1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection Burke Chapter 4-5

Transcript of Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project...

Page 1: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

1

Project ManagementSharif MBA – Fall 1385

Session 4 - Dr. SepehriFeasibility Study, Project Selection

Burke Chapter 4-5

Page 2: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

2

Project Feasibility• Feasibility study ensures that projects are technically

and legally possible, and are economically justified.• Feasibility study must be managed as a mini-project

using planning and control, with its own life-cycle.• Senior manager has the responsibility to select the

project manager for feasibility study.• Project manager then selects the feasibility study

team, including a representative of future operators. • Decision to proceed with the feasibility study does

not mean the decision to go ahead with the project!

Not every project is doable!Not every project should be done!

Not every project makes the best use of company’s resources

Page 3: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

3

1- Feasibility Study Initiation

The lead up to the project feasibility study is the formalization of the project with the project charter.Project Feasibility Study should be formalized with requirements, boundaries, and expected outcomes:

• Who is responsible• Project brief to be analyzed• Who should be involved• Level of details• Budget for the feasibility study• Report back date

Page 4: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

4

2- Planning the Feasibility Study

Page 5: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

5

3- Stakeholder Analysis• The purpose of the needs analysis in feasibility study is

to determine needs and expectations of all stakeholders• Project stakeholders are people and organizations (both

internal and external) who are either actively involved in the project, or whose interests are affected by project.

• Originator• Owner• Sponsor• Project Champion• Users• Customers • Suppliers/Vendors

• Project Team• Senior Management• Functional Managers• Boss• Colleagues• Sub-contractors• Supports

• Health/SafetyAuthorities

• Trade Unions• Interest Groups• Lobby Groups• Government• Citizens

Page 6: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

6

Stakeholders Analysis• Stakeholders may be positively or negativelyaffected by the project (cannot cancel out!).

• Project manager must negotiate to build acoalition among stakeholders to move forward.

Page 7: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

7

4- Define the Client’s Needs• Function at a pre-defined rate• Operate in a specific environment• Have working life of so many years• Budget not to exceed $x amount• Meet certain specifications/standards• Achieve reliability requirements• Must be energy efficient• Meet health and safety regulations• Ease of maintenance and repairs• Provide opportunity for expansions • Etc.

Page 8: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

8

5. Evaluate Constraints• Internal Project Constraints

Technical, Technology, Resources, Budget, etc.• Internal Corporate Constraints

Financial, Marketing, Partner, Exports, Training• External Constraints

Laws & Regulations, Logistics, Environment

Page 9: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

9

Technology Transfer• Should we start the project now with the present technology or should we wait for better technology?

• At what point in the development should a design freeze, with the current technology, be imposed?

Page 10: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

10

6- Evaluate Alternatives and Options

By breaking down a complex project into components, by• work breakdown structure (WBS) or activity,• the project constraints,• the project objectives,

alternatives and options may be assessed more effectively.

Page 11: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

11

7- Gather InformationInformation is a pre-requisite for effective problem solving and decision making.The size of the company will influence how and where information is available.Responsibility for setting up a database of information should lie with either theproject office or the company’s general manager.

• Sales/Marketing Brochures • Books and Periodicals• Technical Reports• Bureau Specifications• Market Research• Internet• Stakeholders• Close-up Reports

Page 12: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

12

8- Value Management

Value Management is a structured, systematic and analytical process that seeks to achieve value for money by providing all the necessary functions at the lowest total cost, consistent

with desired levels of quality and performance.

• Identify unnecessary expenditures• Challenge assumptions• General alternative ideas• Promote innovation• Optimize resources• Save time, money, and energy• Simplify methods and procedures• Eliminate redundant items• Update standards, criteria, objectives

• Clarify customers’ needs• Create ideas• Challenge assumptions• Participate everyone• See the purpose• Seek lowest cost

Page 13: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

13

9- Cost Benefit Analysis

Initial cost-benefit analysis to establish the financial feasibility of the project.– Pareto improvement criteria: the project should make some

people better off without making anyone worse off.

– Hick-Kaldor test: the aggregate gains of the project should exceed aggregate losses.

– Willingness to pay: to determine how much your clients are prepared to pay for your product

Page 14: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

14

Communication Gap in Needs Assessment

Page 15: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

15

Project SelectionProject Selection = Investment Decision = Commitment for Future

• Production Consideration• Marketing Consideration• Financial Consideration• Personnel Consideration• Administration Consideration

• Maximize Profit• Utilize workforce• Increase Market share• Enter new markets• Improve image

Page 16: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

16

Numeric Methods – Payback Period

• Most widely used• Simple and quick• An initial filter• Future is uncertain

Payback Period =The time taken to gain a financial return equal to the original investment.

Page 17: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

17

Disadvantages =• No time value of money• Indifferent to the timing• Not for long-term projects• Based only on cash flow• Not consider risk exposure• Not consider total project

Page 18: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

18

Return on Investment (ROI)Average Annual Profit = (Total Gains) – (Total outlay) / No. of YearsReturn on Investment = Average Annual Profit / Original Investment

Profit ( A & B ) = $55,000 - $35,000Annual Profit = $20,000 / 4 = $5,000ROI = $5,000 / $35,000 = 14%

Page 19: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

19

Net Present ValuePresent Value = discount factor x cash-flowDiscount factor = 1 / (1+i)n

i = the forecast interest yearn = number of years from start

Page 20: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

20

Example of Net Present Value

Page 21: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

21

Net Present ValueDisadvantages of Net Present Value• Bias towards short run projects• Limited by accuracy of interest rate

Advantages of Net Present Value• Uses Time value of money• Allows for inflation/escalation

Page 22: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

22

Internal Rate of Return (IRR)IRR or DCF is the value of the discount factor when the NPV is zero.

Page 23: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

23

Example of IRR

Page 24: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

24

Net Present Value (NPV)using Variable Interest Rates

Page 25: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

25

Scoring ModelsFinancial and Non-financial factors with varying weights

Page 26: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

26

Break-even AnalysisBreak-even point = Fixed costs / Contribution per unit

Page 27: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

27

Project Life-cycle Cash-flow

Page 28: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

28

Choosing the Right Project

Page 29: Project Management - Sharifgsme.sharif.edu/~projectmanagement/PMSession4.pdf · 1 Project Management Sharif MBA – Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection

29

Next Classes:• Today Sunday 30th of Mehr

• Regular class 12:20 pm Feasibility, Project Selection• Review session 1:20 pm Problem Solving, Exercises

• Tuesday 2nd of Aban• Finish Session 3 from last week• Session 4: Planning, Initiation and Integration

• Sunday 7th Aban• Regular Class: Case studies (TBA)• Review session: Problem Solving, Exercises

• Tuesday 9th Aban• Session 5: Scope Management

• Wednesday 10th Aban (make-up class)• Session 6 Organization Structure