Project Die Design Tooling UTM 20112012

download Project Die Design Tooling UTM 20112012

of 39

Transcript of Project Die Design Tooling UTM 20112012

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    1/39

    SMR 4712

    TOOLING FOR PRODUCTION

    GROUP ASSIGNMENT: DIE DESIGN

    2011/2012-SEM 1

    LECTURER

    PM ZAINAL ABIDIN

    SECTION 02

    NO. GROUP MEMBERS MATRIX NO

    Faculty of

    MechanicalEngineering

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    2/39

    TABLE OF CONTENTS

    CHAPTER TITLE PAGE

    1 INTRODUCTION 1

    1.1 Part 1

    1.2 Station and Operation Sequence 2

    2 CUTTING FORC 3

    2.1 Station One 3

    2.1.1 Blanking (Oval Contour) 3

    2.1.2 Piercing (2 holes of 4 mm) 4

    2.2 Station Two 5

    2.2.1 Embossing (Rectangular Offset Embossing) 5

    2.2.2 Slotting (Square Fillet Feature) 6

    2.3 Station Three 6

    2.3.1 Embossing (5 Interior Offset Emboss of 12) 7

    2.3.2 Embossing (2 Interior Offset Emboss of 16) 8

    2.3.3 Piercing (5 holes of 4 mm) 9

    2.3.4 Piercing (2x Pre-pierced Holes) 10

    2.3.5 Beading (V-Bead) 12

    2.4 Station Four 13

    2 4 1 E tr ding 13

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    3/39

    4 PUNCH AND DIE 16

    4.1 Clearance 164.2 Determining Size 16

    4.2.1 Station One 16

    4.2.2 Station Two 17

    4.2.3 Station Three 18

    4.2.4 Station Four 19

    5 DIE COMPONENT 20

    5.1 Thickness of Punch Holder and Die Holder 20

    5.1.1 Station 1 20

    5.1.2 Station 2 21

    5.1.3 Station 3 22

    5.1.4 Station 4 23

    6 PRESS CAPACITY 24

    6.1 Calculation for Press Capacity of Each Station 24

    7 SCRAP STRIP LAYOUT 25

    7.1 The Scrap Strip Layout 25

    7.2 Scrap Strip Allowances 25

    7.3 Strip Area per Blank Calculations 26

    7.3.1 Single Row, One Pass Positioning 26

    7.3.2 Number of Blanks per Strip 26

    7.3.3 End Waste of Single Pass Strip 27

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    4/39

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    5/39

    CHAPTER 1

    INTRODUCTION

    1.1 Part

    Assumption Made: Material is made of Soft Steel 0.3% C

    Shear Resistance (SR) = 32 kgf/mm2

    Tensile Strength (TS) = 40 kgf/mm2

    Thickness = 0.5 mm

    1

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    6/39

    1.2 Station and Operation Sequence

    Station Operation Feature

    Station 1 Blanking Blank Contour

    Piercing 2x 4mm

    Station 2 Emboss Rectangular Offset Emboss

    Slotting 2x Square Fillet

    Station 3 Emboss 5x 14mm

    2x 16mm

    Piercing 5x 4mm

    2x 3.16mm

    Beading 1x 83mm V Bead

    2x 43mm V Bead

    Station 4 Extruding 2x 2.5mm Wall

    2

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    7/39

    CHAPTER 2

    CUTTING FORCE

    2.1 Station One

    2.1.1 Blanking (Oval Contour)

    3

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    8/39

    Blanking Force = SR x A

    = 32 kgf/mm2x 316.42 mm

    2

    = 10125.44 kgf

    2.1.2 Piercing (2 holes of 4 mm)

    Perimeter = 2 x 2r

    = 2 x 2 x 2mm

    = 25.13 mm

    Area to be Cut = Perimeter x Thickness

    = 25.13mm x 0.5 mm

    = 12.57 mm2

    4

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    9/39

    2.2 Station Two

    2.2.1 Embossing (Rectangular Offset Embossing)

    Perimeter = 315.41 mm

    Embossing Force = TS x t x L

    = 40 kgf/mm2

    x 0.5 mm x 315.41mm

    = 6308.2 kgf

    5

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    10/39

    2.2.2 Slotting (Square Fillet Feature)

    Perimeter = 74 mm (measured using UG software)

