FEMA Benefit-Cost Analysis
Re-engineering (BCAR)
Project Cost Guidance Methodology Report
Version 4.5
May 2009
-
8/4/2019 Project Cost Guidance
2/87
-
8/4/2019 Project Cost Guidance
3/87
i
Table of Contents
Purpose.....................................................................................................................................................1 Introduction: Problem Statement..............................................................................................................1Recommendations: Proposed Methodology to Address Problem Statement ............................................. 2Section 1: Cost Estimating Methodology Programming and User Overview............................................. 4
Step 1: Developing an Estimate of Pre-Construction Costs.......................................................................8Step 2: Developing an Estimate of Construction Costs ............................................................................. 8Step 3: Developing an Estimate of Ancillary Costs....................................................................................9Step 4: Developing an Estimate of Annual Maintenance Costs............................................................... 10
Step 5: Adjusting Your Estimate to Account for Project Timing .............................................................. 10Step 6: Review and Confirmation of the Estimate .................................................................................. 12
Section 2 Provide Specific Guidance......................................................................................................14Section 3 Benefit-Cost Analysis Handout Tool ....................................................................................... 15Conclusions: Reasons for Selection of Proposed Methodology ................................................................ 16APPENDIX A: Mitigation Strategy Flow Charts.......................................................................................... 17
APPENDIX B: Sample Estimates................................................................................................................34APPENDIX C: Cost Estimating Storyboard................................................................................................ 67Sample BCA Tool Cost Estimating Screenshot .......................................................................................... 68APPENDIX D: Scope Builder Checklists ..................................................................................................... 69
Tables
Table 1. Proposed Hazard Mitigation Project Types ................................................................................. 2Table 2. Recommended Proxy Values ...................................................................................................... 9
-
8/4/2019 Project Cost Guidance
4/87
ii
-
8/4/2019 Project Cost Guidance
5/87
1
Purpose
This Benefit-Cost Analysis Re-engineering (BCAR) report is provided for use by the Federal Emergency
Management Agency (FEMA) Technical Advisory Group (TAG) to review and approve the recommended
methodology to provide project cost guidance for the FEMA benefit-cost analysis (BCA) modules. The
methodology report is part of a larger effort to re-engineer the FEMA BCA methods, modules, guidance,
and training to improve the BCA process.
Introduction: Problem Statement
The BCA modules were developed to calculate project benefits and project costs as part of the effort to
evaluate the cost-effectiveness of proposed hazard mitigation projects. However, since project benefits
are more difficult to determine than project costs, the FEMA BCA modules and guidance devote most of
their efforts to estimating and documenting project benefits. As a result, there is little guidance
provided on how to properly and completely estimate and document project costs used in the BCAmodules. For this reason, many applicants submit BCAs with project costs that are incomplete,
inaccurate, or poorly documented.
In response to this problem, FEMA Headquarters has requested that additional guidance be provided to
assist applicants with the preparation of complete and well-documented project costs as part of the
BCAR initiative. Specifically, additional guidance was requested on the following five project cost
estimate issues:
1. What hard construction and ancillary costs related to a variety of mitigation project types are
acceptable?
2. Should contingencies and allowances for change orders be accounted for in project cost
estimates?
3. What are the acceptable sources of data for the mitigation project cost estimates?
4. What is an appropriate level of detail to be included in a mitigation project cost estimate?
5. Can we provide helpful hints and defined values to help the grant applicant develop complete
and accurate cost estimates?
At present, the inclusion of contingencies and allowances for change orders is not being considered by
the mitigation directorate; these items are more relevant to FEMAs Public Assistance Program, and are
not applicable to the majority of mitigation projects being considered.
Specifically, the URS BCA team has been asked to address 16 specific mitigation project cases comprised
of five hazards (flood, wind, earthquake, landslide, and wildfire) and two to five project types per
hazard, including structural and non-structural mitigation alternatives, as shown in Table 1. While the
estimating methodology is applicable to additional hazards and project types, sample scope items,
-
8/4/2019 Project Cost Guidance
6/87
2
estimating flowcharts, and sample estimates are only provided for the 16 specific mitigation project
cases shown in Table 1. Any project types that do not fit into the 16 defined types shall be defined as
other.
Table 1. Proposed Hazard Mitigation Project Types
Hazard Mitigation Project Type
Flood Acquisition
Elevation
Relocation
Wet and dry floodproofing/floodwalls
Drainage structures (culverts, storm drains, etc.)
Wind A combination of strengthening load path members and connections and addingshutters/impact-resistant glazing
Tornado safe roomsEarthquake Strengthen structural elements
Anchor/brace non-structural elementsLandslide Retaining structures (gabions, piles, mechanically stabilized earth systems, etc.)
Toe erosion armoring
Surface/subsurface drainage improvements
Bio-engineered surface erosion protection
Fire Vegetation control (including fire breaks around critical facilities/roads)
Fire-resistant roofing
Fire suppression
Recommendations: Proposed Methodology to Address Problem
Statement
To address the problem of inadequate project cost estimates as well as the project cost estimate issues
raised by the BCAR initiative, the URS BCA team proposes the following methodology to provide
expanded cost estimating guidance:
Our efforts focused on three main areas:
1. Guidance on how to develop a complete estimate is presented in the 16 hazard/mitigation
project type flow charts and sample estimates provided in Appendices A and B. These flowcharts and sample estimates are further supported by definitions and references contained in
the help area of the BCAR tool.
2. An overall estimating approach that walks the users through a six step process designed to help
account for construction and non-construction related costs associated with a mitigation
project. This process is defined and outlined in the storyboard presented in Appendix C.
-
8/4/2019 Project Cost Guidance
7/87
3
3. A Scope Builder Checklist is designed for reference by Applicants/subapplicants prior to their use
of the BCA cost estimating tool. This Handout will provide guidance to assist in the preparation
of an effective scope of work and will assist the preparer in the identification and collection of
the cost information needed to use the BCA module. The Checklists are provided in Appendix D.
-
8/4/2019 Project Cost Guidance
8/87
4
Section 1: Cost Estimating Methodology Programming and User
Overview
The critical part of developing an accurate cost estimate is having a defined scope of work that itemizes
the specific work elements (tasks) that will be accomplished as part of the mitigation project. Once
these specific work elements are defined they can be translated into work element descriptions for
which quantities and unit prices can be estimated. The flow charts, sample estimates, and scope builder
tables provided in Appendices A, B, and D offer guidance and suggestions as to typical work elements
associated with the various mitigation measures. Those resources are not intended to be all inclusive,
and each mitigation project may have different and unique elements that must be included in the scope
of work and cost estimate.
An estimate can be developed in a variety of ways, but most estimates fall into the following categories:
1. Published unit price information for defined work elements can be obtained from commercialestimating sources such as RS Means and Marshall & Swift. This information is copyrighted and
users typically purchase the right to use their information. Note that these published cost
sources are regularly updated and if the estimate is prepared using old unit price information,
the estimate should be updated to reflect current pricing.
2. Historical Costs for completing the similar projects can be obtained from local contractors,
building officials, State hazard mitigation officers, and project owners. Note that these historical
costs should be escalated to ensure current pricing.
3. Contractor Bids or estimates for completing a specific scope of work or project are typically
completed at the time of the bid and account for inflation over the course of the project.
The accuracy of each of these estimates will vary according to the level of detail in the scope of work
and work elements to be estimated. Preliminary estimates are applicable for initial project screening or
scoping, but detailed costs estimates should be used when submitting project applications for funding
approvals.
The cost estimating portion of the BCA methodology shall use a step by step process of simple inquiries,
dynamic help screens, and input boxes to walk users through the six steps associated with developing a
complete cost estimate for their mitigation project. This six-step process outlined below follows the
users selection of a hazard and mitigation strategy and consists of:
1. Developing an estimate of pre-construction or non-construction costs
2. Developing an estimate of construction costs
3. Developing an estimate of ancillary costs
4. Developing an estimate of annual maintenance costs
-
8/4/2019 Project Cost Guidance
9/87
5
5. Adjusting the estimate to account for project timing and currency of the data used in the
estimate
6. Reviewing and confirming the cost estimate
At any time during this process users can input a previously completed estimate, an explanation of their
estimating approach, and their estimate file (spreadsheet). Each step in that process is explained and
illustrated in the following paragraphs. Prior to entering the cost estimation portion of the BCAR tool,
users will have chosen a hazard mitigation strategy and defined a mitigation project type for a specific
structure. The initial cost estimation screen will pre-populate the project and structure names and the
mitigation option will be displayed for reference. At this point users will be asked to:
verify the projects useful life in years;
verify that a detailed scope of work has been developed; and
answer whether or not a detailed cost estimate has already been developed for the project.
Depending on the answers to the above questions, users will be prompted to input a completed
estimate, explanation/justification, and upload their file or they will be directed to the estimating tool.
This process is presented in screen shot CE1 of the BCAR cost estimating storyboard shown in Appendix
C. As noted in screen shots CE2 and CE3 of the storyboard, if a completed estimate is input (rather than
built), users will be queried to ensure that the estimate includes applicable construction markups and
that it reflects current pricing. If it does not include those items, users will be led through a process of
adding them to their previously completed estimate.
Once users have selected the option of developing a detailed cost estimate, they will follow the six-step
process outlined above as they develop their project cost estimate.
-
8/4/2019 Project Cost Guidance
10/87
8
Step 1: Developing an Estimate of Pre-Construction Costs
In this section, users will be asked to develop an estimate of all pre-construction costs associated with
the mitigation project. Pre-construction costs are also called non-construction costs and may include
those non-construction costs an owner incurs in the planning, permitting, and management of a
mitigation project.
For example, pre-construction costs for an acquisition project may include the costs for propertysurveys, property appraisal fees, transaction and legal fees, the cost to purchase property and
improvements, and the cost of professional services needed for environmental or engineering
assessments and/or managing the process.
This process is presented in screen shot CE2a of the BCAR cost estimating storyboard shown in Appendix
C. As noted in the two screen shots, users can enter a lump sum amount (if a completed estimate is
available) or they can use the cost tool to develop their estimate by building on the pre-populated cells.
