Knots Ahead of the Rest
HIRING OF FPSO FOR CLUSTER-7
12th
AUGUST 2013
-
Overall Project Timeline
2
-
Milestone Dates
MILESTONE BASELINE ACTUAL
Project Award 16-FEB-13 16-Feb-13
Commence Long Lead Item Procurement 2-Apr-13 2-Apr-13
Award to yard (Shipyard & Fabrication yard) 15-Jul-13
Donor Vessel Arrive at Shipyard 6-Aug-13
Commence Fabrication of Topsides 14-Oct-13
Complete Fabrication of Topside Module 27-Jun-14
FPSO Ready for Sailaway 30-Aug-14
FPSO Ready for Startup 4-Nov-14
Final Acceptance 15-Nov-14
-
Module/ Turret Lift Dates for Integration
MILESTONE BASELINE LIFT
DATES
Deck Crane 16-Apr-14
Module M15 Flare Tower 6-May-14
Module M70 E House 15-May-14
Module M55 Port Laydown / Chemical Injection Pkg 7-Jun-14
Module M10 Internal Turret 10-Jun-14
Module M60 Power Gen. Pkg / Fiscal Metering / Heli Refueling Skid 12-Jun-14
Module M30 Export Gas Comp. Pkg / Fuel Gas Sys. / Gas Metering / TEG Pkg / Flash Gas Comp. Pkg
14-Jun-14
Module M20 Flare Knock Out Drum 16-Jun-14
Module M35 Slug Catcher / CSU / PW Sys. / Cooling Medium Sys. 24-Jun-14
Module M50 Laydown / Water Inj. Sys. / Hypochlorination Pkg / Air Comp. Pkg / N2 Pkg 28-Jun-14
-
FPSO Module Construction & Lift Dates
5
15-MAY-14
M70 E-HOUSE
12-JUN-14
M60 POWER GEN. PKG
/ FISCAL METERING/
HELIDECK FUEL SKID
16-APR-14
STBD CRANE
28-JUN-14
M50 LAYDOWN/ W.I.
SYS/
HYPOCHLORINATION
PKG/ AIR COMP. PKG /
N2 PKG
24-JUN-14
M35 CSU/ SLUG
CATCHER/ PRODUCED
WATER COOLING
MEDIUM SYS
14-JUN-14
M30 EXPORT GAS
COMP PKG/ FUEL
GAS/ GAS METERING/
TEG PKG / FLASH GAS
COMP. PKG
06-MAY-14
M15 FLARE TOWER
16-APR-14
PORT CRANE
07-JUN-14
M55 PORT LAYDOWN/
CHEMICAL INJ. PKG
16-JUN-14
M20 FLARE KOD
10-JUN-14
M10 INTERNAL
TURRET
-
Overall Project Timeline
6
-
Turret General Arrangement
7
-
CHAIN / RISER PULL-IN PLAN
8
-
C7 Internal Turret M10
9
CAISSON
TURNTABLE
CHAIN TABLE
UPPER
BEARING
LOWER BEARING
CAISSON RING
STIFFENERS
PLATFORM 1
PLATFORM 2
PLATFORM 3
GEOSTATIONARY SIDE ROTATING (SHIP) SIDE
-
C7 Turret Internal Shaft arrangement
10
-
C7 Turret pull-in arrangement as designed
11
-
C7 Internal Turret Pull in 3D Arrangement
12
PULL IN
PULLEY
BEAM TURN
AROUND
SHAFT
TRANSLATION
IN AND OUT
-
C7 Turret Upper deck FEA results as designed
13
-
C7 Turret Geostationary Area above Deck
14
-
C7 Turret Piping as designed
15
PROPOSED PIPING
SHOWN ON THE
TURRET
GEOSTATIONARY
PART.
-
C7- Mooring pattern as designed
16
SYSTEM CHARACTERISTICS
Chain size : 130mm R3S Wire rope : 114mm Spiral strand SPR2Plus
PRETENSIONS
Ballast 100 MT Loaded 80 MT
-
C7 Mooring - Loads as designed
17
MOORING STRENGTH ANALYSIS RESULTS
Design Tensions :
Intact Condition:
Fairlead 754T Anchor 693T SLF Condition:
Fairlead 998 MT Anchor 940T
Design Offsets :
Intact Condition 20.1m (24% of Depth) SLF Condition 22.7m (27% of Depth)
-
C7 - Turret Mooring Response as designed
18
-
C7 Turret Shaft FEA results as designed
19
-
C7 Turret -Chain Stopper Analysis Results
20
Section cut:
Trunnion fillet stress surface bending stress
Clacker Contact area
overstressed
-
C7 Turret -Chain Stopper Analysis Results
21
Peak Strain = 0.010
-
C7 Turret Riser System
22
-
23
C7 Turret Chain table Arrangement
-
C7 Turret MWA details
24
-
TURRET INSTALLATION PROCEDURE
25
1. CAISSON INSTALLATION FROM TOP
2. SHELL CUT AT DRYDOCK
3. JACK UP THE CHAIN TABLE TO POSITION
4. INSERT SHAFT FROM TOP
5. FINAL WELDING AT DRYDOCK IWO SHAFT
-
CHAINTABLE INSTALLATION IN DRYDOCK
26
-
MACHINING REQUIRED LOCATIONS - TURRET
27
TURNTABLE LINERS
CRANE FLANGE
SWIVEL STACK
FOUNDATION PLATE
-
TURRET FABRICATION INTERFACES
28
SEPARATELY FABRICATED/CAST
-
Video on Installation
29
Video1
-
30
End of Presentation