents. j. Submittal procedures. k. Preparation of record documents. l. Use of the premises and existing building. m. Work restrictions. n. Working hours. o. Owner's occupancy requirements. p. Responsibility for temporary facilities and controls. q. Procedures for moisture and mold control. r. Procedures for disruptions and shutdowns. s. Construction waste management and recycling. t. Parking availability. u. Office, work, and storage areas. v. Equipment deliveries and priorities. w. First aid. x. Security. y. Progress cleaning.

3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Architect of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents. b. Options. c. Related RFIs. d. Related Change Orders. e. Purchases. f. Deliveries. g. Submittals.

Page 85: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013100 Page 6

UCA Mashburn Hall Reroofing and PROJECT MANAGEMENT AND COORDINATION Deck Replacement SMA #1505H

h. Review of mockups. i. Possible conflicts. j. Compatibility problems. k. Time schedules. l. Weather limitations. m. Manufacturer's written recommendations. n. Warranty requirements. o. Compatibility of materials. p. Acceptability of substrates. q. Temporary facilities and controls. r. Space and access limitations. s. Regulations of authorities having jurisdiction. t. Testing and inspecting requirements. u. Installation procedures. v. Coordination with other work. w. Required performance results. x. Protection of adjacent work. y. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements. 4. Reporting: Distribute minutes of the meeting to each party present and to other parties

requiring information. 5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Progress Meetings: Conduct progress meetings at intervals agreed upon at the Preconstruction Conference. Coordinate dates of meetings with preparation of payment requests.

1. Attendees: In addition to representatives of Owner and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

1) Interface requirements. 2) Sequence of operations. 3) Status of submittals.

Page 86: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013100 Page 7

UCA Mashburn Hall Reroofing and PROJECT MANAGEMENT AND COORDINATION Deck Replacement SMA #1505H

4) Deliveries. 5) Off-site fabrication. 6) Access. 7) Site utilization. 8) Temporary facilities and controls. 9) Work hours. 10) Hazards and risks. 11) Progress cleaning. 12) Status of correction of deficient items. 13) Field observations. 14) Status of RFIs. 15) Status of proposal requests. 16) Pending changes. 17) Status of Change Orders. 18) Pending claims and disputes. 19) Documentation of information for payment requests.

3. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present. Include a brief summary, in narrative form, of progress since the previous meeting and report.

a. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 013100

Page 87: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013200 Page 1

UCA Mashburn Hall Reroofing and CONSTRUCTION PROGRESS DOCUMENTATION Deck Replacement SMA #1505H

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's Construction Schedule. 2. Submittals Schedule. 3. Field condition reports.

B. See Division 1 Section "Payment Procedures" for submitting the Schedule of Values.

1.2 DEFINITIONS

A. Critical Path: The longest continuous chain of activities through the network schedule that establishes the minimum overall Project duration and contains no float.

B. Float: The measure of leeway in starting and completing an activity.

1. Float time is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.

C. Major Area: A story of construction, a separate building, or a similar significant construction element.

1.3 SUBMITTALS

A. Submittals Schedule: Submit three copies of schedule. Arrange the following information in a tabular format:

1. Scheduled date for first submittal. 2. Specification Section number and title. 3. Submittal category (action or informational). 4. Name of subcontractor. 5. Description of the Work covered. 6. Scheduled date for Architect's final release or approval.

B. Contractor's Construction Schedule: Submit three printed copies of initial schedule, large enough to show entire schedule for entire construction period.

C. CPM Reports: Concurrent with CPM schedule, submit three printed copies of each of the following computer-generated reports. Format for each activity in reports shall contain activity

Page 88: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013200 Page 2

UCA Mashburn Hall Reroofing and CONSTRUCTION PROGRESS DOCUMENTATION Deck Replacement SMA #1505H

number, activity description, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float.

1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of preceding and succeeding activities for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.

3. Total Float Report: List of all activities sorted in ascending order of total float.

D. Field Condition Reports: Submit two copies at time of discovery of differing conditions.

1.4 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.

B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from parties involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

2.1 SUBMITTALS SCHEDULE

A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, ordering, manufacturing, fabrication, and delivery when establishing dates.

1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's Construction Schedule.

2. Submit concurrently with the first complete submittal of Contractor's Construction Schedule.

2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Substantial Completion.

1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

Page 89: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013200 Page 3

UCA Mashburn Hall Reroofing and CONSTRUCTION PROGRESS DOCUMENTATION Deck Replacement SMA #1505H

B. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following:

1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Architect.

2. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

3. Submittal Review Time: Include review and resubmittal times indicated in Division 1 Section "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule.

4. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Architect's administrative procedures necessary for certification of Substantial Completion.

C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.

1. Phasing: Arrange list of activities on schedule by phase. 2. Work Restrictions: Show the effect on the schedule of the following:

a. Coordination with existing construction. b. Limitations of continued occupancies. c. Uninterruptible services. d. Use of premises restrictions.

3. Work Stages: Indicate important stages of construction for each major portion of the Work.

D. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, interim milestones indicated below, Substantial Completion, and Final Completion.

1. Start and end of each phase.

E. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule.

2.3 CONTRACTOR'S CONSTRUCTION SCHEDULE (GANTT CHART)

A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal Gantt-chart-type, Contractor's Construction Schedule within 10 days of date established for the Notice to Proceed. Base schedule on the Preliminary Construction Schedule and whatever updating and feedback was received since the start of Project.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.

Page 90: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013200 Page 4

UCA Mashburn Hall Reroofing and CONSTRUCTION PROGRESS DOCUMENTATION Deck Replacement SMA #1505H

1. For construction activities that require 3 months or longer to complete, indicate an estimated completion percentage in 10 percent increments within time bar.

2.4 REPORTS

A. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare a detailed report. Submit with a request for information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.

PART 3 - EXECUTION

3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.

1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.

2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.

3. As the Work progresses, indicate Actual Completion percentage for each activity.

B. Distribution: Distribute copies of approved schedule to Architect, Owner, and other parties identified by Contractor with a need-to-know schedule responsibility.

1. Post copies in Project meeting rooms and temporary field offices. 2. When revisions are made, distribute updated schedules to the same parties and post in

the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.

END OF SECTION 013200

Page 91: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013300 Page 1

UCA Mashburn Hall Reroofing and SUBMITTAL PROCEDURES Deck Replacement SMA #1505H

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals.

B. Related Requirements:

1. Section 013200 "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule.

2. Section 017823 "Operation and Maintenance Data" for submitting operation and maintenance manuals.

3. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

B. Informational Submittals: Written information that does not require Architect's approval. Submittals may be rejected for not complying with requirements.

1.3 ACTION SUBMITTALS

A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Architect and additional time for handling and reviewing submittals required by those corrections.

1.4 SUBMITTAL ADMINISTRATIVE REQUIREMENTS

A. Architect's Digital Data Files: Electronic copies of digital data files of the Contract Drawings will not be provided by Architect for Contractor's use in preparing submittals.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

Page 92: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013300 Page 2

UCA Mashburn Hall Reroofing and SUBMITTAL PROCEDURES Deck Replacement SMA #1505H

a. Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Architect's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 10 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Architect will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 10 days for review of each resubmittal.

D. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.

2. Name file with submittal number or other unique identifier, including revision identifier.

a. File name shall use project identifier and Specification Section number followed by a decimal point and then a sequential number (e.g., Bldg 7200-061000.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., Bldg 7200-061000.01.A).

3. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by Architect.

4. Transmittal Form for Electronic Submittals: Use electronic form acceptable to Owner, containing the following information:

a. Project name. b. Date. c. Name and address of Architect. d. Name of Construction Manager. e. Name of Contractor. f. Name of firm or entity that prepared submittal. g. Names of subcontractor, manufacturer, and supplier. h. Category and type of submittal. i. Submittal purpose and description. j. Specification Section number and title. k. Specification paragraph number or drawing designation and generic name for each

of multiple items. l. Drawing number and detail references, as appropriate. m. Location(s) where product is to be installed, as appropriate. n. Related physical samples submitted directly. o. Indication of full or partial submittal. p. Transmittal number, numbered consecutively. q. Submittal and transmittal distribution record. r. Other necessary identification.

Page 93: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013300 Page 3

UCA Mashburn Hall Reroofing and SUBMITTAL PROCEDURES Deck Replacement SMA #1505H

s. Remarks.

5. Metadata: Include the following information as keywords in the electronic submittal file metadata:

a. Project name. b. Number and title of appropriate Specification Section. c. Manufacturer name. d. Product name.

E. Options: Identify options requiring selection by Architect.

F. Deviations: Identify deviations from the Contract Documents on submittals.

G. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal. 2. Note date and content of revision in label or title block and clearly indicate extent of

revision. 3. Resubmit submittals until they are marked with approval notation from Architect's action

stamp.

H. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

I. Use for Construction: Provide complete paper copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Architect's action stamp.

PART 2 - PRODUCTS

2.1 SUBMITTAL PROCEDURES

A. General Submittal Procedure Requirements:

1. Submit electronic submittals via email as PDF electronic files.

a. Architect will return annotated file. Annotate and retain one copy of file as an electronic Project record document file.

2. Certificates and Certifications Submittals: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

a. Provide a digital signature with digital certificate on electronically-submitted certificates and certifications where indicated.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

Page 94: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013300 Page 4

UCA Mashburn Hall Reroofing and SUBMITTAL PROCEDURES Deck Replacement SMA #1505H

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable. 3. Include the following information, as applicable:

a. Manufacturer's catalog cuts. b. Manufacturer's product specifications. c. Standard color charts. d. Statement of compliance with specified referenced standards. e. Testing by recognized testing agency. f. Application of testing agency labels and seals. g. Notation of coordination requirements. h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams showing factory-installed wiring. b. Printed performance curves. c. Operational range diagrams. d. Clearances required to other construction, if not indicated on accompanying Shop

Drawings.

5. Submit Product Data before or concurrent with Samples. 6. Submit Product Data in the following format:

a. PDF electronic file.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products. b. Schedules. c. Compliance with specified standards. d. Notation of coordination requirements. e. Notation of dimensions established by field measurement. f. Relationship and attachment to adjoining construction clearly indicated. g. Seal and signature of professional engineer if specified.

2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring. 3. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop

Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 42 inches. 4. Submit Shop Drawings in the following format:

a. PDF electronic file.

D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

Page 95: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013300 Page 5

UCA Mashburn Hall Reroofing and SUBMITTAL PROCEDURES Deck Replacement SMA #1505H

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Attach label on unexposed side of Samples that includes the following:

a. Generic description of Sample. b. Product name and name of manufacturer. c. Sample source. d. Number and title of applicable Specification Section.

3. For projects where electronic submittals are required, provide corresponding electronic submittal of Sample transmittal, digital image file illustrating Sample characteristics, and identification information for record.

4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use.

b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.

5. Samples for Initial Selection: Submit manufacturer's color charts (not digital) consisting of units or sections of units showing the full range of colors, textures, and patterns available.

a. Number of Samples: Submit two full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Architect will return one submittal with options selected.

6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

a. Number of Samples: Submit two sets of Samples. Architect will retain one Sample sets; remainder will be returned.

1) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations.

E. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

1. Submit product schedule in the following format:

Page 96: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013300 Page 6

UCA Mashburn Hall Reroofing and SUBMITTAL PROCEDURES Deck Replacement SMA #1505H

a. PDF electronic file.

F. Coordination Drawings Submittals: Comply with requirements specified in Section 013100 "Project Management and Coordination."

G. Contractor's Construction Schedule: Comply with requirements specified in Section 013200 "Construction Progress Documentation."

H. Application for Payment and Schedule of Values: Comply with requirements specified in Section 012900 "Payment Procedures.

I. Test and Inspection Reports and Schedule of Tests and Inspections Submittals: Comply with requirements specified in Section 014000 "Quality Requirements."

J. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified in Section 017700 "Closeout Procedures."

K. Maintenance Data: Comply with requirements specified in Section 017823 "Operation and Maintenance Data."

L. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified.

M. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.

N. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

O. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.

P. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

Q. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

R. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

S. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

Page 97: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013300 Page 7

UCA Mashburn Hall Reroofing and SUBMITTAL PROCEDURES Deck Replacement SMA #1505H

T. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.

U. Schedule of Tests and Inspections: Comply with requirements specified in Section 014000 "Quality Requirements."

V. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

W. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

X. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

Y. Design Data: Prepare and submit written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.

2.2 DELEGATED-DESIGN SERVICES

A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Architect.

B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally signed PDF electronic file of certificate, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.

1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.

PART 3 - EXECUTION

Page 98: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

013300 Page 8

UCA Mashburn Hall Reroofing and SUBMITTAL PROCEDURES Deck Replacement SMA #1505H

3.1 CONTRACTOR'S REVIEW

A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Architect.

B. Project Closeout and Maintenance Material Submittals: See requirements in Section 017700 "Closeout Procedures."

C. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

3.2 ARCHITECT'S ACTION

A. General: Architect will not review submittals that do not bear Contractor's approval stamp and will return them without action.

B. Action Submittals: Architect will review each submittal, make marks to indicate corrections or modifications required, and return it. Architect will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows:

1. Approved 2. Approved as Noted 3. Revise and Resubmit 4. Not Approved

C. Informational Submittals: Architect will review each submittal and will not return it, or will reject and return it if it does not comply with requirements. Architect will forward each submittal to appropriate party.

D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

E. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

END OF SECTION 013300

Page 99: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

014000 Page 1

UCA Mashburn Hall Reroofing and QUALITY REQUIREMENTS Deck Replacement SMA #1505H

SECTION 014000 - QUALITY REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for quality assurance and quality control.

B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.

1. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -control procedures that facilitate compliance with the Contract Document requirements.

2. Requirements for Contractor to provide quality-assurance and -control services required by Architect, Owner, or authorities having jurisdiction are not limited by provisions of this Section.

C. Related Sections:

1. Divisions 2 through 33 Sections for specific test and inspection requirements.

1.2 DEFINITIONS

A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Services do not include contract enforcement activities performed by Architect.

C. Mockups: Full size physical assemblies that are constructed on-site. Mockups are constructed to verify selections made under sample submittals; to demonstrate aesthetic effects and, where indicated, qualities of materials and execution; to review coordination, testing, or operation; to show interface between dissimilar materials; and to demonstrate compliance with specified installation tolerances. Mockups are not Samples. Unless otherwise indicated, approved mockups establish the standard by which the Work will be judged.

D. Preconstruction Testing: Tests and inspections performed specifically for the Project before products and materials are incorporated into the Work to verify performance or compliance with specified criteria.

Page 100: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

014000 Page 2

UCA Mashburn Hall Reroofing and QUALITY REQUIREMENTS Deck Replacement SMA #1505H

E. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with specified requirements.

F. Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.

G. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.

H. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.

I. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

1. Use of trade-specific terminology in referring to a trade or entity does not require that certain construction activities be performed by accredited or unionized individuals, or that requirements specified apply exclusively to specific trade or trades.

J. Experienced: When used with an entity or individual, "experienced" means having successfully completed previous projects similar in nature, size, and extent to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

1.3 CONFLICTING REQUIREMENTS

A. Referenced Standards: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer conflicting requirements that are different, but apparently equal, to Architect for a decision before proceeding.

B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding.

1.4 INFORMATIONAL SUBMITTALS

A. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

Page 101: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

014000 Page 3

UCA Mashburn Hall Reroofing and QUALITY REQUIREMENTS Deck Replacement SMA #1505H

1.5 REPORTS AND DOCUMENTS

A. Test and Inspection Reports: Prepare and submit certified written reports specified in other Sections. Include the following:

1. Date of issue. 2. Project title and number. 3. Name, address, and telephone number of testing agency. 4. Dates and locations of samples and tests or inspections. 5. Names of individuals making tests and inspections. 6. Description of the Work and test and inspection method. 7. Identification of product and Specification Section. 8. Complete test or inspection data. 9. Test and inspection results and an interpretation of test results. 10. Record of temperature and weather conditions at time of sample taking and testing and

inspecting. 11. Comments or professional opinion on whether tested or inspected Work complies with

the Contract Document requirements. 12. Name and signature of laboratory inspector. 13. Recommendations on retesting and reinspecting.

B. Manufacturer's Field Reports: Prepare written information documenting tests and inspections specified in other Sections. Include the following:

1. Name, address, and telephone number of representative making report. 2. Statement on condition of substrates and their acceptability for installation of product. 3. Summary of installation procedures being followed, whether they comply with

requirements and, if not, what corrective action was taken. 4. Results of operational and other tests and a statement of whether observed performance

complies with requirements. 5. Other required items indicated in individual Specification Sections.

C. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

1.6 QUALITY ASSURANCE

A. General: Qualifications paragraphs in this article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.

B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

Page 102: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

014000 Page 4

UCA Mashburn Hall Reroofing and QUALITY REQUIREMENTS Deck Replacement SMA #1505H

D. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.

E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar to those indicated for this Project in material, design, and extent.

F. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 329; and with additional qualifications specified in individual Sections; and where required by authorities having jurisdiction, that is acceptable to authorities.

1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7. 2. NVLAP: A testing agency accredited according to NIST's National Voluntary Laboratory

Accreditation Program.

G. Manufacturer's Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

H. Mockups: Before installing portions of the Work requiring mockups, build mockups for each form of construction and finish required to comply with the following requirements, using materials indicated for the completed Work:

1. Build mockups in location and of size indicated or, if not indicated, as directed by Architect.

2. Notify Architect seven days in advance of dates and times when mockups will be constructed.

3. Demonstrate the proposed range of aesthetic effects and workmanship. 4. Obtain Architect's and Construction Manager's approval of mockups before starting work,

fabrication, or construction.

a. Allow five days for initial review and each re-review of each mockup.

5. Maintain mockups during construction in an undisturbed condition as a standard for judging the completed Work.

6. Demolish and remove mockups when directed, unless otherwise indicated.

1.7 QUALITY CONTROL

A. Owner Responsibilities: Where quality-control services are indicated as Owner's responsibility, Owner will engage a qualified testing agency to perform these services.

1. Owner will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged and a description of types of testing and inspecting they are engaged to perform.

Page 103: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

014000 Page 5

UCA Mashburn Hall Reroofing and QUALITY REQUIREMENTS Deck Replacement SMA #1505H

2. Costs for retesting and reinspecting construction that replaces or is necessitated by work that failed to comply with the Contract Documents will be charged to Contractor, and the Contract Sum will be adjusted by Change Order.

