Project Delivery Manual Overvie Delivery Manual...Project Delivery Manual Introduction •Where do...
Transcript of Project Delivery Manual Overvie Delivery Manual...Project Delivery Manual Introduction •Where do...
Project Delivery Manual
Overview
Introduction
2007
Project Delivery ManualIntroduction
• Where do projects come from?
• How do they get in the Highway Program?
• Once they are in the Program, what do we
do with them?
Highway Needs Study
“It [the department] shall undertake a continuing study of needs of the various highways…..”
RS 8:228
Highway Needs Study
TOTAL = $11.709 BILLION
DISTRIBUTION OF 2006 NEEDS BY CATEGORY
PRESERVATION
$2.914 BILLION
20.8%
CAPACITY
$7.837 BILLION
56.0%
SAFETY
(GEOMETRICS)
$3.249 BILLION
23.2%
Total = 14.000 BILLION
Highway NeedsTrend
$0
$2,000
$4,000
$6,000
$8,000
$10,000
$12,000
$14,000
$16,000
1997 1998 1999 2000 2001 2002 2003 2004 2005 2006
Mil
lio
ns
of
Do
lla
rs
Preserv Safety Capacity
Highway Needs vs. Available Funding
$0
$2,000
$4,000
$6,000
$8,000
$10,000
$12,000
$14,000
Mil
lio
ns o
f D
oll
ars
Needs Resources
Resources = 3%
of Needs
$14,000 M
$400 M
Qualitative-Based Needs
• Needs identified through customer input– Public - State and Local Elected Officials
– Metropolitan Planning Organizations
– Regional/Local Planning Officials
– Business/Civic Organizations
– State Agencies -Federal Agencies
• Often based on qualitative considerations– Economic growth -Connectivity
– Quality of Life -Evacuation
Demand for Resources
• Preservation, Safety, and Capacity Needs
• Operations Needs (assessment techniques
under development)
• Qualitative-Based Needs (connectivity,
economic growth, quality of life)
• Mega Projects (I-49 North, I-49 South, LA 1, LA
28, etc.)
Budget Partition
“In fixing priorities, the department shall consider primarily the condition of roads, streets, and structures making up the state highway system…..”
RS 8:229
TOTALCONSTRUCTIONBUDGET
SYSTEMPRESERVATION
OPERATIONS/MOTORISTSERVICES
TRAFFICSAFETY
ADDITIONALCAPACITY/NEWINFRASTRUCTURE
Budget Partition
FY 2006 - 2007
• Sys Preservation $ 273 M
• Ops/Motor. Serv $ 26 M
• Safety $ 29 M
• Add. Capacity - Discretionary $ 62 M
- Corridors $ 10 M
Total $ 400 M
• Enhancements $ 8 M
• TIMED $ 830 M
• Urban Areas $ 36 M
• High Priority / Bond / Misc. $ 130 M
Grand Total $1,404 M
Budget Sub-Partition
System Preservation
• Pavement Pres. (non-Interstate) $112 M
• Pavement Pres. (non-Interstate NFA) $ 28 M
• Pavement Pres. (Interstate) $ 45 M
• Bridge Pres. (on-system) $ 73 M
• Bridge Pres. (off-system) $ 15 M
Total $273 M
Budget Sub-Partition
Operations/Motorist Services
• ITS $ 9.9 M
• Traffic Control Devices $ 7.5 M
• Roadway Flooding $ 3.0 M
• Weigh Stations $ 1.5 M
• Rest Areas $ 0.0 M
• Ferries Operating Budget
• Movable Bridge Preventive Maintenance $ 0.5 M
• Interstate Lighting $ 1.0 M
• TSM $ 2.5 M
Total $25.9 M
Overview of the DOTD
Highway Project Selection Process
How are projects prioritized and selected?
• DOTD District and MPO officials rank projects based on:
– Technical analyses -Customer input
• Project Selection Teams make the final selections based
on:
– District Recommendations -Technical analyses
– Customer input -Available funding
Overview of the DOTD
Highway Project Selection Process
Who are on these “Project Selection Teams”?
• People with expertise in certain fields:
- DOTD Headquarters Officials
- Representatives from other state agencies
- DOTD District Officials (in a few cases)
- Representatives from Federal, local, &
private-sector associations (in a few cases)
Overview of the DOTD
Highway Project Selection Process
Then What Happens?
Overview of the DOTD
Highway Project Selection Process
Recommended (selected) projects assembled into proposed Highway Program
Proposed Highway Program submitted to House & Senate Transportation Committees
Joint Transportation Committee holds public hearings throughout state
Final decision on Highway Program rests with House & Senate Trans. Committees and ultimately full Legislature
Project Delivery System
• Highway Program approved by Legislature
• Must have orderly process to move each project through preconstruction, construction, and into post-construction
• PD System is intended to overcome historic problems maintaining scope, schedule, and budget
• Relies heavily on strong Project Manager (s) taking charge on individual projects
• Program Managers oversee the various project categories (safety, capacity, etc.)