In all cases, flexibility is built into the cost estimating tool to allow users to input specific work elements
that are applicable to their mitigation project rather than use the default line items that were developed
for each of the 16 mitigation project types.
Within the cost estimating tool, the column format is consistent across all six steps. Each template has a
description of the work element, followed by a box to check the source of the unit pricing used (i.e.,
published data, historical data, or contractor data), the quantity and unit associated with each work
element, the unit cost of the work and a task cost, which is the product of the quantity and the unit cost.
Additional rows can be added to introduce work elements that were not included in the default format.
Step 2: Developing an Estimate of Construction Costs
In this section, users will be asked to develop an estimate of all hard construction costs associated
with the mitigation project. Hard construction costs are costs associated with the actual physical
altering of the property or structure. In the acquisition example, costs associated with site demolitionmight include the removal of hazardous materials, general demolition activities, well and septic
abandonment, utility disconnections, and utility removals.
This process is presented in screen shot CE2b of the BCAR cost estimating storyboard shown in Appendix
C. As noted in the two screen shots, users can enter a lump sum amount (if a completed estimate is
available) or they can use the cost tool to develop their estimate by building on the pre-populated cells.
In all cases, flexibility is built into the cost estimating tool to allow users to input specific work elements
that are applicable to their mitigation project rather than use the default line items that were developed
for each of the 16 mitigation project types.
Within the cost estimating tool, the column format is consistent across all six steps. Each template has a
description of the work element, followed by a box to check the source of the unit pricing used (i.e.,
published data, historical data, or contractor data), the quantity and unit associated with each work
element, the unit cost of the work and a task cost, which is the product of the quantity and the unit cost.
Additional rows can be added to introduce work elements that were not included in the default format.
-
8/4/2019 Project Cost Guidance
11/87
9
Step 3: Developing an Estimate of Ancillary Costs
Once users input a detailed construction cost estimate, they will be queried to ensure that all general
construction and ancillary costs have been accounted for. Specifically, users will be asked if their unit
prices/costs have accounted for any of the following cost elements:
A/E Costs associated with project design and construction administration
General Contractor costs for general requirements and general conditions
General Contractor costs for overhead and profit
Project management costs associated with executing the project
Permit fees, testing costs, and plan approval fees
Mobilization and Demobilization costs
Depending upon the answer to each of the above questions, users will be asked to include those costs in
their estimate. This can be accomplished in two ways. First, users can revisit their pre-construction andconstruction costs and add a line item for the ancillary costs not previously included. Alternatively, they
can use industry standard proxy values as shown below in Table 2. These specific value ranges are
referenced using RS Means construction cost data as a resource. However, other national cost data
sources have similar values.
Table 2. Recommended Proxy Values
Cost Element Proxy Value
Mobilization and Demobilization 3% of the hard
construction cost
Construction General Conditions and Requirements (i.e.,
costs associated with a general contractors field supervision
costs and job site costs, such as temporary services and
utilities, safety and security measures, quality control, and
administrative submittals)
10% of the hard
construction cost
General Contractor Overhead Costs, Insurance Costs and
Payment/Performance Bond Costs, and Profit
10-20% of the hard
construction cost
Architectural and Engineering Services to cover the cost of
basic design and inspection services normally associated with
a construction project, such as preliminary engineering
analysis, preliminary design, final design, and construction
inspection.
10% of the hard
construction cost
Project Management costs to cover the applicant costs to
manage the project during the evaluation, design, permitting,
coordination, and construction phases
4% of the hard
construction cost
-
8/4/2019 Project Cost Guidance
12/87
10
This process is presented in the BCA Tool screen shot shown in Appendix C. As noted in the screen shots,
the users can select a proxy value that will be included in the mitigation project estimate.
Step 4: Developing an Estimate of Annual Maintenance Costs
The cost of maintaining mitigation measures is often not accounted for in mitigation cost estimates. If
maintenance is required for the proper and effective implementation of the mitigation measure, it
should be included in the cost estimate. In this section, the users will be asked to develop an estimate of
the annual maintenance costs necessary for the proper and effective implementation of the mitigation
project and to identify the number of years maintenance will be required (which is typically the project
useful life). The software will then calculate the present worth of the annual maintenance costs and add
that value to the project cost. This process is presented in screen shot CE3 of the BCAR cost estimating
storyboard shown in Appendix C.
Step 5: Adjusting Your Estimate to Account for Project Timing
In this section, the users will be asked if the estimate reflects current prices. Price currency is a function
of two separate issues. First, was the estimate prepared using current pricing data and second, was the
estimate escalated to the midpoint of construction to account for anticipated inflation in labor,
materials, and equipment over the term of the construction project.
With regard to the current pricing question, historical data must be escalated to todays values and
published data may vary based on the date of the published source. With regard to the issue of inflation
over the course of a project, the issue is the length of time between when the estimate was developed
and the start/completion of construction. Estimates are typically escalated to the midpoint of
construction to account for the inflation that will occur over the project lifecycle (design, bidding, and
construction).
As noted in screen CE3 of the storyboard (Appendix C), users will be asked if their estimate reflects
current prices and if not, they will be asked to input information on the type of construction project, the
cost basis year, the construction start year and the construction end year. The software will calculate
the escalation according to the methodology described in the following paragraphs.
The escalation is based on a computed 5-year annual building construction escalation rate for each
FEMA Region based on Engineering News RecordBuilding Cost Index for cities within each region. The
5-year average annual escalation used in this step is based on index values from December 2002 to
December 2007. The recommended escalation factors are provided in the following table.
-
8/4/2019 Project Cost Guidance
13/87
11
FEMA Region(s)2002 - 2007 Average Annual
Escalation Rate
1 6.4%
2 3.9%
3 5.0%4 and 10 4.3%
5 4.4%
6 and 9 4.9%7 5.4%
8 5.2%
We recommend that the escalation factors be used to escalate cost data from the date of its source to
the anticipated mid-point of construction of the proposed project. Escalation can be calculated using the
formula:
EC = PC*(1+E)N
Where EC = Escalated cost
PC = Present cost
E = Escalation rate
N = Estimated number of years from data date of date source to midpoint of
construction
Project schedules must indicate reasonable periods for project design, bid and contract award and
construction. Cost data should be escalated to the estimated mid-point of construction. The mid-point
of construction is calculated as the time for design, bid and contract award plus one-half the
construction period. Based on the precision of the data, including proposed project schedules, we
recommend that times to mid-point of construction be rounded upward to the next full year for
escalation purposes
Project schedules should be developed by experienced project and construction professionals. However,
a general guide to estimating project timelines as a function of project construction cost is provided on
the following table.
15,000$ 2 Months35,000$ 4 Months
125,000$ 2 Months
200,000$ 3 Months
350,000$ 4 Months500,000$ 6 Months
$500,000 to $1 Million$1 to $5 million
$5 million
Construction Estimate
Fee < $50,000Fee > $50,000
Ramp-up and close-
out timeDesign
Design & Construction Monthly ExpenditureRate Assumptions
-
8/4/2019 Project Cost Guidance
14/87
12
Example 1: A proposed drainage mitigation project located in FEMA Region 3 is identical to a project
completed by the applicant in 2005. The proposed project is scheduled for completion by the end of
2010. The project cost in 2005 was $300,000 plus $30,000 design and construction inspection fees.
Estimated Schedule:
Design fee approx. $30,000
Design time = ($30,000/$15,000 per month) + 2 months = 4 months
Construction cost = $300,000
Construction time = ($300,000/125,000) + 2 months = 4.4 months
Time to mid-point of construction = 4 months design + (4.4 months construction/2) = 6.2months. Round up to 1 year from start of design.
Escalated Project Cost
Estimated project start data January 2009
Escalation period = (Estimated start date + Time to midpoint of construction) Datasource year
(2009 + 1) 2005 = 5 years
EC = ($330,000)*(1+0.05) 5
EC = $421,173
Example 2: The $1,750,000 construction cost estimate for a proposed relocation in FEMA Region 6 is
based on 2008 published construction cost data. The estimated design and construction inspection fee is
$175,000. The project is expected to be completed in 2011.
Estimated Schedule
Design fee $175,000
Design time = ($175,000/$35,000 per month) + 4 months = 9 months
Construction cost = $1,750,000
Construction time = ($1,750,000/$350,000 per month) + 4 months = 9 months
Time to midpoint of construction = 9 months design + (9 months construction/2) = 13.5months. Use 2 years from start of design.
Escalated Project Cost
Estimated project start January 2009
Escalation period = (Estimated start date + Time to midpoint of construction) Datasource year
(2009 + 2) 2008 = 3 years
EC = (1,925,000)*(1+0.049)3
EC = $2,222,067
Step 6: Review and Confirmation of the Estimate
Finally, users will be required to certify that their cost estimate is complete and includes all costs
associated with the mitigation project scope of work. Queries should require the users to be instructed
to:
Compare each item in the cost estimate with the scope of work to make certain that all work
necessary to complete the project has been included
-
8/4/2019 Project Cost Guidance
15/87
13
Review the unit and quantity of each item to confirm accuracy of the total costs
Assure that items that have been presented as lump sums are appropriate and cannot be readily
broken into units, and
Accept the following certification language by checking a box and entering the preparers name:
Information provided in this section has been reviewed and found to be complete.
The information represents a full and complete description of the components of the
project scope of work and associated costs.
-
8/4/2019 Project Cost Guidance
16/87
14
Section 2 Provide Specific Guidance
The flow charts provided in Appendix A lead the estimator through specific steps in developing a cost
estimate that is consistent with the scope of work, transparent, and contains only the appropriate lump
sum items. To assist the estimator in developing a complete and comprehensive cost estimate, the
following specific guidance will be provided within the cost portion of the BCAR effort.
Estimating process flow charts: Appendix A provides 16 cost estimation process flow charts that
detail the general steps required in developing reliable estimates, and offer specific suggestions for
each hazard and mitigation combination identified in Table 1. These estimating process flow charts
are designed to be referenced in Step 1 of the cost estimating process, and provide users with a
road map for developing a valid cost estimate.