B. Contractor Responsibilities: Tests and inspections not explicitly assigned to Owner are Contractor's responsibility. Perform additional quality-control activities required to verify that the Work complies with requirements, whether specified or not.

1. Where services are indicated as Contractor's responsibility, engage a qualified testing agency to perform these quality-control services.

a. Contractor shall not employ same entity engaged by Owner, unless agreed to in writing by Owner.

2. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed.

3. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service.

4. Testing and inspecting requested by Contractor and not required by the Contract Documents are Contractor's responsibility.

5. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.

C. Manufacturer's Field Services: Where indicated, engage a manufacturer's representative to observe and inspect the Work. Manufacturer's representative's services include examination of substrates and conditions, verification of materials, inspection of completed portions of the Work, and submittal of written reports.

D. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents.

E. Testing Agency Responsibilities: Cooperate with Architect and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.

1. Notify Architect and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.

2. Determine the location from which test samples will be taken and in which in-situ tests are conducted.

3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.

4. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor.

5. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the Work.

6. Do not perform any duties of Contractor.

F. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:

Page 104: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

014000 Page 6

UCA Mashburn Hall Reroofing and QUALITY REQUIREMENTS Deck Replacement SMA #1505H

1. Access to the Work. 2. Incidental labor and facilities necessary to facilitate tests and inspections. 3. Adequate quantities of representative samples of materials that require testing and

inspecting. Assist agency in obtaining samples. 4. Facilities for storage and field curing of test samples. 5. Delivery of samples to testing agencies. 6. Preliminary design mix proposed for use for material mixes that require control by testing

agency. 7. Security and protection for samples and for testing and inspecting equipment at Project

site.

G. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and -control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.

1. Schedule times for tests, inspections, obtaining samples, and similar activities.

1.8 SPECIAL TESTS AND INSPECTIONS

A. Special Tests and Inspections: Engage a qualified testing agency to conduct special tests and inspections required by authorities having jurisdiction as the responsibility of Owner, and as follows:

1. Verifying that manufacturer maintains detailed fabrication and quality-control procedures and reviewing the completeness and adequacy of those procedures to perform the Work.

2. Notifying Architect and Contractor promptly of irregularities and deficiencies observed in the Work during performance of its services.

3. Submitting a certified written report of each test, inspection, and similar quality-control service to Architect with copy to Contractor and to authorities having jurisdiction.

4. Submitting a final report of special tests and inspections at Substantial Completion, which includes a list of unresolved deficiencies.

5. Interpreting tests and inspections and stating in each report whether tested and inspected work complies with or deviates from the Contract Documents.

6. Retesting and reinspecting corrected work. 7. .

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 REPAIR AND PROTECTION

A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.

1. Provide materials and comply with installation requirements specified in other Specification Sections or matching existing substrates and finishes. Restore patched

Page 105: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

014000 Page 7

UCA Mashburn Hall Reroofing and QUALITY REQUIREMENTS Deck Replacement SMA #1505H

areas and extend restoration into adjoining areas with durable seams that are as invisible as possible. Comply with the Contract Document requirements for cutting and patching in Division 1 Section "Execution Requirements."

B. Protect construction exposed by or for quality-control service activities.

C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.

END OF SECTION 014000

Page 106: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

014200 Page 1

UCA Mashburn Hall Reroofing and REFERENCES Deck Replacement SMA #1505H

SECTION 014200 - REFERENCES

PART 1 - GENERAL

1.1 DEFINITIONS

A. General: Basic Contract definitions are included in the Conditions of the Contract.

B. "Approved": When used to convey Architect's action on Contractor's submittals, applications, and requests, "approved" is limited to Architect's duties and responsibilities as stated in the Conditions of the Contract.

C. "Directed": A command or instruction by Architect. Other terms including "requested," "authorized," "selected," "required," and "permitted" have the same meaning as "directed."

D. "Indicated": Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms including "shown," "noted," "scheduled," and "specified" have the same meaning as "indicated."

E. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work.

F. "Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations.

G. "Install": Operations at Project site including unloading, temporarily storing, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.

H. "Provide": Furnish and install, complete and ready for the intended use.

I. "Project Site": Space available for performing construction activities. The extent of Project site is shown on Drawings and may or may not be identical with the description of the land on which Project is to be built.

1.2 INDUSTRY STANDARDS

A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.

B. Publication Dates: Comply with standards in effect as of date of the Contract Documents unless otherwise indicated.

Page 107: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

014200 Page 2

UCA Mashburn Hall Reroofing and REFERENCES Deck Replacement SMA #1505H

C. Copies of Standards: Each entity engaged in construction on Project should be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents.

1. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source.

D. Abbreviations and Acronyms for Standards and Regulations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the organizations responsible for the standards and regulations in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

ADAAG Americans with Disabilities Act (ADA) Architectural Barriers Act (ABA) CFR Code of Federal Regulations

1.3 ABBREVIATIONS AND ACRONYMS

A. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities indicated in Thomson Gale's "Encyclopedia of Associations" or in Columbia Books' "National Trade & Professional Associations of the U.S."

B. Code Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

BOCA BOCA International, Inc. (See ICC) IAPMO International Association of Plumbing and Mechanical Officials ICBO International Conference of Building Officials (See ICC) ICBO ES ICBO Evaluation Service, Inc. (See ICC-ES) ICC International Code Council ICC-ES ICC Evaluation Service, Inc. SBCCI Southern Building Code Congress International, Inc. (See ICC)

C. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

CE Army Corps of Engineers

Page 108: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

014200 Page 3

UCA Mashburn Hall Reroofing and REFERENCES Deck Replacement SMA #1505H

CPSC Consumer Product Safety Commission DOC Department of Commerce DOD Department of Defense DOE Department of Energy EPA Environmental Protection Agency FAA Federal Aviation Administration FCC Federal Communications Commission FDA Food and Drug Administration GSA General Services Administration HUD Department of Housing and Urban Development LBL Lawrence Berkeley National Laboratory NCHRP National Cooperative Highway Research Program (See TRB) NIST National Institute of Standards and Technology OSHA Occupational Safety & Health Administration PBS Public Building Service (See GSA) PHS Office of Public Health and Science RUS Rural Utilities Service (See USDA) SD State Department TRB Transportation Research Board USDA Department of Agriculture USPS Postal Service

D. State Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

AHTD Arkansas State Highway and Transportation Department

Page 109: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

014200 Page 4

UCA Mashburn Hall Reroofing and REFERENCES Deck Replacement SMA #1505H

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 014200

Page 110: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

015000 Page 1

UCA Mashburn Hall Reroofing and TEMPORARY FACILITIES AND CONTROLS Deck Replacement SMA #1505H

SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes requirements for temporary facilities and controls, including temporary utilities, support facilities, and security and protection facilities.

B. Related Requirements:

1. Section 011000 "Summary" for work restrictions and limitations on utility interruptions. 2. Section 017300 Section "Execution" for progress cleaning requirements.

1.2 DEFINITIONS

A. Permanent Enclosure: As determined by Architect, permanent or temporary roofing is complete, insulated, and weathertight; exterior walls are insulated and weathertight; and all openings are closed with permanent construction or substantial temporary closures.

1.3 USE CHARGES

A. General: Installation and removal of and use charges for temporary facilities shall be included in the Contract Sum unless otherwise indicated. Allow other entities to use temporary services and facilities without cost, including, but not limited to, Owner's construction forces, Architect, testing agencies, and authorities having jurisdiction.

B. Water and Sewer Service from Existing System: Water from Owner's existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.

C. Electric Power Service from Existing System: Electric power from Owner's existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.

1.4 SUBMITTALS

A. Site Plan: Show temporary facilities, utility hookups, staging areas, and parking areas for construction personnel.

B. Fire-Safety Program: Show compliance with requirements of NFPA 241 and authorities having jurisdiction. Indicate Contractor personnel responsible for management of fire prevention program.

1.5 QUALITY ASSURANCE

Page 111: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

015000 Page 2

UCA Mashburn Hall Reroofing and TEMPORARY FACILITIES AND CONTROLS Deck Replacement SMA #1505H

A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.

1.6 PROJECT CONDITIONS

A. Temporary Use of Permanent Facilities: Installer of each permanent service shall assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities.

B. Conditions of Use: The following conditions apply to use of temporary services and facilities by all parties engaged in the Work:

1. Keep temporary services and facilities clean and neat. 2. Relocate temporary services and facilities as required by progress of the Work.

PART 2 - PRODUCTS

2.1 MATERIALS

A. General: Provide new materials. Undamaged, previously used materials in serviceable condition may be used if approved by Architect. Provide materials suitable for use intended.

B. Lumber and Plywood: Comply with requirements in Division 6 Section "Rough Carpentry."

C. Gypsum Board: ASTM C 36, minimum 1/2 inch thick by 48 inches wide by maximum available lengths; regular-type panels with tapered edges.

D. Insulation: Unfaced mineral-fiber blanket, manufactured from glass, slag wool, or rock wool; with maximum flame-spread and smoke-developed indices of 25 and 50, respectively.

E. Tarpaulins: Fire-resistive labeled with flame-spread rating of 15 or less.

F. Water: Potable.

2.2 TEMPORARY FACILITIES

A. Field Offices, General: Prefabricated or mobile units with serviceable finishes, temperature controls, and foundations adequate for normal loading.

B. Common-Use Field Office: Of sufficient size to accommodate needs of Owner, Architect, and construction personnel office activities and to accommodate Project meetings specified in other Division 01 Sections. Keep office clean and orderly.

Page 112: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

015000 Page 3

UCA Mashburn Hall Reroofing and TEMPORARY FACILITIES AND CONTROLS Deck Replacement SMA #1505H

C. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment for construction operations.

2.3 EQUIPMENT

A. Fire Extinguishers: Hand carried, portable, UL rated. Provide class and extinguishing agent as indicated or a combination of extinguishers of NFPA-recommended classes for exposures.

1. Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and size required by location and class of fire exposure.

B. Drinking-Water Fixtures: Containerized, tap-dispenser, bottled-water, drinking-water units, including paper cup supply.

C. HVAC Equipment: Unless Owner authorizes use of permanent HVAC system, provide vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space thermostatic control.

1. Use of gasoline-burning space heaters, open-flame heaters, or salamander-type heating units is prohibited.

2. Heating Units: Listed and labeled, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use for type of fuel being consumed.

3. Permanent HVAC System: If Owner authorizes use of permanent HVAC system for temporary use during construction, provide filter with MERV of 8 at each return air grille in system and remove at end of construction.

D. Electrical Outlets: Properly configured, NEMA-polarized outlets to prevent insertion of 110- to 120-V plugs into higher-voltage outlets; equipped with ground-fault circuit interrupters, reset button, and pilot light.

E. Power Distribution System Circuits: Where permitted and overhead and exposed for surveillance, wiring circuits, not exceeding 125-V ac, 20-A rating, and lighting circuits may be nonmetallic sheathed cable.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required.

B. Provide each facility ready for use when needed to avoid delay. Maintain and modify as required. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

3.2 TEMPORARY UTILITY INSTALLATION

A. General: Install temporary service or connect to existing service.

Page 113: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

015000 Page 4

UCA Mashburn Hall Reroofing and TEMPORARY FACILITIES AND CONTROLS Deck Replacement SMA #1505H

1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

B. Sewers and Drainage: Provide temporary utilities to remove effluent lawfully.

1. Connect temporary sewers to private system as directed by Owner.

C. Water Service: Connect to Owner's existing water service facilities. Clean and maintain water service facilities in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use.

D. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.

1. Disposable Supplies: Provide, paper towels, paper cups, and similar disposable materials for each facility. Maintain adequate supply. Provide covered waste containers for disposal of used material.

2. Drinking-Water Facilities: Provide bottled-water, drinking-water units.

E. Heating and Cooling: Provide temporary heating and cooling required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of low temperatures or high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed.

F. Ventilation and Humidity Control: Provide temporary ventilation required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of high humidity. Select equipment from that specified that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce ambient condition required and minimize energy consumption.

G. Electric Power Service: Provide electric power service and distribution system of sufficient size, capacity, and power characteristics required for construction operations.

1. Install electric power service overhead, unless otherwise indicated. 2. Connect temporary service to Owner's existing power source, as directed by Owner.

H. Electric Distribution: Provide receptacle outlets adequate for connection of power tools and equipment.

1. Provide waterproof connectors to connect separate lengths of electrical power cords if single lengths will not reach areas where construction activities are in progress. Do not exceed safe length-voltage ratio.

I. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations and traffic conditions.

1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.

Page 114: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

015000 Page 5

UCA Mashburn Hall Reroofing and TEMPORARY FACILITIES AND CONTROLS Deck Replacement SMA #1505H

J. Telephone Service: Provide temporary telephone service in common-use facilities for use by all construction personnel. Install one telephone line for each field office.

1. Provide additional telephone lines for the following:

a. Provide a dedicated telephone line for each facsimile machine and computer in each field office.

2. At each telephone, post a list of important telephone numbers including police and fire departments, Contractor's home office, Architect's office, Owner's office, and Principal subcontractors' field and home offices.

3. Provide superintendent with cellular telephone or portable two-way radio for use when away from field office.

3.3 SUPPORT FACILITIES INSTALLATION

A. General: Comply with the following:

1. Provide incombustible construction for sheds located within construction area or within 30 feetf building lines. Comply with NFPA 241.

2. Maintain support facilities until near Substantial Completion. Remove before Substantial Completion. Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to Owner.

B. Traffic Controls: Comply with requirements of authorities having jurisdiction.

1. Protect existing site improvements to remain including curbs, pavement, and utilities. 2. Maintain access for fire-fighting equipment and access to fire hydrants.

C. Parking: Use designated areas of Owner's existing parking areas for construction personnel.

D. Dewatering Facilities and Drains: Comply with requirements of authorities having jurisdiction. Maintain Project site, excavations, and construction free of water.

1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining properties or endanger permanent Work or temporary facilities.

2. Remove snow and ice as required to minimize accumulations.

A. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction. Comply with progress cleaning requirements in Section 017300 "Execution."

B. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment involved, including temporary utility services. Sheds may be open shelters or fully enclosed spaces within building or elsewhere on-site.

1. Construct framing, sheathing, and siding using fire-retardant-treated lumber and plywood.

3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION

Page 115: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

015000 Page 6

UCA Mashburn Hall Reroofing and TEMPORARY FACILITIES AND CONTROLS Deck Replacement SMA #1505H

A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities.

B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

C. Temporary Erosion and Sedimentation Control: Provide measures to prevent soil erosion and discharge of soil-bearing water runoff and airborne dust to adjacent properties and walkways, according to requirements of authorities having jurisdiction.

D. Tree and Plant Protection: Install temporary fencing located as indicated or outside the drip line of trees to protect vegetation from damage from construction operations. Protect tree root systems from damage, flooding, and erosion.

E. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.

F. Temporary Egress: Maintain temporary egress from existing occupied facilities as indicated and as required by authorities having jurisdiction.

G. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.

1. Where heating or cooling is needed and permanent enclosure is not complete, provide insulated temporary enclosures. Coordinate enclosure with ventilating and material drying or curing requirements to avoid dangerous conditions and effects.

H. Temporary Partitions: Provide floor-to-ceiling dustproof partitions to limit dust and dirt migration and to separate areas occupied by Owner and tenants from fumes and noise.

1. Construct dustproof partitions with two layers of 6-mil polyethylene sheet on each side. Cover floor with two layers of 6-mil polyethylene sheet, extending sheets 18 inches up the sidewalls. Overlap and tape full length of joints. Cover floor with fire-retardant-treated plywood.

a. Provide swinging temporary door at each entrance through temporary partition.

2. Where fire-resistance-rated temporary partitions are indicated or are required by authorities having jurisdiction, construct partitions according to the rated assemblies.

3. Insulate partitions to control noise transmission to occupied areas. 4. Seal joints and perimeter. Equip partitions with gasketed dustproof doors and security

locks where openings are required. 5. Protect air-handling equipment. 6. Provide walk-off mats at each entrance through temporary partition.

3.5 OPERATION, TERMINATION, AND REMOVAL

Page 116: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

015000 Page 7

UCA Mashburn Hall Reroofing and TEMPORARY FACILITIES AND CONTROLS Deck Replacement SMA #1505H

A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.

B. Maintenance: Maintain facilities in good operating condition until removal. Protect from damage caused by freezing temperatures and similar elements.

1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.

2. Prevent water-filled piping from freezing. Maintain markers for underground lines. Protect from damage during excavation operations.

C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.

D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

1. Materials and facilities that constitute temporary facilities are the property of Contractor. 2. At Substantial Completion, repair, renovate, and clean permanent facilities used during

construction period. Comply with final cleaning requirements specified in Section 017700 "Closeout Procedures."

END OF SECTION 015000

Page 117: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

016000 Page 1

UCA Mashburn Hall Reroofing and PRODUCT REQUIREMENTS Deck Replacement SMA #1505H

SECTION 016000 - PRODUCT REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for selecting products for use in Project; product delivery, storage, and handling; manufacturers' standard warranties on products; special warranties; product substitutions; and comparable products.

B. Related Requirements:

1. Section 012500 "Substitution Procedures" for requests for substitutions.

1.2 DEFINITIONS

A. Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.

1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation, shown or listed in manufacturer's published product literature, that is current as of date of the Contract Documents.

2. New Products: Items that have not previously been incorporated into another project or facility. Products salvaged or recycled from other projects are not considered new products.

3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

A. Basis-of-Design Product Specification: A specification in which a specific manufacturer's product is named and accompanied by the words "basis-of-design product," including make or model number or other designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of additional manufacturers named in the specification.

1.3 ACTION SUBMITTALS

A. Comparable Product Requests: Submit request for consideration of each comparable product. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within one week of receipt of a comparable product request. Architect will notify Contractor of approval or rejection of proposed comparable product

Page 118: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

016000 Page 2

UCA Mashburn Hall Reroofing and PRODUCT REQUIREMENTS Deck Replacement SMA #1505H

request within 14 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Form of Approval: As specified in Section 013300 "Submittal Procedures." b. Use product specified if Architect does not issue a decision on use of a

comparable product request within time allocated.

B. Basis-of-Design Product Specification Submittal: Comply with requirements in Section 013300 "Submittal Procedures." Show compliance with requirements.

