Page 1: PROJECT DEVELOPMENT UNIT - Home - Ministry of … and Quotations Document/Aircond... · Web viewBasic Guideline to the scope of works for installation and repair of Air Conditioning

ASSET MANAGEMENT SECTION, ASSET MANAGEMENT SECTION, MINISTRY OF FOREIGN AFFAIRS AND TRADEMINISTRY OF FOREIGN AFFAIRS AND TRADE

NEGARA BRUNEI DARUSSALAMNEGARA BRUNEI DARUSSALAM

A. Please complete and submit the Quotation Form provided.

B. Quotation shall be addressed to :

HEAD OF ASSET MANAGEMENTMINISTRY OF FOREIGN AFFAIRS AND TRADE

JALAN SUBOKBRUNEI DARUSSALAM

C. Quotation shall be deposited in the Quotation box located at the Ground Floor, Ministry of Foreign Affairs and Trade, Jalan Subok. Negara Brunei Darussalam.

D. Contractors who are unable to submit quotation as required are requested to state their inability to quote by writing “No Quote” in the Quotation Form provided and to submit to the above address.

E. Closing date for the submission of Quotation is on Wednesday, 18 th May 2016 before 2.00 p.m )

F. The envelope containing the quotation shall not bear the name or address of the contractor and shall have on its top the quotation title and reference number together with the closing date and time of the quotation.

07/ASSET.MoFAT/2016

Page 2: PROJECT DEVELOPMENT UNIT - Home - Ministry of … and Quotations Document/Aircond... · Web viewBasic Guideline to the scope of works for installation and repair of Air Conditioning

ASSET MANAGEMENT SECTION, ASSET MANAGEMENT SECTION, MINISTRY OF FOREIGN AFFAIRS AND TRADEMINISTRY OF FOREIGN AFFAIRS AND TRADE

Title : SUPPLY, INSTALL, TESTING AND COMMISSIONING OF AIR-CONDITIONERS FOR ROOM 217 AND 218 AT MOFAT, JALAN SUBOK .

I. GENERAL CONDITIONSScope Of WorkThe Contractor shall provide everything deemed necessary such as materials, labour, plant and equipment, supervision and transportation etc., for the proper execution of the works according to the true intent of the Specification and Schedule of Works. Any ambiguities shall be referred to the Superintending Officer (S.O) whose decision shall be final.

Site Visit And Show-AroundThe Contractor shall be considered to have visited the site and shall have taken into account all relevant aspects of the works. Where show-around is organized and deemed necessary, all contractors must be present and attend the show-around. The Government reserves the right to accept Quotations only from those Contractors who have attended the show-around.

Contact Person: Suhara Fadhilah or Masehi Ahmad

Telephone no: 2261177 ext 131 / 155

Making Good Any DamagesAny existing work damaged shall be made good at Contractor’s own expense with materials and workmanship to match in every respect the surrounding work and shall be properly bonded therefore.

Site RestrictionsThe Contractors shall comply with all the regulations that might be imposed by the authorities concerned with regards to movements inside the compounds. The Contractors shall be solely responsible to seeing that his men follow these regulations.

Tidiness And DisturbanceThroughout the progress of the works, the Contractor shall maintain the site in a neat condition. Any spillage of building materials on the compound shall be cleaned immediately. The Contractor shall ensure that materials and tools stored on site are kept safely. No claims for the loss of materials, tools etc., will be entertained.

Defects Liability PeriodThe defects liability period after the satisfactory completion of work shall be six (6) calendar months during which period defect shall be made good by the contractor at his own expense.

Clearing On CompletionThe Contractor shall leave every part of the works included in this contract in a clean, sound and perfect condition, free from flaws, cracks and settlements what so ever on completion of the works.

07/ASSET.MoFAT/2016

Page 3: PROJECT DEVELOPMENT UNIT - Home - Ministry of … and Quotations Document/Aircond... · Web viewBasic Guideline to the scope of works for installation and repair of Air Conditioning

II. PARTICULAR SPECIFICATION - AIR-CONDITIONING

1. By signing and placing your official seal to this document, the contractor gives acceptance to the previously signed, sighted, sealed section that are referred to this quotation by way of:i. General conditions of Contract Maintenance of Air Conditioning system

(DME)ii. Basic Guideline to the scope of works for installation and repair of Air

Conditioning system. (DME)iii. Basic Guideline to the scope works for maintenance of Air Conditioning

system (DME)

2. Air-conditioning equipment offered must be as per DME Approved List of Air Conditioning Equipment and Accessories for Government Projects. Category selected shall be of “Superior” type.

3. All hangers and brackets necessary for mounting the units shall be suitably painted to be corrosion resistant. Motors and controls shall be mounted inside the casing with the hinged and removable panels for service access.

4. All Electrical works will comply with the Institute of Electrical Engineers Regulations 15th Edition, the Department of Electrical Services General Specification for Electrical Installations and appropriate Building Standards Codes of Practice.

5. For equipment, which is installed outdoors, power cables shall be suitably protected i.e. in PVC/steel conduits.

6. To connect the units to the existing electrical outlets.

7. All Split unit Air-conditioning shall be provided with remote control.

8. All Split Units shall be of good quality, on DES category (please attach the copy). Attach original catalogues and technical data sheet with offer clearly marked on the existing catalogue.

9. Refrigerant piping shall be insulated with pipe insulation with not less than 2” thick or provided with Nippondenso tape or approved equivalent and cover with PVC trunking.

10. All works and materials used for this job shall be of high quality.

11. Special care shall be taken not to dirty or damage the finishes of the premises. Canvas / Plastic sheets shall be used to cover the floor etc.