See Figures 1-16 in Appendix A.
Sample estimate template: A sample cost estimate will be prepared for each of the 16 hazard
mitigation project types covered in Table 1. These estimates are designed to be referenced duringeach step of the cost estimating process, providing the users with a typical approach to developing a
valid cost estimate. It is important to note that these estimates are only samples, and each
mitigation project may have different descriptions of the items of work, different quantities,
different units, and different unit costs based on each projects specific scope of work.
Estimating helpful hints: Dynamic help features will be available to guide the users through the
software and define terms and processes associated with each step in the process. Examples of
these helpful hints are shown in the layout of the main cost estimation screen shown in Appendix A.
-
8/4/2019 Project Cost Guidance
17/87
15
Section 3 Benefit-Cost Analysis Handout Tool
The Benefit Cost Analysis (BCA) Handout is designed for reference by Applicants and subapplicants prior
to their use of the BCA tool. This Handout will provide guidance to assist in the preparation of an
effective scope of work and will assist the preparer in the identification and collection of the cost
information needed to use the BCA module. This handout will consist of the following elements and willbe developed once the software is beta tested:
1. Overview of the BCA Tool
2. Scope Builder checklists for each of the 16 mitigation project types covered in the estimating
module. These checklists will provide an itemized breakdown of the primary work tasks and
subtasks and are provided in Appendix D. (To be finalized after the tool structure is completed.)
3. Estimating Flow Charts for each of the 16 mitigation project types as provided in Appendix A
4. Sample Cost Estimates for each of the 16 mitigation project types as provided in Appendix B
-
8/4/2019 Project Cost Guidance
18/87
16
Conclusions: Reasons for Selection of Proposed Methodology
In conclusion, the URS BCA team recommends the proposed methodology because it provides a simple,
straightforward approach to supplying comprehensive cost estimate guidance for a wide range of
hazard mitigation projects. The proposed methodology does not require recreating, linking, or updating
any existing cost estimating tools or products. Instead, users will be referred to those tools/productswhere applicable, and would be expected to learn tools or purchase products to address shortcomings
in their project cost estimates, as illustrated in the flow charts. This will simplify programming, reduce
development costs, and avoid licensing issues with firms that have proprietary estimating products.
Specifically, the proposed methodology addresses the five project cost estimate issues identified earlier
as follows:
Provides guidance on what hard construction and ancillary costs should be included for a variety of
mitigation project types
Does not include contingencies or allowances for change orders
Reinforces to the users that historical cost data is as useful as standard cost estimating references
Provides guidance on an appropriate level of detail to be included in a mitigation project cost
estimate
Provides helpful hints, reference values, and sample cost estimates to guide the user through the
cost estimating process
-
8/4/2019 Project Cost Guidance
19/87
17
APPENDIX A: Mitigation Strategy Flow Charts
-
8/4/2019 Project Cost Guidance
20/87
18
Flood
Flood-Proofing
Step 1Preconstruction Cost
Non-construction costs for planning,permitting, and managing mitigation projects
Typical Preconstruction Activities (listedbelow)
o Site Topographic Surveyo Feasibility Studieso Materials Evaluations
Ancillary Cos
Mobil
Const
condit Gene
A/E s
docum
Estima
Adjus
Rev
A-1 Cost Estimate
Step 2Construction Costs (Develop hard costs to
execute the project)
Identify All Work Elementso Flood Proofing
Wet Flood Proofing Dry Flood Proofing
Identify Cost Data Sourceso Published vs. Historicalo Current Bids
Develop Cost Estimateo Itemize cost elements using
appropriate units of measurement
o Limit lump sums to less than 20% of
Task line items
-
8/4/2019 Project Cost Guidance
21/87
Flood
Relocation
Step 1Preconstruction Cost
Non-construction costs for planning, design,permitting, and managing mitigation projects
Typical Preconstruction Activities (listedbelow)
o New Site Phase I EnvironmentalSite Assessment
o Site Purchas New Locationso Property Surveyo Transaction Closing Fees
Step 2
Construction Costs (Develop hard costs toexecute the project)
Identify All Work Elementso Site Acquisitiono Transport Facilityo Foundation Constructiono Site Improvements and
Infrastructureo Old Site Restoration
Identify Cost Data Sourceso Published vs. Historicalo Current Bids
Develop Cost Estimateo Itemize cost elements using
appropriate units of measurement
o Limit lump sums to less than 20% of
Task line items
Ancillary Co
Mobi
Cons
cond
Gene
A/E sdocu
Estima
Adjus
Re
A-2 Cost Esti
R
-
8/4/2019 Project Cost Guidance
22/87
Flood
Drainage
Step 1Preconstruction Cost
Non-construction costs for planning, design,permitting, and managing mitigation projects
Typical Preconstruction Activities (listed below)o Hydrology Studieso Environmental Assessmento Compliance Studies
Step 2Construction Costs (Develop hard costs to
execute the project)
Identify All Work Elementso Site Acquisitiono Demolitiono Site Restorationo Site Maintenanceo Professional Fees
Identify Cost Data Sourceso Published vs. Historicalo Current Bids
Develop Cost Estimateo Itemize cost elements using appropriate
units of measurement
o Limit lump sums to less than 20% of
Task line items
Ancillary Cos
Mobiliz
Constr
conditi
Gener
A/E se
docum
Estimat
Adjust
Re
A-3 Cost Estimate
-
8/4/2019 Project Cost Guidance
23/87
Flood
Elevation
Step 1Preconstruction Cost
Non-construction costs for planning, design,permitting, and managing mitigation projects
Typical Preconstruction Activities (listedbelow)
o Site Topographic surveyo Existing Floor Elevation Certification
Survey
Step 2Construction Costs (Develop hard costs to
execute the project)
Identify All Work Elements
o Elevate Facilityo Foundation Constructiono Utilities Adjustmentso Building Accesso Site Restorationo Professional Feeso Demolition of Existing Facilityo Construction of New Facilityo Site Restorationo Professional Fees
Identify Cost Data Sourceso Published vs. Historicalo
Current Bids
Develop Cost Estimateo Itemize cost elements using
appropriate units of measurement
o Limit lump sums to less than 20% of
Task line items
Ancillary Costs (AIn
Mobilizatio
Constructi
conditions
General C A/E servic
document
Estimate A
Adjust Est&
Review
A-4 Cost Esti
-
8/4/2019 Project Cost Guidance
24/87
Flood
Acquisition
Step 1Preconstruction Cost
Non-construction costs for planning, design,permitting, and managing mitigation projects
Typical Preconstruction Activities (listedbelow)
o Property Surveyso Appraisal Feeso Property Purchaseo Transaction Closin Fees
Step 2Construction Costs (Develop hard costs to
execute the project)
Identify All Work Elementso Site Acquisitiono Demolitiono Site Restorationo Site Maintenanceo Professional Fees
Identify Cost Data Sourceso Published vs. Historicalo Current Bids
Develop Cost Estimateo Itemize cost elements using
appropriate units of measurement
o Limit lump sums to less than 20% of
Task line items
Ancillary Cos
Mobiliz
Constrconditi
Gener
A/E se
docum
Es
Ad
A-5 Cost Esti
A
-
8/4/2019 Project Cost Guidance
25/87
-
8/4/2019 Project Cost Guidance
26/87
Earthquake
Strengthen Structural Elements
Step 1Preconstruction Cost
Non-construction costs for lannin , desi n,
Step 2Construction Costs (Develop hard costs to
execute the project)
Identify All Work Elementso Work Area Preparationo Reinforce Facilityo Strengthen Structural Memberso Professional Fees
Identify Cost Data Sourceso Published vs. Historicalo Current Bids
Develop Cost Estimateo Itemize cost elements using
appropriate units of measurement
o Limit lump sums to less than 20% of
Task line items
Ancillary Co
Mob
Cons
cond
Gene
A/E s
docu
Esti
Adj
R
A-7 Cost Estimate Process Earthquake-
Strengthen Structural Elements
-
8/4/2019 Project Cost Guidance
27/87
Wildfire
Vegetative Control
Step 1Preconstruction Cost
Non-construction costs for planning, design,permitting, and managing mitigation projects
Typical Preconstruction Activities (listedbelow)
o Erosion/Environmental Studyo Property Survey
Step 2Construction Costs (Develop hard costs to
execute the project)
Identify All Work Elementso Vegetative Control (Fuel Reduction)o Fire Breakso Professional Fees
Identify Cost Data Sourceso Published vs. Historicalo Current Bids
Develop Cost Estimateo Itemize cost elements using
appropriate units of measurement
o Limit lump sums to less than 20% of
Task line items
Ancillary Cos
Mobiliz
Constr
conditi
Gener
A/E se
docum
Estima
Adjus
Re
A-8 Cost Estimate Pr
Vegetative
-
8/4/2019 Project Cost Guidance
28/87
Wildfire
Fire Resistant Exterior
Step 1Preconstruction Cost
Non-construction costs for planning, design,permitting, and managing mitigation projects
Typical Preconstruction Activities (listedbelow)