1.4 QUALITY ASSURANCE

A. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, product selected shall be compatible with products previously selected, even if previously selected products were also options.

1.5 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft. Comply with manufacturer's written instructions.

1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.

2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

3. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.

4. Inspect products on delivery to ensure compliance with the Contract Documents and to ensure that products are undamaged and properly protected.

5. Store products to allow for inspection and measurement of quantity or counting of units. 6. Store materials in a manner that will not endanger Project structure. 7. Store products that are subject to damage by the elements, under cover in a weathertight

enclosure above ground, with ventilation adequate to prevent condensation. 8. Comply with product manufacturer's written instructions for temperature, humidity,

ventilation, and weather-protection requirements for storage. 9. Protect stored products from damage.

1.6 PRODUCT WARRANTIES

A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents.

1. Manufacturer's Warranty: Written warranty furnished by individual manufacturer for a particular product and specifically endorsed by manufacturer to Owner.

Page 119: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

016000 Page 3

UCA Mashburn Hall Reroofing and PRODUCT REQUIREMENTS Deck Replacement SMA #1505H

2. Special Warranty: Written warranty required by the Contract Documents to provide specific rights for Owner.

B. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution. Submit a draft for approval before final execution.

1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed.

1. Refer to other Sections for specific content requirements and particular requirements for submitting special warranties.

C. Submittal Time: Comply with requirements in Section 017700 "Closeout Procedures."

PART 2 - PRODUCTS

2.1 PRODUCT OPTIONS

A. General Product Requirements: Provide products that comply with the Contract Documents, that are undamaged and, unless otherwise indicated, that are new at time of installation.

1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect.

2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.

3. Owner reserves the right to limit selection to products with warranties not in conflict with requirements of the Contract Documents.

4. Where products are accompanied by the term "as selected," Architect will make selection.

5. Where products are accompanied by the term "match sample," sample to be matched is Architect's.

6. Descriptive, performance, and reference standard requirements in the Specifications establish "salient characteristics" of products.

B. Product Selection Procedures: Procedures for product selection include the following:

1. Products: Where Specification paragraphs or subparagraphs titled "Products" introduce a list of names of both products and manufacturers, provide one of the products listed that complies with requirements.

a. Substitutions may be considered, unless otherwise indicated.

2. Manufacturers: Where Specification paragraphs or subparagraphs titled "Manufacturers" introduce a list of manufacturers' names, provide a product by one of the manufacturers listed that complies with requirements.

a. Substitutions may be considered, unless otherwise indicated.

Page 120: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

016000 Page 4

UCA Mashburn Hall Reroofing and PRODUCT REQUIREMENTS Deck Replacement SMA #1505H

3. Available Products: Where Specification paragraphs or subparagraphs titled "Available Products" introduce a list of names of both products and manufacturers, provide one of the products listed or another product that complies with requirements. Comply with provisions in "Comparable Products" Article to obtain approval for use of an unnamed product.

4. Available Manufacturers: Where Specification paragraphs or subparagraphs titled "Available Manufacturers" introduce a list of manufacturers' names, provide a product by one of the manufacturers listed or another manufacturer that complies with requirements. Comply with provisions in "Comparable Products" Article to obtain approval for use of an unnamed product.

5. Basis-of-Design Products: Where Specification paragraphs or subparagraphs titled "Basis-of-Design Product" are included and also introduce or refer to a list of manufacturers' names, provide either the specified product or a comparable product by one of the other named manufacturers. Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on the product named. Comply with provisions in "Comparable Products" Article to obtain approval for use of an unnamed product.

a. Substitutions may be considered, unless otherwise indicated.

6. Visual Matching Specification: Where Specifications require matching an established Sample, select a product (and manufacturer) that complies with requirements and matches Architect's sample. Architect's decision will be final on whether a proposed product matches satisfactorily.

a. If no product available within specified category matches satisfactorily and complies with other specified requirements, comply with provisions of the Contract Documents on "substitutions" for selection of a matching product.

7. Visual Selection Specification: Where Specifications include the phrase "as selected from manufacturer's colors, patterns, textures" or a similar phrase, select a product (and manufacturer) that complies with other specified requirements.

a. Standard Range: Where Specifications include the phrase "standard range of colors, patterns, textures" or similar phrase, Architect will select color, pattern, or texture from manufacturer's product line that does not include premium items.

b. Full Range: Where Specifications include the phrase "full range of colors, patterns, textures" or similar phrase, Architect will select color, pattern, or texture from manufacturer's product line that includes both standard and premium items.

2.2 COMPARABLE PRODUCTS

A. Where products or manufacturers are specified by name, submit the following, in addition to other required submittals, to obtain approval of an unnamed product:

1. Evidence that the proposed product does not require extensive revisions to the Contract Documents, that it is consistent with the Contract Documents and will produce the indicated results, and that it is compatible with other portions of the Work.

2. Detailed comparison of significant qualities of proposed product with those named in the Specifications. Significant qualities include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated.

Page 121: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

016000 Page 5

UCA Mashburn Hall Reroofing and PRODUCT REQUIREMENTS Deck Replacement SMA #1505H

3. Evidence that proposed product provides specified warranty. 4. List of similar installations for completed projects with project names and addresses and

names and addresses of architects and owners, if requested. 5. Samples, if requested.

PART 3 - EXECUTION (Not Used)

END OF SECTION 016000

Page 122: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017300 Page 1

UCA Mashburn Hall Reroofing and EXECUTION REQUIREMENTS Deck Replacement SMA #1505H

SECTION 017300 - EXECUTION

PART 1 - GENERAL

1.1 SUMMARY

1.2 SUMMARY

A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following:

1. Construction layout. 2. Field engineering and surveying. 3. Installation of the Work. 4. Cutting and patching. 5. Coordination of Owner-installed products. 6. Progress cleaning. 7. Starting and adjusting. 8. Protection of installed construction.

B. Related Requirements:

1. Section 011000 "Summary" for limits on use of Project site. 2. Section 017700 "Closeout Procedures" for recording of Owner-accepted deviations from

indicated lines and levels, and final cleaning.

1.3 QUALITY ASSURANCE

A. Cutting and Patching: Comply with requirements for and limitations on cutting and patching of construction elements.

1. Structural Elements: When cutting and patching structural elements, notify Architect of locations and details of cutting and await directions from Architect before proceeding. Shore, brace, and support structural element during cutting and patching. Do not cut and patch structural elements in a manner that could change their load-carrying capacity or increase deflection.

2. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety.

3. Other Construction Elements: Do not cut and patch other construction elements or components in a manner that could change their load-carrying capacity, that results in reducing their capacity to perform as intended, or that results in increased maintenance or decreased operational life or safety.

Page 123: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017300 Page 2

UCA Mashburn Hall Reroofing and EXECUTION REQUIREMENTS Deck Replacement SMA #1505H

4. Visual Elements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch exposed construction in a manner that would, in Architect's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.

PART 2 - PRODUCTS (Not Used)

2.1 MATERIALS

A. General: Comply with requirements specified in other Sections.

B. In-Place Materials: Use materials for patching identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.

1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide a match acceptable to Architect for the visual and functional performance of in-place materials.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Existing Conditions: The existence and location of site improvements, utilities, and other construction indicated as existing are not guaranteed. Before beginning work, investigate and verify the existence and location of mechanical and electrical systems and other construction affecting the Work.

1. Before construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer, and water-service piping; underground electrical services, and other utilities.

A. Examination and Acceptance of Conditions: Before proceeding with each component of the Work, examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.

1. Examine roughing-in for mechanical and electrical systems to verify actual locations of connections before equipment and fixture installation.

2. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed.

3. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.

B. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

Page 124: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017300 Page 3

UCA Mashburn Hall Reroofing and EXECUTION REQUIREMENTS Deck Replacement SMA #1505H

3.2 PREPARATION

A. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Architect not less than two days in advance of proposed utility interruptions. 2. Do not proceed with utility interruptions without Architect's written permission.

B. Field Measurements: Take field measurements as required to fit the Work properly. Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

C. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.

D. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents caused by differing field conditions outside the control of Contractor, submit a request for information to Architect according to requirements in Section 013100 "Project Management and Coordination."

3.3 CONSTRUCTION LAYOUT

A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify Architect promptly.

B. General: Engage a land surveyor to lay out the Work using accepted surveying practices.

1. Establish benchmarks and control points to set lines and levels at each story of construction and elsewhere as needed to locate each element of Project.

2. Establish limits on use of Project site. 3. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain

required dimensions. 4. Inform installers of lines and levels to which they must comply. 5. Check the location, level and plumb, of every major element as the Work progresses. 6. Notify Architect when deviations from required lines and levels exceed allowable

tolerances. 7. Close site surveys with an error of closure equal to or less than the standard established

by authorities having jurisdiction.

C. Site Improvements: Locate and lay out site improvements, including pavements, grading, fill and topsoil placement, utility slopes, and rim and invert elevations.

D. Building Lines and Levels: Locate and lay out control lines and levels for structures, building foundations, column grids, and floor levels, including those required for mechanical and electrical work. Transfer survey markings and elevations for use with control lines and levels. Level foundations and piers from two or more locations.

Page 125: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017300 Page 4

UCA Mashburn Hall Reroofing and EXECUTION REQUIREMENTS Deck Replacement SMA #1505H

E. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by Architect.

3.4 FIELD ENGINEERING

A. Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations.

B. Benchmarks: Establish and maintain a minimum of one permanent benchmark on Project site, referenced to data established by survey control points. Comply with authorities having jurisdiction for type and size of benchmark.

1. Record benchmark locations, with horizontal and vertical data, on Project Record Documents.

3.5 INSTALLATION

A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level. 2. Where space is limited, install components to maximize space available for maintenance

and ease of removal for replacement. 3. Conceal pipes, ducts, and wiring in finished areas, unless otherwise indicated.

B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.

C. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Substantial Completion.

D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.

E. Sequence the Work and allow adequate clearances to accommodate movement of construction items on site and placement in permanent locations.

F. Tools and Equipment: Do not use tools or equipment that produce harmful noise levels.

G. Templates: Obtain and distribute to the parties involved templates for work specified to be factory prepared and field installed. Check Shop Drawings of other work to confirm that adequate provisions are made for locating and installing products to comply with indicated requirements.

H. Attachment: Provide blocking and attachment plates and anchors and fasteners of adequate size and number to securely anchor each component in place, accurately located and aligned

Page 126: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017300 Page 5

UCA Mashburn Hall Reroofing and EXECUTION REQUIREMENTS Deck Replacement SMA #1505H

with other portions of the Work. Where size and type of attachments are not indicated, verify size and type required for load conditions.

1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by Architect.

2. Allow for building movement, including thermal expansion and contraction. 3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions

for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

I. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.

J. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.

3.6 CUTTING AND PATCHING

A. Cutting and Patching, General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.

1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.

B. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during installation or cutting and patching operations, by methods and with materials so as not to void existing warranties.

C. Temporary Support: Provide temporary support of work to be cut.

D. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.

E. Adjacent Occupied Areas: Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.

F. Existing Utility Services and Mechanical/Electrical Systems: Where existing services/systems are required to be removed, relocated, or abandoned, bypass such services/systems before cutting to prevent interruption to occupied areas.

G. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.

Page 127: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017300 Page 6

UCA Mashburn Hall Reroofing and EXECUTION REQUIREMENTS Deck Replacement SMA #1505H

1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots neatly to minimum size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.

2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces. 3. Asphalt Paving, Concrete and Masonry: Cut using a cutting machine, such as an

abrasive saw or a diamond-core drill. 4. Excavating and Backfilling: Comply with requirements in applicable Sections where

required by cutting and patching operations. 5. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be

removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting.

6. Proceed with patching after construction operations requiring cutting are complete.

H. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other work. Patch with durable seams that are as invisible as practicable. Provide materials and comply with installation requirements specified in other Sections, where applicable.

1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate physical integrity of installation.

2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will minimize evidence of patching and refinishing.

3. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.

4. Ceilings: Patch, repair, or rehang in-place ceilings as necessary to provide an even-plane surface of uniform appearance.

5. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weathertight condition and ensures thermal and moisture integrity of building enclosure.

I. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials from adjacent finished surfaces.

3.7 PROGRESS CLEANING

A. General: Clean Project site and work areas daily, including common areas. Coordinate progress cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg FContainerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

B. Site: Maintain Project site free of waste materials and debris.

Page 128: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017300 Page 7

UCA Mashburn Hall Reroofing and EXECUTION REQUIREMENTS Deck Replacement SMA #1505H

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

1. Remove liquid spills promptly. 2. Where dust would impair proper execution of the Work, broom-clean or vacuum the

entire work area, as appropriate.

D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

F. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.

G. Waste Disposal: Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.

H. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

I. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

J. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

3.8 STARTING AND ADJUSTING

A. Start equipment and operating components to confirm proper operation. Remove malfunctioning units, replace with new units, and retest.

B. Adjust equipment for proper operation. Adjust operating components for proper operation without binding.

C. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

D. Manufacturer's Field Service: Comply with qualification requirements in Section 014000 "Quality Requirements"

3.9 PROTECTION OF INSTALLED CONSTRUCTION

Page 129: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017300 Page 8

UCA Mashburn Hall Reroofing and EXECUTION REQUIREMENTS Deck Replacement SMA #1505H

A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.

B. Comply with manufacturer's written instructions for temperature and relative humidity.

3.10 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes. Comply with requirements in "Cutting and Patching" article.

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

B. Restore permanent facilities used during construction to their specified condition.

C. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.

END OF SECTION 017300

Page 130: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017700 Page 1

UCA Mashburn Hall Reroofing and CLOSEOUT PROCEDURES Deck Replacement SMA #1505H

SECTION 017700 - CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Substantial Completion procedures. 2. Final completion procedures. 3. Warranties. 4. Final cleaning. 5. Repair of the Work.

B. Related Sections:

1. Section 017823 "Operation and Maintenance Data" for operation and maintenance manual requirements.

2. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data.

3. Divisions 2 through 33 Sections for specific closeout and special cleaning requirements for the Work in those Sections.

1.2 ACTION SUBMITTALS

A. Product Data: For cleaning agents.

B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.

C. Certified List of Incomplete Items: Final submittal at Final Completion.

1.3 SUBSTANTIAL COMPLETION

A. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete with request.

1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.

2. Advise Owner of pending insurance changeover requirements. 3. Obtain and submit releases permitting Owner unrestricted use of the Work and access to

services and utilities. Include occupancy permits, operating certificates, and similar releases.

4. Deliver tools, spare parts, extra materials, and similar items to location designated by Owner. Label with manufacturer's name and model number where applicable.

Page 131: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017700 Page 2

UCA Mashburn Hall Reroofing and CLOSEOUT PROCEDURES Deck Replacement SMA #1505H

5. Make final changeover of permanent locks and deliver keys to Owner. Advise Owner's personnel of changeover in security provisions.

6. Complete startup testing of systems. 7. Submit test/adjust/balance records. 8. Terminate and remove temporary facilities from Project site, along with mockups,

construction tools, and similar elements. 9. Advise Owner of changeover in heat and other utilities. 10. Submit changeover information related to Owner's occupancy, use, operation, and

maintenance.

B. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, Architect will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by Architect, that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for final completion.

1.4 FINAL COMPLETION

A. Preliminary Procedures: Before requesting final inspection for determining final completion, complete the following:

1. Submit a final Application for Payment according to Division 1 Section "Payment Procedures."

2. Submit certified copy of Architect's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Architect. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

3. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

4. Submit pest-control final inspection report and warranty. 5. Submit specific warranties, workmanship bonds, maintenance service agreements, final

certifications, and similar documents. 6. Prepare and submit Project Record Documents, operation and maintenance manuals,

final completion construction photographic documentation, damage or settlement surveys, property surveys, and similar final record information.

7. Instruct Owner's personnel in operation, adjustment, and maintenance of products, equipment, and systems.

8. Complete final cleaning requirements, including touchup painting. 9. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual

defects.

B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, Architect will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

Page 132: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017700 Page 3

UCA Mashburn Hall Reroofing and CLOSEOUT PROCEDURES Deck Replacement SMA #1505H

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

1.5 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

A. Organization of List: Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

1. Organize list of spaces in sequential order, starting with exterior areas first. 2. Organize items applying to each space by major element, including categories for ceiling,

individual walls, floors, equipment, and building systems. 3. Submit list of incomplete items in the following format:

a. PDF electronic file. Architect will return annotated copy.

1.6 WARRANTIES

A. Submittal Time: Submit written warranties on request of Architect for designated portions of the Work where commencement of warranties other than date of Substantial Completion is indicated.

B. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual.

1. Bind warranties and bonds in heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch paper.

2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor.

4. Warranty Electronic File: Scan warranties and bonds and assemble complete warranty and bond submittal package into a single indexed electronic PDF file with links enabling navigation to each item. Provide bookmarked table of contents at beginning of document.

C. Provide additional copies of each warranty to include in operation and maintenance manuals.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

Page 133: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017700 Page 4

UCA Mashburn Hall Reroofing and CLOSEOUT PROCEDURES Deck Replacement SMA #1505H

PART 3 - EXECUTION

3.1 REPAIR OF THE WORK

A. Complete repair and restoration operations before requesting inspection for determination of Substantial Completion.

B. Repair or remove and replace defective construction. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. Where damaged or worn items cannot be repaired or restored, provide replacements. Remove and replace operating components that cannot be repaired. Restore damaged construction and permanent facilities used during construction to specified condition.

1. Remove and replace chipped, scratched, and broken glass, reflective surfaces, and other damaged transparent materials.

2. Touch up and otherwise repair and restore marred or exposed finishes and surfaces. Replace finishes and surfaces that that already show evidence of repair or restoration.

a. Do not paint over "UL" and other required labels and identification, including mechanical and electrical nameplates. Remove paint applied to required labels and identification.

3. Replace parts subject to operating conditions during construction that may impede operation or reduce longevity.

4. Replace burned-out bulbs, bulbs noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures.

3.2 FINAL CLEANING

A. General: Perform final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions.

1. Complete the following cleaning operations before requesting inspection for Final Completion for entire Project or for a portion of Project:

a. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.

c. Rake grounds that are neither planted nor paved to a smooth, even-textured surface.