    Area to be Cut = Perimeter x Thickness

    = 74 mm x 0.5 mm

    = 37 mm2

    Piercing Force = SR x A

    = 32 kgf/mm2x 37 mm

    2

    = 1184 kgf

    Total Cutting Force at Station Two = 6308.2 kgf + 1184 kgf

    = 7492.2 kgf

    6

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    11/39

    2.3.1 Embossing (5 Interior Offset Emboss of 12 mm)

    Sectional View of Interior Offset Emboss

    7

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    12/39

    2.3.2 Embossing (2 Interior Offset Emboss of 16 mm)

    Sectional View of Interior Offset Emboss

    Perimeter = 2 x 2r

    8

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    13/39

    2.3.3 Piercing (5 holes of 4 mm)

    Perimeter = 5 x 2r

    = 5 x 2 x 2mm

    = 62.83 mm

    Area to be Cut = Perimeter x Thickness

    = 62.83 mm x 0.5 mm

    = 31.42 mm2

    Piercing Force = SR x A

    = 32 kgf/mm2x 31.42 mm

    2

    9

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    14/39

    2.3.4 Piercing (2x Pre-pierced Holes)

    Comparing from both diagram above and determined the parameter:

    A = 1.5 mm B = 4.5 mm h = 2.5 mm BR = 1.0 mm

    Determine BA from Table:

    Material Thickness = 0.5 mm

    Bending Radius = 1.0mm

    10

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    15/39

    By taking Interpolation BA = {[(1.29-0.97) / (1.50/0.75)] x (1.5-1)}+0.97 = 1.08

    Determined Pre-pierced Holes Diameter:

    Dpre-pierce = 2[B-(A+h-BA)]

    = 2 [4.5mm (1.5mm + 2.5mm 1.08)]

    = 3.16 mm

    Piercing Force:

    Perimeter = 2 x 2r

    = 2 x 2 x (3.16/2) mm

    = 19.85 mm

    Area to be Cut = Perimeter x Thickness

    = 19.85 mm x 0.5 mm

    = 9.93 mm2

    Piercing Force = SR x A

    = 32 kgf/mm2 x 9.93 mm2

    = 317.68 kgf

    11

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    16/39

    2.3.5 Beading (V-Bead)

    Perimeter = 361.8 mm

    Beading Force = TS x t x L

    = 40 kgf/mm2

    x 0.5 mm x 361.8 mm

    = 7236 kgf

    Total Cutting Force at Station Three = 3770 kgf + 2010.6 kgf + 1005.31 kgf +

    317.68 kgf + 7236 kgf

    = 14339.59 kgf

    12

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    17/39

    2.4 Station Four

    2.4.1 Extruding

    Perimeter = 2 x 2r

    = 2 x 2 x 3.5mm

    = 43.98 mm

    Extruding Force = TS x t x L

    = 40 kgf/mm2

    x 0.5 mm x 43.98mm

    = 879.65 kgf

    Total Cutting Force at Station Four = 879.65 kgf

    13

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    18/39

    CHAPTER 3

    STRIPPER

    3.1 Stripping Force

    When sheet metals are punched or blanked, the metal surrounding the punch steel

    clings tightly and must be removed by some mechanical means.

    Harder and thinner metals require very small stripping forces, and in some

    instances none at all. Most die design rules recommend a stripper capable of exerting 10

    percent of the cutting force. Technique Of Press Working Sheet Metal, 1974

    General rules regarding stripping force are

    1. Softer metals need higher force2. Smaller clearances need higher force3. Cutting near sheet edge required less force since the sheet can be deflected away

    f h h

    14

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    19/39

    3.2 Calculation of Stripping Force

    Stripping Force = 0.1 x Cutting Force

    Station Cutting Force (kg f) Stripping Force (kg f)