o Appraisers Feeso Property Survey
Step 2Construction Costs (Develop hard costs to
execute the project)
Identify All Work Elementso Roofingo Walls
Identify Cost Data Sourceso Published vs. Historicalo Current Bids
Develop Cost Estimateo Itemize cost elements using
appropriate units of measurement
o Limit lump sums to less than 20% of
Task line items
Ancillary Cos
Mobiliz
Constr
conditi
Gener
A/E se
docum
Estima
Adjus
Re
A-9 Cost Estimate Process Wildf
Resistant Exterior
-
8/4/2019 Project Cost Guidance
29/87
-
8/4/2019 Project Cost Guidance
30/87
Wind
Strengthen Load Path Elements/Shutters
Step 1Preconstruction Cost
Non-construction costs for planning, design,permitting, and managing mitigation projects
Typical Preconstruction Activities (listedbelow)
o Feasibility Studyo Structural Assessment Of Existing
Structural Systemo Feasibility Analysis Of Alternatives
Step 2
Construction Costs (Develop hard costs toexecute the project)
Identify All Work Elementso Temporary Relocation Costso Strengthen Structural Memberso Strengthen Load Path Connectionso Strengthen Building Openingso Impact Resistant Glazingo Install Shutterso Reengineer Ancillary Equipment
Connectionso Selective Demolitiono Professional Fees
Identify Cost Data Sourceso Published vs. Historicalo Current Bidso
Develop Cost Estimateo Itemize cost elements using
appropriate units of measurement
o Limit lump sums to less than 20% of
Task line items
Ancillary Cos
Mobiliz
Constr
conditi
Gener
A/E se
docum
Estimat
Adjust
Rev
A-11 Cost Estimate Pro
Strengthen Load Path Ele
-
8/4/2019 Project Cost Guidance
31/87
Wind
Tornado Shelter
Step 1
Preconstruction Cost Non-construction costs for planning, design,
permitting, and managing mitigation projects Typical Preconstruction Activities (listed
below)o Site Acquisitiono Inspection Feeso Property Survey
Step 2Construction Costs (Develop hard costs to
execute the project) Identify All Work Elements
o Strengthen Designated ShelterAreas
o Provide Emergency Accesso Retrofit Services For Emergency
Useo Site Acquisitiono New Constructiono Site Improvementso Professional Fees
Identify Cost Data Sources
o Published vs. Historicalo Current Bidso
Develop Cost Estimateo Itemize cost elements using
appropriate units of measurement
o Limit lump sums to less than 20% of
Task line items
Ancillary Cos
Mobiliz
Constr
conditi
Gener
A/E se
docum
Estimat
Adjust
Rev
A-12 Cost Estimate P
Sh
-
8/4/2019 Project Cost Guidance
32/87
Landslide
Slope Drainage Improvements
Step 1Preconstruction Cost
Non-construction costs for planning, design,permitting, and managing mitigation projects
Typical Preconstruction Activities (listedbelow)
o Site Surveyo Geotechnical Boringso Environmental Assessment and
Compliance Studies
Step 2Construction Costs (Develop hard costs to
execute the project) Identify All Work Elements
o Gradingo Install Channel Liningo Outlet Structureso Dimensionso Professional Feeso Excavationo Drain Installationo Ancillary Structureso Dimensionso Professional Services
Identify Cost Data Sourceso Published vs. Historicalo Current Bidso
Develop Cost Estimateo Itemize cost elements using
appropriate units of measurement
o Limit lump sums to less than 20% of
Task line items
Ancillary Costs
Mobiliza
Constru
conditio
Genera
A/E ser
docume
Estimate A
Adjust Es
Review
A-13 Cost Estimate Process Landsl
Slope Drainage Improvements
-
8/4/2019 Project Cost Guidance
33/87
Landslide
Bio-Engineered Slope Stabilization
Step 1Preconstruction Cost
Non-construction costs for planning, design,permitting, and managing mitigation projects
Typical Preconstruction Activities (listedbelow)
o Environmental Assessment andCompliance Reviews
o Agricultural Assessmento Geotechnical Studieso Typographic Surveys
Step 2Construction Costs (Develop hard costs to
execute the project)
Identify All Work Elementso Site Gradingo Bio-Engineered Slope Protectiono Dimensionso Professional Fees
Identify Cost Data Sourceso Published vs. Historicalo Current Bids
Develop Cost Estimateo Itemize cost elements using
appropriate units of measurement
o Limit lump sums to less than 20% of
Task line items
Ancillary Cos
Mobiliz
Constr
conditi
Gener
A/E se
docum
Estimat
Adjust E
Revie
A-14 Cost Estimate Process Landslide-
Bio-Engineered Slope Stabilization
-
8/4/2019 Project Cost Guidance
34/87
Landslide
Toe Armoring
Step 1Preconstruction Cost
Non-construction costs for planning, design,permitting, and managing mitigation projects
Typical Preconstruction Activities (listedbelow)
o Hydrology/Hydraulic Studieso Environmental Assessment and
Compliances Studieso Geotechnical Studies
Step 2Construction Costs (Develop hard costs to
execute the project)
Identify All Work Elementso Surface Water (if required)o Armoring Approacho Site Gradingo Professional Fees
Identify Cost Data Sourceso Published vs. Historicalo Current Bids
Develop Cost Estimateo Itemize cost elements using
appropriate units of measurement
o Limit lump sums to less than 20% of
Task line items
Ancillary Costs (Ad
In T Mobilization
Construction
conditions/re
General Con
A/E services
documents
Estimate Annu
Adjust Estima
& Da
Review an
A-15 Cost Estimate Proc
Armor
-
8/4/2019 Project Cost Guidance
35/87
-
8/4/2019 Project Cost Guidance
36/87
34
APPENDIX B: Sample Estimates
-
8/4/2019 Project Cost Guidance
37/87
35
BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant City of Lowland, GAProject Title Lowland Civic Center FloodproofingPreparer:
HAZARD: FloodMITIGATION STRATEGY Floodproofing
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
$
$
$
$
1Pre-Construction
(Specify)
Pre-construction subtotal $
Excavating, trench or continuous footing, commonearth, 3/8 C.Y. excavator, 1' to 4' deep, excludessheeting or dewatering
260.00 B.C.Y. $7.55 $1,963
Excavating, trench or continuous footing, commonearth, trim sides and bottom for concrete pours,
excludes sheeting or dewatering
5,700.00 S.F. $0.81 $4,617
Structural concrete, in place, continuous stripfooting, 36" wide x 12" deep, includes forms(4uses), reinforcing steel, and finishing
130.00 C.Y. $255.00 $33,150
Curing, burlap, 12 oz., 4 uses assumed 23.00 C.S.F. $28.50 $656
Structural concrete, in place, grade wall, 12" thickx 8' high, includes forms(4 uses), reinforcing steel,and finishing
65.00 C.Y. $375.00 $24,375
Backfill, light soil, by hand, no compaction 65.00 L.C.Y. $27.00 $1,755
Backfill, 6" layers, compaction in layers, handtamp
65.00 E.C.Y. $18.50 $1,203
Anchor bolt, J-type, plain steel, 1/2" dia x 18" L,incl nut & washer
300.00 Ea. $18.15 $5,445
Column base plates, structural, heavy, 100-tonproject, over 150 lb each, A992 steel, shopfabricated, incl shop primer
900.00 Lb. $2.07 $1,863
Precast wall panel, exposed aggregate,uninsulated, low rise, 8' x 8' x 4" thick, 3000 psi
5,700.00 S.F. $33.00 $188,100
Precast column, small, rectangular to 12' high.,3000 psi, includes material only
600.00 L.F. $113.00 $67,800
Waterstop, fittings, rubber, flat, dumbbell or centerbulb, flat cross, 3/8" thick x 9" wide
60.00 Ea. $68.50 $4,110
Caulking & Sealants, backer rod, polyethylene,1/4" dia
1,200.00 L.F. $1.12 $1,344
Caulking & Sealants, acrylic latex caulk, white,1/2" x 1/2", in place
1,200.00 L.F. $2.40 $2,880
Self-raising flood gate @ pedestrian entrance 1.00 Ea. $13,250.00 $13,250
Self-raising flood gate @ vehicle entrance 1 Ea. $41,700.00 $41,700
$-
2Construction
(Specify Phases)
Construction Subtotal $394,210
-
8/4/2019 Project Cost Guidance
38/87
36
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
Insurance and Bonds 1 LS 3.5% $13,797
Site supervision and contract requirements 1 LS 10% $40,801
G.C. overhead & profit 1 LS 28% $125,666
Permits and Review Fees 1 LS 0.5% $2,872
Construction -General
General Construction Phase Subtotal $183,137
Preparation of construction documents 1 LS 10% $57,735
Applicant Cost to Manage Design 1 LS 2% $11,547
Applicant Cost to Manage Construction 1 LS 4% $23,094
3
Applicant Costs
Applicant Cost Subtotal $92,375
Maintenance $-
$-
$-4 Maintenance
Annual Maintenance Subtotal $-
5 Escalation Escalation (to mid-point of construction) 12 Months 0.42% $28,890
Pre-construction subtotal $-
Construction subtotal $394,210
General Construction Phase Subtotal $183,137
Applicant Cost Subtotal $92,375
Annual Maintenance Subtotal $-
6Estimate Review& Confirmation
Escalation Subtotal $28,890
PROJECT TOTAL $698,613
-
8/4/2019 Project Cost Guidance
39/87
37
BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Riverside Township, PAProject Title Township Office Building RelocationPreparer: H. Waters
HAZARD: Flood
MITIGATION STRATEGY RelocationEstimating
StepProject Phase Description Quantity Unit Unit Cost Task Cost
Pre-purchase Phase I Environmental SiteAssessment
1 Ea. $2,500.00 $2,500
Site purchase - new location 3 Acres $25,000 $75,000
Property boundary survey 1500 LF $2 $2,370
Legal Fees 1 LS $1,500 $1,500
1Pre-Construction
(Specify)
Pre-construction subtotal $81,370
Building demolition, small buildings or singlebuildings, masonry, elevated slabs, includes 20 milehaul, excludes salvage, foundation demolition ordump fees
100,000 C.F. $0.29 $29,000
Rubbish handling, loading & trucking, chute loaded,including 2 mile haul, cost to be added to demolitioncost.