Page 134: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017700 Page 5

UCA Mashburn Hall Reroofing and CLOSEOUT PROCEDURES Deck Replacement SMA #1505H

d. Remove tools, construction equipment, machinery, and surplus material from Project site.

e. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.

f. Remove debris and surface dust from limited access spaces, including roofs, plenums, shafts, trenches, equipment vaults, manholes, attics, and similar spaces.

g. Sweep concrete floors broom clean in unoccupied spaces. h. Vacuum carpet and similar soft surfaces, removing debris and excess nap;

shampoo if visible soil or stains remain. i. Clean transparent materials, including mirrors and glass in doors and windows.

Remove glazing compounds and other noticeable, vision-obscuring materials. Replace chipped or broken glass and other damaged transparent materials. Polish mirrors and glass, taking care not to scratch surfaces.

j. Remove labels that are not permanent. k. Touch up and otherwise repair and restore marred, exposed finishes and surfaces.

Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.

1) Do not paint over "UL" and other required labels and identification, including mechanical and electrical nameplates.

l. Wipe surfaces of mechanical and electrical equipment and similar equipment. Remove excess lubrication, paint and mortar droppings, and other foreign substances.

m. Replace parts subject to operating conditions during construction that may impede operation or reduce longevity.

n. Clean plumbing fixtures to a sanitary condition, free of stains, including stains resulting from water exposure.

o. Replace disposable air filters and clean permanent air filters. Clean exposed surfaces of diffusers, registers, and grills.

p. Clean light fixtures, lamps, globes, and reflectors to function with full efficiency. Replace burned-out bulbs, and those noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures.

q. Leave Project clean and ready for occupancy.

C. Pest Control: Engage an experienced, licensed exterminator to make a final inspection and rid Project of rodents, insects, and other pests. Prepare a report.

3.3 REPAIR OF THE WORK

A. Complete repair and restoration operations before requesting inspection for determination of Substantial Completion.

B. Repair or remove and replace defective construction. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. Where damaged or worn items cannot be repaired or restored, provide replacements. Remove and replace operating components that cannot be repaired.

Page 135: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017700 Page 6

UCA Mashburn Hall Reroofing and CLOSEOUT PROCEDURES Deck Replacement SMA #1505H

Restore damaged construction and permanent facilities used during construction to specified condition.

1. Remove and replace chipped, scratched, and broken glass, reflective surfaces, and other damaged transparent materials.

2. Touch up and otherwise repair and restore marred or exposed finishes and surfaces. Replace finishes and surfaces that that already show evidence of repair or restoration.

a. Do not paint over "UL" and other required labels and identification, including mechanical and electrical nameplates. Remove paint applied to required labels and identification.

3. Replace parts subject to operating conditions during construction that may impede operation or reduce longevity.

4. Replace burned-out bulbs, bulbs noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures.

END OF SECTION 017700

Page 136: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017823 Page 1

UCA Mashburn Hall Reroofing and OPERATION AND MAINTENANCE DATA Deck Replacement SMA #1505H

SECTION 017823 - OPERATION AND MAINTENANCE DATA

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for preparing operation and maintenance manuals, including the following:

1. Operation and maintenance documentation directory. 2. Operation manuals for systems, subsystems, and equipment. 3. Product maintenance manuals. 4. Systems and equipment maintenance manuals.

1.2 CLOSEOUT SUBMITTALS

A. Manual Content: Operations and maintenance manual content is specified in individual Specification Sections to be reviewed at the time of Section submittals. Submit reviewed manual content formatted and organized as required by this Section.

1. Architect will comment on whether content of operations and maintenance submittals are acceptable.

2. Where applicable, clarify and update reviewed manual content to correspond to revisions and field conditions.

B. Format: Submit operations and maintenance manuals in the both of the following formats:

1. PDF electronic file. Assemble each manual into a composite electronically indexed file. Submit on digital media acceptable to Architect.

a. Name each indexed document file in composite electronic index with applicable item name. Include a complete electronically linked operation and maintenance directory.

b. Enable inserted reviewer comments on draft submittals.

2. One paper copy. Include a complete operation and maintenance directory. Enclose title pages and directories in clear plastic sleeves.

C. Manual Submittal: Submit each manual in final form prior to requesting inspection for Final Completion and at least 15 days before commencing demonstration and training. Architect will return copy with comments.

1. Correct or modify each manual to comply with Architect's comments. Submit copies of each corrected manual within 15 days of receipt of Architect's comments and prior to commencing demonstration and training.

Page 137: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017823 Page 2

UCA Mashburn Hall Reroofing and OPERATION AND MAINTENANCE DATA Deck Replacement SMA #1505H

PART 2 - PRODUCTS

2.1 REQUIREMENTS FOR OPERATION AND MAINTENANCE MANUALS

A. Directory: Prepare a single, comprehensive directory of operation and maintenance data and materials, listing items and their location to facilitate ready access to desired information.

B. Organization: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system. Each manual shall contain the following materials, in the order listed:

1. Title page. 2. Table of contents. 3. Manual contents.

C. Title Page: Include the following information:

1. Subject matter included in manual. 2. Name and address of Project. 3. Name and address of Owner. 4. Date of submittal. 5. Name and contact information for Contractor. 6. Name and contact information for Architect. 7. Names and contact information for major consultants to the Architect that designed the

systems contained in the manuals. 8. Cross-reference to related systems in other operation and maintenance manuals.

D. Table of Contents: List each product included in manual, identified by product name, indexed to the content of the volume, and cross-referenced to Specification Section number in Project Manual.

E. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder.

F. Manuals, Electronic Files: Submit manuals in the form of a multiple file composite electronic PDF file for each manual type required.

1. Electronic Files: Use electronic files prepared by manufacturer where available. Where scanning of paper documents is required, configure scanned file for minimum readable file size.

2. File Names and Bookmarks: Enable bookmarking of individual documents based on file names. Name document files to correspond to system, subsystem, and equipment names used in manual directory and table of contents. Group documents for each system and subsystem into individual composite bookmarked files, then create composite manual, so that resulting bookmarks reflect the system, subsystem, and equipment names in a readily navigated file tree. Configure electronic manual to display bookmark panel on opening file.

G. Manuals, Paper Copy: Submit manuals in the form of hard copy, bound and labeled volumes.

Page 138: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017823 Page 3

UCA Mashburn Hall Reroofing and OPERATION AND MAINTENANCE DATA Deck Replacement SMA #1505H

1. Binders: Heavy-duty, three-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, sized to hold 8-1/2-by-11-inch paper; with clear plastic sleeve on spine to hold label describing contents and with pockets inside covers to hold folded oversize sheets.

a. Identify each binder on front and spine, with printed title "OPERATION AND MAINTENANCE MANUAL," Project title or name, and subject matter of contents. Indicate volume number for multiple-volume sets.

2. Dividers: Heavy-paper dividers with plastic-covered tabs for each section of the manual. Mark each tab to indicate contents. Include typed list of products and major components of equipment included in the section on each divider, cross-referenced to Specification Section number and title of Project Manual.

3. Protective Plastic Sleeves: Transparent plastic sleeves designed to enclose diagnostic software storage media for computerized electronic equipment.

4. Drawings: Attach reinforced, punched binder tabs on drawings and bind with text.

a. If oversize drawings are necessary, fold drawings to same size as text pages and use as foldouts.

b. If drawings are too large to be used as foldouts, fold and place drawings in labeled envelopes and bind envelopes in rear of manual. At appropriate locations in manual, insert typewritten pages indicating drawing titles, descriptions of contents, and drawing locations.

2.2 OPERATION MANUALS

A. Content: In addition to requirements in this Section, include operation data required in individual Specification Sections and the following information:

1. System, subsystem, and equipment descriptions. Use designations for systems and equipment indicated on Contract Documents.

2. Performance and design criteria if Contractor is delegated design responsibility. 3. Operating standards. 4. Operating procedures. 5. Operating logs. 6. Wiring diagrams. 7. Control diagrams. 8. Piped system diagrams. 9. Precautions against improper use. 10. License requirements including inspection and renewal dates.

B. Descriptions: Include the following:

1. Product name and model number. Use designations for products indicated on Contract Documents.

2. Manufacturer's name. 3. Equipment identification with serial number of each component. 4. Equipment function. 5. Operating characteristics. 6. Limiting conditions. 7. Performance curves.

Page 139: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017823 Page 4

UCA Mashburn Hall Reroofing and OPERATION AND MAINTENANCE DATA Deck Replacement SMA #1505H

8. Engineering data and tests. 9. Complete nomenclature and number of replacement parts.

C. Operating Procedures: Include the following, as applicable:

1. Startup procedures. 2. Equipment or system break-in procedures. 3. Routine and normal operating instructions. 4. Regulation and control procedures. 5. Instructions on stopping. 6. Normal shutdown instructions. 7. Seasonal and weekend operating instructions. 8. Required sequences for electric or electronic systems. 9. Special operating instructions and procedures.

D. Systems and Equipment Controls: Describe the sequence of operation, and diagram controls as installed.

E. Piped Systems: Diagram piping as installed, and identify color-coding where required for identification.

2.3 PRODUCT MAINTENANCE MANUALS

A. Content: Organize manual into a separate section for each product, material, and finish. Include source information, product information, maintenance procedures, repair materials and sources, and warranties and bonds, as described below.

B. Source Information: List each product included in manual, identified by product name and arranged to match manual's table of contents. For each product, list name, address, and telephone number of Installer or supplier and maintenance service agent, and cross-reference Specification Section number and title in Project Manual.

C. Product Information: Include the following, as applicable:

1. Product name and model number. 2. Manufacturer's name. 3. Color, pattern, and texture. 4. Material and chemical composition. 5. Reordering information for specially manufactured products.

D. Maintenance Procedures: Include manufacturer's written recommendations and the following:

1. Inspection procedures. 2. Types of cleaning agents to be used and methods of cleaning. 3. List of cleaning agents and methods of cleaning detrimental to product. 4. Schedule for routine cleaning and maintenance. 5. Repair instructions.

E. Repair Materials and Sources: Include lists of materials and local sources of materials and related services.

Page 140: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017823 Page 5

UCA Mashburn Hall Reroofing and OPERATION AND MAINTENANCE DATA Deck Replacement SMA #1505H

F. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds.

2.4 SYSTEMS AND EQUIPMENT MAINTENANCE MANUALS

A. Content: For each system, subsystem, and piece of equipment not part of a system, include source information, manufacturers' maintenance documentation, maintenance procedures, maintenance and service schedules, spare parts list and source information, maintenance service contracts, and warranty and bond information, as described below.

B. Source Information: List each system, subsystem, and piece of equipment included in manual, identified by product name and arranged to match manual's table of contents. For each product, list name, address, and telephone number of Installer or supplier and maintenance service agent, and cross-reference Specification Section number and title in Project Manual.

C. Manufacturers' Maintenance Documentation: Manufacturers' maintenance documentation including the following information for each component part or piece of equipment:

1. Standard maintenance instructions and bulletins. 2. Drawings, diagrams, and instructions required for maintenance, including disassembly

and component removal, replacement, and assembly. 3. Identification and nomenclature of parts and components. 4. List of items recommended to be stocked as spare parts.

D. Maintenance Procedures: Include the following information and items that detail essential maintenance procedures:

1. Test and inspection instructions. 2. Troubleshooting guide. 3. Precautions against improper maintenance. 4. Disassembly; component removal, repair, and replacement; and reassembly instructions. 5. Aligning, adjusting, and checking instructions. 6. Demonstration and training video recording, if available.

E. Maintenance and Service Schedules: Include service and lubrication requirements, list of required lubricants for equipment, and separate schedules for preventive and routine maintenance and service with standard time allotment.

F. Spare Parts List and Source Information: Include lists of replacement and repair parts, with parts identified and cross-referenced to manufacturers' maintenance documentation and local sources of maintenance materials and related services.

G. Maintenance Service Contracts: Include copies of maintenance agreements with name and telephone number of service agent.

H. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds.

Page 141: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017823 Page 6

UCA Mashburn Hall Reroofing and OPERATION AND MAINTENANCE DATA Deck Replacement SMA #1505H

PART 3 - EXECUTION

3.1 MANUAL PREPARATION

A. Product Maintenance Manual: Assemble a complete set of maintenance data indicating care and maintenance of each product, material, and finish incorporated into the Work.

B. Operation and Maintenance Manuals: Assemble a complete set of operation and maintenance data indicating operation and maintenance of each system, subsystem, and piece of equipment not part of a system.

C. Manufacturers' Data: Where manuals contain manufacturers' standard printed data, include only sheets pertinent to product or component installed. Mark each sheet to identify each product or component incorporated into the Work. If data include more than one item in a tabular format, identify each item using appropriate references from the Contract Documents. Identify data applicable to the Work and delete references to information not applicable.

D. Drawings: Prepare drawings supplementing manufacturers' printed data to illustrate the relationship of component parts of equipment and systems and to illustrate control sequence and flow diagrams. Coordinate these drawings with information contained in record Drawings to ensure correct illustration of completed installation.

1. Do not use original project record documents as part of operation and maintenance manuals.

E. Comply with Section 017700 "Closeout Procedures" for schedule for submitting operation and maintenance documentation.

END OF SECTION 017823

Page 142: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017839 Page 1

UCA Mashburn Hall Reroofing and PROJECT RECORD DOCUMENTS Deck Replacement SMA #1505H

SECTION 017839 - PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for project record documents, including the following:

1. Record Drawings. 2. Record Specifications. 3. Record Product Data.

B. Related Requirements:

1. Section 017823 "Operation and Maintenance Data" for operation and maintenance manual requirements.

1.2 CLOSEOUT SUBMITTALS

A. Record Drawings: Comply with the following:

1. Number of Copies: Submit copies of record Drawings as follows:

a. Submit PDF electronic files of scanned record prints and one paper-copy set of marked-up record prints.

b. Print each drawing, whether or not changes and additional information were recorded.

A. Record Specifications: Submit one paper copy and annotated PDF electronic files of Project's Specifications, including addenda and contract modifications.

B. Record Product Data: Submit one paper copy and annotated PDF electronic files and directories of each submittal.

PART 2 - PRODUCTS

2.1 RECORD DRAWINGS

A. Record Prints: Maintain one set of marked-up paper copies of the Contract Drawings and Shop Drawings.

1. Preparation: Mark record prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data,

Page 143: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017839 Page 2

UCA Mashburn Hall Reroofing and PROJECT RECORD DOCUMENTS Deck Replacement SMA #1505H

whether individual or entity is Installer, subcontractor, or similar entity, to provide information for preparation of corresponding marked-up record prints.

a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.

b. Record data as soon as possible after obtaining it. c. Record and check the markup before enclosing concealed installations.

2. Mark the Contract Drawings and Shop Drawings completely and accurately. Utilize personnel proficient at recording graphic information in production of marked-up record prints.

3. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

4. Note alternate numbers, Change Order numbers, and similar identification, where applicable.

B. Format: Identify and date each record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location.

1. Record Prints: Organize record prints and newly prepared record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

2. Identification: As follows:

a. Project name. b. Date. c. Designation "PROJECT RECORD DRAWINGS." d. Name of Architect. e. Name of Contractor.

2.2 RECORD SPECIFICATIONS

A. Preparation: Mark Specifications to indicate the actual product installation where installation varies from that indicated in Specifications, addenda, and contract modifications.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected.

3. Record the name of manufacturer, supplier, Installer, and other information necessary to provide a record of selections made.

4. Note related Change Orders and record Drawings where applicable.

B. Format: Submit record Specifications as annotated PDF electronic file and as paper copy.

2.3 RECORD PRODUCT DATA

A. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.

Page 144: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

017839 Page 3

UCA Mashburn Hall Reroofing and PROJECT RECORD DOCUMENTS Deck Replacement SMA #1505H

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.

3. Note related Change Orders and record Drawings where applicable.

B. Format: Submit record Product Data as annotated PDF electronic file and as paper copy.

2.4 MISCELLANEOUS RECORD SUBMITTALS

A. Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference.

B. Format: Submit miscellaneous record submittals as PDF electronic file and as paper copy.

PART 3 - EXECUTION

3.1 RECORDING AND MAINTENANCE

A. Recording: Maintain one copy of each submittal during the construction period for project record document purposes. Post changes and modifications to project record documents as they occur; do not wait until the end of Project.

B. Maintenance of Record Documents and Samples: Store record documents and Samples in the field office apart from the Contract Documents used for construction. Do not use project record documents for construction purposes. Maintain record documents in good order and in a clean, dry, legible condition, protected from deterioration and loss. Provide access to project record documents for Architect's reference during normal working hours.

END OF SECTION 017839

Page 145: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

024119 Page 1

UCA Mashburn Hall Reroofing and SELECTIVE DEMOLITION Deck Replacement SMA #1505H

SECTION 024119 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of building or structure. 2. Demolition and removal of selected site elements. 3. Salvage of existing items to be reused or recycled.

1.2 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.

B. Remove and Salvage: Detach items from existing construction and deliver them to Owner.

C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.

D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

1.3 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.

1. Carefully salvage in a manner to prevent damage and promptly return to Owner.

1.4 PREINSTALLATION MEETINGS

A. Predemolition Conference: Conduct conference at Project site.

1.5 INFORMATIONAL SUBMITTALS

A. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, for dust control and for noise control. Indicate proposed locations and construction of barriers.

Page 146: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

024119 Page 2

UCA Mashburn Hall Reroofing and SELECTIVE DEMOLITION Deck Replacement SMA #1505H

B. Schedule of selective demolition activities with starting and ending dates for each activity.

C. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician.

1.6 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.

C. Standards: Comply with ASSE A10.6 and NFPA 241.

1.7 PROJECT CONDITIONS

A. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

B. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.

1. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from authorities having jurisdiction.

C. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

1. Hazardous materials will be removed by Owner before start of the Work. 2. If suspected hazardous materials are encountered, do not disturb; immediately notify

Architect and Owner. Hazardous materials will be removed by Owner under a separate contract.

E. Storage or sale of removed items or materials on-site will not be permitted.

F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

1.8 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties.

Page 147: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

024119 Page 3

UCA Mashburn Hall Reroofing and SELECTIVE DEMOLITION Deck Replacement SMA #1505H

1. If possible, retain original Installer or fabricator to patch the exposed Work listed below that is damaged during selective demolition. If it is impossible to engage original Installer or fabricator, engage another recognized experienced and specialized firm.

PART 2 - PRODUCTS

2.1 REPAIR MATERIALS

A. Use repair materials identical to existing materials.

1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.

2. Use materials whose installed performance equals or surpasses that of existing materials.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

C. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.

D. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to Architect.

3.2 PREPARATION

A. Refrigerant: Before starting demolition, remove refrigerant from mechanical equipment according to 40 CFR 82 and regulations of authorities having jurisdiction.

3.3 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

B. Do not interrupt existing utilities serving occupied or operating facilities unless authorized in writing by Owner and authorities having jurisdiction. Provide temporary services during interruptions to existing utilities, as acceptable to Owner and to authorities having jurisdiction.

Page 148: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

024119 Page 4

UCA Mashburn Hall Reroofing and SELECTIVE DEMOLITION Deck Replacement SMA #1505H

1. Provide at least 72 hours' notice to Owner if shutdown of service is required during changeover.

A. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Arrange to shut off indicated utilities with utility companies. 2. If services/systems are required to be removed, relocated, or abandoned, provide

temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

3. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated on Drawings to be removed.

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.

b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material and leave in place.

c. Equipment to Be Removed: Disconnect and cap services and remove equipment. d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and

remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.

e. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner.

f. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.

g. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material and leave in place.

3.4 PREPARATION

A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

1. Do not close or obstruct streets, walks, walkways, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction. Provide alternate routes around closed or obstructed traffic ways if required by governing regulations.

2. Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction.

B. Temporary Enclosures: Provide temporary enclosures for protection of existing building and construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.

C. Temporary Partitions: Erect and maintain dustproof partitions and temporary enclosures to limit dust and dirt migration and to separate areas from fumes and noise.

Page 149: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

024119 Page 5

UCA Mashburn Hall Reroofing and SELECTIVE DEMOLITION Deck Replacement SMA #1505H

3.5 PROTECTION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

B. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

C. Remove temporary barricades and protections where hazards no longer exist.

3.6 POLLUTION CONTROLS

A. Dust Control: Use water mist, temporary enclosures, and other suitable methods to limit spread of dust and dirt. Comply with governing environmental-protection regulations.

1. Wet mop floors to eliminate trackable dirt and wipe down walls and doors of demolition enclosure. Vacuum carpeted areas.

B. Disposal: Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

1. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

C. Cleaning: Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

3.7 SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.

1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

4. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

Page 150: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

024119 Page 6

UCA Mashburn Hall Reroofing and SELECTIVE DEMOLITION Deck Replacement SMA #1505H

B. Existing Facilities: Comply with building manager's requirements for using and protecting elevators, stairs, walkways, loading docks, building entries, and other building facilities during selective demolition operations.

C. Removed and Salvaged Items:

1. Clean salvaged items. 2. Pack or crate items after cleaning. Identify contents of containers. 3. Store items in a secure area until delivery to Owner. 4. Transport items to Owner's storage area designated by Owner. 5. Protect items from damage during transport and storage.

D. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse. Paint equipment to match new equipment.

2. Pack or crate items after cleaning and repairing. Identify contents of containers. 3. Protect items from damage during transport and storage. 4. Reinstall items in locations indicated. Comply with installation requirements for new

materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

3.8 PATCHING AND REPAIRS

A. General: Promptly repair damage to adjacent construction caused by selective demolition operations.

B. Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.

C. Floors and Walls: Where walls or partitions that are demolished extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish color, texture, and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.

D. Ceilings: Patch, repair, or rehang existing ceilings as necessary to provide an even-plane surface of uniform appearance.

3.9 CLEANING

A. Remove demolition waste materials from Project site and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction.

1. Do not allow demolished materials to accumulate on-site.

Page 151: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

024119 Page 7

UCA Mashburn Hall Reroofing and SELECTIVE DEMOLITION Deck Replacement SMA #1505H

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

B. Burning: Do not burn demolished materials.

C. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 024119

Page 152: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

053100 Page 1

UCA Mashburn Hall Reroofing and STEEL DECKING Deck Replacement SMA #1505H

SECTION 053100 - STEEL DECKING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Roof deck.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of deck, accessory, and product indicated.

B. Shop Drawings:

1. Include layout and types of deck panels, anchorage details, reinforcing channels, pans, cut deck openings, special jointing, accessories, and attachments to other construction.

1.3 INFORMATIONAL SUBMITTALS

A. Welding certificates.

B. Product certificates.

C. Evaluation reports.

D. Field quality-control reports.

1.4 QUALITY ASSURANCE

A. Testing Agency Qualifications: Qualified according to ASTM E 329 for testing indicated.

B. Welding Qualifications: Qualify procedures and personnel according to AWS D1.3, "Structural Welding Code - Sheet Steel."

1.5 DELIVERY, STORAGE, AND HANDLING

A. Protect steel deck from corrosion, deformation, and other damage during delivery, storage, and handling.

B. Stack steel deck on platforms or pallets and slope to provide drainage. Protect with a waterproof covering and ventilate to avoid condensation.

Page 153: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

053100 Page 2

UCA Mashburn Hall Reroofing and STEEL DECKING Deck Replacement SMA #1505H

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. AISI Specifications: Comply with calculated structural characteristics of steel deck according to AISI's "North American Specification for the Design of Cold-Formed Steel Structural Members."

2.2 ROOF DECK

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1. ASC Profiles, Inc.; a Blue Scope Steel company. 2. Canam United States; Canam Group Inc. 3. CMC Joist & Deck. 4. Consolidated Systems, Inc.; Metal Dek Group. 5. Cordeck. 6. DACS, Inc. 7. Epic Metals Corporation. 8. Marlyn Steel Decks, Inc. 9. New Millennium Building Systems, LLC. 10. Nucor Corp.; Vulcraft Group. 11. Roof Deck, Inc. 12. Valley Joist; Subsidiary of EBSCO Industries, Inc. 13. Verco Manufacturing Co. 14. Wheeling Corrugating Company; Div. of Wheeling-Pittsburgh Steel Corporation.

B. Roof Deck: Fabricate panels, without top-flange stiffening grooves, to comply with "SDI Specifications and Commentary for Steel Roof Deck," in SDI Publication No. 31, and with the following:

1. Galvanized-Steel Sheet: ASTM A 653/A 653M, Structural Steel (SS), Grade 33, G60 zinc coating.

2. Deck Profile: Type WR, wide rib. 3. Profile Depth: 1-1/2 inches. 4. Design Uncoated-Steel Thickness: As indicated.

2.3 ACCESSORIES

A. General: Provide manufacturer's standard accessory materials for deck that comply with requirements indicated.

B. Mechanical Fasteners: Corrosion-resistant, low-velocity, power-actuated or pneumatically driven carbon-steel fasteners; or self-drilling, self-threading screws.

C. Side-Lap Fasteners: Corrosion-resistant, hexagonal washer head; self-drilling, carbon-steel screws, No. 10 minimum diameter.

D. Flexible Closure Strips: Vulcanized, closed-cell, synthetic rubber.

Page 154: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

053100 Page 3

UCA Mashburn Hall Reroofing and STEEL DECKING Deck Replacement SMA #1505H

E. Miscellaneous Sheet Metal Deck Accessories: Steel sheet, minimum yield strength of 33,000 psi, not less than 0.0359-inch design uncoated thickness, of same material and finish as deck; of profile indicated or required for application.

F. Flat Sump Plates: Single-piece steel sheet, 0.0747 inch thick, of same material and finish as deck. For drains, cut holes in the field.

G. Galvanizing Repair Paint: ASTM A 780.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Install deck panels and accessories according to applicable specifications and commentary in SDI Publication No. 31, manufacturer's written instructions, and requirements in this Section.

B. Place deck panels on supporting frame and adjust to final position with ends accurately aligned and bearing on supporting frame before being permanently fastened. Do not stretch or contract side-lap interlocks.

C. Place deck panels flat and square and fasten to supporting frame without warp or deflection.

D. Cut and neatly fit deck panels and accessories around openings and other work projecting through or adjacent to deck.

E. Provide additional reinforcement and closure pieces at openings as required for strength, continuity of deck, and support of other work.

F. Mechanical fasteners are only to be used in lieu of welding to fasten deck. Locate mechanical fasteners and install according to deck manufacturer's written instructions.

G. Miscellaneous Roof-Deck Accessories: Install ridge and valley plates, finish strips, end closures, and reinforcing channels according to deck manufacturer's written instructions. Mechanically fasten to substrate to provide a complete deck installation.

3.2 FIELD QUALITY CONTROL

A. Testing Agency: Engage a qualified testing agency to perform tests and inspections.

B. Testing agency will report inspection results promptly and in writing to Contractor and Architect.

C. Remove and replace work that does not comply with specified requirements.

D. Additional inspecting, at Contractor's expense, will be performed to determine compliance of corrected work with specified requirements.

Page 155: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

053100 Page 4

UCA Mashburn Hall Reroofing and STEEL DECKING Deck Replacement SMA #1505H

3.3 PROTECTION

A. Galvanizing Repairs: Prepare and repair damaged galvanized coatings on both surfaces of deck with galvanized repair paint according to ASTM A 780 and manufacturer's written instructions.

END OF SECTION 053100

Page 156: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

061053 Page 1

UCA Mashburn Hall Reroofing and MISCELLANEOUS ROUGH CARPENTRY Deck Replacement SMA #1505H

SECTION 061053 - MISCELLANEOUS ROUGH CARPENTRY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Rooftop equipment bases and support curbs. 2. Wood blocking and nailers.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of process and factory-fabricated product.

1.3 INFORMATIONAL SUBMITTALS

A. Evaluation Reports: For the following, from ICC-ES:

1. Preservative-treated wood. 2. Power-driven fasteners.

PART 2 - PRODUCTS

2.1 WOOD PRODUCTS, GENERAL

A. Lumber: DOC PS 20 and applicable rules of grading agencies indicated. If no grading agency is indicated, provide lumber that complies with the applicable rules of any rules-writing agency certified by the ALSC Board of Review. Provide lumber graded by an agency certified by the ALSC Board of Review to inspect and grade lumber under the rules indicated.

1. Factory mark each piece of lumber with grade stamp of grading agency. 2. Dress lumber, S4S, unless otherwise indicated.

2.2 WOOD-PRESERVATIVE-TREATED MATERIALS

A. Preservative Treatment by Pressure Process: AWPA U1; Use Category UC2 for interior construction not in contact with ground, Use Category UC3b for exterior construction not in contact with ground, and Use Category UC4a for items in contact with ground.

1. Preservative Chemicals: Acceptable to authorities having jurisdiction and containing no arsenic or chromium.

Page 157: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

061053 Page 2

UCA Mashburn Hall Reroofing and MISCELLANEOUS ROUGH CARPENTRY Deck Replacement SMA #1505H

B. Do not use material that is warped or does not comply with requirements for untreated material.

C. Mark lumber with treatment quality mark of an inspection agency approved by the ALSC Board of Review.

D. Application: Treat items indicated on Drawings, and the following:

1. Wood cants, nailers, curbs, equipment support bases, blocking, stripping, and similar members in connection with roofing, flashing, vapor barriers, and waterproofing.

2. Wood sills, sleepers, blocking, and similar concealed members in contact with masonry or concrete.

3. Wood framing and furring attached directly to the interior of below-grade exterior masonry or concrete walls.

4. Wood framing members that are less than 18 inches above the ground in crawlspaces or unexcavated areas.

5. Wood floor plates that are installed over concrete slabs-on-grade.

2.3 MISCELLANEOUS LUMBER

A. General: Provide miscellaneous lumber indicated and lumber for support or attachment of other construction, including the following:

1. Blocking. 2. Nailers. 3. Rooftop equipment bases and support curbs.

B. Miscellaneous Framing: No. 2 grade of the following species:

1. Southern pine; SPIB.

2.4 PLYWOOD

A. Plywood Sheathing: Either DOC PS 1 or DOC PS 2, Exterior sheathing.

2.5 FASTENERS

A. General: Provide fasteners of size and type indicated that comply with requirements specified in this article for material and manufacture.

1. Where carpentry is exposed to weather, in ground contact, pressure-preservative treated, or in area of high relative humidity, provide fasteners with hot-dip zinc coating complying with ASTM A 153/A 153M or Type 304 stainless steel.

B. Screws for Fastening to Metal Framing: ASTM C 1002, length as recommended by screw manufacturer for material being fastened.

C. Power-Driven Fasteners: Fastener systems with an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES AC70.

Page 158: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

061053 Page 3

UCA Mashburn Hall Reroofing and MISCELLANEOUS ROUGH CARPENTRY Deck Replacement SMA #1505H

D. Screws for Fastening to Concrete: Fastener systems with an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES ESR-1671.

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to the following:

a. ITW Buildex; Tapcon anchors.

2.6 MISCELLANEOUS MATERIALS

A. Underlayment Material: Composite, self-adhesive, flashing product consisting of a pliable, butyl rubber or rubberized-asphalt compound, bonded to a high-density polyethylene film, aluminum foil, or spunbonded polyolefin to produce an overall thickness of not less than 0.025.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Framing Standard: Comply with AF&PA's WCD 1, "Details for Conventional Wood Frame Construction," unless otherwise indicated.

B. Set carpentry to required levels and lines, with members plumb, true to line, cut, and fitted. Fit carpentry accurately to other construction. Locate nailers, blocking,and similar supports to comply with requirements for attaching other construction.

C. Do not splice structural members between supports unless otherwise indicated.

D. Comply with AWPA M4 for applying field treatment to cut surfaces of preservative-treated lumber.

E. Where wood-preservative-treated lumber is installed adjacent to metal decking, install continuous flexible flashing underlayment separator between wood and metal decking.

F. Securely attach carpentry work to substrate by anchoring and fastening as indicated, complying with the following:

1. Table 2304.9.1, "Fastening Schedule," in ICC's International Building Code.

END OF SECTION 061053

Page 159: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

070150.19 Page 1

UCA Mashburn Hall Reroofing and PREPARATION FOR REROOFING Deck Replacement SMA #1505H

SECTION 070150.19 - PREPARATION FOR REROOFING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Full tear-off of roof system at areas indicated on Drawings. 2. Full tear-off of roof system, lightweight concrete and metal deck indicated on the

Drawings. 3. Removal of flashings and counterflashings.

1.2 ALLOWANCES

A. Allowance for removal of existing wet lightweight concrete roof deck, and replacement with new insulation, is specified under Section 012100 "Allowances."

B. Allowance for removal of existing rusted deck in the northwest roof area and replacement with same profile and gauge, is specified under Section 012100 “Allowances.”

C. Allowance for removal of surface rust from existing metal deck in the northwest roof area and paint with a rust inhibitive paint, is specified under Section 012100 “Allowances.”

D. Allowance for drain inserts for damaged roof drains, is specified under Section 012100 “Allowances.”

E. Allowance for removal of existing deteriorated pressure treated wood and replaced with new pressure treated wood in sizes to match existing in areas not scheduled for removal, , is specified under Section 012100 “Allowances.”

F. Allowance for the cleaning of the new TPO roof membrane, , is specified under Section 012100 “Allowances.”

1.3 UNIT PRICES

A. Work of this Section is affected by wet lightweight concrete roof deck removal and replacement with insulation unit price.

1.4 PREINSTALLATION MEETINGS

A. Preliminary Roofing Conference: Before starting removal Work, conduct conference at Project site.

Page 160: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

070150.19 Page 2

UCA Mashburn Hall Reroofing and PREPARATION FOR REROOFING Deck Replacement SMA #1505H

1.5 FIELD CONDITIONS

A. Existing Roofing System: Modified bituminous roofing.

B. Owner will occupy portions of building immediately below reroofing area.

1. Conduct reroofing so Owner's operations are not disrupted. 2. Provide Owner with not less than 72 hours' written notice of activities that may affect

Owner's operations. 3. Coordinate work activities daily with Owner so Owner has adequate advance notice to

place protective dust and water-leakage covers over sensitive equipment and furnishings, shut down HVAC and fire-alarm or -detection equipment if needed, and evacuate occupants from below work area.

4. Before working over structurally impaired areas of deck, notify Owner to evacuate occupants from below affected area.

a. Verify that occupants below work area have been evacuated before proceeding with work over impaired deck area.

C. Protect building to be reroofed, adjacent buildings, walkways, site improvements, exterior plantings, and landscaping from damage or soiling from reroofing operations.

D. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.

E. Conditions existing at time of inspection for bidding will be maintained by Owner as far as practical.

1. The results of an analysis of test cores from existing roofing system are available for Contractor's reference.

F. Weather Limitations: Proceed with reroofing preparation only when existing and forecasted weather conditions permit Work to proceed without water entering existing roofing system or building.

1. Remove only as much roofing in one day as can be made watertight in the same day.

1.6 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during reroofing, by methods and with materials so as not to void existing roofing system warranty.

Page 161: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

070150.19 Page 3

UCA Mashburn Hall Reroofing and PREPARATION FOR REROOFING Deck Replacement SMA #1505H

PART 2 - PRODUCTS

2.1 AUXILIARY REROOFING MATERIALS

A. General: Use auxiliary reroofing preparation materials recommended by roofing system manufacturer for intended use and compatible with components of existing and new roofing system.

PART 3 - EXECUTION

3.1 PREPARATION

A. Seal or isolate windows that may be exposed to airborne substances created in removal of existing materials.

B. Shut off rooftop utilities and service piping before beginning the Work.

C. Test existing roof drains to verify that they are not blocked or restricted.

1. Immediately notify Architect of any blockages or restrictions.

D. Coordinate with Owner to shut down air-intake equipment in the vicinity of the Work.

1. Cover air-intake louvers before proceeding with reroofing work that could affect indoor air quality or activate smoke detectors in the ductwork.

E. During removal operations, have sufficient and suitable materials on-site to facilitate rapid installation of temporary protection in the event of unexpected rain.

F. Maintain roof drains in functioning condition to ensure roof drainage at end of each workday.

1. Prevent debris from entering or blocking roof drains and conductors.

a. Use roof-drain plugs specifically designed for this purpose. b. Remove roof-drain plugs at end of each workday, when no work is taking place, or

when rain is forecast.

2. If roof drains are temporarily blocked or unserviceable due to roofing system removal or partial installation of new roofing system, provide alternative drainage method to remove water and eliminate ponding.

a. Do not permit water to enter into or under existing roofing system components that are to remain.

Page 162: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

070150.19 Page 4

UCA Mashburn Hall Reroofing and PREPARATION FOR REROOFING Deck Replacement SMA #1505H

3.2 ROOF TEAR-OFF

A. Notify Owner each day of extent of roof tear-off proposed for that day and obtain authorization to proceed.

B. Lower removed roofing materials to ground and onto lower roof levels, using dust-tight chutes or other acceptable means of removing materials from roof areas.

