PROJECT DESCRIPTION W.R. T. 16MW Captive power...
Transcript of PROJECT DESCRIPTION W.R. T. 16MW Captive power...
CHAPTER 2: PROJECT DESCRIPTION 2.1
PROJECT DESCRIPTION W.R. T. 16MW Captive power plant
2.0 INTRODUCTION M/s. Pudumjee Pulp & Paper Mills Ltd. is planning to shift its operations from their present
location in Pune to Mahad in Maharashtra along with some new machines too. To cater to the
additional power requirement for the proposed expansion & to improve the availability of
power consistently to the plant, the company proposes to set up a co-generation plant to
cater to its captive requirement of power and steam. M/s. Pudumjee Pulp & Paper Mills Ltd.,
Mahad, has proposed 16MW Coal based Power Plant at MIDC Mahad, Dist- Raigad,
Maharashtra state. This project development will give rise to social and economic
development measures in the study area.
2.1. TYPE OF PROJECT The proposed unit is co-generation power plant covered under the category of 1(d) in schedule “
co-generation power plant)” of EIA Notification 2006. This project falls under category ‘B’.
2.2. CAPITAL INVESTMENT The expected cost of the proposed project will be around Rs. 71.56 crores.
Sl NO. DESCRIPTION
16 MW capacity Rs lacs
1 CIVIL COST 800.00
2 PLANT AND MACHINERY
2.1 WATER TREATMENT PLANT 125.00
2.2 BOILER (INCLUDING THE TURBINE STEAM PIPING, PRDS FOR PROCESS STEAM AND PROCESS STEAM PIPING) 100 TPH 1700.00
2.3 DOSING SYSTEM AND DEAERATOR CUM STORAGE TANK 75.00
2.4 ELECTRO STATIC PRECIPITATOR 325.00
2.5 CHIMNEY 95.00
2.6 FUEL BUNKER 95.00
2.7 FUEL HANDLING SYSTEM 350.00
2.8 ASH HANDLING SYSTEM (DENSE PHASE) WITH ASH SILO 150.00
2.9 DCS BASED CONTROL SYSTEM WITH FIELD INSTRUMENTS 100.00
PROJECT DESCRIPTION 2.2
2.10 TURBO GENERATOR 16 MW 1350.00
2.11 AIR COOLED CONDENSER 400.00
2.12 AUXILIARY COOLING TOWER & CW PUMPS 30.00
2.13 POWER PLANT INTEGRAL PIPING OTHER THN STEAM PIPING 40.00
2.14 POWER PLANT ELECTRICALS OTHER THAN SWITCHYARD 350.00
2.15 EOT CRANE+ AIR COMPRESSOR& MISC 90.00
2.16 AIR CONDITIOING FIRE EXTINGUISHER 60.00
SUB TOTAL-I 5335.00
3 PACKING & FORWARDING 53.35
4 ERECTION & COMMISSIONING CHARGES 640.20
5 TRANSPORTATION 160.05
6 CONSULTING FEES AND EXPENSES 50.00
SUB TOTAL -II 903.60
7 TAXES AND DUTIES
7.1 EXCISE DUTY @ 10.3% 549.51
7.2 SERVICE TAX @ 10.3% 102.40
7.3 SALES TAX @ 2% 117.69
SUB TOTAL -III 769.60
8 PRE OPERATIVE EXPENSES INCLUDING TRAVEL, INTEREST DURING ONSTRUCTION PERIOD AND DEPOSITS, IF ANY) 605.61
GRAND TOTAL 7808.20
PROJECT COST NETT OF CENVAT 7156.29
2.3. NEED OF THE PROJECT For economic growth of any country, development of energy resources is vital importance.
Energy in the form of electricity is most convenient for generation, transmission and
utilization and hence it is widely used. The living standard and prosperity of nation vary
directly with increase in use of power.
PROJECT DESCRIPTION 2.3
Faced with the grim realities of load shedding, voltage fluctuations, tripping, consequent loss
of production, damage to costlier/critical equipments and with no hopes of improvement in
this scenario in the foreseeable future, Many power intensive industries have to install their
own captive or co-generation plants. This will ensure uninterrupted, quality power, meeting
the needs of the companies.