12. Maintenance (service warranty) should be included within 1 year from the date handover.

13. All the compressors shall carry a minimum of 5 year warranty from the manufacturer.

07/ASSET.MoFAT/2016

Page 4: PROJECT DEVELOPMENT UNIT - Home - Ministry of … and Quotations Document/Aircond... · Web viewBasic Guideline to the scope of works for installation and repair of Air Conditioning

TECHNICAL DATA OF EQUIPMENT(AIR-CONDITIONING)

WALL MOUNTED SPLIT UNIT

FAN COIL UNIT (Indoor Air Conditioning Unit)

1 Make

2 Model

3 Serial No.

4 Size ( W x H x D )mm

5 Net Weight (Kg)

6 Cfm

7 Ceiling or Wall mounted

8 Coil (Copper or Aluminium)

9 Country of Manufacturer

10 Cooling Capacity (Btu/h)

11 Fan Blade Scroll (Aluminium/Plastic)

12 Air Filter Type

13 E.E.R

MOTOR BLOWER

1 Motor Brand

2 Motor Model

3 Motor Voltage

4 Motor kW

5 Motor Ampere (FLA)

6 R.P.M

07/ASSET.MoFAT/2016

Page 5: PROJECT DEVELOPMENT UNIT - Home - Ministry of … and Quotations Document/Aircond... · Web viewBasic Guideline to the scope of works for installation and repair of Air Conditioning

TECHNICAL DATA OF EQUIPMENT(AIR-CONDITIONING)

WALL MOUNTED SPLIT UNIT

TYPE OF CONDENSING UNIT (Outdoor Condenser)

1 Make

2 Model

3 Serial No.

4 Size ( W x H x D )mm

5 Net Weight (Kg)

6 Compressor Capacity

7 Compressor and Type

8 Compressor Full Load Amps

9 Compressor Locked Rotor Amps

10 Condenser Fans and Type

11 Condenser Fans Make and Model

12 Fan, Bearing / Bush Type

13 Coil, Copper / Aluminium

14 Type of Condensing Blade

07/ASSET.MoFAT/2016

Page 6: PROJECT DEVELOPMENT UNIT - Home - Ministry of … and Quotations Document/Aircond... · Web viewBasic Guideline to the scope of works for installation and repair of Air Conditioning

ASSET MANAGEMENT SECTION, ASSET MANAGEMENT SECTION, MINISTRY OF FOREIGN AFFAIRS AND TRADEMINISTRY OF FOREIGN AFFAIRS AND TRADE

Title : SUPPLY, INSTALL, TESTING AND COMMISSIONING OF AIR-CONDITIONERS FOR ROOM 217 AND 218 AT MOFAT, JALAN SUBOK .

SCHEDULE OF PRICES

The work shall comprise supply, installation, testing and commissioning of air conditioning units for Room 217 and 218, Communication Section, Main Building, MOFAT, Jalan Subok. The Contractor shall supply all materials, labour, tools and everything deemed to carry out works as specified to the following.

ITEM DESCRIPTION QTY UNIT RATE AMOUNT

1.0

2.0

3.0

4.0

Supply, install, testing and commissioning of wall mounted split type Air Conditioner with 11,000 – 12,000 BTU/hr capacity (1.5 HP); single phase 240 volt c/w refrigerant pipework, condensate drain pipework, insulation and necessary supports. Location – see appendix

Wall mounted split type Air Conditioner with 20,000 – 23,000 BTU/hr capacity (2.5 HP); single phase 240 volt c/w refrigerant pipework, condensate drain pipework, insulation and necessary supports

Supply and install electrical wiring from the existing nearest electrical DB with circuit breaker (ELCB) for each unit

Supply and install power and control cable between outdoor condensing unit to the indoor fan coil unit using 2 x 1c/2.5mm² pvc cpc cable in conduit trunking

1

1

1

1

no

no

Lot

Lot

Total Carried to Quotation Form

07/ASSET.MoFAT/2016

Page 7: PROJECT DEVELOPMENT UNIT - Home - Ministry of … and Quotations Document/Aircond... · Web viewBasic Guideline to the scope of works for installation and repair of Air Conditioning

ASSET MANAGEMENT SECTION,ASSET MANAGEMENT SECTION,MINISTRY OF FOREIGN AFFAIRS AND TRADEMINISTRY OF FOREIGN AFFAIRS AND TRADE

QUOTATION FORM

Title : SUPPLY, INSTALL, TESTING AND COMMISSIONING OF AIR-CONDITIONERS FOR ROOM 217 AND 218 AT MOFAT, JALAN SUBOK .

I/We the undersigned having read and fully understood the instruction and

specification regarding the above and willing to perform the works for a sum of :-

Brunei Dollars :

_________________________________________________ (B$______________)

I/We have seen the above plans, specification and the site and deemed and the site and deemed to have a clear understanding.

I/We agree to deliver the product / complete the above works in ( ) weeks. This period making allowances for all possible causes of delay which can reasonably foreseen and not merely representing the number of working days required.

Name and Signature :

Position in Company :

Name of Company :

Company’s Stamp / Chop :

Address :

Telephone & Fax No. :

Email :

Date :

07/ASSET.MoFAT/2016

Page 8: PROJECT DEVELOPMENT UNIT - Home - Ministry of … and Quotations Document/Aircond... · Web viewBasic Guideline to the scope of works for installation and repair of Air Conditioning

Appendix – Proposed location of Air-Conditioners in Room 217 and 218

07/ASSET.MoFAT/2016