C. Full Roof Tear-off: Where indicated on Drawings, remove existing roofing and other roofing system components down to the existing roof metal deck or to the lightweight concrete deck as indicated.

1. Remove base flashings and counter flashings. 2. Remove perimeter edge flashing and gravel stops. 3. Remove copings. 4. Remove expansion-joint covers. 5. Remove flashings at pipes, curbs, mechanical equipment, and other penetrations. 6. Remove roof drains indicated on Drawings to be removed. 7. Remove wood blocking, curbs, and nailers where indicated. 8. Remove excess asphalt from steel deck.

a. A maximum of 15 lb/100 sq. ft. of asphalt is permitted to remain on steel decks.

9. Remove fasteners from deck or cut fasteners off slightly above deck surface.

3.3 DECK PREPARATION

A. Inspect lightweight concrete deck after tear-off of roofing system.

B. Inspect metal deck in areas where lightweight concrete has been removed.

C. If broken or loose fasteners that secure deck panels to one another or to structure are observed, or if deck appears or feels inadequately attached, immediately notify Architect.

1. Do not proceed with installation until directed by Architect.

D. If deck surface is unsuitable for receiving new roofing or if structural integrity of deck is suspect, immediately notify Architect.

1. Do not proceed with installation until directed by Architect.

3.4 BASE FLASHING REMOVAL

A. Remove existing base flashings.

1. Clean substrates of contaminants, such as asphalt, sheet materials, dirt, and debris.

B. Do not damage metal counterflashings that are to remain.

Page 163: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

070150.19 Page 5

UCA Mashburn Hall Reroofing and PREPARATION FOR REROOFING Deck Replacement SMA #1505H

1. Replace metal counterflashings damaged during removal with counterflashings specified in Section 076200 "Sheet Metal Flashing and Trim."

C. Inspect parapet sheathing, wood blocking, curbs, and nailers for deterioration and damage.

1. If parapet sheathing, wood blocking, curbs, or nailers have deteriorated, immediately notify Architect.

D. When directed by Architect, replace parapet framing, wood blocking, curbs, and nailers to comply with Section 061053 Miscellaneous Rough Carpentry."

END OF SECTION 070150.19

Page 164: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

072100 Page 1

UCA Mashburn Hall Reroofing and THERMAL INSULATION Deck Replacement SMA #1505H

SECTION 072100 - THERMAL INSULATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Glass-fiber blanket.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

PART 2 - PRODUCTS

2.1 GLASS-FIBER BLANKET

A. Glass-Fiber Blanket, Reinforced-Foil Faced: ASTM C 665, Type III (reflective faced), Class A (faced surface with a flame-spread index of 25 or less); Category 1 (membrane is a vapor barrier), faced with foil scrim, foil-scrim kraft, or foil-scrim polyethylene.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. CertainTeed Corporation. b. Guardian Building Products, Inc. c. Johns Manville; a Berkshire Hathaway company. d. Knauf Insulation. e. Owens Corning.

2.2 ACCESSORIES

A. Insulation Anchors, Spindles, and Standoffs: As recommended by manufacturer.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Comply with insulation manufacturer's written instructions applicable to products and applications.

Page 165: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

072100 Page 2

UCA Mashburn Hall Reroofing and THERMAL INSULATION Deck Replacement SMA #1505H

B. Install insulation that is undamaged, dry, and unsoiled and that has not been left exposed to ice, rain, or snow at any time.

C. Extend insulation to envelop entire area to be insulated. Fit tightly around obstructions and fill voids with insulation. Remove projections that interfere with placement.

D. Provide sizes to fit applications and selected from manufacturer's standard thicknesses, widths, and lengths. Apply single layer of insulation units unless multiple layers are otherwise shown or required to make up total thickness or to achieve R-value.

3.2 INSTALLATION OF INSULATION IN FRAMED CONSTRUCTION

A. Miscellaneous Voids: Install insulation in miscellaneous voids and cavity spaces where required to prevent gaps in insulation using the following materials:

1. Glass-Fiber Insulation: Compact to approximately 40 percent of normal maximum volume equaling a density of approximately 2.5 lb/cu. ft..

END OF SECTION 072100

Page 166: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

075423 Page 1

UCA Mashburn Hall Reroofing and THERMOPLASTIC POLYOLEFIN (TPO) ROOFING Deck Replacement SMA #1505H

SECTION 075423 - THERMOPLASTIC POLYOLEFIN (TPO) ROOFING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

A. Adhered thermoplastic polyolefin (TPO) roofing system. B. Roof insulation. C. Cover board. D. Walkways.

1.2 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

A. For insulation and roof system component fasteners, include copy of FM Approvals' RoofNav listing.

B. Shop Drawings: Include roof plans, sections, details, and attachments to other work, including the following:

A. Layout and thickness of insulation. B. Base flashings and membrane termination details. C. Flashing details at penetrations. D. Tapered insulation layout, thickness, and slopes. E. Roof plan showing orientation of steel roof deck and orientation of roof membrane,

fastening spacings, and patterns for mechanically fastened roofing system. F. Insulation fastening patterns for corner, perimeter, and field-of-roof locations. G. Tie-in with adjoining air barrier.

C. Samples: For the following products:

A. Roof membrane and flashings, of color required. B. Walkway pads or rolls, of color required.

D. Wind Uplift Resistance Submittal: For roofing system, indicating compliance with wind uplift performance requirements.

Page 167: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

075423 Page 2

UCA Mashburn Hall Reroofing and THERMOPLASTIC POLYOLEFIN (TPO) ROOFING Deck Replacement SMA #1505H

1.4 INFORMATIONAL SUBMITTALS

A. Qualification Data: For installer and manufacturer.

B. Manufacturer Certificates:

A. Performance Requirement Certificate: Signed by roof membrane manufacturer, certifying that roofing system complies with requirements specified in "Performance Requirements" Article.

a. Submit evidence of compliance with performance requirements.

B. Special Warranty Certificate: Signed by roof membrane manufacturer, certifying that all materials supplied under this Section are acceptable for special warranty.

C. Product Test Reports: For roof membrane and insulation, for tests performed by a qualified testing agency, indicating compliance with specified requirements.

D. Field Test Reports:

A. Concrete internal relative humidity test reports. B. Fastener-pullout test results and manufacturer's revised requirements for fastener

patterns.

E. Field quality-control reports.

F. Sample warranties.

1.5 CLOSEOUT SUBMITTALS

A. Maintenance data.

B. Certified statement from existing roof membrane manufacturer stating that existing roof warranty has not been affected by Work performed under this Section.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: A qualified firm that is approved, authorized, or licensed by roofing system manufacturer to install manufacturer's product and that is eligible to receive manufacturer's special warranty.

1.7 WARRANTY

A. Special Warranty: Manufacturer agrees to repair or replace components of roofing system, covering both labor and material with no dollar limitation, that fail in materials or workmanship.

1. Warranty Period: 20 years from date of Substantial Completion.

Page 168: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

075423 Page 3

UCA Mashburn Hall Reroofing and THERMOPLASTIC POLYOLEFIN (TPO) ROOFING Deck Replacement SMA #1505H

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Accelerated Weathering: Roof membrane shall withstand 2000 hours of exposure when tested according to ASTM G 152, ASTM G 154, or ASTM G 155.

B. Impact Resistance: Roof membrane shall resist impact damage when tested according to ASTM D 3746, ASTM D 4272, or the "Resistance to Foot Traffic Test" in FM Approvals 4470.

C. Wind Uplift Resistance: Design roofing system to resist the following wind uplift pressures when tested according to FM Approvals 4474 or UL 1897:

A. Zone 1 (Roof Area Field): 55.0 lbf/sq. ft. B. Zone 2 (Roof Area Perimeter): 83.0 lbf/sq. ft.

a. Location: From roof edge to 3’-0” inside roof edge at metal deck. b. Location: From roof edge to 12’-0” inside roof edge at lightweight insulating

concrete decks.

C. Zone 3 (Roof Area Corners): 119.0 lbf/sq. ft..

a. Location: From roof edge to 3’-0” inside roof edge at metal deck. b. Location: From roof edge to 12’-0” inside roof edge at lightweight insulating

concrete decks.

D. FM Approvals' RoofNav Listing: Roof membrane, base flashings, and component materials shall comply with requirements in FM Approvals 4450 or FM Approvals 4470 as part of a roofing system, and shall be listed in FM Approvals' RoofNav for Class 1 or noncombustible construction, as applicable. Identify materials with FM Approvals Certification markings.

A. Hail-Resistance Rating: SH.

E. Energy Performance: Roofing system shall have an initial solar reflectance of not less than 0.79 and an emissivity of not less than 0.90 when tested according to CRRC-1.

F. Exterior Fire-Test Exposure: ASTM E 108 or UL 790, Class A; for application and roof slopes indicated; testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

G. Fire-Resistance Ratings: Comply with fire-resistance-rated assembly designs indicated. Identify products with appropriate markings of applicable testing agency.

2.2 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING

A. TPO Sheet: ASTM D 6878/D 6878M, internally fabric- or scrim-reinforced, fleece-backed TPO sheet.

Page 169: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

075423 Page 4

UCA Mashburn Hall Reroofing and THERMOPLASTIC POLYOLEFIN (TPO) ROOFING Deck Replacement SMA #1505H

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Carlisle SynTec Incorporated. b. Firestone Building Products. c. Johns Manville; a Berkshire Hathaway company. d. GAF Material Corporation

B. Thickness: 135 mils, nominal. C. Exposed Face Color: White.

2.3 AUXILIARY ROOFING MATERIALS

A. General: Auxiliary materials recommended by roofing system manufacturer for intended use and compatible with other roofing components.

A. Adhesive and Sealants: Comply with VOC limits of authorities having jurisdiction.

B. Sheet Flashing: Manufacturer's standard unreinforced TPO sheet flashing, 60 mils thick, minimum, of same color as TPO sheet.

C. Prefabricated Pipe Flashings: As recommended by roof membrane manufacturer.

D. Roofing Adhesive: Roofing manufacturer's recommended adhesive formulated to attach roof membrane to substrate.

E. Bonding Adhesive: Manufacturer's standard one-component, low-viscosity, self wetting, butyl blend mastic used to prevent moisture migration at drains, compression terminations and beneath metal edging.

F. Water Cut-Off Mastic: Manufacturer's standard.

G. Primer: Manufacturer’s standard primer specially formulated for priming lightweight concrete deck prior to applying adhesive for insulation attachment.

H. Metal Termination Bars: Manufacturer's standard, predrilled stainless steel or aluminum bars, approximately 1 by 1/8 inch thick; with anchors.

I. Fasteners: Factory-coated steel fasteners and metal or plastic plates complying with corrosion-resistance provisions in FM Approvals 4470, designed for fastening roofing components to substrate, and acceptable to roofing system manufacturer.

J. Sealants: Manufacturer’s standard one-part polyether sealant.

K. Miscellaneous Accessories: Provide primers, pourable sealers, preformed cone and vent sheet flashings, preformed inside and outside corner sheet flashings, T-joint covers, lap sealants, termination reglets, preformed expansion joint supports and other accessories.

Page 170: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

075423 Page 5

UCA Mashburn Hall Reroofing and THERMOPLASTIC POLYOLEFIN (TPO) ROOFING Deck Replacement SMA #1505H

2.4 ROOF INSULATION

A. Polyisocyanurate Board Insulation: ASTM C 1289, Type II, Class 1, Grade 2, felt or glass-fiber mat facer on both major surfaces.

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Carlisle SynTec Incorporated. b. Firestone Building Products. c. Johns Manville; a Berkshire Hathaway company.

B. Size: 48 by 96 inches. C. Thickness:

a. Base Layer: As indicated on Drawings. b. Upper Layer: As indicated on Drawings.

B. Tapered Insulation: Provide factory-tapered insulation boards.

A. Material: Match roof insulation. B. Minimum Thickness: 1/2 inch. C. Slope:

a. Roof Field: 1/4 inch per foot unless otherwise indicated on Drawings. b. Saddles and Crickets: 1/2 inch per foot unless otherwise indicated on Drawings.

2.5 INSULATION ACCESSORIES

A. Fasteners: Factory-coated steel fasteners with metal or plastic plates complying with corrosion-resistance provisions in FM Approvals 4470, designed for fastening roof insulation and cover boards to substrate, and acceptable to roofing system manufacturer.

B. Insulation Adhesive: Insulation manufacturer's recommended adhesive formulated to attach roof insulation to substrate or to another insulation layer as follows:

A. Bead-applied, low-rise, one-component or multicomponent urethane adhesive.

C. Cover Board: ASTM C 1177/C 1177M, glass-mat, water-resistant gypsum board or ASTM C 1278/C 1278M fiber-reinforced gypsum board.

A. Products: Subject to compliance with requirements, provide one of the following:

a. Georgia-Pacific Building Products; Dens Deck Prime. b. USG Corporation; Securock Gypsum Fiber Roof Board.

B. Thickness: 5/8 inch.

C. Surface Finish: Primed.

Page 171: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

075423 Page 6

UCA Mashburn Hall Reroofing and THERMOPLASTIC POLYOLEFIN (TPO) ROOFING Deck Replacement SMA #1505H

D. Protection Mat: Woven or nonwoven polypropylene, polyolefin, or polyester fabric; water permeable and resistant to UV degradation; type and weight as recommended by roofing system manufacturer for application.

2.6 WALKWAYS

A. Flexible Walkways: Factory-formed, nonporous, heavy-duty, slip-resisting, surface-textured walkway rolls, approximately 3/16 inch thick and acceptable to roofing system manufacturer.

A. Size: Approximately 36 by 60 inches. B. Color: Contrasting with roof membrane.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements and other conditions affecting performance of the Work.

A. Verify that minimum concrete drying period recommended by roofing system manufacturer has passed.

B. Verify that concrete substrate is visibly dry and free of moisture, and that minimum concrete internal relative humidity is not more than 75 percent, or as recommended by roofing system manufacturer, when tested according to ASTM F 2170.

a. Test Frequency: One test probe per each 1000 sq. ft., or portion thereof, of roof deck, with not less than three tests probes.

b. Submit test reports within 24 hours after performing tests.

3.2 PREPARATION

A. Perform fastener-pullout tests according to roof system manufacturer's written instructions.

A. Submit test result within 24 hours after performing tests.

a. Include manufacturer's requirements for any revision to previously submitted fastener patterns required to achieve specified wind uplift requirements.

3.3 ROOFING INSTALLATION, GENERAL

A. Install roofing system according to roofing system manufacturer's written instructions, FM Approvals' RoofNav assembly requirements, and FM Global Property Loss Prevention Data Sheet 1-29.

Page 172: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

075423 Page 7

UCA Mashburn Hall Reroofing and THERMOPLASTIC POLYOLEFIN (TPO) ROOFING Deck Replacement SMA #1505H

B. Complete terminations and base flashings and provide temporary seals to prevent water from entering completed sections of roofing system at end of workday or when rain is forecast. Remove and discard temporary seals before beginning Work on adjoining roofing.

C. Install roof membrane and auxiliary materials to tie in to existing roofing to maintain weathertightness of transition and to not void warranty for existing roofing system.

3.4 INSULATION INSTALLATION

A. Coordinate installing roofing system components so insulation is not exposed to precipitation or left exposed at end of workday.

B. Comply with roofing system and roof insulation manufacturer's written instructions for installing roof insulation.

C. Installation Over Metal Decking:

A. Install base layer of insulation with end joints staggered not less than 12 inches in adjacent rows and with long joints continuous at right angle to flutes of decking.

a. Locate end joints over crests of decking. b. Trim insulation neatly to fit around penetrations and projections, and to fit tight to

intersecting sloping roof decks. c. Make joints between adjacent insulation boards not more than 1/4 inch in width. d. At internal roof drains, slope insulation to create a square drain sump with each

side equal to the diameter of the drain bowl plus 24 inches.

1) Trim insulation so that water flow is unrestricted.

e. Fill gaps exceeding 1/4 inch with insulation. f. Cut and fit insulation within 1/4 inch of nailers, projections, and penetrations. g. Mechanically attach base layer of insulation using mechanical fasteners

specifically designed and sized for fastening specified board-type roof insulation to metal decks.

1) Fasten insulation to resist specified uplift pressure at corners, perimeter, and field of roof.

B. Install upper layers of insulation and tapered insulation with joints of each layer offset not less than 12 inches from previous layer of insulation.

a. Install with long joints continuous and with end joints staggered not less than 12 inches in adjacent rows.

b. Trim insulation neatly to fit around penetrations and projections, and to fit tight to intersecting sloping roof decks.

c. Make joints between adjacent insulation boards not more than 1/4 inch in width. d. At internal roof drains, slope insulation to create a square drain sump with each

side equal to the diameter of the drain bowl plus 24 inches.

1) Trim insulation so that water flow is unrestricted.

Page 173: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

075423 Page 8

UCA Mashburn Hall Reroofing and THERMOPLASTIC POLYOLEFIN (TPO) ROOFING Deck Replacement SMA #1505H

e. Fill gaps exceeding 1/4 inch with insulation. f. Cut and fit insulation within 1/4 inch of nailers, projections, and penetrations. g. Adhere each layer of insulation to substrate using adhesive to resist specified uplift

pressure at corners, perimeter, and field of roof, as follows:

1) Set each layer of insulation in ribbons of bead-applied insulation adhesive, firmly pressing and maintaining insulation in place.

D. Installation Over Lightweight Concrete Decks:

A. Prime surface of lightweight concrete deck with manufacturer’s recommended primer in accordance with manufacturer’s installation instructions, and allow primer to dry

B. Install base layer of insulation with end joints staggered not less than 12 inches in adjacent rows.

a. Trim insulation neatly to fit around penetrations and projections, and to fit tight to intersecting sloping roof decks.

b. Make joints between adjacent insulation boards not more than 1/4 inch in width. c. At internal roof drains, slope insulation to create a square drain sump with each

side equal to the diameter of the drain bowl plus 24 inches.

1) Trim insulation so that water flow is unrestricted.

d. Fill gaps exceeding 1/4 inch with insulation. e. Cut and fit insulation within 1/4 inch of nailers, projections, and penetrations. f. Adhere base layer of insulation to lightweight concrete roof deck using adhesive to

resist specified uplift pressure at corners, perimeter, and field of roof, as follows:

1) Set each layer of insulation in ribbons of bead-applied insulation adhesive, firmly pressing and maintaining insulation in place.

