Project Info - Concrete Canvas

2
® © Concrete Canvas Ltd. 2018 The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express www.concretecanvas.com [email protected] +44 (0) 345 680 1908 www ® *Geosynthetic Cementitious Composite Mat i # Project Info OCT 6 06 / 10 / 15 CC13 TM Bulk Rolls 7,000m 2 Transverse layers Vazante, Minas Gerais, Brazil Cabral Engenharia CC was used to line drainage channels and a drainage lagoon constructed to decant alkaline mine water Completed lagoon In October 2015, Concrete Canvas ® GCCM* (CC) was used to line a newly constructed drainage lagoon at Votorantim Metais Zinco mine in Vazante, Minas Gerais, Brazil. Alkaline mine water would be transported to the lagoon via a series of drainage channels, also lined with CC, to be decanted and treated. Installation was carried out during the rainy season which would have led to programme disruption had shotcrete been used. CC, however, can be installed during inclement weather allowing for a faster and easier installation. CC also negated any of the health and safety risks associated with shotcrete such as rebound. The remote location of the mine also meant using CC was advantageous as transport costs would be drastically reduced. The material was supplied by SPI Engenharia e Representações. Vegetation was removed and the lagoon slopes graded and compacted. Bulk rolls of CC13 TM were mounted onto a spreader beam and unrolled down the lagoon slope faces, before being cut to specific profile length. Subsequent layers overlapped the previous by 100mm and pegs were inserted through the overlaps at the crest. Everbuild Clearfix adhesive sealant was used to join the overlaps, and the joints were compressed to ensure an optimal bond. Hydration was achieved using a water truck and hose with spray nozzle attached. 7000m 2 of CC13 TM were installed in 2 months, compared to the 4+ months it would have taken with shotcrete. CC was able to easily accommodate pipe protrusions and be installed during rain and high temperatures of up to 42 o C.

Transcript of Project Info - Concrete Canvas

Page 1: Project Info - Concrete Canvas

®

© Concrete Canvas Ltd. 2018The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express

[email protected]+44 (0) 345 680 1908 www®

*Geosynthetic Cementitious Composite Mat

i

#

Project Info

OCT

6 06 / 10 / 15

CC13TM Bulk Rolls

7,000m2

Transverse layers

Vazante, Minas Gerais, Brazil

Cabral Engenharia

CC was used to line drainage channels and a drainage lagoon constructed to decant alkaline mine water

Completed lagoon

In October 2015, Concrete Canvas® GCCM* (CC) was used to line a newly constructed drainage lagoon at Votorantim Metais Zinco mine in Vazante, Minas Gerais, Brazil.

Alkaline mine water would be transported to the lagoon via a series of drainage channels, also lined with CC, to be decanted and treated. Installation was carried out during the rainy season which would have led to programme disruption had shotcrete been used. CC, however, can be installed during inclement weather allowing for a faster and easier installation. CC also negated any of the health and safety risks associated with shotcrete such as rebound. The remote location of the mine also meant using CC was advantageous as transport costs would be drastically reduced. The material was supplied by SPI Engenharia e Representações.

Vegetation was removed and the lagoon slopes graded and compacted. Bulk rolls of CC13TM were mounted onto a spreader beam and unrolled down the lagoon slope faces, before being cut to specific profile length. Subsequent layers overlapped the previous by 100mm and pegs were inserted through the overlaps at the crest. Everbuild Clearfix adhesive sealant was used to join the overlaps, and the joints were compressed to ensure an optimal bond. Hydration was achieved using a water truck and hose with spray nozzle attached.

7000m2 of CC13TM were installed in 2 months, compared to the 4+ months it would have taken with shotcrete. CC was able to easily accommodate pipe protrusions and be installed during rain and high temperatures of up to 42oC.

Page 2: Project Info - Concrete Canvas

“We were very happy with the lagoon lining, this installation will become a reference within the Votorantim Group”

Sebastiao Alves da Silva Site Operations Manager,

Votorantim Metais

“We are very happy that there were zero personal accidents in the 63 days on lining and 75 days of all works”

Marcelo Almeida Santos Health and Safety, Votorantim Metais

© Concrete Canvas Ltd. 2018The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express

[email protected]+44 (0) 345 680 1908 www®

®

Mine site

CC pegged at the crest

Compressing the joints

Pipe penetration