    preparepm.com Tutorial - Project Integration Management

    This chapter covers key concepts related to Project Integration Management.

    1. The knowledge area of Project Integration Management consists of the following seven

    processes -Project Integration Processes

    Process Project Phase Key Deliverables

    Develop Project Charter Initiating Project Charter

    Develop Project Management Plan Planning Project Management Plan

    Direct and Manage Project Execution Execution Deliverables

    Monitor and Control Project Work Monitoring and Control Change Requests

    Perform Integrated Change Control Monitoring and Control Change Requests status updates

    Close Project or Phase Closure Final product

    2. A project charter

    o Formally authorizes the project.

    o Gives the objectives and business case

    o Identifies the Project Manager.

    o Generic enough not to change often.

    o Written by a Manager higher in authority than Project Manager.

    o Includes name, description, deliverables

    o A project does not start unless it has a Project charter.

    3. The Inputs, Tools and Techniques and Output of Develop Project Charter process are givenbelow.

    Develop Project Charter processInputs Tools & Techniques Outputs

    Project Statement of work Expert judgment Project Charter

    Business case

    Contract

    Enterprise environmental factors

    Organizational process assets

    4. During project execution the project team focuses on completing the tasks assigned. The Senior

    Management protects the project from changes and loss of resources. The Project Manager

    integrates all the pieces into the project as a whole.5. The Inputs, Tools and Techniques, and Outputs of the Develop Project Management Plan

    process are given in the table below.

    Develop Project Management Plan process

    Inputs Tools & Techniques Outputs

    Project charter Expert judgment Project Management Plan

    Outputs from planning processes

  • 7/30/2019 project integration mangement doc

    2/4

    Enterprise environmental factors

    Organizational process assets

    6. At the end of each phase of a project, a lessons learned document must be prepared. The lessons

    learned document defines what was done right, wrong etc. It is required to be completed in order

    for the project to be completed.7. Project Management Information System (PMIS) is a system that keeps track of status of all the

    project tasks. It is used to track the status of the project. The exam does not focus on any specific

    system (for example Microsoft Project ).8. Project Management Plan is developed by Project Manager with inputs from the team,

    stakeholders and management. Project Management Plan development is iterative. A Project

    Management Plan is bought into, approved, realistic and formal.9. A Project Management Plan includes -

    o Project Charter

    o Budget

    o Schedule

    o Resources

    o Scope Statement

    o WBS

    o Responsibility charts/assignments

    o Management Plans

    10. A Project Management Plan consolidates other management plans. These are:

    A. Scope management plan

    B. Requirement management plan

    C. Schedule management plan

    D. Cost management plan

    E.

    Quality management planF. Process improvement plan

    G. Human resource plan

    H. Communication management plan

    I. Risk management plan

    J. Procurement management plan

    The Project Management Plan also includes project baselines. These are:

    K. Schedule baseline

    L. Cost performance baseline and

    M. Scope baseline2. Project baseline refers to the original version of the project management plan. Once the project

    management plan is baselined, it may only be changed by raising a change request.

    3. Progressive Elaboration involves the process of taking a project from concept to detailed

    design.4. Kick-off meeting happens after the planning phase and before the project execution. It is

    typically used to communicate responsibilities of key stakeholders.

  • 7/30/2019 project integration mangement doc

    3/4

    5. Direct and Manage Project Execution process includes performing the work defined in the PMP

    to achieve project goals. The Input, Tools and Techniques and Outputs of this process are given

    below.

    Direct and Manage Project Execution process

    Inputs Tools & Techniques Outputs

    Project management plan Expert judgment Deliverables

    Approved change requestsProject management information

    system

    Work performance

    information

    Enterprise Environmentalfactors

    Change requests

    Organizational process assetsProject management plan

    updates

    Project document updates

    6. Monitor and Control project work process includes tracking and reviewing the progress of the

    project. The Input, Tools and Techniques and Outputs of this process are given below.Monitor and Control project work process

    Inputs Tools & Techniques Outputs

    Project management plan Expert judgment Change requests

    Performance reports Project management plan updates

    Enterprise environmental factors Project document updates

    Organizational process assets

    7. The change requests that get generated are evaluated as part of the Perform Integrated ChangeControl process. The change requests on the project deliverables and project artifacts are

    managed in this process. The Input, Tools and Techniques and Outputs of this process are given

    below.

    Perform Integrated Change Control process

    Inputs Tools & Techniques Outputs

    Project management plan Expert judgment Change request status updates

    Work performance information Change control meetings Project management plan updates

    Change requests Project document updates

    Enterprise environmental factors

    Organizational process assets

    8. Change Control Board is formed to review change requests. It is used to approve or rejectchange requests. After the project scope has been baselined, each requested change must go

    through a change control review process.

    9. Project Manager needs to be proactive in looking for deviations from project plan and then take

    timely corrective action. After that the Project Manager needs to evaluate the effectiveness ofcorrective action, and measure performance of corrective action, and then determine the need for

    further corrective action.

    10. When a change request is received, the following steps must be taken (in this order) -

  • 7/30/2019 project integration mangement doc

    4/4

    1. Evaluate (assess) the impact of change to the project

    2. Create alternatives including cutting other tasks, crashing, fast-tracking etc.

    3. Meet with management, sponsors etc.

    4. Meet with the customer if necessary

    2. The Close Project or Phase is the process of formal completion of all project related activities.

    The Input, Tools and Techniques and Outputs of this process are given below.Close Project or Phase

    Inputs Tools & Techniques Outputs

    Project management plan Expert judgment Final product, service or result transition

    Accepted deliverables Organizational process assets updates

    Organizational process assets

    3. At the end of each phase of a project, a lessons learned document must be prepared. The lessonslearned document defines what was done right, wrong etc. It is required to be completed in order

    for the project to be completed.

    Questions on Project Integration Management fundamentals are available in Questions by Topic.

    http://www.preparepm.com/pmp/integration.htmlhttp://www.preparepm.com/pmp/integration.htmlhttp://www.preparepm.com/pmp/integration.html