C. Install upper layers of insulation and tapered insulation with joints of each layer offset not less than 12 inches from previous layer of insulation.

a. Install with long joints continuous and with end joints staggered not less than 12 inches in adjacent rows.

b. Trim insulation neatly to fit around penetrations and projections, and to fit tight to intersecting sloping roof decks.

c. Make joints between adjacent insulation boards not more than 1/4 inch in width. d. At internal roof drains, slope insulation to create a square drain sump with each

side equal to the diameter of the drain bowl plus 24 inches.

1) Trim insulation so that water flow is unrestricted.

e. Fill gaps exceeding 1/4 inch with insulation. f. Cut and fit insulation within 1/4 inch of nailers, projections, and penetrations. a. Adhere each layer of insulation to substrate using adhesive to resist specified uplift

pressure at corners, perimeter, and field of roof, as follows:

1) Set each layer of insulation in ribbons of bead-applied insulation adhesive, firmly pressing and maintaining insulation in place.

Page 174: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

075423 Page 9

UCA Mashburn Hall Reroofing and THERMOPLASTIC POLYOLEFIN (TPO) ROOFING Deck Replacement SMA #1505H

3.5 INSTALLATION OF COVER BOARDS

A. Install cover boards over insulation with long joints in continuous straight lines with end joints staggered between rows. Offset joints of insulation below a minimum of 6 inches in each direction.

A. Trim cover board neatly to fit around penetrations and projections, and to fit tight to intersecting sloping roof decks.

B. At internal roof drains, conform to slope of drain sump.

a. Trim cover board so that water flow is unrestricted.

C. Cut and fit cover board tight to nailers, projections, and penetrations. D. Adhere cover board to substrate using adhesive to resist specified uplift pressure at

corners, perimeter, and field of roof, as follows:

1) Set each layer of insulation in ribbons of bead-applied insulation adhesive, firmly pressing and maintaining insulation in place.

3.6 ADHERED ROOFING INSTALLATION

A. Adhere roof membrane over area to receive roofing according to roofing system manufacturer's written instructions.

B. Unroll roof membrane and allow to relax before installing.

C. Start installation of roofing in presence of roofing system manufacturer's technical personnel.

D. Accurately align roof membrane, and maintain uniform side and end laps of minimum dimensions required by manufacturer. Stagger end laps.

E. Bonding Adhesive: Apply to substrate and underside of roof membrane at rate required by manufacturer, and allow to partially dry before installing roof membrane. Do not apply to splice area of roof membrane.

F. Fabric-Backed Roof Membrane Adhesive: Apply to substrate at rate required by manufacturer, and install fabric-backed roof membrane.

G. In addition to adhering, mechanically fasten roof membrane securely at terminations, penetrations, and perimeter of roofing.

H. Apply roof membrane with side laps shingled with slope of roof deck where possible.

I. Seams: Clean seam areas, overlap roof membrane, and hot-air weld side and end laps of roof membrane and sheet flashings, to ensure a watertight seam installation.

A. Test lap edges with probe to verify seam weld continuity. Apply lap sealant to seal cut edges of roof membrane and sheet flashings.

B. Verify field strength of seams a minimum of twice daily, and repair seam sample areas.

Page 175: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

075423 Page 10

UCA Mashburn Hall Reroofing and THERMOPLASTIC POLYOLEFIN (TPO) ROOFING Deck Replacement SMA #1505H

C. Repair tears, voids, and lapped seams in roof membrane that do not comply with requirements.

J. Spread sealant bed over deck-drain flange at roof drains, and securely seal roof membrane in place with clamping ring.

3.7 BASE FLASHING INSTALLATION

A. Install sheet flashings and preformed flashing accessories, and adhere to substrates according to roofing system manufacturer's written instructions.

B. Apply bonding adhesive to substrate and underside of sheet flashing at required rate, and allow to partially dry. Do not apply to seam area of flashing.

C. Flash penetrations and field-formed inside and outside corners with cured or uncured sheet flashing.

D. Clean seam areas, overlap, and firmly roll sheet flashings into the adhesive. Hot-air weld side and end laps to ensure a watertight seam installation.

E. Terminate and seal top of sheet flashings and mechanically anchor to substrate through termination bars.

3.8 WALKWAY INSTALLATION

A. Flexible Walkways:

A. Install flexible walkways at the following locations:

a. Locations indicated on Drawings.

B. Provide 6-inch clearance between adjoining pads. C. Heat weld to substrate or adhere walkway products to substrate with compatible

adhesive according to roofing system manufacturer's written instructions.

3.9 PROTECTING AND CLEANING

A. Protect roofing system from damage and wear during remainder of construction period. When remaining construction does not affect or endanger roofing system, inspect roofing system for deterioration and damage, describing its nature and extent in a written report, with copies to Architect and Owner.

B. Correct deficiencies in or remove roofing system that does not comply with requirements, repair substrates, and repair or reinstall roofing system to a condition free of damage and deterioration at time of Substantial Completion and according to warranty requirements.

C. Clean overspray and spillage from adjacent construction using cleaning agents and procedures recommended by manufacturer of affected construction.

Page 176: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

075423 Page 11

UCA Mashburn Hall Reroofing and THERMOPLASTIC POLYOLEFIN (TPO) ROOFING Deck Replacement SMA #1505H

END OF SECTION 075423

Page 177: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

077100 Page 1

UCA Mashburn Hall Reroofing and ROOF SPECIALTIES Deck Replacement SMA #1505H

SECTION 077100 - ROOF SPECIALTIES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Copings. 2. Roof-Edge Fascia’s. 3. Vent Pipe Extensions

B. Preinstallation Conference: Conduct conference at Project site.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings: For roof specialties.

1. Include plans, elevations, expansion-joint locations, keyed details, and attachments to other work. Distinguish between plant- and field-assembled work.

C. Samples: For each type of roof specialty and for each color and texture specified.

1.3 INFORMATIONAL SUBMITTALS

A. Product Test Reports: For tests performed by a qualified testing agency.

B. Sample warranty.

1.4 CLOSEOUT SUBMITTALS

A. Maintenance Data: For roofing specialties to include in maintenance manuals.

1.5 QUALITY ASSURANCE

A. Manufacturer Qualifications: A qualified manufacturer offering products meeting requirements that are SPRI ES-1 tested to specified design pressure.

Page 178: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

077100 Page 2

UCA Mashburn Hall Reroofing and ROOF SPECIALTIES Deck Replacement SMA #1505H

1.6 WARRANTY

A. Special Warranty on Painted Finishes: Manufacturer agrees to repair finish or replace roof specialties that show evidence of deterioration of factory-applied finishes within specified warranty period.

1. Fluoropolymer Finish: Deterioration includes, but is not limited to, the following:

a. Color fading more than 5 Hunter units when tested according to ASTM D 2244. b. Chalking in excess of a No. 8 rating when tested according to ASTM D 4214. c. Cracking, checking, peeling, or failure of paint to adhere to bare metal.

2. Finish Warranty Period: 20 years from date of Substantial Completion.

B. Special Warranty for Wind: Manufacturer agrees to repair or replace edge metal for wind conditions up to 110 mph.

1. Wind Warranty Period: 20 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. SPRI Wind Design Standard: Manufacture and install copings tested according to SPRI ES-1 and capable of resisting the following design pressures:

1. Outward (horizontal) design pressure:

a. Perimeter: 47.2 lbf/sq. ft. b. Corners: 109.9 lbf/sq. ft.

2. Upward (vertical) design pressure:

a. Perimeter: 73.1 lbf/sq. ft. b. Corners: 109.9 lbf/sq. ft.

B. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes to prevent buckling, opening of joints, hole elongation, overstressing of components, failure of joint sealants, failure of connections, and other detrimental effects. Provide clips that resist rotation and avoid shear stress as a result of thermal movements. Base calculations on surface temperatures of materials due to both solar heat gain and nighttime-sky heat loss.

1. Temperature Change (Range): 120 deg F, ambient; 180 deg F, material surfaces.

Page 179: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

077100 Page 3

UCA Mashburn Hall Reroofing and ROOF SPECIALTIES Deck Replacement SMA #1505H

2.2 COPINGS

A. Metal Copings: Manufactured coping system consisting of metal coping cap in section lengths not exceeding 10 feet, concealed anchorage; with corner units, end cap units, and concealed splice plates with finish matching coping caps.

1. Basis-of-Design Product: Subject to compliance with requirements, provide OMG Roofing Products.; “PermaSnap Coping” or comparable product by one of the following:

a. Garland Company, Inc. (The); “R-Mer Edge Coping”. b. Metal-Era Inc. c. Petersen Aluminum Corporation.

2. Metallic-Coated Steel Sheet Coping Caps: Zinc-coated (galvanized) steel, nominal 0.034-inch (22 gauge) thickness and as required to meet performance requirements.

a. Surface: Smooth, flat finish. b. Finish: Two-coat fluoropolymer. c. Color: As selected by Architect from manufacturer's full range.

3. Corners: Factory mitered and continuously welded. 4. Coping-Cap Attachment Method: Snap-on, fabricated from galvanized steel.

a. Snap-on Coping Anchor Plates: Concealed, 20 gauge galvanized-steel sheet, 12 incheswide, with integral cleats.

2.3 ROOF-EDGE SPECIALTIES

A. Canted Roof-Edge Fascia: Manufactured, two-piece, roof-edge fascia consisting of snap-on metal fascia cover in section lengths not exceeding 10 feet and a continuous formed galvanized-steel sheet cant, 0.028 inch thick, minimum, with extended vertical leg terminating in a drip-edge cleat. Provide matching corner units.

1. Basis-of-Design Product: Subject to compliance with requirements, OMG Roofing Product; “Econosnap” Fascia System, or a comparable product by one of the following:

a. Garland Company, Inc. (The); “R-Mer Edge Fascia”. b. Petersen Aluminum Corporation; “PAC-LOC Fascia 2000”. c. Metal-Era, Inc. “Edge Systems One”

2. Metallic-Coated Steel Sheet Fascia Covers: Zinc-coated (galvanized) steel, nominal 0.034-inch (22 gauge) thickness.

a. Surface: Smooth, flat finish. b. Finish: Two-coat fluoropolymer. c. Color: As selected by Architect from manufacturer's full range.

3. Corners: Factory mitered and continuously welded. 4. Splice Plates: Concealed, of same material, finish, and shape as fascia cover.

Page 180: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

077100 Page 4

UCA Mashburn Hall Reroofing and ROOF SPECIALTIES Deck Replacement SMA #1505H

2.4 MATERIALS

A. Zinc-Coated (Galvanized) Steel Sheet: ASTM A 653/A 653M, G90 coating designation.

2.5 MISCELLANEOUS MATERIALS

A. Fasteners: Manufacturer's recommended fasteners, suitable for application and designed to meet performance requirements. Furnish the following unless otherwise indicated:

1. Exposed Penetrating Fasteners: Gasketed screws with hex washer heads matching color of sheet metal.

2. Fasteners for Zinc-Coated (Galvanized) Steel Sheet: Series 300 stainless steel or hot-dip zinc-coated steel according to ASTM A 153/A 153M or ASTM F 2329.

B. Elastomeric Sealant: ASTM C 920, elastomeric silicone polymer sealant of type, grade, class, and use classifications required by roofing-specialty manufacturer for each application.

C. Butyl Sealant: ASTM C 1311, single-component, solvent-release butyl rubber sealant; polyisobutylene plasticized; heavy bodied for hooked-type joints with limited movement.

D. Bituminous Coating: Cold-applied asphalt emulsion complying with ASTM D 1187/D 1187M.

E. Asphalt Roofing Cement: ASTM D 4586, asbestos free, of consistency required for application.

2.6 FINISHES

A. Coil-Coated Galvanized-Steel Sheet Finishes:

1. High-Performance Organic Finish: Prepare, pretreat, and apply coating to exposed metal surfaces to comply with ASTM A 755/A 755M and coating and resin manufacturers' written instructions.

a. Two-Coat Fluoropolymer: AAMA 621. Fluoropolymer finish containing not less than 70 percent PVDF resin by weight in color coat.

2.7 VENT PIPE EXTENSIONS

A. Roof Vent Pipe Extensions: Solid-wall PVC fitting consisting of pipe and splice sleeve inserts, configured for insertion and sealing to existing plumbing vent piping, sized to fit inside diameter of plumbing vent piping, enabling extension of piping:

1. Basis-of-Design Product: Subject to compliance with requirements, provide

“OMG, inc. Tubos” vent pipe extension or a comparable product:

2. Size: Sizes vary, field verify.

3. Material: Solid-wall PVC, white.

Page 181: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

077100 Page 5

UCA Mashburn Hall Reroofing and ROOF SPECIALTIES Deck Replacement SMA #1505H

4. Splice Sleeve Insert”

a. 6 inches

5. Sealant: Single component, non-sag, urethane joint sealant: ASTM C 920, Type S, Grade NS, Class 25 and acceptable to roofing membrane manufacturer.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. General: Install roof specialties according to manufacturer's written instructions. Anchor roof specialties securely in place, with provisions for thermal and structural movement. Use fasteners, protective coatings, separators, sealants, and other miscellaneous items as required to complete roof-specialty systems.

1. Install roof specialties level, plumb, true to line and elevation; with limited oil-canning and without warping, jogs in alignment, buckling, or tool marks.

2. Provide uniform, neat seams with minimum exposure of solder and sealant. 3. Install roof specialties to fit substrates and to result in weathertight performance. Verify

shapes and dimensions of surfaces to be covered before manufacture. 4. Torch cutting of roof specialties is not permitted. 5. Do not use graphite pencils to mark metal surfaces.

B. Metal Protection: Protect metals against galvanic action by separating dissimilar metals from contact with each other or with corrosive substrates by painting contact surfaces with bituminous coating or by other permanent separation as recommended by manufacturer.

C. Expansion Provisions: Allow for thermal expansion of exposed roof specialties.

1. Space movement joints at a maximum of 10 feet with no joints within 18 inches of corners or intersections unless otherwise indicated on Drawings.

2. When ambient temperature at time of installation is between 40 and 70 deg F, set joint members for 50 percent movement each way. Adjust setting proportionately for installation at higher ambient temperatures.

D. Fastener Sizes: Use fasteners of sizes that penetrate substrate not less than recommended by fastener manufacturer to achieve maximum pull-out resistance.

E. Seal concealed joints with butyl sealant as required by roofing-specialty manufacturer.

F. Seal joints as required for weathertight construction. Place sealant to be completely concealed in joint. Do not install sealants at temperatures below 40 deg F.

3.2 COPING INSTALLATION

A. Install cleats, anchor plates, and other anchoring and attachment accessories and devices with concealed fasteners.

Page 182: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

077100 Page 6

UCA Mashburn Hall Reroofing and ROOF SPECIALTIES Deck Replacement SMA #1505H

B. Anchor copings with manufacturer's required devices, fasteners, and fastener spacing to meet performance requirements.

1. Interlock face-leg and back-leg drip edge into continuous cleat anchored to substrate at manufacturer's required spacing that meets performance requirements.

3.3 ROOF-EDGE SPECIALITIES INSTALLATION

A. Install cleats, cants, and other anchoring and attachment accessories and devices with concealed fasteners.

B. Anchor roof edgings with manufacturer's required devices, fasteners, and fastener spacing to meet performance requirements.

3.4 VENT PIPE EXTESION INSTALLATION

A. Examination 1. Examine each plumbing vent piping location to determine required plumbing vent pipe

extensions based upon minimum finished height requirements and measured existing conditions. Indicate plumbing vent pipe extensions on shop drawings.

2. Notify Architect of conditions that would adversely affect installation or subsequent use. 3. Do not begin installation until unacceptable conditions are corrected.

B. Preparation 1. Remove existing flashing from plumbing vent piping to extent required to enable

installation of new plumbing vent pipe extensions and completion of flashings. 2. Clean plumbing vent piping to ensure that joint surfaces are clean, dry, and free from

contamination including dirt, oils, grease, tar, wax, rust, and other substances that may inhibit adhesive or sealant performance.

C. Installation 1. Insert end of plumbing vent pipe extension into existing plumbing vent piping.

a. Verify circumference of existing plumbing vent piping and plumbing vent pipe extension is appropriate to achieve secure, rigid installation.

b. Mark plumbing vent pipe extension at required height above finished roof surface level, and cut to required length.

c. Apply adhesive or sealant to plumbing vent piping as appropriate to existing pipe material and plumbing vent pipe extension, and mate plumbing vent pipe extension to existing piping. Apply adequate adhesive or sealant to achieve secure, rigid installation.

2. Flashing: Comply with primary roofing material manufacturer’s published recommendations for installation of approved pipe flashings. Match existing flashing materials unless otherwise directed.

Page 183: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

077100 Page 7

UCA Mashburn Hall Reroofing and ROOF SPECIALTIES Deck Replacement SMA #1505H

3.5 CLEANING AND PROTECTION

A. Clean exposed metal surfaces of substances that interfere with uniform oxidation and weathering.

B. Clean and neutralize flux materials. Clean off excess solder and sealants.

C. Remove temporary protective coverings and strippable films as roof specialties are installed.

END OF SECTION 077100

Page 184: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

079200 Page 1

UCA Mashburn Hall Reroofing and JOINT SEALANTS Deck Replacement SMA #1505H

SECTION 079200 - JOINT SEALANTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Silicone joint sealants.

1.2 SUBMITTALS

A. Product Data: For each joint-sealant product indicated.

B. Samples: For each kind and color of joint sealant required.

C. Joint-Sealant Schedule: Include the following information:

1. Joint-sealant application, joint location, and designation. 2. Joint-sealant manufacturer and product name. 3. Joint-sealant formulation. 4. Joint-sealant color.

D. Product test reports.

E. Warranties.

1.3 QUALITY ASSURANCE

A. Preinstallation Conference: Conduct conference at Project site.

1.4 WARRANTY

A. Special Installer's Warranty: Manufacturer's standard form in which Installer agrees to repair or replace joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: Two years from date of Substantial Completion.

B. Special Manufacturer's Warranty: Manufacturer's standard form in which joint-sealant manufacturer agrees to furnish joint sealants to repair or replace those that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: 20 years from date of Substantial Completion.

