Project Execution Planning for Building Information Modeling
description
Transcript of Project Execution Planning for Building Information Modeling
Project Execution Planning for Building Information Modeling
A buildingSMART Alliance project sponsored by:• The Charles Pankow Foundation• Construction Industry Institute (CII)• Penn State Office of Physical Plant (OPP)• PACE
Progress Meeting #4 – October 31st, 2008
Conference Call Agenda
1. Introductions2. Project Overview3. Progress Report4. Discussion of Project and Progress5. Set Up Next Meeting Time
Team Members
• Board of Advisory• Deke Smith – Executive Director of buildingSMART Alliance (Industry Champion)• Victor Sanvido – Ph.D., Senior Vice President, Southland Industries• Francois Grobler – Ph.D., US Army CERL and IAI - North America• Steve Hagan – Project Knowledge Center, U.S. General Services Administration• Soad Kousheshi – President, AEC Strategy• Ed Gannon – Manager of Design Services, Penn State Office of Physical Plant• Mark Falzarano – Barton Malow Company• Mark Butler – HDR• Derek Cunz – Director of Project Development, Mortenson Construction• Mark Konchar- Vice President – Balfour Beatty Construction
• CIC Research Program Team Members• John Messner – Director of the CIC Research Program• Chimay Anumba – Professor and Head of Architectural Engineering• Sam Hunter – Assist. Professor of Psychology• Craig Dubler – PhD Student, Architectural Engineering (Construction)• Colleen Kasprzak – MS Student, Architectural Engineering (Operations)• Chitwan Saluja – MS Student, Architectural Engineering (Planning)• Nevena Zikic – MS Student, Architectural Engineering (Design)• Shane Goodman – BAE/MAE Student, Architectural Engineering
• Sponsor Represenatives• Bob Tener – Director, The Charles Pankow Foundation • Steve Thomas – Director of Research, The Construction Industry Institute
Project Overview
• Identify BIM methods and implementation strategies organized by project phase• Planning, Design, Construction, Operations
• Develop implementation guidelines and best practice methods
• Disseminate the results• BIM Execution Planning Guide• Interactive execution planning computer tool• Presentations at national conferences e.g. buildingSMART, AIA, AGC
BIMForum, etc.• Articles in industry and academic publications
Progress Report
• Continuously developing concept for BIM Execution Planning Process.
• Wrapping-up Interview process.• Conducted focus group discussion at PACE
(10.16.2008)• Reviewing additional resources with similar scopes for
collaborative efforts and/or additional value to our guide.
• BIM Ex Class • Developed BIM uses on wiki through interviews
and lit review• Currently investigating case study projects
Plan
Design
Construct
Operate
Design Communication System Analysis Estimation Scheduling
Existing Conditions Modeling Programming
Design Authoring Design Reviews
(Constructability, 3D Design Coordination, Virtual Mock-ups)
Site Analysis Engineering Analysis
(Structural, Energy, Lighting , CFD, IAQ Evaluation, Thermal Performance)
Code Validation (Emergency Evacuation, Security Analysis)
LEED Evaluation
Site Selection Preliminary Cost
Estimation
Cost Estimation
Phase Planning
Phase Planning (Tenant Fit-out)
3D MEP Coordination
Digital Fabrication 3D Control and Planning Record Model Asset Management Space
Management/ Tracking Disaster/Emergency Planning
3D System Design
Building Performance Analysis
Unit Price Estimating
Maintenance Cost Estimation
4D Planning Site Utilization
Planning
Building Maintenance
Renovation Coordination
BIM USE from WIKI
CLICK HERE(Link to WIKI)
Operation Construction Design Planning
E SD S
First Pass = Use
Second Pass = Who creates it? What Platform?
Operation Construction Design Planning
E SD S E SD S E SD S
E SD S E SD S E SD S E SD S
Execution Planning Process Concept:“Begin with the End in Mind”
Execution Planning Process
BIM Use Identificati
on
•Manual review of BIM uses•Decision Support System to proceed from project characteristic to recommended BIM uses
BIM Use Definition
•Documentation of BIM Uses to be performed along with the underlying goal for pursuing each defined use.
BIM Execution Plan
Development
•Development of a detailed plan an procedure for each use and the information flow from between uses•Performed through ‘
Project X
BIM Execution
Plan
Execution Planning Categories
•Critical project overview information, contractual requirements related to BIM, and key project contacts
Project Reference Information
•Include model elements by discipline, level of detail, and specific attributesBIM Scope Definitions
•Identification of the process for creating, reviewing and modifying the model. Include information exchange requirements.
Model Development Process
•Define the roles of each organization along with responsibilities•Define contracting strategies for organizations
Organizational Roles and Responsibilities
•Electronic communication procedures•Meeting communication procedures
Communication Procedures
•Identify the methods to ensure model accuracy and comprehensiveness
Model Quality Control Procedures
BIM USE Identification Prototype
CLICK HERE
Project Input
Project Characteristics + BIM Objectives
Decision SupportTool
Decision Matrix
BIM Use Identification Process
BIM GOALS
Design Support System: Matrix Model
Next Tasks
• Develop detailed execution planning process model• Complete the content analysis of interviews for each
phase and for BIM uses• Perform Case Studies• Develop detailed list of content for BIM Execution Plan• Identify next focus group locations
• buildingSMART Alliance Conf (?)• PACE Seminar in Spring 09
Example: Interview Content Analysis
Additional Resources
• Autodesk Communication Specifications• AIA BIM Exhibit• AGC Guide to BIM• Australian BIM National Guidelines• Key success factors for adopting BIM (Gang Lee)
• Board Members:Feel free to add more if they come to mind.
Discussion
Ways that you can help us:• Feedback:
• BIM Uses (posted at bimex.wikispace.com)• Process overview / format
• Identify potential case study projects for BIM Execution Planning course
• Projects to test drive BIM Execution Plan Process• Share BIM Execution Plans if you have them and can
share them
Thank You
Next Meeting Time?
Video conferencing during meetings – need friend of PSU Account
SIGN UP HERE:
https://fps.psu.edu/mkuser/index.html