• At a glance, people know where any given project is in the overall process
DOTD Project Delivery Process
REJECT
Elected OfficialsMPOLong Range PlanDistrictsPublic
Stage 0: Feasibility
One Year
Feasibility Analysis of the Proposed Project
Stage 0: Feasibility
One Year
Feasibility Analysis of the Proposed Project
One to Two YearsDetailed Planning & Environmental Analysis
Stage 1: Planning/Environmental Process
One to Two YearsDetailed Planning & Environmental Analysis
Stage 2: Funding
Indefinite Period
Funding Allocation for Design & Construction
Stage 2: Funding &Project Prioritization
Indefinite Period
Funding Allocation for Design & Construction
One to Three Years
Development of Final Plans & Specifications
Stage 3: Final Design Process
One to Three Years
Development of Final Plans & Specifications
Stage 4: Letting
One YearBid Letting Process
Stage 4: Letting
One YearBid Letting Process
Construction of ProjectStage 5: Construction
One to Three Years Construction of Project
Stage 6: Operation
Indefinite Period
On-going Monitoring of Operation & Maintenance
Stage 6: Operation
Indefinite Period
On-going Monitoring of Operation & Maintenance
Project Delivery System
Comments
• Stage 0 occurs prior to project selection
• Some projects will go through Stage 1 and then will be held in Stage 2 indefinitely
• We are working on an estimating procedure for each Stage
• Project Delivery Steering Committee in place to deal with problems that arise on projects and in programs
• “Project Manager” curriculum under development
• Project Management Unit is being staffed to oversee Mega projects and “high risk” projects
Project Delivery System
Overview of the Project Delivery Manual
• 10 chapters – posted on the DOTD website
• Begins with philosophy, principles & quick overview
• Elaboration on each stage
• Ends with appendices on project plan, estimating, Project Delivery Steering Committee, & team building
• Important that you have an understanding of overall process and where you fit in
• More detailed training on individual stages is coming
QUESTIONS?
Project Delivery Manual
Overview
Stage 0
Feasibility
DOTD Project Delivery Process
REJECT
Elected OfficialsMPOLong Range PlanDistrictsPublic
Stage 0: Feasibility
One Year
Feasibility Analysis of the Proposed Project
Stage 0: Feasibility
One Year
Feasibility Analysis of the Proposed Project
One to Two YearsDetailed Planning & Environmental Analysis
Stage 1: Planning/Environmental Process
One to Two YearsDetailed Planning & Environmental Analysis
Stage 2: Funding
Indefinite Period
Funding Allocation for Design & Construction
Stage 2: Funding &Project Prioritization
Indefinite Period
Funding Allocation for Design & Construction
One to Three Years
Development of Final Plans & Specifications
Stage 3: Final Design Process
One to Three Years
Development of Final Plans & Specifications
Stage 4: Letting
One YearBid Letting Process
Stage 4: Letting
One YearBid Letting Process
Construction of ProjectStage 5: Construction
One to Three Years Construction of Project
Stage 6: Operation
Indefinite Period
On-going Monitoring of Operation & Maintenance
Stage 6: Operation
Indefinite Period
On-going Monitoring of Operation & Maintenance
Stage 0 Purpose
• Determine project feasibility
- Technical (will it work and can we build it)
- Environmental
- Financial
• “GO / NO-GO”
Stage 0 Process Overview
• Addresses different project types- Typical (regular program and “mega’)
- Federal/State Earmark
- Special Category (urban sys/CMAQ, RR crossing,
CM, Enhance)
• Complexity of project will determine extent of
documentation
• Integrated with the Project Selection Process
Stage 0 Process Steps
1. Determine purpose and need
2. Identify the initial project concept
3. Screen for major environmental impacts
4. Develop preliminary scope and estimate
5. Identify expected funding source (s)
Stage 0 Checklist
Stage 0
Environmental Checklist
Stage 0 Checklists
• Stage 0 Study Checklist- Completed checklist is Stage 0 study for minor or
routine projects
- Checklist is outline of Stage 0 study for complex
projects
• Stage 0 Environmental Checklist- Aids in preliminary review of potential impacts to
natural and human environment
- Includes a list of environmental database websites
- Explanation of relevance of each item in checklist
Responsibility
• Responsibility Matrix
• Program Manager
– Check Completeness / Approve Stage 0
– Advance to Stage 1
Stage 0 Benefits
• Will allow more informed decisions before any
promises are made
• Will make it easier to determine type of
environmental document needed (CE, EA, EIS)
in Stage 1
• Can reduce time required for Stage 1
• Will allow better financial planning and a better
public image
Stage 0 (Feasibility)
• Manual
• Training
QUESTIONS?
