Page 1 of 22 PROJECT FACT SHEET ADDENDUM NO.1 CAMPUS WIDE SUB-METERING EQUIPMENT AND ENERGY MANAGEMENT SOFTWARE UNIVERSITY OF SOUTH FLORIDA SAINT PETERSBURG Bidders are advised that the Project Fact Sheet for the above noted project are hereby modified, corrected, and supplemented as follows in accordance with this Addendum Number One. ITEM NO.1: The priority buildings are: Poynter Lab, Residence Hall One (RHO), College of Business (COB), and University Student Center (USC). ITEM NO.2: All data shall be stored and retrievable from the cloud. ITEM NO.3: Residence Hall One (RHO) main electrical is Square D Power Style 1600 amp, 480/277 volt ITEM NO.4: Residence Hall One (RHO) floor level electrical panels are 500 amp, 208/120 volt. All breaker spaces are full. Reference voltage may be taken from the other panel in the room that does have spaces. ITEM NO.5: Residence Hall One (RHO) main domestic potable water pipe is a 4 inch. ITEM NO.6: The Central Utility Plant (CUP) will require two (2) new Chilled Water BTU meters. There is an existing Onicon model F-1110 flow meter in the 12 inch chilled water supply line from chillers no.1 and no.2 which may be able to be used with the required new BTU meter and new matching supply and return chilled water temperature sensors. A second BTU meter, flow meter and matching temperature sensors are needed for the 12 inch chilled water supply line from chillers no.3 and no.4. There is an existing tap in the piping that may be able to accept a flow meter. ITEM NO.7: The Central Utility Plant (CUP) has an existing water meter with pulse output at the west end of the cooling tower yard in the 3 inch domestic potable water main serving the water treatment for

Transcript of PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative...

Page 1: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 1 of 22

PROJECT FACT SHEET – ADDENDUM NO.1

CAMPUS WIDE SUB-METERING EQUIPMENT AND ENERGY MANAGEMENT SOFTWARE

UNIVERSITY OF SOUTH FLORIDA SAINT PETERSBURG

Bidders are advised that the Project Fact Sheet for the above noted project are hereby modified,

corrected, and supplemented as follows in accordance with this Addendum Number One.

ITEM NO.1:

The priority buildings are: Poynter Lab, Residence Hall One (RHO), College of Business (COB),

and University Student Center (USC).

ITEM NO.2:

All data shall be stored and retrievable from the cloud.

ITEM NO.3:

Residence Hall One (RHO) main electrical is Square D Power Style 1600 amp, 480/277 volt

ITEM NO.4:

Residence Hall One (RHO) floor level electrical panels are 500 amp, 208/120 volt. All breaker

spaces are full. Reference voltage may be taken from the other panel in the room that does

have spaces.

ITEM NO.5:

Residence Hall One (RHO) main domestic potable water pipe is a 4 inch.

ITEM NO.6:

The Central Utility Plant (CUP) will require two (2) new Chilled Water BTU meters. There is an

existing Onicon model F-1110 flow meter in the 12 inch chilled water supply line from chillers

no.1 and no.2 which may be able to be used with the required new BTU meter and new

matching supply and return chilled water temperature sensors. A second BTU meter, flow meter

and matching temperature sensors are needed for the 12 inch chilled water supply line from

chillers no.3 and no.4. There is an existing tap in the piping that may be able to accept a flow

meter.

ITEM NO.7:

The Central Utility Plant (CUP) has an existing water meter with pulse output at the west end of

the cooling tower yard in the 3 inch domestic potable water main serving the water treatment for

Page 2: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 2 of 22

the cooling towers. The signal may be able to be converted through a JACE for the needs of this

project.

ITEM NO.8:

The Central Utility Plant (CUP) has three existing main switchboards:

a. MSB-1 Square D power style 2000 amp.

b. MSB-2 GE Spectra APN 1600 amp.

c. MSB-3 Square D QED 3000 amp.