    1 10527.56 1052.8

    2 7492.2 749.2

    3 14339.59 1434.0

    4 879.65 88.0

    15

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    20/39

    CHAPTER 4

    PUNCH AND DIE

    4.1 Clearance

    Assumption: Material is made of Soft Steel 0.3% C

    Thickness = 0.5 mm ~ 0.020 inch

    By referring to the table at page 228 of 3

    rd

    Edition Die Design FundamentalC = 0.0011 inch ~ 0.02794 mm

    4.2 Determining Size

    Operation Die Size Punch Size

    Blanking Part Size Part Size 2C

    Piercing Part Size + 2C Part Size

    16

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    21/39

    Piercing: Die Size = 4mm + 2(0.02794) = 4.056 mm

    Punch Size = 4mm

    Die Punch

    4.2.2 Station Two

    Slotting: Die Size = Part Size + Offset Clearance

    Punch Size = Part Size

    Die Punch

    17

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    22/39

    4.2.3 Station Three

    Piercing: Die Size = 4mm + 2(0.02794) = 4.056 mm

    Punch Size = 4mm

    Die Punch

    Piercing: Die Size = 3.16mm + 2(0.02794) = 3.216 mm

    Punch Size = 3.16mm

    Die Punch

    `

    18

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    23/39

    4.2.4 Station Four

    Extruding: Die Size = 6mm + 2(0.02794) = 6.056 mm

    Punch Size = 6mm

    Die Punch

    19

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    24/39

    CHAPTER 5

    DIE COMPONENT

    5.1 Thickness of Punch Holder and Die Holder

    5.1.1 Station 1

    Blanking Force (Blank Contour) = 10125.44 kgf

    Piercing Force (2x 4mm) = 402.12 kgf

    Total Cutting Force at Station 1 = 10527.6 kgf

    = 10.5276 tonnes

    20

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    25/39

    Punch Holder Thickness = 44.50 mm

    Die Holder Thickness = 51.00 mm

    5.1.2 Station 2:

    Embossing Force (Rectangular Offset) = 6308.2 kgf

    Piercing Force (2x Square Fillet) = 1184 kgf

    Total Cutting Force at Station 2 = 7492.2. kgf

    = 7.4922 tonnes

    21

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    26/39

    5.1.3 Station 3:

    Embossing Force (5x 14mm) = 3770 kgf

    Embossing Force (2x 16mm) = 2010.6 kgf

    Piercing Force (5x 4mm) = 1005.31 kgf

    Piercing Force (2x 3.16mm) = 317.68 kgf

    Beading Force (3x V-bead) = 7236 kgf

    Total Cutting Force at Station 3 = 14,339.59 kgf

    = 14.34 tonnes

    22

    23

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    27/39

    5.1.4 Station 4:

    Extruding Force (2x 2.5mm Wall) = 879.65 kgf

    Total Cutting Force at Station 4 = 879.65 kgf

    = 0.88 tonnes

    Punch Holder Thickness = 31.75 mm

    Die Holder Thickness = 38.10 mm

    23

    24

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    28/39

    CHAPTER 6

    PRESS CAPACITY

    6.1 Calculation for Press Capacity of Each Station

    Press Capacity = Total Cutting Force + Stripping Force

    StationCutting Force

    (kg f)

    Stripping Force

    (kg f)

    Press Capacity

    (kg f)

    1 10527.56 1052.8 11580.36

    2 7492.2 749.2 8241.42

    3 14339.59 1434.0 15773.55

    4 879.65 88.0 967.62

    24

    25

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    29/39

    CHAPTER 7

    SCRAP STRIP LAYOUT

    7.1 The Scrap Strip Layout

    In this design, we had chosen the single-row one-pass layout method for our scrap

    strip layout. For part positioning, we choose narrow-run positioning. All the calculation

    below will use this scrap strip criteria.

    7.2 Scrap Strip Allowances

    A

    AA

    AA

    25

    26

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    30/39

    Curved outlines: For these, dimensions A are given a minimum allowance of 70%

    of the strip thickness T.

    T = 0.5mm

    A = 70% of 0.5mm

    A = 0.35mm

    7.3 Strip Area per Blank Calculations

    7.3.1 Single Row, One Pass Positioning

    As = AB

    Where:

    As = area of the strip per one blank

    A = width of strip

    B = length of one piece

    As = 125.7 256.35

    As = 32223.195 mm2

    7.3.2 Number of Blanks per Strip

    N =()

    + 1

    26

    27

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    31/39

    7.3.3 End Waste of Single Pass Strip

    D = S [B (N1) + X + Y + 2E]

    D = 1500 [256.35(51) + 128 + 128 + 2(0.35)]

    D = 217.9mm

    27

    28

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    32/39

    Appendices

    1. Scrap Strip Layout2. Die Set Station 13. Die Set Station 24. Die Set Station 35. Die Set Station 4

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    33/39

    PART DRAWING

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    34/39

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    35/39

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    36/39

    STATION ONE

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    37/39

    STATION TWO

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    38/39

    STATION THREE

  • 7/30/2019 Project Die Design Tooling UTM 20112012

    39/39

    STATION FOUR