Project Delivery Manual
Overview
Stage 1
Planning and Environment
DOTD Project Delivery Process
REJECT
Elected OfficialsMPOLong Range PlanDistrictsPublic
Stage 0: Feasibility
One Year
Feasibility Analysis of the Proposed Project
Stage 0: Feasibility
One Year
Feasibility Analysis of the Proposed Project
One to Two YearsDetailed Planning & Environmental Analysis
Stage 1: Planning/Environmental Process
One to Two YearsDetailed Planning & Environmental Analysis
Stage 2: Funding
Indefinite Period
Funding Allocation for Design & Construction
Stage 2: Funding &Project Prioritization
Indefinite Period
Funding Allocation for Design & Construction
One to Three Years
Development of Final Plans & Specifications
Stage 3: Final Design Process
One to Three Years
Development of Final Plans & Specifications
Stage 4: Letting
One YearBid Letting Process
Stage 4: Letting
One YearBid Letting Process
Construction of ProjectStage 5: Construction
One to Three Years Construction of Project
Stage 6: Operation
Indefinite Period
On-going Monitoring of Operation & Maintenance
Stage 6: Operation
Indefinite Period
On-going Monitoring of Operation & Maintenance
Stage 0: Feasibility
• Provides a “Go/No Go” Decision
– Preliminary Purpose and Need
– Initial Project Concept
– Preliminary Environmental Review
– Preliminary Project Estimate and Budget
– Expected Funding Sources
• Stage 0 Environmental Checklist completed and
provided for Stage 1 Processing
National Environmental Policy Act
NEPA says all agencies of the Federal Government shall –
• utilize a systematic, interdisciplinary approach which will insure the integrated use of the natural and social sciences and the environmental design arts in planning and in decision making which may have an impact on man's environment;
• identify and develop methods and procedures…which will insure that presently unquantified environmental amenities and values may be given appropriate consideration in decision making…
National Environmental Policy Act
• Include in every recommendation or report on proposals for…major Federal actions significantly affecting the quality of the human environment, a detailed statementon:
– the environmental impact of the proposed action,
– any adverse environmental effects which cannot be avoided should the proposal be implemented,
– alternatives to the proposed action,…
NEPA
• NEPA acts as an
“umbrella’ under
which all
environmental laws,
regulations, and
Executive Orders are
administered
• Results in the Best
Overall Public
Interest Decision
Wetl
an
ds
Cu
ltu
ral
Reso
urc
es
Co
mm
un
ity I
mp
acts
Air
Qu
ali
ty
Sta
te a
nd
Lo
cal
Law
s
Farm
lan
ds
Civ
il R
igh
ts
En
vir
on
men
tal
Ju
sti
ce
Park
lan
ds
All
Ap
pli
cab
le F
ed
era
l L
aw
s
En
dan
gere
d S
pecie
s
Safe
ty
Wetl
an
ds
Cu
ltu
ral
Reso
urc
es
Co
mm
un
ity I
mp
acts
Air
Qu
ali
ty
Sta
te a
nd
Lo
cal
Law
s
Farm
lan
ds
Civ
il R
igh
ts
En
vir
on
men
tal
Ju
sti
ce
Park
lan
ds
All
Ap
pli
cab
le F
ed
era
l L
aw
s
En
dan
gere
d S
pecie
s
Safe
ty
Wetl
an
ds
Cu
ltu
ral
Reso
urc
es
Co
mm
un
ity I
mp
acts
Air
Qu
ali
ty
Sta
te a
nd
Lo
cal
Law
s
Farm
lan
ds
Civ
il R
igh
ts
En
vir
on
men
tal
Ju
sti
ce
Park
lan
ds
All
Ap
pli
cab
le F
ed
era
l L
aw
s
En
dan
gere
d S
pecie
s
Safe
ty
Stage 1: NEPA Process
• Federal-aid or Federal Action
– Lead Federal Agency Determination
– Cooperating Agency Determination
– Participating Agency Designation (SAFETEA-LU)
• Categorical Exclusion (CE)
• Environmental Assessment/Finding of No
Significant Impact (EA/FONSI)
• Environmental Impact Statement/ Record of
Decision (EIS/ROD)
Stage 1: “NEPA-like” Process
• State-Funded Only
– Environmental Engineer Administrator acts as
surrogate for Lead Agency
• Environmental Exclusion (EE)
• Environmental Assessment/ Environmental
Finding (EA/EF)
• Environmental Impact Statement/ Environmental
Record (EIS/ER)
Stage 1: Project Management
• Project Managers
– Overall from Project Management Unit
– Dual Managers from Environmental Section and
appropriate Design Section
• Project Team staffed by representatives of other
Sections (Design, Geometrics, Hydraulics,
Traffic, Real Estate, Utilities, District, Planners,
Consultants)
Stage 1: CE/EE
• Project/Program Manager prepares budget from
Stage 0
• Environmental Coordinator coordinates analysis
and prepares documentation in accordance with
NEPA
• Completes CE/EE determination
Stage1:EA/FONSI/EF Or EIS/ROD/ER
• Project Manager (s) appointed
• Team Building
• Project Manager initiates environmental process
• FONSI/EF or ROD/ER issued
• Scope and Budget Memo prepared and
approved
Stage 1: Team Building
• Overall or Environmental Project Manager assumes lead role
• Preliminary Project Plan established