ITEM NO.9:

The University Student Center (USC) will require a new Electric sub-meter.

ITEM NO.10:

The Poynter Lab building will also have 40 KW Solar panels with Solar Edge Inverters with

possible data collection port, installed at the end of May. These shall be monitored with an

Electric Sub-Meter and displayed in the dashboard similarly to the solar panels at the parking

garage.

ITEM NO.11:

The Poynter Lab building has a chilled water Onicon F-1210 flow meter which may be able to be

used with the required new BTU meter and new matching supply and return chilled water

temperature sensors.

ITEM NO.12:

The Poynter Lab main electrical panel is GE Spectra Series 800 amp. 480/277 volts

ITEM NO.13:

The Science and Tech. Building (STG) has a 3 inch domestic potable water main, inside the

same mechanical room as the existing BTU meters.

ITEM NO.14:

The Integration of existing controls will require bring in points from the various control systems.

There are primarily Trane controls on campus however Allerton Controls are at the USC

building. There are also various versions of the Trane systems such as Tracer Summit, Tracer

SC, etc.

ITEM NO.15:

All new meters to be utility grade meters (except domestic potable water). Utility grade meter

shall be equal to or better than the following standards:

Electric Meters: ASNI C12.20 5S (0.2 or 0.2S) power and energy metering 2x digital input / 1x

digital input, or better. UL listed. Installed per manufacturing instructions.

Chilled Water BTU Meters: Onicon System 10 BTU meter with Onicon flow meter and Onicon

matching solid-state temperature sensors custom calibrated using N.I.S.T. traceable

Page 3: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 3 of 22

temperature standards, current based signal (mA) unaffected by wire length. Installed per

manufacturing instructions.

Domestic Potable Water Meter: Accuracy plus or minus 1-1/2% of reading. Does not need to be

utility grade

ITEM NO.16

All new meter output systems must communicate using a system equal to BACnet. Modbus is

allowed at the meter level but must be converted to BACnet in the gateway to be available for

future use.

ITEM NO.17

Pay for all required licenses, fees, inspections and permits. Submit for permitting through

USFSP permitting office.

ITEM NO.18

All line voltage electrical work must be performed by a Florida licensed electrical contractor.

ITEM NO.19

All information technology and communication (IT) structured cabling installations shall be

designed and overseen by a BICSI (Building Industry Consulting Service International) certified

RCDD (Registered Communications Distribution Designer). The design shall be per the TDMM

manual.

ITEM NO.20

All cabling between the patch panel and meter controllers shall be CAT6.

ITEM NO.21

Multi-port controllers are allowed, with a single port output to the patch panel

ITEM NO.22

All data storage, software, dashboards & phone apps shall be cloud based and accessible from any location. ITEM NO.23

Mine existing data from the existing building automation systems on campus: Trane and

Allerton. All BACnet is at the system level BCU level. A fee may be required to Trane and

Allerton to elevate points that are not already available.

ITEM NO.24

USFSP will provide IP addresses and internet connection data ports inside existing IT closets in

each building. All other cabling, hardware and software must be provided by the vendor.

ITEM NO.25

All systems must comply with USFSP – Network Standards and Guidelines.

Page 4: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 4 of 22

ITEM NO.26

Level 5 – Advance Diagnostics and Analytics shall include human data analysis of all mapped

data points. At a minimum, a quarterly report, evaluations and energy improvement solutions

shall be provided.

ITEM NO.27

Provide preliminary pricing at the time of contractor selection Submittals Due date. Pricing

should be broken down for a la cart (separately priced) selection of options and items.

ITEM NO.28

Contractor selection Submittals may exceed 20 pages.

ITEM NO.29

The vendor is to provide connectivity with the City of Saint Petersburg and USF-Tampa Campus

ITEM NO.30

USFSP reserves the right not to award a contract for this project.

ITEM NO.31

All funds must be allocated prior to June 30th, 2017.

