Project Management beyond critical chain scheduling (Journal Article Presentation)

22
© Gregor Strutz/Axel Völcker 1 MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 0 Innovation is new perception”, Drucker

Transcript of Project Management beyond critical chain scheduling (Journal Article Presentation)

Page 1: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

1

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 0

“Innovation is new perception”, Drucker

Page 2: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

Article Project management applications of the theory of

constraints beyond critical chain scheduling.

International Journal of Project Management, 20(1),

75-80, 2002

Author Steyn, H

Presented by Anubhav Dhiman & Onurhan Irkin

MPMD International Project

Management

Journal Article Presentation

2nd November 2016

Page 3: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

Executive

Summary

Title of Presentation:

Journal Article Presentation on Steyn, H. (2002). Project management applications of the theory of

constraints beyond critical chain scheduling.

Key Message of the Presentation:

‣ Application of Theory Of Constrains to scheduling of a single project to reduce project duration

and simplify project control (Critical Chain)

‣ The importance on product life cycle as opposed to the project life cycle in decision making

‣ Basic principles to application of TOC in concurrent projects: to manage shared resources, cost

management and risk management

Takeaways:

‣ Understanding and appreciation of the Theory of Constraints and its practical applications in the

field of project management

‣ Discussion on the TOC application in other project management areas

3

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 1

Executive Summary

Page 4: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

4

Ref: Shuba Kathikeyan, Apex Global

Curriculum Vitae of Prof. Hermanus de Villiers Steyn

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 2

Page 5: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

Executive

Summary

5Contents

1 Critical Chain - Project Buffer & Feeding Buffer 2

2 Multi-project environment - Maximising the number of concurrent projects 5

3 Managing resources in multi-project environments 7

4 Application of TOC to Project Cost Management & Risk Management 9

5 Conclusion - Ideas & Applications 10

Time (mins)

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 3

Page 6: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

6The concept of Critical Chain Taking resource limitations into account along with precedence

Ref: Steyn H. An investigation into the fundamentals of critical chain project management. International Journal of Project Management 19 (2000), 365

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 4

Page 7: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

7The concept of Project Buffer Aggregation leads to a reduction in risk

σ Σ = n ×σRef: Steyn H. An investigation into the fundamentals of critical chain project management. International Journal of Project Management 19 (2000), 365

Imp: commitments regarding the completion date are only made at project level.

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 5

Page 8: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

8The Concept of Feeding Buffer “JIT-with-buffers” Flexibility in tackling unforeseen changes and improving cashflow

Ref: Steyn H. An investigation into the fundamentals of critical chain project management. International Journal of Project Management 19 (2000), 365

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 6

Page 9: Project Management beyond critical chain scheduling (Journal Article Presentation)

Ref: Steyn H. An investigation into the fundamentals of critical chain project management. International Journal of Project Management 19 (2000), 365

© A

pple

Inc

9Why the emphasis on scheduling?

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 7

Page 10: Project Management beyond critical chain scheduling (Journal Article Presentation)

© J

ames

Bar

eham

, The

Ver

ge

10The Project and The Product lifecycle

September 16, 2016 - …

June 29, 2007 - July 15, 2008

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 8

Page 11: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

Executive

Summary

11Contents

1 Critical Chain - Project Buffer & Feeding Buffer 2

2 Multi-project environment - Maximising the number of concurrent projects 5

3 Managing resources in multi-project environments 7

4 Application of TOC to Project Cost Management & Risk Management 9

5 Conclusion - Ideas & Applications 10

Time (mins)

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 9

Page 12: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

12

“The optimum number of new product

development projects assigned concurrently to a

single engineer is two”, Clark & Wheelwright

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 10

Page 13: Project Management beyond critical chain scheduling (Journal Article Presentation)

© A

lexi

Fal

son,

Per

form

ance

Dri

ve

13

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 11

Page 14: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

Executive

Summary

14Contents

1 Critical Chain - Project Buffer & Feeding Buffer 2

2 Multi-project environment - Maximising the number of concurrent projects 5

3 Managing resources in multi-project environments 7

4 Application of TOC to Project Cost Management & Risk Management 9

5 Conclusion - Ideas & Applications 10

Time (mins)

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 12

Page 15: Project Management beyond critical chain scheduling (Journal Article Presentation)

15An iterative approach to allocate scarce resources in multiple concurrent projects

1. Identify CCR

2. Schedule sequence of work*

3. Insert CCR buffer before each task**

4. Invest in additional resource

5. Iterate and identify current constraint

CCR

CCR

CCR

CCR

Buffer

CCR

Buffer

CCR

Buffer

Project

Buffer

Project

Buffer

Project 1

Project 2

Ref: Steyn, H. (2002). Project management applications of the theory of constraints beyond critical chain scheduling

* Non-constraints are

subordinated to CCR

** Risk of a resource delaying

the CCR is addressed

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 13

Page 16: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

Executive

Summary

16Contents

1 Critical Chain - Project Buffer & Feeding Buffer 2

2 Multi-project environment - Maximising the number of concurrent projects 5

3 Managing resources in multi-project environments 7

4 Application of TOC to Project Cost Management & Risk Management 9

5 Conclusion - Ideas & Applications 10

Time (mins)

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 14

Page 17: Project Management beyond critical chain scheduling (Journal Article Presentation)

17More applications of TOC principle to project management 1. Cost Management

Ref: Steyn, H. (2002). Project management applications of the theory of constraints beyond critical chain scheduling

$161

$110 1.1

1.21

1.61*

Snowballing of costs

Planned cost vs Budgeted costPossible Issues

"No blame" culture

n ×σ

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 15

n ×σvs

*1.15

Page 18: Project Management beyond critical chain scheduling (Journal Article Presentation)

18More applications of TOC principle to project management 1. Cost Management

Ref: Steyn, H. (2002). Project management applications of the theory of constraints beyond critical chain scheduling

$161

$110 1.1

1.14

1.22*

Snowballing of costs

Planned cost vs Budgeted costPossible Issues

"No blame" culture

n ×σ

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 16

n ×σvs

$122

*1+ 5 × 0.1

Page 19: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

Executive

Summary

19Contents

1 Critical Chain - Project Buffer & Feeding Buffer 2

2 Multi-project environment - Maximising the number of concurrent projects 5

3 Managing resources in multi-project environments 7

4 Application of TOC to Project Cost Management & Risk Management 9

5 Conclusion - Ideas & Applications 10

Time (mins)

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 17

Page 20: Project Management beyond critical chain scheduling (Journal Article Presentation)

© P

MBO

K 5

20Ideas and Applications for the future

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 18

Project Selection

Procurement

Decision Making

Quantitative assessment of the

maximum number of projects an

organisation can do with the

current resources…

Page 21: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

21

“TOC approach puts together concepts that have

not been put together in the same way before and

is therefore considered an innovation”, Steyn

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 19

Page 22: Project Management beyond critical chain scheduling (Journal Article Presentation)

© G

rego

r Str

utz/

Axe

l Völ

cker

22

Thank you for your attention!

MPMD1.1 | Dhiman & Irkin | 2nd Nov 2016 | 20