• Project Team established
• Scope of Work finalized
• Consultant selected, if appropriate
• Development of project activity schedule (PPMS)
• Project Management Plan finalized
• Project initiation meeting held
Stage 1: EA or EIS
• Documentation of social, economic and
environmental impacts
• List of Permits
• Location and Major Design Features
• Updated Cost Estimate (PE and FE, Cons,
ROW, Utilities, Mitigation)
• Mitigation and Environmental Commitments
Stage1: Authority – CE/EE
• Programmatic – Environmental Engineer
Administrator (EEA) has authority from FHWA to
make CE determination, EEA has authority to
make EE determination
• Documented – FHWA has authority to make CE
determination, EEA has authority to make EE
determination
Stage 1: Authority: EA/FONSI/EF
• Lead Federal Agency determines need to
prepare EA, issues FONSI for NEPA projects or
requires preparation of EIS
• EEA determines need to prepare EA, issues EF
for non-NEPA projects or requires preparation of
EIS
Stage 1: Authority – EIS/ROD/ER
• Lead Federal Agency determines need to
prepare EIS, issues ROD for NEPA projects
• EEA determines need to prepare EIS, issues ER
for non-NEPA projects
Stage 1: Deliverables
• Environmental Closure Documentation– CE/EE
– EA/FONSI/EF
– EIS/ROD/ER
• Scope and Budget Memorandum– Description of Project
– Estimates and Full-Implementation Funding
– Commitments, Agreements, and Permits
– Recommended by Project Manager (s)
– Signed by Chief Engineer
Stage 1 Manual of Standard Practice
…ENVIRONMENTALLY
Louisiana Department ofTransportation and DevelopmentandFederal Highway AdministrationLouisiana Division
State Project No. 736-99-1025F.A.P. No. SPR-0010(025)
Stage 1 – Planning/EnvironmentalManual of Standard Practice
…ENVIRONMENTALLY
Louisiana Department ofTransportation and DevelopmentandFederal Highway AdministrationLouisiana Division
State Project No. 736-99-1025F.A.P. No. SPR-0010(025)
Stage 1 – Planning/EnvironmentalManual of Standard Practice
QUESTIONS?
Project Delivery Manual
Overview
Stage 2
Funding and Project Prioritization
DOTD Project Delivery Process
REJECT
Elected OfficialsMPOLong Range PlanDistrictsPublic
Stage 0: Feasibility
One Year
Feasibility Analysis of the Proposed Project
Stage 0: Feasibility
One Year
Feasibility Analysis of the Proposed Project
One to Two YearsDetailed Planning & Environmental Analysis
Stage 1: Planning/Environmental Process
One to Two YearsDetailed Planning & Environmental Analysis
Stage 2: Funding
Indefinite Period
Funding Allocation for Design & Construction
Stage 2: Funding &Project Prioritization
Indefinite Period
Funding Allocation for Design & Construction
One to Three Years
Development of Final Plans & Specifications
Stage 3: Final Design Process
One to Three Years
Development of Final Plans & Specifications
Stage 4: Letting
One YearBid Letting Process
Stage 4: Letting
One YearBid Letting Process
Construction of ProjectStage 5: Construction
One to Three Years Construction of Project
Stage 6: Operation
Indefinite Period
On-going Monitoring of Operation & Maintenance
Stage 6: Operation
Indefinite Period
On-going Monitoring of Operation & Maintenance
Stage 2: Funding and
Project PrioritizationPurpose: To provide for a realistic
project time line.
Stage 2: Funding and Project
Prioritization
Objectives:
• Update the Cost Estimate and Insure
Funding Is Available to Proceed
• Develop the Project Plan and Project
Delivery Date (PDD)
• Establish the Program Fiscal Year (for the
Construction Letting)
• Determine the Funding Source
• Insure the Project Is Included in the STIP
and Highway Program
Process
Identify Origin of Project
• Priority program
• Earmark project
Priority Program
Task & Responsibility
• Check estimate & update Project Manager
if necessary
• Establish project plan Project & Program Manager
• Establish tentative Highway Program Engr.
source
• Enter milestones in Highway Program Engr.
LETS system
• Enter project info. in Project Manager
PPMS
• Changes in Project Section Head of Project
Delivery date Manager
Demo, Bond, or Other Earmark
Funds
Task & Responsibility
• Check estimate & update Project Manager
if necessary
• Review funding Program Manager
status
• Identify activities which Project Manager
can be accomplished
• Enter milestones for activities Highway Program Engr.
that are funded in LETS system
• Enter project information in Project Manager
PPMS system
• Inform Project sponsors & Program Manager
legislators of funding needs
Deliverables:
· Updated Cost Estimate
· Project Plan
· Project Delivery Date (PDD)
· Program Fiscal Year for Engineering,
ROW, Utilities, & Construction
· Funding Source Identified
Gatekeeper For Stage 2:
Highway Program Engineer
QUESTIONS?