1,300 C.Y. $45.50 $59,150
Dump charges, typical urban city, buildingconstruction materials, includes tipping fees only
1,400 Ton $90.00 $126,000
Seeding, wildflower, 0.10 lb. per M.S.F., tractorspreader
40 M.S.F. $17.35 $694
A Substructure $-
Standard Foundations 8,000 SF $2.40 $19,200
Slab on Grade 8,000 SF $4.45 $35,600
Basement Excavation 8,000 SF $0.24 $1,920
Basement Walls 8,000 SF $3.33 $26,640
B Shell $-
Roof Construction 8,000 SF $6.25 $50,000
Exterior Walls 8,000 SF $8.56 $68,480
Exterior Windows 8,000 SF $4.76 $38,080
Exterior Doors 8,000 SF $0.81 $6,480
Roof Coverings 8,000 SF $2.88 $23,040C Interiors 8,000 SF $-
Partitions 8,000 SF $4.05 $32,400
Interior Doors 8,000 SF $2.60 $20,800
Fittings 8,000 SF $0.48 $3,840
Wall Finishes 8,000 SF $1.26 $10,080
Floor Finishes 8,000 SF $7.00 $56,000
Ceiling Finishes 8,000 SF $4.71 $37,680
2Construction
(Specify Phases)
D Services $-
Plumbing Fixtures 8,000 SF $5.26 $42,080
Domestic Water Distribution 8,000 SF $1.40 $11,200
Rain Water Drainage 8,000 SF $0.89 $7,120
Terminal & Package Units 8,000 SF $7.94 $63,520
Sprinklers8,000 SF
$2.40$19,200
Electrical Service/Distribution 8,000 SF $2.33 $18,640
Lighting and Branch Wiring 8,000 SF $9.00 $72,000
Communications and Security 8,000 SF $2.40 $19,200
Other Electrical Systems 8,000 SF $0.13 $1,040
E Equipment & Furnishings $-
Other Equipment 8,000 SF $2.08 $16,640
Parking lot, 60 degree angle parking, 3" bituminouspaving, 6" gravel base 50 Car $965.01 $48,251
2 Construction(SpecifyPhases)
Concrete sidewalk, 4" thick, 4" gravel base, 5' wide 150 L.F. $24.71 $3,706
-
8/4/2019 Project Cost Guidance
40/87
38
$-
Construction Subtotal $967,680
-
8/4/2019 Project Cost Guidance
41/87
39
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
Insurance and Bonds 1 LS 3.5% $33,869
Site supervision and contract requirements 1 LS 10% $100,155
G.C. overhead & profit 1 LS 28% $308,477
Permits and Review Fees 1 LS 0.5% $7,458
Construction -General
General Construction Phase Subtotal $449,959
Preparation of construction documents 1 LS 10% $141,764
Applicant Cost to Manage Design 1 LS 2% $28,353
Applicant Cost to Manage Construction 1 LS 4% $56,706
3
Applicant Costs
Applicant Cost Subtotal $226,822
Maintenance $-
$-
$-4 Maintenance
Annual Maintenance Subtotal $-
5 Escalation Escalation (to mid-point of construction) 19 Months 0.42% $112,320
Pre-construction subtotal $81,370
Construction subtotal $967,680
General Construction Phase Subtotal $449,959
Applicant Cost Subtotal $226,822
Annual Maintenance Subtotal $-
6Estimate Review &
Confirmation
Escalation Subtotal $112,320
PROJECT TOTAL $1,838,151
-
8/4/2019 Project Cost Guidance
42/87
40
BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Palisades County, New Jersey Dept. of RoadsProject Title Hill Bench Road StabilizationPreparer: N. Wetfoot
HAZARD: LandslideMITIGATION STRATEGY Drainage Improvements
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
Site survey 1 LS $5,000.00 $5,000
Geotechnical Borings 1 LS $27,500.00 $27,500
$
$
1Pre-Construction
(Specify)
Pre-construction subtotal $32,500
Minor site demolition, patio/carport, bituminous, to6" thick, with hand held air equipment, excludeshauling
1,000 S.F. $1.29 $1,290
Demo guard rail, corrugated steel 600 L.F. $2.38 $1,428
Demo guard rail, wood posts 75 Ea. $5.95 $446
Rubbish handling, loading & trucking, machineloading truck, includes 2 mile haul, cost to beadded to demolition cost.
20 C.Y. $18.30 $366
Rubbish handling, up to 8 C.Y. truck, loading &trucking, haul, per mile, includes 2 mile haul, costto be added to demolition cost.
100 C.Y. $0.81 $81
Dump charges, typical urban city, reclamationstation, usual charge, includes tipping fees only 30 Ton $104.50 $3,135
Excavating, trench or continuous footing, commonearth, 1/2 C.Y. excavator, 1' to 4' deep, excludessheeting or dewatering
80 B.C.Y. $5.65 $452
Excavating, trench or continuous footing, commonearth, 1/2 C.Y. excavator, 4' to 6' deep, excludessheeting or dewatering
50 B.C.Y. $5.65 $283
Drainage geotextiles, fabric, laid in trench,polypropylene, ideal conditions 450 S.Y. $1.90 $855
Bedding, for pipe and conduit, crushed orscreened bank run gravel, excludes compaction 500 L.C.Y. $36.00 $18,000
Corrugated plastic tubing, perforated or plain, inrolls, 8" diameter, excludes excavation and backfill 500 L.F. $10.30 $5,150
Piping, HDPE, butt fusion joints, 40' lengths, 24"diameter, SDR 21 50 L.F. $116.00 $5,800
Excavating, trench backfill, 1 C.Y. bucket, minimalhaul, front end loader, wheel mounted, excludesdewatering
30 L.C.Y. $2.17 $65
2Construction
(Specify Phases)
Asphaltic concrete pavement, for highways andlarge paved areas, pavement replacement overtrench, 6" thick, for paving projects 300 tons orless add for trucking
125 S.Y. $61.99 $7,748
-
8/4/2019 Project Cost Guidance
43/87
41
EstimatingStep Project Phase Description Quantity Unit Unit Cost Task Cost
Manholes, concrete, precast, 4' I.D., 6' deep,excludes base, excavation, backfill, frame andcover
2 Ea. $1,799.87 $3,600
Manhole steps, heavyweight cast iron, 8" x 9" 4 Ea. $38.00 $152
Catch basins, frames and covers, cast iron, heavytraffic, 24" diameter, 400 lb., excludes footing,excavation, and backfill
2 Ea. $469.97 $940
Fine grade, slopes, steep, gentle, finish grading 200 S.Y. $0.20 $40
Soil stabilization, geotextile fabric, woven, heavyduty, 600 lb. tensile strength
200 S.Y. $2.34 $468
Rip-rap, random, broken stone, 18" minimumthickness, machine placed for slope protection, notgrouted
200 S.Y. $84.00 $16,799
Guide/Guard rail, corrugated steel, galvanized steelposts, install wrap around end section 2 Ea. $165.00 $330
Guide/Guard rail, corrugated steel, galvanized steelposts, install metal guide/guard rail, double face,steel posts 6' - 3" O.C., W6x8 posts
600 L.F. $32.50 $19,500
2Construction(Specify
Phases)
Construction Subtotal $86,928
Insurance and Bonds 1 LS 3.5% $3,042Site supervision and contract requirements 1 LS 10% $8,997
G.C. overhead & profit 1 LS 28% $27,711
Permits and Review Fees 1 LS 0.5% $796
Construction -General
General Construction Phase Subtotal $40,546
Preparation of construction documents 1 LS 10% $12,747
Applicant Cost to Manage Design 1 LS 2% $2,549
Applicant Cost to Manage Construction 1 4% $5,099
3
Applicant Costs
Applicant Cost Subtotal $20,396
Maintenance $
$
$4 Maintenance
Annual Maintenance Subtotal $
5 Escalation Escalation (to mid-point of construction) 9 Months 0.33% $3,729
Pre-construction subtotal $32,500
Construction subtotal $86,928
General Construction Phase Subtotal $40,546
Applicant Cost Subtotal $20,396
Annual Maintenance Subtotal $
6Estimate Review &
Confirmation
Escalation Maintenance Subtotal $3,729
PROJECT TOTAL $184,100
-
8/4/2019 Project Cost Guidance
44/87
42
BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Lowland, MSProject Title Elevate Town Hall BuildingPreparer: P. Riser
HAZARD: FloodMITIGATION STRATEGY Elevation
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
$
$
$
$
1Pre-Construction
(Specify)
Pre-construction subtotal $
Selective demolition- wood frame, includesloading and 5 mile haul to dump
2,500.00 C.Y. $17.75 $44,375
Demolition, concrete slab on grade, reinforced, 5,400.00 S.F. $5.95 $32,130
Footings and foundations demolition, removeconcrete footing, 2' thick, 3' wide
510.00 L.F. $22.00 $11,220
Selective demolition, timber piles, up to 14",diameter
900.00 V.L.F. $9.30 $8,370
Dump charges, typical urban city, buildingconstruction materials, includes tipping fees only
150.00 Ton $90.00 $13,500
Bulk Asbestos Removal, remove VAT from floorby hand, incl. disp. and tools
4,800.00 S.F. $1.83 $8,784
Waste Packaging, Handling & Disposal,containerize bagged material in drums, per 3 CFdrum
25.00 Ea. $12.40 $310
Waste Packaging, Handling & Disposal, collectand bag bulk material, by hand, 3 CF
25.00 Ea. $11.85 $296
Asbestos contaminated waste Packaging,Handling & Disposal, disposal charges,
5.00 C.Y. $175.00 $875
Decontamination Containment Area Demolition &Cleanup, fine clean exposed substrate, wet wipesubstrate
4,800.00 S.F. $0.88 $4,224
Excavating, grade beams 100.00 B.C.Y. $6.65 $665
Piles, concrete, precast, prestressed; 10" square, 1,900.00 V.L.F. $19.55 $37,145
Piles, mobilization, 1 1,900.00 V.L.F. $1.68 $3,192
Structural concrete, in place, grade beams 100.00 C.Y. $249.00 $24,900
Structural concrete, in place, handicap accessramp, railing both sides, 5' wide, 120.00 L.F. $650.00 $78,000
Cast-in-place concrete beam and slab, 75 PSFsuperimposed load 5,400.00 S.F. $17.95 $96,930
Wood roof, truss, 4/12 slope, 24" O.C., 44' to 60'span
5,400.00 S.F. $6.26 $33,794
Wood siding, 2"x6" studs 24"OC, insulated wall,1" x 4" vertical T&G redwood 3,024.00 S.F. $11.30 $34,165
2Construction
(Specify Phases)