ITEM NO.32

A final completion date of 6 months from the notice to proceed. Liquidated damages of $100 per

day will be imposed if not complete.

ITEM NO.33

Provide all materials, equipment and labor necessary for a complete and properly functioning

installation in accordance with all applicable codes. Install all work in accordance with the latest

edition of all applicable regulations and governing codes, including the regulation of the utility

companies serving the project. Where a conflict I code requirements occurs the more stringent

requirement shall govern.

ITEM NO.34

All equipment and devices shall bear U.L. label or a label of an industry recognized approved

testing agency for said item of equipment or device. All electrical devices must be U.L.

approved.

ITEM NO.35

Check site and existing conditions thoroughly before providing a bid price. Advise owner’s

representative of discrepancies or questions before final bidding.

ITEM NO.36

Provide all required openings to accomplish the work. Provide sleeves or other approved

methods to allow passage of items install. Re-seal all openings and return all surfaces and

finishes to match existing conditions.

Page 5: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 5 of 22

ITEM NO.37

Any interruption of existing mechanical and electrical services shall be coordinated in advance

with the owner’s representative. This includes, but is not limited to, services providing chilled

water, electricity, data, potable water, or other critical systems as may be pertinent to this

particular project. Service interruption times and duration of services shall be decided by the

owner’s representative. Provide appropriate provisions (e.g. isolation shut-off valves and similar

items) as necessary to accommodate the required service interruptions. If shutdowns cannot be

accommodated, provide means for “wet” tapping or “hot” tapping of systems.

ITEM NO.38

All equipment shall be thoroughly cleaned of all dirt, oil, debris, etc. Any dents, scratches or

other visible blemishes shall be corrected and the appearance of the equipment made “like new”

and to the satisfaction of the owner’s representative. Upon completion, and before final

acceptance of the work, all debris, rubbish, leftover materials, tools and equipment shall be

removed from the site.

ITEM NO.39

Near conclusion of work and not less than 10 days prior to substantial completion inspection,

submit a technical information document containing all final shop drawing and submittal

information for the project. Submit shop drawings for all work including all items, services and

systems provided for the project. Provide in a degree which is both quantitatively and

qualitatively equal to that installed. Submit owners and operation manuals of all equipment

installed. The technical information document shall consist of one or more adequately sized,

hard-cover, 3-ring binders for 8-1/2”x11” sheets, and digital copies of the same material on a

CD.

ITEM NO.40

Submit for checking a specific set of written operation instructions on each item which requires

instructions to operate. After acceptance, insert information in each technical information

document.

ITEM NO.41

Submit for acceptance maintenance information consisting of manufacturer’s printed

instructions and parts lists for each major item of equipment. After acceptance, insert

information in each technical information document.

ITEM NO.42

When all work is completed, provide the owner’s representative training an “instruction in

operation conference”. At the conference, the contractor shall review with the owner all

appropriate information. The training and conference is to be videotaped for future review.

Provide digital video files on DVD of the training and conference sessions. Training shall be up

to 40 hours by a factory authorized representative.

Page 6: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 6 of 22

ITEM NO.43

All warranties shall include parts and labor. The warranties shall be by the contractor to the

owner to replace for the owner any defective workmanship, equipment, or material which has

been furnished under this contract at no cost to the owner for a period of one year from the date

of acceptance of the system by the owner’s representative in writing. This warranty shall also

include reasonable adjustments to the system required for proper operation during the warranty

period. Explain the provisions of warranty to the owner’s representative at the “instruction in

operation conference”. The optional extended 5 year warranty, if accepted, will provide for the

same provisions as a one year warranty.

