![Page 1: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/1.jpg)
Project Management Capacity Building for Planning and
Implementing for Tsunami Development Projects in Sri
Lanka
Dr. Janaka RuwanpuraDirector and Associate Professor of Project Management
Schulich School of Engineering(University of Calgary, Canada)
Professor Ananda JayawardaneDean and Professor
Faculty of Engineering(University of Moratuwa, Sri Lanka)
![Page 2: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/2.jpg)
Objectives of the Presentation
• Overview of the Project Management Challenges and Problem Areas
• Proposed Project – Capacity Building • Example: Stakeholder Analysis
![Page 3: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/3.jpg)
Project Management…Post tsunami situation – PM Lapses• Immediate relief – Government slow to respond
due to lack of effective mechanism• Distribution of relief donations – Ad hoc donations,
lack of co-ordination reported despite attempts by Government Organizations and Centres
• Prevention of epidemics through shelter, water & sanitation – Handled marginally well but fortunate to escape
• Immediate restoration of basic infrastructure –Handled generally well due to commitment by organisations
![Page 4: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/4.jpg)
Project Management…
Post tsunami situation – PM Lapses….• Assessment of damage to infrastructure – Ad
hoc attempts, repeated efforts, confusion• Data gathering – non availability of population
data, refusal, lack of co-operation, ad hoc efforts
• Co-ordinating donors for re-construction –Lack of overall co-ordination, lack of guidance for donors, lack of clear policy, lack of information
![Page 5: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/5.jpg)
Project Management…
Post tsunami situation – PM Lapses….
• Co-ordinating other statutory decision making bodies – Confusion due to lack of communication/co-ordination between state organisations
![Page 6: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/6.jpg)
Project Management…
Post tsunami situation – PM Lapses….• Lack of expertise in donors/NGOs
– Unprecedented commitment– Lack of experience in large scale construction– Lack of project management expertise– Lack of knowledge on procurement (e.g. D&B)– Approach to wrong parties for advice– Confused donors
![Page 7: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/7.jpg)
Project Management…
Infrastructure renewal and reconstruction concerns:
• Lack of clear policy by government– No building zone– Relocation of cities– City planning– Lack of co-ordinated
efforts/expertise/resources
![Page 8: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/8.jpg)
Project Management…
Infrastructure renewal and reconstruction concerns:
• Lack of clear expressed vision and commitment by government– Identification of long term
infrastructure needs– Need for professional persuasion
![Page 9: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/9.jpg)
Project Management…
Infrastructure renewal and reconstruction concerns:
• Shortage of skilled manpower– Man power planning models– Accelerated training– Sustainability concerns– Manpower training modalities
![Page 10: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/10.jpg)
Project Management…
Infrastructure renewal and reconstruction concerns:
• Limited technology options– Mainly conventional technologies– Lack of diffusion of low-cost/affordable
technologies– Lack of research on alternative
technologies/study assembly type technologies offered by other countries
![Page 11: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/11.jpg)
Project Management…
Infrastructure renewal and reconstruction concerns:
• Limited contractor capacity– Shortage of manpower, working capital and
machinery– Sustainability/down scaling after reconstruction– Limited technological capabilities (only 2
contractors with pre-cast technology)– Inadequate project management skills
![Page 12: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/12.jpg)
Project Management…
Infrastructure renewal and reconstruction concerns:
• Scarcity of materials –research/dissemination– Alternative materials– Alternative technologies
Indigenous/appropriate
![Page 13: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/13.jpg)
Project Management…
Infrastructure renewal and reconstruction concerns:
• Building standards/Design guides– Important revisions to incorporate
• Alternative technologies• Alternative materials• Seismic activity/tsunami resistant
structures
![Page 14: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/14.jpg)
Project Management…
Infrastructure renewal and reconstruction concerns:
• Project Management challenges– Effective stakeholder management
• When the client is not the end user• With line ministries/functional organisations
– Project Management in a disaster situation• No standard procedures• How to deal with many outside parties• Risk Management
![Page 15: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/15.jpg)
Project Objective
Capacity building of
stakeholders in
productively managing
tsunami recovery and
reconstruction projects
![Page 16: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/16.jpg)
Project Locations• Western Province
Colombo, Kalutara