Page 185: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

079200 Page 2

UCA Mashburn Hall Reroofing and JOINT SEALANTS Deck Replacement SMA #1505H

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Structural-Sealant Joints:

1. Designed to produce tensile or shear stress of less than 20 psi (138 kPa).

B. Structural Sealant: Capable of withstanding tensile and shear stresses imposed by structural-sealant-glazed canopy glazing without failing adhesively or cohesively. When tested for preconstruction adhesion and compatibility, cohesive failure of sealant shall occur before adhesive failure.

1. Adhesive failure occurs when sealant pulls away from substrate cleanly, leaving no sealant material behind.

2. Cohesive failure occurs when sealant breaks or tears within itself but does not separate from each substrate because sealant-to-substrate bond strength exceeds sealant's internal strength.

2.2 MATERIALS, GENERAL

A. Liquid-Applied Joint Sealants: Comply with ASTM C 920 and other requirements indicated for each liquid-applied joint sealant specified, including those referencing ASTM C 920 classifications for type, grade, class, and uses related to exposure and joint substrates.

B. Stain-Test-Response Characteristics: Where sealants are specified to be nonstaining to porous substrates, provide products that have undergone testing according to ASTM C 1248 and have not stained porous joint substrates indicated for Project.

2.3 SILICONE JOINT SEALANTS

A. Neutral-Curing Silicone Joint Sealant SS-1: ASTM C 920.

1. Basis-of-Design Product: Subject to compliance with requirements, provide Dow Corning Corporation “790” Silicone Sealant or comparable product by one of the following:

a. GE Advanced Materials - Silicones. b. Pecora Corporation. c. Sika Corporation; Construction Products Division. d. Tremco Incorporated.

2. Type: Single component (S). 3. Grade: Nonsag (NS). 4. Class: 100/50. 5. Uses Related to Exposure: Nontraffic (NT).

B. Neutral-Curing Silicone Joint Sealant SS-2: ASTM C 920.

Page 186: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

079200 Page 3

UCA Mashburn Hall Reroofing and JOINT SEALANTS Deck Replacement SMA #1505H

1. Basis-of-Design Product: Subject to compliance with requirements, provide Dow Corning Corporation “795” Silicone Sealant or comparable product by one of the following:

a. GE Advanced Materials - Silicones. b. Pecora Corporation. c. Sika Corporation; Construction Products Division. d. Tremco Incorporated.

2. Type: Single component (S). 3. Grade: Nonsag (NS). 4. Class: 50. 5. Uses Related to Exposure: Nontraffic (NT).

2.4 JOINT SEALANT BACKING

A. Cylindrical Sealant Backings: ASTM C 1330, Type C (closed-cell material with a surface skin) Type O (open-cell material) Type B (bicellular material with a surface skin) or any of the preceding types, as approved in writing by joint-sealant manufacturer for joint application indicated, and of size and density to control sealant depth and otherwise contribute to producing optimum sealant performance.

B. Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant manufacturer.

2.5 MISCELLANEOUS MATERIALS

A. Primer: Material recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.

B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials.

C. Masking Tape: Nonstaining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints.

PART 3 - EXECUTION

3.1 PREPARATION

A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with joint-sealant manufacturer's written instructions.

1. Remove laitance and form-release agents from concrete. 2. Clean nonporous joint substrate surfaces with chemical cleaners or other means that do

not stain, harm substrates, or leave residues capable of interfering with adhesion of joint sealants.

Page 187: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

079200 Page 4

UCA Mashburn Hall Reroofing and JOINT SEALANTS Deck Replacement SMA #1505H

B. Joint Priming: Prime joint substrates where recommended by joint-sealant manufacturer or as indicated by preconstruction joint-sealant-substrate tests or prior experience. Apply primer to comply with joint-sealant manufacturer's written instructions. Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining surfaces.

C. Masking Tape: Use masking tape where required to prevent contact of sealant or primer with adjoining surfaces that otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears. Remove tape immediately after tooling without disturbing joint seal.

3.2 INSTALLATION

A. Sealant Installation Standard: Comply with recommendations in ASTM C 1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.

B. Install sealant backings of kind indicated to support sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.

1. Do not leave gaps between ends of sealant backings. 2. Do not stretch, twist, puncture, or tear sealant backings. 3. Remove absorbent sealant backings that have become wet before sealant application

and replace them with dry materials.

C. Install bond-breaker tape behind sealants where sealant backings are not used between sealants and backs of joints.

D. Install sealants using proven techniques that comply with the following and at the same time backings are installed:

1. Place sealants so they directly contact and fully wet joint substrates. 2. Completely fill recesses in each joint configuration. 3. Produce uniform, cross-sectional shapes and depths relative to joint widths that allow

optimum sealant movement capability.

E. Tooling of Nonsag Sealants: Immediately after sealant application and before skinning or curing begins, tool sealants according to requirements specified in subparagraphs below to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint.

1. Remove excess sealant from surfaces adjacent to joints. 2. Use tooling agents that are approved in writing by sealant manufacturer and that do not

discolor sealants or adjacent surfaces. 3. Provide concave joint profile per Figure 8A in ASTM C 1193, unless otherwise indicated.

F. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.

Page 188: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

079200 Page 5

UCA Mashburn Hall Reroofing and JOINT SEALANTS Deck Replacement SMA #1505H

3.3 FIELD QUALITY CONTROL

A. Testing Agency: Engage a qualified testing agency to perform tests and inspections.

B. Field Quality-Control Testing: Perform the following test on representative areas of structural-sealant-glazed canopy.

C. Structural-Sealant Adhesion: Test structural sealant according to recommendations in ASTM C 1401, Destructive Test Method A, "Hand Pull Tab (Destructive)," Appendix X2.

1. Test a minimum of four areas on each building facade. 2. Repair installation areas damaged by testing.

D. Prepare test and inspection reports.

3.4 JOINT-SEALANT SCHEDULE

A. Joint-Sealant Application: Exterior joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Locations:

a. Construction joints in cast-in-place concrete. b. Control and expansion joints in unit masonry.

2. Joint Sealant: Silicone; SS-1. 3. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.

B. Joint-Sealant Application: Exterior joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Locations:

a. Joints between metal flashings. b. Perimeter joints between masonry or metals and frames of doors windows and

louvers. c. Other joints as indicated.

2. Joint Sealant: Silicone; SS-2. 3. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.

C. Joint-Sealant Application: Exterior joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Locations:

a. Perimeter joints of Exterior Insulation and Finish System.

2. Joint Sealant: Silicone; SS-2. 3. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.

D. Joint-Sealant Application: Interior joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Locations:

Page 189: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

079200 Page 6

UCA Mashburn Hall Reroofing and JOINT SEALANTS Deck Replacement SMA #1505H

a. Perimeter joints of exterior openings of aluminum storefront system. b. Perimeter joints of interior openings of aluminum frames.

2. Joint Sealant: Silicone; SS-2. 3. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.

END OF SECTION 07920

Page 190: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

099123 Page 1

UCA Mashburn Hall Reroofing and PAINTING Deck Replacement SMA #1505H

SECTION 099123 - PAINTING

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes surface preparation and field painting of exposed exterior and interior items and surfaces.

1.2 SUBMITTALS

A. Product Data: For each product indicated.

B. Samples: For each type of finish-coat material indicated.

1.3 PROJECT CONDITIONS

A. Store materials not in use in tightly covered containers in a well-ventilated area at a minimum ambient temperature of 45 deg F. Maintain storage containers in a clean condition, free of foreign materials and residue.

B. Apply waterborne paints only when temperatures of surfaces to be painted and surrounding air are between 50 and 90 deg F.

C. Apply solvent-thinned paints only when temperatures of surfaces to be painted and surrounding air are between 45 and 95 deg F.

D. Do not apply paint in snow, rain, fog, or mist; or when relative humidity exceeds 85 percent; or at temperatures less than 5 deg F above the dew point; or to damp or wet surfaces.

1.4 EXTRA MATERIALS

A. Furnish extra paint materials from the same production run as the materials applied and in the quantities described below. Package with protective covering for storage and identify with labels describing contents. Deliver extra materials to Owner.

1. Quantity: 5 percent, but not less than 1 gal., of each material and color applied.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Basis-of-Design Product: Subject to compliance with requirements, provide Sherwin-Williams Co. (Sherwin-Williams) products indicated or comparable product by one of the following:

Page 191: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

099123 Page 2

UCA Mashburn Hall Reroofing and PAINTING Deck Replacement SMA #1505H

1. Benjamin Moore & Co. (Benjamin Moore). 2. PPG Industries, Inc. (Pittsburgh Paints).

2.2 PAINT MATERIALS, GENERAL

A. Material Compatibility: Provide block fillers, primers, and finish-coat materials that are compatible with one another and with the substrates indicated under conditions of service and application, as demonstrated by manufacturer based on testing and field experience.

B. Material Quality: Provide manufacturer's best-quality paint material of the various coating types specified that are factory formulated and recommended by manufacturer for application indicated. Paint-material containers not displaying manufacturer's product identification will not be acceptable.

C. Colors: As selected from manufacturer's full range.

2.3 PREPARATORY COATS

A. Exterior Primer: Exterior alkyd or latex-based primer of finish coat manufacturer and recommended in writing by manufacturer for use with finish coat and on substrate indicated.

1. Ferrous-Metal and Aluminum Substrates: Rust-inhibitive metal primer. 2. Zinc-Coated Metal Substrates: Galvanized metal primer. 3. Where manufacturer does not recommend a separate primer formulation on substrate

indicated, use paint specified for finish coat.

B. Interior Primer: Interior latex-based or alkyd primer of finish coat manufacturer and recommended in writing by manufacturer for use with finish coat and on substrate indicated.

1. Ferrous-Metal Substrates: Quick drying, rust-inhibitive metal primer. 2. Zinc-Coated Metal Substrates: Galvanized metal primer. 3. Where manufacturer does not recommend a separate primer formulation on substrate

indicated, use paint specified for finish coat.

2.4 EXTERIOR FINISH COATS

A. Exterior Primer Acrylic Paint for surface rust areas on metal deck. 1. Krylon, CoverMaxx Primer

B. Exterior Low-Luster Acrylic Paint:

1. Sherwin-Williams; A-100 Exterior Latex Satin House & Trim Paint A82-100 Series.

C. Exterior Semigloss Acrylic Coating:

1. Sherwin-Williams; Pro Industrial 0 VOC Acrylic Coating, B66-650 Series.

Page 192: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

099123 Page 3

UCA Mashburn Hall Reroofing and PAINTING Deck Replacement SMA #1505H

2.5 INTERIOR FINISH COATS

A. Interior Low-Luster Acrylic Latex:

1. Sherwin-Williams; ProGreen 200 Low VOC Interior Latex Egg-Shell, B20-600 Series.

B. Interior Semigloss Acrylic Coating:

1. Sherwin-Williams; Pro Industrial 0 VOC Acrylic Coating, B66-650 Series.

PART 3 - EXECUTION

3.1 APPLICATION

A. Examine substrates, areas, and conditions, with Applicator present, for compliance with requirements for paint application.

B. Coordination of Work: Review other Sections in which primers are provided to ensure compatibility of the total system for various substrates. On request, furnish information on characteristics of finish materials to ensure use of compatible primers.

C. Remove hardware and hardware accessories, plates, machined surfaces, lighting fixtures, and similar items already installed that are not to be painted. If removal is impractical or impossible because of size or weight of the item, provide surface-applied protection before surface preparation and painting.

1. After completing painting operations in each space or area, reinstall items removed using workers skilled in the trades involved.

D. Surface Preparation: Clean and prepare surfaces to be painted according to manufacturer's written instructions for each particular substrate condition and as specified.

1. Provide barrier coats over incompatible primers or remove and reprime. 2. Cementitious Materials: Remove efflorescence, chalk, dust, dirt, grease, oils, and

release agents. Roughen as required to remove glaze. If hardeners or sealers have been used to improve curing, use mechanical methods of surface preparation.

3. Wood: Clean surfaces of dirt, oil, and other foreign substances with scrapers, mineral spirits, and sandpaper, as required. Sand surfaces exposed to view smooth and dust off.

a. Scrape and clean small, dry, seasoned knots, and apply a thin coat of white shellac or other recommended knot sealer before applying primer. After priming, fill holes and imperfections in finish surfaces with putty or plastic wood filler. Sand smooth when dried.

b. Prime, stain, or seal wood to be painted immediately on delivery. Prime edges, ends, faces, undersides, and back sides of wood, including cabinets, counters, cases, and paneling.

c. If transparent finish is required, backprime with spar varnish.

Page 193: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

099123 Page 4

UCA Mashburn Hall Reroofing and PAINTING Deck Replacement SMA #1505H

d. Backprime paneling on interior partitions where masonry, plaster, or other wet wall construction occurs on back side.

e. Seal tops, bottoms, and cutouts of unprimed wood doors with a heavy coat of varnish or sealer immediately on delivery.

4. Ferrous Metals: Clean ungalvanized ferrous-metal surfaces that have not been shop coated; remove oil, grease, dirt, loose mill scale, and other foreign substances. Use solvent or mechanical cleaning methods that comply with SSPC's recommendations.

a. Treat bare and sandblasted or pickled clean metal with a metal treatment wash coat before priming.

b. Touch up bare areas and shop-applied prime coats that have been damaged. Wire-brush, clean with solvents recommended by paint manufacturer, and touch up with same primer as the shop coat.

5. Galvanized Surfaces: Clean galvanized surfaces with nonpetroleum-based solvents so surface is free of oil and surface contaminants. Remove pretreatment from galvanized sheet metal fabricated from coil stock by mechanical methods.

E. Material Preparation:

1. Maintain containers used in mixing and applying paint in a clean condition, free of foreign materials and residue.

2. Stir material before application to produce a mixture of uniform density. Stir as required during application. Do not stir surface film into material. If necessary, remove surface film and strain material before using.

F. Exposed Surfaces: Include areas visible when permanent or built-in fixtures, grilles, convector covers, covers for finned-tube radiation, and similar components are in place. Extend coatings in these areas, as required, to maintain system integrity and provide desired protection.

1. Paint surfaces behind movable equipment and furniture the same as similar exposed surfaces. Before final installation of equipment, paint surfaces behind permanently fixed equipment or furniture with prime coat only.

2. Paint interior surfaces of ducts with a flat, nonspecular black paint where visible through registers or grilles.

3. Paint back sides of access panels and removable or hinged covers to match exposed surfaces.

4. Finish exterior doors on tops, bottoms, and side edges the same as exterior faces.

G. Sand lightly between each succeeding enamel or varnish coat.

H. Scheduling Painting: Apply first coat to surfaces that have been cleaned, pretreated, or otherwise prepared for painting as soon as practicable after preparation and before subsequent surface deterioration.

1. Omit primer over metal surfaces that have been shop primed and touchup painted. 2. If undercoats, stains, or other conditions show through final coat of paint, apply additional

coats until paint film is of uniform finish, color, and appearance.

I. Application Procedures: Apply paints and coatings by brush, roller, spray, or other applicators according to manufacturer's written instructions.

Page 194: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

099123 Page 5

UCA Mashburn Hall Reroofing and PAINTING Deck Replacement SMA #1505H

J. Minimum Coating Thickness: Apply paint materials no thinner than manufacturer's recommended spreading rate. Provide total dry film thickness of the entire system as recommended by manufacturer.

K. Mechanical and Electrical Work: Painting of mechanical and electrical work is limited to items exposed in equipment rooms and occupied spaces, unless noted otherwise.

L. Block Fillers: Apply block fillers to concrete masonry block at a rate to ensure complete coverage with pores filled.

M. Prime Coats: Before applying finish coats, apply a prime coat, as recommended by manufacturer, to material that is required to be painted or finished and that has not been prime coated by others. Recoat primed and sealed surfaces where evidence of suction spots or unsealed areas in first coat appears, to ensure a finish coat with no burn-through or other defects due to insufficient sealing.

N. Pigmented (Opaque) Finishes: Completely cover surfaces as necessary to provide a smooth, opaque surface of uniform finish, color, appearance, and coverage. Cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness, or other surface imperfections will not be acceptable.

O. Transparent (Clear) Finishes: Use multiple coats to produce a glass-smooth surface film of even luster. Provide a finish free of laps, runs, cloudiness, color irregularity, brush marks, orange peel, nail holes, or other surface imperfections.

P. Stipple Enamel Finish: Roll and redistribute paint to an even and fine texture. Leave no evidence of rolling, such as laps, irregularity in texture, skid marks, or other surface imperfections.

3.2 CLEANING AND PROTECTING

A. At the end of each workday, remove empty cans, rags, rubbish, and other discarded paint materials from Project site.

B. Protect work of other trades, whether being painted or not, against damage from painting. Correct damage by cleaning, repairing or replacing, and repainting, as approved by Architect.

C. Provide "Wet Paint" signs to protect newly painted finishes. After completing painting operations, remove temporary protective wrappings provided by others to protect their work.

1. After work of other trades is complete, touch up and restore damaged or defaced painted surfaces. Comply with procedures specified in PDCA P1.

3.3 EXTERIOR PAINT SCHEDULE

A. Existing Metal Deck, areas with surface rust: Two coats of rust-inhibitive primer.

B. Ferrous Metal:

Page 195: Project Manual Mashburn Hall Re‐roof & Deck Replacement …uca.edu/purchasing/files/2018/05/UCA-18-108-Mashburn... · 2018. 5. 21. · Project Manual Mashburn Hall Re‐roof & Deck

099123 Page 6

UCA Mashburn Hall Reroofing and PAINTING Deck Replacement SMA #1505H

1. Acrylic Finish: Two finish coats over a rust-inhibitive primer.

a. Primer: Exterior ferrous-metal primer (not required on shop-primed items). b. Finish Coats: Exterior semigloss acrylic enamel.

C. Zinc-Coated Metal:

1. Acrylic Finish: Two finish coats over a galvanized metal primer.

a. Primer: Exterior galvanized metal primer. b. Finish Coats: Exterior low-luster acrylic paint.

3.4 INTERIOR PAINT SCHEDULE

A. Ferrous Metal:

1. Acrylic Finish: Two finish coats over a primer.

a. Primer: Interior ferrous-metal primer. b. Finish Coats: Interior semigloss acrylic coating.

B. Zinc-Coated Metal:

1. Acrylic Finish: Two finish coats over a primer.

a. Primer: Interior zinc-coated metal primer. b. Finish Coats: Interior low-luster acrylic latex.

END OF SECTION 099123