ITEM NO 44. 1) The SQ footage for the following buildings:

Lynn Pippenger Hall (College of Business)- 68,000 sq. ft. Poynter Warehouse Lab- 9,960 sq. ft. Barnes & Noble/Parking Garage- 359,595 sq. ft. Bayboro Hall- 35,669 sq. ft. Central Utlity Plant- 3,392 sq. ft. Coquina Hall- 35,190 sq. ft. Davis Hall- 69,738 sq. ft. Harbor Hall- 30,472 sq. ft. Residence Hall One- 125,000 sq. ft. Student Life Center- 36,547 sq. ft. Sciene & Tech Building- 34,027 sq. ft. University Student Center- 92,770 sq. ft.

ITEM NO 45. 2) Refer to campus map on website and as builts for building locations on campus. The main campus address is 140 7th Ave. South St. Petersburg, FL 33701. http://www.usfsp.edu/visit/files/2015/04/USFSP-Campus-Map.pdf

ITEM NO 46.

Total building energy consumption for the 2015-2016 fiscal year was 17,498,995 kWh at a total

cost of $1,562,237.07

ITEM NO 47. International companies may submit a response to the RFP and were not required to attend the pre-submittal meeting. However, you will have to demonstrate how you will be able to manage this project (i.e. Issues that will arise and need to be resolved asap, internal IT security, constant communication, etc.) while working from an international platform. Also, you must be able to formally meet in person due to State University System regulations. ITEM NO 48. Hard copies of the proposals are required and will not be accepted through email.

Page 7: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 7 of 22

ITEM NO 49. The PQS form is located on our www.usfsp.edu/sustainability/ below the RFP under “Current Projects” ITEM NO 50. As built drawings, will be provided in a zip file of the buildings along with the Addendum (College of Business & Poynter Lab as builts are currently unavailable but will be provided as soon as they are available). Please refer to these plans for any questions in regards to Electrical, Plumbing and HVAC. ITEM NO 51. The University requires documentation of work performed and direction by a registered Florida Professional Engineer for mechanical and electrical work performed. ITEM NO 52. The contractor will need to have liability insurance meeting and provide the University with a Certificate of Liability Insurance form which will include USF as the certificate holder. USF requires general liability to be a minimum amount of $1,000,000.00. When adding USF as the certificate holder please address the holder as “University of South Florida Board of Trustees”. ITEM NO 53. We have limited historical utility data. Utility data is available per meter/building (limited), per month (limited), per cost (limited), per usage, per fiscal year. For the solar array we have data that has been stored for the past two years through Lucid (Building OS) and SolarEdge.

ITEM NO 54.

USFSP understands that Software-As-A-Service (SAAS) will likely include an annual cost which

we are prepared to handle. It would be best for you, the vendor, to separate the costs

individually in order for the University to determine what will be a one-time cost (i.e.

hardware/installation) in addition to what would be a reoccurring cost (i.e. SAAS). This will help

us better determine future budgeting beyond our current finance

Page 8: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 8 of 22

ITEM NO 55.

The newly renovated Poynter Lab building will have a 40kW solar carport array (120 total 72 cell

Canadian Solar panels) constructed to the north end of the building which will help power the

building through the MDP. Currently our subcontractors are conducting the energy model of the

building to better determine the volts/amps. The building itself had a major renovation and

change-of-function thus past energy models for this building are insufficient. Thus, the energy

data for this building is pending.

ITEM NO 56.

In regards to metering the kwh consumption of Barnes and Noble separately from the parking

garage. We figure to just submeter the parking garage as a whole (Barnes & Noble included),

however, Barnes & Noble likely consumes most of the buildings energy usage thus if funding

allows then it would be great to meter them separately.

ITEM NO 57. Due to building priority and funding constraints, Harbor Hall was not identified as a key priority

for this project as compared to several other buildings evaluated.

ITEM NO 58.

The USFSP Facilities Services crew is interested in pursuing energy analytic packages.

ITEM NO 59.

Points read from meters at a minimum: chilled water (BTU, GPM, Temp-in, Temp-out), electric

(KWH, KW) and domestic potable water (GPM). Read other points as needed to enhance

dashboard outputs. Electrical data however is the immediate priority in terms of current project

funding.

