Don't Change A Thing: Why Your Style is EXACTLY What Your Project, Team, & Organization NEED!
Project Management: What and Why
description
Transcript of Project Management: What and Why
Project Management:What and Why
Wayne Baggett
12/1/2008 PM: What & Why W. Baggett 2
What is a Project?
• PMI (PMBOK) definition:– a temporary endeavor undertaken to create a
unique product, service, or result
• Important words:– Temporary = definite beginning and end
• Could be long term, though!
– Unique• Product doesn’t already exist in *exactly* the same
form
12/1/2008 PM: What & Why W. Baggett 3
What is Project Management?
• PMI (PMBOK) definition:– the application of knowledge, skills, tools and
techniques to project activities to meet project requirements
• Not the technical work of the project!– PM *enables* the technical work to proceed– PM activities define/control/direct the technical work
• Establishes project goals (scope, cost, schedule, quality)• Identifies and deals with risks (technical, managerial)• Establishes the processes to be used by the project
12/1/2008 PM: What & Why W. Baggett 4
Triple Constraint
• Classically, Project Management works with three quantities– Scope – what is being done– Cost – how much $ you have to spend– Schedule – when it needs to be done
• Project Manager manages these items to accomplish the project goals
• These items interact to affect quality
12/1/2008 PM: What & Why W. Baggett 5
Why Project Management?
?
12/1/2008 PM: What & Why W. Baggett 6
Why Project Management?
• Have you– Ever worked on a project?– Provided a time estimate for a task?– Provided a progress estimate on a task?– Helped decide who would work on a project?– Helped decide what work is needed on a
project?
12/1/2008 PM: What & Why W. Baggett 7
Why Project Management?
Because we do many PM activities as part of our
work, anyway!
Might as well learn and
apply accepted best practices
to what we already do!
12/1/2008 PM: What & Why W. Baggett 8
What Are Those Best Practices?
• PMI defines five “Process Groups”– Initiating
• Project charter & Initial scope
– Planning• Scope definition & schedule, cost, risk, etc. planning
– Executing• Team building, QA, general management
– Monitoring & Controlling• Schedule & cost control, risk monitoring, performance
reporting, contract administration
– Closing• Contract closure, project closing
Process: A set of interrelated activities performed to achieve a pre-specified set of products, services, or results.
12/1/2008 PM: What & Why W. Baggett 9
What Are Those Best Practices?
• PMI defines nine “Knowledge Areas”– Project Integration Management– Project Scope Management– Project Time Management– Project Cost Management– Project Quality Management– Project Human Resource Management– Project Communications Management– Project Risk Management– Project Procurement Management
12/1/2008 PM: What & Why W. Baggett 10
Best Practice MatrixInitiating Planning Executing
Monitoring & Controlling Closing
Integration 2 1 1 2 1
Scope 3 2
Time 5 1
Cost 2 1
Quality 1 1 1
Human Resources 1 2 1
Communications 1 1 2
Risk 5 1
Procurement 2 2 1 1
Process GroupsK
no
wle
dg
e A
rea
sK
no
wle
dg
e A
reas
12/1/2008 PM: What & Why W. Baggett 11
Summary
• Project Management– Is something we do anyway– Is an organized approach to achieve project
goals– Utilizes best practices
• Well-defined• Time-tested• Generally accepted
– Is worth learning and applying to our work