The present trend in process industries which consume large quantum of process steam and
electric power is to establish captive power generation facility; which can simultaneously meet
the process steam as well as the electrical energy requirements of the plant. The captive
power plant will go a long way in improving the overall energy balance of the plant which will
in turn improve the economy of operation. In line with the present trend, establishing a
captive power generation facility in M/S. PUDUMJEE PULP & PAPER MILLS LTD is expected to
substantially improve the overall energy economy.
Moreover power tariff of state electricity board is high and is expected to increase further in
the years to come, M/S. PUDUMJEE PULP & PAPER MILLS LTD will have to pay a very high
cost if the plant power requirements are to be met from the electricity board grid. On the
other hand, if power requirements are to be met from the in-plant power generation through
new diesel generator sets using Diesel, the prevailing uncertainty with regards to the price of
oil due to changing global scenario, and the cost of oil at the present level makes the DG sets
based in plant power generation also unattractive. In addition, generation of steam in a
separate boiler adds to the production cost. In order to reduce the cost of production to
sustain the operation in the globally competitive environment, it is essential for M/S.
PUDUMJEE PULP & PAPER MILLS LTD to look into the examine its viability. It is imperative to
improve the energy efficiency and thereby the economy of plant operation by simultaneous
generation of steam and power from one source of fuel.
2.4 LOCATION OF PROJECT SITE The unit is located at K-5 Additional Industrial Estate, MIDC Mahad, Dist Raigad, State
Maharashtra. The project site is located in additional Industrial Estate of MIDC. The
environmental setting around the proposed site is given in Table 2.1. The location map of
project site is shown in figure 2.1 & Google map of project site is shown as Figure 2.2.
Table 2.1: Environment Setting of the Proposed Project
Sr. No.
Particulars Details
1 Latitude 180 06’N,
2 Longitude 730 30’ E
3 Elevation above MSL 115 ft above Mean Sea Level
PROJECT DESCRIPTION 2.4
Sr. No.
Particulars Details
4 Climatic Conditions.
Annual Mean Maximum Temperature: 31.8 °C
Annual Mean Minimum Temperature: 17.7°C
Annual Mean Maximum Rainfall: @ 3360 mm**
5 Present land use at the location Industrial
6 Nearest Village Birwadi ( 2.5 km)
7 Nearest Town/City Town: Mahad (12 km)
City: Mumbai (200 km, SE)
8 Nearest Railway Station Veer Railway Station (27 km, SE)
9 Nearest Hospital MMA Hospital (4 km, SE)
10 Nearest Highway NH –17 (8 km, WSW )
11 Nearest Airport Mumbai Airport (200 km, ESE)
12 Nearest Water Body Kal River (3.0 km, ESE)
13 Ecologically sensitive zones within 10-
km area (NPKs, WLS etc) Nil
14 Ecologically sensitive Areas within 5
km area Villages: Jite, Solamkond
15 Historical/ Archaeological places Nil
16 List of Major Industries (within 10 km)
Sandoz Pvt. Ltd., Piramal Health care, Kopran,
Adventz (Zuari Agro), Vinati Organics Ltd, Pidilite
industries Ltd, laxmi Organics industries Ltd, Shri
Hari Export Ltd.
17 Critically Polluted Areas within 10 Km
radius Nil
18 Seismic Zone Zone –III
PROJECT DESCRIPTION 2.6
Figure: 2.2: Google Map of Project Site
2.5. Highlights of projects
SL.NO DESCRIPTION DETAILS
1 PROJECT 16 MWe Co-generation power project
1.1 Proponent M/s. PUDUMJEE PULP & PAPER MILLS LTD
2 Location details
2.1 - Place Mahad
2.2 - District Raigad (MH)
2.3 - State MAHARASHTRA
PROJECT DESCRIPTION 2.7
3 Plant capacity 1x 16 MW co-generation power plant
4 Technology
Conventional steam cycle operating in Rankine cycle
consisting of 1 no. AFBC boiler and 1X 16 MW
extraction cum condensing Turbine
5 Fuel
Indian and imported coal shall be 50 % each. However
the boiler shall be capable of operation with 100 % of
Indian as well as imported coal.