• Southern ProvinceGalle, Matara, Hambantota
• Eastern ProvinceAmpara, Batticaloa, Trincomalee
• Northern ProvinceMullaitivu, Jaffna
![Page 17: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/17.jpg)
Limitation of Effective Resource Utilization
• Centralized top-down planning/decision-making
• Magnitude of the reconstruction
• Conflicting demands from diverse stakeholders (local, central and international)
![Page 18: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/18.jpg)
Proposed ActivitiesProfessional PM services on micro and mega housing and infrastructure projects with participation of
• National Water Supply and Drainage Board• Ministry of Housing and Construction• Urban Development Authority • Ministry of Highways and Transportation • Institute for Construction Training and Development• Institute of Project Managers Sri Lanka (IPMSL)• Institute of Project Managers in Sri Lanka (IPMSL) • NGO working on reconstruction projects
![Page 19: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/19.jpg)
Proposed ActivitiesProvide PM Training for several levels of staff under the topics of
• Project Management• Stakeholder Management• High Performance Teams• Risk and Uncertainty Management• Procurement and Logistics• Project External Issues• Infrastructure Management• Technology Implementation• Extreme Project Management• Project Assessments
![Page 20: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/20.jpg)
Expected OutcomesDeveloping a Comprehensive Project Management model with worldwide proven practices & principles which delivers followings;
• Improve project success and sustainability
• Reduce long term dependency on foreign expertise
• Strengthens the capacity of local authorities & communities
• Improving the collaboration between central decision-makers and local people
• Optimize the existing capabilities of Sri Lanka to manage their rehabilitation and rebuilding projects
![Page 21: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/21.jpg)
Partnerships and Coordinating
Working through The International Institute for Infrastructure Renewal and Reconstruction (IIIRR) where
University of Calgary
University of Moratuwa
are partners.
![Page 22: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/22.jpg)
Long-term Sustainability
Retaining and sustaining knowledge within• Local Communities
• Local Authorities
Development and delivery of a Masters program in Project Management with the collaboration of
• University of Moratuwa
• University of Calgary
![Page 23: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/23.jpg)
Current Research
• Stakeholder Analysis (Needs Analysis of Stakeholders)
• Mitigation Strategies and Better Planning (Decision Analysis)
![Page 24: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/24.jpg)
Mitigation Strategies and Better Planning
Detect - Local Seismic NetworkUniform (0,10)
Detect - Global Seismic NetworkUniform (0,10)
TsunamiUniform (0,3)
Process Seismic Info.
Uniform (0,2)
Info. Received by Analyst
Uniform (0,5)
Radio SignalUniform (0,1)
Process Seismic Info.
Uniform (0,2)
Validate with Global NetworkUniform (1,5)
Detected by Tsunami Warning
SystemUniform (5,20)
Detect - Tide Gauge System
Uniform (5,20)
Perform Seismic Analysis
Uniform (2,5)
Info. Received by TWC
Uniform (0,5)
Issue an AlertUniform (1,3)
Issue a Decision on EQ
Uniform (1,3)
Info Received - National
Uniform (0,5)
Issue a Detailed Analysis
Uniform (1,3)
Detect EQ - Human
Uniform (0,10)
Tsunami AnalysisUniform (2,5)
Detect - HumanUniform (5,20)
Info. Received - Local
Uniform (1,10)
Process Info - Human
Uniform (0,20)
Telephone SignalUniform (1,30)
Internet SignalUniform (0,2)
Inform Local Authorities for
PreparationUniform (5,30)
Dummy
Human Info Validated - Local
Uniform (3,10)
Satellite SignalUniform (0,2)
Tsunami Simulation Analysis
Uniform (5,10)
Start
Inform National Centre
Uniform (0,5)
National Office Makes a Decision
Uniform (0,5)
Inform Local Authorities for
InitiationUniform (5,30)
Evacuation Start
FS/FF
FS/FF
FS/FF
FS
FS
FS FS
FS FS FS
FS
FS
FS FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
FS
![Page 25: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/25.jpg)
![Page 26: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/26.jpg)
Infrastructure Needs and Concerns• Roads
• Schools• Community Centers
• Employment Villages/Centres
Entities Impacted by Tsunami
Immediate Needs and Concerns• Shelter• Job• Health
![Page 27: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/27.jpg)
Snap Shot Analysis
Standard of Living
+
-
Dec. 26, 2004
Aug. 2006
![Page 28: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/28.jpg)
Snap Shot Analysis
Standard of Living
+
-
Dec. 26, 2004
Aug. 2006
![Page 29: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/29.jpg)
Stakeholders
• Will all parties see Tsunami as an opportunity to develop better infrastructure and development projects?
![Page 30: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/30.jpg)
![Page 31: Project Management Capacity Building for Planning and ... · Project Management Capacity Building for Planning and Implementing for Tsunami Development Projects in Sri Lanka Dr. Janaka](https://reader034.fdocuments.in/reader034/viewer/2022042314/5f02da9c7e708231d40656a6/html5/thumbnails/31.jpg)