9M603.56 1 Name : V.Rama Rao Designation : Head of the Department Branch : Mechanical Engg. Institution : 028 Sir C R R Polytechnic Eluru Year/Semester : VI Semester Subject : Industrial Engg. & Estimating and Costing Subject code : M603 Topic : Estimation of Weights Duration : 50 Minutes Sub Topic : Mensuration Of 2D objects Teaching Aids :PPT Animations Revised by : M.V.CH Jagadeeswarudu Department of Technical Education Andhra Pradesh

description

This contains the valuable formulaes for various objects Project Management ManualforDesign and Construction Projects(RevisedAugust 2010)Table of Contents2Table of Contents1. Overview......................................................................................................................................51.1 Introduction...........................................................................................................................61.2 Design and Construction Process..........................................................................................71.3 Project Delegation & Coordination Chart.............................................................................81.4 Responsibility Matrix............................................................................................................91.5 Roles & Responsibilities.......................................................................................................92. Project Initiation......................................................................................................................152.1 Project Delivery Method.....................................................................................................152.2 Select Project Management Team......................................................................................162.2.1 C/U Project Manager Criteria......................................................................................172.2.2 A/E Design Team Selection.........................................................................................192.2.3 OR Selection................................................................................................................212.2.4 Specialty Consultant Selection....................................................................................232.3 Owner Provided Information..............................................................................................243. Design Management.................................................................................................................263.1 Design Principles................................................................................................................263.2 Predesign Phase..................................................................................................................263.3 Schematic Design Phase.....................................................................................................273.4 Design Development Phase................................................................................................313.5 Construction Documents Phase..........................................................................................343.6 Bidding................................................................................................................................363.7 Contracts and Awards.........................................................................................................383.8 Public Art Procedures.........................................................................................................403.9 Architect/Engineer Evaluation............................................................................................414. Construction Management.......................................................................................................424.1 Pre-Construction.................................................................................................................424.2 Construction Progress Meetings...................................................................

Transcript of Project Management Manual for Design

  • 9M603.56*Name: V.Rama RaoDesignation: Head of the DepartmentBranch: Mechanical Engg.Institution: 028 Sir C R R Polytechnic EluruYear/Semester: VI SemesterSubject: Industrial Engg. & Estimating and CostingSubject code: M603Topic: Estimation of WeightsDuration: 50 MinutesSub Topic: Mensuration Of 2D objectsTeaching Aids:PPT AnimationsRevised by : M.V.CH JagadeeswaruduDepartment of Technical Education Andhra Pradesh

    9M603.56

  • 9M603.56*RecapIn previous class, we have reviewed about

    Elements of cost , Depreciation and related problems,Estimation procedure Difference between estimation and costing

    9M603.56

  • 9M603.56*ObjectivesOn completion of this period you will be able to know Procedure for estimation of weights of materials.calculation of areas and circumference of SquareTriangleTrapeziumRectangleParallelogramCircleOther such standard geometric figures

    9M603.56

  • 9M603.56*Procedure for estimation of weights of materialsBreak up the component drawing into simple and meaningful parts.Calculate the volume of each individual part making use of mensuration formulae.Small fillets and rounded corners may be neglected.Add all these volumes to get total volume of component.Multiply the volume by density of material .Account for scrap and wastage.Weight of material is multiplied by cost per unit weight of material to arrive direct material cost.

    9M603.56

  • 9M603.56*Areas Of Plane Figures Rectangle: l=Length of rectangle b=Breadth of rectangle Then, Area = l x b Perimeter = 2(l + b)

    9M603.56

  • 9M603.56*Square Let, S = Length of each side of square d = Length of diagonal

    Then, Area = S2 or d2 / 2 Perimeter = 4S

    9M603.56

  • 9M603.56*Parallelogram l = Length of one side of Parallelogram b = breadth of another side of Parallelogram h = Height of ParallelogramThen, Area = l X h Perimeter = 2(l+ b)

    9M603.56

  • 9M603.56* Triangle let a, b and c are lengths of the sides of a triangle. h = height of `A` from base BCThen, Area = a x h = x Base x Perpendicular height Perimeter = a + b + c and S = (a + b + c)/2 Then, Area =

    9M603.56

  • 9M603.56*Hexagon : Let, a = length of each side of Hexagon h = heightThen, Perimeter = 6a Height h = 3 a Area = (3 3/2)a2

    9M603.56

  • 9M603.56*Any Regular Polygon :

    General formula for any regular polygon having `n sides of length `a` units each are : Perimeter = n.a Area = perimeter x inner radius

    9M603.56

  • 9M603.56*Trapezium : Let a, b, c, and d are the lengths of four sides. h = Perpendicular distance between parallel sides Perimeter = a + b + c+ d Area =

    9M603.56

  • 9M603.56*Circle :Let r = radius of circle d = Diameter of circle

    Area =

    =

    Perimeter = d = 2 r

    9M603.56

  • 9M603.56*Sector : Let r = radius of circle = Angle in radians l = Length of arc l = r

    Area = (Angle of sector/(2 )) X Area of circle = =

    9M603.56

  • 9M603.56*Fillet (Circular) : Let r = radius of fillet. Then, Area of fillet = r2 - /4 r2 = r2(1 - /4 r2) = 0.215r2 = r2(approx)

    9M603.56

  • 9M603.56*Ellipse : Let a = semi major axis. b = semi minor axis Area = ab Perimeter = (a + b)

    9M603.56

  • 9M603.56*Segment of a circle : Area = Where h = BD l = AC

    9M603.56

  • 9M603.56*SUMMARYWe have discussed about calculation of various areas of

    SquareRectangleParallelogramTriangleHexagonTrapeziumCircleSector

    9M603.56

  • 9M603.56*QUIZ1. Area of the ellipse a) Area = ab b) Area = (a+b) c) Area = /ab d) Area = (a-b)

    9M603.56

  • 9M603.56*2. Area of circular fillet a) 0.215r2 b) 0.150r2 c) 0.225r2 d) 0.250r2

    9M603.56

  • 9M603.56*AssignmentWrite the procedure to be followed for estimating direct material cost.Write down the formulae for areas ofEllipseFillet SectorRegular polygonSegment of circle