Project Delivery Manual
Overview
Stage 3
Final Design Process
DOTD Project Delivery Process
REJECT
Elected OfficialsMPOLong Range PlanDistrictsPublic
Stage 0: Feasibility
One Year
Feasibility Analysis of the Proposed Project
Stage 0: Feasibility
One Year
Feasibility Analysis of the Proposed Project
One to Two YearsDetailed Planning & Environmental Analysis
Stage 1: Planning/Environmental Process
One to Two YearsDetailed Planning & Environmental Analysis
Stage 2: Funding
Indefinite Period
Funding Allocation for Design & Construction
Stage 2: Funding &Project Prioritization
Indefinite Period
Funding Allocation for Design & Construction
One to Three Years
Development of Final Plans & Specifications
Stage 3: Final Design Process
One to Three Years
Development of Final Plans & Specifications
Stage 4: Letting
One YearBid Letting Process
Stage 4: Letting
One YearBid Letting Process
Construction of ProjectStage 5: Construction
One to Three Years Construction of Project
Stage 6: Operation
Indefinite Period
On-going Monitoring of Operation & Maintenance
Stage 6: Operation
Indefinite Period
On-going Monitoring of Operation & Maintenance
Needed Input From Stage 2
Well-defined scope
Preliminary schedule (PDD)
Up to date budget
Purpose: Is to execute the final plans &
specifications within scope,
on-schedule and within budget.
Major Tasks for Stage 3
Develop Topographical survey
Prepare Preliminary Plans, Cost Estimate &
Conduct Plan-in-Hand (Road and Bridge)
Value engineering
Prepare Right-of-Way Maps
Determine Utility Conflicts
Appraise and Acquire Right-of-Way
Prepare Final Road & Bridge Plans (ACP’s)
Determine Permits or Agreements Needed
Develop Construction Proposal (PS&E)
Output Of Stage 3
Signed final plans
Specifications – 95% construction proposal
Signed cost estimate
Right-of-way acquired
All agreements secured (utility, RR, cooperative
endeavor-city/parish, etc.)
Environmental (scenic stream, COE-wetlands, coastal
use) and
Non-environmental permits (coast guard)
Completion Of Stage 3
Project delivery date (PDD)
Goal: To have the “PDD” efforts
complete prior to fiscal year
(July 1 – June 30).
Will allow the department to be
flexible with the letting dates.
Effectively Managing Project
Delivery
Endorsed scope, schedule and budget
Project Manager assigned – key contact
Build team – task managers assigned
Frequently communicate to all team members to get status on all progress
Manage any change
Use PPMS System, update frequently
Regular schedule & budget monitoring/evaluation with revisions to reflect actual progress
Value Engineering (EDSM No: I.1.1.18) - mandated for projects with total cost of $25 million or more ($20 million or more for bridge projects)
Application of resources to meet schedule.
Plan The Work & Work The Plan
Tools:
Project Scheduling Software = PPMS + Primavera
(CPM Software)
DOTD Construction Program (PPMS Templates)
PPMS Standard And Summary Templates
Current templates:
Standard DOTD – approx. 125 activities or tasks
Stage “1+3” CE Summary
Stage “3” EA-EIS Summary
Urban Projects Standard
Pavement Preservation Standard
Pavement Preservation Summary
Templates to be developed:
Stage “1” EA summary (Environmental)
Stage “1” EIS Summary (Environmental)
Stage “1+3” CE Standard
Stage “3” EA-EIS Standard
STAGE “3” CE SUMMARY TEMPLATE
STAGE “1+3” CE SUMMARY TEMPLATE ADDS PRELIMINARY TASKS.