6 Source of fuel OUT SIDE SOURCING
7 Fuel requirement
(APPROX)
INDIAN COAL : 18908 kg/hr
IMPORTED COAL: 19854 kg/hr
8 Source of water Raw water from MIDC supply.
9 Water requirement 735 m3/day / 31 m3/hr
10 Gross power Generation 16000 Units/hour
11 In house Consumption 2080 Units/hour
12 Net power generation 13920 Units/hour
13
Land requirement (Acres) 4.25 Acres (Power Plant equipments & Switch Yard)
1.00 Acres (Open Yard for Coal Storage)
1.00 Acres (Covered coal storage)
Total of 8.00 Acres is required including roads.
14 Total Project Cost Rs. 7156 Lacs
15 Project implementation
schedule
3 months for major machinery order placement
16 Commissioning schedule 16 months from zero date to commissioning.
PROJECT DESCRIPTION 2.8
Figure: 2.3: Layout Plan of Proposed Project
2.6 Technology Alternatives: Method of Power Generation The thermal power plant option selected is a co-generation thermal power plant with
Atmospheric Fluidized Bed Combustion (AFBC) boilers.
Conventional Method of Power Generation
The conventional method of power generation and supply to the user is wasteful in the sense
that only about a third of the primary energy fed into the power plant is actually made to
available to the user in the form of electricity. In conventional power plants, efficiency is only
35% and remaining energy is lost as heat through the stack or condenser water. The major
loss in the conversion process is the heat rejected to surrounding water or air due to the
inherent constraints of the different thermodynamic cycles employed in power generation.
Co-generation
Co-generation is the merging of a system designed to produce electric power and a system
used for producing industrial heat and steam for industrial processes. This system is a more
efficient way of using energy inputs and allows the recovery of otherwise wasted thermal
energy for use in an industrial process.
Through the utilization of the heat, the efficiency of the co-generation plant can reach 90% or
more. In addition, the electricity generated by the co-generation plant is normally used
PROJECT DESCRIPTION 2.9
locally, leading to negligible transmission and distribution losses. It is an accepted fact that
co-generation therefore offers energy savings ranging between 15-40% when compared
against the supply of electricity and heat from the power stations and boilers. Its long term
future in the global energy markets is secured by its ability to provide operational, financial
and environmental benefits from to a single unit of a fuel. The following benefits arise as co-
generation is a well proven technology, recognized world over as a cleaner alternative to
traditional centralized generation:
Base load electrical supply
Security of supply
Increased diversity on heating and hot water
Steam raising capabilities
Considering the above points, Pudumjee has selected co-generation as its chosen power
generation option over a conventional option.
Technology Alternatives: Boilers
As mentioned, two, Atmospheric Fluidized Bed Combustion Boilers (AFBC) of 100 Tonnes per
Hour (TPH) capacity have been proposed for the project. Conventionally, stoker fired boilers
have been used for power generation. Stoker fired boilers do not provide equivalent efficiency
as compared to fluidized bed combustion boilers across a number of key parameters
including: boiler size, flexibility of fuel quality, ability to burn fines, pollution control, low
corrosion and erosion, ash removal, simple operations such as start-up, faster response to
load fluctuations, avoidance of slag formation or soot blowing, reduced maintenance and
higher thermal efficiency. The Machinery and Units The captive co-generation power plant of 16 MW capacity will be operated on 100 % coal
Imported or Indian) throughout the year. It shall employ High Pressure and Temperature
configuration Boiler and Steam Turbine, as well as ESP for emission control, DCS and SCADA
control system for efficient operations.
