PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

40
BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS 1 COURSE / WORKSHOP PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS [email protected]

Transcript of PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

Page 1: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

1

COURSE / WORKSHOP

PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS

[email protected]

Page 2: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

6th March 2017

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

2

COURSE / WORKSHOP OBJECTIVE

To provide Shipyard Project Managers and Shipyard personnel with project management tools for planning and controlling projects, using recognized project management standards applied on ship repair industry. Through this course learning experience will be improved by practicing concepts through a real-world ship repair project.

“This will increase the chance of success on your projects”

[email protected]

Page 3: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

6th March 2017

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

3

• Module 0. Project Management Standards and overview (1 hour): Definition of Project Management. Project Management Standards, Knowledge Areas and Process groups. Project Management in Shipyard industry overview.

• Module 1. WBS for Ship Repair Projects – (4 hours): What is a WBS?. Components of a WBS. Steps to create a WBS for a ship repair project. WBS top 4 Benefits in Ship Repair industry. WBS Manual exercise. Create the WBS for project QUEEN ANDREA using a WBS software.

• Module 2. Critical Path / Ms Project for Ship Repair Projects – (4 to 5 hours): Basic concepts for project scheduling. What is critical path? How to use it in Ship Repair Projects. Critical path Top 5 benefits. Aspects on which the Ship Repair Project Manager should focus in project scheduling. Critical Path Exercise. Steps to Create a project schedule in Ms Project. How to monitor the schedule in Ms Project. Schedule Accuracy level in ship repair projects based on uncertainty. Create the project schedule for project QUEEN ANDREA using Ms Project.

COURSE / WORKSHOP CONTENT

[email protected]

Page 4: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

6th March 2017

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

4

• Module 3. Time and Cost Control with EVM Ship Repair Projects – (4 to 5 hours): What is EVM?. EVM formulas (Variance, KPIs and Forecast). How to use EVM in Ship Repair Projects to control cost and time (calculations and reports). Relationship between the WBS, Project Schedule (Ms Project) and EVM. Use EVM calculations and reports for the project QUEEN ANDREA.

• Module 4. Risk Management in Ship Repair Projects – (4 hours): What is Risk Management?. Steps for risk management in ship repair projects. Understanding the Risk Register and Risk Assessment Matrix for Ship Repair Projects. Apply Risk Management for project QUEEN ANDREA.

• Module 5. Stakeholders Management in Ship Repair Projects – (4 hours): What is Stakeholder Management?. Identify and analyze ship repair stakeholders. Manage ship repair stakeholders engagement. Identify and analyze stakeholders for project QUEEN ANDREA.

COURSE / WORKSHOP CONTENT

[email protected]

Page 5: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

6th March 2017

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

5

• Module 6. Ship Repair Project Manager Soft Skills (1 to 2 hours): The 3 propeller blades of knowledge for the Ship Repair Project Manager. Recognized Project Management Certifications. Coordination skills. Overview on negotiation skills.

• Module 7. Multi-Projects (Program) Control using Ms-Project and EVM (3 to 4 hours): What is Multi-Project / Program Management in the ship repair industry. Planning the Program. Controlling the Program. The benefits of controlling the program. Then need of a Program or Project Management Manager in the ship repair industry. Practical exercise using Ms Project and EVM

COURSE / WORKSHOP CONTENT

[email protected]

Page 6: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

6th March 2017

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

6

COURSE / WORKSHOP METHODOLOGY

The course / workshop methodology is based on “experiential learning”.

Theory + subject specific exercise + real-world ship repair project practice

MV “QUEEN ANDREA”

IMO number: 0000000Length Overall: 250 mBreadth: 40.06 mGross Tonnage: 120.000 Vessel Type: Tanker

[email protected]

Page 7: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

6th March 2017

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

7

COURSE / WORKSHOP FOUNDATION

• PMBOK guide from PMI• My upcoming book “Shipyard Project

Management”

Coming soon May 2017

[email protected]

Page 8: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

8

EDUCATIONAL BACKGROUND

• Industrial Engineer• Post Graduate - Diploma in Project Management• Project Management for Engineering projects course from Delft

University• Certified as Project Management Professional - PMP by the Project

Management Institute (PMI) since 2011.

EXPERIENCE

• 10 years of experience in the industry• Positions held: Project Manager, Risk Engineer, Production

Superintendent (Shipbuilding), Marine Maintenance Supervisor.• 6 years of experience using PMI Standard in Ship Repair Projects

• Author and speaker about Project Management focused on Ship Repair

6th March [email protected]

Page 9: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

9

…… based on PMI Standard

MODULE 0

PROJECT MANAGEMENT

STANDARDS AND OVERVIEW

“….What is Project Management about? Project Management is about how to organize yourself, your team and your project….”