Windows, aluminum, projecting, insulated glass,4'-5" x 5'-3" 57.00 Ea. $622.95 $35,508
-
8/4/2019 Project Cost Guidance
45/87
43
EstimatingStep Project Phase Description Quantity Unit Unit Cost Task Cost
Door, aluminum & glass, with transom, narrowstile, double door, hardware, 6'-0" x 10'-0"opening
1.00 Opng. $2,221.21 $2,221
Door, steel 18 gauge, hollow metal, 1 door with
frame, no label, 3'-0" x 7'-0" opening 2.00 Opng. $1,073.67 $2,147
Asphalt roofing, strip shingles, premiumlaminated, multi-layered, Class A, 4" slope, 260-300 lbs/SQ
5,700.00 S.F. $2.14 $12,181
Flashing, aluminum, no backing sides, .019" 360.00 S.F. $3.88 $1,397
Gravel stop, aluminum, extruded, 4", mill finish,.050" thick 360.00 L.F. $8.85 $3,186
Wood partition, 5/8" fire rated gypsum boardface, 5/8" fire rated gypsum board base, 2x4 @16", 5/8" fire rated gypsum board opposite face,no insulation
2,700.00 S.F. $4.99 $13,469
1/2" fire rated gypsum board, taped & fi nished,painted on metal furring 3,024.00 S.F. $3.85 $11,644
Door, single leaf, wood frame, 3'-0" x 7'-0" x 1-3/8", birch, solid core 27.00 Opng. $521.02 $14,067
Toilet partitions, cubicles, ceiling hung, plasticlaminate 6.00 Unit $874.28 $5,246
Painting, interior on plaster and drywall, walls &ceilings, roller work, primer & 2 coats 4,860.00 S.F. $0.71 $3,450
Ceramic tile, thin set, 4-1/4" x 4-1/4" 540.00 S.F. $6.26 $3,381
Carpet tile, nylon, fusion bonded, 18" x 18" or24" x 24", 35 oz 3,780.00 S.F. $4.47 $16,899
Terrazzo, maximum 810.00 S.F. $22.79 $18,462
Vinyl, composition tile, maximum 810.00 S.F. $3.11 $2,518
Acoustic ceilings, 3/4" mineral fiber, 12" x 12"tile, concealed 2" bar & channel grid, suspendedsupport
5,400.00 S.F. $4.71 $25,433
Water closet, vitreous china, bowl only with flushvalve, wall hung 6.00 Ea. $1,465.48 $8,793
Urinal, vitreous china, wall hung 3.00 Ea. $1,055.95 $3,168
Lavatory w/trim, vanity top, PE on CI, 19" x 16"oval
6.00 Ea. $956.20 $5,737
Kitchen sink w/trim, countertop, PE on CI, 24" x21", single bowl 1.00 Ea. $1,006.87 $1,007
Service sink w/trim, PE on CI, corner floor, 28" x28", w/rim guard 3.00 Ea. $1,813.30 $5,440
Water cooler, electric, wall hung, 8.2 GPH 2.00 Ea. $1,131.71 $2,263
2Construction(Specify
Phases)
Water cooler, electric, wall hung, wheelchairtype, 7.5 GPH 1.00 Ea. $2,013.13 $2,013
-
8/4/2019 Project Cost Guidance
46/87
44
EstimatingStep Project Phase Description Quantity Unit Unit Cost Task Cost
Gas fired water heater, commercial, 100< F rise, 95MBH input, 86 GPH
2.00 Ea. $5,601.54 $11,203
Roof drain, CI, soil, single hub, 4" diam, 10' high 3.00 Ea. $1,502.62 $4,508
Roof drain, CI, soil, single hub, 4" diam, for eachadditional foot add
95.00 Ea. $27.81 $2,642
Rooftop, single zone, air conditioner, offices,
10,000 SF, 31.67 ton5,400.00 S.F. $7.94 $42,885
Wet pipe sprinkler systems, steel, light hazard, 1floor, 10,000 SF
5,400.00 S.F. $2.40 $12,960
Service installation, includes breakers, metering,20' conduit & wire, 3 phase, 4 wire, 120/208 V, 400A
1.00 Ea. $6,623.60 $6,624
Feeder installation 600 V, including RGS conduitand XHHW wire, 400 A
50.00 L.F. $94.48 $4,724
Switchgear installation, incl switchboard, panels &circuit breaker, 400 A
1.00 Ea. $7,251.83 $7,252
Receptacles incl plate, box, conduit, wi re, 16.5 per1000 SF, 2.0 watts per SF
5,292.00 S.F. $3.14 $16,619
Wall switches, 1.0 per 1000 SF 5,400.00 S.F. $0.25 $1,350
Miscellaneous power, 1.2 watts 5,400.00 S.F. $0.29 $1,566
Central air conditioning power, 6 watts 5,076.00 S.F. $0.91 $4,619
Fluorescent fixtures recess mounted in ceiling, 2watt per SF, 40 FC, 10 fixtures per 1000 SF
5,400.00 S.F. $4.52 $24,408
Communication and alarm systems, includesoutlets, boxes, conduit and wire, fire detectionsystems, 25 detectors
1.00 Ea. $3,073.06 $3,073
Generator sets, w/battery, charger, muffler andtransfer switch, gas/gasoline operated, 3 phase, 4wire, 277/480 V, 15 kW
1.00 kW $689.36 $689
Directory boards, plastic, glass covered, 36" x 48" 1.00 Ea. $1,375.27 $1,375Detection Systems, heat detector, smoke detector,ceiling type, excl. wires & conduit
8.00 Ea. $171.03 $1,368
Emergency light units, nickel cadmium batteryoperated, twin sealed beam light, 25 W, 6 V each
8.00 Ea. $769.77 $6,158
Bituminous roadway, two lanes, 3-1/2" thickpavement, 3" thick gravel base, 24' wide
100.00 L.F.$91.00
$9,100
2Construction
(Specify Phases)
Parking lot, 90 degree angle parking, 3" bituminouspaving, 6" gravel base
25.00 Car$965.00
$24,125
Bituminous sidewalk, 1" thick paving, 4" gravelbase, 5' width
200.00 L.F.$7.00
$1,400
Septic system, 2000 gal tank, 6' high precast pit,2@6'-6" diameter, 50 feet from building
1.00 Ea. $10,628.46 $10,628
$$$
2 Construction(Specify Phases)
Construction Subtotal $831,785
Insurance and Bonds 1 LS 3.5% $29,112
Site supervision and contract requirements 1 LS 10% $86,090
G.C. overhead & profit 1 LS 28% $265,156
Permits and Review Fees 1 LS 0.5% $6,061
Construction -General
General Construction Phase Subtotal $386,419
Preparation of construction documents 1 LS 10% $121,820
3
Applicant CostsApplicant Cost to Manage Design 1 LS 2% $24,364
Maintenance $
$
$4 Maintenance
Annual Maintenance Subtotal $
5 Escalation Escalation (to midpoint of construction) 14 Months 0.36% $ 61,056
Pre-construction subtotal $
Construction subtotal $831,785
General Construction Phase Subtotal $386,419
Applicant Cost Subtotal $194,913
Annual Maintenance Subtotal $
6Estimate Review& Confirmation
Escalation Subtotal $ 61,056
PROJECT TOTAL $1,474,173
-
8/4/2019 Project Cost Guidance
47/87
45
BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Shaking Heights, CA Fire DepartmentProject Title Heavy Equipment Storage StabilizationPreparer: 0
HAZARD: EarthquakeMITIGATION STRATEGY Anchor Non-structural Component
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
Remove equipment from storage shelves andremove shelves to storage
160 Hrs. $28.75 $4,600
$
$
$
1Pre-Construction
(Specify)
Pre-construction subtotal $4,600
Walls and partitions demolition, brick wall, 4" thick 280 S.F. $2.13 $596
Rubbish handling, 100' haul, load, haul to chute anddumping into chute, cost to be added to demolitioncost.
5 C.Y. $46.00 $230
Dump charges, typical urban city, buildingconstruction materials, includes tipping fees only 7 Ton $90.00 $630
Rubbish handling, up to 8 C.Y. truck, loading &
trucking, haul, per mile, includes 2 mile haul, cost tobe added to demolition cost.
50 C.Y. $0.83 $42
Channel framing, structural steel, field fabricated,C4x5.4, incl cutting & welding 160 L.F. $34.49 $5,518
Acoustical slotted concrete masonry unit (CMU),partition, 2000 psi, 4" thick, NRC .65 type A-1,includes mortar, excludes scaffolding, horizontalreinforcing, vertical reinforcing and grout
280 S.F. $10.40 $2,912
Concrete masonry unit (CMU), high strength, hollow,5000 psi, 4" x 8" x 16", includes mortar andhorizontal joint reinforcing every other course,excludes scaffolding, grout and vertical reinforcing
280 S.F. $7.35 $2,058
#3 and #4 reinforcing steel bars, placed vertically,ASTM A615 1,000 Lb. $1.90 $1,900
$
2Construction
(Specify Phases)
Construction Subtotal $13,886
Insurance and Bonds 1 LS 3.5% $486
Site supervision and contract requirements 1 LS 10% $1,437
G.C. overhead & profit 1 LS 28% $4,427
Permits and Review Fees 1 LS 0.5% $124
Construction -General
General Construction Phase Subtotal $6,474
Preparation of construction documents 1 LS 10% $2,036
Applicant Cost to Manage Design 1 LS 2% $407
Applicant Cost to Manage Construction 1 LS 4% $814
3
Applicant Costs
Applicant Cost Subtotal $3,258
Maintenance $
$
$4 Maintenance
Annual Maintenance Subtotal $
5 Escalation Escalation (to mid-point of construction) 9 Months 0.41% $748Pre-construction subtotal $4,600
Construction subtotal $13,886
General Construction Phase Subtotal $6,474
Applicant Cost Subtotal $3,258
Annual Maintenance Subtotal $
6Estimate Review& Confirmation
Escalation Subtotal $748
PROJECT TOTAL $28,966
-
8/4/2019 Project Cost Guidance
48/87
46
BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Shaking Dunes, SCProject Title Earthquake Retrofit of Public Work BuildingPreparer: J. E. Orler
HAZARD: EarthquakeMITIGATION STRATEGY Strengthen Structural Elements
Estimating Step Project Phase Description Quantity Unit Unit Cost Task Cost
$
$
$
$
1Pre-Construction
(Specify)
Pre-construction subtotal $
Office systems furniture, cubicle, selectivedemolition
14,400 S.F. $0.25 $3,600
Ceiling demolition, suspended ceiling, mineral fiber,on suspension system, remove
4,080 S.F. $0.64 $2,611
Walls and partitions demolition, drywall, nailed 5,000 S.F. $0.38 $1,900
Walls and partitions demolition, metal or woodstuds, finish two sides, plywood
300 S.F. $2.60 $780
Rubbish handling, 100' haul, load, haul to chuteand dumping into chute, cost to be added todemolition cost.
