Project Value: $52,000,000 Project Overview ACS held a single-source contract to design and construct the 75,000 square feet expansion of the existing Product Development Center. Key Performance Features: Additional space included Powertrain engine development laboratory (15,000 sq. ft.). Space also included Noise, Vibration and Harshness development and structures test laboratories (60,000 sq. ft.). 81,629 sq. ft. office building to house Engineering and Development teams. This building received LEED Certification in 2003. PROJECT CAMEO PRODUCT DEVELOPMENT CENTER EXPANSION / HARLEY DAVIDSON / WAUWATOSA, WI ACS Services: ACS held a single-source contract for design and construction management; equipment specification, procurement and installation; integration of equipment and facility systems; and commissioning. Project Duration: 2 years, 6 months Completion Date: March 2003 Headquarters - Madison, WI - USA / Greenville, SC - USA / Troy, MI - USA / TEDA Tianjin, China / Leicester, UK / www.acscm.com / [email protected]

Transcript of PROJECT CAMEO PRODUCT DEVELOPMENT CENTER EXPANSION HARLEY DAVIDSON ... Expansion_Har… · Project...

Page 1: PROJECT CAMEO PRODUCT DEVELOPMENT CENTER EXPANSION HARLEY DAVIDSON ... Expansion_Har… · Project Value: $52,000,000 Project Overview ACS held a single-source contract to design

Project Value: $52,000,000

Project Overview

ACS held a single-source contract to design and

construct the 75,000 square feet expansion of the

existing Product Development Center.

Key Performance Features:

• Additional space included Powertrain

engine development laboratory (15,000

sq. ft.).

• Space also included Noise, Vibration and

Harshness development and structures

test laboratories (60,000 sq. ft.).

• 81,629 sq. ft. office building to house

Engineering and Development teams.

This building received LEED Certification

in 2003.

P R O J E C T C A M E O

P R O D U C T D E V E L O P M E N T C E N T E R E X PA N S I O N / H A R L E Y D AV I D S O N / WA U WAT O S A , W I

ACS Services:

ACS held a single-source contract for design and

construction management; equipment specification,

procurement and installation; integration of

equipment and facility systems; and commissioning.

Project Duration: 2 years, 6 months

Completion Date: March 2003

Headquarters - Madison, WI - USA / Greenville, SC - USA / Troy, MI - USA / TEDA Tianjin, China / Leicester, UK / www.acscm.com / [email protected]