The Machinery and units which to be installed are as follows;
1. Boiler (Multi Fuel Fired) 2. Turbine 3. Water Cooled Condenser 4. Cooling tower 5. Coal Storage and handling system 6. Ash Handling system 7. Generator 8. Pumps 9. Water supply, DM plant and Treatment Plant 10. Vessels and Tanks 11. Piping 12. Insulation 13. Civil and Structure
PROJECT DESCRIPTION 2.10
14. Electricals 15. Control and Instrumentation 16. Fire hydrant system 17. Power switch yard
2.7 BASIC REQUIREMENT
The basic input requirement for the power plant is fuel and water.
M/s. PUDUMJEE PULP & PAPER MILLS LTD is planning to source the fuel namely Imported coal
& Indian coal. On the basis of the design consideration and expected heat rate of the power
plant, the consumption of imported coal firing as mentioned elsewhere in the report while
generating 16 MW on co-generation.
The following configurations have been proposed
STEAM GENERATOR SL.NO DESCRIPTION DETAILS
a. No. and ratings 1 no, 100 TPH, 88 ATA and 525°C
b. Type of boiler AFBC
c. No. of boiler fans 2 x 100% ID, FD and PA fan
d. Type of APCS Electro Static Precipitators
STEAM TURBINE GENERATOR
SL.NO DESCRIPTION DETAILS
a. No. and ratings of turbine 1 no. 16 MW having inlet parameters
of 85 ata and 520°C
b. Capacity 1x 16 MW,11 KV
c. No.of controlled extractions 1 no.
d. No.of bleed 1 no.
Emphasis has been given on optimum layout, energy efficient, environment friendly and state
of art technology, special care shall be taken in choosing pollution control equipment so as to
maintain emission levels below 50 mg/Nm^3. Fuel shall be stored in a heap and reclaiming
shall be with pay Loader. The fly ash generated from the power plant shall be truck
transported to suitable destination. For control of boiler and TG, Micro processor based DCS
controls has been considered.
2.7 HUMAN RESOURCES
PROJECT DESCRIPTION 2.11
Hiring of project consultant for project engineering is envisaged. 60 personnel shall be
required during the operation phase and are summarized in Table below:
MANPOWER DETAILS
SL.NO MANPOWER CATEGORY SHIFT
1. Assistant Manager General
1
2. Operation Engineer (B.O.E) Shift 1
3. Maintenance Mechanical Engineer General 1
4. Engineer (Electrical & Instrumentation) General 2
5. First Class Boiler Operator (3 + 1) Shift 4
6. Second Class Boiler Operator (3 + 1) Shift 4
7. Turbine Operator (3 + 1) Shift 4
8. Fitter (Mechanical, Electrical, Instrument) Shift + Gen 8
9. Water Treatment Plant Operator & Lab. Chemist Shift + Gen 8
10. Helper for Operation & Maintenance Shift + Gen 25
Some personnel have to be recruited and shall be involved during construction stage itself for
execution of the project and make them acquainted with the system. Comprehensive training
programme have been envisaged for key personnel both in operation and maintenance of the
plant at an appropriate stage of project execution. The training shall encompass:
i) Manufacturers works
ii) On job training during commissioning
2.8 FUEL ANALYSIS:
Constituent Unit Indian coal Imported coal Carbon % 39.9 40.51
Hydrogen % 2.48 3.02 Oxygen % 6.76 11 Sulphur % 0.38 0.26 Nitrogen % 0.48 0.64 Moisture % 8 38
Ash % 42 6.57
GCV, Kcal /kg 3800 3900
PROJECT DESCRIPTION 2.12
2.9 Water and waste Water treatment plant: Water is required to meet the requirement of:
Makeup water for boiler makeup and auxiliary cooling tower make up. The daily water
requirement is to be met from MIDC or Savitri River. From the view point of basic
requirement viz. fuel and water for auxiliary system no major problems are envisaged.
Figure: 2.4: Water Balance Diagram
Water system facilities requirement for the complete power plant are covered under the following
categories.
1) Raw water pretreatment system.
2) Water treatment plant for power cycle make up.
3) Water treatment plant for cooling tower make up.
The raw water supply for the power plant shall be arranged from savitri River and MIDC
water to plant site. In plant site, the water will be stored in the raw water storage tank.