SFD410
Final Plans
Notice to
Proceed
SFD420
DUS Coordinate
Required Utility
Agreements
SFD460
Obtain Required
Permits/
Agreements
SFD470
Obtain Scenic
Stream Permit
SFD420
Develop 95%
Final Road
Design
SFD430
Develop 95%
Final Bridge
Design
SFD440
Appraise and
Acquire Right of
Way
SFD455
Approval of Utility
Agreements
SFD480
Develop 100% Final
Design Plans and
Estimates
SFD499
Project Delivery
Date
SFD469
Develop
Construction
Proposals to 95%
STAGE “3” EA OR EIS SUMMARY TEMPLATE
SPD200
Stage 3
Project Startup
SPD210I
Topographical
Surveying
(In-house)
SPD210C
Topographical
Surveying
(Consultant)
SPD260
Perform
Property
Survey Work
SPD270
Develop
Preliminary
ROW Maps
SPD250
District/Utilities
Preliminary
Design
Coordination
SPD220
Develop 100%
Preliminary
Road Design
SPD230
Develop 100%
Preliminary
Bridge Design
SPD280
Setup for Final
Plan Work
SFD210
Final Plans
Notice to
Proceed
SPD290
Schedule and
Conduct Joint
Review Meeting
SFD260
Obtain Required
Permits/
Agreements
SFD270
Obtain Scenic
Stream Permit
SFD250
DUS Coordinate
Required Utility
Agreements
SPD292
Prepare, Review,
and Transmit
Final ROW Maps
SPD296
Prepare HQ
Utility Cost
Estimate
SPD294
Prepare ROW
Cost Estimate
SFD255
Approval of Utility
Agreements
SFD230
Develop 95%
Final Bridge
Design
SFD220
Develop 95%
Final Road
Design
SFD240
Appraise and
Acquire Right of
Way
SFD280
Develop 100%
Final Design
Plans and
Estimates
SFD289
Develop
Construction
Proposal to 95%
SFD299
Project
Delivery Date
PRELIMINARY
PLANS
(COMPLETE)
Environ
CLR.(CE)
R/W Map
(COMPLETE)12 MONTHS – 3 SITES OR LESS
18 MONTHS – 3 SITES, 2 RELOCATIONS
24 MONTHS – COMPLEX URBAN
UTILITY
CLR.
R/W CLR.
PDD
TRANSMIT
95% ACP
For
Review
ACP
COMPLETE
3 MONTHS
(MIN.)12 – 24 MONTHS
2 MONTHS (MIN.)
3 MONTHS
(MIN.) 3 MONTHS (MIN.)
TYPICAL STAGE “3” MAJOR
MILESTONE TIMELINES
A Project Task Is An Assignable
Item Of Work That Has:
A definable beginning and end
A time planned duration
A state of completion that can be estimated at any time
A reviewable internal and external deliverable at task
completion
Significant Milestones in Stage “3”
Completion of topographic survey
60% preliminary design geometric review
60% preliminary design hydraulic review
Develop preliminary pavement design
Plan-in-hand meeting (major milestone)
Joint plan review R/W (major milestone)
Advance check prints (major milestone)
Release letter (utilities)
Certify R/W complete
Finalize permit
Develop construction proposal – 95%
Plans signed by Chief Engineer
Any Change In Scope, Schedule Or Budget
Requires The Following Documentation:
Project overview narrative
Original project scope
Change project scope
Reasons for change
Environmental requirement changes
Project schedule changes
Budget and funding changes
Send change scope and budget memorandum approved by Chief
engineer to program manager and project delivery steering
committee.
Current And Future Project
Management Stage 3Current:
All projects to be placed in PPMS System.
Stage “3” PM’s are located in major design units.
Both Project Management and Design (Engr. & Plans).
Future:
New Project Management section being formed.
PM’s in new section responsible for management of high
risk projects (DOTD Risk Matrix.)
New section responsible for PPMS System management.
Project not high-risk to be managed & designed by Major
Design sections.
QUESTIONS?
Project Delivery Manual
Overview
Stage 4
Assignment of Optimized Letting
Dates
Purpose and Scope
Purpose:
Provide an orderly, predictable mix and flow
of projects.
Scope:
All headquarters let projects except contract
maintenance projects.
Stage 4 Goals
• Reflective of DOTD’s Budget Partitions.
• Optimized geographical mix of projects.
• Reflective of local and statewide priorities.
• Reducing socio-economic impacts.
• Level monthly letting schedule.
• Baseline for annual Dashboard measure.
• Re-level monthly schedule as necessary.
Stage 4 Benefits
• Greater confidence in letting schedule.
• Reduced adverse effects of construction.
• Improved planning horizon for contractors.
• Fewer last minutes changes.
• Increased public awareness.
• Reasonable adjustment of schedule.
Preliminary Work
• Starting in Mid-February.
• Determination of potential project list.
– Projects that will not be let this SFY
– Projects in the next SFY’s capital outlay
program
Baseline Letting Schedule
The process contains eight steps starting in
March of each year to prepare a letting
schedule for a SFY that starts July 1st of the
same calendar year.
Step1 - 1st week
• Sort all potential projects by program.
• Based on PDDs, determine the earliest possible letting dates.
Step 2 - 2nd and 3rd weeks
• Preliminary review by program managers:
– Preliminary letting order
– Budgeting issues
– Determination of potential conflicts
– District priorities
Step 3 - 4th week
• Create the preliminary letting list.
• Applying level dollar value per letting.
• Mix of projects based on defined goals.
Step 4 - 5th week
• Section 39 ( Project Finance) review
• Verification of Federal Funding availability:
–Projects scheduled from July thru
October
–Determining alternative options if federal
funding not available
Step 5 - 6th week
• Review by District Administrators for:
– Conflicts
– Special Needs
– Specific requirements
• Adjustments will be made accordingly.