75 C.Y. $46.00 $3,450
Rubbish handling, dumpster, 30 C.Y., 10 toncapacity, weekly rental, includes one dump perweek, cost to be added to demolition cost.
1 Week $990.00 $990
Temporary floor protection, exterior plywood, 2uses, 1/2" thick
10,800 S.F. $0.91 $9,828
Steel plate, structural, for connections & stiffeners,1/2" T, shop fabricated, incl shop primer
600 S.F. $23.00 $13,800
Welding, structural steel, in field, cleaning &welding plates/bars/rods to existingbeams/columns/trusses
750 L.F. $66.00 $49,500
Gypsum wallboard, on walls, standard,w/compound skim coat (level 5 finish), 1/2" thick
5,300 S.F. $1.70 $9,010
2Construction
(Specify Phases)
Suspended Acoustic Ceiling Tiles, fiberglassboards, film faced, 2' x 2' or 2' x 4' x 5/8" thick
4,080 S.F. $1.43 $5,834
Paints & Coatings, walls & ceilings, interior,concrete, drywall or plaster, oil base, 2 coats,smooth finish, roller
10,000 S.F. $0.65 $6,500
Flooring demolition, remove temporary floorprotection
10,800 S.F. $0.81 $8,748
Systems furniture, replace secretarial work station,minimum
3 Ea. $3,075.00 $9,225
Systems furniture, replace management workstation, minimum
10 Ea. $3,500.00 $35,000
Systems furniture, replace executive work station,minimum
2 Ea. $7,800.00 $15,600
$
2Construction(Specify
Phases)
Construction Subtotal $176,377
-
8/4/2019 Project Cost Guidance
49/87
47
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
Insurance and Bonds 1 LS 3.5% $6,173
Site supervision and contract requirements 1 LS 10% $18,255
G.C. overhead & profit 1 LS 28% $56,225
Permits and Review Fees 0 LS 0.5% $
Construction -General
General Construction Phase Subtotal $80,653
Preparation of construction documents 1 LS 10% $25,703
Applicant Cost to Manage Design 1 LS 2% $5,141
Applicant Cost to Manage Construction 1 LS 4% $10,281
3
Applicant Costs
Applicant Cost Subtotal $41,125
Maintenance $
$
$4 Maintenance
Annual Maintenance Subtotal $
5 Escalation Escalation (to mid-point of construction) 10 Months 0.36% $9,202
Pre-construction subtotal $
Construction subtotal $176,377
General Construction Phase Subtotal $80,653
Applicant Cost Subtotal $41,125
Annual Maintenance Subtotal $
6Estimate Review& Confirmation
Escalation Subtotal $9,202
PROJECT TOTAL $307,357
-
8/4/2019 Project Cost Guidance
50/87
48
BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Weeville, COProject Title West Trail High School Landscaping ImprovementsPreparer: S. Bear
HAZARD: WildfireMITIGATION STRATEGY Vegetation Control
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
$
$
$
$
1Pre-Construction
(Specify)
Pre-construction subtotal $
Site clearing trees, with 335 H.P. dozer, to 24"diameter
25 Ea. $20.50 $513
Selective clearing, brush, medium clearing, to 4"diameter, with dozer and brush rake, excludesremoval offsite
2.2 Acre $239.00 $526
Grub stumps, with 335 H.P. dozer, to 36" diameter 125 Ea. $10.65 $1,331Tree pruning, 36" caliper, aerial lift equipment 100 Ea. $608.00 $60,800
Ground covers, vines and climbing plants, phloxsubulata, (Moss Phlox, Creeping Phlox), B&B, zone4, 1 gallon
150 Ea. $4.73 $710
Deciduous trees, oak, B & B, 2-1/2"-3" caliper, inprepared beds
10 Ea. $640.00 $6,400
Loam or topsoil, up to 200' radius, remove andstockpile on site, spread from pile to rough finishgrade, by hand
1,200 E.C.Y. $25.50 $30,600
Lawn bed preparation, rake topsoil, site materials,adverse conditions, harley rock rake
45 M.S.F. $205.00 $9,225
Lawn bed preparation, root raking and loading,municipal, no boulders
50 M.S.F. $7.15 $358
Lawn bed preparation, spread conditioned topsoil,6" deep, by hand
550 S.Y. $8.45 $4,648
Mulch, filter fabric weed barrier 550 S.Y. $1.38 $759
Mulch, stone mulch, ceramic chips, deluxe, handspread
550 S.Y. $15.40 $8,470
$
$
$
2Construction
(Specify Phases)
Construction Subtotal $124,338
Insurance and Bonds 1 LS 3.5% $4,352
Site supervision and contract requirements 1 LS 10% $12,869
G.C. overhead & profit 0 LS 28% $
Permits and Review Fees 0 LS 0.5% $
Construction -General
General Construction Phase Subtotal $17,221
Preparation of construction documents 1 LS 10% $14,156
Applicant Cost to Manage Design 1 LS 2% $2,831
Applicant Cost to Manage Construction 1 LS 4% $5,662
3
Applicant Costs
Applicant Cost Subtotal $22,649
-
8/4/2019 Project Cost Guidance
51/87
49
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
Maintenance $
Site maintenance, general site work maintenance,clearing brush, by hand - quarterly 2,200 S.Y. $1.28 $2,816
Site maintenance, flower bed maintenance, weedmulched bed - quarterly 20 M.S.F. $17.90 $358
$
4 Maintenance
Annual Maintenance Subtotal $3,174
5 Escalation Escalation (to mid-point of construction) 9 Months 0.43% $5,517
Pre-construction subtotal $
Construction subtotal $124,338
General Construction Phase Subtotal $17,221
Applicant Cost Subtotal $22,649
Annual Maintenance Subtotal $3,174
6Estimate Review& Confirmation
Escalation Subtotal $5,517
PROJECT TOTAL $172,899
-
8/4/2019 Project Cost Guidance
52/87
50
BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Upland County, CA Library DistrictProject Title Middle County Library RenovationPreparer: C. Pasquel
HAZARD: WildfireMITIGATION STRATEGY Fire Resistant Exterior Materials
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
$
$
$
$
1Pre-Construction
(Specify)
Pre-construction subtotal $
Siding demolition, wood, boards, vertical 5,000 S.F. $0.90 $4,501
Insulation removal, rigid board 15,000 B.F. $0.10 $1,500
Roofing and siding demolition, shingles, wood 12,000 S.F. $0.83 $9,960
Brick veneer wall, standard face, 2x4 studs @ 16"back-up, running bond
5,400 S.F. $20.75 $112,059
Slate roofing, shingles, 3/16" thick, 4" min slope,8.0 PSF
12,000 S.F. $6.98 $83,760
Insulation, rigid, roof deck, polyisocyanurate,2#/CF, 3.5" thick, R25
12,000 S.F. $2.55 $30,590
$
$
2Construction
(Specify Phases)
Construction Subtotal $242,370
Insurance and Bonds 1 LS 3.5% $8,483
Site supervision and contract requirements 0 LS 10% $
G.C. overhead & profit 0 LS 28% $
Permits and Review Fees 1 LS 0.5% $1,254
Construction -General
General Construction Phase Subtotal $9,737
Preparation of construction documents 1 LS 10% $25,211
Applicant Cost to Manage Design 1 LS 2% $5,042
Applicant Cost to Manage Construction 1 LS 4% $10,084
3
Applicant Costs
Applicant Cost Subtotal $40,337
Maintenance $
$
$4 Maintenance
Annual Maintenance Subtotal $
5 Escalation Escalation (to mid-point of construction) 12 Months 0.41% $12,343
Pre-construction subtotal $
Construction subtotal $242,370
General Construction Phase Subtotal $9,737
Applicant Cost Subtotal $40,337
Annual maintenance Subtotal $
6Estimate Review& Confirmation
Escalation Subtotal $12,343
PROJECT TOTAL $304,788
-
8/4/2019 Project Cost Guidance
53/87
51
BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Sedge County, FloridaProject Title Emergency Wildfire Suppression Water StoragePreparer: T. Bear
HAZARD: Wildfire
MITIGATION STRATEGY SuppressionEstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
Land acquisition 1.5 Acres $3,500.00 $5,250
$
$
$
1Pre-Construction
(Specify)
Pre-construction subtotal $5,250
Clear and grub, cut & chip, light trees, to 6"diameter
1.00 Acre $3,475.00 $3,475
Stripping and stockpiling, topsoil, sandy loam,adverse conditions, 200 H.P. dozer 450.00 C.Y. $1.51 $680
Fine grade, fine grade for slab on grade, machine 3,400.00 S.Y. $1.32 $4,488
Fill, from stockpile, 130 H.P., 2-1/2 C.Y., 300'haul, spread fill, with front-end loader, excludescompaction
1,150.00 L.C.Y. $2.60 $2,990
Compaction, riding, vibrating roller, 3 passes, 6"lifts
1,150.00 E.C.Y. $0.49 $564
Backfill, structural, common earth, 80 H.P. dozer,50' haul, excludes compaction 800.00 L.C.Y. $1.06 $848
Compaction, riding, vibrating roller, 2 passes, 6"lifts
800.00 E.C.Y. $0.37 $296
Storage Tanks, vinyl coated fabric pillow type,freestanding, 50,000 gallons, excl. supportingembankment
1.00 Ea. $31,400.00 $31,400
Aggregate base course, for roadways and largepaved areas, alternate method to figure basecourse, crushed stone, compacted, 3/4", 6" deep
270.00 E.C.Y. $43.50 $11,745
Chain link fence, industrial, galvanized steel, 6 ga.wire, 2-1/2" posts @ 10' OC, 8' high, includesexcavation
570.00 L.F. $44.00 $25,080
Chain link fence, double swing gates, 6' high, 20'opening 2.00 Opng. $1,675.00 $3,350
2Construction
(Specify Phases)
Construction Subtotal $84,915
Insurance and Bonds 1 LS 3.5% $2,972
Site supervision and contract requirements 1 LS 10% $8,789
G.C. overhead & profit 1 LS 28% $27,069
Permits and Review Fees 1 LS 0.5% $645
Construction -General
General Construction Phase Subtotal $39,475
Preparation of construction documents 1 LS 10% $12,439
Applicant Cost to Manage Design 1 LS 2% $2,488
Applicant Cost to Manage Construction 1 4% $4,976Applicant Costs
Applicant Cost Subtotal $19,902
-
8/4/2019 Project Cost Guidance
54/87
52
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
Maintenance $
$
Labor for weed control: Laborer 2 days/month 192 Hrs. $31.76 $6,0984 Maintenance
Annual Maintenance Subtotal $6,098
5 Escalation Escalation (to mid-point of construction) 11 Months 0.42% $5,706
Pre-construction subtotal $5,250
Construction subtotal $84,915
General Construction Phase Subtotal $39,475
Applicant Cost Subtotal $19,902
Annual Maintenance Subtotal $6,098
6Estimate Review& Confirmation
Escalation Subtotal $5,706
PROJECT TOTAL $161,346
-
8/4/2019 Project Cost Guidance
55/87
53
BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Seawinds, TexasProject Title Town Hall StrengtheningPreparer: Norman Storm
HAZARD: Wind
MITIGATION STRATEGYRoof and Load Path Strengthening and
Shutters
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
$
$
Relocation costs: moving expenses $
Relocation costs: rental assistance $
1Pre-Construction
(Specify)
Pre-construction subtotal $
Roof Reinforcement $
Light Framing, average for all light framing 1 M.B.F. $1,599.94 $1,600
Labor productivity for restricted work space forcrew of two carpenters
3 Days $1,009.60 $3,029
Load Path Reinforcement
Ceiling demolition, drywall, furred and nailed,remove
3,820 S.F. $1.00 $3,819
Walls and partitions demolition, drywall, nailed 2,300 S.F. $0.40 $925
Selective demolition, rubbish handling, dumpster,30 C.Y., 10 ton capacity, weekly rental, includesone dump per week, cost to be added todemolition cost.