PMBOK - PMI

APMBOK - APM PRINCE2 - AXELOS

[email protected]

Page 10: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

10

…… based on PMI Standard

MODULE 0

PROJECT MANAGEMENT

STANDARDS AND OVERVIEW

EXISTING PROJECT MANAGEMENT WAY

OF THINKING IN SHIPREPAIR INDUSTRY

OLD FASHIONED MANAGEMENT

STYLE

QUA

LITY

MAN

AGEM

ENT

HU

MAN

RES

OU

RCE

MAN

AGEM

ENT

COM

MU

NIC

ATIO

N M

ANAG

EMEN

T

RISK

MAN

AGEM

ENT

PRO

CURE

MEN

T M

ANAG

EMEN

T

STAK

EHO

LDER

MAN

AGEM

ENT

Cost

ScopeTime

SHIPS TECHNICAL

KNOWLEDGE

PROJECT MANAGEMENT STANDARDS

SUST

AIN

IBIL

ITY

THE CORRECT WAY TO MANAGE SHIPREPAIR PROJECTS

[email protected]

Page 11: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

11

…… based on PMI Standard

IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]

MODULE 0

PROJECT MANAGEMENT

STANDARDS AND OVERVIEW

[email protected]

Page 12: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

12

…… based on PMI Standard

MODULE 1

WBS – WORK BREAKDOWN STRUCTURE

APPLIED TO SHIP REPAIR

PROJECTS

[email protected]

Page 13: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

13

…… based on PMI Standard

MODULE 1

WBS – WORK BREAKDOWN STRUCTURE

APPLIED TO SHIP REPAIR

PROJECTSVessel Location /

Deliverable

Work Packages

Main Deliverable or Project

Figure 13. WBS example

1

1.1

1.1.1

1.2

1.1.2 1.2.1

LEVEL 1

LEVEL 2

LEVEL 3

WBS COMPONENTS

• Deliverable: is what we are going to deliver, either a service or a product requested by the client.• Work package: is the lowest level of decomposition. As from the work packages you can define the activities• ID number: is the number located on each component for easy identification• Level of decomposition: is related how deep you decompose each element

[email protected]

Page 14: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

14

…… based on PMI Standard

MODULE 1

WBS – WORK BREAKDOWN STRUCTURE

APPLIED TO SHIP REPAIR

PROJECTS

HOW TO CREATE AND USE A WBS FOR SHIP REPAIR PROJECTS

STEP 1. Collect input

documents

STEP 2. Divide ship

per locations

and systems

STEP 3. Define the software to

be used

STEP 4.Create the

WBS

[email protected]

Page 15: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

15

…… based on PMI Standard

MODULE 1

WBS – WORK BREAKDOWN STRUCTURE

APPLIED TO SHIP REPAIR

PROJECTS

[email protected]

IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]

Page 16: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

16

…… based on PMI Standard

MODULE 2

CRITICAL PATH – MS PROJECT

CRITICAL PATH – MS PROJECT

[email protected]

Page 17: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

17

…… based on PMI Standard

MODULE 2

CRITICAL PATH – MS PROJECT

CRITICAL PATH METHOD

Critical Path is the longest path from the beginning to the end of the project. A path is a sequence of activities in a certain time frame and the longest path is the one leading the finish of the project

[email protected]

Page 18: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

18

…… based on PMI Standard

MODULE 2

CRITICAL PATH – MS PROJECT

IN WHAT ASPECTS THE SHIPREPAIR PROJECT MANAGER SHOULD FOCUS WHILE PLANNING AND CONTROLLING THE PROJECT SCHEDULE?

[email protected]

Page 19: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

19

…… based on PMI Standard

MODULE 2

CRITICAL PATH – MS PROJECT

STEPS TO CREATE A SCHEDULE IN MS-PROJECT

Transfer WBS information into MS PROJECT

Adjust initial settings: Calendar and Project start date

Define activities and milestones

Define activity duration and sequence the activities

Calculate the critical path

Save baseline

1

2

3

5

6

4

[email protected]

Page 20: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

20

…… based on PMI Standard

MODULE 2

CRITICAL PATH – MS PROJECT

STEPS TO CREATE A SCHEDULE IN MS-PROJECT

Define activity duration and sequence the activities4

[email protected]

Page 21: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

21

…… based on PMI Standard

MODULE 2

CRITICAL PATH – MS PROJECT

[email protected]

IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]

Page 22: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

22

…… based on PMI Standard

MODULE 3

TIME AND COST CONTROL WITH

EVM

[email protected]