Step 6 - 7th week
• Evaluation of all information received.
• Non-critical projects are moved to re-
balance the monthly letting list.
Step 7 - 7th and 8th week
• Draft final project letting list.
• Project Delivery Steering Committee (PDSC)
review:
– Specific project adjustment
– Legislative input
– Any special requirements or criteria
– Re-adjustment of the list
Step 8 - end of April
• Chief Engineer's approval of the final list.
• Must be completed by 1st of May.
• Annual baseline is established upon Chief Engineer’s approval.
Letting Schedule Maintenance
• PDD changes
• No bids or all bids rejected
• Project postponement
• Project withdrawal
• Letting changes due to executive decision
• Changes to adjust for other projects
Processes Remaining the
Same….
• Project authorization
• DBE issues
• Award process
• Contract administration
Concluding Remarks
• Stage 4 process is still evolving.
• Impact on business/civic interests must be
determined by project managers and
Districts.
• Project Control will work with all
responsible parties to minimize conflict in
the letting schedule.
QUESTIONS?
Project Delivery Manual
Overview
Stage 5
Construction
Purpose
• To administer a construction contract between the Department and a Contractor.
• To have the project completed–On time
–In budget
–In scope
Additional Goals
• To minimize disruption to the traveling
public
• To keep the public accurately informed
about the project.
Duration
• Stage 5 begins with receipt of the Notice
of Contract Execution (NOCE) from
Project Control in Stage 4 and continues
through the final acceptance at which time
the project is delivered to the operations
staff in Stage 6
• Projects vary immensely. From turn lanes
to major Interstate interchanges.
• Some things are common to all projects.
ProcessProject Schedule
Contractor Responsibility
Project Inspection
Sampling and Testing
Partial Estimates
Creating and Processing Change
Order
Environmental Mitigation
Notice to Proceed
Preconstruction Conference
Contract Administration
Final Inspection
Final Acceptance
Final Audit Deliver to Stage 6 (System Operations and Performance)
Construction Public Information Plan
Construction Impact Mitigation
Notice of Contract Execution from Stage 4
Contract Administration
• Project Schedule
• Contractor Responsibility
• Project Inspection
• Sampling & Testing
• Partial Estimates
• Creating & Processing Change Orders
• Environmental Mitigation
• Construction Impact Mitigation
• Final Inspection
• Final Acceptance
• Final Audit
Contract Administration Manuel
• Provides guidelines for Project Engineers
and Inspectors.
• Found on the DOTD Intranet
Construction Impact Mitigation
• Public Information
• Construction Time
• Milestones
• Traffic Delay Mitigation
• Construction Funding
Construction Public
Information Plan
• Effective communication is essential to the overall success of any major construction project
• Our goal is to provide timely and accurate information to motorists, emergency services personnel, business owners, public officials, commercial truck operators, the media and all others that may be impacted by the construction
• Complaints usually drop if the stakeholders are informed
Construction Public
Information Plan
• A written public information plan will be developed
for each project
• The plan will be developed by the assigned public
affairs officer, local district representative, the
contractor & other DOTD personnel as needed
• Detail of the plan proportional to the project’s
impact
• Act 103 of the 2003 Legislature requires project
notifications to sheriffs, parish presidents, fire
chiefs & state legislators
Key Elements of the Plan
• Development of project fact sheet for all DOTD personnel to use in providing consistent message
• Development of media contact list
• Development & distribution of initial project notification to media, affected businesses & residents, emergency services, schools & school transportation, etc.
• Regular updates to media
• Possible periodic appearances by DOTD on local morning TV shows, radio interviews, etc.
Construction Time
• Projects are let with several different types of
contract times: working day, calendar day & A+B
calendar day
• A+B bidding with calendar day will be used
whenever practical
• Exceptions are non-interstate pavement
preservation projects, typical contract
maintenance projects and enhancement projects
which will be let as working day projects. Clearing
& grubbing projects which will be let as calendar
day projects
Construction Time (continued)
• As of the December 2003 letting, calendar day
projects have a special provision allowing
contract time extensions for adverse weather
conditions. The contractor is required to include
these adverse weather days in their “B” bid. At
the conclusion of the contract, the contractor can
request additional time if the actual adverse
weather days exceed the anticipated days in the
contract. In no case will the original “B” contract
days be reduced
Milestones
• All calendar day projects will require a milestone
schedule
• Schedule will include starting date, completion
date, lane closure & re-openings & other
pertinent events determined during the project
development process
• These milestones will determine the status of a
project
Traffic Delay Mitigation
• The lion’s share of traffic mitigation will be addressed during Stage 3, Final Design Process
• Goal is to use real time traffic data (permanent and construction ITS) to notify the motoring public of unexpected delays
• Traffic mitigation will require a review of the traffic flow during the different phases of the project
• Adjustments will be made to the traffic control plan if warranted
Construction Funding
• Change orders are coded based on the reason for the change order
• 7 categories: plan error or omission, different site conditions, DOTD convenience, Third party accommodation, contractor convenience, untimely ROW/Utility Relocation & Design Error
• These codes will help us identify problem areas
Construction Funding (continued)
• Change orders that are caused by plan errors, different site conditions & untimely ROW/Utility Relocation will be noted to the Project Delivery Steering Committee (PDSC) since they normally increase the cost of the project
• Change orders that are caused by DOTD convenience, Third party accommodation and contractor convenience may not always be approved. The Project Delivery Steering Committee will be notified when the approved funding has been exceeded
Project Development Steering
Committee Duties in Stage 5
• The PDSC authorizes, monitors and tracks
expenditures vs budget for Stage 5 work.