PROJECT DESCRIPTION 2.13
Figure: 2.5: ETP Flow Diagram
RAW WATER PRETREATMENT SYSTEM
A pretreatment plant to treat the water received to produce water for the power plant shall
be considered. 2x100% capacity raw water pumps (1W+1S) shall pump raw water from the
raw water storage tank to the pretreatment plant consisting clarifier shall be considered. All
pipings, fittings and valves etc as required for complete intake system with handling
facilities for raw water intake shall be provided. Chlorine dosing system in boiler make up
line is considered in order to reduce the chloride content in the raw water. There are two
streams considered, one for boiler heat cycle make up. The boiler make up stream shall
consist of chlorine dosing system with MGF, SAC, SBA, Degasser unit and MB units. The
cooling tower make up comprises of MGF & Softner. Both the streams will have common
pumps for feeding the required water.
Water treatment plant for heat cycle make up
The water treatment plant shall provide makeup of specified quality and quantity to meet
the heat cycle makeup of the unit. The WTP permeate flow has been selected considering
process steam losses, boiler blow down, other vent / drain losses. The operating hours of
the plant shall be considered as 20hrs in a day. For the requirement of very high quality of
water with conductivity less than 0.5 micro Siemens per cm and total silica, less than 0.02
ppm and removal of complete colloidal silica the water treatment plant with reverse osmosis
followed by ion exchange is proposed for this plant. Water must have a very low silt (solids)
PROJECT DESCRIPTION 2.14
content to keep the membranes from plugging up. From MGF, water will be directed to
Degassifier tower to remove carbon di oxide and then stored in permeate water storage
tank. From permeate water storage tank, the water will be pumped by permeate water
transfer pumps to Mixed Bed Exchangers through SBA and SAC to produce demineralized
water.PH boosting system at the outlet of MB shall be considered in order to maintain the
required PH of water.
Demineralized water will be collected in the demineralized water storage tank. Water from
the demineralized water storage tank will be distributed to the consumption points through
pumps in others scope.
Water treatment plant for cooling tower make up
The water treatment plant shall provide makeup of specified quality and quantity to meet
the cooling tower makeup of the unit. The WTP capacity with Softner outlet flow has been
selected considering evaporation losses in cooling tower, drift, cooling tower blow down &
other vent / drain losses. The operating hours of the plant shall be considered as 20hrs in a
day.
In the complete plant, all continuous duty pump requirement will have each 2 nos x 100%
pumps with (1W+1S) arrangement to have flexibility for pumps and the plant will be having
single stream with space for future provision shall be considered. The entire system shall be
housed in a building.
Control & Instrumentation
The operation shall be based on a control system, which consists of a control panel
complete with PLC system. The control system will have all safety interlocks. Also the PLC
will have RS 485 modbus connectivity, so that it will be linked with plant DCS systems.
Plant instruments shall consist of the following minimum requirements.
1) Inlet and outlet pressure indicators for vessels & discharge pressure indicators for
various pumps.
2) Flow indicators
3) Level / flow /pressure switches
4) Conductivity meters at R.O outlet and MB outlet with transmitters.
5) PH meters at MB outlet.
6) ORP meter with auto dump valves.
Control panel shall be considered to locate instruments / annunciators in order to operate
the plant.
As the WTP effluent comprises mainly of regeneration waste and filter back wash, suitable
blow down from the neutralizing pit shall also be provided. Pumps for effluent handling shall
be considered.
WATER QUALITY REQUIREMENTS
PROJECT DESCRIPTION 2.15
FEED WATER
Total Iron max. ppm 0.01
Total copper Max. Ppm 0.01
Total silica Max. Ppm 0.02
Oxygen Max. Ppm 0.007
Hydrazine residual Ppm 0.01 – 0.02
PH at 25 OC (Copper alloy pre-boiler system) 8.8 – 9.2
PH at 25 OC (Copper free pre-boiler system) 9.0 – 9.4
Permanganate Max. Ppm Nil
Hardness Ppm Nil
Total CO2 Ppm Nil
Oil Ppm Not allowed
BOILER WATER Total dissolved solids Ppm Not more than 100
Specific electrical conductivity at 25 OC Us/cm Not more than 200
Phosphate residual Ppm 15 – 25
pH at 25 Deg.C. 9.8 – 10.2
Silica Max. Ppm Note no. 4 & 9
2.10 Fuel handling system
The fuel handling system consisting of Fuel conveying, Crushing, screening and Feeding to
boiler bunkers. Also the system includes Vibratory feeders, magnetic separator etc.