Page 23: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

23

…… based on PMI Standard

MODULE 3

TIME AND COST CONTROL WITH

EVM

Project information

Project estimates: Price / MH / Materials / Contractor invoice price /

Contractor prices / SC % margin

Monitoring dates: PV, EV, AC, Variance for Man hours and

Materials

Jobs description + Control account

Totals: Revenues, MH, Materials, Subcontractors

Totals per date: PV, EV, AC, Variance for MH and Materials

[email protected]

Page 24: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

24

…… based on PMI Standard

MODULE 3

TIME AND COST CONTROL WITH

EVM

[email protected]

Page 25: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

25

…… based on PMI Standard

MODULE 3

TIME AND COST CONTROL WITH

EVM

[email protected]

IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]

Page 26: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

26

…… based on PMI Standard

MODULE 4

RISK MANAGEMENT

FOR SHIP REPAIR

PROJECTS

[email protected]

Page 27: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

27

…… based on PMI Standard

MODULE 4

RISK MANAGEMENT

FOR SHIP REPAIR

PROJECTS

STEPS FOR PROJECT RISK MANAGEMENT IN SHIP REPAIR PROJECTS 1. Identify Risks: Once the scope is known a risk identification can be performed. Risk can be identified during project

initiation till the end.

This are the most important aspects to consider when you are identifying Risk and Causes:

• The Risks must be identified based on the Project Objectives• The Risks cannot be a constraint (a constraint is something that already exists and should be responded with

a contingency plan)• When the risk is going to be identified you should ask yourself: What can go wrong that can impact the

project objectives?• The cause of the risk could be a constraint, an assumption, requirement or condition that originates the

unwanted or wished event.

Example 1: Lack of man power, due to interference with other projects, impacting undocking date and departure date.Example 2: To not finish Hull blasting on planned date, due to extreme weather conditions on April, impacting dry-docking time of the vessel

[email protected]

Page 28: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

28

…… based on PMI Standard

MODULE 4

RISK MANAGEMENT

FOR SHIP REPAIR

PROJECTS

[email protected]

Page 29: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

29

…… based on PMI Standard

MODULE 4

RISK MANAGEMENT

FOR SHIP REPAIR

PROJECTS

[email protected]

IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]

Page 30: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

30

…… based on PMI Standard

MODULE 5

STAKEHOLDER MANAGEMENT

FOR SHIP REPAIR

PROJECTS

STAKEHOLDER MANAGEMENT FOR

SHIP REPAIR PROJECTS

[email protected]

Page 31: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

31

…… based on PMI Standard

MODULE 5

STAKEHOLDER MANAGEMENT

FOR SHIP REPAIR

PROJECTS

[email protected]

Stakeholder Identification

Page 32: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

32

…… based on PMI Standard

MODULE 5

STAKEHOLDER MANAGEMENT

FOR SHIP REPAIR

PROJECTS

Figure 12. Stakeholders Analysis Matrix

[email protected]

Stakeholder Analysis Matrix

Page 33: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

33

…… based on PMI Standard

MODULE 5

STAKEHOLDER MANAGEMENT

FOR SHIP REPAIR

PROJECTS

[email protected]

IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]

Page 34: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

34

…… based on PMI Standard

MODULE 6

SOFT SKILLS FOR SHIPREPAIR

PROJECT MANAGERS

Project Management

Technical Business

[email protected]

Page 35: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

35

…… based on PMI Standard

MODULE 6

SOFT SKILLS FOR SHIPREPAIR

PROJECT MANAGERS

[email protected]

Page 36: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

36

…… based on PMI Standard

MODULE 6

SOFT SKILLS FOR SHIPREPAIR

PROJECT MANAGERS

[email protected]

IF YOU ARE INTERESTED TO KNOW MORE AND LEARN ABOUT THIS MODULE PLEASE CONTACT ME [email protected]

Page 37: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

37

…… based on PMI Standard

MODULE 7

MULTI-PROJECTS CONTROL

USING EVM

[email protected]

Page 38: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

38

…… based on PMI Standard

MODULE 7

MULTI-PROJECTS CONTROL

USING EVM

Figure 26. Program planning in MS Project

[email protected]

Page 39: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

39

…… based on PMI Standard

MODULE 7

MULTI-PROJECTS CONTROL

USING EVM

1 765432 1098 1211

13

Figure 27. Program EVM report

[email protected]

Page 40: PROJECT MANAGEMENT TOOLS FOR SHIPYARD PROJECT MANAGERS/ Course - Workshop

BASIC PROJECT MANAGEMENT TOOLS FOR SHIPREPAIR PROJECT MANAGERS

40