• The PDSC receives, from the Construction
Division, and reviews large change order
requests that exceed contingency limits and
assesses impact to the budget
• The PDSC receives and reviews project close-
out report from Construction Audit and Project
Control and accounts for funds being restored to
the program
Performance Indicators
• Percentage of projects completed within contract
time
• Percentage of partial estimates processed on
time
• Percentage of final estimates processed on time
(30 calendar days for projects<$2 million & 60
calendar days for projects >$2 million
• Time to process plan changes
QUESTIONS?
Project Delivery Manual
Overview
Stage 6
After The Project Is Complete
DOTD Project Delivery Process
REJECT
Elected OfficialsMPOLong Range PlanDistrictsPublic
Stage 0: Feasibility
One Year
Feasibility Analysis of the Proposed Project
Stage 0: Feasibility
One Year
Feasibility Analysis of the Proposed Project
One to Two YearsDetailed Planning & Environmental Analysis
Stage 1: Planning/Environmental Process
One to Two YearsDetailed Planning & Environmental Analysis
Stage 2: Funding
Indefinite Period
Funding Allocation for Design & Construction
Stage 2: Funding &Project Prioritization
Indefinite Period
Funding Allocation for Design & Construction
One to Three Years
Development of Final Plans & Specifications
Stage 3: Final Design Process
One to Three Years
Development of Final Plans & Specifications
Stage 4: Letting
One YearBid Letting Process
Stage 4: Letting
One YearBid Letting Process
Construction of ProjectStage 5: Construction
One to Three Years Construction of Project
Stage 6: Operation
Indefinite Period
On-going Monitoring of Operation & Maintenance
Stage 6: Operation
Indefinite Period
On-going Monitoring of Operation & Maintenance
• Disposal of excess right-of-way
• Documentation of additional Utilities permitted
on the right-of-way
• Compliance with post-construction
environmental commitments
• Materials durability and performance
• Identification of design features that complicate
maintenance activities
• Identification of design features that impede
efficient traffic operations
Stage 6 Activities
Disposal of excess right-of-way
• District Maintenance Engineer, District Design
Engineer, and Real Estate Section
• Reduce Maintenance and Liability, and put
property back into the tax base
• Un-economic remainder, temporary need for
construction, change order, anticipation of future
need, realignment…
Disposal of excess right-of-way
• May be identified during the project
• Usually identified when someone makes an
inquiry (such as a joint use) or when a problem
develops (such as additional maintenance or a
law suit).
Disposal of excess right-of-way
• Identify potential excess property
• Check against standards
• Check for future needs
• District Administrator agrees that the parcel should be disposed of
• Real Estate Section grants servitude to each utility
• Real Estate handles disposal through sale or transfer; may lease if no buyer is available (only excess property may be leased; required property is covered by joint use)
Documentation of additional Utilities
permitted on the right-of-way
• District Utility Relocation
Unit with assistance of
District Right-of-way Permit
Unit
• Right-of-way Permit
Database
• Two Thirds of facilities are
installed without permit
Compliance With Post-Construction
Environmental Commitments
• District Maintenance Engineer, District Traffic Engineer, Environmental Section
• Erosion control, water quality monitoring, vegetation maintenance…
• Notify the Environmental Section upon completion
Materials Durability and
Performance
• District Maintenance Engineer, District Traffic Engineer
• Early failure of surface, shoulder, drainage, etc…
• Project number and completion date, description of failure, corrective action and date of action
• Submit report to Chief Engineer, Assistant Secretary of Operations, District Administrator, Design Division, Maintenance Management, and any other effected parties
Identification of Design Features That
Complicate Maintenance Activities
• District Maintenance Engineer
• List feature that make maintenance more difficult, reason, and correction
• Submit report to Chief Engineer, Assistant Secretary of Operations, District Administrator, Design Division, Maintenance Management, and any other effected parties
Identification of Design Features that
Impede Efficient Traffic Operations
• District Traffic Engineer
• List feature that impedes traffic
flow, reason, and correction
• Submit report to Chief
Engineer, Assistant Secretary
of Operations, District
Administrator, Design Division,
Traffic Division, and any other
effected parties
QUESTIONS?