The handling system shall be capable of handling the following fuels:
100% Indian coal, 100% Imported coal
Fuel from stockpile will be moved to the ground hopper using bull dozers/dumpers/front
end loaders as applicable. Also provision has been envisaged to dump the fuel received
through truck directly into the ground hoppers.
Fuel from ground hopper will be fed to Crusher & vibrating screen designed to screen out
foreign particals and over size. The Product Fuel received from screen will be falling to
conveyor that will be fed to boiler bunkers. The over size Fuel will be recycled.
At bunker top, ‘Y’ chutes shall be considered to distribute the Fuel uniformly to the
bunkers.
2.11 Ash handling system
A Dense phase Pneumatic type fly ash handling system is proposed forboth bed ash& Fly
ash. Out of the total ash generated, 10% is considered as bed ash and remaining 90% is
collected as fly ash at various hoppers like Economiser, Air heater and ESP hoppers.
PROJECT DESCRIPTION 2.16
Considering 90% of ESP ash will be collected in field– I as well as field – II & III and also
the adverse condition of field –I or field –II not in line. Generally for design purpose the
same ash quantity shall be considered and all the three fields have provision for inter
changeability.
A Dense phase Pneumatic type fly ash handling system is proposed for the removal of bed
ash collected at furnace bottom, fly ash collected at Economiser, APH & ESP hopper zones.
The system will start from Surge hopper, which is kept above the Ash transmitter vessel.
Water jacket cooling facility, which is required to cool the fly ash temperature less than
200°C, shall be provided in Surge hoppers as applicable. The fly ash collected in the
various hoppers will be fed by Gravity into individual transmitter vessel located below the
hoppers.
The system shall have dual operation ability either through level probe material sensing or
Timer based mode. In Timer based mode, the system shall convey material automatically
in batches at preset programmable interval of time. In level probe mode, level sensing
probe provided in the hopper above Denseveyor of Transfer level shall sense the pressure
of material in the hopper and initiate the conveying cycle. Dome valve shall open and
allow the material to gravitate into transmitter vessel for a preset time & then close
automatically based on the Ash level in the hopper. After the inlet valve closes,
compressor air will be allowed in to the vessel by the opening the air inlet valve.
Once the desired conveying pressure is reached inside the vessel, the outlet valve will
open and the ash shall be conveyed to Fly ash silos through suitably sized pipes. The
conveying air will be vented out from silo through the bag filter provided on top of the
silo. Further, disposal of Fly ash from silo will be by Trucks. Silo is of RCC construction.
2.12 Chimney
The chimney height depends upon the Sulphur content in the fuel. The chimney height of
the proposed boiler is 63 m considering 100% Indian coal, 100% Imported coal having
GCV of 3800 kcal/kg with 0.38 % Sulphur content. It is used to exhaust the fluegas to
the atmosphere. Chimney is of RCC construction.
Turbo generator set
The Turbine shall be horizontal, single cylinder, Extraction cum condensing design
coupled to a generator to generate the rated output with the steam inlet parameters
as specified elsewhere in this specification.
The Steam turbine, gear box, main oil pump with its interconnecting piping and its
supports shall be assembled and aligned on a single skid and shall be delivered.
PROJECT DESCRIPTION 2.17
All the cabling within the skid shall be laid in the metal conduits and shall be fixed to
the base frame with respective junction boxes mounted on the skid.
2.13 ROADS AND PAVEMENT
Any new roads proposed within the plant shall be with 6.0 m black topping & 1.5 wide
shoulders on either side of the roads or shall be single lane roads with 4.0 m black topping
and one meter wide shoulders on either side of the road for sub roads having lesser access.