4 Week $990.00 $3,960
Selective demolition, rubbish handling, 100' haul,load, haul to chute and dumping into chute, cost tobe added to demolition cost.
10 C.Y. $48.50 $485
Timber Connectors, joist & beam hangers,galvanized, 18 gauge, for 2" x 6" to 2" x 10" joist
560 Ea. $4.14 $2,318
Timber Connectors, split rings, twist straps, 18gauge, 12" x 1-1/4"
570 Ea. $7.30 $4,162
Concrete impact drilling, for anchors, 3/8" dia, in
concrete or brick walls and floors, incl bit & layout,excl anchor, for each additional inch of depth, add
160 Ea. $1.51 $242
Anchor, expansion shield, zinc, 3/8" dia x 1-1/2" L,single, in concrete, brick or stone, excl layout &drilling
160 Ea. $8.05 $1,288
Gypsum wallboard, on beams, columns, or soffits,w/compound skim coat (level 5 finish), 1/2" thick
3,820 S.F. $2.24 $8,557
2Construction
(Specify Phases)
Paints & Coatings, walls & ceilings, interior,concrete, drywall or plaster, oil base, 3 coats,smooth finish, roller
3,820 S.F. $0.88 $3,362
-
8/4/2019 Project Cost Guidance
56/87
54
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
Ceiling Suspension System, class A, 15/16" T bar,2' x 4" grid
2,300 S.F. $1.21 $2,783
Exterior Shutters, polystyrene, solid raised panel,16" wide x 80" long
72 Pr. $129.01 $9,288
Door hardware, hinges, full mortise, averagefrequency, steel base, USP, 6" x 6"
144 Pr. $85.80 $12,355
Concrete impact drilling, for anchors, 1/4" dia, inconcrete or brick walls and floors, incl bit & layout,excl anchor, for each additional inch of depth, add
576 Ea. $1.20 $691
Anchor, expansion shield, zinc, 1/4" dia x 1-5/16" L,single, in concrete, brick or stone, excl layout &drilling
576 Ea. $6.90 $3,975
$
$
$
$
$
2Construction(Specify
Phases)
Construction Subtotal $62,839
Insurance and Bonds 1 LS 3.5% $2,199
Site supervision and contract requirements 1 LS 10% $6,504
G.C. overhead & profit 1 LS 28% $20,032
Permits and Review Fees 0 LS 0.5% $
Construction -General
General Construction Phase Subtotal $28,735
Preparation of construction documents 1 LS 10% $9,157
Applicant Cost to Manage Design 1 LS 2% $1,831
Applicant Cost to Manage Construction 1 LS 4% $3,663
3
Applicant Costs
Applicant Cost Subtotal $14,652
Maintenance $
$
$4 Maintenance
Annual Maintenance Subtotal $
5 Escalation Escalation (to mid-point of construction) 11 Months 0.41% $4,110
Pre-construction subtotal $
Construction subtotal $62,839
General Construction Phase Subtotal $28,735
Applicant Cost Subtotal $14,652
Annual Maintenance Subtotal $
6Estimate Review &
Confirmation
Escalation Subtotal $4,110
PROJECT TOTAL $110,335
-
8/4/2019 Project Cost Guidance
57/87
55
BENEFIT COST ANALYSIS PROJECT COST ESTIMATE TEMPLATEApplicant Prairieland Texas School BoardProject Title Flattop Elementary School Tornado Safe roomPreparer: B. Eddy
HAZARD: WindMITIGATION STRATEGY Tornado Safe Room
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
$
$
$
$
1Pre-Construction
(Specify)
Pre-construction subtotal $
Strip footing, concrete, reinforced, 180 L.F. $38.55 $6,939
Foundation wall, CIP, 180 L.F. $60.35 $10,863
Slab on grade, 6" thick, light industrial, reinforced 900 S.F. $6.76 $6,084
Concrete block (CMU) wall, regular weight, solid,double wythe, reinforced and grouted
1,200 S.F. $17.80 $21,360
Concrete block (CMU) partition, regular weight,solid, 6" thick, no finish
300 S.F. $7.75 $2,325
Exterior Door, steel 18 gauge, hollow metal, 1door with frame, "A" label, 3'-0" x 7'-0" opening
2 Opng. $1,740.00 $3,480
Metal door/metal frame, flush, composite, 18 gafull panel, 3'-0" x 6'-8", KD drywall frame, 4-7/8"
2 Ea. $870.00 $1,740
Interior Door frames, steel channels with anchorsand bar stops, 8" channel@ 11.5 lb/LF, 6' x 8'door, weighs 275 lb
1 Ea. $655.55 $656
Interior Doors, commercial, steel, flush, full panel,hollow core, 18 ga., 3'-0" x 6'-8" x 1-3/4" thick
2 Ea. $360.00 $720
Painting, masonry or concrete, latex, brushwork,primer & 2 coats
1,500 S.F. $1.75 $2,625
Roof, steel joists, on bearing walls 900 S.F. $3.34 $3,006
Insulation, rigid, roof deck, fiberboard, highdensity, 3'x4' sheets, 1-1/2" thick, R3.8
900 S.F. $1.26 $1,134
Roofing, coal tar pitch, gravel, coated glass fiberbase sheet, 3 plies glass fiber felt (Type IV),mopped, on nailable deck
900 S.F. $3.10 $2,790
Switchgear installation, incl switchboard, panels &circuit breaker, 400 A
1 Ea. $7,250.00 $7,250
Receptacles and wall switches, 600 SF, 10receptacles
900 S.F. $3.17 $2,853
Receptacles and wall switches, 600 SF, 2switches
900 S.F. $0.76 $684
2Construction
(Specify Phases)
Urinal, vitreous china, wall hung 2 Ea. $1,185.00 $2,370
-
8/4/2019 Project Cost Guidance
58/87
56
EstimatingStep
Project Phase Description Quantity Unit Unit Cost Task Cost
Water closets, battery mount, wall hung, side byside, first closet
1 Ea. $1,720.00 $1,720
Water closets, battery mount, wall hung, side by
side, each additional water closet, add
5 Ea. $1,615.00 $8,075
Lavatories, battery mount, side by side, firstlavatory
1 Ea. $1,540.00 $1,540
Lavatories, battery mount, side by side, eachadditional lavatory, add
3 Ea. $1,245.00 $,735
Heat pump, thru-the-wall, supplemental electricheat, cabinet, louver, 1-1/2 ton
2 Ea. $3,205.00 $6,410
Partitions, toilet, cubicles, ceiling hung, paintedmetal
6 Ea. $705.00 $4,230
Partitions, toilet, cubicles, floor & ceiling anchored,incl. 52" grab bars, for handicap units, add
2 Ea. $330.00 $660
$
2Construction
(Specify Phases)
Construction Subtotal $103,249
Insurance and Bonds 1 LS 3.5% $3,614
Site supervision and contract requirements 1 LS 10% $10,686
G.C. overhead & profit 1 LS 28% $32,914
Permits and Review Fees 0 LS 0.5% $
Construction -General
General Construction Phase Subtotal $47,213
Preparation of construction documents 1 LS 10% $15,046
Applicant Cost to Manage Design 1 LS 2% $3,009
Applicant Cost to Manage Construction 1 LS 4% $6,018
3
Applicant Costs
Applicant Cost Subtotal $24,074
Maintenance $
$
$4 Maintenance
Annual Maintenance Subtotal $
5 Escalation Escalation (to mid-point of construction) 11 months 0.41% $6,753