Project management network diagram

6
PGBM 48 Project Management Sunderland Business School Level: M Module: Project Management Assignment Code: PGBM 48 Module Leader: Tom Cuthbertson Issue date: TBA Return date: 14 May 2015 Contribution to module assessment: 100% This is an individual assignment - You are required to complete both parts A and B Part A (80% Marks) Only use times new roman. You are required to prepare a report (2500+/- 10% words) and critically review and reflect on the reasons why organizations are using Project Management to achieve their strategic objectives. ( Refer to Segisphere) Use relevant example of successful companies doing it. Report topic: Critically report / analysis on…. 1. Executive summary 2. Table of content 3. Part A :Executive summary 4. Introduction 5. Body 6. Conclusions 7. References 8. List of appendix Part B (20% marks) Project name: Defining the project plan of Refurbishment of UOS (whatever ) business school . You are a member of the University Executive and have been requested to prepare a project plan for the refurbishment of the Business School student lounge and dining room. document.doc8

description

Project Management

Transcript of Project management network diagram

Page 1: Project management network diagram

PGBM 48 Project Management

Sunderland Business School

Level: M Module: Project Management

Assignment Code: PGBM 48 Module Leader: Tom Cuthbertson

Issue date: TBA Return date: 14 May 2015

Contribution to module assessment: 100%

This is an individual assignment - You are required to complete both parts A and B

Part A (80% Marks) Only use times new roman.

You are required to prepare a report (2500+/- 10% words) and critically review and reflect on the reasons why organizations are using Project Management to achieve their strategic objectives. ( Refer to Segisphere)

Use relevant example of successful companies doing it.

Report topic: Critically report / analysis on….

1. Executive summary

2. Table of content

3. Part A :Executive summary

4. Introduction

5. Body

6. Conclusions

7. References

8. List of appendix

Part B (20% marks) Project name: Defining the project plan of Refurbishment of UOS (whatever ) business school .

You are a member of the University Executive and have been requested to prepare a project plan for the refurbishment of the Business School student lounge and dining room.

The work must start on the 9 July 2015 and be complete and available for use by the 5th September 2015 when students return for the new academic year. A penalty clause of £10,000 per day of delay beyond the 5th September is written into the contract.

All of the information on project activities and planned durations are shown in the table provided. Using Microsoft Project prepare the following.

document.doc8

Page 2: Project management network diagram

PGBM 48 Project Management

1) A one page Gantt Chart to establish Start and Finish times and Total Slack, add title and insert your name and student number into the legend box – print landscape on one page.

2) A Network Diagram, insert your name and student number into the legend box –print on one page including title and legend. (Created by Microsoft project).

3) Using activity numbers determine the critical path and project duration. (Explain in theory) A : the critical path is ID 9 , ID 1 and ………

4) If the project starts on the 9 July 2015 what is the earliest date it can be completed.

Answer: 7th Sept 2015.

5) If any of the following events happened individually, what would be the effect on the duration of the whole project? Explain the reasons why.

a) Gas Fire commissioning is delayed by 15 days.

b) Applying 30 rolls of Wallpaper now takes 3 days longer than planned. ( there is a change in finish date because it fall under critical path)

c) Delivery of Furniture is delayed by 2 days ( it does not change the complete date of project because it has 4 slack days ).

Project Activities

ID Activity Duration Days

Predecessors

1 Project Start and appoint contractors 1

2 Select and Order Gas Fire 1 1

3 Delivery of Gas Fire and Fireplace 15 2

4 Install Gas Fire and Fireplace 1 3

5 Commission Gas Fire 1 4

6 Select and Order Wallpaper 1 1

7 Delivery of Wallpaper 15 6

8 Remove Furniture & Lamps to Storage 2 7

9 Strip Wallpaper from Walls 5 8

10 Remove Dado Rail and Re Plaster 3 9

11 Paint Ceilings, Windows and Doors 4 10

12 Apply 30 rolls of Wallpaper 7 7,11

document.doc8

Page 3: Project management network diagram

PGBM 48 Project Management

13 Select and Order Carpet 5 1

14 Delivery of Carpet 30 13

15 Remove Existing Carpet 1 13

16 Install New Carpet 1 5,12,14,15

17 Select and Order New Furniture 5 1

18 Delivery of New Furniture 30 17

19 Install New Furniture 1 4,12,16,18

20 Install Existing Lamps & Mirrors 1 19

21 Project Completed, Inspection and handover 1 20

For this case assume the following:

1) The following holidays are observed. Last Monday in August for the Bank holiday2) The contractors work a 5 day week Monday through Friday

A: there is a two days delay in finishing the project because of the public holiday.

Assignment presentation and assessment

The answers to both parts must be incorporated into one report .

Part B may be included in the appendices,

The criteria for assessing the report will be:

Report presentation (20%)

The extent to which the assignment represents an effective report. This will be judged on:

Appearance: Is a word count included at the end of the report? is it within the specified amount? Is the text double spaced?

Structure: Does the report follow the conventions of the format? Does is have a clear introduction, explaining how it answer the questions? Do the sections of the report develop ideas in a logical sequence? Are diagrams used

Spelling and grammar: Are all words spelled correctly and is the meaning of sentences clear?

document.doc8

Page 4: Project management network diagram

PGBM 48 Project Management

Referencing: Have appropriate references been included in the report. Has a recognised referencing system been used for notation? (see relevant section in the Guide to Basic Study Skills)

Use of relevant theory (40%)

Has the right theoretical content been chosen as the basis for answering the questions? Is there evidence of the use of course notes and books and further reading? Is the academic theory selected significant to the questions?

Analysis (40%)

This measures the extent to which students develop a structured argument for the points they make, by combining relevant theory with the information provided in the questions.

Part A of your report should be submitted to Turnitin and a copy of the receipt attached to your assignment submitted to the Prospect Gateway

Any work submitted is subject to the University's rules and procedures governing infringement of assessment regulations.

Module Leader Tom Cuthbertson Moderated by Dr Ian Evans

Grading Criteria - Individual Assignment

First Class (70% – 100%)A creative and original response to the question. Critically reflecting on perceived theory and experiences. Wide and appropriate use of sources (theory and practice) based on reading and experiences. Answer written fluently, with evidence of a highly developed capacity to structure work systematically and argue logically.

Grade B (55% – 69%)Comprehensive knowledge of concepts and theories. Appropriate application of theory and experience to the question answered. Ability to inter-relate concepts and ideas. Some originality in approach and awareness of scope and limitations. Answer systematically structured and coherent.

document.doc8

Page 5: Project management network diagram

PGBM 48 Project Management

Grade C (40%-54%)Evidence of knowledge of concepts and theories. Attempts to relate and balance theory and practice. Main issues addressed appropriately. Mainstream texts and lecture notes used .Limited evidence of wider reading. Work presented in a structured form but arguments weak in places.

Fail (0 – 39%)Some knowledge of main concepts and theory but major omissions and / or misunderstandings. Style and structure weak and overly descriptive. Considerable limitations in ability to perceive the relationship of theory and practice. Limited reading.

document.doc8