Roads geometry and construction shall be in accordance with Indian Road Congress (IRC) or
equivalent. All the roads shall be designed to withstand the largest expected loads.
Minimum longitudinal slope of the road shall be 1 in 200 where there are curbs on each
side. Without curbs the roads may be laid flat. Slope from crown to edge should be 1 in 50
generally on straight stretches. Super elevation shall be provided on curves.
The sub grade shall be compacted to the levels, falls, widths and cambers as per the grade
requirements. Sub base will be laid on a prepared sub grade. Base and final road surfacing
shall be of bitumen macadam. Seal coat will also be provided. Precast RC kerbs on both
sides of road shall be provided. The rainwater shall be collected in road side gullies and let
into the plant surface drainage system.
Paving areas shall be properly graded and compacted to required grade and slopes before
providing the base layer. Reinforced concrete paving (grade MI5) shall be done in alternate
panels not exceeding 3.0 m x 3.0 m in size. Construction joints shall be filled with sealing
compound. Around equipment foundations / columns isolation joint shall be provided upto
full depth of the pavement. Expansion joints shall be provided at a maximum spacing of
15.0 m.
Top surface of the pavement shall be provided with adequate slopes as required for the
surface drainage.
2.14 Solid and Hazardous Waste
Sr.
No.
Type of Waste Quantity Disposal
1 Domestic Solid waste 15 Kg/day Used as Manure for Gardening
2 Used Oil 1200 Lit / Annum MPCB authorized Recycler
3 Fly ash 83 MT/Day The fly ash will be stored in pneumatic silos of sufficient capacity (5 day storage) and provided to nearby cement plants
PROJECT DESCRIPTION 2.18
5 Bottom Ash 9 MT/Day As per MPCB directives
2.15 Pollution Monitoring System
Monitoring of various environmental aspect is of prime relevance in setting-up the proposed power plants. The following aspects would be critically monitored:-
To keep watch on the state of pollution To generate data for predictive and corrective measures To quantify environmental impacts The important area requiring periodic/conditions monitoring are:-
Stack emission Ambient air quality Disposed water quality
Electronic smoke density analyzer and gas analyzer equipment is proposed to provide for continuous monitoring of particulate matters at outlet of ESP and sample analysis of SO2 and other pollutants from chimney would be carried out. Waste water would be checked for any harmful pollutants before discharging to outfall. An oil/water separation unit has been envisaged near fuel oil day tank/pump house area in order to keep plant drains free of oil and to reclaim waste oil as far as practicable. Oil thus separated would be returned to the fuel oil tank and used or disposed off by incineration. 2.16 Environmental Aspects For thermal power stations, the Indian Emission Regulations dated July 1984 stipulate the limits for particulate matter emission and minimum stack heights to be maintained for keeping the sulphur dioxide levels in the ambient within the air quality standards. The characteristics of the effluent from the plant would be maintained so as to meet the requirements of the State Pollution Control Board and the Minimum National Standards for Thermal Power Plants stipulated by the Central Board for Prevention and Control of Water Pollution. Windblown pollution will be contained by adequate green belts to be planned during construction. Wastewater, if any, from the plant will be adequately treated before being discharged into the common brine water discharge line leading to river. There being no fragile environmental consideration for the area, no degradation is apprehended. The effect of the proposed project on environment would be mitigated in the following manner:-
Air Pollution: A highly efficient electrostatic precipitator with properly designed boiler and a 63 m high twin stack shall contain air pollution in the form of suspended particulate matter and gaseous emission.
Liquid effluent shall be treated and collected in a guard pond. Liquid effluent would be recycled after treatment as far as practicable. Following CPCB norms, attempts would be made to attain “zero discharge”.
Solid waste in the form of coal ash shall be utilized for mine filling and other possible usages. Noise pollution shall be curbed by selection of suitable equipment.
Green verge to be developed as per MoEF/CPCB norms. Fly ash from the station would be utilized in land filling of low lying areas in the
vicinity, as filler materials in cement plants located in adjoining districts, for construction of bunds, flood protection dykes, ash dykes, road sub-base etc.
* * * * *