ITEM NO 60. Preferred location of the potable water meters should be inside the building, but will depend on each building.

ITEM NO 61. Network drop costs will vary based on the level of difficulty and material for each drop. Complications such as drilling through walls, running conduit, cable fishes that require two people increase the man hour costs. Extra materials such as conduit, cable hangers and firewall putty can also change quotes.

Page 9: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 9 of 22

ITEM NO 62.

Bulk metering at the building level is preferred over per floor metering.

ITEM NO 63.

Building monitoring should be made the priority for this project (in order to collect data and set

baselines – data should be able to be stored for several years for research purposes); then

USFSP can focus on retro-commissioning to better identify inefficiencies.

ITEM NO 64.

Kiosk displays are existing touch screen units located throughout the campus, at 7 locations:

Bayboro Hall (BAY), Parking Garage (FPF), University Student Center (USC), Student Life

Center (SLC), Harbor Hall (HH), Poynter Nelson Library (POY) and Science Technology Center

(STG). The same data is transmitted and displayed on each kiosk. The kiosks are interactive.

ITEM NO 65.

Campus News on the Advanced Dashboard, Smart Phone and Digital Kiosks should display

similar energy information.

In addition to energy information, and added selection is, Campus News. The Campus News

shall be easily updatable by the owner’s representative. Such events as: Semester begin dates

(Fall, Spring, Summer session A, Summer session B, Summer session C), Registration begin

dates, Registration end dates (without having to pay $100 late fee), Financial Aid deadlines,

Class Withdrawal deadlines, Final Exam begin dates, Deadlines for Graduation application,

Holidays, and other Deadlines, Events, How to be a part of said event, etc., shall be able to be

incorporated into the displays.

Page 10: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 10 of 22

ITEM NO 66.

Advanced Dashboard, Smart Phone and Digital Kiosks.

Some information on the existing Kiosks are of interest to keep and some can go. Coordinate

final look and display information through Brian Pullen. The following information is of interest

on the displayed information:

a. 3-D map of campus including building acronyms.

b. Selection of each building and solar panels will open a new screen with specific

information on that building or solar panel.

c. Information for the specific building will include: name, acronym, square footage, solar

panel KW rating, real time energy use, weather normalization.

d. Incorporate a weather widget on each page.

e. Green tips/news.

f. Display energy use for each building (graphs)

g. Compare building energy use to other similar buildings in Florida.

h. Compared floor to floor energy use for the Residence Hall One (RHO) building.

i. Solar panels display should show:

a. Energy generated from Solar Panels / Photovoltaics (PV).

b. Energy delivered to the grid.

c. Energy delivered to the batteries.

d. Energy consumed from Solar Panels / Photovoltaics (PV).

e. Energy consumed from the batteries.

f. Energy used on campus.

j. Campus News (see above item).

k. Clubs.

*ALL SOFTWARE SOLUTIONS MUST ALLOW THE UNIVERSITY OF SOUTH FLORIDA

SYSTEM TO OWN THE DATA (I.E IF CONTRACT ENDS, USF RESERVES THE RIGHT TO

KEEP THE DATA).

Page 11: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 11 of 22

ITEM NO 67.

The existing Kiosks have the following displays. There are some feature that are of interest to

keep however there is a desires to redo how and what is displayed. The following images are

for reference only:

Page 12: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 12 of 22

Page 13: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 13 of 22

Page 14: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 14 of 22

Page 15: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 15 of 22

Page 16: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 16 of 22

Page 17: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 17 of 22

Page 18: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 18 of 22

Page 19: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 19 of 22

Page 20: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 20 of 22

Page 21: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 21 of 22

Page 22: PROJECT FACT SHEET ADDENDUM NOWhen all work is completed, provide the owner’s representative training an “instruction in operation conference”. At the conference, the contractor

Page 22 of 22

There are approximately 32 other Green Tips pages.

End of Addendum No. 1.